Sie sind auf Seite 1von 11

The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents


Construction Engineering and Management CEM - 164



PROBABILITY DISTRIBUTION ANALYSIS OF ACTIVITY DURATION IN
INDIAN HIGHWAY PROJECTS

C.Arun
1
and Bh. Nagabhushana Rao
2


ABSTRACT : Traditionally, project scheduling is carried out using CPM or PERT model on a network.
CPM assumes that activity durations are deterministic while PERT assumes that they are probabilistic and
follow Beta distribution. In most practical cases, a number of random factors influence the activity
durations. Whether this randomness would lead to a Beta probability distribution for the activity duration is
debatable. The local regional conditions are expected to have an influence on this. Considering this, a
probability analysis has been performed for activity durations in several highway projects in India. Details
regarding the various activity durations have been collected from a large number of highway projects from
all over India. The data obtained from these sources was analyzed using standard statistical tools and the
results of the analysis discussed. It is observed that none of the activity durations followed the Beta
distribution as assumed in the PERT model. Rather most of the activities followed the log-log distribution.

This analysis is helpful for scheduling highway projects whose activity durations are highly random. The
probability distribution curves for activity durations, derived from this study, can be used for formulating a
simulation model whose simulated runs can realistically predict the completion time of the project and
associated confidence limits.

1. INTRODUCTION

A high level of uncertainty is associated with the activities in the highway construction projects in India.
The uncertainties in the project duration are mainly attributed due to the highly random characteristics like
unexpected variations in ground water table, delay in obtaining statutory clearances, political uncertainties,
etc. These uncertainties are observed when there is variation in the planned duration and the observed
duration for the activities. Hence the project personnel have to reschedule the activities in accordance with
the site parameters.

Due to the randomness associated with activity durations, a probability analysis is essential for the activity
duration. Studies conducted on process duration (S.M.Abourizk, D.W.Halpin 1992) indicated the
requirement of a flexible distribution function to model diversified construction activity durations. The
quality of probability distribution associated with the activity is essential for any simulation model and the
quality is essentially dependent on the sample size of the activity duration. The model put forward by
Christino Mio, et.al. (2000) provided method to fit probability distribution to activity durations recorded
from Truck payload monitoring system.

The scheduling of highway projects in India is highly dependent on the site characteristics. Hence, the
activity durations require rigorous stochastic analysis to determine the activity duration probability
function, which will stand as the backbone for any simulation model for construction projects.



1
Teaching/Research Associate,Structural Engineering Division,College of Engineering, Guindy,Anna University, Chennai-25 India
Email: arun_c77@hotmail.com

2
Chairman Faculty of Civil EngineeringAnna University, Chennai-25IndiaEmail: nags@annauniv.edu

The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 165

2. STOCHASTIC MODEL BUILDING

The probability model developed for the activity durations of highway projects is based on the actual
duration of the activities on the project site. The data regarding the activity durations has been collected
from one hundred and twenty highway construction sites located geographically all over India. The data
collected from all over India represents wide variations in geographic, topographic and climatic conditions,
which are likely to create hindrance to construction project. This also provides the various scenarios at the
construction site viz., the unexpected variations in the soil conditions, ground water table, labor unrest, etc
that are likely to influence the activity durations. From the data, collected eleven major activities
associated with highway construction have been identified for detailed study. These cleaning and grubbing,
laying of sub grade, laying of capping layers, laying of sub base, laying of road base, laying of base course,
laying of wearing course, construction of foundation for cross drainage, construction of substructure for
cross drainage, construction of super structure for cross drainage and construction of drainage works. The
duration of these activities in a project varies with the length of the highway to be constructed at any
instant. In order to have the uniform comparison amongst various projects, the activity durations are
reduced to duration of unit length. This is based on the assumption that the site factors that affect the
activity duration will influence the activity throughout the length.
The adequacy of the sample size is tested using Students T test given by.
where M is the median of the sample
2
25 . 1
3 . 0

=
t
M
n
n is the sample size
t is the Students t value for 90% confidence limit and corresponding degree of freedom
and is the standard deviation of the sample.
The sample size required at 90 percent confidence level has been determined. It was found from the
analysis that the size of the data obtained for each activity at this confidence level is far higher than the
required sample size. The minimum sample size required and the sizes of the data collected for each
activity are given in Table1.

