Sie sind auf Seite 1von 7

Kudler Fine Foods Network: Final

University of Phoenix











Network Deployment/Timeline
The new network roll out for Kudler Fine Foods will not take place overnight. The
ability to keep Kudler in operation is very important to the owners and is why implementation
will take place in three phases. The one important factor of this build out is the documentation
that will be taken at each phase. This information will be used to provide vital network
information and proper network install accreditation for the client. The first phase will be the
installation of the network. Phase two will cover all the testing and security checks needed. The
third phase of this roll out will included the observation of the network when it goes live, the
removal of the old network, and the pass down of all documentation to the owners and
networking teams.
In the first phase of this project the Del Mar site will be the first store to be upgraded
because it will become the backbone to the entire operation. This site will contain the POS
server, inventory data base, File integrity checker, security console for monitoring and the T1
line. The completion for the Del Mar site will take 5 weeks. Once this site has been completed
the La Jolla site will begin. The integration for this site is expected to go smoothly, but with all
of the unknowns that can factor in, the expected completion time for this site will be five weeks
as well. The lessons learned from this install should make the installation at the Encinitas site go
much smoother and will take three weeks to install.
Once all sites have been completed phase two will begin. This is the network testing
phase and will take three weeks to complete. For the first week of this phase load and speed
testing of the network will be conducted. This will help detect and solve any lagging, latency, or
jitter that may be on the network and will increase the speed and performance as well. The
second week of this phase will cover pen testing and security hardening of the new network. This
will prevent any security holes from being left opened. Any discrepancies that are discovered
must be fixed by the end of the second week. Week three will be for retesting of any
discrepancies found in the week prior and will provide the time needed to fine tune all firewall
and IPS/IDS rules. This is a very critical phase of the project and everything must check out
before moving on to the last phase.
Phase three of the network rollout will be taking the network live. This will be a four
week phase and will make sure everything is working at 100% normal. The first three weeks will
be checking to make sure that all systems are updating and working together as designed. Once
everything checks out the removal of the old network will be completed. The last and final piece
to this project is the passed down of all documentation that was gathered during the build out.
This is important information that will provide all network layout designs and will show proof
for the proper installation of the net network.
Phase One Network Roll Out Del Mar 5 weeks
Week 1 6 February 2012
o Installation of T1 line
o Installation of new high speed internet for wireless communication
o Installation of all network cables needed for site
Week 2 13 February 2012
o Installation and configuration of Cisco 1941 routers and Cisco 1941W wireless
routers
o Configuration of Backend VPN
o Installation of VoWLAN phone system
Week 3 20 February 2012
o Point of Sales(POS) server Configuring, hardening, and installation
o Inventory Database server Configuring, hardening, and installation
o Load out of 4 POS windows sever systems and adding to network
o Setup and configure 4 Real Time inventory PDAs.
Week 4 27 February 2012
o Source Fire Management Console Configuring, hardening, and installation
o Install and configure Source Fire IDS and IPS systems
o Install and configure Tripe wire program and sends logs to Source Fire
Management Console
Week 5 5 March 2012
o Fine tune SourceFire Rules and activate systems
o Turn on network for testing and Fine tuning
o Del Mar network goes live
o Old network stay until network completion at all sites
o Document all lessons learned from phase
Phase One Network Roll Out - Lo Jolla 5 weeks
Week 1 12 March 2012
o Installation of all network cables needed for site
o Installation and configuration of Cisco 1941W wireless router
Week 2 19 March 2012
o Installation of VoWLAN phone system
o Setup and configure 4 Real Time inventory PDAs.
Week 3 26 March 2012
o Load out of 4 POS windows sever systems and adding to network
o Install and configure Source Fire IDS and IPS systems
Week 4 27 February 2012
o Fine tune SourceFire Rules and activate systems
o Turn on network for testing and Fine tuning
Week 5 2 April 2012
o La Jolla network goes live
o Old network stay until network completion at all sites
o Document all lessons learned from phase
Phase One Network Roll Out Encinitas - 3 weeks
Week 1 9 April 2012
o Installation of all network cables needed for site
o Installation and configuration of Cisco 1941W wireless router
o Installation of VoWLAN phone system
Week 2 16 April 2012
o Load out of 4 POS windows sever systems and adding to network
o Setup and configure 4 Real Time inventory PDAs.
o Install and configure Source Fire IDS and IPS systems
o Fine tune SourceFire Rules and activate systems
Week 3 23 April 2012
o Turn on network for testing and Fine tuning
o La Jolla network goes live
o Old network stay until network completion at all sites
o Document all lessons learned from phase
Phase Two Network Testing 3 weeks
Week 1 30 April 2012
o Load/Speed testing for Del Mar
o Jitter/lagging issues addressed for Del Mar
o Load/Speed testing for Lo Jolla
o Jitter/lagging issues addressed for Lo Jolla
o Load/Speed testing for Encinitas
o Jitter/lagging issue addressed for Encinitas
o Load/Speed testing for Entire WLAN network
o Jitter/lagging issue addressed for Entire WLAN network
o Retest Load/Speed testing for Entire WLAN network
Week 2 1 May 2012
o Pen testing/security hardening for Entire WLAN network
o Address any discrepancies
Week 3 8 May 2012
o Retest entire network for discrepancies that were discovered
o Fine tuning of all firewalls and IDS/IPS systems.
o Document all lessons learned from phase
Phase Two Network Testing 4 weeks
Week 1 14 May 2012
o Network goes live and observed for any issues
o Fix any issues that may arise and document

2 22 May 2012
o Network goes live and observed for any issues
o Fix any issues that may arise and document
Week 1 29 May 2012
o Network goes live and observed for any issues
o Fix any issues that may arise and document
Week 1 5 June 2012
o Old network is removed with all systems and parts
o New network becomes official
o All documentation is passed down to owners and network team
Total estimated time: 20 weeks