Publication / Presented: Originally posted to Society of Petroleum Engineers website (www.spe.org) Date: January 13, 2008 FLOATOVER INSTALLATIONS ON THE RISE
- 1 - 2008 Society of Petroleum Engineers. All Rights Reserved.
Floatover installations on the rise By Ted Moon, PhD, J PT Online Technology Editor Posted to www.spe.org on 13 J anuary 2008 An offshore installation method that is nearly 30 years old is generating renewed interest from many operators who are challenged with designing heavy-lift crane installations. According to global engineering company KBR, the floatover installation method is experiencing a steady surge in new contracts, particularly for platforms in remote locations with very heavy topsides. KBR is one of the pioneers of the floatover installation method, initiating research as far back as 1977 for the North Sea market. The company envisioned developing floatovers as a cheaper and more flexible alternative to heavy-lift installations. In general, a platform's installation option is ultimately dictated by its end design. But in water depths ranging from 10 to 200 m (the ideal range for a floatover installation), there are distinct advantages to doing a floatover when you can, according to Lindsay Woodhead, vice president- Offshore Operations for KBR. "While the big lift tends to be the norm, the floatover is done when you can't get the big lift vessels, or when the big lift will be prohibitively expensive," Woodhead said. "Floatover installs are quite convenient to perform in areas where it is difficult to get the heavy-lift crane vessels. You also avoid the problems of high day rates and, given the high demand for cranes, the very narrow installation window." If a deck is not completely finished and operational on the date that a heavy-lift vessel is scheduled to lift it offshore, then the deck may have to be towed out unfinished. The operator will be forced to carry over its onshore work to the offshore location, after the crane has delivered the deck. This adds time, logistics challenges, and costs to the installation. North Sea installations differed from original plan "Back in the late 1970s, we initially referred to floatover technologies as a HIDECK concept," said Woodhead. "Our original concept was to build the complete deck structures, including all facilities, such that they could be jacked up, skidded onto a transportation barge, floated over a preinstalled offshore jacket, and be totally operational very quickly. Our scope was always to design the platforms and develop the mating concept between the deck and the jacket. Then, we'd hand the installation off to a specialist installation contractor." Despite its potential, KBR's vision for floatover technologies in the North Sea did not go according to plan. It took KBR nearly 6 years to get from initial concept to first installation, and the first two projects slated for the North Sea deviated slightly from the original concept. "The first HIDECK was installed in 1983 for the Maureen platform. Instead of sliding the deck into position between the legs of a preinstalled jacket, the floating jacket was used to lift the deck from the transportation barge. Then the deck and jacket were installed together at the offshore location," said Woodhead.
- 2 - 2008 Society of Petroleum Engineers. All Rights Reserved.
The second installation was performed for the Hutton tension-leg platform (TLP), and it took a similar approach to Maureen. "This was the first-ever TLP, and we designed an 18,000-ton deck for it. The deck was fully operational before it left the construction yard. You could even cook in the accommodation module before it left land," Woodhead said. "Again, this deck was picked up off a barge by the floating hull." These two platforms have since been decommissioned, but their successful installation, though slightly different from the original plan, proved parts of the floatover concept. However, they were not followed by further projects in the North Sea, and Woodhead pointed to two major reasons for this. "Around this time, the early 1980s, the very big crane vessels started receiving a great deal of attention from the operators, because the vessels were able to lift such large decks. Plus, the metocean criteria in the North Sea called for pretty heavy wave events and harsh operating climates. There was a reluctance to risk a floatover installation. To this day, no one has ever done a true floatover onto a previously installed platform in the North Sea." This is not to say that the initial work in the North Sea did not lead to more floatover work for KBR. Greater interest in floatover installations came from operators in other parts of the world, most notably in the Far East. "It really took until the mid 90s before floatover started getting serious attention, but it took off with a flourish after that," said Woodhead. True floatovers get offshore Asia debut The flourish began with the back-to-back installations of the M1 and M3 platforms for Shell, offshore Malaysia, in 1995. These projects, which were the first true floatover installations KBR designed, called for each deck to be completed on land and placed onto a barge at the same elevation they would be installed offshore. "Neither of these platforms was terribly high, which was good, because the higher you get, the less stable the barge is during transportation," Woodhead confirmed. The decks, weighing in at 6,045 and 7,550 tons respectively, were then towed out to their jackets, which were already fixed to the seafloor, and floated between the jacket legs until the mating points between the deck and the jacket were aligned. This process of moving the deck into position over the jacket is a painstakingly slow one, often taking hours to accomplish. The actual floatover moves so slowly because there is very little margin for error. The spacing between the deck and the jacket legs is kept intentionally as small as possible, typically on the order of 0.5 m on each side, to avoid striking the deck against the legs. "In addition, the decks have a rather large overhang on the barge and they are not on their final support point, so moving slowly minimizes wave-induced rocking," Woodhead said.
