Sie sind auf Seite 1von 6

Case Study 3:

Aylesbury Pressings
Case Studies,
Bsc Hons Quality Management and
Technology
Authors :Roddy McGuinn (s00093607) and Martin Toher(s00093928 )
12/5/2009
Using the Lean Principles as a framework, what improvements do you
consider that the management team at Aylesbury should be giving priority to,
and why?

Introduction
Aylesbury pressings is a manufacturing company that produces automotive metal
components that supplies the automobile industry. The business displays
characteristics of a high volume high variety operation as its’ products are
considered runners or repeaters with batch ranges of between 150-500 parts and a
variety of 80 main products many of which have several versions. This complex
environment posses some difficult challenges for the Aylesbury pressings operation.
Many of the difficulties faced by Aylesbury pressings can be alleviated by using
some techniques associated with lean manufacturing.
Suggested improvements
1/ Quality: The Lean philosophy identifies seven different forms of waste (muda),
these are over production, waiting time, transport, process, inventory, motion and
defectives. One obvious source of waste in the operation is in the production of
defectives in the pressing stage of operations. Many of the dies used are old and
difficult to adjust which results in defective materials being produced. These dies
should be replaced as a matter of urgency and should be the first priority of the
management team. This is so because if the output of this early stage of production
is of a high quality and the process itself controlled, it will make all subsequent
stages of production much easier to improve as the supply of materials to these
stages will be more predictable and of higher quality. Quality, right first time does not
seem to be a major priority for Aylesbury pressings as only 4 of the 280 staff are
actually employed doing quality work.
2/ Involvement of all staff: The level of suggestions for improvements coming from
staff is very low and few if any visual indictors of quality are being used. This is a
strong indicator that all staff are not being encouraged to participate in process
improvement. One more subtle area of concern is with the use of poka yoke (Error
proofing) systems. These were implemented by an outside consultant but one of the
key ideas behind pokayoke is that the operations staff themselves are involved in
coming up with error proofing ideas rather than having ideas imposed without the
involvement of all staff. This lack of staff involvement is also reflected the manner in
which the Standard operating procedures (SOPs) were completed. The SOPs used
within the operation were completed by the Kaizen promotion office but little
consideration was given to the expertise of operations staff in this process. A recent
audit showed that the SOPs were in many cases not being followed. This may be
expected if the SOPs are impractical and did not consider the capability of operators
or machinery. It is therefore very important that all staff be involved in the
improvement process this is one of the key themes in the lean manufacturing
philosophy. This can be viewed as adopting basic working practices which will
operationalise the involvement of all staff.

