1. 12 bit was worn out at 2000 m. String was pulled out for bit change, changed the bit and
RIH with new bit
2. Drilled down from 2000 m to 2200 m. Then Geologist asked for core.
3. C & C of mud. POOH. RIH to bottom with core bit.
4. Cored from 2200 m to 2215 m.
5. Core bit was pulled out and roller bit was RI to prove the hole
6. C & C of mud . POOH. Carried out logging. Again RIH with 12 bit. C & C of mud
7. Made a wiper trip
8. Circulation and Condition the mud POOH.
9. Lowered 9 5/8 Casing upto 2208 m
String Details:
Bit = 12
Drill Collar 8 X 3, 145.6 PPF = 200 m
Drill Collar 6 X 2 , 95.5 PPF = 200 m
HWDP 5, 73.4 kg/m = 100 m
5 G grade pipe = 1865 m
Wt of Traveling Block & Elevator assembly = 8000 kg
Mud wt = 1.4 gm/cc
13 3/8 Casing depth = 1200 m
9 5/8 N-80, 43.5 PPF casing =2208 m
1 dn = 1.02 kgf
Sl No
Operation
Cumulative Ton Km
Solution:Air wt of5 G grade (19.9 PPF) drill pipe with tool joint = 31.99 kg/m
Apparent wt drill pipe with tool joint = 31.99 X 0.822 = 26.30 kg/m
Air wt of 5 HWDP = 73.4 kg/m
Apparent wt of 5 HWDP = 73.4 kg/m X 0.822 = 60.33 kg/m
Wt of drill collar 6 X 2 = 95.5 x 1.488 = 142.10 kg/m
Apparent wt of drill collar = 142.10 x .822 = 116.81 kg/m
Wt of drill collar 8 x 3 = 145.6 ppf x 1.488 = 216.65 kg/m
Apparent wt = 216.65 x .822 = 178.08 kg/m
Wt of BHA
8 drill collar = 35616 kg
6 drill collar = 5840.5 kg
5 HWDP = 6033 kg
___________________
Total = 47489.5 kg
Wt of BHA length of 5 drill pipe = 8347.5 kg
Total additional apparent wt
d = 47489.5 8347.5
= 39142 kg
103 dn km
Tonkm at 2200 = 0.981{ 26.30 x 2200 (2200+ 27) +4 x 2200 (8000 + 39142/2)} 10 -6
= 372 Ton km
103 dn km
103 dn km
= 375 ton km
T coring = 2(375-372)
= 6 ton km
5. Round trip work done PO core bit from 2215 m and running in rollar bit to prove the hole
= 375 ton km
6. POOH & carried out logging and again RIH at 2215 m
work done by the rope = 375 ton km
7. Made a wiper trip
T WT = T2215- T1200
T2215 = 375 Ton km
T 1200 =0.981{ 26.30 x 1200 (1200+ 27) +4 x 1200 (8000 + 39142/2)} 10 -6
= 171 Ton km
103 dn km
Work done by the casing line during wiper trip =375-171 =204 ton km
8. After C&C of mud POOH prior to lowering of casing = x 375 ton km = 187.5
9.Lowered 9 5/8 , N-80, 43.5 PPF casing upto 2208 m mw =1.4 gm/cc
Lengh of each casing is 11 m
53.5 PPF = 64.68 kg/m,
Apparent wt 64.68 x .8318 = 53.80 kg/m
Ton km casing =
[0.981{ 53.80 x 2208 (2208+ 11) +4 x 2208 x 8000 )} 10 -6 ]
= 334 ton km
103 dn km
Sl
No
Operation
Round trip
1
2
Drilling
137
464
Round Trip
372
836
coring
842
375
1217
375
1592
204
1796
187.5
1983.5
334
2317.5
Cumulative Ton Km
327
POOH
9
casing