ActivityID ActivityName Start Finish Original

Duration
PROCUREMENT,CONSTRUCTION AND PRE-COMMISSIONING SERVICES- CAIRN BHOGAT PROCUREMENT,CONSTRUCTION AND PRE-COMMISSIONING SERVICES- ...
01-Sep-10
A
19-Mar-14 916
MILESTONES MILESTONES
01-Sep-1... 11-Mar-14 916
INT0100 Award of Contract (LOA) 01-Sep-1... 0
INT0110 Kick of meeting 15-Sep-1... 0
INT0120 Site Enabling works ( Site office,Warehouse) 07-Oct-1... 02-Apr-11 A 100
INT0130 Completion of Residual Basic Engg. for Packages 04-Oct-12 A 0
INT0140 Ordering of Steam Generation Package 25-Oct-10 A 0
INT0150 Ordering of Air Compressor Package 16-Mar-11 A 0
INT0170 Ordering of OilyWater Treatment Package (OWS) 28-Oct-10 A 0
INT0180 Ordering of Gate/Ball Valves 16-Mar-11 A 0
INT0190 Ordering of Control Valves 11-Feb-11 A 0
INT0191 Ordering of EmergencyShut Down Valves 11-Feb-11 A 0
INT0200 Ordering of Nitrogen Package 01-Dec-10 A 0
INT0210 Ordering of Panel / Switchgear 01-Dec-10 A 0
INT0220 Ordering of Power Transformer 31-Dec-10 A 0
INT0230 Ordering of FF Pumps 09-J un-11 A 0
INT0240 Ordering of DG set 14-J an-11 A 0
INT0250 Receipt of Steam Generation Package 16-May-12 A 0
INT0260 Receipt of Air Compressor Package 10-May-12 A 0
INT0280 Receipt of OilyWater Treatment Package (OWS) 20-Nov-13 A 0
INT0290 Receipt of Gate/Ball Valves 24-J ul-13 A 0
INT0300 Receipt of Control Valves 05-Aug-13 A 0
INT0301 Receipt of EmergencyShut Down Valves 16-J ul-13 A 0
INT0310 Receipt of Nitrogen Package 04-J un-12 A 0
INT0320 Receipt of Panel / Switchgear 11-Oct-12 A 0
INT0330 Receipt of Power Transformer 15-J ul-12 A 0
INT0340 Receipt of Fire Water System 16-J ul-13 A 0
INT0350 Receipt of DG set 21-Apr-12 A 0
INT0360 All Building's Construction Completion 22-Oct-13 A 0
INT0380 Hydrotesting Completion 08-J an-14 A 0
INT0390 Erection of Equipments completion 15-J ul-13 A 0
INT0400 Electrical works completion 12-Feb-13 A 0
INT0410 Instrument works completion 11-Mar-14 A 0
INT0420 Fire Fighting Work Completion 18-Nov-13 0
INT0430 Mechanical Completion 13-J an-14 0
INT440 Receipt of FIM-GT 06-Apr-12 A 0
INT450 Receipt of FIM-Export Booster Pumps 11-Apr-12 A 0
INT460 Receipt of Heat Tracing System 21-Oct-13 A 0
INT470 Receipt of Foam Concentrate Tank 27-Mar-12 A 0
INT480 Receipt of Deludge Valve 15-May-13 A 0
INT490 Receipt of Electronic Flow Meter 04-J un-13 A 0
INT500 Mobilization of Mechanical Contractor 07-Nov-11 A 0
INT510 Mobilization of Electrical Contractor 10-Apr-12 A 0
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 1 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 2 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
INT520 Mobilization of Instrumentation Contractor 10-Apr-12 A 0
INT530 Receipt of Intrusion Detection System 13-Apr-12 A 0
INT540 Mobilization of Insulation Contractor 05-J un-12 A 0
INT550 Completion of Piping Erection 14-Dec-13 A 0
INT560 Installation of J ockeyPump 22-Nov-12 A 0
INT570 Deliveryof Gate Valves 15-J ul-13 A 0
INT580 RCC Completion of Dyke Wall 18-Sep-13 A 0
INT590 Installation of Booster Pump 31-May-12 A 0
CONTRACTUAL MILESTONES- FINISH MILESTONES CONTRACTUAL MILESTONES- FINISH MILESTONES
07-Dec-1... 19-Mar-14 526
COMIM4.11 UNPRICED PO COPIES OF FIRE PROTECTION SYSTEM 16-Aug-12 A 0
COMIM4.15 UNPRICED PO COPIES OF E &I WORKS SUB-CONTRACT 15-Mar-12 A 0
COMIM4.16 UNPRICED PO COPIES OF HVAC WORKS SUB-CONTRACT 12-Dec-11 A 0
COMIM4.9 UNPRICED PO COPIES OF HEAT TRACING 29-Dec-11 A 0
COMIM5.1.1 COMPLETION OF CIVIL FDN. FOR FIRE WATER STORAGE TANKS 15-Mar-12 A 0
COMIM5.1.10 COMPLETION OF CIVIL FDN. FOR DIESEL GENERATOR 24-Feb-12 A 0
COMIM5.1.11 COMPLETION OF CIVIL FDN. FOR VENT STACK 15-May-12 A 0
COMIM5.1.13 COMPLETION OF CIVIL FDN. FOR DIESEL STORAGE TANK 24-Feb-12 A 0
COMIM5.1.2 COMPLETION OF CIVIL FDN. FOR RAW WATER STORAGE TANKS 13-Sep-12 A 0
COMIM5.1.3 COMPLETION OF CIVIL FDN. FOR CLOSED DRAIN TANKS 13-Sep-12 A 0
COMIM5.1.4 COMPLETION OF CIVIL WORKS FOR TANK DYKE WALLS AND PAVING 20-Nov-13 A 0
COMIM5.1.5 COMPLETION OF CIVIL FDN. FOR EXPORT PUMPS 07-Dec-11 A 0
COMIM5.1.6 COMPLETION OF CIVIL FDN. FOR GAS TURBINES 15-J an-12 A 0
COMIM5.1.7 COMPLETION OF CIVIL FDN. FOR CUSTODY TRANSFER METERING SKID 17-J an-12 A 0
COMIM5.1.8 COMPLETION OF CIVIL FDN. FOR FIRE WATER &J OCKEY PUMPS 28-Apr-12 A 0
COMIM5.1.9 COMPLETION OF CIVIL FDN. FOR STEAM GENERATION PACKAGE 26-Mar-12 A 0
COMIM5.2.1 RECEIPT AT SITE OF STEAM GENERATION PACKAGE 14-Nov-12 A 0
COMIM5.2.10 RECEIPT AT SITE OF FIRE WATER AND J OCKEY PUMPS 16-Oct-12 A 0
COMIM5.2.12 RECEIPT AT SITE OF HT &LT CABLES 13-Nov-12 A 0
COMIM5.2.13 RECEIPT AT SITE OF PIPING BULKS PIPE, FLANGES, FITTINGS, GASKETS 18-Sep-13 A 0
COMIM5.2.15 RECEIPT AT SITE OF ELECTRICAL BULKS 18-J ul-13 A 0
COMIM5.2.2 RECEIPT AT SITE OF DIESEL GENERATOR PACKAGE 21-Apr-12 A 0
COMIM5.2.3 RECEIPT AT SITE OF RAW WATER TREATMENT PACKAGE 15-Nov-12 A 0
COMIM5.2.4 RECEIPT AT SITE OF INSTRUMENT AIR PACKAGE 24-Oct-12 A 0
COMIM5.2.5 RECEIPT AT SITE OF OWS PACKAGE 20-Nov-13 A 0
COMIM5.2.6 RECEIPT AT SITE OF SEWAGE/EFFLUENT TREATMENT PACKAGES 21-Oct-13 A 0
COMIM5.2.7 RECEIPT AT SITE OF POWER &DISTRIBUTION TRANSFORMERS 20-Dec-12 A 0
COMIM5.2.8 RECEIPT AT SITE OF HEAT TRACING 21-Nov-13 A 0
COMIM5.2.9 RECEIPT AT SITE OF HV / LV SWITCHGEAR 23-J an-13 A 0
COMIM5.3.1 COMP. INSTAL. OF STEAM GENERATION PACKAGE 15-Nov-12 A 0
COMIM5.3.10 COMP. INSTAL. OF HV / LV SWITCHGEAR 18-Sep-13 A 0
COMIM5.3.11 COMP. INSTAL. OF FIRE WATER AND J OCKEY PUMPS 22-J ul-13 A 0
COMIM5.3.13 COMP. INSTAL. OF FREE-ISSUE ITEMS 15-May-13 0
COMIM5.3.14 COMP. INSTAL. OF ALL EXPORT PUMPS 31-May-12 A 0
COMIM5.3.15 COMP. INSTAL. OF GAS TURBINES 25-J an-12 A 0
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 3 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 4 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
COMIM5.3.16 COMP. INSTAL. OF SEHMS HARDWARE / EQUIPMENT 15-May-13 0
COMIM5.3.17 COMP. INSTAL. OF CUSTODY TRANSFER METERING PACKAGE 20-Mar-12 A 0
COMIM5.3.2 COMP. INSTAL. OF INSTRUMENT AIR PACKAGE 16-Nov-12 A 0
COMIM5.3.3 COMP. INSTAL. OF RAW WATER TREATMENT PACKAGE 17-J an-13 A 0
COMIM5.3.4 COMP. INSTAL. OF TREATED WATER PACKAGE 20-Nov-13 A 0
COMIM5.3.5 COMP. INSTAL. OF DIESEL GENERATOR PACKAGE 30-Apr-12 A 0
COMIM5.3.6 COMP. INSTAL. OF OWS PACKAGE 19-Mar-14 A 0
COMIM5.3.7 COMP. INSTAL. OF SEWAGE/EFFLUENT TREATMENT PACKAGES 13-J un-13 A 0
COMIM5.3.8 COMP. INSTAL. OF POWER &DISTRIBUTION TRANSFORMERS 23-J ul-13 0
COMIM5.3.9 COMP. INSTAL. OF HEAT TRACING 30-Dec-13 0
COMIM5.4.1 COMPLETION OF SUPER-STRUCTURE FOR ADMIN BUILDING 01-Nov-12 A 0
COMIM5.4.2 COMPLETION OF SUB-STRUCTURE FOR ADMIN BUILDING 15-May-13 0
COMIM5.4.3 COMPLETION OF INTERNAL FIT-OUT FOR CONTROL BUILDINGS 15-May-13 0
COMIM5.5.1 COMPLETION OF WORKSHOP/WAREHOUSE/LABORATORY 15-May-13 0
COMIM5.5.2 COMPLETION OF ADMINISTRATION BDLG 15-May-13 0
COMIM5.5.3 COMPLETION OF SECURITY BUILDINGS &CABINS 15-May-13 0
COMIM5.5.4 COMPLETION OF FIRE STATION &MEDICAL CENTRE 15-May-13 0
COMIM5.5.5 COMPLETION OF MAIN PLANT SUBSTATION 15-May-13 0
COMIM5.5.6 COMPLETION OF 11KV SUBSTATION 15-May-13 0
COMIM5.5.7 COMPLETION OF SEHMS SUBSTATION 15-May-13 0
COMIM5.5.8 COMPLETION OF MAIN DG ROOM 15-May-13 0
COMIM5.5.9 COMPLETION OF VARIOUS MCC ROOMS 03-J ul-13 0
COMIM5.6.1 COMPLETION OF WALLS, FENCING INCL. SECURITY GATES, CABINS, TOWERS 15-May-13 0
COMIM5.6.10 COMPLETION OF ALL OTHER CIVIL, MECHANICAL, ELECTRICAL &INSTRUMENT... 06-J an-14 0
COMIM5.6.12 TEST. &COMMI. OF STEAM GENERATION PACKAGE 17-Aug-13 0
COMIM5.6.13 TEST. &COMMI. OF DIESEL GENERATOR PACKAGE 15-May-13 0
COMIM5.6.14 TEST. &COMMI. OF RAW WATER TREATMENT PACKAGE 02-Oct-13 0
COMIM5.6.15 TEST. &COMMI. OF TREATED WATER PACKAGE 29-Oct-13 0
COMIM5.6.16 TEST. &COMMI. OF INSTRUMENT AIR PACKAGE 15-May-13 0
COMIM5.6.17 TEST. &COMMI. OF OWS PACKAGE 03-J ul-13 0
COMIM5.6.18 TEST. &COMMI. OF SEWAGE/EFFLUENT TREATMENT PACKAGES 29-Oct-13 0
COMIM5.6.19 TEST. &COMMI. OF POWER &DISTRIBUTION TRANSFORMERS 23-J ul-13 0
COMIM5.6.2 COMPLETION OF TERMINAL ROADS AND DRAINS 09-Sep-13 0
COMIM5.6.20 TEST. &COMMI. OF HEAT TRACING 30-Dec-13 0
COMIM5.6.21 TEST. &COMMI. OF HV / LV SWITCHGEAR 15-May-13 0
COMIM5.6.22 TEST. &COMMI. OF FIRE WATER AND FOAM SYSTEM 09-Aug-13 0
COMIM5.6.24 TEST. &COMMI. OF TERMINAL PIPING 06-J an-14 0
COMIM5.6.25 TEST. &COMMI. OF TERMINAL TANKS FIRE WATER, CLOSED DRAIN, FOAM C... 09-Aug-13 0
COMIM5.6.26 TEST. &COMMI. OF DIESEL STORAGE AND DISTRIBUTION SYSTEM 15-May-13 0
COMIM5.6.3 COMPLETION OF DRILLING OF 5 BORE WELLS AND ASSOCIATED PUMP &ITS P... 01-J un-13 0
COMIM5.6.4 COMPLETION OF TERMINAL PIPING, VALVES (INCL FREE-ISSUE), PIPING RACK... 14-Dec-13 0
COMIM5.6.5 COMPLETION OF POWER AND CONTROL CABLING 30-Nov-13 0
COMIM5.6.7 COMPLETION OF DIESEL STORAGE AND DISTRIBUTION SYSTEM 15-May-13 0
COMIM5.6.8 COMPLETION OF ALL TANKS &VESSELS FIRE WATER, CLOSED DRAIN, FOA... 15-May-13 0
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 5 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 6 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
DETAIL ENGINEERING DETAIL ENGINEERING
02-Sep-1... 09-J an-13 A 611
Equi pment / System Packages Equi pment / System Packages 15-Sep-1... 24-Aug-11 A 277
EPR100 Receive of Package Scheme, Flow Diagrams, system data sheets, equipment layout ... 15-Sep-1... 16-Sep-10 A 1
EPR110 Review of Package Scheme, Flow Diagrams, system data sheets, equipment layout ... 18-Sep-1... 26-Nov-10 A 25
EPR140 Release of P&ID for package items byIOT 19-J an-1... 08-Aug-11 A 30
EPR150 Release of Final Equipment Layout drawings, GADs byIOT 17-J an-1... 04-J ul-11 A 15
EPR160 Participation of Hazop studyfor package equipments 04-Aug-1... 24-Aug-11 A 7
EPR170 Incorporatiion of recommendations as per Hazop Review 12-J un-1... 24-J un-11 A 10
Ci vi l Ci vi l 10-Sep-1... 27-Apr-12 A 467
ECV050 Receipt of AFC Architectural Drawing from TCEL / CEIL 12-Oct-1... 15-Oct-10 A 5
ECV100 Receipt of AFC Drawing of Admin Building from TCEL / CEIL 21-Sep-1... 23-Sep-10 A 2
ECV110 Receipt AFC Drawing for Control Building from TCEL / CEIL 21-Sep-1... 23-Sep-10 A 2
ECV120 Receipt of AFC Drawing of canopyat entrance from TCEL / CEIL 15-Oct-1... 18-Oct-10 A 2
ECV130 Receipt of AFC Drawing of laboratoryBuilding from TCEL / CEIL 20-Sep-1... 21-Sep-10 A 2
ECV140 Receipt of AFC Drawing of Warehouse/ Workshop Building from TCEL / CEIL 21-Sep-1... 23-Sep-10 A 2
ECV150 Receipt of AFC Drawing of Electrical substation from TCEL / CEIL 21-Sep-1... 25-Sep-10 A 5
ECV160 Receipt AFC Drawing for Fire station Building from TCEL / CEIL 18-Sep-1... 23-Sep-10 A 5
ECV170 Receipt of AFC Drawing of Medical Centre from TCEL / CEIL 18-Sep-1... 20-Sep-10 A 2
ECV180 Receipt of AFC Drawing for Fire Water Pump House from TCEL / CEIL 20-Oct-1... 29-Oct-10 A 10
ECV190 Receipt of AFC Drawing for Pump/Package Foundation from TCEL / CEIL 19-Oct-1... 27-Oct-10 A 10
