Sie sind auf Seite 1von 138

176,0-Preface-EN-v-05.09.2011.

pdf
99,Chap-0-Introduction-EN-v-02.09.2011.pdf
357,Chap-1-Strategy-EN-v-21.09.2011.pdf
211,Chap-2-Safety-EN-v-06.09.2011.pdf
217,Chap-3-Human-factors-v-06.09.2011.pdf
236,Chap-4-Operation-and-maintenance-EN-.pdf
153,Chap-5-Environment-EN-v-06.09-2011.pdf
244,Chap-6-Geometry-EN-v-30.08.2011.pdf
223,Chap-7-Structural-facilities-EN-v-07.pdf
257,Chap-8-Equipment-and-systems-EN-v-21.pdf
262,Chap-9-Response-to-fire-EN-v-07.09.2.pdf
164,Glossary-EN-v-07.09.2011.pdf








ROAD TUNNELS MANUAL




PREFACE










All rights reserved. World Road Association (PIARC).
PIARC ROAD TUNNELS MANUAL PIARC
Preface

This Road Tunnels Manual, in electronic version, is a major achievement of the technical committee
C.4 Road Tunnel Operations, during the operating cycle 2008-2011, under the decisive leadership of
its president Pierre Schmitz (Belgium).
This work makes it possible to make available in readily accessible form the knowledge and
recommendations hitherto published, by the World Road Association, in the form of separate reports.
The organization in the form of Web pages facilitates the access to information and will also in the
future make it possible to more easily update the contents in accordance with the progress of
knowledge.
The version put on line at the time of XXIV World Road Congress in Mexico City, in September 2011,
is a first version of this Manual. Initially, the contents of the old reports will remain accessible by the
means of links towards the PDF files from these documents. Later on, when the contents of these
reports are updated, the text will be recast in the form of Web pages to improve reader convenience.
In order to give a broad audience to this Manual, which is without equivalent in its field, the electronic
version is produced and will be maintained, by the technical committee in the two official languages
of the Association: English and French. Nevertheless some countries have expressed an interest to
have a version of the Manual in their own language; thus versions are under development in Spanish,
Chinese, J apanese, Korean and Czech on the initiative of various organizations and with the assistance
of the technical committee. We make a point of encouraging such initiatives which must be expressed
to the Secretary General of the World Road Association, who will guide the proposals.
We hope that this Manual will be an indisputable reference in the whole world, and that it translates, in
an objective way, the best practices and knowledge at the moment. For that we need your remarks and
suggestions in order to improve and to update this Manual.
Good reading and thanks in advance for your comments and suggestions,



Jean-Franois Cort
Secretary General
World Road Association
August 2011

http://tunnels.piarc.org/en/preface/ 2 / 2








ROAD TUNNELS MANUAL




0. INTRODUCTION










All rights reserved. World Road Association (PIARC).
PIARC ROAD TUNNELS MANUAL PIARC
Introduction

1. Origins and objectives of the Manual
Road tunnels are increasingly
used to cross natural barriers such
as mountain ranges, rivers, straits
or bays. They also constitute a
solution, sometimes the only one,
to the environmental and spatial
constraints of the urban
environment, where in the future
three-quarters of the global
population will live. Under these
conditions, the construction and
the maintenance of a tunnel are
always a challenge and their
realisation requires the use of
techniques and tools that are
increasingly sophisticated and
complex.

Fig. 0-1 : C4 Committee meeting in Madrid (March 2009)
The need for bringing together the experiences gained in the field of the tunnel operations goes back
several decades already. This is why, in 1957, PIARC created the "Road Tunnel Committee" to
address the range of aspects concerned in the use of road tunnels, such as geometry, equipment and its
maintenance, operation, safety and environment. Since then, supervised by successive presidents and
with the help of the secretaries (see list below), this committee has produced technical
recommendations across all of these various fields.
President
French-speaking
secretary
English-
speaking
secretary
Spanish-
speaking
secretary
From 1957 to 1975
J acques Rerolle
(France)
Fernand Ramel
(France)
- -
From 1976 to 1979
J acques Rerolle
(France)
Claude
Brenguier
(France)
- -
From 1980 to 1991
Sir Alan Muir
Wood (UK)
Claude
Brenguier
(France)
- -
From 1992 to 1995
Emanuele Scotto
(Italy)
Michel Marec
(France)
G.R. Fellowes
(UK)
-
From 1996 to 1999
Michel Marec
(France)
Willy De
Lathauwer
(Belgium)
Alan West
(UK)
-
From 2000 to 2003
Didier Lacroix
(France)
Willy De
Lathauwer
(Belgium)
Alan West
(UK)
-
From 2004 to 2007
Didier Lacroix
(France)
Pierre Schmitz
(Belgium)
Alan West
(UK)
Manuel Romana
(Spain)
From 2008 to 2011
Pierre Schmitz
(Belgium)
Alexandre Debs
(Canada-Quebec)
Robin Hall
(UK)
Ignacio Del Rey
(Spain)

Table 0-2 : List of the road tunnel committee presidents and secretaries
http://tunnels.piarc.org/en/introduction/ 2 / 5
PIARC ROAD TUNNELS MANUAL PIARC
These recommendations are substantially followed worldwide and they are even often used as the
basis for contractual specifications in many countries. In 1974, ITA (International Tunnel and
Underground Space Association) was created to address aspects of the construction of all types of
underground works, including road tunnels. In 2005, a Memorandum of Understanding was concluded
between these two international associations to ensure that their actions are and will remain
complementary and not overlapping.
Since its creation, the "Road Tunnel Committee", which was renamed the "Technical Committee for
Road Tunnel Operations" in 1996, has taken part in 14 World Road Congresses. For the first 5 of
them, from 1959 to 1975, it published several hundreds of pages of documentary materials. From 1971
(the Prague Congress) onwards, the committee released an up-to-date summary report that listed
recommendations on all of the topics examined during each cycle. Since the Kuala Lumpur Congress
in 1999, these summary reports were replaced by introductory assessments for each Congress session
organised by the committee. In 1995, the committee started to issue PIARC reports outside of the
Congresses. The first of them was the special report "The first Road Tunnel" authored by Sir Alan
Muir Wood under the aegis of the committee and published in 1995 with the intention of reaching
tunnel designers in countries facing the prospect of introducing tunnels in their road networks. Since
then, 32 other reports have been published or are in preparation. All these Reports are available free of
charge on the PIARC Website.
In addition to these outputs of the committee, many articles have been published in Routes/Roads,
notably the October 2004 special issue 324 written in collaboration with ITA and entirely devoted to
fire safety in tunnels.
The tunnel committee was also involved in the ERS2 research project, undertaken jointly from 1997 to
2001 by OECD and PIARC, on dangerous goods transport through road tunnels. A Quantitative Risk
Assessment Model (QRA Model) was developed within the framework of the ERS2 project.
During the preparation of the centenary Congress in Paris in September 2007, the members of the
committee discussed the interest there would be in gathering, synthesising and if necessary updating
the large quantity of information disseminated in these various reports and articles. During the Paris
Congress, it was decided that this idea would be proposed at the PIARC executive committee for the
next cycle of the Road Tunnel Operations committee. This proposal was adopted and the committee
was requested, within the 2008-2011 cycle, to produce an electronic encyclopaedia, which would be
hosted on the PIARC Website.

2. Contents of the Manual
Fig. 0-3 : Tunnel Calle 30 in Madrid (Spain)

This electronic encyclopaedia,
called the "PIARC Road
Tunnel Manual", primarily
takes the contents of the 35
reports issued by the
committee between 1995 and
2011, the twenty or so most
recent articles published in
Routes/Roads in the field of
tunnels plus the documents of
the joint OECD/PIARC
research project. It also links
to several useful sites.

J ust like the PIARC Road Tunnel Operations Committee, this Manual exclusively concerns the
operational aspects of these works (geometry, equipment and its maintenance, operation, safety,
http://tunnels.piarc.org/en/introduction/ 3 / 5
PIARC ROAD TUNNELS MANUAL
environment). It does not consider the civil engineering aspects of tunnels (geology, geotechnics,
structures, coatings, waterproofing, drainage, etc), except with regard to their effects on the operation
and maintenance of the road tunnels
The Manual comprises two principal parts.
The first part considers general aspects of road tunnels. Chapter 1 presents the principal strategic
elements of which any decision maker must take into account before making a decision concerning the
choice or the design of a tunnel. This chapter is addressed particularly to the decision makers and to the
designers of countries that are starting to tackle the construction or major refurbishment of a tunnel.
Chapter 2 deals with the crucial topic of safety in tunnels. In particular, it considers methods for risk
analysis. Chapter 3 considers the human aspects that affect the operation of road tunnels. The severe
fires in 1999 and 2000 confirmed how important it is to take human behaviour into account at the
design stage. Chapter 4 examines the management and the maintenance of tunnels for which, in
addition to safety, durability is a key concern. Chapter 5 deals with the environmental aspects of road
tunnel operations, not only in terms of air pollution but also noise and water pollution.
The second part of the Manual addresses particular elements of tunnels taking operational and safety
requirements into consideration. Chapter 6 addresses the geometrical characteristics of the tunnels and
their influence on operation and safety. Chapter 7 deals with the structural facilities that support
operations and safety and must be taken into account at the early stages in a tunnel project, and whose
impacts should not be underestimated, particularly on costs. Chapter 8 reviews the different types of
tunnel equipment and gives recommendations covering the whole of their lifecycle. Lastly, Chapter 9
addresses the performance of materials, structures and equipment in fire.
The Manual ends with a Glossary showing the contents of the PIARC Tunnels Dictionary.
This Manual was designed to be a "live" document in order to be able to follow the frequent
technological developments that are adopted from the design to the operation of the tunnels, and to be
able to easily integrate the new reports that will be produced by the committee during following cycles.
In this first version (2008-2011), the committee members have primarily endeavoured to define the
structure of the Manual and to integrate into it, by means of new text or hyperlinks, the most relevant
documents that already exist. Later, the old texts will be up-dated and up-graded as necessary and on
this occasion the integration of their content within the Manual will be examined when appropriate.

3. Contributors
The preparation of the first
version of this Manual was
coordinated by Working
Group 5 of the C4 committee
(2008-2011) in which:
Pierre Schmitz (Belgium),
president of the committee,
assumed the coordination of
the working group, carried
out the electronic page-
setting of the Manual, wrote
the introduction and the
home page, supervised the
Glossary;
Bernard Falconnat
(France) wrote chapter 1;

Fig. 0.4 : WG5 meeting in London
Didier Lacroix (France), former president of the committee, reviewed all the French texts,
checked their accordance with the English texts and supervised the writing of chapter 2;
http://tunnels.piarc.org/en/introduction/ 4 / 5
PIARC ROAD TUNNELS MANUAL
Willy De Lathauwer (ITA), former French-speaking secretary of the committee, supervised the
writing of chapters 3 and 6;
Roberto Arditi (Italy) supervised the writing of chapters 4 and 5;
Robin Hall (UK), English-speaking secretary of the committee, reviewed all the English texts
and supervised the writing of chapters 7 and 9;
Antonio Valente (Italy) supervised the writing of chapter 8;
Rafael Lpez Guarga (Spain) managed and supervised the translation of the encyclopaedia
pages in Spanish.

4. Future evolutions and thanks
In order to help the committee to improve this Manual, all your comments and suggestions are
welcome. You can forward them just by clicking on "Contact" at the top of a page of the Manual.
We want to thank all those who have contributed to the realisation of this Manual and in particular all
members of the preceding tunnel committees which wrote the reports on which this Manual is based
and whose names appear at the beginning of those reports. The contributors of the committee and its
working groups to the writing of the various chapters of the Manual appear in bottom of the
introductory page of each one of these chapters.
We hope that this Manual will constitute a useful and convivial reference work for all those who are
concerned with road tunnels. We hope that this Manual can meet their needs and, with the comments
and suggestions of its readers, that following tunnel committees can improve this Manual so that it
becomes for all a valuable tool which helps to support the effective and safe transport of goods and
people in road tunnels thanks to the contributions of all the PIARC committees members who will
have contributed to it.


Pierre SCHMITZ
President of the PIARC Technical Committee C4 Road Tunnel Operations (2008-
2011)
Ministry of the Region Brussels Capital - Brussels Mobility
Brussels (Belgium)
September 2011

http://tunnels.piarc.org/en/introduction/ 5 / 5








ROAD TUNNELS MANUAL




1. STRATEGIC ISSUES










All rights reserved. World Road Association (PIARC).
PIARC ROAD TUNNELS MANUAL PIARC

1. Strategic issues

Tunnels, initially aimed at crossing an obstacle (in general a mountain), have become increasingly
complex during recent years, incorporating increasingly complex equipment (including ventilation
systems) and methods of operation. Such operation includes the deployment of control and supervision
systems that able to handle tens of thousands of items to be controlled, and which can accommodate
increasingly sophisticated management scenarios.
Following the catastrophes at the Mont Blanc,
Tauern and Gothard tunnels in the years 1999
and 2001, the need for recognising all aspects
relating to safety as a holistic system was
reinforced. This resulted in the integration, from
the design of the works onwards, of more
constraining provisions, which have an
important impact on the required civil
engineering and the specified tunnel equipment.
Tunnels are in general considered as "expensive
and risky" works, both with regards to their
construction as well as their operation. This

Figure 1.0 : St Gothard tunnel fire
"image" makes some countries very reluctant when considering the construction of their first tunnel for
their road or railway infrastructure. In order to address such concerns, it is inevitable that the costs of
construction and operation, the control of risks (mainly during the construction phase), the minimisation
of accidents or fires during the operation and the optimisation of the tunnel facilities at each stage of the
design, construction and operation become increasingly necessary.This control of the risks and the costs is
reinforced when considering current procurement and financing models for the construction of tunnels,
which are increasingly being implemented as "Concession", "Design and Build" or "Private Public
Partnership" models.
Chapter 1 of this manual has the following aims:
to make the reader aware of the "complex system" that a tunnel comprises;
to highlight the importance of the definition of the "function" of the facility for both the upstream
(design) and downstream (operational) aspects of the design;
to draw the attention of the tunnel owner to the need for surrounding himself with multidisciplinary
competences with skills and in-depth experience to ensure the success of the mission;
to make the reader aware that a tunnel is essentially designed to be used in conditions of comfort
and safety, and that it must be the subject of continuous and reliable maintenance by the operator.
The concept of a tunnel must take into account these safety and operational objectives and
constraints;
and finally to make the reader understand that the facility itself constitutes only a part of the
problems which the owner will have to solve, and that very often it will be necessary to develop in
parallel certain external elements which may be outside the tunnel owners authority: regulation,
intervention and safety services, procedures, etc.
It is not the intention for Chapter 1 to be a detailed handbook of the actions required by tunnel owners, or
to specify the technical provisions to be implemented by the designers, or to determine the tasks to be
taken by the operators to ensure a safe and comfortable tunnel. In particular, Chapter 1 does not have an
objective to be a handbook of design. Its only objective is to make the reader aware of certain issues, in
order to facilitate his approach and comprehension of this complex field, to hopefully enable him to avoid
the many possible errors in tunnel operations, and to enable him to perceive the possibilities of
optimisation.
http://tunnels.piarc.org/en/strategic-issues/ 2 / 35

PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/ 3 / 35

Section 1.1 presents the "complex system" that a tunnel is, and lists the main interfaces of the various
subsets Civil Engineering, Ventilation and Safety;
Section 1.2 presents the major elements which have to be considered when designing a tunnel;
Section 1.3 concerns the upgrading and the refurbishment of existing tunnels under operation;
Section 1.4 analyses various stages of the cycle of construction and the life cycle, and underlines the key
actions of each one of these phases;
Section 1.5 explains issues relating to the costs of construction, operation and renovation, as well as the
main stakes specific to the modes of financing;
Section 1.6 gives a list of the main recommendations, instructions and regulations published by a number
of countries in Europe and in the world.

Contributors
This document was compiled by Bernard Falconnat (Egis, France), French representative in the Road
Tunnels Operation Committee and member of Working Group 5, which has also translated his French
version into the present English version.
Its original version in French was revised by Didier Lacroix (France) and Willy De Lathauwer
(Belgium ITA representative within the committee).
The English version has been reviewed by Lucy Rew (Egis, France) and Fathi Tarada (UK).
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 4 / 35

1.1. Tunnel is a complex system

1.1.1. Complexity of the system
A tunnel constitutes a "complex system" which is the result of the interaction of very many parameters.
These parameters can be gathered by subsets, the principal ones of which are represented on the graph
below (fig. 1.1-1).
All these parameters are variable and interactive, within each subset, and between the subsets themselves.
The relative weighting of the parameters and their character varies according to the nature of each tunnel.
For example:
the determining criteria and the weighting of parameters are not the same for an urban tunnel and a
mountain tunnel;
the parameters differ for short and long tunnels, for tunnels passed through by vehicles transporting
dangerous goods and for those transporting passenger vehicles only;
the criteria are not the same for a new-build tunnel or a tunnel to be refurbished or upgraded to put
it in conformity with new standards concerning safety.

Fig. 1.1-1 : Sketch of main subsets of the "complex tunnel system"
Note 1: the links are multiple and often reversible - the general concept of the tunnel and the functional
section are placed in the centre of the figure. Similar diagrams could be drawn up while placing other
factors in the centre of the figure.
Note 2 : the first circle represents "technical fields". Some fields represent multiple aspects:
safety: regulation - risk analysis - intervention means - requirement of availability,
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 5 / 35

geology: geology - geotechnics - structural dimensioning,
civil works: methods - construction schedule - risks and hazards,
operation: operation and maintenance (technical aspects),
costs: construction - operation - daily maintenance - major repairs,
environment: regulation - diagnosis - impact assessment - treatment and mitigation,
Note 3: the second circle represents the "context" in which the project is to be developed. Some elements
represent multiple aspects:
human environment: sensitivity - urbanisation - presence of buildings or infrastructure,
natural environment: sensitivity - water - fauna - flora - air quality - landscape,
nature of the transport: nature and volume of the traffic - typology - types of goods that are
transported - etc.
various external constraints: accesses and particular constraints - climatic conditions - avalanches
- stability of the ground - socioeconomic context - etc.
level of profitability: economic acceptability - capacity of financing - control of the financial costs -
general economic and political context in case of concession or Public Private Partnership (PPP).
The design of a new tunnel (or the refurbishment and upgrading of an old tunnel) requires these numerous
parameters to be taken into account. The decision tree relating to these parameters is complex, and
requires the input of experienced multidisciplinary parties. They must intervene as early as possible, for
the following reasons:
to enable all relevant parameters to be considered from project commencement, and to avoid
numerous potential pitfalls noted in projects in progress or in recently completed tunnels. Such
errors include the late consideration of the required equipment for operation and safety, and the
development of a supervision system without integrating the results of the risks analyses, the
emergency response plan or the operation procedures.As a consequence, the tunnel and its systems
and equipment for operation and supervision may be inappropriate for safe and reliable operation.
an early intervention contributes to a better optimisation of the project, both from the perspective of
safety as well as for construction and operation costs. Recent examples indicate that transverse
optimisations (civil engineering - ventilation - safety evacuation) made at early project stages can
contribute about 20% towards cost savings.
Each tunnel is unique and a specific analysis has to be developed, while taking into account all the
specific and particular conditions.This analysis is essential to bring suitable answers and to allow:
optimisation of the project from a technical and financial aspect;
reduction of the technical, financial and environmental risks;
guaranteeing the required level of safety for tunnel users.
There is no "magic key solution", and a simple "copy and paste" process is almost always unsuitable.
The design and optimisation of a tunnel require:
an exhaustive and detailed inventory of all the parameters,
an analysis of the interactions between parameters,
the evaluation of the degree of flexibility of each parameter, and if necessary of the sensitivity of
each one of them with respect to the required objectives,
a holistic approach to achieving success, because:
- a purely mathematical approach is not possible, owing to the fact that the "system" is too
complex, and there is no single answer;
- too many parameters are still unspecified or variable during the early stages of a project, but
essential choices still have to be made;
- the evaluation of the risks, their gravity and their likelihood of occurrence must be taken into
account;
- many parameters are interdependent and many interactions are circular.
Several examples are given in the following paragraphs making it possible to clarify the complexity, the
interactivity, as well as the iterative and "circular" character of the analysis.
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 6 / 35

These examples are not exhaustive. Their aim is simply to make the reader aware of the issues and make
it possible to focus considerations on each specific tunnel.