The data collected is analyzed for fitting the probability distribution using Best Fit software from Pallisade
Inc. This software fits the data for each activity with sixteen standard probability distribution functions and
tests for Goodness of Fit (GOF) using Kolmogrov-Smirnov (K-S), Anderson Darling (A-D), Chi-square
(
2
) criteria. This software will fit the probability distribution function and arrives at the parameters for the
distribution obtained by Moment matching method.

The sixteen standard distribution functions then formulated for each of the activity under each GOF criteria
are ranked based on the root mean square error (RMSE) between the probability obtained from the fitted
distribution function and the actual probability value.

=
2
) (
1
. . .
i i
y fx
n
E S M R


Where f(x
i
) is the probability of x
i
from the probability function
y
i
is the probability of x
i
from the observed data
n is the number of samples

3. STOCHASTIC ANALYSIS

All the major activities involved in the highway construction project are analyzed using Best Fit by varying
the sample size. The sample size is varied randomly from thirty to the maximum available with increments
of ten samples taken uniformly throughout the population. The study was carried out for A-D test and K-S
The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 166

test and the variation in the probability distribution function was studied. From this analysis it was found
that the samples showed variation in the distribution function when the sample size was less than forty in
the K-S test and all the activities except one followed log-log distribution when the sample size was more
than forty. When the same activities were analyzed, using A-D criteria five of them converged to Log
logistic distribution while two converged to Inverse Gauss two converged to Exponential and one followed
Extreme value distribution.
2
test is not taken into account due to the inherent disadvantage of this test that
the distribution function is likely to vary with the size and number of bins used in the analysis. Table 2
shows the variation and the convergence of the probability distribution function for various activities with
varying sample size employing both A-D and K-S tests.

It is observed from Table 2 that none of the activity durations is following the Beta distribution irrespective
4. DISCUSSION AND CONCLUSION
he stochastic analysis of the data collected from one hundred and twenty different highway construction
he probability distribution for most of the activities for the highway construction project is following the
he actual probability distribution for the activities can be incorporated in simulation model of project
. REFERENCES
hua D.K.H., Li G.M. (2002) RISim: Resource interacted simulation modeling in construction, ASCE
Der
a probability distribution function for
Jona d,
Lero abilistic cost and schedule
Pho ecission
Sim duration data, ASCE

of the sample size is varied. Two examples of the final distribution curves and the frequency histograms for
various activities obtained with A-D and K-S tests are given in Figures 1 and 2. It can be seen from these
figures that the probability distribution in all the cases is skewed towards the left, the skewness and kurtosis
of the final distribution for each activity is given in Table 3.


T
sites shows that the duration of most of the major activities associated with highway construction follows
Log-logistic distribution. Further this analysis shows that Beta distribution is not followed in any case even
when the sample size is increased five fold than the minimum required. This probability can be attributed to
the highly random nature of reasons for time and cost overruns in developing countries. Thus in such cases,
network analysis with Beta distribution of PERT is debatable. It is essential that network analysis should
follow the actual distribution function for activity duration.

T
log logistic distribution model. The skewness and kurtosis for this distribution is tending towards positive
infinity that clearly shows that the distributions are biased to the left. This implies that for the activity the
most likely duration is very close to the optimistic duration as compared to pessimistic duration.

T
network. This will result in more realistic estimate of the project duration and the associated confidence
level. This will also enable the project personnel to provide an intermediate schedule for the project
depending on the ambient and temporal site conditions and provide necessary changes in the whole project
schedule.

5

C
journal of Construction Engineering and Management (pp195-202)
k T Beeston (1983) Statistical methods for building price data
Javier Fente, Cliff Schexnayder, Kraig Knutson (2000) Defining
construction simulation, ASCE journal of Construction Engineering and Management (pp 234- 241)
than Jingsheng Shi (1999) Activity based construction (ABC) modelling and simulation metho
ASCE journal of Construction Engineering and Management (pp 354-360)
y. J Isidore, W.Edward Back (2002) Multiple simulation analysis for prob
integration, ASCE journal of Construction Engineering and Management (pp 211-219)
tios G Ioannou, Julio C Matinez (1998) Project scheduling using state based probabilistic d
network, Proceedings of the 1998 Winter simulation conference(pp 1287-1295)
aan M Aburizk, Daniel W Halpin(1992) Statistical properties of construction
journal of Construction Engineering and Management (pp 525-544)
The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 167


Table 1 Sample size required and available

Activity
Sample size required
(90% confidence level)
Available
sample
size
Clearing 8 94
Subgrade 4 94
Capping layer 4 74
Sub base 12 80
Road base 12 94
Base Course 12 94
Wearing Course 40 94
C.D. Foundation 4 74
C.D.Substructure 4 74
C.D.Super structure 3 74
Drainage 4 90