ECV200 Release of Pipe Sleepers Drgs for Fire Water Network 13-J ul-11 A 24-J ul-11 A 1
ECV210 Receipt of AFC Drawing of Roads,Culverts, walkways, etc from TCEL / CEIL 17-Sep-1... 20-Sep-10 A 3
ECV220 Receipt of AFC Drawing of Dyke wall and Paving in the Tank Farm from TCEL / CEIL 23-Sep-1... 24-Sep-10 A 2
ECV240 Receipt AFC Drawing of MCC &Substation from TCEL / CEIL 20-Sep-1... 21-Sep-10 A 2
ECV250 Receipt of AFC Drawing for Drains system from TCEL / CEIL 17-Sep-1... 18-Sep-10 A 2
ECV260 Detail Engineeing for Foundations of Package items 10-Sep-1... 22-Sep-10 A 15
Equipment Foundation Equipment Foundation 05-Sep-1... 27-Apr-12 A 241
ECV270 Fdn Drgs for Air Compressor 10-J an-1... 10-Feb-12 A 25
ECV280 Fdn Drgs for STP Package 12-Dec-1... 30-Dec-11 A 25
ECV290 Fdn Drgs for Water Treatment Package 16-J an-1... 27-Feb-12 A 25
ECV300 Fdn Drgs for OWS Treatment Package 23-Apr-1... 27-Apr-12 A 15
ECV310 Fdn Drgs for Nitrogen Package 02-J an-1... 10-Feb-12 A 25
ECV320 Fdn Drgs for Steam Generation Package / Boiler 01-Feb-1... 10-Feb-12 A 25
ECV330 Fdn Drgs for Pumps 21-Apr-1... 25-Apr-12 A 25
ECV340 Fdn Drgs for Fuel &Gas System (KO Drum,Cartridge Filter, Electric Heater) 28-Mar-1... 09-Apr-12 A 25
ECV350 Fdn Drgs for NGR 26-Mar-1... 20-Apr-12 A 25
ECV360 Fdn Drgs for Transformer 06-Dec-1... 23-Dec-11 A 25
ECV370 Fdn Drgs for SHEMS Transformer 05-Dec-1... 30-Dec-11 A 25
ECV380 Fdn Drgs for Vent Stack 05-Sep-1... 23-Feb-12 A 25
ECV390 Fdn Drgs for DG Set 05-Dec-1... 29-Dec-11 A 25
ECV400 Fdn Drgs for Foam Pump Skid 16-J an-1... 22-Feb-12 A 25
ECV410 Fdn Drgs for Foam Concentrate Tank 27-Feb-1... 03-Apr-12 A 25
ECV420 Fdn Drgs for Fire Water Tank (New) 01-Feb-1... 26-Mar-12 A 25
ECV430 Fdn Drgs for Fire Water Pump 01-Mar-1... 11-Apr-12 A 25
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 7 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 8 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
Pi pi ng Pi pi ng 08-Sep-1... 12-J ul-12 A 437
EPIP090 Incorporate Vendor datas and Finalisation of Plot Plan 22-Feb-1... 08-May-12 A 30
EPIP100 Receipt of P&ID Piping Layout, GAD, Sectional Drawings from TCEL/CEIL 08-Sep-1... 09-Sep-10 A 2
EPIP110 Receipt of Updated PMS and VMS from TCEL / CEIL 08-Sep-1... 09-Sep-10 A 2
EPIP120 Layout &Isometric drgs for U/G Services like OWS / CBD / Sewage 13-Apr-1... 29-Apr-11 A 1
EPIP130 Layout &Isometric for Fire Water Network 21-Apr-1... 21-Apr-11 A 1
EPIP140 Issue of Piping/ Fitting MTO-1 byIOT 21-Sep-1... 10-Nov-10 A 10
EPIP150 Issue of Piping / Fitting MTO-2 15-Feb-1... 15-Feb-11 A 10
EPIP160 Issue of Isometric from CEIL/Vendor 22-Feb-1... 12-J ul-12 A 60
EPIP170 Detail Engineeing for Package items 18-J an-1... 08-Apr-11 A 15
Mechani cal Mechani cal 16-Sep-1... 01-J un-12 A 46
EME120 Issue of MR for Oilywater/ Sewage water treatment package 16-Sep-1... 18-Sep-10 A 2
EME140 Issue of MR for Plant and Treated water package 16-Sep-1... 21-Sep-10 A 2
EME150 Issue of MR for Plant and Instrument Air Package 16-Sep-1... 21-Sep-10 A 2
EME160 Issue of MR for Raw Water Treatment Package 16-Sep-1... 21-Sep-10 A 1
EME170 Issue of MR for Steam generation system package 16-Sep-1... 21-Sep-10 A 2
EME175 Issue of MR for Nitrogen Generation System 16-Sep-1... 21-Sep-10 A 5
EME180 Issue of MR for Fuel Gas System 29-Sep-1... 03-Dec-10 A 20
EME220 Issue of MR for Pipes Bulks 21-Sep-1... 23-Sep-10 A 2
EME250 Issue of MR for Fire water pump package 16-Sep-1... 21-Sep-10 A 2
EME260 Issue of MR for Closed Drain Pump 16-Sep-1... 21-Sep-10 A 2
EME270 Issue of MR for Diesel Unloading pump 16-Sep-1... 21-Sep-10 A 2
EME280 Issue of MR for Reinforecement Steel / Structural Steel Bulk items 21-Sep-1... 26-Oct-10 A 40
EME290 Issue of MR for Air conditioning and Ventiliation system 16-Sep-1... 20-Nov-10 A 2
EME300 Issue of MR for EOT Crane or Material Handling system 16-Sep-1... 21-Sep-10 A 6
EME310 Detail Engineering for Tanks (Fabrication Drawings.) 28-Oct-1... 01-J un-12 A 25
El ectri cal El ectri cal 02-Sep-1... 11-Apr-12 A 91
EEL100 Receipt of SLDs from TCEL / CEIL 27-Sep-1... 28-Sep-10 A 1
EEL120 Receipt of Approved Area classification Drawing from TCEL / CEIL 29-Oct-1... 06-Nov-10 A 10
EEL130 Receipt of Approvevd Load List from TCEL / CEIL 27-Sep-1... 28-Sep-10 A 1
EEL140 Issue of MR for Transformer 28-Sep-1... 30-Sep-10 A 2
EEL150 Issue of MR for UPS 28-Sep-1... 30-Sep-10 A 2
EEL160 Issue of MR for Switchgear/Panel 28-Sep-1... 30-Sep-10 A 2
EEL170 Receipt of Approvevd data sheet &Cable Schedule from TCEL / CEIL 02-Sep-1... 21-Sep-10 A 5
EEL180 Issue of MR C.P. System 30-Sep-1... 08-Oct-10 A 10
EEL190 Issue of MR for DG 30-Sep-1... 01-Oct-10 A 2
EEL200 Issue of MR for Batteryand BatteryCharger 30-Sep-1... 01-Oct-10 A 2
EEL210 Issue of MR for NGR 30-Sep-1... 01-Oct-10 A 2
EEL220 Detail Engineeing for Package items 01-Dec-1... 11-Apr-12 A 15
Instrumentati on Instrumentati on 25-Sep-1... 09-May-12 A 82
EIN100 Receipt of Approvevd instrument indexfrom TCEL / CEIL 11-Oct-1... 15-Oct-10 A 5
EIN110 Receipt of Approvevd I/O list from TCEL / CEIL 28-Sep-1... 02-Oct-10 A 5
EIN120 Receipt of Approvevd Instrument data sheet from TCEL /CEIL 25-Sep-1... 30-Sep-10 A 5
EIN130 Receipt of Approvevd Instrument Hook up drawing from TCEL / CEIL 31-Dec-1... 03-J an-11 A 7
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 9 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 10 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
EIN140 Issue of MR for Bulk Items (MOV / PCV / Transmitters / Gauges etc.) 16-Oct-1... 12-Nov-10 A 30
EIN150 Detail Engineeing for Package items 20-Dec-1... 09-May-12 A 15
Addi ti on Engi neeri ng-Fi re Fi ghti ng Changes Addi ti on Engi neeri ng-Fi re Fi ghti ng Changes 25-Apr-1... 05-Sep-11 A 74
MDPP-FPSC-0001 RECEIPT OF CONSOLIDATED CHANGE LIST ON FPS FROM CEIL AND CHANGE ... 15-J ul-11 A 0
MDPP-FPSC-E-00001 RECEIPT OF REVISED PLOT PLAN 02-Sep-1... 05-Sep-11 A 1
MDPP-FPSC-E-0002MR FOR FIRE WATER MAIN &J OCKEY PUMP 25-Apr-1... 25-Apr-11 A 1
MDPP-FPSC-E-0003MR FOR FOAM CONCENTRATE TANK 25-Apr-1... 25-Apr-11 A 1
MDPP-FPSC-E-0004MR FOR FOAM CONCENTRATE 25-Apr-1... 25-Apr-11 A 1
MDPP-FPSC-E-0005MR FOR FOAM SYSTEM ACCESSORIES 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0006MR FOR DELUGE VALVES 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0007MR FOR STRAINERS 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0008MR FOR GATE VALVES 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0009MR FOR CHECK VALVES 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0010MR FOR ELECTROMAGNETIC FLOW METER 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0011MR FOR PLC FOR PUMPS 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0012MR FOR RUBBER EXPANSION BELLOW 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0022MR FOR CP SYSTEM 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0032MR FOR FPS-PIPES 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0042MR FOR FPS-FITTINGS 24-May-1... 24-May-11 A 1
MDPP-FPSC-E-0052MR FOR FPS-FLANGES &MISCELLENOUS 24-May-1... 24-May-11 A 1
ENGINEERING-FREE ISSUE MATERIAL ENGINEERING-FREE ISSUE MATERIAL 20-Sep-1... 09-J an-13 A 601
EFI010 Receipt of Input of free issue material from CEIL 20-Sep-1... 28-Sep-10 A 10
EFI030 Receipt of Electrical Input for GT / MAIN LINE PUMP / BOOSTER PUMPS/ CTM Pkg 20-Oct-1... 28-Feb-11 A 10
EFI040 Receipt of Civil Foundation drawing of free issue material from CEIL 31-J an-1... 01-May-12 A 10
EFI050 Detail Engineering for Clean agent system, location of Fire Extinguisher byVendor 20-Mar-1... 30-Mar-12 A 10
EFI051 Receipt of Hydrant Layout form CEIL/TCE 11-Dec-1... 09-J an-13 A 10
AS BUILT DRAWING AS BUILT DRAWING
18-Nov-13 10-J an-14 39
EBD100 As Built drawing &Final Documentation 18-Nov-13 10-J an-14 60
PROCUREMENT PROCUREMENT
17-Sep-1... 20-Sep-13 777
SUBCONTRACTING SUBCONTRACTING 30-Sep-1... 14-Feb-12 A 129
CIVIL/STRUCTURAL CIVIL/STRUCTURAL 30-Sep-1... 08-J an-11 A 40
SC120 Prep. of Tender &award of contract for all Civil Package (Road, Dyke wall, drain etc.) 30-Sep-1... 25-Oct-10 A 25
SC130 Finalisation of Civil Contractor for all packages (Equipment foundations etc.) 02-Oct-1... 03-J an-11 A 60
SC140 Prep. of Tender &award of contract for Building Contractor 04-Oct-1... 08-J an-11 A 25
MECHANICAL/PIPING MECHANICAL/PIPING 03-J an-1... 06-J ul-11 A 22
SC160 Prep. of Tender Mechanical ( Piping &Fire Fighting) 03-J an-1... 04-Feb-11 A 20
SC170 Finalisation of Mechanical Contractor 12-Feb-1... 06-J ul-11 A 5
ELECTRICAL ELECTRICAL 30-Dec-1... 14-Feb-12 A 16
SC260 Preparation and Issue Tender for Electrical 30-Dec-1... 07-Feb-11 A 22
SC270 Finalisation of Tender for Electrical Contractor 11-Feb-1... 14-Feb-12 A 25
INSTRUMENT INSTRUMENT 29-Dec-1... 14-Feb-12 A 29
SC180 Preparation and Issue Instrumentation Tender 29-Dec-1... 01-Feb-11 A 22
SC190 Finalisation of Instrumentation Contractor 09-Feb-1... 14-Feb-12 A 5
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 11 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 12 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
INSULATION INSULATION 29-Dec-1... 21-Dec-11 A 9
SC200 Preparation and Issue Tender for piping Insulation 29-Dec-1... 02-Feb-11 A 15
SC210 Finalisation of Tender for Insulation contractor 08-Feb-1... 21-Dec-11 A 7
PAINTING PAINTING 30-Dec-1... 01-J un-11 A 22
SC220 Preparation and Issue Tender for Painting 30-Dec-1... 07-Feb-11 A 15
SC230 Finalisation of Tender for Painting Contractor 15-Feb-1... 01-J un-11 A 5
MECHANICAL/ EQUIPMENT MECHANICAL/ EQUIPMENT 17-Sep-1... 17-Sep-13 587
OWS Package OWS Package 20-Sep-1... 13-Aug-13 127
PRE120 Issue Enquiry 20-Sep-1... 20-Sep-10 A 1
PRE122 Bids received 20-Sep-1... 01-Oct-10 A 10
PRE123 TBA / CBA 29-Sep-1... 25-Oct-10 A 20
PRE124 Ordering for Oilywater treatment package 25-Oct-1... 28-Oct-10 A 8
PRE130 Mfg and Del at site-Oilywater treatment package 28-Oct-1... 13-Aug-13 160
Water Treatment Package Water Treatment Package 17-Sep-1... 14-Sep-13 163
PRE191 Issue Enquiry 17-Sep-1... 21-Sep-10 A 1
PRE192 Bids received 18-Sep-1... 05-Oct-10 A 10
PRE193 TBA / CBA 27-Sep-1... 25-Oct-10 A 15
PRE194 Ordering of Raw Water Treatment Package 25-Oct-1... 28-Oct-10 A 8
PRE195 Mfg and Del at site-Water Treatment Package 28-Oct-1... 14-Sep-13 200
STP Package STP Package 18-Sep-1... 08-J un-13 133
PRE160 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1
PRE162 Bids received 20-Sep-1... 05-Oct-10 A 10
PRE163 TBA / CBA 05-Oct-1... 25-Oct-10 A 12
PRE164 Ordering for Sewage water treatment package 25-Oct-1... 28-Oct-10 A 8
PRE170 Mfg and Del at site- Sewage water treatment package 28-Oct-1... 08-J un-13 160
Closed Drain Pump Closed Drain Pump 18-Sep-1... 23-J ul-12 A 207
PRE100 Issue Enquiry 18-Sep-1... 20-Sep-10 A 1