- 3 - 2008 Society of Petroleum Engineers. All Rights Reserved.
As the deck moves over the jacket, it is aligned with special catch points on the jacket where the pieces will mate. There is a slight clearance between the deck and the jacket at these mating points. Once the deck and jacket's mating points are aligned, the transportation barge is ballasted with water, which lowers the deck onto the jacket. To complete the deck/jacket link, mating joints are designed to transfer the final load rapidly from the barge to the jacket and create a gap between deck and the transportation steel. The deck weight is quickly transferred to the jacket. "This final step may take less than a minute to complete, but it takes hours to get to that minute," Woodhead said. With M1 and M3 successfully behind them, KBR quickly moved onto the Wandoo project, offshore Australia, and Shell's Malampaya project in the South China Sea. Both were concrete gravity bases, as opposed to steel jackets. The Wandoo deck's floatover weight was comparable to those of M1 and M3, but Malampaya was nearly double the weight, at 11,600 tons. KBR's initial floatover successes in Asia Pacific opened the door for this installation method in other regions, most notably the Caspian. "We have recently completed the design of the ACG complex for AIOC, which consists of seven platforms," said Woodhead. Six of the seven platforms have large floatover decks installed over fixed jackets. In 1999, KBR initiated a design program for this project wherein the company would use the same barge, Saipem's stb-1, to install each platform. The barge would make separate trips to each offshore site to deliver first the jacket and then the deck. These installations occurred year after year between 2004 and 2007 until they were all completed. They also used the same spacer frame between the deck and the barge. "Each platform's deck and jacket weighed between 13,000 and 15,000 tons apiece, which was among the largest platforms we had designed to be installed via floatover," said Woodhead. KBR balances floatover demand with common industry challenges While KBR is enjoying a steady stream of floatover installation projects over the next several years, the company is not immune to the challenges facing other segments of the industry. "I would say shortage of manpower and high global demand for steel and equipment are the major delay drivers for us," said Woodhead. "I think in the next few years, it could go either way as to whether this demand will increase or decrease. It is really tied to the economies of certain countries, like China and India," he continued. "In addition, the technologies we have developed for offshore are now being used in other areas such as liquefied natural gas (LNG). Demand for LNG projects is driving much of this competition for resources. If the big LNG projects ramp up, particularly in Australia, that will really impact things. Modularization of LNG plants is also affecting the capacity of fabricators in the Far East. " For now, however, floatover demand does not appear to be waning, and larger installation projects are on the horizon.
- 4 - 2008 Society of Petroleum Engineers. All Rights Reserved.
Bigger, heavier decks on the horizon According to Woodhead, the architecture of a floatover has not changed much from the original design nearly 30 years ago. "The steelwork is pretty much the same, as are the jackets. The only thing that has really changed is the size of the platforms that you are building and floating over." One of the larger floatover installations is the Arthit platform (17,000 tons), installed 24 December 2007 in the Gulf of Thailand. KBR plans to follow Arthit with the CPOC project in the South China Sea in 2009. The CPOC platform is still in its design phase, with fabrication set to start in 2008. It will have a planned floatover weight of nearly 18,000 tons. Both Arthit and CPOC will be installed in what are considered benign climates (minimal impact from wind and waves) and at water depths of 60 to 80 m. In terms of weight and weather, Woodhead envisions Woodside's North Rankin 2 platform as being the next big floatover challenge. "The North Rankin will be the biggest floatover deck we've have designed, with a weight of 23,000 tons. In addition, its height will be an interesting challenge for us. The elevation of the underside of the deck will be 28 to 29 m (approximately 90 ft) above sea level once installed. That's about the equivalent of a 9-story building."
The North Rankin 2 is being designed by the EOS joint venture of KBR and WorleyParsons. EOS will have to factor in this height during the design phase, particularly in terms of how to most efficiently tow the deck offshore. "A major consideration has to be the motions of the barge during towing. Weight control and center of gravity are absolutely critical," Woodhead confirmed. The North Rankin 2 deck will be built in the next 3 to 4 years in the Far East, where a busy cyclone season could narrow the towing window. "If we build in Korea, we'll be transporting from the northern hemisphere (winter season) to the southern hemisphere (summer season)," said Woodhead. "Ideally we'll aim to get it in just before the cyclone season, or find a gap between cyclone events, where you tend to get the calmest weather." To learn more about floatover installation options and KBR's upcoming installation projects, contact KBR at offshore@kbr.com.