1.1.2. Subset "Civil Engineering"
1.1.2.1. Parameters
Table 1.1-2 below gives an example of the principal parameters concerning the aspects relating to civil
engineering:

Table 1.1-2 : Main parameters according to civil engineering
The first column of the table indicates the principal sets of parameters,
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 7 / 35

The second column of the table indicates the principal subsets of parameters relating to a principal
set,
The third column lists a certain number of elementary parameters relating to a subset. The list is not
exhaustive,
The fourth column of the table indicates by set, or subset, the principal outcomes related to the
subset.

1.1.2.2. Interactions between parameters
The interactions between parameters are numerous and often connected by circular links taking into
account the overlaps between the various parameters.
The example below (Table 1.1-3) relates to the interactions between ventilation, the cross section, and
safety:
The first column concerns ventilation. The parameters listed in this column are the elementary
parameters resulting from table 1.1-2 above for the subset "ventilation",
The second column concerns the cross section. The parameters result from table 1.1-2,
The third column concerns safety.

Table 1.1-3 : Interactions between parameters
The figure reveals a certain number of parameters common to several columns (see line connectors),
which create circular interactions between the various subsets of parameters. These interactions are linked
by complex functions, which make a purely mathematical resolution of the problem nearly impossible.
The resolution of the problem requires the definition of a hierarchy between the various parameters,
followed by taking into account assumptions for the parameters of higher hierarchy. This hierarchy differs
from one project to another, such as for example:
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 8 / 35

For a short bored tunnel or a medium-length bored tunnel with one-way traffic, the most probable
ventilation system is "longitudinal ventilation". The jet fans fixed in the crown have indeed usually
a very low impact on the dimension of the cross-section. This one could thus be dimensioned
initially before designing the ventilation, but by taking into account the other determining
parameters. The impact of the ventilation on the cross-section will then be checked afterwards,
Conversely, if the tunnel is very long or the cross-section is rectangular (cut and cover), the
ventilation system and its components (section, number and nature of the possible air ducts -
dimension of the jet fans if required - etc.) have an essential impact on the cross-section size. The
ventilation system will have to be pre-dimensioned at the beginning of the analysis by making
preliminary assumptions of the dimension of the cross section. The geometry of the cross-section
will then be checked.
The process of resolution is then iterative and based on a first set of assumptions, as the previous
examples show. This process requires a large transverse multi-technical experience of the engineers,
making it possible to take into account the relevant parameters for the project, to better target the
successive iterations, and to guarantee the best optimisation of the project, with the required level of
service and safety.

1.1.3. Subset "Ventilation"
Table 1.1-4 below gives an example of the principal parameters concerning the aspects relating to
ventilation. This table is not exhaustive.
As for "civil engineering", the interactions between parameters are numerous. They also are subject to
circular relations.
The process to solve the problems is similar to the one outlined above for "civil engineering".
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 9 / 35


Table 1.1-4 : Main parameters influencing ventilation

1.1.4. Subset "Operation equipment"
They do not constitute fundamental parameters for the definition of the functional section, with the
exception of:
box-outs and sleeves for the passage of cables, pipes for water supply to the fire fighting system,
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm
signalling, signage for information, safety or police instructions. Signalling may have sometimes
(rectangular cut and cover) a very important impact on the geometry (distance between roadway
and soffit with a possible impact on the vertical alignment and the tunnel length). This may
eventually require a more global optimisation, which may concern the position and/or the design of
the interchanges outside the tunnel close to the portals.
"Operation equipment" constitutes on the other hand essential parameters for the dimensioning of the
technical buildings at the portals, of underground M&E sub-stations, and of all underground technical
spaces, or various provisions, recesses and niches. They often require particular arrangements concerning
temperature, air conditioning, and air quality.
They also are important parameters in terms of cost: construction, operation and maintenance.
"Operation equipment" constitutes essential parameters regarding tunnel safety. It must be designed, built
and maintained in this objective:
availability and reliability, in particular power supply and distribution, as well as all the
communication networks,
protection against fire of all equipment, in particular of the main power supply cables and the cables
of the transmission networks,
hardiness of the equipment and its components in order to guarantee its life-span, reliability and
optimisation of costs: operation and maintenance,
to facilitate maintenance interventions, their low impact on the traffic conditions, as well as on the
safety of the maintenance teams and the users, which requires particular arrangements concerning
the design and the accessibility of these facilities,
integration of the procedures for operation, and the emergency response plan in the design of the
supervision system (SCADA), the ergonomics of the man/machine interfaces, and assistance to the
operator in particular during an incident.

1.1.5. Subset "Safety"
1.1.5.1. Concept "Safety"
The conditions of safety in a tunnel result from
many factors as presented in chapter 2 of this
Manual.It is necessary to take into account all
the aspects of the system formed by the
infrastructure itself to ensure safety as well as its
operation, interventions, vehicles and users (Fig.
1.1-5).

Fig. 1.1-5 : Factors affecting safety
Infrastructure is an essential parameter of
construction cost. However, one can invest
highly in infrastructure without improving
conditions of safety if essential provisions are
not considered in parallel concerning:
organisation, human and material means, the procedures of operation and intervention,
training of operating staff,
the emergency services' equipment with efficient material and training of their staff,
communication with users.
1.1.5.2. How do these parameters affect a tunnel project?
These parameters relating to safety may affect in a more or less important way a tunnel project. The tables
below give some examples.
Note: The four tables below refer to the four principal fields represented in Fig. 1.1-5.
Column 1 indicates the principal infrastructure or actions concerned,
10 / 35

PIARC ROAD TUNNELS MANUAL PIARC

Columns 2 and 3 indicate the degree of influence on the tunnel project (civil engineering -
ventilation - operating and safety equipment):
Green: important or major impact
Yellow: medium impact,
Red: no impact.
Column 4 specifies the main reasons or causes of influence.
Fig. 1.1-6 : Main impacts on the project due to infrastructure

Fig. 1.1-7 : Main impacts on the project due to intervention conditions and the organisation of the operation

Fig. 1.1-8 : Main impacts on the project due to vehicles

Fig. 1.1-9 : Main impacts on the project due to the tunnel users

1.1.6. Synthesis
A tunnel is a "complex system" which means in particular that:
approaching the design of a tunnel from the point of view of only the alignment, the geology or the
civil engineering, leads to serious design deficiencies, which are likely to make the tunnel less safe
(possibly even dangerous) and difficult to operate (perhaps impossible to be operated under
reasonable conditions).
http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 11 / 35

PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/complex-system.htm 12 / 35

in the same way, to approach the design of a tunnel from the point of view of only the operating
equipment without integrating an upstream analysis of risks and safety, intervention and operation,
will also lead to deficiencies that will very quickly appear as soon as the tunnel is open to traffic,
not taking into account, from the preliminary design stage, all the objectives and constraints relating
to the operation and to the maintenance, will inevitably lead to increased operational costs and to
reduced overall reliability.
Partial treatment of problems is unfortunately still rather frequent, due to lack of sufficient "tunnel
culture" of the various actors involved in the design.
Control of this complex system is difficult but essential in order to:
find the appropriate solution to each problem,
ensure the users have an essential level of safety, and to offer them a service of quality and good
comfort.
In a parallel way the control of this complex system very often contributes to the technical and
economical optimisation of the project, by a clear and early definition of the functions to be ensured and
by using a value engineering process.
Taking into account, from the start of the project, the major issues relative to:
horizontal and vertical alignments, geology, civil engineering construction provisions and methods,
ventilation,
safety (by a preliminary analysis of risks and danger and a preliminary emergency plan),
operation and maintenance conditions,
constitutes an effective approach to solving this complex equation.
PIARC ROAD TUNNELS MANUAL PIARC

1.2. General design of the tunnel (new tunnel)

Section 1.2 relates to the design of new tunnels. The design concerning the refurbishment and the safety
upgrading of tunnels under operation is presented in Section 1.3.

1.2.1 Horizontal and vertical alignment
The design of the horizontal and vertical alignment of a road or highway section, which includes a tunnel,
constitutes a major and fundamental first stage in the creation of a new tunnel, to which the necessary
attention is seldom given.
The consideration of the "complex system" which constitutes a tunnel has to start at the early stage of the
design of the general alignment, which is seldom the case. It is however at this stage that technical and
financial optimisations are the most important.
It is essential to mobilise from the earliest stage of the design a multidisciplinary team made up of very
experienced specialists and designers, who will be able to identify all the project's potential problems,
despite inevitably incomplete preliminary information. This team will be able to make good and reliable
decisions for the major choices, and then consolidate these elements progressively taking into account the
availability of additional information.
The objective of this section is not to define the rules regarding tunnel layout design (several countries'
design handbooks are referred to in Section 1.6) but essentially to sensitise the owners and the designers
to the necessity of a global and multicultural approach, from the early stages of the design, and to the
importance of essential experience that is paramount to the success of the project.
1.2.1.1 Countries without "tunnel culture"
In these countries owners and designers have a certain apprehension about tunnels. They very often prefer
"acrobatic road layouts" passing along ridges, with steep gradients, huge retaining walls or very long
viaducts, and sometimes tremendous consolidation works (which are very expensive and not always
effective over a long period of time), in order to cross zones with active landslides.
Numerous examples of projects including tunnels and alignment variations designed with a global
system approach demonstrate, in comparison with approaches refusing systematically the construction
of tunnels:
construction cost savings may reach between 10% and 25% in areas with mountainous conditions,
important savings of operation and maintenance costs can be achieved. The reliability of the route
can be improved, in particular in zones of instability or active landslides, or subject to severe
climatic conditions,
environmental impact is significantly reduced,
the level of service for the users is improved, and the operating conditions, in particular in winter (in
countries subject to snowfall) are made reliable by the reduction of the gradients required by
passages along ridges.
The assistance of an external assessor makes it possible to mitigate the insufficiency or the lack of "tunnel
culture", and to improve the project significantly.
1.2.1.2 Countries having a tradition of construction and operation of tunnels
The concept of "complex system" is seldom integrated upstream, to the detriment of the global
optimisation of the project. Too often the "geometry" of the new infrastructure is fixed by layout
specialists without any integration of the whole of the constraints and tunnel components.
It is however essential to take into account from this stage all the parameters and interfaces described in
paragraph 1.1 above, and in particular:
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 13 / 35

PIARC ROAD TUNNELS MANUAL PIARC

the general geology and hydrogeology of the area (with the available level of knowledge) as well as
preliminary appreciation of the geological difficulties and the potential risks concerning the
methods, costs and construction duration,
the potential geomechanical, hydro-geological, hydrographical conditions at the tunnel portals and
along the accesses,
the risks and hazards related to winter conditions for countries subjected to noteworthy snowfall, in
particular:
- the risks of avalanche or formation of snow-drifts and the possibilities of protecting the access
roads and the portals against these risks,
- the maintenance conditions of access roads in case of significant snowfalls to guarantee the
reliability of the route. This provision may condition the altitude of the tunnel portals, the
maximum slopes of the access roads, and if necessary the place available to arrange surfaces for
chaining and unchaining in the vicinity of the portals,
the environmental conditions at the tunnel portals and on the access roads. The impact can be
significant in urban environments (in particular because of the noise and the discharge of polluted
air), as well as for interurban tunnels,
the gradient of the approach ramps:
- the least expensive tunnel is not always the shortest tunnel,
- the suppression of a special lane for slow vehicles is difficult to manage in the vicinity of a
tunnel portal, and keeping such a lane in a tunnel is generally very expensive,
- the gradient of the access roads can have a very strong impact on the capacity of the route in
terms of traffic volume and winter reliability.
the possibility of incorporating adits as lateral accesses (ventilation - evacuation and safety -
reduction of the construction works schedule), or as vertical or inclined shafts (ventilation -
evacuation and safety),
- these particular access points, their impact on the surface (in particular in urban environments:
available space - sensitivity to the discharge of polluted air - etc), their year-round accessibility
(e.g., exposure to avalanches) may constitute important constraints for the design of the
horizontal and vertical alignment. Conversely they very often contribute to the optimisation of
the construction and operation costs,
- these particular access points may have a major impact on the construction and operation costs,
and on the size of the cross section (potential optimisation of the ventilation and the evacuation
facilities),
the methods of construction which may have a major impact on the design of the horizontal and
vertical alignment, for example:
- crossing under a river with a bored tunnel constitutes an essentially different project to that of a
solution by immersed prefabricated boxes,
- interfaces with a viaduct at the tunnel portal,
- the imposed construction deadline may have a direct impact on the layout, in particular to allow
driving from both tunnel portals as well as intermediate drives, using adits,
the geometrical characteristics of the layout and the longitudinal profile of the tunnel for which it is
also necessary to integrate the following elements:
- limitation of gradients, which have a major impact on the sizing of the ventilation system and
on the reduction of the traffic volume capacity of the tunnel,
- the hydraulic conditions of underground drainage during the construction and the operation
period, which affect the vertical alignment,
- reduced lateral clearance (construction of additional widths is very expensive) which require
particular analysis of the visibility conditions and particular vigilance in the choice of the radii
of the curves for the horizontal alignment,
- the best choice of the radii in order to avoid alternating cross-fall slopes, and their major impact
on water collecting and drainage systems from the carriageways, interfaces with sleeves for the
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 14 / 35

PIARC ROAD TUNNELS MANUAL PIARC

installation of cables, water pipes for fire fighting, which can even lead to an increase in the
dimension of the cross section,
all usual constraints related to the occupation of the underground space, in particular in urban
environments: subways - car parks - foundations - structures sensitive to settlements,
construction and operation costs:
- the least expensive tunnel is not necessarily the shortest one,
- an additional investment in civil engineering can be overall more economic over the tunnel
lifetime if it enables a reduction of the costs for construction, operation, maintenance and heavy
repairs (in particular ventilation), or if it makes it possible to postpone for several years the date
of traffic capacity saturation (impact of the gradient in the tunnel and on the accesses),
the coordination between the horizontal and the vertical alignments must be carefully studied in a
tunnel in order to support the level of comfort and safety of the users. The visual effect of the
changes of slopes in the vertical alignment, in particular in high points, is highlighted by the limited
visual field of the tunnel and by the lighting,
the conditions of operating with uni- or bidirectional traffic have to be taken into account in the
design of the layout, in particular:
- the usual conditions of visibility and legibility,
- the possibility of arranging lateral accesses (adits) or vertical accesses (shafts), in particular for:
optimisation of ventilation and the cross-section, improvement of safety (evacuation of the
users and access of the emergency teams by avoiding the construction of an expensive parallel
gallery),
the layout in the vicinity of the portals:
- the tunnel portals constitute singular points of transition, and it is necessary to take into account
human behaviour and the physiological conditions. It is essential to preserve a geometrical
continuity to make it possible for the user to preserve his instinctive trajectory,
- a rectilinear tunnel is not desirable, in particular along the approach of the exit portal. It may be
necessary to reinforce the exit lighting over a long distance,
underground junctions at or very close to the tunnel portals:
- interchanges inside a tunnel or outside in the immediate vicinity of the portals are to be avoided,
- if they are unavoidable, a very detailed analysis must be made to determine all the constraints
and particular consequences to be taken into account (layout - cross-section - exit or merging
lanes - risk of backward traffic flow - evacuation - ventilation - lighting - etc) to ensure safety in
all circumstances.

1.2.2 The functional transverse profile
1.2.2.1 The issues
The functional transverse profile constitutes the second major stage of the design of a tunnel after
selecting the alignment. As for the first stage, the "complex system" approach must be taken into account
in a very attentive way, as upstream as possible with an experienced multidisciplinary team. All of the
parameters and interfaces described in Paragraph 1.1 must be considered.
This second stage (functional transverse profile) is not independent of the first stage (alignment), and it
must obviously take into account the resulting provisions. The two stages are interdependent and very
closely linked together.
Moreover, as mentioned in paragraph 1.1.2.2 above, the process of the first two stages is iterative and
interactive. There is no direct mathematical approach to bring a single response to the "complex system"
analysis. There is also no uniqueness of answer but a very limited number of good answers and a great
number of bad answers. The experience of the multidisciplinary team is essential for a good solution to be
identified quickly.
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 15 / 35

PIARC ROAD TUNNELS MANUAL PIARC

The examples quoted in paragraph 1.2.1 above illustrate that the provisions of the "functional transverse
profile" can have a major impact on the design of the horizontal and vertical alignments.
Experience shows that the analysis of the "functional transverse profile" is very often incomplete and
limited to the sole provisions of civil engineering, which leads inevitably to:
in the best case, a project that is not optimised from the functional, operational and financial points
of view. Experience shows that potential optimisations can reach in exceptional cases 20% of the
construction costs,
in the most frequent case, an inadequate consideration of the functions, their constraints and their
impacts on the project. These functions will have to be integrated in the following stages of the
project by implementing late and often very expensive solutions,
in the worst case, fundamental design errors with an irremediable and permanent impact on the
tunnel, on its conditions of operation and safety, as well as on its construction and operation costs.
1.2.2.2 Principal provisions
The major parameters of the "functional transverse profile" are as follows:
Traffic volume - nature of the traffic - operation organisation - urban or non-urban tunnel, in order
to determine:
- the number and width of the lanes, according to the traffic and the type of vehicles admitted to
the tunnel,
- the headroom (according to the type of vehicle),
- the hard shoulder, emergency stopping lane or lay-by, according to the volume of traffic, the
mode of operation, i.e. uni- or bidirectional, the statistical rate of breakdowns,
- a possible central separator and its width in the event of bidirectional operation,
Ventilation has a major impact which depends on:
- the selected system of ventilation, itself depending on many other parameters (see Paragraph
8.5),
- the space required for the ventilation ducts, for the installation of axial fans, jet fans, secondary
ducts, and all the other ventilation equipment,
Evacuation of the users and the access of the emergency and rescue teams which depend on the
numerous factors detailed in Chapter 7,
The length and the gradient of the tunnel. These parameters intervene in an indirect way through the
ventilation, the concepts of access and safety,
The networks and equipment for operation are also very often determining factors in the
dimensioning of the functional cross section, taking into account their number, the space they
require, the essential protection associated with them to guarantee the operational safety of the
tunnel, and the relatively limited space under the walkways and hard shoulders to locate them. The
following networks are in particular concerned, which have a dimensional impact:
- separated or combined sewer system(s) - collection of polluted liquids from the roadways and
associated siphons. The absence of variation in the crossfall, associated with the conditions of
the alignment (see 1.2.1.2) allow a simplification and an optimisation of the functional
transversal profile,
- water supply network for the fire fighting system, fire hydrants, and if necessary their protection
against freezing,
- all networks of cables of high and medium voltage, as well as low voltage currents. It is
essential to take into account on the one hand, the cables necessary at the time of the tunnel
opening and their protection against fire, as well as the provisions allowing their partial or total
replacement, and on the other hand the provisionsfor the inevitable addition of other networks
throughout the tunnel's life,
- the particular needs in the short or medium term for external networks likely to pass through the
tunnel,
- all interactions between networks and needs (technical or legal) for spacing between some
networks,
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 16 / 35

PIARC ROAD TUNNELS MANUAL PIARC

- all of the signalling for operation: signalling and signage - lane signals - panels with variable
messages - regulation indications - safety indications - directional indications,
Localised functional interfaces: underground sub-stations - underground ventilation plant - safety
recesses - shelters - etc. It is essential to take into account the provisions for operation and the
maintenance, and in particular the construction of lay-bys for maintenance interventions and the
safety of the operating teams,
Construction methods and geological conditions have an impact on the functional transverse section
(independently of the dimensioning of the civil engineering structures), for example:
- the underwater crossing mentioned in section 1.2.1.2 above. The solution with immersed
precast boxes enables a very different design and arrangement of the ventilation system, the
evacuation galleries or the access of the emergency teams, in comparison with the arrangement
for the same equipment in the case of a bored tunnel,
- a tunnel bored with a TBM (tunnel boring machine) makes surfaces available under the
roadway which can be used for example for ventilation, for the users' evacuation, or for the
access of the emergency services. This can allow optimisations (removal of connection galleries
or a parallel gallery) which can be financially very important if the tunnel is located under
groundwater level in permeable materials.