PRE102 Bids received 20-Sep-1... 30-Oct-10 A 8
PRE103 TBA / CBA 31-Oct-1... 28-J an-11 A 14
PRE104 Ordering for Closed Drain Pump 28-J an-1... 07-Feb-11 A 7
PRE110 Mfg and Del at site-Closed Drain pump 28-Feb-1... 23-J ul-12 A 150
Diesel Unloading Pump Diesel Unloading Pump 18-Sep-1... 30-May-12 A 172
PRE260 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1
PRE262 Bids received 25-Sep-1... 28-Oct-10 A 8
PRE263 TBA / CBA 28-Oct-1... 23-Nov-10 A 15
PRE264 Ordering for Diesel unloading pump 27-Nov-1... 17-Dec-10 A 8
PRE270 Mfg and Del at site-Diesel unloading pump 17-Dec-1... 30-May-12 A 150
Interface Transfer Pump Interface Transfer Pump 18-Sep-1... 20-Dec-12 A 172
PRE272 Bids received 25-Sep-1... 28-Oct-10 A 8
PRE273 TBA / CBA 28-Oct-1... 23-Nov-10 A 15
PRE274 Ordering for Interface Transfer Pump 27-Nov-1... 17-Dec-10 A 8
PRE280 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1
PRE290 Mfg and Del at site-Interface Transfer Pump 17-Dec-1... 20-Dec-12 A 150
Structural Steel / Reinforcement Steel/ Plates Structural Steel / Reinforcement Steel/ Plates 23-Sep-1... 12-Dec-12 A 80
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 13 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 14 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
PRE300 Issue Enquiry 23-Sep-1... 24-Sep-10 A 1
PRE302 Bids received 24-Sep-1... 20-Oct-10 A 10
PRE303 TBA / CBA 20-Oct-1... 02-Nov-10 A 15
PRE304 Ordering of Structural Steel / Reinforcement Steel 05-Nov-1... 01-J un-11 A 25
PRE310 Mfg and Del at site-Structural steel and Plate 06-Nov-1... 12-Dec-12 A 80
Treated Water Package Treated Water Package 0
Air Compressor Air Compressor 18-Sep-1... 28-Nov-12 A 292
PRE180 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1
PRE182 Bids received 20-Sep-1... 19-Oct-10 A 10
PRE183 TBA / CBA 20-Oct-1... 16-Feb-11 A 15
PRE184 Ordering of Air Compressor 16-Feb-1... 16-Mar-11 A 8
PRE190 Mfg and Del at site-Air Compressor-(Dryer &receiver pending) 23-May-1... 28-Nov-12 A 160
Nitrogen Package Nitrogen Package 21-Sep-1... 22-Nov-12 A 240
PRE201 Issue Enquiry 21-Sep-1... 22-Sep-10 A 1
PRE202 Bids received 22-Sep-1... 29-Oct-10 A 12
PRE203 TBA / CBA 29-Oct-1... 24-Nov-10 A 20
PRE204 Ordering for Nitrogen Generation System 24-Nov-1... 01-Dec-10 A 10
PRE210 Mfg and Del at site-Nitrogen Generation System 02-Dec-1... 22-Nov-12 A 230
HVAC System HVAC System 18-Sep-1... 25-Dec-12 A 256
PRE340 Issue Enquiry 18-Sep-1... 04-Nov-10 A 1
PRE342 Bids received 04-Nov-1... 14-Dec-10 A 10
PRE343 TBA / CBA 15-Dec-1... 17-J an-11 A 25
PRE345 Ordering of Air conditioning and Ventiliation system 19-J an-1... 03-Feb-11 A 7
PRE350 Mfg and Del at site-Air conditioning and Ventiliation system 28-Feb-1... 25-Dec-12 A 200
EOT Crane EOT Crane 27-Sep-1... 17-J an-13 A 233
PRE360 Issue Enquiry 27-Sep-1... 28-Sep-10 A 1
PRE362 Bids received 28-Sep-1... 16-Oct-10 A 8
PRE363 TBA / CBA 16-Oct-1... 10-Feb-11 A 15
PRE364 Ordering of -EOT Crane or Material Handling system 10-Feb-1... 15-Mar-11 A 8
PRE370 Mfg and Del at site-EOT Crane 17-Mar-1... 17-J an-13 A 160
Fuel & Gas System Fuel & Gas System 30-Sep-1... 27-Dec-12 A 238
PRE400 Issue Enquiry 30-Sep-1... 03-Dec-10 A 1
PRE402 Bids received 15-Dec-1... 20-Dec-10 A 10
PRE403 TBA / CBA 23-Dec-1... 24-J an-11 A 15
PRE405 Ordering of Fuel &Gas System 25-J an-1... 10-Feb-11 A 8
PRE410 Mfg and Del at site-Fuel &Gas System 15-Feb-1... 27-Dec-12 A 200
Steam Generation System / Boiler Steam Generation System / Boiler 18-Sep-1... 16-Oct-12 A 232
PRE420 Issue Enquiry 18-Sep-1... 21-Sep-10 A 1
PRE422 Bids received 20-Sep-1... 04-Oct-10 A 10
PRE423 TBA / CBA 04-Oct-1... 21-Oct-10 A 22
PRE424 Ordering of Steam generation system 21-Oct-1... 25-Oct-10 A 8
PRE430 Mfg and Del at site-Steam generation system 26-Oct-1... 16-Oct-12 A 240
SMC Panel Tank SMC Panel Tank 01-J un-1... 28-J un-13 135
PRE434 Ordering of SMC Panel Tank 01-J un-1... 09-J un-11 A 8
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 15 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 16 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
PRE470 Mfg and Del at site-SMC Panel Tank 13-J un-1... 28-J un-13 180
Fire Fighting System Fire Fighting System 18-Sep-1... 17-Sep-13 587
PRE440 Issue Enquiry 18-Sep-1... 18-Sep-10 A 1
PRE442 Bids received 20-Sep-1... 10-Dec-10 A 8
PRE443 TBA / CBA 11-Dec-1... 20-J an-11 A 20
PRE444 Ordering of Fire Fighting System 31-J an-1... 12-Apr-11 A 20
PRE450 Mfg and Del at site of Fire Fighting System 07-J un-1... 17-Sep-13 140
PIPING PIPING 27-Sep-1... 22-J ul-13 301
Pipes - 1st MTO Pipes - 1st MTO 27-Sep-1... 15-Dec-11 A 131
PPIP100 Issue Enquiry 27-Sep-1... 28-Sep-10 A 1
PPIP102 Bids received 28-Sep-1... 07-Oct-10 A 10
PPIP103 TBA / CBA 07-Oct-1... 30-Oct-10 A 5
PPIP104 Ordering for Pipes -1st MTO (in Lots) 30-Oct-1... 16-Nov-10 A 60
PPIP110 Mfg and Del at site-Pipe 1st MTO-A1 18-Nov-1... 15-Dec-11 A 150
Pipes - 2nd MTO Pipes - 2nd MTO 15-Feb-1... 14-Nov-12 A 79
PPIP120 Issue Enquiry 15-Feb-1... 15-Feb-11 A 1
PPIP122 Bids received 15-Feb-1... 31-Oct-11 A 1
PPIP123 TBA / CBA 15-Feb-1... 15-Feb-11 A 5
PPIP124 Ordering for Pipes -2nd MTO 15-Feb-1... 15-Feb-11 A 30
PPIP130 Mfg and Deliveryat site- 2nd MTO-A3 15-Feb-1... 14-Nov-12 A 70
Fittings / Flanges Fittings / Flanges 12-Oct-1... 04-J ul-13 193
PPIP140 Issue Enquiry 12-Oct-1... 13-Oct-10 A 1
PPIP142 Bids received 13-Oct-1... 30-Oct-10 A 10
PPIP143 TBA / CBA 03-Nov-1... 06-Nov-10 A 5
PPIP144 Ordering for Fitting / Flanges 09-Nov-1... 11-Apr-11 A 25
PPIP150 Mfg and Del at site- Fittings / Flanges 15-Apr-1... 04-J ul-13 90
Gate / Ball Valve Gate / Ball Valve 27-Sep-1... 22-J ul-13 301
PRE320 Issue Enquiry 27-Sep-1... 28-Sep-10 A 1
PRE322 Bids received 28-Sep-1... 16-Oct-10 A 8
PRE323 TBA / CBA 16-Oct-1... 23-Oct-10 A 8
PRE324 Ordering of Ball / Gate Valve 15-Nov-1... 16-Mar-11 A 14
PRE330 Mfg and Del at site- Ball and Gate Valve 25-May-1... 22-J ul-13 180
ELECTRICAL ELECTRICAL 21-Sep-1... 20-Sep-13 438
6.6KV Switchgear 6.6KV Switchgear 23-Sep-1... 08-May-12 A 177
PELE131 Issue Enquiryfor 6.6KV Switchgear 23-Sep-1... 24-Sep-10 A 1
PELE132 Bids received 30-Sep-1... 15-Oct-10 A 7
PELE133 TBA / CBA 15-Oct-1... 24-Nov-10 A 15
PELE134 Ordering of Switchgear 24-Nov-1... 01-Dec-10 A 12
PELE135 Mfg and Del at site- 6.6KV Switchgear 02-Dec-1... 08-May-12 A 220
11KV Switchgear 11KV Switchgear 22-Sep-1... 13-J ul-12 A 184
PELE120 Issue Enquiry 22-Sep-1... 23-Sep-10 A 1
PELE122 Bids received 30-Sep-1... 15-Oct-10 A 10
PELE124 TBA / CBA 15-Oct-1... 24-Nov-10 A 12
PELE125 Ordering of Switchgear 25-Nov-1... 01-Dec-10 A 22
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 17 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 18 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
PELE130 Mfg and Del at site-11KV Switchgear 02-Dec-1... 13-J ul-12 A 220
Distribution Transformer Distribution Transformer 21-Sep-1... 12-Mar-12 A 192
EPR130 Preparation of Detail specifications, data sheets, standard drawings and documents f... 28-Oct-1... 03-Feb-11 A 30
PELE151 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1
PELE152 Bids received 05-Oct-1... 15-Oct-10 A 8
PELE153 TBA / CBA 19-Oct-1... 24-Nov-10 A 20
PELE154 Ordering of Transformer 24-Nov-1... 01-Dec-10 A 8
PELE155 Mfg and Del at site-Distribution Transformer 02-Dec-1... 12-Mar-12 A 240
415 V Panel 415 V Panel 22-Sep-1... 13-Nov-12 A 177
PELE100 Issue Enquiry 22-Sep-1... 23-Sep-10 A 1
PELE102 Bids received 04-Oct-1... 15-Oct-10 A 7
PELE104 TBA / CBA 15-Oct-1... 24-Nov-10 A 18
PELE105 Ordering of Panel 25-Nov-1... 01-Dec-10 A 8
PELE110 Mfg and Del at site- Panel 02-Dec-1... 13-Nov-12 A 220
Power Transformer Power Transformer 21-Sep-1... 12-Nov-12 A 201
PELE140 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1
PELE141 Bids received 04-Oct-1... 13-Nov-10 A 10
PELE142 TBA / CBA 13-Nov-1... 24-Nov-10 A 20
PELE143 Ordering of Power Transformer 24-Nov-1... 31-Dec-10 A 8
PELE150 Mfg and Del at site-Power transformer 31-Dec-1... 12-Nov-12 A 210
DG Sets DG Sets 21-Sep-1... 21-Apr-12 A 248
PELE160 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1
PELE162 Bids received 04-Oct-1... 12-Nov-10 A 8
PELE163 TBA / CBA 13-Nov-1... 15-Dec-10 A 20
PELE164 Ordering of DG sets 16-Dec-1... 14-J an-11 A 10
PELE170 Mfg and Del at site-DG sets 14-J an-1... 21-Apr-12 A 180
Cables Cables 21-Sep-1... 03-Dec-12 A 152
PELE180 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1
PELE182 Bids received 09-Oct-1... 15-Oct-10 A 7
PELE183 TBA / CBA 15-Oct-1... 22-Nov-10 A 12
PELE184 Ordering of Cables 29-Nov-1... 30-Dec-10 A 25
PELE190 Mfg and Del at site-Cable 30-Dec-1... 03-Dec-12 A 150
UPS / Battery Charger UPS / Battery Charger 04-Oct-1... 05-Nov-11 A 227
PELE200 Issue Enquiry 04-Oct-1... 04-Oct-10 A 1
PELE202 Bids received 04-Oct-1... 11-Oct-10 A 7
PELE203 TBA / CBA 11-Oct-1... 23-Dec-10 A 20
PELE204 Ordering of UPS and batterycharger 23-Dec-1... 11-Feb-11 A 8
PELE210 Mfg and Del at site-UPS and Batterycharger 28-Feb-1... 05-Nov-11 A 175
Heat Tracing System Heat Tracing System 25-Nov-1... 20-Sep-13 433
PELE220 Issue Enquiry 25-Nov-1... 25-Nov-10 A 1
PELE222 Bids received 26-Nov-1... 30-Nov-10 A 8
PELE223 TBA / CBA 01-Dec-1... 13-May-11 A 18
PELE224 Ordering of Heat Tracing System 13-May-1... 21-Dec-11 A 10
PELE230 Mfg and Del at site-Heat tracing 15-Nov-1... 20-Sep-13 145
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 19 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 20 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CP System CP System 04-Nov-1... 30-J an-12 A 196
PELE240 Issue Enquiry 04-Nov-1... 04-Nov-10 A 1
PELE242 Bids received 05-Nov-1... 25-Nov-10 A 8
PELE243 TBA / CBA 25-Nov-1... 03-J an-11 A 20
PELE244 Ordering of CP System 03-J an-1... 04-Feb-11 A 10
PELE250 Mfg and Del at site-CP System 15-Feb-1... 30-J an-12 A 150
Electrical Bulk Material Electrical Bulk Material 04-Oct-1... 01-J ul-13 187
PELE260 Issue Enquiry 04-Oct-1... 06-Oct-10 A 2
PELE262 Bids received 30-Oct-1... 06-Nov-10 A 8
PELE263 TBA / CBA 06-Nov-1... 04-Feb-11 A 15
PELE264 Ordering of Electrical Bulk material (Cable Tray, Switches, DB etc.) 17-J an-1... 14-Feb-11 A 20
PELE270 Mfg and Del at site-Electrical Bulk material 17-Feb-1... 01-J ul-13 120
NGR NGR 01-Oct-1... 31-Dec-10 A 149
PELE280 Issue Enquiry 01-Oct-1... 02-Oct-10 A 1
PELE282 Bids received 02-Oct-1... 11-Oct-10 A 8
PELE283 TBA / CBA 11-Oct-1... 25-Nov-10 A 20
PELE284 Ordering of NGR 26-Nov-1... 17-Dec-10 A 10
PELE290 Mfg and Del at site-NGR 18-Dec-1... 31-Dec-10 A 130
INSTRUMENTATION INSTRUMENTATION 21-Sep-1... 05-Aug-13 452
Tank Farm Management System (TFMS) Tank Farm Management System (TFMS) 22-Sep-1... 30-Nov-12 A 145
PINS100 Issue Enquiry 22-Sep-1... 22-Sep-10 A 1
PINS102 Bids received 01-Oct-1... 15-Nov-10 A 10
