Ref: CBL/171C/2013-14

SEP 7, 2013

M/s VAPI CARE PHARMA
NALAGRAH ROAD,BADDI

Kind Attention: - INDERJEET

SUBJECT: OFFER FOR 1 TPH (F & A 100C) 10.54 KG/CM
2
WOOD
FIRED WATER CUM SMOKE TUBE, EFFYPAC BOILER.

Dear Sir,

With reference to your requirement for the above said boiler. We are pleased to
enclose herewith our best offer for 1TPH (F & A 100C), 10.54 Kg/cm
2
water cum
smoke tube, compact & ready to use EFFYPAC boiler.

We hope you will find our offer in line with your requirements. For further
clarifications, please feel free to contact us.

Thanking you and assuring you of our best services at all the times, we remain.

Yours faithfully,
For CHEEMA BOILERS LIMITED,



B. NAGPAL
Sr. Manager-Marketing
Mb: +91-9781054444
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 2 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR

OFFER INDEX

ANNEXURE I COMMENTS & CLARIFICATIONS
ANNEXURE II DESIGN BASIS
ANNEXURE III DATA SHEET
ANNEXURE IV WATER QUALITY REQUIREMENT
ANNEXURE V SCOPE OF WORK & SUPPLY
ANNEXURE VI EXCLUSIONS
ANNEXURE VII TERMINAL POINTS
ANNEXURE VIII PRICE SCHEDULE
ANNEXURE IX TERMS & CONDITIONS














CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 3 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
COMMENTS & CLARIFICATIONS ANNEXURE I

01. As desired by you we have offered one no. Three pass, Water cum smoke tube
boiler capable of generating 1 TPH steam (F & A 100
O
C) at 10.54 Kg/cm
2
(g)
pressure, capable of firing
- 100 % Wood

02. We have considered the ultimate analysis available with us and given in design
data for reference. If there is any change please do let us know to design
accordingly.

03. Kindly note that the design parameters for the equipments furnished along with
this offer are liable to change during project execution without affecting the
boiler's performance parameters.
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 4 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
DESIGN BASIS ANNEXURE II

Installation Semi Outdoor
Design code IBR 1950 with latest amendments
Boiler capacity (F & A 100
O
C) Kg/hr 1000
Steam pressure Kg/cm
2
10.54
Steam quality Dry Saturated
Fuel : 100 % Wood
NCV Kcal/kg 3000
Fuel sizing As available, duly sized
Thermal efficiency % 80 1
Outlet flue gas temp.
O
C 150 160
Relative humidity % 60
Ambient temp.
O
C
- Efficiency 30
- Insulation 45
- Electrical 48
Electrical data
- LT Volt V 415 + 6%
- Control Volt V 220 + 5%
- Frequency Hz 50 + 3%
Note: efficiency is based on NCV of fuel
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 5 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
TECHNICAL DATA SHEET ANNEXURE IV
1.0 BOILER SHELL
1.1 Design code IBR 1950 with latest amendments
1.2 Material specifications ASTM SA 516 Gr.70 / Equiv.
1.3 Safety valve I set pressure Kg/cm
2
11.00
1.4 Safety valve II set pressure Kg/cm
2
11.25
2.0 BOILER TUBES
2.1 Shell tubes
2.1.1 Tube size mm x mm 50.8 OD x 3.25 thk.
2.1.2 Tube material BS-3059 / 320 Part I ERW
2.2 Water wall tubes
2.2.1 Type of arrangement Fin welded membrane wall
2.2.2 Tube size mm x mm 50.8 OD x 3.25 thk.
2.2.3 Tube material BS-3059 / 320 Part I ERW
2.2.4 MOC of headers ASTM A 106, Gr. B / Equiv.
2.3 Water pre-heater
2.3.1 Type of arrangement Shell & Tube type
2.3.2 Flow medium - Inside tubes
- Outside tubes
Flue Gases
Water
2.3.3 Tube size mm x mm 60.3 OD x 2.34 thk.
2.3.4 Tube material IS 1239 ERW
3.0 FEED PUMPS
3.1 Capacity m
3
/hr. 1.2
3.2 Total differential head MLC 125
3.3 Speed RPM 2900
3.4 NPSH required Meter 3.0
3.5 No. of pumps in operation One
3.6 No. of stand by pumps One
3.7 Motor rating KW 2.2
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 6 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR

