Sie sind auf Seite 1von 27

K:\Current Development Standards\2011 PW Dev. Standards\SECTION 2 Sewer\DETAILS COVER AND TABLE CONTENTS.

doc
SECTION 2
SEWER DETAILS
K:\Current Development Standards\2011 PW Dev. Standards\SECTION 2 Sewer\DETAILS COVER AND TABLE CONTENTS.doc
STANDARD DETAILS:
SEWER MAIN INSTALLATION............................................................................ ATTACHMENT
SEWER TANK ABANDONMENT POLICY........................................................... ATTACHMENT
SANITARY SEWER TRENCH.............................................................................................SS-10
48 DIAMETER PRECAST CONCRETE MANHOLE...........................................................SS-20
48 DIA. PRECAST CONCRETE MANHOLE WITH DROP CONNECTION.........................SS-21
NEW MAIN & MANHOLE CONNECTION TO EXISTING MAIN...........................................SS-22
NEW MAIN CONNECTION TO EXISTING MANHOLE........................................................SS-23
MANHOLE COVER ADJUSTMENT PATCH GRAVEL AREAS........................................SS-25
MANHOLE COVER ADJUSTMENT PATCH ASPHALT AREAS......................................SS-26
MANHOLE 24 X (4 OR 6) FRAME AND COVER.................................... SS-27 and SS-27A
SIDE SEWER CONSTRUCTION WITH TAP ON EXISTING MAIN......................................SS-30
SIDE SEWER CONSTRUCTION FOR NEW DEVELOPMENT ............................................SS-31
SANITARY SEWER MAIN CLEANOUT ..............................................................................SS-40
PRIVATE FORCE SEWER SERVICE..................................................................................SS-61
SINGLE FAMILY GRINDER PUMP SPECIFICATIONS.......................................................SS-62
TYPICAL UTILITY SERVICE LAYOUT FOR NEW PLATS.................................................. MI-10
KOR-N-SEAL (FLEXIBLE PIPE TO MANHOLE CONNECTORS) ........................ ATTACHMENT
CHERNE INSIDE THE PIPE GRIPPER PLUGS ................................................... ATTACHMENT
PRETREATMENT OF WASTEWATER................................................................ ATTACHMENT
K:\PW Details\sewer installation.doc
CITY OF ELLENSBURG
SEWER INSTALLATION
9-23-09

ALL SANITARY SEWERS SHALL BE CONSTRUCTED IN ACCORDANCE
WITH THESE SPECIFICATIONS, THE CITY OF ELLENSBURG STANDARD
PLANS, AND THE STANDARD SPECIFICATIONS FOR MUNICIPAL
CONSTRUCTION AND AS STAKED BY THE ENGINEER.

The following is an outline the City of Ellensburg requires for sewer construction.

The Contractor will furnish and operate all tools and equipment needed to complete the
project, including safety, dewatering, pipe installation, pipe cleaning and testing.

Pipe laying
1. Bedding shall provide uniform support along the entire barrel without load
concentration at joint collars or bells. Blocking will not be allowed to adjust pipe
to grade.
2. Sewer pipe will be laid to a true line and grade at the invert of the pipe. The sewer
pipe shall be laid up grade from the point of connection on the existing sewer. The
pipe shall be laid with the bell forward or upgrade. The forward end of the bell
shall be kept tightly closed with an approved temporary plug.
3. Ground water is strictly prohibited from entering a sanitary sewer. Sediment must
be removed from ground water before it is allowed to enter a Storm drain. Obtain
City approval prior to discharge into a Storm drain.

Joints
1. J oints shall be clean of dirt and other foreign material. Any gaskets that are
disturbed or rolled shall be removed, replaced, and relubricated before joining the
pipe sections.
2. The Contractor shall use a factory-fabricated adapter coupling as approved by the
Engineer to join dissimilar pipe.

Service line connections
Taps into existing sewer mains shall be performed by the City. The contractor is
responsible for exposing the main, providing shoring, backfill and surface restoration.

Protection of existing sewer facilities
1. All existing live sewers shall be kept in service at all times. The Contractor shall
make provisions for handling and disposing of sewage flow. The Contractor shall
repair damage to existing sewers. The City must inspect all repair work.
2. Whenever possible, the contractor shall plug the downstream end of the sewer
prior to construction. Any debris of water in the new line shall be cleaned by the
contractor prior to removal of the plug.

Backfilling sewer trenches
1. Backfilling in the vicinity of catch basins, manholes, or other appurtenances will
not be permitted until the cement in the masonry has thoroughly hardened.
K:\PW Details\sewer installation.doc
2. Backfill above the pipe shall be accomplished in such a manner that the pipe will
not be shifted out of position or damaged. Compaction shall be as indicated in the
plans and specifications.