PINS103 TBA / CBA 15-Nov-1... 24-Nov-10 A 10
PINS104 Ordering of TFMS 26-Nov-1... 03-J an-11 A 15
PINS110 Mfg and Del at site-TFMS 03-J an-1... 30-Nov-12 A 150
Control Valve / MOV/On-Off /ESV Control Valve / MOV/On-Off /ESV 23-Sep-1... 05-Aug-13 249
PINS120 Issue Enquiry 23-Sep-1... 23-Sep-10 A 1
PINS122 Bids received 14-Oct-1... 18-Nov-10 A 8
PINS123 TBA / CBA 18-Nov-1... 28-Dec-10 A 8
PINS124 Ordering of Control valve/On Off Valve/ESV/MOV's 28-Dec-1... 10-Feb-11 A 20
PINS130 Mfg and Del at site-Control Valve/MOV's /On off valves/ESV 15-Feb-1... 05-Aug-13 230
Instrumentation Bulk items Instrumentation Bulk items 02-Oct-1... 15-J ul-13 186
PINS140 Issue Enquiry 02-Oct-1... 02-Oct-10 A 1
PINS142 Bids received 08-Oct-1... 10-Nov-10 A 10
PINS143 TBA / CBA 12-Nov-1... 07-Feb-11 A 8
PINS144 Ordering of Instruments Bulk item 29-Dec-1... 01-Mar-11 A 25
PINS150 Mfg and Del at site-Instrumentation Bulk items 15-Mar-1... 15-J ul-13 150
Instrument Cables Instrument Cables 21-Sep-1... 21-J ul-13 237
PINS160 Issue Enquiry 21-Sep-1... 21-Sep-10 A 1
PINS162 Bids received 09-Oct-1... 19-Oct-10 A 10
PINS163 TBA / CBA 19-Oct-1... 16-Dec-10 A 8
PINS164 Ordering for Instrument Cable 25-Nov-1... 26-Feb-11 A 25
PINS170 Mfg and Del at site-Instrument Cable 11-Apr-1... 21-J ul-13 150
Instrustion Detection System Instrustion Detection System 16-J an-1... 13-Apr-12 A 156
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 21 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 22 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
PINS172 Bids received 13-Feb-1... 13-Feb-11 A 10
PINS173 TBA / CBA 25-Mar-1... 25-Mar-11 A 8
PINS174 Ordering for Instrusion Detection System 04-Apr-1... 04-Apr-11 A 25
PINS180 Issue Enquiry 16-J an-1... 16-J an-11 A 1
PINS190 Mfg and Del at site-Instrusion Detection System 05-Apr-1... 13-Apr-12 A 180
Fire & Gas Detection System Fire & Gas Detection System 12-Oct-1... 20-J ul-13 236
PINS182 Bids received 17-Dec-1... 20-Dec-10 A 10
PINS183 TBA / CBA 19-Oct-1... 16-Dec-10 A 8
PINS184 Ordering for Fire &Gas Detection System 25-Nov-1... 26-Feb-11 A 25
PINS200 Issue Enquiry 12-Oct-1... 13-Oct-10 A 1
PINS210 Mfg and Del at site-Fire &Gas Detection System 11-Apr-1... 20-J ul-13 155
Nitrogen Blanketing Valves Nitrogen Blanketing Valves 19-Nov-1... 01-May-12 A 157
PINS192 Bids received 17-J an-1... 27-J an-11 A 10
PINS193 TBA / CBA 27-J an-1... 16-Mar-11 A 8
PINS194 Ordering for Nitrogen Blanketing Valves 17-Mar-1... 09-J un-11 A 25
PINS220 Issue Enquiry 19-Nov-1... 19-Nov-10 A 1
PINS230 Mfg and Del at site-Nitrogen Blanketing Valves 20-J un-1... 01-May-12 A 180
Instruments Cable Trays / Conduits Instruments Cable Trays / Conduits 02-J an-1... 10-J un-13 93
PINS202 Bids received 25-J an-1... 31-J an-12 A 10
PINS203 TBA / CBA 02-Feb-1... 15-Feb-12 A 8
PINS204 Ordering for Instrument Cable Trays / Conduits 16-Mar-1... 17-Apr-12 A 25
PINS240 Issue Enquiry 02-J an-1... 02-J an-12 A 1
PINS250 Mfg and Del at site-Instrument Cable Trays / Conduits 23-Apr-1... 10-J un-13 69
In-Line Instruments In-Line Instruments 16-Nov-1... 23-Sep-11 A 170
PINS212 Bids received 19-Nov-1... 29-Nov-10 A 30
PINS213 TBA / CBA 30-Nov-1... 31-Dec-10 A 8
PINS214 Ordering for In-line Instruments 03-J an-1... 25-J an-11 A 25
PINS260 Issue Enquiry 16-Nov-1... 17-Nov-10 A 1
PINS270 Mfg and Del at site-In-line Instruments 01-Feb-1... 23-Sep-11 A 180
Addi ti onal / Procurement- Fi re Fi ghti ng Changes Addi ti onal / Procurement- Fi re Fi ghti ng Changes 10-Nov-1... 27-Aug-13 599
FIRE WATER PUMPS (3 NOS) FIRE WATER PUMPS (3 NOS) 31-May-1... 14-Aug-12 A 216
MDPP-FPSC-P-0001 ISSUE ENQUIRY 31-May-1... 31-May-11 A 1
MDPP-FPSC-P-0011 RECEIPT BIDS 01-J un-1... 01-J un-11 A 1
MDPP-FPSC-P-0021 TECHNICAL BID ANALYSIS 02-J un-1... 06-J un-11 A 1
MDPP-FPSC-P-0031 COMMERCIAL BID ANALYSIS 06-J un-1... 07-J un-11 A 1
MDPP-FPSC-P-0041 ISSUE LOI 07-J un-1... 08-J un-11 A 1
MDPP-FPSC-P-0051 MANUFACTURING &DELIVERY AT SITE 01-J ul-11 A 14-Aug-12 A 250
MDPP-FPSC-P-0061 ISSUE PO / PR TO VENDOR 08-J un-1... 09-J un-11 A 1
MDPP-FPSC-P-0071 RECEIPT OF VENDOR DRAWINGS 07-J ul-11 A 10-Feb-12 A 15
MDPP-FPSC-P-0081 APPROVAL OF VENDOR DRAWINGS 05-Dec-1... 19-Mar-12 A 15
JOCKEY PUMP (2 NOS) JOCKEY PUMP (2 NOS) 31-May-1... 20-Mar-12 A 217
MDPP-FPSC-P-0251 ISSUE ENQUIRY 31-May-1... 31-May-11 A 1
MDPP-FPSC-P-0261 RECEIPT BIDS 01-J un-1... 03-J un-11 A 1
MDPP-FPSC-P-1321 TECHNICAL BID ANALYSIS 03-J un-1... 06-J un-11 A 1
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 23 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 24 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
MDPP-FPSC-P-1331 COMMERCIAL BID ANALYSIS 06-J un-1... 06-J un-11 A 1
MDPP-FPSC-P-1341 ISSUE LOI 06-J un-1... 07-J un-11 A 1
MDPP-FPSC-P-1351 MANUFACTURING &DELIVERY AT SITE 20-J ul-11 A 04-Oct-11 A 230
MDPP-FPSC-P-1361 ISSUE PO / PR TO VENDOR 08-J un-1... 09-J un-11 A 1
MDPP-FPSC-P-1371 RECEIPT OF VENDOR DRAWINGS 07-J ul-11 A 05-J an-12 A 15
MDPP-FPSC-P-1381 APPROVAL OF VENDOR DRAWINGS 05-Dec-1... 20-Mar-12 A 15
FOAM CONCENTRATE TANK FOAM CONCENTRATE TANK 03-J an-1... 26-Mar-12 A 260
MDPP-FPSC-P-0091 ISSUE ENQUIRY 03-J an-1... 03-J an-11 A 1
MDPP-FPSC-P-0101 RECEIPT BIDS 28-Feb-1... 28-Feb-11 A 26
MDPP-FPSC-P-0111 TECHNICAL BID ANALYSIS 14-Mar-1... 06-J un-11 A 1
MDPP-FPSC-P-0121 COMMERCIAL BID ANALYSIS 06-J un-1... 10-J un-11 A 1
MDPP-FPSC-P-0131 ISSUE LOI 10-J un-1... 13-J un-11 A 1
MDPP-FPSC-P-0141 MANUFACTURING &DELIVERY AT SITE 15-Feb-1... 26-Mar-12 A 75
MDPP-FPSC-P-0151 ISSUE PO / PR TO VENDOR 13-J un-1... 13-J un-11 A 1
MDPP-FPSC-P-0161 RECEIPT OF VENDOR DRAWINGS 30-J un-1... 27-Dec-11 A 18
MDPP-FPSC-P-0171 APPROVAL OF VENDOR DRAWINGS 26-Dec-1... 13-Feb-12 A 15
FIRE WATER TANK- PLATE'S FIRE WATER TANK- PLATE'S 15-Dec-1... 31-May-12 A 140
MDPP-FPSC-P-1081 ISSUE ENQUIRY 15-Dec-1... 15-Dec-11 A 1
MDPP-FPSC-P-1091 RECEIPT BIDS 16-Dec-1... 30-Dec-11 A 18
MDPP-FPSC-P-1101 TECHNICAL BID ANALYSIS 02-J an-1... 03-J an-12 A 1
MDPP-FPSC-P-1111 COMMERCIAL BID ANALYSIS 04-J an-1... 04-J an-12 A 1
MDPP-FPSC-P-1121 ISSUE LOI 16-J an-1... 16-J an-12 A 1
MDPP-FPSC-P-1131 MANUFACTURING &DELIVERY AT SITE 28-Mar-1... 31-May-12 A 90
FIRE PROTECTION SYSTEM-PIPES FIRE PROTECTION SYSTEM-PIPES 02-Aug-1... 23-Nov-11 A 156
MDPP-FPSC-P-1141 ISSUE ENQUIRY 02-Aug-1... 02-Aug-11 A 1
MDPP-FPSC-P-1151 RECEIPT BIDS 03-Aug-1... 05-Aug-11 A 18
MDPP-FPSC-P-1161 TECHNICAL BID ANALYSIS 05-Aug-1... 05-Aug-11 A 1
MDPP-FPSC-P-1171 COMMERCIAL BID ANALYSIS 08-Aug-1... 08-Aug-11 A 1
MDPP-FPSC-P-1181 ISSUE LOI 09-Aug-1... 09-Aug-11 A 1
MDPP-FPSC-P-1191 MANUFACTURING &DELIVERY AT SITE 11-Aug-1... 23-Nov-11 A 120
FIRE PROTECTION SYSTEM-FITTINGS FIRE PROTECTION SYSTEM-FITTINGS 28-J ul-11 A 08-May-12 A 187
MDPP-FPSC-P-1201 ISSUE ENQUIRY 28-J ul-11 A 28-J ul-11 A 1
MDPP-FPSC-P-1211 RECEIPT BIDS 29-J ul-11 A 05-Aug-11 A 18
MDPP-FPSC-P-1221 TECHNICAL BID ANALYSIS 05-Aug-1... 09-Aug-11 A 1
MDPP-FPSC-P-1231 COMMERCIAL BID ANALYSIS 09-Aug-1... 12-Aug-11 A 1
MDPP-FPSC-P-1241 ISSUE LOI 09-Sep-1... 12-Sep-11 A 1
MDPP-FPSC-P-1251 MANUFACTURING &DELIVERY AT SITE 15-Mar-1... 08-May-12 A 30
FIRE PROTECTION SYSTEM-FLANGES & MISC. FIRE PROTECTION SYSTEM-FLANGES & MISC. 29-J ul-11 A 05-J un-12 A 214
MDPP-FPSC-P-1261 ISSUE ENQUIRY 29-J ul-11 A 29-J ul-11 A 1
MDPP-FPSC-P-1271 RECEIPT BIDS 29-J ul-11 A 05-Aug-11 A 18
MDPP-FPSC-P-1281 TECHNICAL BID ANALYSIS 05-Aug-1... 09-Aug-11 A 1
MDPP-FPSC-P-1291 COMMERCIAL BID ANALYSIS 09-Aug-1... 12-Aug-11 A 1
MDPP-FPSC-P-1301 ISSUE LOI 09-Sep-1... 15-Sep-11 A 1
MDPP-FPSC-P-1311 MANUFACTURING &DELIVERY AT SITE 19-Apr-1... 05-J un-12 A 40
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 25 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 26 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
FOAM CONCENTRATE FOAM CONCENTRATE 24-J an-1... 15-May-13 195
MDPP-FPSC-P-0181 ISSUE ENQUIRY 24-J an-1... 24-J an-11 A 1
MDPP-FPSC-P-0191 RECEIPT BIDS 26-J an-1... 28-J an-11 A 26
MDPP-FPSC-P-0201 TECHNICAL BID ANALYSIS 31-J an-1... 31-J an-11 A 1
MDPP-FPSC-P-0211 COMMERCIAL BID ANALYSIS 02-Feb-1... 02-Feb-11 A 1
MDPP-FPSC-P-0221 ISSUE LOI 03-Feb-1... 24-Feb-11 A 1
MDPP-FPSC-P-0231 PRODUCTION &DELIVERY AT SITE 30-May-1... 15-May-13 90
MDPP-FPSC-P-0241 ISSUE PO / PR TO VENDOR 25-Feb-1... 28-Feb-11 A 1
FOAM SYSTEM ACCESSORIES FOAM SYSTEM ACCESSORIES 10-Nov-1... 27-Aug-13 379
MDPP-FPSC-P-0271 ISSUE ENQUIRY 14-Nov-1... 21-Nov-11 A 1
MDPP-FPSC-P-0281 RECEIPT BIDS 16-Nov-1... 25-Nov-11 A 20
MDPP-FPSC-P-0291 TECHNICAL BID ANALYSIS 30-Nov-1... 30-Nov-11 A 1
MDPP-FPSC-P-0301 COMMERCIAL BID ANALYSIS 01-Dec-1... 01-Dec-11 A 1
MDPP-FPSC-P-0311 ISSUE LOI 05-Dec-1... 06-Dec-11 A 1
MDPP-FPSC-P-0321 MANUFACTURING &DELIVERY AT SITE 14-Dec-1... 27-Aug-13 105
MDPP-FPSC-P-0331 ISSUE PO / PR TO VENDOR 07-Dec-1... 07-Dec-11 A 1
MDPP-FPSC-P-0341 RECEIPT OF VENDOR DRAWINGS 10-Nov-1... 21-Nov-11 A 18
MDPP-FPSC-P-0351 APPROVAL OF VENDOR DRAWINGS 30-Nov-1... 30-Nov-11 A 15
DELUGE VALVES DELUGE VALVES 19-J an-1... 06-Nov-12 A 433
MDPP-FPSC-P-0361 ISSUE ENQUIRY 12-Dec-1... 12-Dec-11 A 1
MDPP-FPSC-P-0371 RECEIPT BIDS 13-Dec-1... 13-J an-12 A 26
MDPP-FPSC-P-0381 TECHNICAL BID ANALYSIS 14-J an-1... 17-J an-12 A 1
MDPP-FPSC-P-0391 COMMERCIAL BID ANALYSIS 19-J an-1... 02-Feb-11 A 1
MDPP-FPSC-P-0401 ISSUE LOI 08-Mar-1... 07-J un-12 A 1
MDPP-FPSC-P-0411 MANUFACTURING &DELIVERY AT SITE 11-J ul-12 A 06-Nov-12 A 120
MDPP-FPSC-P-0421 ISSUE PO / PR TO VENDOR 02-Mar-1... 02-Mar-11 A 1
MDPP-FPSC-P-0431 RECEIPT OF VENDOR DRAWINGS 04-Feb-1... 08-Feb-11 A 18
MDPP-FPSC-P-0441 APPROVAL OF VENDOR DRAWINGS 13-Feb-1... 15-Feb-11 A 12
STRAINERS STRAINERS 02-Mar-1... 12-Aug-13 358
MDPP-FPSC-P-0451 ISSUE ENQUIRY 02-Mar-1... 02-Mar-11 A 1
MDPP-FPSC-P-0461 RECEIPT BIDS 04-Mar-1... 10-Mar-11 A 15
MDPP-FPSC-P-0471 TECHNICAL BID ANALYSIS 11-Mar-1... 12-Mar-11 A 1
MDPP-FPSC-P-0481 COMMERCIAL BID ANALYSIS 13-Mar-1... 14-Mar-11 A 1
MDPP-FPSC-P-0491 ISSUE LOI 15-Mar-1... 15-Mar-11 A 1
MDPP-FPSC-P-0501 MANUFACTURING &DELIVERY AT SITE 12-Apr-1... 12-Aug-13 90
MDPP-FPSC-P-0511 ISSUE PO / PR TO VENDOR 15-Mar-1... 15-Mar-11 A 1
MDPP-FPSC-P-0521 RECEIPT OF VENDOR DRAWINGS 03-Mar-1... 07-Mar-11 A 18
MDPP-FPSC-P-0531 APPROVAL OF VENDOR DRAWINGS 04-Mar-1... 04-Mar-11 A 15
GATE VALVES GATE VALVES 02-Aug-1... 15-J ul-13 222
MDPP-FPSC-P-0541 ISSUE ENQUIRY 02-Aug-1... 02-Aug-11 A 1
MDPP-FPSC-P-0551 RECEIPT BIDS 03-Aug-1... 05-Aug-11 A 20
MDPP-FPSC-P-0561 TECHNICAL BID ANALYSIS 15-Aug-1... 22-Aug-11 A 1
MDPP-FPSC-P-0571 COMMERCIAL BID ANALYSIS 24-Aug-1... 25-Aug-11 A 1
MDPP-FPSC-P-0581 ISSUE LOI 02-Sep-1... 05-Sep-11 A 1
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 27 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 28 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
MDPP-FPSC-P-0591 MANUFACTURING &DELIVERY AT SITE 31-Oct-1... 15-J ul-13 220