4.0 FANS ID Fan
4.1 Type Centrifugal
4.2 Capacity m
3
/hr. 3000
4.3 Total differential pressure mmwc 250
4.4 Design temp.
O
C 160
4.5 Fan speed RPM 1440
4.6 Motor rating KW 3.7
5.0 FLUE GAS CLEANING EQUIPMENT (C Cyclone)
5.1 Gas flow rate m
3
/hr. 2400
5.2 Dust concentration at outlet mg/Nm
3
< 350
5.3 Collection efficiency %age 96
5.4 Principle of separation Centrifugal
5.5 Pressure drop across cyclone mmwc 100
5.6 Body thickness mm 4
6.0 ELECTRICALS
6.1 Motor Control Centre
Make CBL
Standard followed IS 8623
Rated voltage Volts 415
6.2 Installed power KW/unit Total
ID fan 1 x 3.7 3.7
Feed pump 2 x 2.2 4.4
RALV 1 x 0.75 0.75
Sub Total KW 8.85

Note: The above specifications may change at the time of designing and engineering without
affecting the performance and /or efficiency of the boiler.
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 7 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
WATER QUALITY REQUIREMENT ANNEXURE V
Characteristics Limit Unit Specifications
Feed water
Total hardness (as CaCO
3
) Max. mg/ltr. 5.0
pH value 8.5 to 9.5
Dissolved oxygen Max. mg/ltr. 0.02
Silica (as SiO
2
) Max. mg/ltr. 0.5
TDS Max. PPM 350-400
Boiler Water
Total hardness (of filtered sample) (as CaCO
3
) mg/ltr. Not detectable
Total alkalinity (as CaCO
3
) Max. mg/ltr. 300
Caustic alkalinity (as CaCO
3
) Max. mg/ltr. 150
pH Value 10.5 to 11.5
*Residual sodium sulphite (as Na
2
SO
3
) mg/ltr. 20 to 30
Residual hydrazine as (N
2
H
4
) mg/ltr. 0.1 to 0.5
Phosphates (as PO
4
) (if added) mg/ltr. 15 to 30
**Total dissolved solids Max. mg/ltr. 3000
Silica (as SiO
2
) mg/ltr. 15.0

* Total alkalinity should preferably be about 20% of total dissolved salts.
** Shall not apply if reducing agents other than sodium sulphite are used.
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 8 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
SCOPE OF WORK AND SUPPLY ANNEXURE VI
SCOPE OF WORK
1.1 Complete engineering and preparation of all data, drawings, calculations etc., as
required for boiler and its auxiliaries, which are under CBL scope of supply.
1.2 Co-ordination with Director of Boilers for engineering and manufacturing of boiler
at Punjab.


SCOPE OF SUPPLY FOR MAIN BOILER
1.0 Boiler
1.1 Main boiler Shell with tubes.
1.2 Membrane four sided water wall furnace.
1.3 Additional convection membrane for better heat transfer & efficiency.
1.4 Down comers and risers.
1.5 Boiler internals.
1.6 Supporting structures for CBL equipment.
1.7 Insulation and cladding at water wall and main boiler shell.

2.0 Feed water system
2.1 Boiler Feed water pumps (2 Nos.) & complete with coupling, base frame
and driving arrangement.
2.2 IBR feed water line from feed pump discharge to boiler inlet.

3.0 FURNACE SYSTEM
Fixed grate furnace adequately designed for better combustion of fuel.
Refractory lining in furnace.
The easy to open hinged type cast iron doors for firing fuel into the furnace &
for easy access to the water walls from inside.
Ash discharge doors.
Ash collection tray for easy removal of Ash.


4.0 VALVES & MOUNTINGS: Set of IBR Valves and Mountings:
Main steam stop valve 1 no
Single Port spring loaded Safety valve 2 nos.
Main blow down valve 1 no.
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 9 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
Boiler Air vent valve 1 no.
Non-Return valve on water inlet line 1 no.
Gauge glass with shields & Cock set 2 nos.
Feed stop valve on water line 1 no.
Non-Return valve on pump outlet line 1 no.
Header drain valve 2 nos.