Table 2 Convergence of Distribution Function for Activities

A.D.Test K.S.Test
Activity
< 40 40 50 > 50 < 40 40 50 > 50
Clearing Lognormal Lognormal Exponential Lognormal Loglog Exponential
Sub grade Lognormal Loglog Loglog Inv. gauss Loglog Loglog
Capping layer Inv. gauss Lognormal Lognormal Inv. gauss Lognormal Lognormal
Sub base course. Inv. gauss Inv. gauss Inv. Gauss Loglog Loglog Loglog
Road Base Exp. Loglog Loglog Exp. Loglog Loglog
Base course Pearson Loglog Loglog Pearson Loglog Loglog
Wearing Course Exp. Pearson Inv. Gauss Loglog Loglog Loglog
C.D. Foundation Loglog Loglog Loglog Exp. Loglog Loglog
C.D.Substructure Loglog Loglog Lognormal Inv. gauss Pearson Loglog
C.D.Super structure Ext. value Ext.value Ext.value Pearson Pearson Loglog
Drainage Exp. Loglog Loglog Exp. Loglog Loglog
Table 3. Probability distribution for activities with skewness and kurtosis
Activity Probabaility Distribution Skewness Kurtosis
Clearing y=Exp(8.7740) Shift= +0.90391 1.1395 5.4
Subgrade y= Loglog(-0.25766,14.356,1.7980) +Infinity +Infinity
Capping Layer y=Lognormal2(1.6585,11.46)shift=+0.73546 9.389 328.8852
Sub base y=loglog(3.878,7.3434,1.7212) +Infinity +Infinity
Road Base y=Loglog(0.037730,13.425,1.6813) +Infinity +Infinity
Base Course y=Loglog(1.1471,11.283,1.6399) +Infinity +Infinity
Wearing Course y=loglog(0.42242,10.653,1.5038) +Infinity +Infinity
C.D. Foundation y=Loglog(0.30439,11.616,1.8924) +Infinity +Infinity
C.D.Substructure y=Loglog(0.30439,11.616,1.8924) +Infinity +Infinity
C.D.Super structure y=loglog(-1.0579,12.290,2.6968) +Infinity +Infinity
Drainage y=Loglog(0.31680,10.658,2.0930) +Infinity +Infinity
The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 168


Figure 1. Probability Distribution for the Activity Clearing

Figure 2. Probability Distribution for the Activity Sub Grade
The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 169


Figure 3. Probability Distribution for the Activity Capping Layer




Figure 4. Probability Distribution for the Activity Sub Base Course

The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 170


Figure 5. Probability Distribution for the Activity Road Base



Figure 6. Probability Distribution for the Activity Base Course
The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 171


Figure 7. Probability Distribution for the Activity Wearing Course


Figure 8. Probability Distribution for the Activity -CD-Foundation




The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 172


Figure 9. Probability Distribution for the Activity CD-Substructure




Figure 10. Probability Distribution for the Activity CD-Superstructure

The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 173


Figure 11. Probability Distribution for the Activity Drainage


APPENDIX
Distributions Probability Distribution Function


Erlang
( )

x
e
x
m
m f

=
1
! 1
1
) , (
m>0 (integer shape parameter)
>0(continuous scale parameter)


Exp f(x)=

x
e

=mean


Ext. Value
f(x)=
) (
1
z
e z
e b

+

b
a x
z

=
a=Continuous location parameter
b=Continuous shape parameter



Gamma


x
e
x
f

=
1
) (
.
1
) , (
>0 (scale parameter)
The Ninth East Asia-Pacific Conference on Structural Engineering and Construction

Main Menu Table of Contents
Construction Engineering and Management CEM - 174

>0 (shape parameter)

Inv. Gauss

=
x
x
e
x
x f
2
2
2
) (
3
2

) ( , >0


Loglog
2
) 1 (
1
) (

t
xt
x f
+


=
x
t
= Continuous shape parameter
= Continuous scale parameter
= Continuous location parameter

LogNormal
2

) ln(
2
1
2
1
) (

=
x
e
x
x f
, are continuous parameters
>0




Pearson
1

.
) (
.
1
) (
+

x
x
e
x
x f
>0 (continuous shape parameter)
>0 (continuous scale parameter)



Weibull

=

1
.
) , (
x
e
x
f
>0 (scale parameter)
>0 (shape parameter)

Das könnte Ihnen auch gefallen