2/ Reduction of set up and Change over times: A lot of time is wasted in Aylesbury
pressings in setting up a run or completing change over activities. Excess time spent
completing these tasks adds to the overall cost of the product and does not add
value. Some of the activities and times associated with these are as follows:
• Blanking process Change over time 15 minutes.
• Pressing process sampling time of 10 minutes and a 1% scrap rate
associated with each change over cycle.
• The case study also states that some Pressing changeovers take between 30
and 60 minutes. Benchmarking has demonstrated that this time is excessive
with little value being added.
• Painting process takes around 90 minutes to complete. In that time only 3
minutes is actually spent painting, the remainder of the time is spent setting
up for a run or removing painted parts once a run is complete.
As the operation currently stands much of the work completed for set up and change
over activities are probably being completed while the production machinery is idle.
This is referred to as internal work in the SMED approach. Time spent in this manner
leaves less value added time for production and is a form of waste called waiting
time. These inefficacies can be addressed by using a single minute exchange of die
(SMED) approach. Where possible tasks for set up and change over should be
completed while the production machinery is still running, this is called external work.
Tasks which could be completed in this manner include pre set tools instead of
having to set tools when the process is stopped, the use of standard fixtures and
devices to speed changeover times. This can also be aided by having the materials
within easy reach when required which is linked to layout.
3/ Total Productive Maintenance: Some of the machinery in the pressing stage of the
operation is running at 80% of their rated efficiency. Maintenance staff have currently
a downtime target of less than 5%. The introduction of total productive maintenance
will involve every staff member in finding ways to improve the process. Many routine
maintenance tasks can be completed by the operators themselves with the more
complex tasks being completed by specialist engineers. These more specialised
staff will then have more time to dedicate to the overall improvement of the
maintenance process.
4/ Inventory Reduction: There are considerable levels of inventory being held within
the operation, after pressing, production materials are moved to a warehouse and
stored, buffer inventories are held before Assembly stage and each cell within the
assembly process has its own inventory. Inventory is kept at every intermediate
stage and the dispatch process holds additional inventory ranging from 2 hours to 2
weeks. The lean philosophy regards the holding of inventory as a form of waste. This
is true because inventory ties up capital, there is a cost to insure, maintain and store
inventory and there is always the risk of inventory becoming damaged or becoming
obsolete. Inventory may be considered as a blanket of obscurity that masks
problems that exist within the operation as a whole. Many of the problems with
Aylesbury pressings are being compensated for by holding excess inventory at every
stage which will ultimately fail in the long term. These problems include poor die
quality, excessively long change over times of between 30 and 60 minutes, Standard
operating procedures not being followed (Perhaps because they were poorly
written), insufficient flexibility and poor plant layout. The inventory levels within the
operation should be gradually reduced overtime, this will have the effect of exposing
the problems that exist and a concerted effort can be undertaken to permanently
resolve these issues. This will initially slow production but this will be more than
compensated for in the long run by having a much more efficient operation.
5/ Levelled scheduling ,Mixed Modelling and Synchronisation: These ideas are best
applied to operations whose products may be described as runners and/or
repeaters, these are products which are produced daily or at very frequent intervals.
As such the Aylesbury pressings operation is ideally suited to levelled scheduling,
synchronisation and mixed modelling methodologies. The idea behind levelled
scheduling is to spread the production of a batch over a wider period of time. For
example if a batch size of 300 units was required for part A , then a batch size of 100
could be run on day 1, a second batch size of 100 on day 2 and a third batch size of
100 run on day 3. With smaller batch sizes inventory can be reduced and the
throughput time for each smaller batch will also be reduced. This can have the
added benefit of making the production schedule much more stable as more of the
same products are produced each day and the in turn makes the process less
variable. With reduced variability the process is itself simplified, this simplification
combined with repetition and experience results in staff which are much more
competent at daily tasks which in turn improves quality and reduces waste and
costs.
6/ Value Stream Mapping: At the most fundamental level any process in an
organisation can be regarded as either adding value or adding cost. End to end
system mapping (Value steam mapping) would allow Aylesbury pressings to quantify
how much time of a products throughput time is actually spent adding value and how
much is adding cost. The throughput time for some products is likely to be very high
with very little time spent adding value as some materials are held between 1 day
and 4 months between the pressing and assembly operations. This is one of the 7
forms of waste which is waiting time. Value stream mapping takes a holistic look at
the entire operation, firstly a process is selected for analysis, then the path of
material through the entire operation is physically mapped the flow of information
that allows that drives the process is also recorded. This stage is called the current
stage map and describes the operation in its present state. Using this map a more
detailed diagnosis of the problems within the operation will occur and new
opportunities for process optimisation can be identified. A new ideal state map of the
process is then completed and improvements implemented.
7/ Operation layout: The operation layout in its present state may not the most
efficient. The press shop and blanking cell are located in separate areas away from
assembly facilities. This was originally designed in this manner as these there is a lot
of noise associated with these activities. This should be reviewed to see if all
processes can be arranged closer together. It is not clear that noise is an entirely
justified reason for the present layout. The process of assembly itself must generate
considerable noise as it involves drilling and punching steps. Excess noise may be
addressed through the use of personnel protective equipment and insulation
materials. As the different processes are presently arranged there is unnecessary
motion in the manufacturing process which is a form waste and there is the addition
risk of damage to inventory when the unnecessary motion occurs. Another area
which could be improved is within the pressing process, some types manufacture
involves the manual movement between different presses, the possibility of
automating this process should be considered. A key technique in the lean
philosophy is simplification, where possible processes should be simplified and
made more efficient. As the operation is designed at present there is an assembly
stage followed by a painting stage and then a final assembly stage. The possibility of
painting first and then having a single assembly stage should be explored, however
the quality of the product not be compromised in pursuing this change. Any damage
to painted parts would render this change counterproductive.
Discussion
The Aylesbury pressings operation is facing a difficult situation, not only has it a high
volume high variety operation but many of its customers are trying to micro manage
the internal processes which has resulted a highly complex environment with many
different strategies being pursued. Some efforts at improvement have been made
and have been partially successful, for example there has been a reduction in the
defect rate from 40,000 parts per million to 1600 parts per million, reduction in the
number of samples being taken through the use of statistical process control and the
supplier development programme. Another encouraging development is the use of
Kaizen events, these did involve a range of staff and resulted initially at least in a
32% reduction in inventory levels and a reduction in lead time.
However other efforts at improvement have been much less successful. The
completion of Standard operating procedures has had limited success, and
Aylesbury does seem to have difficulty in sustaining many of the quality improvement
projects introduced. This is evidenced by the fact that many of the gains brought
about by the Kaizen events have begun to be lost. Another example is with the 5 S
programme. The 5 S programme is outlined as follows:
1. Sort (Seiri) remove what is not required
2. Straighten (Seiton) Arrange things so that they can be accessed easily.
3. Shine (Seiso) Keep areas neat and clean
4. Standardise (Seiketsu) Perpetual neatness.
5. And lastly Sustain (Shitsuke) maintaining standards.
Initially this was quite successful but there has been little emphasise placed on the
sustain part of the 5 S programme. The operation has opted to use “Rounds” of 5 S
programmes which means in practice that things improve for a while but will
ultimately relapse in to older less optimal patterns. The only way this can be
corrected is though on ongoing commitment to improve quality involving everyone in
the operation with clearly communicated goals and objectives which are measured
on an ongoing basis and not just at intermittent intervals. This will help in sustaining
quality improvements.
The operation is currently using an MRP II system to plan the production
requirements of the plant which is excellent at planning but relatively poor at
controlling the operation. MRP type systems are ideally suited to push type
production systems with fixed lead times and a master production schedule. Just in
time production is driven by actual orders from customers and this a pull type system
where materials are pulled through each stage of production from a stage further
along the process in response to a customer order. It uses simple controls like
kanbans which the operation is using to some extent already. Ideally it would be best
to use the MRP II system to complete planning and use just in time techniques for
internal control.
Conclusion
The key goal for Aylesbury pressings is to reduce cost. This can be best achieved by
moving to a pull type production system with low inventory. In order to facilitate this
change product quality must be improved, efficiency needs to be improved by
reducing set up times and adopting a Total productive maintenance system. Every
staff member must be included and valued in this process and management must
demonstrate an unwavering commitment towards sustaining improvement.

Das könnte Ihnen auch gefallen