MDPP-FPSC-P-0601 ISSUE PO / PR TO VENDOR 03-Aug-1... 09-Aug-11 A 1
MDPP-FPSC-P-0611 RECEIPT OF VENDOR DRAWINGS 04-Aug-1... 11-Aug-11 A 18
MDPP-FPSC-P-0621 APPROVAL OF VENDOR DRAWINGS 19-Aug-1... 19-Aug-11 A 15
CHECK VALVES CHECK VALVES 03-Aug-1... 27-J un-13 203
MDPP-FPSC-P-0631 ISSUE ENQUIRY 03-Aug-1... 03-Aug-11 A 1
MDPP-FPSC-P-0641 RECEIPT BIDS 04-Aug-1... 08-Aug-11 A 26
MDPP-FPSC-P-0651 TECHNICAL BID ANALYSIS 10-Aug-1... 16-Aug-11 A 1
MDPP-FPSC-P-0661 COMMERCIAL BID ANALYSIS 17-Aug-1... 18-Aug-11 A 1
MDPP-FPSC-P-0671 ISSUE LOI 05-Sep-1... 05-Sep-11 A 1
MDPP-FPSC-P-0681 MANUFACTURING &DELIVERY AT SITE 13-Sep-1... 27-J un-13 72
MDPP-FPSC-P-0691 ISSUE PO / PR TO VENDOR 16-Aug-1... 04-Sep-11 A 1
MDPP-FPSC-P-0701 RECEIPT OF VENDOR DRAWINGS 23-Aug-1... 25-Aug-11 A 18
MDPP-FPSC-P-0711 APPROVAL OF VENDOR DRAWINGS 29-Aug-1... 29-Aug-11 A 15
ELECTROMAGNETIC FLOW METER ELECTROMAGNETIC FLOW METER 03-J an-1... 22-May-13 239
MDPP-FPSC-P-0721 ISSUE ENQUIRY 03-J an-1... 03-J an-11 A 1
MDPP-FPSC-P-0731 RECEIPT BIDS 04-J an-1... 17-J an-11 A 26
MDPP-FPSC-P-0741 TECHNICAL BID ANALYSIS 17-J an-1... 28-J an-11 A 1
MDPP-FPSC-P-0751 COMMERCIAL BID ANALYSIS 31-J an-1... 08-Feb-11 A 1
MDPP-FPSC-P-0761 ISSUE LOI 28-J an-1... 29-J an-11 A 1
MDPP-FPSC-P-0771 MANUFACTURING &DELIVERY AT SITE 06-Mar-1... 22-May-13 150
MDPP-FPSC-P-0781 ISSUE PO / PR TO VENDOR 24-Feb-1... 24-Feb-11 A 1
MDPP-FPSC-P-0791 RECEIPT OF VENDOR DRAWINGS 16-J an-1... 24-J an-11 A 18
MDPP-FPSC-P-0801 APPROVAL OF VENDOR DRAWINGS 26-J an-1... 31-J an-11 A 15
PLC FOR PUMPS PLC FOR PUMPS 11-J an-1... 17-Aug-11 A 482
MDPP-FPSC-P-0811 ISSUE ENQUIRY 11-J an-1... 11-J an-11 A 1
MDPP-FPSC-P-0821 RECEIPT BIDS 14-J an-1... 19-J an-11 A 26
MDPP-FPSC-P-0831 TECHNICAL BID ANALYSIS 25-J an-1... 25-J an-11 A 1
MDPP-FPSC-P-0841 COMMERCIAL BID ANALYSIS 02-Feb-1... 04-Feb-11 A 1
MDPP-FPSC-P-0851 ISSUE LOI 07-Feb-1... 10-Feb-11 A 1
MDPP-FPSC-P-0861 MANUFACTURING &DELIVERY AT SITE 09-Feb-1... 17-Aug-11 A 137
MDPP-FPSC-P-0871 ISSUE PO / PR TO VENDOR 25-J an-1... 26-J an-11 A 1
MDPP-FPSC-P-0881 RECEIPT OF VENDOR DRAWINGS 21-J an-1... 30-J an-11 A 18
MDPP-FPSC-P-0891 APPROVAL OF VENDOR DRAWINGS 28-J an-1... 01-Feb-11 A 12
RUBBER EXPANSION BELLOW RUBBER EXPANSION BELLOW 09-Mar-1... 13-Oct-12 A 114
MDPP-FPSC-P-0901 ISSUE ENQUIRY 09-Mar-1... 09-Mar-11 A 1
MDPP-FPSC-P-0911 RECEIPT BIDS 10-Mar-1... 21-Mar-11 A 26
MDPP-FPSC-P-0921 TECHNICAL BID ANALYSIS 29-Mar-1... 04-Apr-11 A 1
MDPP-FPSC-P-0931 COMMERCIAL BID ANALYSIS 06-Apr-1... 08-Apr-11 A 1
MDPP-FPSC-P-0941 ISSUE LOI 15-Apr-1... 15-Apr-11 A 1
MDPP-FPSC-P-0951 MANUFACTURING &DELIVERY AT SITE 31-May-1... 13-Oct-12 A 120
MDPP-FPSC-P-0961 ISSUE PO / PR TO VENDOR 15-Apr-1... 15-Apr-11 A 1
MDPP-FPSC-P-0971 RECEIPT OF VENDOR DRAWINGS 17-Apr-1... 30-Apr-11 A 18
MDPP-FPSC-P-0981 APPROVAL OF VENDOR DRAWINGS 01-May-1... 11-May-11 A 15
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 29 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 30 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CP SYSTEM CP SYSTEM 10-Mar-1... 20-J ul-11 A 157
MDPP-FPSC-P-0991 ISSUE ENQUIRY 10-Mar-1... 10-Mar-11 A 1
MDPP-FPSC-P-1001 RECEIPT BIDS 14-Mar-1... 14-Mar-11 A 1
MDPP-FPSC-P-1011 TECHNICAL BID ANALYSIS 15-Mar-1... 17-Mar-11 A 1
MDPP-FPSC-P-1021 COMMERCIAL BID ANALYSIS 19-Mar-1... 22-Mar-11 A 1
MDPP-FPSC-P-1031 ISSUE LOI / AMMENDMENT 23-Mar-1... 23-Mar-11 A 1
MDPP-FPSC-P-1041 MANUFACTURING &DELIVERY AT SITE 21-Apr-1... 20-J ul-11 A 100
MDPP-FPSC-P-1051 ISSUE PO / PR TO VENDOR 23-Mar-1... 23-Mar-11 A 1
MDPP-FPSC-P-1061 RECEIPT OF VENDOR DRAWINGS 31-Mar-1... 07-Apr-11 A 18
MDPP-FPSC-P-1071 APPROVAL OF VENDOR DRAWINGS 09-Apr-1... 12-Apr-11 A 13
PROCUREMENT- FREE ISSUE MATERIAL PROCUREMENT- FREE ISSUE MATERIAL 06-J un-1... 01-J un-13 679
PRFI001 Deliveryat Site of GT 06-J un-1... 29-J un-11 A 20
PRFI011 Deliveryat Site of Export Booster Pumps 12-J ul-11 A 31-J ul-11 A 20
PRFI021 Deliveryat Site of CustodyTransfer Metering system 05-J ul-11 A 20-J ul-11 A 20
PRFI031 Deliveryat Site of Butterfly/Ball Valves above 24" size 15-May-13* 01-J un-13 20
CONSTRUCTION CONSTRUCTION
07-Oct-1... 06-J an-14 891
CNCM001 Site Mobilization 07-Oct-1... 28-Oct-10 A 20
CNCM011 Camp Establishment 28-Oct-1... 03-Dec-10 A 30
MOBILISATION MOBILISATION 28-Oct-1... 22-Nov-11 A 407
CNM100 Mobilise Civil Contractor - For Roads, Dyke Wall 30-Oct-1... 18-Nov-10 A 22
CNM105 Mobilise Civil Contractor - For Packages (foundations etc.) 16-Dec-1... 28-Dec-10 A 22
CNM110 Mobilise Building Contractor 12-Nov-1... 27-Dec-10 A 12
CNM130 Mobilise Mechanical / Piping Contractor 07-Apr-1... 30-Apr-11 A 15
CNM140 Mobilization of Batching Plant-II 28-Oct-1... 03-Dec-10 A 45
CNM150 Mobilise Contractor- Instrumentation Contractor 24-May-1... 13-J un-11 A 20
CNM160 Mobilise Electrical Contractor 03-May-1... 25-May-11 A 12
CNM180 Mobilise Insulation &C.P. Contractor 02-Nov-1... 22-Nov-11 A 15
CNM190 Mobilise Plant and Machineryat site 31-Dec-1... 02-Mar-11 A 90
PHASE-1 PHASE-1 23-Nov-1... 06-J an-14 846
THREE OIL TANKS (TAG NO.-2,3,4) THREE OIL TANKS (TAG NO.-2,3,4) 11-Feb-1... 04-May-13 A 357
Construction of Vertical Dyke Wall V-2 Construction of Vertical Dyke Wall V-2 11-Feb-1... 07-J un-11 A 183
CNCV550 Release of Front 11-Feb-11 A 0
CNCV592 RCC 17-Mar-1... 07-J un-11 A 72
CNCV610 Excavation 22-Feb-1... 28-Feb-11 A 15
CNCV651 PCC 02-Mar-1... 09-Mar-11 A 15
Construction of Horizontal Dyke Wall H-1 Construction of Horizontal Dyke Wall H-1 18-Apr-1... 06-Nov-12 A 273
CNCV270 Release of Front 15-Feb-12 A 0
CNCV331 PCC 11-Mar-1... 03-Sep-12 A 101
CNCV332 RCC 18-Apr-1... 06-Nov-12 A 150
CNCV390 Excavation 22-Feb-1... 18-J ul-12 A 97
Construction of Vertical Dyke Wall V-4 Construction of Vertical Dyke Wall V-4 15-J ul-12 A 03-Nov-12 A 68
CNCV612 RCC 10-Sep-1... 03-Nov-12 A 79
CNCV640 Release of Front 15-J ul-12 A 0
CNCV650 Excavation 30-J ul-12 A 08-Aug-12 A 15
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 31 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 32 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV671 PCC 13-Aug-1... 29-Aug-12 A 15
Construction of Vertical Dyke Wall V-3 Construction of Vertical Dyke Wall V-3 15-Feb-1... 11-J un-12 A 317
CNCV602 RCC 23-Mar-1... 11-J un-12 A 79
CNCV620 Release of Front 15-Feb-12 A 0
CNCV630 Excavation 22-Feb-1... 28-Feb-12 A 15
CNCV661 PCC 02-Mar-1... 15-Mar-12 A 15
Construction of Vertical Dyke Wall V-5 Construction of Vertical Dyke Wall V-5 17-Feb-1... 25-J un-12 A 320
CNCV622 RCC 21-Mar-1... 25-J un-12 A 80
CNCV660 Release of Front 17-Feb-12 A 0
CNCV670 Excavation 20-Feb-1... 29-Feb-12 A 15
CNCV681 PCC 06-Mar-1... 16-Mar-12 A 15
Construction of Horizontal Dyke Wall H-2 Construction of Horizontal Dyke Wall H-2 15-Feb-1... 18-Aug-12 A 274
CNCV280 Release of Front 15-Feb-12 A 0
CNCV352 RCC 06-Mar-1... 18-Aug-12 A 152
CNCV400 Excavation 21-Feb-1... 27-Mar-12 A 97
CNCV401 PCC 01-Mar-1... 03-J ul-12 A 101
Construction of Horizontal Dyke Wall H-3 Construction of Horizontal Dyke Wall H-3 15-Feb-1... 04-Dec-12 A 200
CNCV310 Release of Front 15-Feb-12 A 0
CNCV362 RCC 31-J ul-12 A 04-Dec-12 A 84
CNCV410 Excavation 15-Feb-1... 11-Apr-12 A 35
CNCV411 PCC 31-May-1... 20-J un-12 A 65
Construction of Vertical Dyke Wall V-8 Construction of Vertical Dyke Wall V-8 07-Feb-1... 04-Aug-12 A 247
CNCV382 RCC 30-May-1... 04-Aug-12 A 90
CNCV431 PCC 30-Mar-1... 05-J un-12 A 75
CNCV440 Release of Front 07-Feb-12 A 0
CNCV450 Excavation 10-Feb-1... 22-Mar-12 A 45
Construction of Vertical Dyke Wall V-7 Construction of Vertical Dyke Wall V-7 09-Feb-1... 03-Apr-13 A 103
CNCV372 RCC 02-May-1... 21-Aug-12 A 90
CNCV420 Release of Front 09-Feb-12 A 0
CNCV421 PCC 11-Apr-1... 11-J ul-12 A 75
CNCV430 Excavation 15-Feb-1... 03-Apr-13 A 45
Construction of Vertical Dyke Wall V-6 Construction of Vertical Dyke Wall V-6 16-Feb-1... 04-Sep-12 A 355
CNCV402 RCC 12-Apr-1... 04-Sep-12 A 90
CNCV451 PCC 30-Mar-1... 10-J ul-12 A 75
CNCV480 Release of Front 16-Feb-12 A 0
CNCV490 Excavation 22-Feb-1... 22-Mar-12 A 35
Construction of Vertical Dyke Wall V-1 Construction of Vertical Dyke Wall V-1 26-Dec-1... 13-J un-12 A 266
CNCV392 RCC 14-Mar-1... 13-J un-12 A 60
CNCV441 PCC 24-J an-1... 17-Apr-12 A 45
CNCV460 Release of Front 26-Dec-11 A 0
CNCV470 Excavation 02-J an-1... 31-J an-12 A 35
Construction of Vertical Dyke Wall V-9 Construction of Vertical Dyke Wall V-9 18-J an-1... 04-May-13 A 98
CNCV412 RCC 02-Mar-1... 04-May-13 A 58
CNCV461 PCC 29-Feb-1... 20-Mar-13 A 47
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 33 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 34 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV500 Release of Front 18-J an-12 A 0
CNCV510 Excavation 08-Feb-1... 04-Mar-12 A 35
EXPORT MANIFOLD,BOOSTER AND EXPORT PUMPS ETC (TAG-22,25 & 70) EXPORT MANIFOLD,BOOSTER AND EXPORT PUMPS ETC (TAG-22,25 & 70) 15-J un-1... 25-J un-13 482
Export Booster Pumps Export Booster Pumps 14-Nov-1... 31-May-12 A 182
CNCV380 Excavation 14-Nov-1... 16-Nov-11 A 6
CNCV385 Foundation 15-Nov-1... 07-Dec-11 A 21
INT150 Installation of Export and Booster Pump 21-Apr-1... 31-May-12 A 31
Export & Booster Pump House (SHED) Export & Booster Pump House (SHED) 03-Oct-1... 25-J un-13 334
CNCV224 Brick works -deleted 31-May-1... 31-May-12 A 45
CNCV232 Superstructure -deleted 31-May-1... 31-May-12 A 75
CNCV233 Structural Fab.,Shot Blasting &primer Painting 29-May-1... 25-J un-13 60
CNCV234 Structural Erection &Final painting 12-Sep-1... 26-Oct-12 A 45
CNCV251 Substructure 03-Oct-1... 10-J an-12 A 60
CNCV324 Sheet Fixing 08-Aug-1... 20-Sep-12 A 45
CNCV445 Finishing (Paving,Elect. Inst.,Doors &Window fixing,Painting) 12-J un-1... 15-Oct-12 A 80
Custody Transfer Metering (CTM) Custody Transfer Metering (CTM) 16-Nov-1... 15-Mar-12 A 68
CNCV370 Excavation 16-Nov-1... 22-Nov-11 A 15
CNCV375 Foundation 26-Dec-1... 17-J an-12 A 31
INT140 Installation of CustodyTransfer Metering 15-Feb-1... 15-Mar-12 A 21
Panel Room for CTM Panel Room for CTM 19-Dec-1... 14-Nov-12 A 270
CNCV242 Superstructure 01-Mar-1... 26-Mar-12 A 65
CNCV253 Structural Fab.,Shot Blasting &primer Painting 01-May-1... 25-J ul-12 A 60
CNCV474 Brick works 10-Apr-1... 13-J un-12 A 45
CNCV475 Finishing (Paving,Elect. Inst.,Doors &Window fixing,Painting) 25-J un-1... 08-Aug-12 A 70
CNCV484 Structural Erection &Final painting 12-Sep-1... 14-Nov-12 A 60
CNCV494 Sheet Fixing 23-Oct-1... 07-Nov-12 A 30
CNCV761 Substructure 19-Dec-1... 25-Feb-12 A 45
CTM Package Shed CTM Package Shed 15-J un-1... 29-Nov-12 A 482
CNCV181 Substructure 15-J un-1... 25-J an-12 A 60
CNCV184 Sheet Fixing 01-J un-1... 04-Aug-12 A 45
CNCV192 Superstructure 26-J an-1... 02-May-12 A 75
CNCV193 Masonary 17-May-1... 19-J un-12 A 45
CNCV255 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 02-J ul-12 A 29-Nov-12 A 110