Cleaning and testing
1. The contractor will be responsible for cleaning the new line prior to testing and
inspection. All work involving cleaning and testing of sewer lines shall be
accomplished within fifteen working days after backfilling. The Contractor shall
test sewer lines by low air pressure, or as approved by the City, in the presence of
a City inspector.
2. The City will perform television inspection on mains.
3. If any sewer installation fails to meet the requirements of the test method used,
the Contractor will determine the source of the leakage or defect and perform the
repair.

Air Pressure Test
Refer to APWA Standard Specifications for Municipal Construction 7-17.3 (4) d.

Water Testing
Refer to APWA Standard Specifications for Municipal Construction 7-17.3 (4) b.

Television inspection
1. Television inspection will be required of new sewer mains. Costs incurred in
making the initial inspection will be included in the permit from the City.
2. The Contractor will bear all costs incurred in correcting any deficiencies found
during the television test, including the cost of any additional television inspection
that may be required to verify the correction of the deficiency.

The City of Ellensburg sewer crews will TV the sewer mains once the contractor has
completed the following items:

1. The new line has passed the pressure test and there are no repairs or changes
needed.
2. The line is clean of ALL debris and has no leaks in the pipe or manholes.
3. The TV crew requires firm, smooth, unyielding access to all manholes (preferably
crushed rock).
4. All other utilities in the vicinity of the sewer main need to be in before any testing can
take place.
This reduces the risk of disturbances to the new line.

Call the sewer department 72 hours in advance of needing the test or schedule through your
inspector. The pipe will need a minimal amount of water ran through it to allow the camera
to check for bellies and sags. The maximum belly allowed in the pipe is .

It is strongly advised that completion and acceptance of all tests occur in a timely fashion to
allow ample time for the rocking and paving of the roads.


K:\PW Details\sewer installation.doc
Plugging an abandoned sewer pipe
All holes created in an abandoned sewer main shall be sealed with a disposable plug and
cemented in to provide a leak proof seal.

All inspections, taps, and tests require 2 working days notice to the City.

City of Ellensburg contact numbers. If you have any questions, please call.

Assistant Public Works Director 962-7133

Permits - Engineering Dept. 962-7233

Inspection - Engineering Dept. 962-7135

City Engineer 962-7238

Wastewater Treatment Plant Foreperson 962-7277
K:\PW Details\Septic Tank Abandonment Policy.doc

CITY OF ELLENSBURG
501 N. Anderson Street; Ellensburg, WA 98926
Ph: (509) 962-7230 Fax: (509) 962-7127







SEPTIC TANK ABANDONMENT POLICY

The City of Ellensburg Sewer Department has the following policy
regarding abandoning septic tanks within the City of Ellensburg.

1. All septic tanks that are abandoned must be inspected or verified by the Sewer
Department. The abandonment inspection or verification is required with or
without side sewer connection of the property to the City Sewer system. The
Sewer Permit for inspection must be obtained from the Public Works
Department.

2. The lid of the septic tank shall be removed or destroyed. The septic tank must
be pumped out and filled with clean fill. Call the City Sewer Department at
962-7277 to schedule the inspection of abandoned septic tank. This may be
done at the same time as inspection of a new side sewer connection to a City
sewer main.

3. The contractor shall provide the Sewer Department a copy of the bill from a
septic tank pumping company as proof of that the tank has been pumped out.
The copy of the bill shall be provided within 2 weeks of the septic system
abandonment.












