Beruflich Dokumente
Kultur Dokumente
IN THE MATTER OF :
VERSUS
to the extent borne out from documents on record and such of the
contents as are not borne out from the documents on record are
award (12th August, 2003). After that Registry of this Hon Court
that it was not the fault of petitioner in filing the petition hence not
Petitioner.
has failed to complete the work within the schedule time and
Respondent about the delay. The petitioner was time and again
Claimant.
completion of work.
schedule.
completion of work.
be completed.
Claimant.
over.
by Respondent
1. Shifting of site and area grading 72 days
work.
2. Non availability of site for out 63 days
door courts.
3. Execution of extra items. 26 days
4. Transporters strike 12 days
5. Parliament election 07 days
Total 180 days
weeks.
Rs.19,89,306/-
the Petitioner.
rejoinder are reiterated and reaffirmed for the reply of this para.
is very much clear about its contents which is given below for
Quote
NO DEMAND CERTIFICATE
Date: 14.1.1999
Eight Thousand Five Hundred and Fifty One Only) in full and
contract.
Unquote
Proceeding.
misconceived.
clause 80.0 and 80.2,” the time period allowed for carrying out
defects works is about one month and if such defect be not
the final bill such amount as may be decided by the owner” and
defects, even though those were within their scope of the work.
final bill and the same was accepted by the respondent also.
to R/4/10).
amount of Rs.85,904/-.
attending DLP.
same. Before taking over the building finally, they were again
but again Claimant did not take any positive action for attending
risk and cost of the Claimant as per the terms of the Contract.
Petitioner would like mention the following documents enclosed
to R/4/10).
amount of Rs.85,904/-.
Exhibit-R11: GAIL’s letter dated 02.02.99 reminder for
attending DLP.
the Respondent.
R19/3).
(R21/1 t R21/7).
VERIFICATION
that the contents of the above affidavit are true and correct,
concealed.
DEPONENT