CNCV691 Structural Fab.,Shot Blasting &primer Painting 26-J an-1... 10-May-12 A 75
CNCV701 Structural Erection. &final Painting 07-Aug-1... 23-Aug-12 A 110
LFO TANKS (TAG NO-44,45 & 46) LFO TANKS (TAG NO-44,45 & 46) 0
LFO MANIFOLD,EXPORT PUMP (TAG NO-65,66 & 67) LFO MANIFOLD,EXPORT PUMP (TAG NO-65,66 & 67) 03-Oct-1... 19-Dec-12 A 357
Interface Storage tanks Interface Storage tanks 03-Oct-1... 31-May-12 A 80
CNCV132 Excavation 03-Oct-1... 25-Nov-11 A 15
CNCV134 Barbending 28-Oct-1... 22-Nov-11 A 25
CNCV136 Form Work 28-Oct-1... 22-Nov-11 A 25
CNCV138 RCC 29-Dec-1... 05-Feb-12 A 35
CNCV140 Backfilling &Compaction 02-Apr-1... 31-May-12 A 8
Interface Transfer Pump Bay Interface Transfer Pump Bay 06-J ul-12 A 30-Aug-12 A 222
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 35 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 36 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV158 RCC 14-J ul-12 A 14-J ul-12 A 35
CNCV210 Backfilling &Compaction 19-J ul-12 A 28-J ul-12 A 10
CNCV244 Barbending 09-J ul-12 A 11-J ul-12 A 3
CNCV246 Form Work 11-J ul-12 A 13-J ul-12 A 25
CNCV262 Excavation 06-J ul-12 A 11-J ul-12 A 15
CNEQ180 Installation of Interface Transfer pump 08-Aug-1... 30-Aug-12 A 15
INTERFACE HOLDUP TANK INTERFACE HOLDUP TANK 01-Mar-1... 19-Dec-12 A 204
CNME460 Fabtication of Tank 01-Mar-1... 02-J ul-12 A 90
CNME470 Erection of Tank 15-J un-1... 05-Nov-12 A 65
CNME480 Hydrotesting of Tank 20-Nov-1... 30-Nov-12 A 10
CNME490 Painting of Tank 01-Dec-1... 19-Dec-12 A 21
INTERFACE STORAGE TANK-DYKE WALL INTERFACE STORAGE TANK-DYKE WALL 10-J ul-12 A 29-Aug-12 A 53
CNCV520 Excavation 10-J ul-12 A 14-J ul-12 A 11
CNCV632 RCC &RELATED FACILITIES 02-Aug-1... 29-Aug-12 A 75
CNCV711 PCC 13-J ul-12 A 31-J ul-12 A 21
INTERFACE HOLD UP TANK-DYKE WALL INTERFACE HOLD UP TANK-DYKE WALL 08-Aug-1... 22-Nov-12 A 111
CNCV530 Excavation 08-Aug-1... 15-Aug-12 A 90
CNCV642 RCC &RELATED FACILITIES 25-Oct-1... 14-Nov-12 A 120
CNCV721 PCC 06-Sep-1... 22-Nov-12 A 90
DYKE WALL AROUND TANK -9,10,11 DYKE WALL AROUND TANK -9,10,11 25-May-1... 07-Nov-12 A 131
CNCV662 RCC &RELATED FACILITIES 16-Aug-1... 07-Nov-12 A 120
CNCV680 Excavation 25-May-1... 14-J ul-12 A 90
CNCV741 PCC 28-May-1... 28-Aug-12 A 90
AIR COMPRESSOR & PSA NITROGEN SYSTEM (TAG NO-12) AIR COMPRESSOR & PSA NITROGEN SYSTEM (TAG NO-12) 22-J an-1... 20-Dec-12 A 380
Air Compressor Air Compressor 22-J an-1... 23-Aug-12 A 119
CNCV273 Earth Work 22-J an-1... 24-Mar-12 A 26
CNCV283 PCC 26-Mar-1... 26-Mar-12 A 36
CNCV313 Barbending 26-Mar-1... 30-Mar-12 A 31
CNCV323 Form Work 26-Mar-1... 30-Mar-12 A 31
CNCV333 RCC 31-Mar-1... 31-Mar-12 A 46
CNCV442 Back filling &Compaction 16-Apr-1... 23-Apr-12 A 11
CNEQ120 Installation of Air Compressor 15-May-1... 23-Aug-12 A 61
Nitrogen Package Nitrogen Package 20-Mar-1... 17-Sep-12 A 295
CNCV276 Earth Work 20-Mar-1... 24-Mar-12 A 26
CNCV286 PCC 26-Mar-1... 26-Mar-12 A 31
CNCV296 Barbending 26-Mar-1... 30-Mar-12 A 31
CNCV306 Form Work 26-Mar-1... 30-Mar-12 A 31
CNCV316 RCC 31-Mar-1... 16-May-12 A 46
CNCV472 Back filling &Compaction 30-May-1... 05-J un-12 A 11
CNEQ130 Installation of Nitrogen Generation Package 21-Aug-1... 17-Sep-12 A 46
Air Compressor Shed Air Compressor Shed 22-J an-1... 20-Dec-12 A 380
CNCV343 Earth Work 22-J an-1... 25-Mar-12 A 15
CNCV353 PCC 26-Mar-1... 26-Mar-12 A 1
CNCV363 Barbending 28-Mar-1... 02-J ul-12 A 30
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 37 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 38 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV373 Form Work 30-Mar-1... 13-J ul-12 A 30
CNCV383 RCC 20-Feb-1... 19-Apr-12 A 40
CNCV393 Structural Fab. Shot Blasting &Primer painting 15-J un-1... 04-Sep-12 A 60
CNCV403 Structural Erection &Final painting 26-J ul-12 A 04-Sep-12 A 40
CNCV413 Metal Sheet Fixing &Side Cladding 17-Sep-1... 10-Oct-12 A 60
CNCV423 Internal &External Painting 15-Nov-1... 20-Dec-12 A 50
FUEL GAS HANDLING (TAG NO-38) FUEL GAS HANDLING (TAG NO-38) 15-May-1... 02-Oct-12 A 298
Fuel Gas system foundation (KO Drum,Cartridge Filter, Electric Heater) Fuel Gas system foundation (KO Drum,Cartridge Filter, Electric Heater) 15-May-1... 02-Oct-12 A 298
CNCV349 Earth Work 15-May-1... 30-May-12 A 26
CNCV359 PCC 04-J un-1... 14-J un-12 A 6
CNCV369 Form Work 20-J un-1... 04-J ul-12 A 15
CNCV379 RCC 10-J ul-12 A 18-J ul-12 A 16
CNCV512 Back filling &Compaction 24-J ul-12 A 09-Aug-12 A 10
CNEQ250 Installation of Fuel &Gas system 03-Sep-1... 02-Oct-12 A 45
RAW WATER SYSTEM (TAG NO-34) RAW WATER SYSTEM (TAG NO-34) 14-J un-1... 02-Oct-13 307
CNCV414 Earth Work 15-J un-1... 09-J ul-12 A 25
CNCV424 PCC 25-J un-1... 18-J ul-12 A 60
CNCV434 Barbending 20-J ul-12 A 22-Aug-12 A 60
CNCV444 Form Work 08-Aug-1... 04-Sep-12 A 60
CNCV454 RCC 23-Aug-1... 16-Oct-12 A 90
CNCV464 Handover of Area 14-J un-12 A 0
CNCV502 Back filling &Compaction 14-Nov-1... 23-Nov-12 A 11
CNEQ185 Installation of Raw Water Package(Water Treatment Package 22-Nov-1... 02-Oct-13 55
WATER TREATMENT SYSTEM (TAG NO-35,36,37,51,56 & 72) WATER TREATMENT SYSTEM (TAG NO-35,36,37,51,56 & 72) 10-May-1... 29-Oct-13 369
Water Treatment Package (WTP) Water Treatment Package (WTP) 10-May-1... 29-Oct-13 363
CNCV274 Earth Work 10-May-1... 25-May-12 A 26
CNCV284 PCC 25-May-1... 30-May-12 A 31
CNCV294 Barbending 01-J un-1... 02-J ul-12 A 31
CNCV304 Form Work 06-J un-1... 03-J ul-12 A 21
CNCV314 RCC 06-J un-1... 18-J ul-12 A 46
CNCV452 Back filling &Compaction 01-Aug-1... 13-Aug-12 A 11
CNEQ195 Installation Testing &Commissioning of Water Treatment Package 16-Oct-1... 29-Oct-13 60
Treated Water Storage Tank (1263-TK-21) Treated Water Storage Tank (1263-TK-21) 15-J un-1... 14-Nov-12 A 273
CNME660 Pre-Fabtication of Plates 15-J un-1... 26-J un-12 A 90
CNME710 Hydrotesting of Tank 04-Sep-1... 14-Nov-12 A 10
CNME720 Erection &Painting of Tank 11-J ul-12 A 04-Oct-12 A 90
Treated Water Overhead Storage Tank-(1263-TK-22) Treated Water Overhead Storage Tank-(1263-TK-22) 15-J un-1... 11-Sep-13 107
CNEQ200 FDN &Fabrication &Erection of SMC Panel Tank 15-J un-1... 11-Sep-13 150
DM Water Tank DM Water Tank 15-May-1... 09-Nov-12 A 114
CNME730 Pre-Fabtication of Plates 17-May-1... 18-J ul-12 A 90
CNME740 Erection &Painting of Tank 15-May-1... 10-Sep-12 A 90
CNME750 Hydrotesting of Tank 10-Oct-1... 09-Nov-12 A 10
Filter Water Storage Tank Filter Water Storage Tank 11-May-1... 12-Nov-12 A 223
CNME760 Pre-Fabtication of Plates 11-May-1... 25-May-12 A 90
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 39 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 40 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNME770 Erection &Painting of Tank 25-May-1... 12-Sep-12 A 90
CNME780 Hydrotesting of Tank 04-Nov-1... 12-Nov-12 A 10
DUG BOREWELL DUG BOREWELL 18-May-1... 29-Oct-13 369
CNCV334 DRILLING 18-May-1... 01-J un-13 45
CNCV354 INSTALLATION OF PIPES 18-May-1... 16-J ul-13 60
CNCV364 FDN / FIXING OF PUMPS 17-J ul-13 14-Sep-13 60
CNCV374 CONNECTION OF PUMPS 31-Aug-13 29-Oct-13 60
STEAM GENERATION PLANT (TAG NO-21) STEAM GENERATION PLANT (TAG NO-21) 02-J an-1... 17-Aug-13 404
Steam Generation System / Boiler Foundation Steam Generation System / Boiler Foundation 25-J an-1... 17-Aug-13 169
CNCV277 Earth Work 25-J an-1... 15-Feb-12 A 31
CNCV287 PCC 31-J an-1... 09-Mar-12 A 46
CNCV297 Barbending 31-J an-1... 12-Mar-12 A 36
CNCV307 Form Work 02-Feb-1... 15-Mar-12 A 36
CNCV317 RCC 15-Feb-1... 24-Mar-12 A 76
CNCV482 Back filling &Compaction 29-Mar-1... 04-Apr-12 A 11
CNEQ260 Installation Testing &Commissioning of Steam Generation system 04-Sep-1... 17-Aug-13 95
Boiler House Shed (32MX24MX9H) Boiler House Shed (32MX24MX9H) 02-J an-1... 26-Dec-12 A 355
CNCV523 Earth Work 02-J an-1... 06-J an-12 A 15
CNCV533 PCC 09-J an-1... 20-J an-12 A 30
CNCV543 Barbending 02-Apr-1... 04-J un-12 A 30
CNCV553 Form Work 05-Apr-1... 12-J un-12 A 30
CNCV563 Structural Fab. Shot Blasting &Primer painting 17-May-1... 24-Aug-12 A 60
CNCV573 RCC 04-J un-1... 27-J un-12 A 40
CNCV583 Structural Erection &Final painting 20-J ul-12 A 23-Oct-12 A 40
CNCV593 Sheet Fixing 05-Sep-1... 03-Dec-12 A 80
CNCV603 Final Painting 14-Nov-1... 26-Dec-12 A 40
CLOSED DRAIN SYSTEM (TAG NO-10 & 59) CLOSED DRAIN SYSTEM (TAG NO-10 & 59) 06-J un-1... 14-Dec-12 A 380
CNEQ100 Installation of Closed drain Pump 14-Nov-1... 14-Dec-12 A 30
CLOSED DRAIN TANK PIT (CRUDE & LIGHT FLUSING OIL -1 NOS) CLOSED DRAIN TANK PIT (CRUDE & LIGHT FLUSING OIL -1 NOS) 22-Dec-1... 31-May-12 A 380
CNCV090 Excavation 22-Dec-1... 22-Feb-12 A 20
CNCV100 Barbending 27-Feb-1... 08-May-12 A 40
CNCV110 Form Work 28-Feb-1... 10-May-12 A 10
CNCV120 RCC 10-Mar-1... 16-May-12 A 60
CNCV125 Backfilling &Compaction 23-May-1... 31-May-12 A 16
CLOSED DRAIN TANK-FABRICATION (CRUDE & LIGHT FLUSING OIL -1 NOS) CLOSED DRAIN TANK-FABRICATION (CRUDE & LIGHT FLUSING OIL -1 NOS) 15-May-1... 13-Dec-12 A 237
CNME630 Pre-Fabtication &Transportation of Dish End &Fabrication 15-May-1... 04-Sep-12 A 120
CNME640 Erection &Painting of Tank 18-J ul-12 A 22-Nov-12 A 60
CNME650 Hydrotesting of Tank 04-Dec-1... 13-Dec-12 A 20
CLOSED DRAIN TANK-DYKE WALL ( LIGHT & FLUSHING OIL) CLOSED DRAIN TANK-DYKE WALL ( LIGHT & FLUSHING OIL) 06-J un-1... 08-Aug-12 A 122
CNCV540 Excavation 06-J un-1... 09-J ul-12 A 90
CNCV652 RCC &RELATED FACILITIES 26-J un-1... 08-Aug-12 A 120
CNCV731 PCC 06-J un-1... 16-J ul-12 A 90
DG SET ( TAG NO-52 & 23) DG SET ( TAG NO-52 & 23) 02-Aug-1... 05-Dec-12 A 552
CNEL190 Installation of DG set outside of substation bldg 23-Apr-1... 12-Sep-12 A 31
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 41 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 42 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
DG Set Foundation DG Set Foundation 13-J an-1... 28-Feb-12 A 64
CNCV561 Earth Work 13-J an-1... 14-J an-12 A 9
CNCV562 Back filling &Compaction 17-Feb-1... 28-Feb-12 A 11
CNCV571 PCC 16-J an-1... 30-J an-12 A 11
CNCV581 RCC 24-J an-1... 15-Feb-12 A 21
Diesel Storage tanks-Foundation Diesel Storage tanks-Foundation 02-Aug-1... 13-Apr-12 A 167
CNCV122 Excavation 08-Aug-1... 12-Aug-11 A 20
CNCV124 Barbending 13-Aug-1... 18-Feb-12 A 30
CNCV126 Form Work 02-Aug-1... 23-Feb-12 A 45
CNCV128 RCC 19-Aug-1... 24-Feb-12 A 60
CNCV130 Backfilling &Compaction 02-Apr-1... 13-Apr-12 A 20
DIESEL STORAGE TANK-Fabrication DIESEL STORAGE TANK-Fabrication 15-Nov-1... 05-Dec-12 A 356
CNEQ170 Installation of Diesel Unloading pump 26-May-1... 09-Aug-12 A 15
CNME670 Fabtication of Tank 15-Nov-1... 15-Feb-12 A 45
CNME680 Erection of Tank 22-May-1... 30-May-12 A 40
CNME690 Hydrotesting of Tank 13-Nov-1... 20-Nov-12 A 14
CNME700 Painting of Tank 22-Nov-1... 05-Dec-12 A 23
DIESEL STORAGE TANK-DYKE WALL DIESEL STORAGE TANK-DYKE WALL 21-Mar-1... 06-J ul-12 A 129