SEWER MAIN
PRIVATE
GRINDER
PUMP
2" MIN. SCH 40 PVC OR HDPE
FORCE SEWER SERVICE
(w/ PEA GRAVEL BEDDING)
(PIPE SHALL MEET THE REQ.
OF GENERAL NOTE #1)
PVC SEWER SERVICE
PER DETAIL SS-30 OR SS-31
2
1
NOTES:
1. IF PUMP IS LOCATED WITHIN 2' OF THE FOUNDATION, THEN THE SEWER PUMP
SHALL BE INCLUDED IN THE CITY OF ELLENSBURG BUILDING PERMIT, AND
SHALL MEET THE REQUIREMENTS OF THE UNIFORM PLUMBING CODE AS WELL
AS THESE REQUIREMENTS. IF OUTSIDE OF 2' FROM FOUNDATION THAN THESE
DETAILS SHALL APPLY. A PUBLIC WORKS PERMIT SHALL BE REQUIRED FOR ALL
SEWER SERVICES.
2. SEE STANDARD DETAIL SS-62 FOR SPECIFICATIONS ON THE GRINDER PUMP.
3. A PVC GRAVITY SEWER SERVICE SHALL BE INSTALLED FROM THE MAIN TO
THE EDGE OF RIGHT OF WAY. A SEWER CLEANOUT SHALL BE INSTALLED
WITHIN 5' OF THE REDUCER.
4. THE 2" PVC FORCE SERVICE LINE SHALL BE INSTALLED FROM GRINDER PUMP
TO THE 4" GRAVITY SERVICE LINE. AN APPROPRIATE 2" FITTING (BEND), IF
REQUIRED, SHALL BE USED TO GO FROM THE FORCE LINE TO THE GRAVITY
LINE. A 2"x4" REDUCER SHALL BE USED WITHIN 6" OF THE FITTING (BEND).
CLEAN OUT @
BEGINNING OF
GRAVITY SERVICE
3
4
2" CLEAN OUT
GENERAL NOTES:
1. ALL FORCE SEWER SERVICE LINES SHALL BE HYDROSTATICALLY TESTED AT A MINIMUM
PRESSURE OF ATLEAST 50% ABOVE THE DESIGN WORKING PRESSURE, AND SHALL BE IN
ACCORDANCE WITH THE MOST CURRENT REQUIREMENTS OF THE DEPT. OF ECOLOGY.
2. ALL FORCE SEWER LINES SHALL HAVE WATERTIGHT CLEANOUTS INSTALLED AT MAX.
SPACINGS OF 100' AND AT AGGREGATE HORIZONTAL DIRECTION CHANGES OF 135.
3. EACH CLEANOUT SHALL BE INSTALLED SO THAT IT OPENS TO ALLOW FOR CLEANING IN
THE DIRECTION OF FLOW, AND SHALL BE INSTALLED VERTICALLY ABOVE THE FLOW LINE
OF THE PIPE.
4. CLEANOUTS SHALL BE INSTALLED TO ABOVE GRADE, AND SHALL HAVE A MINIMUM OF 12"
OF CLEARANCE IN FRONT OF CLEANOUT.
5. ALL FORCE AND GRAVITY SERVICE LINES SHALL HAVE PEA GRAVEL BEDDING (4" ABOVE
AND 4" BELOW PIPE).
6. ALL FORCE AND GRAVITY SERVICE LINES, CLEANOUTS, PUMPS, WET WELL, ECT., SHALL
REMAIN UNDER THE OWNERSHIP OF THE PROPERTY OWNER WHO SHALL BE RESPONSIBLE
FOR THEIR OPERATION AND MAINTENANCE.
7. PERMITTEE SHALL SUBMIT DRAWING SHOWING LOCATIONS OF PUMP, CLEANOUT(S), AND
FORCE LINE. ALSO INCLUDED IN THE SUBMITTAL SHALL BE STORAGE CAPACITY, AND PUMP
SPECIFICATIONS AND CURVE (TOTAL HEAD IN FEET vs. CAPACITY IN G.P.M.).
R
I
G
H
T
O
F
W
A
Y
L
I
N
E
SIZE 12 USE
GREEN PLASTIC
SOLID COPPER
TRACER WIRE
CLEANOUT REQUIRED
WITHIN 5' OF PUMP
INSPECTION REQUIRED:
SIDE SEWER: CITY SEWER DIVISION SHALL BE
CONTACTED FOR INSPECTION OF SIDESEWER
PRIOR TO BURIAL.
PUMP STATION: IF WITHIN 2' OF FOUNDATION
THEN BUILDING INSPECTION REQUIRED ALONG
WITH SIDE SEWER INSPECTION.
SEWER MARKING
TAPE, 1' ABOVE
TOP OF FORCE
SEWER SERVICE
K:\PW Details\KOR-N-SEAL CONNECTORS.doc
KOR-N-SEAL (Flexible Pipe to MH Connectors)


K:\PW Details\CHERNE Plugs.doc
CHERNE (Inside the Pipe Gripper Plugs)