1.2.3 Safety and Operation
1.2.3.1 General provisions
PIARC's recommendations are numerous in the fields of safety and operation for the finalisation of safety
studies, the organisation of operation and emergencies, as well as the provisions for operation. The reader
is invited to refer to theme : see Chapter 2 "Safety" and Chapter 3 "Human factors regarding tunnel
safety").
This present chapter primarily treats safety and operation interfaces within the "complex system". The
tables of section 1.1.5.2 above indicate the degree of interdependence of each parameter compared to the
various subsets of the project.
A certain number of parameters have a major impact from the upstream stages of the project onward.
They must be analysed from the first phases of the design and deal in particular with:
volume of traffic - nature of the traffic (urban, non urban) - nature of vehicles (possibly tunnel
dedicated to one category of vehicles) - transport or not of dangerous goods,
evacuation of the users and access of the emergency teams,
ventilation,
communication with the users - supervision system.
These major parameters for the design of the tunnel are also the essential factors of the "hazard analysis",
and drafts of the "intervention plan of the emergency teams". This is why we consider that it is essential
that a "preliminary risk analysis", associated with a preliminary analysis of an "emergency response plan"
should be carried out in the initial stages of the preliminary design. This analysis makes it possible to
better describe the specific features of the tunnel and the functional and safety specifications which it
must satisfy. It also contributes to a value engineering analysis, to a better design and to the technical and
financial improvement and optimisation.
These parameters and their impacts are detailed in the following paragraphs
1.2.3.2 Parameters relating to the traffic and its nature
These parameters have an impact mainly on the functional cross-sectional profile (See 1.2.2), and through
it a partial impact on the layout:
the volume of traffic affects the number of lanes, ventilation and evacuation. It also affects the
impact of breakdown vehicles and their management when stopped: requirement for a lateral
stopping lane or not, for lay-bys, and organisation of particular provisions for repair service,
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 17 / 35

PIARC ROAD TUNNELS MANUAL PIARC

the nature of the traffic, the type of vehicles and their distribution affect the evacuation concept
(cross-passages, evacuation galleries, their dimensioning, their spacing) according to the volume of
people to be evacuated,
tunnels dedicated to particular categories of vehicle relate to the width of the lanes, headroom and
ventilation,
the passage or not of dangerous goods has an important impact on the ventilation system, the
"functional cross-section", fluid collection and dewatering measures, diversion routes, the
environment of the tunnel portals or ventilation stacks, the protection of the structures against the
consequences of a major fire, as well as on evacuation and the organisation of the emergency
services and the provision of the fire brigade in specific means and material.
1.2.3.3 Evacuation of the users - access of the emergency teams
This is a fundamental parameter concerning the functional provisions and the general design. This
parameter also often affects the alignment (direct exits to outside) and construction provisions: cross-
passages - under gallery - parallel gallery - shelters or temporary refuges connected to a gallery.
Its analysis requires an integrated approach with the ventilation design (in particular the ventilation in case
of fire), volume of traffic, risk analysis, drafting of the emergency response plan (in particular
investigation of the scenarios ventilation / intervention) and construction methods.
It is necessary from a functional point of view to define the routes, their geometrical characteristics and
spacing in order to ensure the flow of able-bodied and disabled people.
It is essential to insure the homogeneity, the legibility and the welcoming and calming character of these
facilities. They are used by people in situations of stress (accident - fire), at the self-rescue stage (before
the arrival of the emergency services). Their use has to offer a natural, simple, efficient and calming
character in order to avoid the transformation of the state of stress into a state of panic.
1.2.3.4 Ventilation
Ventilation facilities designed as a pure "longitudinal ventilation" system have little impact on the
"functional cross section" or on the "alignment".
This is not the case for "longitudinal ventilation" facilities equipped with a smoke extraction duct, or for
"transverse ventilation" systems, "semi-transverse" or "semi-longitudinal" systems, "mixed" systems, or
for ventilation systems including shafts or intermediate galleries permitting to draw or to discharge air
outside other than at the tunnel portals. All these facilities have a very important impact on the "functional
cross section", the "alignment" and all the additional underground structures.
The ventilation facilities of the traffic space are essentially designed in order to :
provide healthy conditions inside the tunnel by the dilution of air pollution in order to keep the
concentrations to a level lower than those required by the recommendations of national regulations,
ensure the safety of the users in case of fire inside the tunnel, until their evacuation outside of the
traffic space, by providing efficient smoke extraction,
The ventilation facilities may also provide additional functions:
limitation of air pollution at the tunnel portals, by improved dispersal of the polluted air, or by
cleaning the air prior to its discharge outside the tunnel,
underground plants for cleaning the polluted air in order to reuse it within the tunnel. These
facilities exist in urban tunnels or in very long non-urban tunnels. They are complex and expensive
technologies, requiring a lot of space and considerable maintenance,
in case of fire, to contribute to limiting the temperature inside the tunnel in order to reduce the
deterioration of the structure by thermal effects.
The ventilation facilities do not only concern the traffic space. They also concern:
the connection galleries between the tubes,
the evacuation galleries or the shelters used by the users in case of fire,
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 18 / 35

PIARC ROAD TUNNELS MANUAL PIARC

the technical rooms or plants situated inside the tunnel or outside near the tunnel portals that may
require air renewal, or management and control of the temperature level (air heating or conditioning
according to the geographical conditions).
The ventilation facilities have to be designed in order to be able to:
adapt in a dynamic and fast way to the numerous conditions and capacities in which they are
operated in order to face :
- climatic constraints, in particular significant and fluctuating differentials of pressure between
the portals for long tunnels in mountainous areas,
- variable operating rates for smoke management in case of fire, according in particular to the
development of the fire, then its regression, as well as throughout the fire period in order to be
suited to the evolution of the fire fighting strategies at each stage of evacuation, of fire fighting,
of preservation of the structures, etc.
present enough development capacity in order to be able to adapt throughout the tunnel's life to the
evolution of the traffic (volume - nature), lowering of the admissible pollution levels and various
conditions of operation.
1.2.3.5 - Communication with the users - supervision
Communication with users has an important impact on the "functional transverse profile" through
signalling.
The other major impacts do not relate to the whole of the "complex system". They relate to the subsystem
concerning the operating equipment, in particular remote monitoring, detection, communications, traffic
management, control and supervision, as well as the organisation of evacuation.
1.2.3.6 - Particular requirements for operation
The operation of a tunnel and the intervention of the maintenance teams may require particular
arrangements in order to enable interventions under full safety conditions, and to reduce restrictions to the
traffic.
These arrangements concern for example the provision of lay-bys in front of the underground facilities
requiring regular maintenance interventions, accessibility to materials for their replacement and
maintenance (in particular heavy or cumbersome material).

1.2.4 The operating equipment
The objective of this section is not to describe in detail operation facilities and equipment, their function
or their design. These elements are defined in the recommendations of the current "Road Tunnels
Manual", as well as in the handbooks or national recommendations listed in section 1.6 below.
The objective is to draw the attention of owners and designers to the particular issues peculiar to the
equipment and the facilities of tunnel operation.
1.2.4.1 Strategic choices
The operating equipment must allow the tunnel to fill its function, which is to ensure the passage of
traffic, and to satisfy the double mission of providing for the users a good level of comfort and safety
when crossing the tunnel.
The operation facilities must be suited to the function of the tunnel, its geographical location, its intrinsic
features, the nature of the traffic, the infrastructures downstream and upstream of the tunnel, the major
issues relating to safety and to emergency organisation, as well as the regulation and the cultural and
socioeconomic environment of the country in which the tunnel is situated.
A plethora of operation facilities does not automatically contribute to the improvement of the level of
service, comfort and safety of a tunnel. It requires increased maintenance and human intervention, which,
if not implemented, may lead to a reduction in the reliability of the tunnel and its level of safety. The
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 19 / 35

PIARC ROAD TUNNELS MANUAL PIARC

juxtaposition or the abuse of gadgets is also useless. The facilities must be suited, complementary,
sometimes redundant (for the essential functions of safety), and have to form a coherent whole.
The facilities of operation are "living":
They require a rigorous care and maintenance regime, recurrent and suited to their level of
technology. This maintenance has a cost and requires skilled human resources, as well as recurrent
financial investment throughout the tunnel's life. Lack of maintenance (or insufficient maintenance)
leads to major dysfunctions, to the failing of the facilities, and as a consequence to the calling into
question of the tunnel's function and the users' safety. Maintenance of the facilities under traffic
conditions is often difficult and very restricted. Arrangements must be considered from the design
of the facilities. For this reason the "architecture" of the systems, their design and their installation
have to be thought out in order to limit the impact of the dysfunctions on the availability and the
safety of the tunnel, as well as the impact of the maintenance interventions or the renovation of the
facilities,
Their "life span" is variable: about ten to thirty years according to their nature, their hardiness, the
conditions to which they are exposed, as well as the organisation and the quality of the
maintenance. They must therefore be replaced regularly, which requires adequate financing,
Technological evolution often makes essential the replacement of facilities that include advanced
technologies, because of technological obsolescence and the impossibility of obtaining spare parts,
The facilities must show evidence of adaptability to take into account the evolution of the tunnel
and its environment.
All these considerations lead to strategic choices of which the main ones are:
To define the necessary facilities according to the real needs of the tunnel, without yielding to the
temptation of accumulating gadgets. Risk analysis combined with value engineering is a powerful
tool allowing the rationality of the choice of the necessary facilities. This approach also allows to
better master the complexity of the systems, that is often a source of delays, cost over-runs and
major dysfunctions if this complexity has not been managed by a rigorous and competent
organisation,
To give priority to the quality and the hardiness of the equipment in order to reduce the need and
frequency of maintenance and the difficulties of intervention under traffic conditions. This can
result in a higher investment cost but is compensated very extensively during the operation period,
To verify the quality and the performance of the facilities at each stage of the design, manufacture,
factory acceptance tests, installation on site and then site acceptance tests. Experience shows that
numerous facilities are deficient and do not satisfy the objectives because of lack of rigorous
organisation and efficient controls,
To choose technologies suitable to the climatic and environmental conditions, which the facilities
will have to face, as well as to the socio-cultural conditions (deficiency of the maintenance concept
in some countries), and to technological and technical conditions, as well as to the organisation of
the services,
To take into account, from the design of the facilities and the choice of the equipment, the operation
costs and in particular energy costs. These costs are recurrent throughout the tunnel's life.
Ventilation and lighting facilities are in general the highest consumers of energy. Particular
attention must be drawn to this aspect from the preliminary design stages,
To take into account from the preliminary stages of design and financing analysis:
-the necessity to implement, to organise, to learn and to train teams dedicated to operation and
intervention on the one hand, and on the other hand to cleaning and maintenance,
-the constraints of intervention under traffic conditions for maintenance,resulting operation,
maintenance and refurbishment costs,
To take into account in the general organisation and scheduling of a new tunnel project, the time
required to recruit the teams and to train them, for tests, as well as the "dry run" of all the facilities
and systems (period of 2 to 3 months), for practices and manoeuvres on site with all the external
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 20 / 35

PIARC ROAD TUNNELS MANUAL PIARC

intervening parties (in particular emergency services - fire brigade) in order to familiarise them with
the particularities of the tunnel.
1.2.4.2 - Key recommendations concerning the main facilities
1.2.4.2.a Energy - sources of power - electric distribution
For the tunnel equipment to function there must be a power sources. Large tunnels can require a power of
several MW (megawatts), which may not always be available on site. Particular arrangements must be
taken from the first stages of the design in order to strengthen and make more reliable the existing
networks, or often to create new networks. The power supply is essential for the operation of the tunnel. It
is also essential for its construction.
The supply of electric energy and its distribution inside the tunnel must provide:
the required capacity,
a reliable supply,
a reliable, redundant and protected energy distribution system: redundancy and interconnectionof
the distribution networks - transformers in parallel - cables located inside sleeves and in manholes
protected against the fire.
Every tunnel is specific and has to be subjected to a specific analysis according to its geographical
position, the context of the existing electrical networks, the energy supply conditions (priority or not
priority), the possibility of increasing or not the power and the reliability of the existing public networks,
the risks peculiar to the tunnel, as well as the conditions of intervention of the emergency services.
The facilities must be then designed consequently, and the operating procedures must be implemented
according to the reliability of the system and the choices that have been taken during the design period.
The objectives concerning safety, in case of a power supply cut are:
immediate emergency supply without interruption of all of the following safety equipment during a
period of about half to one hour (according to the tunnel and the evacuation conditions) :
- minimal lighting level - signalling - CCTV monitoring - telecommunications - data transmission
and SCADA - sensors and various detectors (pollution - fire - incidents - etc.),
- power supplies to safety niches, evacuation routes and shelters,
- this function is usually ensured by UPS systems, or diesel generators immediately able to
supply energy,
varying from tunnel to tunnel, its urban or rural location and the risks incurred, additional objectives
of MOC (Minimal Operation Conditions) can be set to assure the electrical supply of the following
equipment, as long as specific procedures are implemented during the whole duration of the power
cut. For example: emergency power supply of the ventilation system (by generators or a partial
external supply) permitting the tackling of light vehicle fires, but not truck fires: the passage of
trucks is then temporarily forbidden.
The arrangements usually implemented for the electrical power supply are as follows:
Emergency power supply from the public network:
- 2 to possibly 3 supplies from the public network grid with connections to independent segments
of the high voltage or middle voltage network. Automatic switching between "normal supply"
and "emergency supply" inside the tunnel power substation with, if required, interruption of the
power supply to some of the equipment, if the emergency external power supply is insufficient,
- no diesel generators,
- installation of a UPS emergency power supply.
No external emergency power supply:
- a single external power supply from the public network,
- diesel generators able to provide a part of the power in case of interruption of the main external
power supply, and setting up of MOC and particular operating procedures,
- installation of a UPS emergency power supply.
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 21 / 35

PIARC ROAD TUNNELS MANUAL PIARC

Full autonomy of the power supply - no external power supply available:
- the public network is not able to provide the required power, or does not have the required
reliability. The tunnel is then in complete autonomy. The energy is entirely provided by a set of
diesel generators working simultaneously. An additional generator is installed as "back up" in
case one of the generators should fail,
- possible installation of a UPS emergency power supply, if the level of reliability of the
generators is considered insufficient, or for safety reasons.
1.2.4.2.b Ventilation
PIARC recommendations are numerous in this field and constitute the essential international references
for the conception and the design of ventilation facilities.In addition to section 1.2.3.4 above, the reader
should refer to Section 8.5.
However, it must be remembered that even if the ventilation equipment constitutes one of the essential
facilities in assuring the health, comfort and safety of the users in a tunnel, it is only one of the links of the
system, in which the users, the operators and the emergency and rescue teams constitute the most
important elements by their behaviour, their expertise and their capacity to act.
The ventilation facilities alone cannot deal with all scenarios, nor satisfy all the functions that might be
assumed, especially concerning air cleaning and the protection of the environment.
The relevance of the choice of a ventilation system and its dimensioning requires lengthy experience, the
understanding of the complex phenomena of fluid mechanics in an enclosed environment, associated with
the successive stages of the development of a fire, the propagation, radiation and thermal exchanges, as
well as the development and the propagation of toxic gases and smoke.
The ventilation facilities are in general energy-consuming and particular attention must be paid to the
optimisation of their dimensioning and their operation, by using for example expert systems.
The ventilation facilities may be very complex, and their relevant management in case of fire may require
the implementation of automated systems that allow to manage and master the situation more efficiently
than an operator under stress.
As indicated in section 1.2.3.4 above, the ventilation facilities must above all satisfy the requirements for
health and hygiene during normal conditions of operation, and to the objectives of safety in case of fire.
Hardiness, reliability, adaptability, longevity and optimisation of energy consumption constitute major
quality criteria that the ventilation facilities must satisfy.
1.2.4.2.c Additional equipment to the ventilation facilities
Two types of additional equipment for ventilation are often the subject of pressing demands from
stakeholders, resident associations or lobbies:
Air treatment or air cleaning facilities,
Fixed fire suppression systems.
A. Air cleaning facilities. Section 5.1 deals with this question and the reader is invited to refer to it.
The implementation of air cleaning facilities is a recurrent demand of resident protection associations in
urban areas. These facilities, usually installed underground, are very expensive to construct as well as to
operate and maintain. They are also high consumers of energy.
Results to date are far from convincing, due in particular to important emission reductions from the
vehicles, and to the difficulty for these systems to clean the very low concentrations of pollutants that are
in the tunnel, contained in large volumes of air. Consequently, many systems installed in the last ten years
are no longer operational.
The future of air cleaning facilities is very uncertain in countries where there is more coercive regulation,
imposing more and more rigorous reductions of polluting emissions at the source.
B. Fixed fire suppression system (FFSS). Section 8.7 deals with this issue, and the reader is invited to
refer to it.
http://tunnels.piarc.org/en/strategic-issues/general-design.htm 22 / 35