CNCV672 RCC &RELATED FACILITIES 21-May-1... 06-J ul-12 A 120
CNCV690 Excavation 21-Mar-1... 02-Apr-12 A 45
CNCV751 PCC 08-Apr-1... 22-May-12 A 90
FIRE PROTECTION SYSTEM (TAG NO-18,19,47 & 53) FIRE PROTECTION SYSTEM (TAG NO-18,19,47 & 53) 24-J an-1... 25-Aug-13 715
FW PUMP HOUSE FW PUMP HOUSE 09-Feb-1... 09-Aug-12 A 603
CNCV215 Substructure 09-Feb-1... 20-Mar-12 A 45
CNCV216 Superstructure 26-Mar-1... 14-J un-12 A 75
CNCV218 Flooring 03-J ul-12 A 09-Aug-12 A 35
FIRE STATION BUILDING ( Drill Yard) FIRE STATION BUILDING ( Drill Yard) 02-J an-1... 23-Aug-13 A 567
CNCV204 Flooring 10-J ul-12 A 28-J ul-12 A 30
CNCV212 Superstructure 07-Feb-1... 03-Apr-12 A 95
CNCV213 Masonary 21-Mar-1... 13-J un-12 A 60
CNCV221 Substructure 02-J an-1... 04-Feb-12 A 60
CNCV350 Installation of Split Air Conditioner 29-Aug-1... 04-Sep-12 A 10
CNCV425 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 08-Aug-1... 23-Aug-13 A 90
FIRE WATER TANK FOUNDATION - 2 NOS FIRE WATER TANK FOUNDATION - 2 NOS 24-J an-1... 05-J ul-11 A 304
CNCV050 Excavation 24-J an-1... 04-Feb-11 A 8
CNCV060 Barbending 31-J an-1... 31-Mar-11 A 12
CNCV070 Form Work 16-Mar-1... 13-Apr-11 A 15
CNCV080 RCC 19-Apr-1... 30-May-11 A 90
CNCV085 Backfilling &Compaction 15-J un-1... 05-J ul-11 A 30
FIRE WATER TANK FABRICATION - 2 NOS FIRE WATER TANK FABRICATION - 2 NOS 28-Oct-1... 28-Dec-12 A 423
CNME590 Fabtication of Tank 28-Oct-1... 06-J an-12 A 105
CNME600 Erection of Tank 04-Dec-1... 05-Mar-12 A 120
CNME610 Hydrotesting of Tank 20-Nov-1... 04-Dec-12 A 90
CNME620 Painting of Tank 11-Dec-1... 28-Dec-12 A 90
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 43 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 44 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
FIRE WATER PUMP HOUSE -SHED FIRE WATER PUMP HOUSE -SHED 15-Nov-1... 22-J an-13 A 403
CNCV433 Earth Work 15-Nov-1... 09-J an-12 A 15
CNCV443 PCC 09-Feb-1... 20-Mar-12 A 30
CNCV453 Barbending 09-Feb-1... 20-Mar-12 A 30
CNCV463 Form Work 09-Feb-1... 20-Mar-12 A 30
CNCV473 Structural Fab. Shot Blasting &Primer painting 15-Aug-1... 29-Nov-12 A 60
CNCV483 RCC 26-Mar-1... 16-May-12 A 40
CNCV493 Structural Erection &Final painting 27-Sep-1... 13-Nov-12 A 40
CNCV503 Metal Sheet Fixing &Side Cladding 05-Nov-1... 14-J an-13 A 80
CNCV513 Internal &External Painting 18-Dec-1... 22-J an-13 A 60
CNCV613 Installation of Monorail 16-Nov-1... 13-Dec-12 A 78
Impact Fire Fighting Changes- Construction Impact Fire Fighting Changes- Construction 15-Feb-1... 25-Aug-13 390
CIVIL CIVIL 15-Feb-1... 13-J ul-12 A 108
MDPP-FPSC-CC-0001 FDN. FOR FIRE WATER PUMP 24-Feb-1... 30-Apr-12 A 45
MDPP-FPSC-CC-0011 FDN. FOR J OCKEY PUMP 07-Mar-1... 30-Apr-12 A 45
MDPP-FPSC-CC-0021 FDN. FOR FOAM CONCENTRATE TANK 15-J un-1... 13-J ul-12 A 60
MDPP-FPSC-CC-0031 FDN. FOR FIRE WATER TANK (NEW TANK) 15-Feb-1... 16-Mar-12 A 60
MECHANICAL & PIPING MECHANICAL & PIPING 05-Mar-1... 09-Aug-13 348
FIRE WATER TANK FABRICATION FIRE WATER TANK FABRICATION 05-Mar-1... 12-Dec-12 A 312
MDPP-FPSC-CC-0051 CATHODIC PROTECTION FOR FIRE WATER TANK (NEW TANK) 08-May-1... 28-May-12 A 60
MDPP-FPSC-CMP-0051 FABRICATION OF PLATES 05-Mar-1... 15-May-12 A 50
MDPP-FPSC-CMP-0121 ALIGNMENT &ERECTION OF ROLLED SEGMENTS 16-Apr-1... 03-Oct-12 A 120
MDPP-FPSC-CMP-0131 NDT 27-Nov-1... 12-Dec-12 A 30
MDPP-FPSC-CMP-0141 PIPING CONNECTION 05-J un-1... 10-Oct-12 A 30
FIRE WATER PUMP FIRE WATER PUMP 07-Aug-1... 28-May-13 31
MDPP-FPSC-CMP-0021 ASSEMBLY,INSTALLATION OF FIRE WATER PUMP 07-Aug-1... 09-Oct-12 A 30
MDPP-FPSC-CMP-0061 PIPING CONNECTION 17-Oct-1... 24-May-13 10
MDPP-FPSC-CMP-0071 NDT &HYDROTESTING 12-Mar-1... 28-May-13 10
JOCKEY PUMP JOCKEY PUMP 03-Oct-1... 08-J un-13 63
MDPP-FPSC-CMP-0031 INSTALLATION OF J OCKEY PUMP 03-Oct-1... 23-Oct-12 A 12
MDPP-FPSC-CMP-0081 PIPING CONNECTION 04-Dec-1... 08-J un-13 25
FOAM CONCENTRATE TANK FOAM CONCENTRATE TANK 12-Sep-1... 09-Aug-13 35
MDPP-FPSC-CMP-0041 ERECTION AND ALLIGNMENT 12-Sep-1... 04-Oct-12 A 12
MDPP-FPSC-CMP-0101 PIPING CONNECTION 12-Nov-1... 09-Aug-13 20
ELECTRICAL ELECTRICAL 21-Aug-1... 13-J un-13 21
MDPP-FPSC-CE-0001 INSTALLATION &TERMINATION OF CABLES 21-Aug-1... 13-J un-13 30
INSTRUMENTATION INSTRUMENTATION 04-Oct-1... 25-Aug-13 65
MDPP-FPSC-CI-0001 INSTALLATION OF INSTRUMENTATION ITEMS 04-Oct-1... 25-Aug-13 90
SEWAGE TREATMENT SYSTEM (TAG NO-32) SEWAGE TREATMENT SYSTEM (TAG NO-32) 22-J an-1... 13-J un-13 339
Sewage Treatment Package (STP) Sewage Treatment Package (STP) 22-J an-1... 13-J un-13 339
CNCV272 Earth Work 22-J an-1... 26-Apr-12 A 30
CNCV282 PCC 28-J an-1... 29-Mar-12 A 35
CNCV302 Barbending 30-J an-1... 11-May-12 A 30
CNCV312 Form Work 30-J an-1... 15-May-12 A 30
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 45 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 46 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV322 RCC 20-Apr-1... 26-May-12 A 45
CNCV432 Back filling &Compaction 28-May-1... 29-J un-12 A 10
CNEQ150 Installation of Sewage water treatment plant 11-Sep-1... 13-J un-13 30
OILY WATE TREATMENT SYSTEM(TAG NO-11 & 71) OILY WATE TREATMENT SYSTEM(TAG NO-11 & 71) 13-J un-1... 03-J ul-13 304
Oily Water Package (OWP) Oily Water Package (OWP) 13-J un-1... 03-J ul-13 304
CNCV271 Earth Work 13-J un-1... 18-J ul-12 A 25
CNCV281 PCC 08-Aug-1... 12-Aug-12 A 12
CNCV301 Barbending 16-Aug-1... 04-Sep-12 A 45
CNCV311 Form Work 21-Aug-1... 10-Sep-12 A 30
CNCV321 RCC 14-Sep-1... 09-Oct-12 A 60
CNCV462 Back filling &Compaction 09-Oct-1... 18-Oct-12 A 10
CNEQ140 Installation of Oilywater treatment plant 11-Feb-1... 03-J ul-13 50
SUB STATION ( TAG NO-27) SUB STATION ( TAG NO-27) 15-Mar-1... 23-J ul-13 664
Main Substation Building Main Substation Building 15-Mar-1... 20-Mar-13 A 664
CNCV185 Substructure 15-Mar-1... 30-Oct-11 A 75
CNCV186 Superstructure 20-Oct-1... 30-Dec-11 A 110
CNCV187 Masonary 15-Feb-1... 10-May-12 A 60
CNCV188 Flooring 08-May-1... 17-Aug-12 A 60
CNCV190 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 29-Aug-1... 04-Nov-12 A 95
CNCV191 HVAC ducting work 12-Nov-1... 12-Dec-12 A 30
CNEL175 Installation of Switchgear &Panel 29-Nov-1... 10-J an-13 A 50
CNEL185 Installation of Substation Equipment incl. testing 10-J an-1... 12-Mar-13 A 90
CNEL200 Installation of Substation Automation System 10-J an-1... 20-Mar-13 A 90
Transformer Transformer 14-J an-1... 23-J ul-13 328
CNCV471 Earth Work 14-J an-1... 16-J an-12 A 8
CNCV481 PCC 18-J an-1... 18-J an-12 A 10
CNCV491 RCC 22-J an-1... 08-Feb-12 A 20
CNCV532 Back filling &Compaction 20-Feb-1... 28-Feb-12 A 10
CNEL177 Installation of Transformers 28-Nov-1... 23-J ul-13 70
NGR NGR 08-May-1... 05-Dec-12 A 55
CNCV371 Earth Work 08-May-1... 24-May-12 A 8
CNCV381 PCC 28-May-1... 06-J un-12 A 10
CNCV391 RCC 11-J un-1... 28-J un-12 A 20
CNCV522 Back filling &Compaction 11-J ul-12 A 30-J ul-12 A 10
CNEQ190 Installation of NGR 13-Nov-1... 05-Dec-12 A 45
Gas Turbine Gas Turbine 11-Nov-1... 25-J an-12 A 90
CNCV342 Excavation 11-Nov-1... 30-Nov-11 A 12
CNCV344 Foundation 20-Nov-1... 15-J an-12 A 60
INT160 Installation of Gas turbine Generator 21-J an-1... 25-J an-12 A 60
11-KV Kiosk 11-KV Kiosk 31-J ul-12 A 03-Oct-12 A 40
CNCV700 Excavation &Foundation 31-J ul-12 A 20-Aug-12 A 21
CNCV720 Installation of kiosk 29-Aug-1... 03-Oct-12 A 40
2 Pole Structure for incoming Grid Structure 2 Pole Structure for incoming Grid Structure 10-Sep-1... 06-Dec-12 A 54
CNCV730 Excavation &Foundation 10-Sep-1... 04-Oct-12 A 21
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 47 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 48 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV740 Erection of Structure 08-Nov-1... 06-Dec-12 A 60
CONTROL ROOM BUILDING (TAG NO-30) CONTROL ROOM BUILDING (TAG NO-30) 23-Nov-1... 21-May-13 486
Control Room Building Control Room Building 23-Nov-1... 21-May-13 486
CNCV150 Substructure 23-Nov-1... 15-Feb-12 A 75
CNCV151 Superstructure 08-Dec-1... 27-Apr-12 A 120
CNCV152 Masonary 14-Feb-1... 01-May-12 A 60
CNCV153 Flooring 03-May-1... 11-J ul-12 A 40
CNCV155 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 14-Mar-1... 12-J un-12 A 120
CNCV156 HVAC ducting work 18-J ul-12 A 10-Oct-12 A 75
CNEL140 Installation of UPS in Control Room 07-May-1... 21-May-13 25
BUILDING AND INFRASTRUCTURE BUILDING AND INFRASTRUCTURE 28-J an-1... 21-Nov-13 759
BUILDING WORKS BUILDING WORKS 28-J an-1... 21-Nov-13 739
Administration Building Administration Building 04-Apr-1... 10-Apr-13 A 706
CNCV141 Substructure 04-Apr-1... 05-J un-12 A 75
CNCV142 Superstructure 11-J un-1... 11-Sep-12 A 66
CNCV143 Masonary 24-Aug-1... 04-Oct-12 A 60
CNCV144 Flooring 04-Mar-1... 10-Apr-13 A 40
CNCV145 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 09-Oct-1... 13-Feb-13 A 120
CNCV146 HVAC ducting work 18-Dec-1... 09-Apr-13 A 40
Medical Centre Building Medical Centre Building 28-J an-1... 15-Oct-13 A 672
CNCV235 Substructure 28-J an-1... 15-Feb-12 A 75
CNCV236 Superstructure 01-Feb-1... 13-Apr-12 A 90
CNCV237 Masonary 15-Mar-1... 06-J un-12 A 60
CNCV238 Flooring 02-Oct-1... 01-Nov-12 A 30
CNCV240 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 17-May-1... 15-Oct-13 A 120
CNCV250 Installation of Split Air Conditioner 04-Apr-1... 24-Apr-13 A 10
Security Building Security Building 12-Oct-1... 08-May-13 A 567
CNCV195 Substructure 12-Oct-1... 10-J an-12 A 75
CNCV196 Superstructure 13-J an-1... 13-Mar-12 A 90
CNCV197 Masonary 05-Mar-1... 24-Apr-12 A 60
CNCV198 Flooring 14-Nov-1... 04-Dec-12 A 50
CNCV200 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 23-May-1... 12-Sep-12 A 120
CNCV201 HVAC ducting work 27-Mar-1... 08-May-13 A 40
Admin MCC Substation Admin MCC Substation 28-Nov-1... 13-J un-13 237
CNCV225 Substructure 28-Nov-1... 22-Feb-12 A 30
CNCV226 Superstructure 12-Mar-1... 16-May-12 A 70
CNCV227 Masonary 09-May-1... 13-J un-12 A 55
CNCV228 Flooring 07-Aug-1... 12-Dec-12 A 55
CNCV230 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 13-Aug-1... 12-Dec-12 A 120
CNCV231 HVAC ducting work 08-J an-1... 13-J un-13 30
Workshop / Warehouse Building / Laboratory Workshop / Warehouse Building / Laboratory 04-Feb-1... 23-May-13 609
CNCV165 Substructure 04-Feb-1... 02-J ul-12 A 75
CNCV166 Superstructure 15-Feb-1... 05-J un-12 A 90
CNCV167 Masonary 01-May-1... 13-J un-12 A 45
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 49 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 50 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV168 Flooring 03-Dec-1... 10-J an-13 A 60
CNCV170 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 26-Sep-1... 13-Feb-13 A 80
CNCV176 Fab. &Erection of Structural Steel Works 07-May-1... 15-Nov-12 A 120
CNCV180 Sheet Fixing 06-Nov-1... 28-Nov-12 A 90
CNCV320 Installation of Split Air Conditioner 15-May-13 23-May-13 10
CNEQ220 Erection of EOT crane 24-Oct-1... 10-J an-13 A 60