K:\PW Details\CHERNE Plugs.doc


Department of Public Works Sewer Division
POLICY AND PROCEDURE

Pretreatment of Wastewater


1.0 PURPOSE
1.1 This procedure establishes the rules for discharge of water or wastes into the City of
Ellensburg sewer system.
2.0 ORGANIZATIONS AFFECTED
2.1 City of Ellensburg Sewer Division
3.0 DEFINITIONS
3.1 BOD Biochemical Oxygen Demand means the quantity of oxygen utilized in the
biochemical oxidation of organic matter under standard laboratory procedure in five
days at twenty degrees centigrade, expressed in parts per million by weight.
3.2 Composite Sample - A combination of individual samples of water or wastewater
taken at selected intervals, generally 8 samples collected over a 24 hour period, to
minimize the effect of the variability of the individual sample.
3.3 Grab Sample - A single sample of wastewater taken at neither set time nor flow.
3.4 Owner - The title holder or proprietor of property.
3.5 pH - The logarithm of the reciprocal of the weight of hydrogen ions in grams per liter
of solution.
3.6 Suspended Solids - The solids that either float or are in suspension in water, sewage
or other liquids, and which are removable by laboratory filtering.
4.0 POLICY
4.1 Pretreatment facilities shall comply with the applicable requirements and regulations
of local, federal and state, Chapter 173-240 and Section 173.216.110 of the
Washington Administrative Code (WAC), Revised Code of Washington (RCW)
90.48.010,and the Uniform Plumbing Code as now or as they may be amended, and
with the accepted plan of operations and maintenance procedures.

4.2 The requirement for any and all such pretreatment devices and equipment exterior to
the building shall be determined by and shall be subject to the approval of the
Director of Public Works; devices and equipment interior to the structure shall be
determined by and subject to approval by the Building Department and the Director
of Public works.
.
4.3 Review of plans by the director of Public works shall in no way relieve the discharger
from the responsibility of modifying its facility or process as necessary to produce an
acceptable effluent under the provisions of this ordinance.

4.4 All Pretreatment devises, including grease interceptors and traps, sedimentation
chambers, chemical or biological plants and other devices to remove pollutants prior
to discharge to the sanitary sewer must be located as to be readily accessible for
cleaning, sampling, and inspection. Dischargers must maintain pretreatment devices
in a manner that will always prevent fat waste, oil grease, flammable wastes, sand or
other harmful ingredients from being carried into the sewer system. The owner shall
be responsible for the proper removal and disposal of wastes captured and shall
maintain records of the dates and means of disposal, which shall be available for
review by the director or representative. Collected materials shall not be disposed of
in sanitary, industrial or storm sewers. Failure to provide or maintain pretreatment
devises such as grease, oil and sand traps in accordance with the provisions of this
section shall be a violation and subject to the sections Municipal Code 9.94

4.5 All costs associated with installing, maintaining, and testing of any and all required
pretreatment facilities are the sole responsibility of the owner.
4.6 No statement contained in this policy and procedure shall be construed as preventing
an agreement between the city and any industrial concern whereby an industrial waste
of unusual strength or character may be accepted by the city for treatment, subject to
payment therefore, by the industrial concern provided that the following criteria are
met:
4.5.1 The city has the physical capacity for treatment; and (Currently and in the
future)
4.5.2 The industrial waste is compatible with the biological treatment process as
determined by the city.
4.7 Separators shall not be required for private living quarters or dwelling units.

5.0 PROCEDURES
All measurements, and analyses of the characteristics of wastewater, to which reference is
made in this policy and procedure shall be determined in accordance with the latest edition of
"Standard Methods of the Examination of Water and Wastewater" published by the
American Public Health Association, and shall be determined from an approved sampling
location provided by the owner.

6.0 GREASE INTERCEPTORS
Grease, oil and sand interceptors shall be provided in commercial and or retail food
preparation operations, regardless of size when, in the opinion of the Director of Public
Works, they are necessary for proper handling of liquid wastes containing floatable or
emulsified grease, fats or oil in amounts exceeding those specified in section 9.25.310.F).
This shall include Dischargers who operate restaurants, cafes, lunch counters, cafeterias, bars
or clubs: or hotel, hospital, sanitarium, factory or school kitchens: or other establishment that
serve or prepare food where grease may be introduced into the sewer system shall have
grease interceptor (grease traps) to prevent the discharge of fat waste, oil or grease. Take out
food establishments or other establishments that prepare food but do not cook in oil or
grease, and who serve only in disposable containers, may be exempted from this requirement,
provided their discharges do not violate section 9.25.310-(F) general discharge prohibitions
of this chapter.

All wastes discharged into the food processing sewer will be adequately screened by a twenty
mesh or finer screen before discharge. An additional screen, with openings no larger than one
quarter square inch shall be installed in a fixed position so all materials must pass through
said screen immediately before entrance into the sewer.

Commercial garbage disposals or grinders are not recommended. Enzymes, bio additives
chemical degreasers and hot water flushes are prohibited from entering the grease interceptor
or trap.

Size and design of the grease interceptor shall conform to the Uniform Plumbing Code
Standards most recently adopted by the City and be subject to approval by the Director of
Public Works in conjunction with the Building Department.

7.0 SUPPORTING DOCUMENT IN APPENDIX

Das könnte Ihnen auch gefallen