PIARC ROAD TUNNELS MANUAL PIARC

The technologies are numerous and answer to varied criteria: fire fighting - containment of the fire -
reduction of thermal radiation and temperature for the users situated in the vicinity of the fire -
preservation of the tunnel structure against damage due to high temperature, etc.
These systems, even though presenting positive aspects, also present negative aspects related in particular
to the deterioration of the conditions of visibility if they are activated from the start of the fire. The use of
an FFSS requires a coherent approach to all aspects of the users' safety, as well as to ventilation and
evacuation strategy.
The decision concerning the implementation or not of such systems is complex and has important
consequences. It must be subject to a thorough reflection relating to the particular conditions of safety of
the work concerned and to the added value obtained by the implementation of the system. It should not be
taken under the influence of fashion or a lobby.
The FFSS requires the implementation of important maintenance measures, the carrying out of regular
and frequent tests, without which its reliability cannot be assured.
1.2.4.2.d Lighting
The recommendations of the CIE (International Commission for Lighting) have been criticised by PIARC
because of the high levels of lighting to which they often lead. The reader is invited to refer to the
technical report published by the European Committee of Normalization that presents several methods
including the CIE's.
Lighting is a fundamental tool to ensure the comfort and safety of the users in a tunnel. The objectives of
the lighting level must be adapted to the geographical location of the tunnel (urban or not), its features
(short or very long), to the volume and nature of the traffic.
Lighting equipment consumes a lot of power and developments are in progress to optimise their features
and performance.
1.2.4.2.e Data transmission - Supervision - SCADA
SCADA is the "nervous system" and the "brain" of the tunnel, permitting the compilation, transmission
and treatment of information, and then the transmission of the equipment's operating instructions.
This system requires a meticulous analysis according to the specific conditions inside the tunnel, its
facilities, the organisation and the mode of operation, the context of risks in which the tunnel is placed, as
well as the arrangements and procedures implemented for interventions.
The organisation of the supervision and control centre has to be analysed very carefully, according to the
specific context of the tunnel (or of the group of tunnels), the necessary human and material means, the
missions to be assumed, the essential aid brought by the automatic devices or the expert systems to the
operators in event of an incident, allowing the operators to reduce and simplify their tasks and to make
them more efficient.
The detailed design of these systems is long, delicate and requires a very rigorous methodology of
developing, of controlling by successive stages (in particular during factory tests), of testing, of globally
controlling after integration of all the systems on site. Experience shows that the numerous errors noted on
these systems come from the following gaps:
badly defined specifications, insufficient functional analysis, or ignorance of operational conditions
and procedures,
late systems development, which does not allow the time necessary for detailed analyses, transverse
integration, or to take into account the peculiar conditions of operation of the tunnel,
lack of rigour in the development, testing, control and integration of all of the systems,
lack of taking into account human behaviour and general ergonomics,
lack of experience in tunnel operation, in the hierarchy of the decisions that are to be integrated and
the logical sequences of these decisions in the event of a serious incident.
Section 8.2 of the manual sums up these different aspects.

http://tunnels.piarc.org/en/strategic-issues/general-design.htm 23 / 35

PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/general-design.htm 24 / 35

1.2.4.2.f Radio-communications - low voltage circuits
These facilities include:
emergency phone network,
radio network for the operation teams and the emergency services. Radio channels for tunnel users,
through which it is possible to transmit information and instructions related to safety,
numerous sensors destined for taking measurements and detection,
CCTV network.
an AID system (Automatic Incident Detection) is usually associated with a CCTV system. The AID
system requires an increased number of cameras in order to make detection more reliable and more
relevant.
1.2.4.2.g Signalling
Signalling refers to Section 8.9.
Even more than for the other facilities, an overabundance of signalling is detrimental to its relevance and
objectives.
The legibility, the consistency, the homogeneity and the hierarchy of signalling (priority to evacuation
signalling and information for users) have to be a priority of the signalling design inside the tunnel and on
its approaches.
Fixed signage panels, traffic lanes signals, variable messages signals, traffic lights and stopping lights,
signalling to emergency exits, the specific signalling of these exits, signalling of safety niches, physical
devices for closing the lanes (removable barriers),horizontal markings and horizontal rumble strips are all
part of the signalling devices. They assure a part of the communication with the users.
1.2.4.2.h Devices for fire fighting
The devices for fire detection are either localised (detection of fire in the underground substations or the
technical rooms), or linear (thermal sensing cable) inside the traffic space.
There are various devices for fire fighting:
automatic facilities in the technical rooms and underground substations,
powder extinguishers for use by drivers,
facilities for firemen: water pipe and hydrants - foam pipe in some countries. The volume of the
water tanks is variable. It depends on the local regulations and the particular conditions of the
tunnel.
Some tunnels have an FFSS (see 1.2.4.2.c above).
1.2.4.2.i Miscellaneous equipment
Other equipment may be installed according to the objectives and needs concerningsafety, comfort and
protection of the structure. Some examples are:
luminous beacons inserted in the side walls or walkway kerbs,
a hand rail or a "life-line" fixed on the side wall permitting the movement in safety of firemen in a
smoke-filled atmosphere,
painting of the side walls or the installation of prefabricated panels on the side walls,
devices for the protection of the structures against damage resulting from a fire. Such protective
arrangements have to be taken into account from the origin of the project. Thermal exchanges (with
the concrete lining or with the ground) are indeed modified during a fire, as well as air
characteristics, which must be designed for when dimensioning the ventilation facilities,
management and treatment of water collected on the road pavement inside the tunnel before
discharge outside in the natural environment,
arrangements for the measurement of environmental conditions at the tunnel portals, associated with
particular operational procedures if the limits defined by the regulations are exceeded.
PIARC ROAD TUNNELS MANUAL PIARC

1.3. Renovation upgrading of existing tunnels

The upgrading (in particular for safety improvement) and refurbishment of existing tunnels in operation
gives rise to specific problems of analysis and method. The degree of freedom is less than for new tunnels,
because it is necessary to take into account the existing space and constraints. The technologies peculiar to
each type of equipment and their integration are however identical.
The renovation and upgrading of a tunnel under operation quite often result in an increase of the
construction schedule and costs, in much lower safety conditions during the works, and with badly
controlled impacts on the traffic volume and conditions. These disadvantages are often the result of an
incomplete analysis of the existing situation, the real condition of the tunnel, its facilities and its
environment, as well as of a lack of strategy and procedures that would mitigate the effects on the traffic.
Section 2.8 proposes a methodology for the safety diagnosis of existing tunnels and the development of an
upgrading programme. In addition, Section 4.9 presents specific issues related to works carried out on
tunnels in operation. Their dispositions help mitigate the problems mentioned above.
It however appears appropriate to draw the reader's attention to the key points of the following sections.

1.3.1. Diagnosis
Detailed and rigorous diagnosis of a tunnel is an essential stage in the process of its upgrading or
renovation. Unfortunately this stage is often neglected.
The physical diagnosis of a tunnel requires:
to establish in detail and to describe in a precise manner the functions and the geometry of the
structure,
to establish a detailed condition statement of the structure. To evaluate in particular fire resistance,
uncertainties and potential risks, and to list the tests that would be needed in order to provide a solid
basis for the detailed design,
to list all existing equipment, their functions, their condition, their technology, their actual features
(tests or measurements will be required) and the stock of spare parts that might be available,
to evaluate the remaining life span of the aforementioned equipment before their replacement, and
to identify the availability or not of spare parts on the market (notably because of the technological
obsolescence),
to identify maintenance and inspection reports, equipment malfunctions and the rate of breakdowns.
This physical diagnosis must be supplemented by a diagnosis concerning the organisation, maintenance
and operation procedures, as well as by a specific diagnosis concerning all documents relating to the
organisation of safety and rescue interventions. This stage of diagnosis may eventually lead to the setting
up of actions for the training of the various intervention parties in order to improve the global conditions
of safety of the tunnel in its initial state prior to renovation.
The diagnosis must be followed by a risk analysis of the tunnel based on its actual state. This analysis has
a double objective:
to assess if the tunnel can continue to be operated in its present state prior to renovation, or if it is
necessary to take temporary transitional arrangements: restriction of access to some vehicles only -
strengthening of the arrangements for surveillance and intervention - additional equipment - etc.,
to constitute a referential of the existing state from the point of view of safety in order to refine the
definition of the renovation programme.
The diagnosis has to identify (without running the risk of late discoveries during the works period) if the
existing facilities, supposedly in working condition, can be modified, be added to or integrated in the
http://tunnels.piarc.org/en/strategic-issues/renovation-upgrading.htm 25 / 35

PIARC ROAD TUNNELS MANUAL PIARC

future updated facilities (technological compatibility - performance in particular for data collection and
transmission, automatic functioning devices and SCADA).

1.3.2. Renovation or upgrading programme
The renovation or upgrading programme proceeds from two stages.
1.3.2.1. First stage: programme development
The development of the programme results from:
the detailed diagnosis as described above,
the risk analysis developed considering the initial state of the tunnel,
the gaps noted concerning safety,
the analysis of what it is possible to achieve in the existing spaces and their potential enlargements
in order to enable the upgrading of the tunnel.
Depending on the physical environment of the tunnel and the spaces available, the optimum upgrading
programme for the infrastructure or equipment may not be feasible under acceptable conditions, and that
it is necessary to define a more restricted programme. This restricted programme may require the
implementation of mitigating measures ensuring that the required level of safety is achieved in a global
sense, after completion of the works.
1.3.2.2. Second stage: validation of the programme
The validation of the programme requires:
development of a risk analysis based of the final state of the tunnel after upgrading in order to test
the new arrangements introduced by the programme. This analysis has to be established with the
same methodology that the one used for the prior analysis based on the initial state. It also enables a
search for optimisations,
detailed examination of the feasibility of the works to be carried out for the improvement or the
renovation under the requisite conditions of operation: for example, banning of tunnel closure or of
temporary traffic restrictions. In case of incompatibility between the objectives of the programme
and the works required for its application, iteration is necessary. This iteration may concern :
- the programme itself, insofar as adaptation of the programme is compatible on the one hand
with the safety objectives, and on the other hand with its implementation in the required
conditions of operation,
- the required conditions of operation that it may necessary to modify in order to be physically
able to carry out the works resulting from the upgrading programme.
The upgrading or improvement programme does not necessarily require physical works. It may only
consist in a modification of the functions of the tunnel, or of the operating arrangements, for example:
modification of the category of the vehicles authorised to access the tunnel: no access to trucks no
access to vehicles carrying dangerous goods,
setting up of specific procedures for traffic restriction: in a permanent way or only during peak
traffic,
tunnel operated initially in bi-directional traffic, transformed for the implementation of
unidirectional traffic,
modification of the means for supervision or intervention.

1.3.3. Design implementation and construction
The stage of design implementation and construction involves translating the renovation or upgrading
programme into technical and contractual specifications and implementing it.
This stage requires a very detailed analysis of:
http://tunnels.piarc.org/en/strategic-issues/renovation-upgrading.htm 26 / 35

PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/strategic-issues/renovation-upgrading.htm 27 / 35

the successive stages of construction, the content of each of these stages, the logical and priority
sequences of the works,
safety conditions inside the tunnel at each construction stage. This requires partial risk analyses and
the implementation if necessary of mitigation arrangements: traffic regulation traffic restrictions -
patrol strengthening of the intervention means - etc.
traffic conditions inside the tunnel and on its approaches, with partial and temporary restrictions
according to the various stages of works (different arrangements for daytime and night-time, for
normal periods and vacation periods), of the potential diversions, of the global impact on the traffic
and safety conditions in the areas concerned by the works,
the constraints and subjections, the partial and global contractual deadlines for the works, in order to
be able on the one hand to define the contractual specifications for the contactor, and on the other
hand to implement all necessary temporary arrangements, and to proceed to an information
campaign for the users and residents.
PIARC ROAD TUNNELS MANUAL PIARC


http://tunnels.piarc.org/en/strategic-issues/stages-tunnel-life.htm 28 / 35

1.4. Stages of the "tunnel life"

Arbitrarily the "tunnel life" may be broken down in several main stages whose essential stakes are:

1.4.1. Design
This is the most important stage of the life of a new tunnel. It is decisive in terms of construction and
operation costs, safety, as well as management of the technical and financial risks.
This stage requires a transverse integration of all interfaces of the complex system" that constitutes a
tunnel. This integration has to start from the earliest stage of the design (see paragraphs above).
Experience testifies to the fact that this is unfortunately rarely the case and that often the design of a
tunnel results from a succession of stages considered as independent. Albeit caricaturising, we can note
that:
the function is not always clearly defined,
the alignment is designed without any integration of the tunnel, of its constraints, or of the whole set
of optimisation possibilities,
the civil engineering manages with the set horizontal and vertical alignments, with all the
consequences that can result concerning the construction costs and risks,
the equipment, safety level and operation fit in somehow and not always harmoniously or optimally
with the arrangements chosen during the previous stages.

1.4.2. Construction
For what concerns Civil engineering, the most important aspect is the management of technical risks (in
particular geological) and of all the resulting consequences concerning construction costs and duration.
Considerations relating to risk management for the construction have to be taken into account from the
design. These considerations must be detailed and shared with the owner of the tunnel. Decisions
concerning the risks must be developed and clearly documented.
The decision to take some risks does not necessarily constitute a mistake and must not necessarily be
forbidden, because as a result some imperatives may be met, for example concerning a tight schedule,
which would be incompatible with the implementation of all the investigations that would be required to
eliminate all uncertainties.
However the decision to take a risk must result from a very detailed reflection concerning:
consequences that may result, which must be clearly identified, analysed and consigned: delays -
costs - human and environmental impacts safety schedule etc.,
the real issues of this decision, its probability of success and its real interest.
Taking of a risk must not be the result of carelessness or incompetence on the behalf of the various parties.
For what concerns Operational facilities, the readers attention is drawn to:
all aspects likely to optimise the life span of the equipment, its reliability and ease of maintenance,
the need of rigorous process and continuous control of the functionality, performances and quality
of the equipment throughout the manufacture of the components, their assembly, their installation
on the site, then at the time of partial and global testing after integration,
the added bonus to quality concerning the choice of the equipment and the contractor, even though
the construction costs may be a somewhat higher. Possible savings due to reduced initial costs are
often quickly compensated for by higher maintenance costs, difficulties of intervention under traffic,
and the additional constraints that would be suffered by the users.

PIARC ROAD TUNNELS MANUAL PIARC


http://tunnels.piarc.org/en/strategic-issues/stages-tunnel-life.htm 29 / 35

1.4.3. Commissioning
This stage of "tunnel life" is often under-estimated and taken into account tardily. It requires taking time
that is not often granted, and leads to the commissioning of the tunnel under unsatisfactory conditions, or
even under conditions that are highly exposed in terms of safety.
This stage includes:
the organisation of the operation and maintenance,
development and adjusting of all procedures of operation, maintenance, intervention and safety
under the normal conditions of tunnel operation, as well as under MOC (Minimal Operation
Conditions),
recruitment and training of the staff,
the dry run" of all the facilities, that cannot take place before the equipment has been fully
completed, tested and delivered (possibly with provisions requiring only minor corrective
interventions),
the practice, training and manoeuvres involving all the intervention teams and services before
commissioning the tunnel.

1.4.4. Operation
The main mission is to ensure:
the management of all facilities, their maintenance, their restoration,
the safety and the comfort of the users.
It is also necessary to be able to look at the situation objectively with a distance to the daily routines in
order to:
establish feedback from experience, adapt the procedures, the conditions of intervention, the
training and the manoeuvres for safety,
optimise operation costs without damaging the level of service and safety,
identify, analyse, plan and achieve heavy repairs, and renovation and upgrading works.
PIARC ROAD TUNNELS MANUAL PIARC


http://tunnels.piarc.org/en/strategic-issues/costs.htm 30 / 35

1.5. Costs of construction, operation, upgrading - financial aspects

1.5.1. Foreword
Tunnels are relatively expensive civil engineering structures with respect to their construction and
operation. Particular attention must be paid from the beginning of the project in order to spot any possible
technical and financial optimisations.
It is recommended from the first stages of the design to implement a process including:
the detailed definition of the "function" of the tunnel,
an iterative process of value engineering analysis" achieved at all strategic stages of the project, to
which must be integrated into the various stages of the risk analysis,
detailed analysis and monitoring of the potential risks in the design and construction stages. These
potential risks are related to:
- technical uncertainties relating in particular to the complexity of the ground (geological and
geotechnical uncertainties),
- uncertainties of traffic volume forecasts, that constitute an important risk concerning earnings in
the case of construction and financing by concession",
- uncertainties and risks concerning the financial environment, in particular changes in interest
rates and conditions of financing and refinancing. This aspect constitutes an important risk in
the case of construction and financing by "concession" or by PPP (Private Public Partnership)
with a financial contribution.
This process will enable the optimisation of the project (construction and operation costs) and an
improved management of the technical and financial risks, as well as the schedule.

1.5.2. Construction costs
1.5.2.1. Cost ratios per kilometre
The construction costs of tunnels are very variable and it is impossible to give representative ratios of
costs per kilometre, because these ratios may vary in important proportions (average of 1 to 5) according
in particular to:
the geological conditions,
difficulties concerning the access roads and the tunnel portals,
the geographical location of the tunnel: urban or non-urban,
the length of the tunnel: in particular the "weight of the ventilation facilities and safety
arrangements is more significant for a long tunnel; on the other hand all the works concerning the
access roads and portals have a more important impact for a short tunnel,
the traffic volume which is a determining factor for the dimensioning of the number of lanes, as
well as for the ventilation facilities,
the nature of the traffic: in particular a tunnel used by vehicles carrying dangerous goods will
require expensive arrangements for ventilation, safety and possibly the resistance of the structure to
fire; conversely, a tunnel dedicated to the passage of only light vehicles may enable very important
savings because of the possible reduction of the width of the lanes, headroom and reduced
requirements for the ventilation facilities,
the tunnel environment that may lead to expensive protection arrangements for the mitigation of its
impact,
arrangements taken for the management or the sharing of construction risks,
the socioeconomic environment of the country in which the tunnel is to be constructed. The impact
can reach about 20% of the costs.
At most it is possible to indicate that the average cost of a usual tunnel, built under average geotechnical
conditions is about ten times the cost of the equivalent infrastructure built in open air (outside of urban
areas).
PIARC ROAD TUNNELS MANUAL PIARC


http://tunnels.piarc.org/en/strategic-issues/costs.htm 31 / 35

1.5.2.2. Breakdown of the construction costs
The construction cost of a tunnel may be broken down into three types of cost:
the cost of the civil engineering structures,
the cost of the operation facilities, including the supervision centre and the energy supply from
public networks,
various costs including in particular: owners costs for the development of the project project
management design and site supervision survey and ground investigations - environmental
studies and mitigation measures land acquisitions - various procedures - etc.
The two diagrams below show examples of the breakdown of construction costs, on the one hand for
tunnels for which the conditions of the civil engineering works are not complex, and on the other hand for
tunnels for which the conditions of the civil engineering works are less favourable.