Canopy at Entrance -DELETED Canopy at Entrance -DELETED 15-Feb-1... 25-Nov-12 A 440
CNCV112 Substructure 15-Feb-1... 19-May-12 A 30
CNCV113 Superstructure 20-May-1... 08-J ul-12 A 50
CNCV116 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 10-May-1... 18-J ul-12 A 70
CNCV123 Sheet Fixing 26-Sep-1... 25-Nov-12 A 60
CNCV133 Fabrication &Erection of Structural Steel 09-J ul-12 A 26-Sep-12 A 90
Security Cabin /Sheds (2 Nos) Security Cabin /Sheds (2 Nos) 21-Sep-1... 05-Feb-13 A 159
CNCV243 Masonary 07-Feb-1... 06-J un-12 A 45
CNCV261 Substructure 21-Sep-1... 04-Nov-11 A 40
CNCV264 Flooring 29-Nov-1... 05-Feb-13 A 40
CNCV422 Superstructure 14-Dec-1... 25-Apr-12 A 45
CNCV455 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 03-J ul-12 A 02-Nov-12 A 75
SEHMS Sub Station SEHMS Sub Station 15-Apr-1... 08-J an-13 A 143
CNCV154 Flooring 11-Dec-1... 08-J an-13 A 30
CNCV160 Release of Front 15-Apr-12 A 0
CNCV161 Substructure 09-May-1... 04-J ul-12 A 45
CNCV162 Superstructure 19-J ul-12 A 03-Sep-12 A 55
CNCV163 Masonary 02-Aug-1... 20-Sep-12 A 45
CNCV205 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 12-Sep-1... 03-Dec-12 A 60
Hazardous Waste Area Shed Hazardous Waste Area Shed 08-J un-1... 18-J ul-13 267
CNCV164 Flooring 24-J an-1... 13-J un-13 30
CNCV169 Release of Front 08-J un-12 A 0
CNCV171 Substructure 31-J ul-12 A 15-Aug-12 A 14
CNCV182 Superstructure 31-Aug-1... 11-Oct-12 A 20
CNCV183 Masonary 19-Sep-1... 14-Nov-12 A 35
CNCV245 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 21-Nov-1... 18-J ul-13 45
Raw Water MCC Room Raw Water MCC Room 06-Mar-1... 08-J ul-13 321
CNCV194 Flooring 23-J an-1... 23-J un-13 40
CNCV202 Superstructure 24-Apr-1... 13-J un-12 A 70
CNCV203 Masonary 14-J un-1... 16-J ul-12 A 45
CNCV209 Release of Front 30-Mar-12 A 0
CNCV211 Substructure 06-Mar-1... 12-Apr-12 A 60
CNCV260 Installation of Split Air Conditioner 29-J un-13 08-J ul-13 10
CNCV265 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 13-Aug-1... 03-J ul-13 50
Chemical House Chemical House 15-J un-1... 22-Aug-13 290
CNCV214 Flooring 12-Dec-1... 05-Feb-13 A 30
CNCV222 Superstructure 30-J ul-12 A 30-Oct-12 A 75
CNCV223 Masonary 25-Sep-1... 18-Oct-12 A 45
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 51 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 52 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNCV241 Substructure 15-J un-1... 18-J ul-12 A 45
CNCV435 Finishing ( Elect. Inst.,Doors &Window fixing,Painting) 12-Dec-1... 22-Aug-13 100
Car parking Car parking 04-Sep-1... 21-Nov-13 A 83
CNCV570 Excavation 04-Sep-1... 18-Sep-12 A 30
CNCV580 PCC &Foundation 17-Sep-1... 21-Nov-13 A 45
CNCV590 Erection of Purlin 04-Dec-1... 09-J an-13 A 40
CNCV600 Erection of Roof Sheet 06-Feb-1... 16-Apr-13 A 60
HVAC System (AC Screw Chillers,Water Pumps Etc) HVAC System (AC Screw Chillers,Water Pumps Etc) 17-Feb-1... 02-Aug-13 433
CNCV384 Foundation 22-Feb-1... 28-Feb-12 A 45
CNCV394 Installation of Chillers, Pumps &Connention of Air handling Unit-AHU) 23-J ul-12 A 14-Nov-12 A 180
CNCV404 Installation of Ventilation System in Buildings 07-J an-1... 02-Aug-13 60
CNCV682 Excavation 17-Feb-1... 20-Feb-12 A 20
INFRASTRUCTURE WORKS INFRASTRUCTURE WORKS 07-Nov-1... 10-Nov-13 725
Civil Work- Foundation of Equipments Civil Work- Foundation of Equipments 28-Apr-1... 12-Dec-12 A 283
Pump's Foundation Pump's Foundation 02-Aug-1... 12-Dec-12 A 94
CNCV318Earth Work 08-Aug-1... 29-Aug-12 A 20
CNCV328PCC 02-Aug-1... 11-Oct-12 A 65
CNCV338Form Work 29-Aug-1... 17-Oct-12 A 50
CNCV348RCC 13-Sep-1... 01-Dec-12 A 80
CNCV492Back filling &Compaction 03-Dec-1... 12-Dec-12 A 10
SHEMS Transformer Foundation SHEMS Transformer Foundation 28-Apr-1... 27-Aug-12 A 162
CNCV501Earth Work 28-Apr-1... 07-May-12 A 8
CNCV511PCC 03-May-1... 25-J un-12 A 10
CNCV521RCC 25-May-1... 04-J ul-12 A 20
CNCV542Back filling &Compaction 07-Aug-1... 27-Aug-12 A 10
Vent Stack Vent Stack 14-May-1... 14-Nov-12 A 283
CNCV531Earth Work 14-May-1... 14-May-12 A 8
CNCV541PCC 15-May-1... 15-May-12 A 10
CNCV551RCC 30-May-1... 31-May-12 A 20
CNCV552Back filling &Compaction 15-J un-1... 29-J un-12 A 10
CNEQ270Installation of Vent Stack 16-Aug-1... 14-Nov-12 A 45
Foam Pump Skid Foundation Foam Pump Skid Foundation 15-J un-1... 21-Aug-12 A 164
CNCV572Back filling &Compaction 06-Aug-1... 21-Aug-12 A 10
CNCV591Earth Work 15-J un-1... 22-J un-12 A 8
CNCV601PCC 18-J un-1... 28-J un-12 A 10
CNCV611RCC 05-J ul-12 A 31-J ul-12 A 20
Foam Concentrate Tank Foundation Foam Concentrate Tank Foundation 15-J un-1... 16-Aug-12 A 35
CNCV582Back filling &Compaction 09-Aug-1... 16-Aug-12 A 10
CNCV621Earth Work 15-J un-1... 29-J un-12 A 15
CNCV631PCC 18-J un-1... 02-J ul-12 A 30
CNCV641RCC 03-J ul-12 A 13-J ul-12 A 30
Construction of Roads Construction of Roads 07-Nov-1... 12-Aug-13 125
CNCV252 WBM (63-40) 07-Nov-1... 15-May-13 90
CNCV254 WBM (50-20) 28-Nov-1... 12-Aug-13 100
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 53 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 54 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
Civil Works - Drains Civil Works - Drains 11-Sep-1... 10-Nov-13 665
CNCV290 Excavation 11-Sep-1... 15-May-13 140
CNCV291 PCC 18-Sep-1... 25-Sep-13 140
CNCV292 Bar Bending 24-Sep-1... 05-Oct-13 140
CNCV293 Form Work 27-Sep-1... 08-Aug-13 90
CNCV298 RCC 03-Oct-1... 09-Sep-13 120
CNCV303 Plastering 15-May-13 10-Nov-13 180
Construction of Cable Trenches around Building Construction of Cable Trenches around Building 18-J un-1... 26-Aug-13 115
CNCV300 Excavation 18-J un-1... 01-Aug-12 A 60
CNCV340 PCC 11-Sep-1... 15-May-13 60
CNCV341 Bar Bending 17-Sep-1... 28-J ul-13 75
CNCV351 Form Work 19-Sep-1... 07-Aug-13 70
CNCV361 RCC 10-Oct-1... 26-Aug-13 90
Civil works- Pipe Sleepers Civil works- Pipe Sleepers 07-Nov-1... 08-J un-13 70
Contruction of Pipe Sleepers ( Pre-Cast) Contruction of Pipe Sleepers ( Pre-Cast) 0
Contruction of Pipe Sleepers ( Cast-In-Citu) Contruction of Pipe Sleepers ( Cast-In-Citu) 07-Nov-1... 08-J un-13 70
CNCV560Excavation &Pedestal Casting 12-Nov-1... 15-May-13 100
CNCV710Release of Front 07-Nov-1... 08-J un-13 70
Civil works- Paving Civil works- Paving 22-Aug-1... 11-Sep-13 86
CNCV330 Civil works - Paving in Tank Farm area 22-Aug-1... 11-Sep-13 120
Construction of Watch Towers Installation Construction of Watch Towers Installation 10-Nov-1... 26-Oct-13 474
CNCV335 Excavation 03-J an-1... 25-J an-12 A 32
CNCV345 PCC 10-Nov-1... 14-Mar-12 A 32
CNCV355 RCC 01-Dec-1... 18-May-13 46
CNCV365 Backing Filling &Compaction 24-Feb-1... 14-Aug-13 A 48
CNCV395 Fabrication 21-Nov-1... 17-J un-13 152
CNCV405 Blasting &Painting 30-Nov-1... 20-J ul-13 93
CNCV415 Installation &Start up of Watch Towers (11 Nos.) 29-Feb-1... 30-Aug-13 110
CNCV465 Final Painting &Touch up 03-Sep-13 26-Oct-13 61
Pathways Pathways 02-Aug-1... 08-Nov-13 127
CNCV505 Construction of Pathways around Terminal 02-Aug-1... 08-Nov-13 200
COMMON AREAS COMMON AREAS 15-Feb-1... 06-J an-14 696
PIPING WORKS PIPING WORKS 06-J un-1... 06-J an-14 646
U/G PIPING U/G PIPING 04-Sep-1... 05-Nov-13 124
CNME501 Excavation &Lowering of Pipes 04-Sep-1... 02-Aug-13 90
CNME502 Piping Laying &Erection &Connection 07-Nov-1... 07-Oct-13 120
CNME512 NDT &Hydrotesting 20-Nov-1... 05-Nov-13 60
CS PIPING/AG PIPING CS PIPING/AG PIPING 05-Dec-1... 06-J an-14 646
CNME500 Pipe Fabrication 10-J ul-12 A 15-May-13 240
CNME510 Pipe Laying, Erection &Connections 05-Dec-1... 14-Dec-13 200
CNME515 NDT Works 12-Dec-1... 18-Dec-13 240
CNME520 Hydrotesting 10-Nov-1... 20-Dec-13 120
CNME530 Insulation 15-Sep-13 03-J an-14 110
CNME540 Painting 14-Aug-1... 30-Dec-13 220
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 55 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 56 of 58 Primavera Systems, Inc.
ActivityID ActivityName Start Finish Original
Duration
CNME550 Flushing and Handing over 12-Nov-13 06-J an-14 55
FIRE FIGHTING SYSTEM FIRE FIGHTING SYSTEM 06-J un-1... 15-Nov-13 550
CNME560 Fabrication of Fire water Networks 06-J un-1... 01-Oct-13 100
CNME570 Erection of Fire water Networks 14-Feb-1... 05-Nov-13 175
CNME580 Flushing 27-Sep-13 15-Nov-13 50
EQUIPMENT ERECTION EQUIPMENT ERECTION 15-May-13 10-Nov-13 128
CNEQ210 Installation of Fire alarm system 15-May-13 22-Aug-13 100
CNEQ261 Installation completion of HVAC 15-May-13 10-Nov-13 180
EQUIPMENT ERECTION OF FREE ISSUE MATERIAL EQUIPMENT ERECTION OF FREE ISSUE MATERIAL 29-Nov-13 29-Dec-13 20
INT170 Installation of Valves (above 24" size) 29-Nov-13 29-Dec-13 30
ELECTRICAL ELECTRICAL 02-Aug-1... 29-Dec-13 290
CNEL100 Laying and termination Cable (HT/LT) in Cable trench 24-Oct-1... 10-Sep-13 90
CNEL110 Laying and termination Cable (HT/LT) on Pipe Sleepers 02-Aug-1... 30-Nov-13 200
CNEL130 Installation of Cable trays and Cables in Buildings 29-Nov-1... 02-Aug-13 70
CNEL150 Installation of Area Lightning 17-Oct-1... 09-Dec-13 125
CNEL160 Installation of Earthing System 09-Aug-1... 10-Nov-13 180
CNEL170 Installation of Electrical Heat tracing system 02-Apr-1... 29-Dec-13 140
CNEL180 Installation of Electrical items (Switches,J B's,Cable Tray, DB ) 15-May-13 11-Sep-13 120
INSTRUMENTATION INSTRUMENTATION 15-Feb-1... 05-J an-14 696
CNINS100 Installation of Tank Farm Management system 13-May-1... 12-Nov-13 A 120
CNINS110 Cable laying and Termination 15-Feb-1... 23-Dec-13 A 150
CNINS120 Installation of Field Instrument ( Radar Guage, PRV, Level Guage) 20-Sep-1... 17-Nov-13 A 790
CNINS130 Installation of Cable Trays 15-Feb-1... 16-Sep-13 A 160
CNINS135 Installation of Valves (On-off, Control Valves) 23-Aug-1... 17-J ul-13 A 90
CNINS140 Instrumentation Works inside Control room 20-J ul-11 A 25-Nov-13 120
CNINS145 Installation of In-Line Instruments 15-May-13 10-Dec-13 210
CNINS150 Instrumentation Loop Testing 06-Nov-13 05-J an-14 60
CNINS155 Installation of Intrusion Detection System 15-May-13 22-Aug-13 100
STATUATORY APPROVALS STATUATORY APPROVALS 15-May-1... 26-Nov-13 2
CNSA100 CEA Approval (GEB Approval) for Electricity 16-May-1... 26-Nov-13 A 1
CNSA110 Final Lincence from PESO / CCOE 15-May-13 15-May-13 1
MECHANICAL COMPLETION MECHANICAL COMPLETION
07-Feb-1... 13-J an-14 174
COM110 Energisation of Substation 06-Mar-1... 28-J un-13 A 20
COM120 Rectification of Check list point 07-Feb-1... 11-J an-14 18
COM130 Mechanical Completion &Pre-Commissioning 16-Dec-13* 13-J an-14 28
COM140 No load run 15-May-13 13-J un-13 30
COM150 Equipment trial run 27-Aug-13 25-Sep-13 30
Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2011 2012
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary
Page 57 of 58 Primavera Systems, Inc.
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
2013 2014 2015 2016 2017
PROJECT SCHEDULE FOR AEGEAN REFINERY - TANKAGE
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary