N QTY DESCRIPTION OF WORK RATE PER AMOUNT
O
1. Cement Mortar 1 :2
2. Cement Mortar 1 :3
MAIN DATA
LS Sundries 2.95
7376.75
LS wedges LS 25.00
L.S Add 10% extra on labour charges for 6300.00 10% 630.00
work in city
1.00 mt Anti corrosive treatment 2000.00 1mt 2000.00
0.300 m3 Vibrated R.C.C M15(1:2:4) using 20mm and 3194.00 1m3 958.20
12 mm ISS HBG Graded metal
2.00 m2 Plastering with cm 1:2 – 12 mm thick 95.40 1m2 190.80
(or) 358.00
Certified that the rates adopted are as per the current schedule of rates for the year of 2007 -
08.
DATA
for 6" (150mm) wall thickness
SL
QTY DESCRIPTION OF WORK RATE PER AMOUNT
NO
1 1 m2
0.150 m3 Vibrated R.C.C M15(1:2:4) using 20mm and 3194.00 1m3 479.10
12 mm ISS HBG Graded metal
2.00 m2 Plastering with cm 1:2 – 12 mm thick 95.40 1m2 190.80
(or) 313.00
Certified that the rates adopted are as per the current schedule of rates for the year of 2007 -
08.