Fig. 1.5.1: Breakdown of construction costs
Note: these two diagrams show how important the costs are of the civil works and illustrate the
consequences of an almost doubling the costs of civil works (right-hand diagram).

1.5.3. Operation costs
The operation costs of a tunnel may be broken down into three types of cost:
the operation costs as such, which essentially include staffing, energy, as well as the management
and expendable equipment. These are recurrent costs;
the recurrent yearly costs of maintenance;
the costs of heavy repairs, as well as the replacement costs of the equipment according to its life
span and its state during the tunnel life. These costs are not recurrent and depend on the equipment,
its quality and the conditions of maintenance, from the tenth or twelfth year after the start of the
operation period.
The two diagrams below represent examples of breakdown (with constant economic conditions) of the
construction costs (civil works, operation facilities, various costs) and of the global operation costs
(accumulated over a duration of thirty years after the start of the operation period).
Note: these diagrams show how important the operation and maintenance costs are and how it is
necessary to choose from the first stages of the tunnel design the arrangements that enable the
optimisation of the recurrent operation and maintenance costs.
n o p a r t i c u l a r c o m p l exi t y f o r c i vi l en g i n eer i n g
70%
15%
15%
civil
engineering
operation
facilities
various
breakdown of the construction costs
bb
d i f f i c u l t c o n d i t i o n s f o r c i vi l en g i n eer i n g
84%
7%
9%
civil
engineering
operation
facilities
various
breakdown of the construction costs
PIARC ROAD TUNNELS MANUAL PIARC


http://tunnels.piarc.org/en/strategic-issues/costs.htm 32 / 35









Fig. 1.5.2: Breakdown of the costs during a 30-year period

1.5.4. Costs of renovation and upgrading
This chapter concerns the renovation or upgrading works that are required for upgrading to new
regulations. The works concern the arrangements for evacuation, the resistance of the structure to fire, the
operation and safety facilities, and all the requirements to satisfy the new safety regulations.
It is not possible to give statistical prices due to the diversity of existing tunnels, their condition, their
traffic and the more or less important requirements of new safety regulations that may vary from one
country to another.
The observations made in France for this nature of upgrading works for complying with the new
regulations, which have been carried out since the year 2000, show a large variation of the corresponding
budgets with a range of costs between about ten million Euros and several hundred million Euros (there
have been several upgrading programmes with a budget of more than 200 million Euros).

1.5.5. Aspects relating to financing
Tunnels constitute costly infrastructure in terms of construction and operation, but this is offset by
economic benefits including regional development, traffic fluidity, comfort, safety, reliable routes
(mountain crossings) as well as protection of the environment.
Financing of these works is ensured either by:
the traditional mode: financing and maintenance by a public authority, the financial resources
coming then from public taxation or fuel taxes,
a "concession" to a private or semi-public body, which is charged with the construction and the
operation of the tunnel during a contractual period of time. This body is in charge of the financing
(often partly by loan), which is offset by a toll paid by the users, that reimburses the costs of the
construction and the operation, as well as the risks and the financial expenses. This type of
"concession" can be granted by the financial involvement of the grantor or by particular guarantees
(example: guarantee of a minimal traffic volume with the payment of a financial compensation if
this minimal traffic volume is not reached),
mixed mode of PPP (Public Private Partnership) or similar, that may concern:
- only the construction or the construction and the operation,
- construction under a turnkey scheme in the case of a design and build process,
- partial or whole financing.
The present manual does not intend detailing these various modes of financing, or presenting their
mechanisms, their advantages or disadvantages. However it is interesting to present some main guidelines
found from experience, which give a preliminary illustration.
d i f f i c ul t c ond i t i ons f or c i vi l eng i neeri ng
80, 0%
5, 5%
6, 0%
8, 5%
construction
operation
maintenance
heavy repairs
no p art i c ul ar c om p l exi t y f or c i vi l
eng i neeri ng
71%
8%
9%
12%
construction
operation
maintenance
heavy repairs
PIARC ROAD TUNNELS MANUAL PIARC


http://tunnels.piarc.org/en/strategic-issues/costs.htm 33 / 35

a) Financing by a public authority
This mode of financing is employed widely. It allows the development of an infrastructure project,
whose financing could not be achieved by a concession (by lack of sufficient income from toll
collection), or when there is political will to avoid a toll.
It requires however that the public authority has the financial capacity to ensure this financing, or
that it has the capacity to borrow money and to support a debt. The financial resources essentially
come from public taxation or fuel taxes and sometimes partially from toll collection.
b) Financing by concession tunnel part of a global infrastructure
The financing of a non-freestanding tunnel by a concession (with or without financial involvement of
the grantor) is the general case for a tunnel that is part of a new interurban highway with toll collection.
The costs (construction and operation) of the tunnel are shared out among the tunnel and the linear
infrastructure above ground. Experience shows that the over-cost of the average toll ratio per kilometre is
accepted by the users as long as the new infrastructure brings sufficient added value concerning time
savings, better or more reliable service, comfort and safety.
c) Financing by "concession" - isolated tunnel
Two main categories of isolated tunnels exist.
Tunnels corresponding to a major improvement of the traffic conditions. This is in particular the
case of urban tunnels aiming to alleviate traffic and to reduce travel times. Experience shows that
financing by concession is only really foreseeable when the following conditions are met:
- high traffic volumes,
- country with high standard of living and revenues, enabling substantial toll rates, which are
essential to ensure the financial balance,
- Significant time gains for the users so that they will accept in return a relatively high toll rate,
- duration of the concession of about fifty years at least.
Regional development tunnels, intended to cross a major natural obstacle (chain of mountains -
estuary). These obstacles constitute an important handicap for trade. The initial traffic volume is
usually relatively low. The new link with the tunnel will enable the growth of traffic, but such a
development is often very difficult to predict in advance, and it constitutes an essential parameter of
financial risk for the funding of the concession. Experience shows that financing by "concession" is
then only realistic when the following conditions are met:
- The natural obstacle is significant and the tunnel is sufficiently attractive (gain of time, level of
service, delivered service, reliability of the link) in order to attract all existing traffic in spite of
the toll,
- Financial involvement of the grantor (possibly also the stakeholders), either with a financial
contribution or direct involvement in the construction and the financing of a part of the works
(for example construction of the access roads),
- Guarantee of a minimal traffic volume by the grantor, with the payment of a contractual
financial contribution if the minimal traffic volume is not reached,
- Contractual arrangements for sharing major risks can put the financial model at risk if they
over-run limits or conditions defined by the contract,
- Very long concession duration: often 70 years or more,
- Financial guarantee brought by the grantor, in order to enable the concession body to benefit
from more favourable conditions of loans on the financial market, which may better ensure the
feasibility of the financial plan.
d) Financing by PPP or similar
The range of contents of a PPP mode is very wide, and it is difficult to establish guidelines because
of the scope of possibilities.
This mode of financing commits public authorities to financial contribution in the long term.
Detailed analysis is necessary to evaluate the real advantage of this mode of financing compared to
traditional financing. Indeed, this mode of financing very often contributes to increasing the global
PIARC ROAD TUNNELS MANUAL PIARC


http://tunnels.piarc.org/en/strategic-issues/costs.htm 34 / 35

cost of the project (with equal functionality and quality) because of the compensation of the risk
assumed by the developer.
Public authorities have to carefully define the required functions of the tunnel, as well as objectives
concerning quality, comfort, safety, level of service, life span, rate of availability, penalties etc. in
order to prevent any ambiguity that may result in important misunderstandings and financial
overruns in the development of the project.
PIARC ROAD TUNNELS MANUAL PIARC

1.6. Regulations - Recommendations

Countries that have many tunnels are endowed with regulations and have developed recommendations
and guidelines for the design, construction, operation, maintenance, safety and the intervention of the
rescue services.
Concerning safety conditions in road tunnels, countries belonging to the European Union are subjected to
Directive 2004/54/CE that prescribes a minimum level of arrangements to be implemented in order to
ensure the safety of users in tunnels longer than 500 m that are part of the trans-European road network. A
wider group of European countries are also bound by an international convention, The European
Agreement concerning the International Carriage of Dangerous Goods by Road (ADR) and includes
specific arrangements for tunnels. Every member country has transposed these European regulations to its
own national legislation. Some member countries have implemented additional regulations that are more
demanding than the one that results from the transposition of the European regulation.
A list of the regulations and recommendations concerning the operation and the safety of road tunnels has
been established in cooperation between the PIARC and the ITA Committee on Operational Safety of
Underground Facilities (ITA-COSUF) of the international tunnelling and underground space association
(ITA - AITES). This document can be consulted on the ITA-COSUF web site. This list is not exhaustive
but presents an international panel of twenty-seven countries and three international organisations.
Many countries do not have any regulations relating to tunnels and to tunnel safety, because they do not
have road tunnels within their territory. It is recommended that these countries choose a complete and
coherent package of the existing regulations of a country with lengthy experience in the field of tunnels,
and not to multiply the origins of the documents by dipping into different sources. The recommendations
of PIARC, as summarised in the present manual, as well as those of European directive 2004/54/CE also
constitute international references that are being applied increasingly often.

http://tunnels.piarc.org/en/strategic-issues/regulations-recommendations.htm 35 / 35









ROAD TUNNELS MANUAL




2. SAFETY










All rights reserved. World Road Association (PIARC)

PIARC ROAD TUNNELS MANUAL PIARC

2. Safety

With the increasing number of tunnels under construction or in planning throughout the world, and the
growing volume of traffic using existing tunnels, safety issues are becoming increasingly important.
Incidents and accidents in road tunnels may be no more frequent than those on the open road, indeed
road tunnels can provide a safer, more controlled driving environment for road users. However, the
consequences of major incidents in the confined tunnel environment are potentially significantly more
severe than on the open road and usually raise stronger reactions from the public.

In a modern road tunnel, safety is assured by taking an integrated approach. Sets of well developed
tools - like risk assessment, safety inspections and safety procedures - are available to help achieve
the safety objectives from the initial planning and design stages of a new tunnel, through to the
operation and upgrading of existing tunnels."

An appropriate level of safety for tunnels that is comparable with that on the open road is achievable
through a structured and integrated approach to the design and operation of tunnels that focuses on the
prevention of serious incidents and the mitigation of consequences through the encouragement and
facilitation of self rescue in the first instance and the subsequent effective intervention of the
emergency services.
Accident in a bidirectional road tunnel (Video)

If you can not see this video, click here to load the video file.
Important lessons can be learned from the experience of past tunnel incidents, these are discussed in
Section 2.3. Previous tunnel incidents have led to an increased international awareness and interest in
tunnel safety impacts; indeed, following the report of the investigation after the Mont Blanc fire in
1999, a number of countries throughout the world initiated a review and update of national standards
and guidelines for tunnel safety.
The United Nations Economic Commission for Europe (UNECE) established a group of experts on
road tunnel safety, with PIARC representation, which produced Recommendations in 2001 on all
aspects of road tunnel safety. These recommendations have contributed to the development and update
of international standards for tunnel safety. In Europe, the European Commission prepared a Directive
on minimum safety requirements for road tunnels on the Trans European Road Network which entered
into force in 2004.
http://tunnels.piarc.org/en/safety/ 2 / 17
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/safety/ 3 / 17
Action has also been taken in other parts of the world. In the USA, the national standard for fire safety
in road tunnels (NFPA 502) has undergone a periodic update, taking account of developments through
research and learning from past tunnel incidents.
The minimum requirements set out in the European Directive relate to tunnels that are on the Trans
European Road Network. In countries throughout Europe and elsewhere, the regulations and
requirements for tunnel safety may be more onerous than the requirements of the Directive. Such
standards may be derived to account for the particular circumstances in the individual countries and to
deal with tunnels that are not governed by the Directive, such as particular urban tunnels for example.
The PIARC Technical Committee on Road Tunnel Operation has advanced the main issues regarding
tunnel safety through the publication of a series of reports under dedicated Working Groups. In
addition to its own activities and the legislative developments, a number of research projects and
thematic networks, mainly in Europe, have contributed to the knowledge and understanding of the
principles of tunnel safety and guided the tunnels community to the conclusion that there is a need for
an integrated approach to road tunnel safety. These general principles are the subject of Section 2.1 of
this Manual and the integrated approach is addressed in Section 2.2.
More details on the international cooperative efforts aimed at better understanding and improving
tunnel safety can be found in the following documents:
"Fire safety in tunnels" special issue Routes/Roads 324 (Oct. 2004) (8,65 MB)
Initiatives since 2000 on road tunnel safety in Chapter 2 "Recent initiatives on road tunnel
safety" of report 2007R07
Appendix A "International projects and networks" of report 2007R07
Further to these activities, PIARC supports the Committee on Operational Safety of Underground
Facilities (ITA-COSUF) of the International Tunnel and Underground Space Association (ITA) as an
international network for exchange of experience and promotion of safety.
Key to the integrated approach to road tunnel safety is the establishment of safety level criteria, the
analysis of safety and the evaluation of the balance between the costs and the benefits to achieve an
acceptable level of safety. Fundamental to this is risk assessment, an essential tool for tunnel safety
management, discussed in Section 2.4.
Of particular importance and requiring particular attention in the analysis and evaluation of tunnel
safety are fires in tunnels, discussed in Section 2.5 and the transport of dangerous goods, discussed in
Section 2.6.
To maximise the effectiveness of tunnel safety management, certain tools are needed to support
strategy, to drive critical decisions and keep a constant and traceable view of all safety issues over a
tunnel's lifetime. The three major tools regarding tunnel safety management are the Safety
Documentation; the Collection and Analysis of Incident Data and Safety Inspections. These are
described in some detail in Section 2.7.
New requirements regarding safety, as well as increase in traffic, lead to upgrading existing tunnels.
This raises specific problems which are examined in Section 2.8.

Contributors
Input to this Chapter was coordinated by Working Group 2 of the C4 committee (2008-2011) in
which:
Didier Lacroix (France), former president of the committee, supervised the writing of the
chapter and reviewed the French text
Gary Clark (UK), reviewed the English text and authored Sections 2.0, 2.1 and 2.2
Alejandro Snchez Cubel (Spain), authored Sections 2.3 and 2.7
Bla Luin (Slovenia) and Bernhard Kohl (Austria), authored Sections 2.4 and 2.6
Ignacio del Rey (Spain)and Fathi Tarada (UK) from WG4, authored Section 2.5
Jerome NKaoua (France) authored Section 2.8.
PIARC ROAD TUNNELS MANUAL PIARC

2.1. General principles

The management of safety has particular challenges in road tunnels where hazards of moving vehicles
carrying loads are significant and the outcome of serious incidents may be significantly affected by
human behaviour which can be difficult to predict (Chapter 3). A'holistic' approach is necessary to
take into account all aspects of the system consisting of the infrastructure, operation, emergency
services, road users and vehicles.
The first step in the assessment of requirements is to define the safety objectives. These are normally
established at a national level in compliance with national laws, regulations and national standards
with safety provisions being a function of the specific characteristics of the tunnel and the associated
risk as defined through analysis and evaluation. Risk analysis and the evaluation of the acceptability of
risk are addressed in Section 2.4 of this Manual.
The fundamental principle to be followed is that in the event of an emergency in a tunnel, tunnel users
will self-rescue. After the self-rescue phase of an emergency, the fire and rescue services will
intervene to fight the fire and assist any remaining tunnel users that are unable to self-rescue.
Safety objectives may be defined in various ways but the work of PIARC, the UNECE and the
European Union agree on the broad definition of objectives as being:
to prevent critical events, and
to reduce the consequences of accidents.
Integrated safety for tunnels (Section 2.2)
requires that attention be given to both of
these two objectives. Such an approach
may be presented as a "safety circle" from
pro-action and prevention through to
mitigation, intervention and evaluation;
and back to pro-action, as shown in Fig.
2.1-1. More information on the objectives
and general principles of safety is given in
Chapter 3 "General principles" of report
2007R07.
Actions aimed at meeting safety objectives
and reducing risk may be classified in the
following categories: Fig. 2.1-1: Safety circle
Tunnel user behaviour (Chapter 3)
Operational and management measures (Chapter 4)
Tunnel geometry (Chapter 6)
Tunnel structural facilities (Chapter 7)
Tunnel equipment (Chapter 8)
Information regarding each of the above topics is given in the relevant chapters of this manual as
shown above. General information on the choice of safety measures can be found in the following
documents:
Chapter 2 "Safety concepts for tunnel fires" of report 05.16.B
Technical report 05.13.B "Good Practice for the Operation and Maintenance of Road Tunnels"
Chapter 4 "Safety practices" of report 2007R07
Technical report 2008R15 "Urban road tunnels - Recommendations to managers and operating
bodies for design, management, operation and maintenance"
Chapter 5 "Recommended additional measures to prevent escalation of critical traffic conditions
in road tunnels" of report 2008R17
http://tunnels.piarc.org/en/safety/general-principles.htm 4 / 17
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/safety/general-principles.htm 5 / 17
The aim of safety planning and implementation is to achieve the right balance between the optimal
safety level provision and the reasonable construction and operating costs. This may be achieved by
taking an integrated approach to tunnel safety (Section 2.2).
PIARC ROAD TUNNELS MANUAL PIARC

2.2. Safety elements and integrated approach

Safety is not the simple adoption of all possible safety measures but is the consequence of a
balance between the forecast risk factors and the safety measures.
With the establishment and development of international regulations, recommendations and
guidelines, there is a need for a framework within which all aspects of tunnel safety are taken
into account. Such a framework may contain the following principal elements:
Safety level criteria (regulations & recommendations)
Infrastructure and operational measures
Socio-economic and cost-benefit criteria
Safety assessment techniques (safety analysis and evaluation)
Road tunnel usage
Stage of tunnel life (planning, design, construction, commissioning, operation,
refurbishment, upgrade)
Operating experience
Tunnel system condition
These safety elements are described in the Chapter 5 "Elements in an integrated approach" of
report 2007R07.
Fig. 2.2-1: Integrated approach

An integrated approach is
a framework to plan,
design, construct and
operate a new tunnel or an
upgrade to an existing
tunnel, fulfilling the
required safety levels at
each stage of the tunnel
life. This should take place
in accordance with a
safety plan, following the
right safety procedures.
The opposite figure shows
a schematic representation
of a proposed integrated
approach for the safety of
new and in-service
tunnels, comprising the
elements listed above
(figure from Chapter 6
"Conclusion" of report
2007R07.
http://tunnels.piarc.org/en/safety/integrated-approach.htm 6 / 17
PIARC ROAD TUNNELS MANUAL PIARC