5.0 Water Pre-Heater cum Storage tank
One number Water pre heater to recover waste heat from flue gases.
Water pre-heater shell and tube type assembly.
Water storage capacity of 1000 ltrs.
Insulation and Cladding for WPH
Feed water piping from WPH to Feed Pumps.


6.0 Auxiliaries
One no. ID fan designed for 100% MCR with motor.
1 nos. manually operated dampers for ID fan.
Dampers and expansion joints in ID fan.
All the inter connecting ducting between:-
- Boiler Outlet to WPH
- WPH to Cyclone
- cyclone to ID fan


7.0 INSTRUMENTATION
The instrumentation and control system consisting of the following automation
system for monitoring and control of the boiler
a. Control panel comprising basic instrument such as
1.0 Instrumentation:
PRESSURE GAUGE AT {10 Dial}:
- Boiler shell
TEMP. ELEMENTS AT: RTD at
- Boiler Outlet Flue Gases
- WPH Outlet Flue Gases

One controller for Auto Cut-off at high boiler out temperature.

CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 10 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
Level controller switch at WPH Tank.
- To maintain water level in WPH tank.
- Auto boiler cut off at extra low levels.

b. Mobrey Drum Level Control
- To maintain water level in Main shell.
- Auto boiler cut off at extra low levels

c. Automatic Pressure Switch
d. The Safety Interlock System


8.0 ELECTRICALS
Power Between:-
- Control panel and feed pump motors
- Control panel and ID fan motor

Control cabling Between:-
- Control panel and RTD assembly at boiler outlet.
- Control panel and RTD assembly at WPH outlet.
- Control panel and Mobrey.
- Control panel and level controller at WPH
- Control panel and Pressure Switch.

Control Panel consists of switches / relays, fuses for the following equipments:
ID fan motors
Feed water pump drives
Rotary air lock valves drive.


9.0 DUST COLLECTING SYSTEM
One no. C cyclone dust collector.
Supporting structure for Dust collector.
Ash hopper with rotary air lock valve for continuous ash discharge.
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 11 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
EXCLUSIONS ANNEXURE VII
The following are EXCLUDED from this scope of supply:
1. Soft water storage tank, Water softener & its piping, Main chimney.
2. Steam and feed water piping, drain and blow down connections.
3. Main civil foundation work of boiler chassis
4. Fuel / Ash conveyor / handling system.
5. Unloading at site, Labour, Tools & tackles, Consumables etc.
6. Boiler shed & its structure.
7. Transportation, insurance, Octroi etc.
8. Boarding and lodging of our staff at site.
9. IBR inspection and approval at your site.
10. Any other item not specifically mentioned in this offer.


CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 12 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
TERMINAL POINTS ANNEXURE VII
Feed water : Inlet of WPH.
Steam : Outlet of main steam stop valve.
Blow down / drains : Outlet of respective valves.
Exhaust steam / Air vent : Up to safe elevation above the roof.
Fuel : Inlet of fire doors.
Ash : Outlet of ash discharge doors.
: Outlet of rotary air lock valve below cyclone.
Combustion air
Flue gas
: Inlet Boiler,
Outlet of ID fan.
Electricals : Inlet terminals of boiler MCC.
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 13 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
PRICE SCHEDULE ANNEXURE VIII
Price for the Designing, Detailed Engineering, Procurement, Manufacturing,
Fabricating and Supply of Steam Generation Plant as per enclosed scope of
supply: -

DESCRIPTION : Price (Rs in Lacs)
1 TPH(F & A 100C) , 10.54 Kg/cm
2
EFFYPAC
Boiler
: 14.00 /-
Note: The prices quoted are Ex works excluding freight, all taxes and duties, transit
insurance, octroi if any etc.

SUPERVISION OF ERECTION AND COMMISSIONING
Included in price.


For CHEEMA BOILERS LIMITED,




B. NAGPAL
Sr. Manager-Marketing
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 14 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
TERMS & CONDITIONS ANNEXURE IX
PRICE
The prices quoted are Ex works excluding freight, transit insurance, all taxes and duties,
octroi if any etc.

VALIDITY
The offer is valid for the period of 20 days.

PACKING AND FORWARDING
Packing and forwarding will be done in accordance with manufacturers standard
practice. Any special requirement desired by purchase will be charged additionally.

DELIVERY
90 Days from the date of confirm order with advance. This delivery period will be counted
from the date of receipt of your fully confirmed technically/commercially formal
order/approval of drawings if any, which ever is later.

WARRANTEE
The boiler is warranted against malfunction arising out of faulty design, material and / or
workmanship for a period of 12 months from the date of commissioning or 18 months
from the date of Invoice, whichever is earlier. This clause will be applicable if the
purchaser strictly adheres to manufacturers recommendations on feed water and fuel
quality.

PAYMENT
30% of the order value as an advance along with LOI / P.O.
Balance with applicable taxes and duties against Performa invoice before delivery.

BOUGHT OUT ITEMS
The purchaser shall indemnify the manufacture for any delay arising from delay in supply
of specific make of sub delivery insisted upon the purchaser where the manufacturer has
no control over the delivery of that sub delivery.

INSPECTION
Where the purchaser desires an inspection at the manufacturer's works, such inspection
can be only for final inspection just before packing. The date of inspection shall be
intimated by the manufacturer about two weeks in advance. If the purchaser fails to
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 15 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
undertake inspection on such date intimated, manufacturer shall proceed for despatch
under no obligation to the purchaser.

HANDING OVER OF THE BOILER
The boiler shall be deemed to have been delivered and commissioned as per
manufacturer scope and the purchaser shall issue a certificate to that effect. On
achieving the rated steam parameters at the time of commissioning, it shall be deemed
that the manufacturer has completed the performance tests. Manufacturer stands no
guarantee if the boiler is put to commercial use without the authorisation of the
manufacturer.

PERFORMANCE GUARANTEE: Refer Design Data sheet.

BOILER REGISTRATION
The boiler is manufactured as per Indian Boiler Regulations with latest amendments /
ISO. One set of relevant documents and certificates signed by the Director of Boiler,
Punjab will be forwarded to the customer. The purchaser at his cost shall complete
subsequent formalities for registration of the boiler with boiler inspectorate of the state
concerned.

WAREHOUSING CLAUSE
If payment is not made within 15 days of date of proforma invoice, we reserve the right to
divert the ordered material. We will give a fresh delivery period and price at the time of
diversion, which will be binding on the purchaser and the contract, can not be rendered
void on this account. If the goods cannot be diverted, charges will be applicable for
storage, insurance and interest at the rate of 1% of the invoice value for each week to a
maximum of 5% commencing 15 days from the date of proforma invoice.

FORCE MAJEURE
All our offer are subject to force majeure by which is meant causes beyond of our control
such as war, invasion, civil disobedience, govt. orders, directives or restrictions, strikes,
lockouts, riots, fire earthquakes, floods, accident delay or inability to obtain labour, raw
material, railway wagon, shipping space or any such and similar causes what so ever.

CANCELLATION
Order received and acknowledged shall not be canceled without the written consent of
the manufacturer. The advance paid along with the order shall be fully forfeited in the
event of cancellation of order. If manufacturing activities has commenced, you shall
CLIENT:M/s VAPI CARE PHARMA DOC: F-MKT-01 PAGE 16 OF 16
PROJECT: 1 TPH, 10.54 KG/CM
2
EFFYPAC BOILER ISSUE 1.0 DATE 1/07/03 APPROVED BY: MR
compensate us for the work already carried out on your behalf, in addition to forfeiture of
advance.

PLACE OF JURISDICTION
In the event of any dispute of arising as result of contracting to supply against this offer
and quotation, the place of Jurisdiction will be Ropar (Punjab) and not any other place.

GENERAL
On receipt of the purchase order the terms and conditions specified in our offer shall be
deemed to have been accepted by the purchaser except in cases when the purchase
order specifies otherwise.

SPECIAL NOTE
Please note that this offer is made strictly on the basis of divisible contract. The property
in the goods shall pass to the buyer on the goods being handed over to the carrier for
onward dispatch to site endorsement and waybills in your favour.

EXCESS MATERIALS
The excess materials send to site along with components for contingency and safe
transportation purpose will be reused up to the maximum extent possible (or) taken back
by CBL.

For CHEEMA BOILERS LIMITED,




B. NAGPAL
Sr. Manager-Marketing

Das könnte Ihnen auch gefallen