2.3. Experience from past tunnel incidents

Information on incidents and accidents in tunnels, as well as lessons drawn, have been addressed by
various reports of the PIARC Committee on Road Tunnels. Earlier reports present a statistical census
of breakdowns, accidents and fires in selected tunnels, as well as the lessons to be drawn from such
events for the geometric design of the tunnel, the design of the safety equipment and the operating
guidelines - thus presenting a collection of data of vital importance to engineers and decision-makers
involved in tunnel design :
Technical report 05.04B "Road Safety in Tunnels"
Chapter 2 "Fire risk and design fires" of report 05.05B :
Chapter 2 "Information on previous large tunnel fires" of OECD/PIARC report on Transport of
Dangerous Goods through Road Tunnels :
Appendix 12.1 "Norwegian incident and accident statistics" of report 05.16B :
The incidents of Mont Blanc, Tauern and St. Gotthard (1999 and 2001) led to an increased awareness
of the possible impact of accidents in tunnels. The likelihood of escalation of accidents into major
events is low, however the consequences of such incidents can be severe in terms of victims, damage
to the structure and impact on the transport economy.
Year Tunnel Lenght Nbr Tubes Casualties
1978 Velsen (The Netherlands) 770 m 2 5 fatalities and 5 injured
1979 Nihonzaka (J apan) 2 km 2 7 fatalities and 2 injured
1980 Sakai (J apan) 460 m 2 5 fatalities and 5 injured
1982 Caldecott (USA) 1,1 km 3 7 fatalities and 2 injured
1983 Pecorile (near Genova, Italy) 660 m 2 9 fatalities and 22 injured
1996 Isola delle Femmine (Italy) 148 m 2 5 fatalities and 20 injured
1999 Mont-Blanc (France-Italy) 11,6 km 1 39 fatalities
1999 Tauern (Austria) 6,4 km 1 12 fatalities and 40 injured
2001 Gleinalm (Austria) 8,3 km 1 5 fatalities and 4 injured
2001 St. Gotthard (Switzerland) 16,9 km 1 11 fatalities
2006 Viamala Tunnel (Switzerland) 750 m 1 9 fatalities and 6 injured
Table 2.3-1: Fires in road tunnels with 5 or more fatalities (due to fire or preceding accident) since
1950
A more complete table can be found on Table 2.1 "Serious fire accidents in road tunnels" of report
05.16.B.
These catastrophes demonstrated the need for improving preparation for, as well as preventing and
mitigating, tunnel accidents. This can be achieved by the provision of safe design criteria for new
tunnels, as well as effective management and possible upgrading of in-service tunnels, and through
improved information and better communications with tunnel users. Conclusions drawn from the
enquiry following the Mont Blanc tunnel fire were that fatal consequences could be greatly reduced
by:
a more efficient organisation of operational and emergency services (harmonised, safer and
more efficient emergency procedures, specifically for cross-border operation),
http://tunnels.piarc.org/en/safety/experience.htm 7 / 17
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/safety/experience.htm 8 / 17
more skilled personnel,
more effective safety systems and
greater awareness among users (car and truck drivers) on how to behave in emergency
situations.
A detailed description of the Mont Blanc, Tauern and St. Gothard accidents including the original
configuration of the tunnels, and a step-by-step guide to the accident, fire progression, and the
behaviour of operators, emergency services and users, as well as the lessons to be drawn can be
found in Chapter 3 "Lessons learned from recent fires" of report 05.16.B : . The lessons learnt are
summarised in Table 3.5 of this report. Similar information is given in Routes/Roads 324 "A
comparative analysis of the Mont-Blanc, Tauern and Gotthard tunnel fires" (Oct. 2004) on p 24.
After the accident of march 24
th
1999, the Mont Blanc tunnel required significant renovation before it
was able to be reopened to traffic. The ventilation system comprised a significant portion of the
rehabilitation design work - a description of the dimensioning, automatic operation and full-scale fire
tests can be found at Appendix 12.2 "The Mont Blanc Tunnel Renovation" of report 05.16.B.
See Appendix 8 "Austrian statistical study of 2005: Comparative Analysis of Safety in Tunnels, during
1999-2003 period" of report 2009 R08 for a contrast of traffic safety of road tunnels on motorways
and expressways compared with safety on other types of roads, and also traffic safety in tunnels
carrying bi-directional traffic with safety in tunnels with uni-directional traffic.
PIARC ROAD TUNNELS MANUAL PIARC

2.4. Risk assessment

In the past, in many countries, the safety design of road tunnels to a great extent was based upon
prescriptive regulations and guidelines. If the applicable prescriptions of relevant guidelines were
fulfilled the tunnel was regarded as safe.
However, this prescriptive approach has some shortcomings:
Even if a tunnel fulfils all regulatory requirements it has a residual risk which is not obvious and
not specifically addressed.
A prescriptive approach defines a certain standard of tunnel equipment etc. but is not suited to
take the specific conditions of an individual tunnel into account. Furthermore, in a major
accident the situation is completely different to normal operation and a great range of different
situations exceeding existing operational experience may occur.
Hence, in addition to the prescriptive approach, a risk-based approach - called risk assessment - can be
used to address the specific features of a tunnel system (including vehicles, users, operation,
emergency services and the infrastructure) and their impact on safety.
Various types of risk can be addressed in a risk based approach, such as harm to a specific group of
people (societal risk), or to an individual person (individual risk), loss of property, damage to the
environment or to immaterial values. Commonly, risk analyses for road tunnels focus on the societal
risk of tunnel users which can be expressed as the expected number of fatalities per year or as a curve
in the FN diagram showing the relationship between frequency and consequences (in terms of number
of fatalities) of possible tunnel accidents.
Risk assessment is a systematic approach to analyse sequences and interrelations in potential incidents
or accidents, thereby identifying weak points in the system and recognising possible improvement
measures. Three steps characterise the risk assessment process:
Risk analysis: Risk analysis is concerned with the fundamental question: "What might happen
and what are the probabilities and consequences?". It involves the identification of hazards and
the estimation of the probability and consequences of each hazard. Risk analysis can be carried
out in a qualitative or in a quantitative way or as a combination of both. Two families of
approaches are suitable for road tunnels:
- a scenario-based approach, which analyses a defined set of relevant scenarios, with a separate
analysis for each one,
- a system-based approach, which investigates an overall system in an integrated process,
including all relevant scenarios influencing the risk of the tunnel, thus producing risk indicators
for the whole system.
For system-based risk analyses, quantitative methods are common practice. Thus probabilities of
accidents and their consequences for different damage indicators (e.g. in terms of fatalities,
injuries, property damage, interruption of services) and the resulting risk are estimated
quantitatively, taking due account of the relevant factors of the system and their interaction.
Risk evaluation: Risk evaluation is directed towards the question of acceptability and the
explicit discussion of safety criteria. In other words risk evaluation has to give an answer to the
question "Is the estimated risk acceptable?" For a systematic risk evaluation safety criteria have
to be defined and determination made of whether a given risk level is acceptable or not.
Acceptance criteria must be chosen in accordance with the type of risk analysis performed. For
instance, scenario-related criteria can be set to evaluate the results of a scenario-based risk
analysis, while criteria expressed in terms of individual risk (e.g. probability of death per year
for a specific person exposed to a risk) or societal risk (e.g. reference line in a FN diagram) can
be applied for a system-based risk analysis. There are different methods of risk evaluation: it can
be done by relative comparison, by a cost-effectiveness approach or by applying absolute risk
criteria. However, in practice a combination of different approaches is often applied.
http://tunnels.piarc.org/en/safety/risk-assessment.htm 9 / 17
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/safety/risk-assessment.htm
Planning of safety measures: If the estimated risk is considered as not acceptable, additional
safety measures have to be proposed. The effectiveness (and also cost-effectiveness) of the
additional measures can be determined by using risk analysis to investigate the impact on the
frequency or consequences of different scenarios. Planning of safety has to answer the question
"Which measures are best suited to get a safe (and cost-efficient) system?
The simplified flowchart in Figure 2.4-1 illustrates the main steps of the risk assessment process.
Risk assessment of road
tunnels allows a
structured, harmonised
and transparent
assessment of risks for a
specific tunnel
including the
consideration of the
relevant influencing
factors and their
interactions. Risk
assessment models
provide a much better
understanding of risk-
related processes than
merely experience-
based concepts may
ever achieve. Moreover,
they allow evaluation of
the best additional
safety measures in
terms of risk mitigation
and enable a comparison
of different alternatives.
Hence, the risk
Fig. 2.4-1: Flowchart of the procedure for risk assessment
assessment approach in the context of tunnel safety management can be an appropriate
supplement to the implementation of the prescriptive requirements of standards and
guidelines. In practice, there are different methods to approach different kinds of problems. It
is recommended to select the best method available for a specific problem.
Although risk models try to be as close to reality as possible and try to implement realistic base data, it
is important to consider that the models can never predict real events and that there is a degree of
uncertainty and fuzziness in the results. Considering this uncertainty, the results of quantitative risk
analysis should be considered accurate only to an order of magnitude and should be supported by
sensitivity studies or similar. Risk evaluation by relative comparison (e.g. of an existing state to a
reference state of a tunnel) may improve the robustness of conclusions drawn but care should be taken
in the definition of the reference tunnel.
Basic principles and important components of risk analysis methodologies are presented in the :
Technical Report 2008R02 "Risk analysis for road tunnels".
This report also presents a survey of practical methods as well as a collection of case studies.
The various approaches to risk evaluation are presented and discussed in a new report entitled:
"Current practice for risk evaluation for road tunnels". This report also includes updates regarding risk
analysis and is currently being finalised.
10 / 17
PIARC ROAD TUNNELS MANUAL PIARC

2.5. Principles and tools for fire safety

Among the possible risks to be considered in road tunnels, vehicle fires give rise to particular concern
because they are not very rare events and their consequences may be far larger underground than in the
open if no appropriate measures are taken. For this reason, several PIARC reports treat the issue of fire
safety in road tunnels.
Part of the material included in these reports relates to specific tunnel features and is dealt with in the
corresponding chapters of this manual, for instance:
fire and smoke detection in Section 8.3,
ventilation for smoke control in Section 8.5
fire-fighting equipment for the users and emergency services in Section 8.6
fixed fire fighting systems in Section 8.7
tunnel response to fire in Chapter 9.
However, before fire-safety measures can be defined, general principles, basic information on tunnel
fires and study methods must be available. These are the issues dealt with in this section.
On the basis of the general safety objectives for road tunnels stated in Section 2.1 above, more precise
aims have been proposed for fire and smoke control:
to save lives by making self evacuation by users possible,
to make rescue and fire fighting operations possible,
to avoid explosions,
to limit damage to tunnel structure and equipment and to surrounding buildings.
These objectives are discussed in Section I "Objectives of fire and smoke control" of report 05.05.B,
which includes a detailed discussion on tenability criteria under fire situations. Complementary
guidance is included in Section 2 "Safety concepts for tunnel fires" of report 05.16.B.
In order to help assess the risk and provide data to be used as a basis for design, information on the
frequency of fires, design fires and design fire scenarios is given in Section II "Fire risk and design
fires"of report 05.05B. Design fires for life safety considerations are normally specified as as either a
constant or time-varying heat release rate, which is related to the assumed type vehicles on fire (e.g.
one or more passenger cars or an HGV), and on the loads carried. Guidance on the selection of design
fires is available from the PIARC report "Design Fire Characteristics for Road Tunnels".
An understanding of how smoke behaves during a tunnel fire is essential for every aspect of tunnel
design and operation. This understanding will influence the type and sizing of the ventilation system to
be installed, its operation in an emergency and the response procedures that will be developed to allow
operators and emergency services to safely manage the incident. Detailed discussion on the topic can
be found in Section III "Smoke behaviour" of report 05.05.B and Section 1 "Basic principles ofsmoke
and heat progress at the beginning of a fire" of report 05.16.B, which analyse in detail the influence of
different parameters (traffic, fire size, ventilation conditions, tunnel geometry) in the development of
an incident.
To help scientists and designers, an exhaustive description of basic (full and small scale experimental
results) and advanced (computer simulation) techniques available to approach fire safety studies is
given in Section IV "Study methods" of report 05.05.B.
http://tunnels.piarc.org/en/safety/fire-safety.htm 11 / 17
PIARC ROAD TUNNELS MANUAL PIARC

2.6. Dangerous goods

Dangerous goods are important for industrial production as well as everyday life, and they must be
transported. However, it is acknowledged that these goods may cause considerable hazards if released
in an accident, on open road sections as well as in tunnels. Accidents involving dangerous goods are
rare, but may result in a large number of victims and severe material and environmental damage.
Special measures are needed to ensure as safe a transportation as possible. For these reasons, the
transport of dangerous goods is strictly regulated in most countries.
Dangerous goods transport raises specific problems in tunnels because an accident may have even
more serious consequences in the confined environment of a tunnel. The following questions must be
addressed:
Should dangerous goods movements be restricted in some tunnels, and what should be the basis
for decisions on such restrictions?
What type of regulation should be applied to restrict dangerous goods movements in tunnels?
If dangerous goods are allowed, what risk reduction measures should be implemented, and what
is their effectiveness?
From 1996 to 2001, the Organisation for Economic Co-operation and Development (OECD) and
PIARC carried out an important joint research project to bring rational answers to the above questions:
OECD. Transport of dangerous goods through road tunnels. Safety in Tunnels, Paris: OECD
Publishing, 2001 ISBN 92-64-19651-X. The following paragraphs summarise the outputs of this
project and the further developments.

2.6.1. Regulations regarding transport of dangerous goods through tunnels
The first step of the joint OECD/PIARC research project was an international survey of regulations
regarding the road transportation of dangerous goods in general and in tunnels.
The survey showed that all investigated countries had consistent regulations for the transport of
dangerous goods on roads in general, and that these regulations were standardised within large parts of
the world. For instance, ADR (the European agreement concerning the international carriage of
dangerous goods by road) is used in Europe and the Asian part of the Russian Federation. Most States
in the USA and provinces in Canada follow codes in compliance with the UN Model Regulations.
Australia and J apan had their own codes, but Australia has aligned with the UN system.
In contrast, the survey highlighted a variety of regulations regarding the transport of dangerous goods
through tunnels. Restrictions applied in tunnels showed considerable variations between countries and
even between tunnels within the same country. The inconsistency of the tunnel regulations posed
problems for the organisation of dangerous goods transport and led a number of vehicles carrying
dangerous goods to infringe restrictions..
As part of their joint project, OECD and PIARC made a proposal for a harmonised system of
regulation. This proposal was further developed by the United Nations Economic Commission for
Europe (UN ECE), then implemented in Europe in the 2007 and further revisions of the ADR.
The harmonisation is based on the assumption that in tunnels there are three major hazards which may
cause numerous victims or serious damage to the tunnel structure, and that they can be ranked as
follows in order of decreasing consequences and increasing effectiveness of mitigating measures: (a)
explosions; (b) releases of toxic gas or volatile toxic liquid; (c) fires. Restriction of dangerous goods in
a tunnel is made by assigning it to one of five categories which are labelled using capital letters from
A to E. The principle of these categories is as follows:
http://tunnels.piarc.org/en/safety/dangerous-goods.htm 12 / 17
PIARC ROAD TUNNELS MANUAL PIARC


Category
A
No restrictions for the transport of dangerous goods
Category
B
Restriction for dangerous goods which may lead to a very large explosion
Category
C
Restriction for dangerous goods which may lead to a very large explosion, a large
explosion or a large toxic release
Category
D
Restriction for dangerous goods which may lead to a very large explosion, a large
explosion, a large toxic release or a large fire
Category
E
Restriction for all dangerous goods (except five goods with very limited danger)
Table 2.6-1: List of the 5 ADR categories
More information on this topic is available on the following websites:
UN ADR 2009 documents website
Australian ADG code website
Canadian TDG regulations

2.6.2. Choice of the most suitable regulation for a tunnel
Banning dangerous goods from a tunnel does not eliminate the risks, but modifies them and moves
them to a different location, where the overall risk may actually be greater (diverting through a dense
urban area for instance). For this reason, the joint OECD/PIARC research project recommended that
decisions on authorisation/restriction of dangerous goods in a tunnel should be based on a comparison
of various alternatives and should take into account the tunnel route as well as possible alternative
routes.
A rational decision process was proposed, with the structure shown in the figure below. The first steps
would produce objective risk indicators, based on quantitative risk analysis (QRA). The last steps
would take into account economic and other data, as well as the political preferences of the decision
maker (risk aversion for instance). These later steps could be based on a decision support
model(DSM).

Fig. 2.6-2: Rational decision process
The OECD/PIARC project has developed a QRA model as well as a DSM. The QRA model is
currently used in a number of countries. It is a system-based risk analysis model (see chapter 2.4 for
definition) and produces indicators of the societal risk (F-N curves for the tunnel users and for the
permanent neighbouring population), as well as the individual risk (for people permanently living in
the neighbourhood of the tunnel) and damage to the tunnel and the environment. It is applicable both
to routes including tunnels and to open-air routes, so that the risks on various alternative routes can be
compared. The model is based on 13 accident scenarios representative of each of the five tunnel
categories (although categories D and E cannot be distinguished because they lead to similar risks).
This model can be bought from PIARC and is described in more detail in its website.
http://tunnels.piarc.org/en/safety/dangerous-goods.htm 13 / 17
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/safety/dangerous-goods.htm 14 / 17
Additional information as well as examples of application can be found in the following PIARC
references:
"Quantitative Risk Assessment Model For Dangerous Goods Transport Through Road Tunnels"
in Routes/Roads 329 (2006)
Section 4.6 "OECD/PIARC Dangerous goods QRA model" of report 2008R02 and Annex 3.7
"OECD/PIARC DG QRA model" of report 2008R02.

2.6.3. Risk reduction measures
The joint OECD/PIARC research project also included an investigation of measures that could reduce
the probability and/or consequences of an accident involving dangerous goods in a tunnel, where such
goods are allowed.
Firstly a state of the art was established, resulting in identification and description of all possible
measures, most of which are described in part 2 of this manual (chapters 6-9). The second, more
challenging step was an attempt at evaluating the cost-effectiveness of these measures with respect to
dangerous goods hazards. Costs were not examined in detail as they will be specific to a particular
tunnel project and can be studied for each individual project. The focus was put on the effectiveness of
measures.
Some of the possible risk reduction measures are directly taken into account in the QRA model
developed under the project (see above). These were called "native" measures. The effectiveness of
each of these measures, or each combination of measures, can be assessed by running the model with
and without the measure(s) and comparing the results. A large number of tests were made and showed
that no general conclusion could be drawn regarding the effectiveness of measures because the
effectiveness very much depends on the specific case. Assessment of effectiveness should thus be
made on a project basis.
The effectiveness of the other, "non-native" measures was much more difficult to assess and methods
were proposed to take a number of them into account. More information can be found in chapter VII
of the OECD project report (Risk reduction measures).
PIARC ROAD TUNNELS MANUAL PIARC

2.7. Safety procedures

To ensure safety in road tunnels, the necessary structural, technical and organisational measures need
to be put in place so that incidents can be prevented as far as possible and their impact can be kept to a
minimum. The level of safety in tunnels is influenced to varying degrees by a variety of factors that
can be collectively summarised in four main groups: Road Users, Infrastructure, Vehicles, and
Operation.
Most of the measures needed to ensure a safe tunnel are based on the above influencing factors and
aim to prevent or mitigate the danger which arises from incorrect user behaviour, inadequate tunnel
installations or operation, vehicle technical defects or other faults. See Chapter 1 "Why are tools for
tunnel safety management needed?" of report 2009R08.
All the above necessary safety measures have to be combined under effective tunnel safety
management. To maximise the effectiveness of tunnel safety management, certain tools are needed to
support strategy, to drive critical decisions and keep a constant and traceable focus on all safety issues,
over a tunnel's lifetime. The three major "tools" for tunnel safety management are described below.

2.7.1. Road Tunnel Safety Documentation
Safety documentation is a key aspect of safety management and should be compiled for each tunnel.
The demands for this information are different depending on which stage the tunnel is at in its life-
cycle: design, commissioning, or operation. At the design stage the safety documentation focuses on
the description of tunnel infrastructure and traffic forecasts, whereas at the operation stage the
operational aspects, such as emergency response plans and measures for transportation of dangerous
goods, gain importance. The degree of detail in the information increases as the project develops. The
safety documentation should comprise'living' documents which are continuously developed and
updated; including detailing changes in tunnel infrastructure, traffic data, etc, as well as important
findings from operational experience (i.e. analysis of significant incidents, safety exercises, etc.). More
information is available on Chapter 2 "Road Tunnel Safety Documentation" of report 2009R08.

2.7.2. Collection and Analysis of Data on Road Tunnel Incidents
Collection and analysis of incident data, as detailed on Chapter 3 "Collection and Analysis of Data on
Road Tunnel Incidents" of report 2009R08 are essential for the risk assessment of a tunnel and for the
improvement of its safety measures. These comprise a two fold process, starting at the local tunnel
level to cover specific needs, like input data for risk analysis, and extends to fulfil legal obligations
such as reporting statistics at national/international level. The evaluation of specific events (accidents
and incidents) may help to identify specific hazards in a tunnel as well as to optimise operational
procedures and the reaction of safety systems. As well as analysis for real accidents, analysis of data
from safety exercises can help to gain experience in the management of incidents under realistic
circumstances.

2.7.3. Safety Inspections of Road Tunnels
Safety inspections, as explained in Chapter 4 of the technical Report 2009R08 (Safety Inspections of
Road Tunnels) are a tool to assess the current tunnel safety level either within a legal framework
(European Directive for instance) or against an accepted level of risk. PIARC has developed an
organisational scheme based on the EU Directive 2004/54/EC to describe the chain of safety
responsibility concerning safety inspections and clarify the responsibilities of the involved parties. It
also proposes the contents of a safety inspection (infrastructure and systems, safety documentation and
existing procedures, tunnel management organisation, training and quality assurance) along with a
comprehensive roadmap with all the necessary steps and preparation needed to carry out a safety
inspection.
http://tunnels.piarc.org/en/safety/safety-procedures.htm 15 / 17
PIARC ROAD TUNNELS MANUAL PIARC

2.8. Assessing and improving safety in existing tunnels

2.8.1. Why upgrading existing tunnels
As a consequence of the major disasters in road tunnels (Mont Blanc tunnel fire in 1999, Tauern
tunnel fire in 1999 or Gotthard tunnel fire in 2001), specific attention was turned to the safety
standards of existing tunnels. Existing tunnels require specific approaches and tools to identify and
evaluate the need for safety upgrade programmes. Substantial research and studies followed these
major tunnel fire incidents, demonstrating that many existing road tunnels require additional and
specific means to ensure a safe environment for users. Even where previous improvement programmes
have been carried out, existing tunnels may not be in line with the current safety standards because of
upgrading of regulations in the meantime.
These incidents and subsequent studies have raised awareness of tunnel risk amongst individuals
involved in road tunnels from designers and operators to authorities' representatives. It has become
clear that safety upgrade is not only a matter of improving the structure and/or equipment, but that
there is also, and sometimes mainly, a strong need to clarify safety management organisation and to
adapt procedures.
In the assessment of safety in existing tunnels, special attention should be paid to changes in the tunnel
environment (traffic volume and composition, dangerous goods transport, construction works in the
surrounding area, etc) which may also induce the requirement for upgrading measures.

2.8.2. Proposed methodology to assess and improve existing tunnels
A structured approach for assessing and preparing refurbishment programmes is proposed with two
main tasks:
The first task aims to assess the current situation of the tunnel, like an instantaneous picture of
the tunnel, in order to identify the current safety level. First of all a reference safety level must
be defined, which is generally provided by regulatory frameworks. Then the current tunnel
functionalities and the state of the facilities which perform them have to be analysed. On this
basis it must be assessed whether the existing tunnel is currently in line with safety-relevant
design criteria. Furthermore, specific risks should be assessed by risk analysis which is an
appropriate tool to evaluate the current safety level of a tunnel in operation. From these initial
analyses, actions can be defined and priorities can be set
The second task aims to define the future tunnel situation after renovation works which can be
acceptable in relation to the defined safety level goal. This can be done by developing
renovation programmes and assessing again the safety level of the renovated tunnel including all
upgrading measures. Once again risk analysis can be applied to demonstrate an adequate safety
level or to evaluate various alternatives of upgrading measures, including cost-effectiveness
criteria. Renovation programmes depend on the specific context of each tunnel, its constraints
and its environment. An iterative process of risk analysis may be followed where agreement is
reached on a projected safety level that is acceptable to all stakeholders in the project.
The multistage process for the preparation of a tailor-made renovation programme for a tunnel in
operation can be summarised in the flowchart below. It describes the functional links between the
various steps and their respective outputs.
In detail, the content of each step is to be adapted to the specific conditions of the individual tunnel, its
environment, and of course specific local practice.
Depending on the tunnel situation, the process can be stopped after step 3 with a simple comparison to
the reference state if the analysis is demonstrating that the required safety level is already achieved.
Indeed, for tunnels already renovated, step 3 can be the end of the process.

http://tunnels.piarc.org/en/safety/improving-safety.htm 16 / 17
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/safety/improving-safety.htm

Fig. 2.8-1 : Flowchart of the multistage process
If not, step 3 may highlight urgent mitigation measures which canbe implemented immediately to
improve the tunnel safety level with non-substantial actions such as closure barriers, signalling or
traffic control measures. In some cases, such measures may be sufficient to obtain the required safety
level.
If more substantial works are required, temporary modifications of the operating conditions may be a
useful tool for a temporary increase in the tunnel safety level, if necessary.
The preparation of renovation works for a tunnel in operation is an iterative process as it is a
combination of technical issues, safety measures, costs implication and works phasing constraints.
This is why step 4 and 5 can be refined several times to obtain an adapted refurbishment programme
taking into account all relevant parameters which may influence the decision. Design activities can
start after step 5.
The new report "Assessing and improving Safety in Existing Road Tunnels" provides guidelines for
each step within this process, up to the definition of an improvement programme.
Typical weak points (safety deficiencies) in existing tunnels are presented. Additionally, case studies
of existing tunnels in Europe demonstrate the strategy adopted for renovation works and upgrading
measures implemented.


17 / 17








ROAD TUNNELS MANUAL




3. HUMAN FACTORS REGARDING TUNNEL SAFETY










All rights reserved. World Road Association (PIARC)

PIARC ROAD TUNNELS MANUAL PIARC

3. Human factors regarding tunnel safety

The PIARC Technical Committee on Road Tunnel 0peration has felt the need to provide a better
understanding of human behaviour in tunnels in both normal and critical situations and to provide
recommendations for tunnel design and operation based on this understanding.
This knowledge of human behavior is decisive to act accordingly towards:
the user himself and the infrastructure (in particular so as to optimize the communication
devices and design of safety facilities including those dedicated to self evacuation),
the tunnel operating body and emergency services who must be able at all times to coordinate to
ensure optimal management of the event.

An adequate knowledge of human factors in the context of road tunnels optimises safety by acting
in the direction of the user, the tunnel design and more generally, the organisation (tunnel
operating body and emergency services).

The whole tunnel system, including the organisation of tunnel management, plays an important role in
tunnel safety as it determines what the tunnel users see or have to respond to, in both normal and
critical situations. The nature of the traffic regulations, motorists' compliance with them and the degree
to which they are enforced contribute significantly to the level of tunnel safety. The properties of the
vehicles using the tunnel and the loads they carry also play an important role.
Additional measures (with respect to the minimum requirements set by the EU-Directive) could be
considered when focussing on human factors and human behaviour in terms of tunnel safety. At this
stage, the focus of this chapter is on the interaction between the tunnel system and tunnel users;
additional information is provided regarding the interaction with tunnel staff and emergency teams.
The main conclusions regarding tunnel users are that (see details in Section 3.1.):
the design of tunnels and their operation should take account of human factors;
drivers need to be more aware of how they should behave in tunnels;
a fairly long stretch of road (if possible 150 - 200 m) before the tunnel portal should not contain
too many signs and signals; the necessary signs and signals at the point of entry into the tunnel
should be strictly limited in number;
the tunnel safety facilities should be easily recognisable even in normal traffic;
alarm signals should be provided by multiple-redundant sources.
Regarding tunnel operators and emergency teams it can also be concluded that it is of utmost
importance for operator's staff (see details in Section 3.2.) and emergency services (see details in
Section 3.3.):
to organize consultation and cooperation during the tunnel design process,
to construct contingency plans in order to prepare for tunnel user protection and fire fighting
operations, and to keep these plans up-to-date,
to organize familiarisation visits to tunnels and arrange exercises to test operational training,
to define the measures necessary to minimise the time required to mobilise the emergency
services,
to organize post accident analysis, including events of limited importance.
Designing for optimal human use should include assessment of human abilities and limitations and
ensuring that the resulting systems and processes that involve human interaction are designed to be
consistent with the human abilities and limitations that have been identified. Human abilities and
limitations refer to those physical, cognitive and psychological processes that deal with perception,
information processing, motivation, decision-making and taking action.
General recommendations are presented in Section 3.4.
http://tunnels.piarc.org/en/human-factors/ 2 / 8
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/human-factors/
Contributors
This chapter of the manual
was written by Marc Tesson,
associate member of C4
committee and leader of
working group n 3 "Influence
users' behaviour".

Fig. 3.0-1: Emergency exit
The previous leader of this
working group, Evert Worm,
contributed to the production
of the English version.
Didier Lacroix, the former
Committee Chairman, re-read
the French version.
3 / 8
PIARC ROAD TUNNELS MANUAL PIARC

3.1. Users
The following aspects are emphasized
in Technical Report 2008R17 "Human
factors and road tunnel safety
regarding users".
models that describe the human
decision-making process: these
are intended to give tunnel
professionals a brief theoretical
background giving insight into
human behaviour: Chapter 1
"General aspects of human
factors" of report 2008R17
observations of the behaviour of
tunnel users in both normal and
critical situations and
discussion, in general terms, of
the main human factors that
influence this behaviour:
Fig. 3.1-1: User approaching a tunnel

Chapter 2 "Human behaviour in road tunnels in normal situations" of report 2008R17 and
Chapter 3 "Human behaviour in road tunnels in critical situations" of report 2008R17
general aims of safety features, followed by a description of the minimum measures required by
the EU directive: these measures are examined in the light of results of psychological research
and recommendations from other sources to finally formulate recommended additional
measures: Chapter 4 "Recommended additional measures to improve road tunnel safety in
normal traffic conditions" of report 2008R17 and Chapter 5 "Recommended additional measures
to prevent escalation of critical traffic conditions in road tunnels" of report 2008R17
models that describe the human decision-making process: this is of interest for the interface
between tunnels and tunnel users: Chapter 6 "Future development of ITS and tunnel safety" of
report 2008R17.
When carrying out these investigations the Working Group members involved in these studies often
had to answer the following question: "should we adapt the tunnel to the user or the user to the
tunnel?" Obviously both strategies should be made use of, and in order to put the existing
recommendations into perspective the Working Group decided to investigate the subject of driver
education and information for drivers.
The following aspects will be emphasized in the planned report "Recommendations regarding road
tunnel drivers' education and information". The goal of this report will be to provide recommendations
to all those in charge of education and information actions: national organisations and agencies,
owners, operators, and consultants in the field of communication. In the first chapter this report will
provide general information for the target readers who it is assumed have little if any knowledge of the
details of the tunnel context. The second will deal with general recommendations valid for all target
readers and/or institutions. Chapters 3 and 4 will propose recommendations for the attention of
organisations and agencies, and specific owners.
http://tunnels.piarc.org/en/human-factors/users.htm 4 / 8
PIARC ROAD TUNNELS MANUAL PIARC

3.2. Operators

The term "operator" describes the
body representing the owner on site
and responsible for operating the
tunnel. This key player for tunnel
safety works in close relation with the
other players concerned (owner, public
authorities, emergency services, sub
contractors, other operators, users,
etc). Its main task is to manage traffic,
civil engineering aspects and tunnel
equipment, together with crisis and
administrative management related
with its missions. It plays a crucial
role for optimum implementation of
the tunnel safety managament system:
this is demonstrated by its
involvement in design studies
Fig. 3.2-1: Road tunnel command post
(including risk analyses) and definition of operating principles, not forgetting the day-to-day
monitoring of tunnel operation (event management, carrying out safety exercises, implementing
experience feedback, regular updating of operating documents, staff training, coordination with other
bodies involved, etc).
With respect to this player, the following aspects are highlighted in the existing Technical Report
2008R03 "Management of the operator-emergency teams interface in road tunnels" :
most relevant lessons learnt from the most serious tunnel fires of the last decades: Chapter 1
"Lessons learnt" of report 2008R03
information and recommendations for best practice. These are based on experience and lessons
learnt: Chapter 2 "Detailed recommendations" of report 2008R03.
More generally the lessons learnt from exercises and real events have shown that the behaviour of all
those in charge of operating the tunnel is a decisive factor in ensuring the safety of people during an
incident.
One of the key issues regarding this topic is appropriate reaction of the operating staff responsible for
monitoring and controlling tunnels. They are the very first to be involved in road tunnel crisis
management and as such carry very considerable responsibilities on behalf of the operator in terms of
daily tunnel management. Their task is all the more difficult in that they may at any time be required
to manage potentially serious events for which the probability they will happen is extremely low. To
react in the appropriate manner, tunnel operators must be able to understand and control sometimes
complex situations, meaning they must be very good at stress management. Specific and appropriate
training is thus essential. European regulations require the personnel involved in operating tunnels to
receive "appropriate initial and continuing training" (European Directive 2004/54/CE - Annex 1 3.1
"Operating means").
http://tunnels.piarc.org/en/human-factors/operators.htm 5 / 8
PIARC ROAD TUNNELS MANUAL PIARC

3.3. Emergency teams

Fig. 3.3-1: Tunnel safety exercise with fire brigade
Rescue teams liable to be called on to
intervene in road tunnels obviously need
to have the general training required to
help people and combat fires in any type
of infrastructure. Tunnels are confined
spaces in which a crisis or fire can very
quickly render rescue operation
conditions more complicated. Over and
above their technical skills, firemen
therefore need to be trained specifically
for this type of intervention. This
training must develop their behavioural
knowhow and enable them to deal
appropriately with the complex
situations they may be confronted with
in a tunnel. This knowhow is particularly
crucial for the supervisory staff who
must be capable under all circumstances of adapting the operational methods initially envisaged, if
needed. In order to fulfill this mission, good coordination with the tunnel staff is decisive, requiring
meticulous preparation, followup and implementation of intervention plans, safety exercises, and
training based on feedback of experience.
In the case of cross-border tunnels, attention needs to be drawn to the collaboration required between
the countries concerned in order to ensure perfect coordination between the rescue teams in crisis
situations.
With respect to the rescue teams, the following
aspects are emphasized in Technical Report
2008R03 "Management of the operator-
emergency teams interface in road tunnels" :
the most relevant lessons learnt from the
most serious tunnel fires of the last
decades : Chapter 1 "Lessons learnt" of
report 2008R03
information and recommendations for
best practice. These are based on
experience and lessons learnt: Chapter 2
"Detailed recommendations" of report
2008R03.

Fig. 3.3-2: Helping users in a shelter

http://tunnels.piarc.org/en/human-factors/emergency-teams.htm 6 / 8
PIARC ROAD TUNNELS MANUAL PIARC

3.4. General recommendations

This paragraph provides general recommendations to those who intend to pay particular attention to
human factors when designing a new tunnel or refurbishing an existing one. Its objective is not to sum
up the fundamental technical recommendations developed in the PIARC reports regarding inclusion of
the human factors when considering safety. It aims above all at summing up the main methodological
recommendations to be implemented when it is desired to pay particular attention to these aspects.
Three main points deserve to be underlined from this viewpoint:
1. the need to intervene as far upstream as possible in the framework of studies,
2. the crucial importance of taking account of the work carried out in the field of integration of
human and organisational factors in safety,
3. the advantages of tests to validate innovative solutions liable to be implemented.
The first point particularly concerns the design of new tunnels for which it is fundamental to intervene
as far upstream as possible during the studies. This should allow better account to be taken of the main
factors which govern the behaviour of users in road tunnels. Among these main factors, the following
can be notably mentioned:
data related to the local context, for example, the type of traffic and thus the users concerned
(locals, professionals, subscribers, etc.),
contextual items related to the existing infrastructures upstream and downstream from the
planned tunnel (route continuity logic),
other tunnels on the route or in the neighbourhood of the tunnel,
cross-border tunnels for which particular attention must be given to the strategies and means
implemented to communicate with the users.
The second point concerns consideration of the work carried out in the field of integration of human
and organisational factors with respect to safety, notably aiming to make best use of knowledge
accumulated to date in the field of general road safety, and evacuation in crisis situations in particular.
This can take shape in two ways: either by referring to general lessons learnt from work carried out in
this field (PIARC recommendations for example), or by involving human science specialists
(psychologists, experts) in the project. The advisability of involving human science specialists
deserves to be considered both for the design of new tunnels and for the refurbishing of existing ones.
Obviously it applies only for the most important projects with particular issues (cross-border and/or
particularly long tunnels, tunnels of limited dimensions, etc.)
In this field and as is already the case for open-air infrastructures, it is necessary to remain very
prudent before implementing a technical solution which appears at first sight to be satisfactory. The
lessons learnt from real events or from the numerous exercises held in tunnels do indeed show that the
technical choices made by engineers specialised in the fields of equipment and safety in tunnels are
not always the most appropriate from the viewpoint of user behaviour.
Independently of the possible implication of human science specialists, it is obviously necessary to
take care to ensure a wide consultation of all the actors concerned at all times. In particular, the
intervention services must be closely associated with the design of the safety equipment (particular
attention must be given to features provided for self-help for evacuation of users).
The third recommendation concerns the tests and trials necessary to validate innovative choices when
the latter prove to be desirable. Much has already been learnt in terms of taking human behaviour in
tunnels into account. Designers are invited to pay attention to these factors when finalising all the
safety measures in tunnels. When it proves to be necessary to develop innovative means, the
preliminary test phases must not be neglected (indoor testing for example), nor trials on site. These
trials could be usefully performed with support from experts in the field of human sciences. Their
objective will be to validate the innovative measures proposed before deployment in tunnels.
As a conclusion and in general, we cannot but recall the need to show much pragmatism and humility
in this field. A basic principle consists in preferring simple and intuitive solutions whenever possible,
http://tunnels.piarc.org/en/human-factors/recommendations.htm 7 / 8
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/human-factors/recommendations.htm 8 / 8
in line with what is currently in practice in non-confined conditions. These types of approach
guarantee that the measures implemented are liable to be well understood and adopted by the users.








ROAD TUNNELS MANUAL




4. OPERATION AND MAINTENANCE










All rights reserved. World Road Association (PIARC)

PIARC ROAD TUNNELS MANUAL PIARC

4. Operation and maintenance

Operation and maintenance are clearly an important issue for a PIARC Committee that a few years
ago changed its name to the Committee for "Road Tunnel Operations".
Operation and maintenance activities can be considered as divided into three main streams of activity:
1. Daily management: this stream includes all activities to monitor the traffic and to cater for an
efficient functioning of all equipment during normal operations and in the case of an emergency,
to ensure the proper functioning of all structural and electro-mechanical installations.
2. Training of the staff: this is normally a multi-organisation task, considering that normally not
only the operator, but also traffic police, fire brigade and other emergency services who
cooperate to deliver an acceptable level of safety in road tunnels. It includes: the basic training
of the staff, exercises, etc.
3. Continuous improvement of safety: this includes all actions of study and planning aiming at a
continuous improvement of safety (emergency planning, feedback of experience from accidents,
replacement of tunnel equipment, etc.).

Efficient operations and a cooperative environment among different stakeholders in charge of
tunnel and emergency management clearly underpin the safety and comfort of users and operators
both in normal operations and in the event of an accident

Considering the European context, the Directive 2004/54/CE on "Minimum safety requirements for
tunnels in the trans-European road network" clearly states that safety is not only related to structures
and equipment. In fact the directive identifies a special role for activities related to Operation and
Maintenance.
In order to successfully and efficiently operate and manage a road tunnel, operational tasks and the
responsible body for carrying them out, need to be established in order to ensure that all actions
required are handled in a consistent and safe way (Section 4.1). The level of safety provided for tunnel
users is highly dependent upon the specific characteristics of the tunnel, but it also depends strongly
on operational procedures and the people who are in charge of the tunnel.
The people in charge do not necessarily need to belong to the same organisation: players and roles
can be quite different. For example, the traffic police are normally in charge of traffic, but the task is
sometimes carried out by a road administration, and in some cases several tasks are entrusted to a
private company/operator. Moreover, the same task (for example: traffic management) can be
performed by many different bodies (operating staff, police, subcontractor), so the relative roles and
responsibilities have to be specified as well as recommendations to improve the behaviour of people
involved in tunnel operation and their level of cooperation (Section 4.2).
In each case the organisation of the operation and coordination with all the different bodies must be
dened, by written procedures and protocols that are simple and straightforward, so that they are
clearly understood by all parties and are robust under pressure in emergency situations.
The organisation of the operation can be quite different from one tunnel to another; consequently it
is difficult to define an overall common framework. However, it is convenient to assess for each
tunnel or group of tunnels the best-fit organisation to be adopted both during the standard operation
and in the event of an emergency situation (Section 4.3).
Moreover it is essential to establish standard operating procedures as well as minimum operating
conditions and emergency plans. This is in fact a key step in planning the operational response to
possible tunnel emergencies for which there need to be appropriate specific responses to various types
of incidents (Section 4.4).
http://tunnels.piarc.org/en/operation-maintenance/ 2 / 14
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/operation-maintenance/ 3 / 14
The management and day to day operation, as well as the maintenance of a tunnel, involve high
operational costs and funding requirements. In fact tunnels are among the most costly parts of a
road network to be operated (in terms of energy requirements, staffing and monitoring). The definition
and optimisation of the different cost elements in a tunnel and appropriate recommendations to reduce
them have been analysed by the PIARC tunnel committee. The efficient use of energy and the
progressive reduction of energy consumption should be considered, with a view to delivering a
sustainable operation of the road network (Section 4.5).
The final objective is clearly to guarantee an appropriate level of service and quality to the users. The
achievement of the objective obviously depends on the nature and overall performance of the facilities
and equipment. The performance of the equipment often depends on how this equipment is operated
by the tunnel staff in terms of timeliness and appropriateness. Therefore the staff called to perform
operational tasks must be well selected when recruited, well trained before starting their tasks and
continually throughout their careers (Section 4.6).
The safety level or the traffic capacity in a tunnel are influenced by changes characterising the road
network and the evolution of the traffic itself. The tunnel operator may occasionally need to make
minor or major changes to the system or to the management criteria to cope with these changes. It is
therefore necessary to monitor changes and accidents using information and feedback, to
continuously and systematically improve tunnel operations.
The operator needs to receive feedback from the experience of operation to be used to make choices
for the improvements (Section 4.7).
Structural elements and the technical equipment need regular maintenance whose goal is to ensure safe
driving conditions for the public by keeping the tunnel at its designed safety standard (Section 4.8).
General recommendations for maintenance in tunnels are defined as well as the specic features
and their facilities.
When the tunnel equipment no longer satisfies the needs of the operator, the requirements of
legislation or when the nature or the level of traffic changes, it may be necessary to upgrade or
refurbish the tunnel. For the refurbishment of an existing tunnel, recommendations mainly
concerning measures to facilitate the management of trafc network, equipment reliability and
durability and whole life costing are defined (Section 4.9).
The present chapter 4 essentially concerns tunnels of medium to long lengths, with medium or heavy
traffic volume, located in places where prompt external emergency interventions are possible.These
tunnels are operated with a specific organisation, dedicated to one tunnel or a group of tunnels, which
are part of the same road network.
Section 4.10 presents the specific conditions concerning short tunnels, or very low trafficked tunnels,
or scattered tunnels situated in areas with low population densities.

Contributors
This Chapter was written by Working Group 1 of the C4 committee (2008-2011) in which:
Roberto ARDITI (Italy) authored section 4.0 and coordinated the work;
Jean-Claude MARTIN (France) authored sections 4.1 to 4.10;
Fathi TARADA (UK) reviewed the full chapter.
PIARC ROAD TUNNELS MANUAL PIARC

4.1. Operational tasks

Generally speaking tunnels are considered as parts of the road network able to ensure a suitable or
even higher level of safety, nevertheless the potential consequences of specific incidents (breakdown,
accident or fire) may be far more serious in tunnels than in the open air. Moreover, the tunnels being
very often obligatory crossing points and maybe bottlenecks of the network, each total or partial
closure can lead to major disturbances of traffic or can oblige users to travel long distances on
alternative routes.
Because of these reasons, operators and road authorities have to ensure the operational continuity and
safety of road tunnels. Therefore, they must guarantee to the users crossing the tunnel a level of
service quality and safety complying strictly with regulatory requirements in force.
According to national regulations, tunnel operators and traffic police have to manage the traffic in the
tunnels (and in the route where the tunnel is located). Specifically, they need to cater for the safety
inside the tunnel for users and for people working inside the tunnel (operating staff, sub-contractors,
etc.). In several countries, the traffic police are in overall charge of traffic management and traffic
patrolling, while the operator is in charge of operational tasks such as maintenance, operation of tunnel
equipment, traffic surveillance and traffic assistance.
Generally speaking, typical tasks for the operators are:
Traffic surveillance and operation of tunnel equipment
Major tunnels (in terms of length, traffic density and complexity of the tunnel) are usually
managed from a Traffic Control Centre. Very often, the Control Centre is equipped with remote
surveillance systems (e.g. television closed circuits, automatic incident detection) and can
remote control certain equipment (ventilation, signalling, closing the tunnel, etc.).
Technical Patrolling
In certain cases, the operator can also deploy patrols that can provide a direct surveillance of the
users by patrolling in the tunnels. These patrols can intervene very rapidly in case of need.
Management of civil engineering works
This means a permanent surveillance of the civil engineering works of the tunnel by conducting
regular surveying and inspections. It also means carrying out regular maintenance of facilities
such as drainage systems, gutters and all secondary structures (premises inside the tunnel,
technical rooms, etc.),
Management of equipment
In major tunnels, the operator deploys several types of equipment that in the operation phase are
under his own control. To this purpose tunnels are also equipped with systemsthat allow the
operator to monitor the status of equipment. The operator must also cater for the maintenance of
equipment fitted in the tunnel. Here again, it is possible to have access to computerised tools for
assisting him in performing this task.
Management of emergency situations
Whatever the nature of the accident, whether it is a problem related to traffic (accident,
interlinked accidents, fire, etc.) or to equipment (loss of power supply, malfunctioning of data
transmission network, etc.), to intervene or to inform/activate the pertinent service/authority is
the standard duty of the operator in charge of the surveillance.
Technical and Administrative management
In addition to tasks directly related to the tunnel operation, the operator provides the technical
and administrative services supporting the management of the infrastructure and, of course, the
personnel. The operator caters for the design of any equipment upgrading, the direction of the
works, the investment and operational budgets for the proper functioning of the tunnel. Lastly,
the operator also develops statistics and monitors the achievement of its own objectives by
preparing periodical reports on the operation of the tunnel/route (financial indicators, traffic
indicators, etc.).
http://tunnels.piarc.org/en/operation-maintenance/operational-tasks.htm 4 / 14
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/operation-maintenance/operational-tasks.htm 5 / 14
The Technical report 05.13.B "Good Practice for the Operation and Maintenance of Road
Tunnels" deals with this subject in parts 2 and 4.
PIARC ROAD TUNNELS MANUAL PIARC

4.2. Players in tunnel operation and their co-operation

The management of the road transport process is a very complex task. It is even more complex if we
consider the road transport into a tunnel environment. Part of the complexity is also related to the fact
that skills and competencies required for the management of tunnels are scattered among different
services. To this purpose, the cooperation of different stakeholders is clearly a vital pre-requisite for a
fair and effective cooperation, in order to deliver good traffic and incident management. The
coordination is normally performed under the umbrella of local or central authorities that coordinate
the process and finally record the result of programmes as approved by inter-organizational
committees.
The main stakeholders that need to cooperate in this frame are:
The tunnel operator;
The operators of different parts of road network who have to be notified in case of tunnel
closure or traffic restrictions, as part of a common traffic management on the route/network;
National and local administrative authorities to whom reports have to be submitted as required
under the regulations;
The owner of the tunnel (if it is not the same as the operator of the tunnel), who also has to be
kept informed;
The public services (fire and rescue services, traffic police, medical services...) with whom
coordinated intervention plans have to be prepared so that they can intervene in a coordinated
and efficient manner in response to any types of incidents;
Other sub-contractors (cleaning, maintenance, breakdown services for users, etc.)
The Technical Report 2007R04 "Guide for organizing, recruiting and training road tunnel operating
staff" defines the organisational tasks in a more precise manner.
http://tunnels.piarc.org/en/operation-maintenance/players.htm 6 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.3. Organisation of operations

The operational tasks (operation, maintenance, etc.) can be considered as similar for a wide range of
tunnels, even of the internal organisation of entities responsible may be very different depending on
the country, and where different tasks can be either be performed by the operator or delivered by other
bodies. In some cases, a single organisation can cater for all the personnel required. In other cases, the
operational tasks may be shared by several public and private organisations. The tunnel owner or the
road administration may for example entrust different public or private organizations to take charge of
the tunnel construction and operation as a whole and/or specific operational tasks(e.g. the maintenance
tasks can be handed out to contractors).
The measures planned for managing incidents may be different, depending on national regulations and
also according to local requirements specific to each tunnel. The organization of the operator and the
traffic police can consequently be different, depending on the local context.
Even though the context varies greatly from one country to another, very generally, the structure of the
operation is organised into three principal groups:
The operating staff, in charge of operation management and traffic assistance;
The technical staff in charge of the construction and management of the tunnel (civil
engineering and equipment);
Administrative personnel;
Emergency rescue services (in a few cases, are also part of the operating staff).
The Technical Report 2007R04 defines in its chapter 4 "Operating staff: tasks and facilities" the
organisation of operation in greater detail.
http://tunnels.piarc.org/en/operation-maintenance/organisation.htm 7 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.4. Operating instructions, minimum operating conditions, emergency plans

Every tunnel operator produces and updates written procedures (sometimes called "operating
instructions") which define the objectives and criteria of possible actions by different internal service
providers, which can affect the tunnel or road. All types of operational events need be taken into
consideration for the procedures, including routine incidents, serious accidents and emergencies.
The'operating instructions' contains the basic actions to be carried out with associated procedures and
existing constraints.
The operator's staff also need an emergency plan for both intervention after a road accident and
technical failure of equipment in the tunnel. This plan usually meets regulatory requirements and
includes operational procedures and instructions involving, at minimum, the tunnel operators and the
intervention personnel in case of incident or technical failure. The emergency intervention procedures
should be coordinated with those applied by emergency and rescue services. The detailed content of
this plan could be defined by national instructions or directives specific to each country and needs to
be tailored to the technical and organizational framework of the tunnel.
The Technical Report 2007R04 defines in its chapter 4 "Operating staff: tasks and facilities" the
organisation of operation in greater detail.
http://tunnels.piarc.org/en/operation-maintenance/operating-instructions.htm 8 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.5. Operational costs

Experience shows that a kilometre in tunnel is always more costly than a kilometre of the same road
outside. In the case of an underground structure, we can find several systems and equipment that are
deployed either for ensuring a safe operation under standard operating conditions or for allowing the
protection and the evacuation of users and the intervention of rescue services in case of incident,
accident or fire. These measures not only represent considerable investment costs but also result in
particularly high costs for operation and maintenance. Thereby the role of the operator is to ensure the
continuity and the safety of the operation in a context of controlled costs.
In all cases, even a high standard of tunnel operation may not allow an optimisation of operational
costs, if the design and the construction of the tunnel have undertaken to a low quality level. The
operational costs therefore need to be a major concern during the different phases of the project and
the work execution, considering that the solution need to be found well before becoming an issue
during the operational phase.
The operation activity has to be designed at an adequate level in order to ensure that the expected
lifecycle of the equipment does not decrease. The lifecycle of equipment in tunnels is normally shorter
than in other environments, since the atmosphere in tunnels particularly corrosive.
The Technical Report 05.06.B "Road Tunnels: reduction of Operating Costs" is entirely devoted to
operating costs and in particular, to reducing them.
http://tunnels.piarc.org/en/operation-maintenance/operational-costs.htm 9 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.6. Staff recruiting, training and exercise

Tasks entrusted to the operating staff are very important in the light of safety and efficiency of the
operation. Moreover, the context is evolving, because on the one hand, the operational problems
assume greater importance compared to purely technical problems and on the other hand, the operating
systems are more and becoming complex.
The staff in charge of the operation need therefore to satisfy the following requirements:
They should be well selected through a recruitment process
They should be well trained before taking up their functions
They need refresher courses throughout their career
They should participate in exercises, possibly organised in cooperation with external services.
During recruitment phases, the qualifications required for the future operators must be defined
according to the nature of operational tasks. It may be remembered that even if the tasks are similar in
all countries, the people responsible for executing them do not necessarily belong to the same kind of
organisation in each country. Nevertheless, the skills and aptitudes required should be similar.
While designing the staff training (initial or permanent), the following two issues need to be
addressed:
What kind of training need to be provided to the operating staff (or, what should be the
obligatory training)?
What criteria are to be applied by the operation manager for validating the quality of the training
and the results obtained?
If there are no national rules on the content of training, the operator has to adapt his training
programme to the specific characteristics and requirements of his tunnels.
The Technical Report 2007R04 "Guide for organizing, recruiting and training road tunnel operating
staff" specifies the recruitment and training of personnel in greater detail, chapters 7 "Recruitment of
operation staff" and 8 "Training operating staff" .
The operator needs to test regularly the efficiency of his personnel and the procedures he has set up.
Thereby the operator needs to make sure that his staff are familiar with the different equipment
installed in the tunnel and he can thus detect any possible deficiencies in the execution of specific
tasks.
In addition to internal exercises, the operator and emergency services need to organise jointrescue
exercises with the participation of the traffic police, the operator, medical services and the fire and
rescue services. The results of each exercise should be analysed. If lessons drawn from an exercise
reveal lacunae, the intervention strategies should be reviewed.
A new Technical Report on "Good practice for road tunnel Emergency exercises" will be available
soon in the PIARC Virtual Library.
http://tunnels.piarc.org/en/operation-maintenance/staff.htm 10 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.7. Feedback from operation and incidents

The collection of data regarding incidents and accidents and their analysis is essential both for the
evaluation of the operation criteria and for the assessment of risks in the tunnel. All of this is important
with a view to a continuous improvement in tunnel safety. The collected data allow, in particular, the
evaluating of the frequency of triggering events. Data also provide a feedback regarding the
consequences of events and also the effective role and the effectiveness of safety measures and
equipment. They also provide additional information on the real behaviour of tunnel users.
The collection and analysis of data regarding incidents and accidents should allow the following two
objectives to be achieved:
At a local level (i.e. at the level of each single tunnel): they form an important base for the
definition and evaluation of improvement to be decided by the owner of the tunnel. They are
also a decision-making aid for the general improvement of safety in a given road network;
At a national and international level: they form a key basis for the reference framework allowing
authorities to formulate and adapt the general policies related to tunnel safety. In particular, they
allow quantifying the magnitude (in terms of frequency and severity) of critical events that can
cause a danger to the life of users. They also allow measuring the efficacy of safety installations
and in certain cases, comparing the level of safety in a given tunnel with national or
international safety data.
Lastly, they provide information (national statistics according to the type of tunnel) useful for the
analysis of risks relating tunnels in project stage or tunnels under operation that do not yet have an
adequate database.
The lessons drawn from the operation, particularly during incidents and accidents, should be analysed.
In fact if the results of these analyses reveal deficiencies, there is an opportunity to intervene by
improving strategies and/or operating instructions.
The Technical Report 2009R08 "Tools for road tunnel safety management" defines in detail the
conditions for analysing data from incidents and/or accidents in its chapter 3 "Collection and analysis
of data on road tunnel incidents" .
http://tunnels.piarc.org/en/operation-maintenance/feedback.htm 11 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.8. Maintenance of equipment

Throughout the life of the tunnel, the operator should carry out both the maintenance of civil
engineering works and the tunnel equipment. The maintenance of civil engineering structures is not
described in this paragraph.
The maintenance operations on equipment can be classified into two groups:
The preventive measures that are carried out at fixed intervals with the objective of preserving
the equipment in a good operating condition. Preventive maintenance offers the advantage of
preventing, as far as possible, unforeseeable failures and, by the way, it is easy to plan in
advance. It can however lead to high costs if the interventions are too frequent: therefore, they
need to be optimised suitably.
The corrective actions that are carried out when a system or a part of a system has failed or been
damaged. Corrective maintenance offers the advantage of using a system to the maximum extent
of its service life. Its disadvantage however is that it cannot be planned and therefore emergency
repairs are normally carried out with a significant surplus cost.
It is recommended to use preventive maintenance where possible and for those systems that are not
redundant and are related with safety. Preventive maintenance allows the joint planning of different
maintenance tasks in the event of every closure of the tunnel to the traffic. Moreover it helps keep the
equipment in a good operating condition. It may be noted however that even when preventive
maintenance is carried out very well, the operator cannot avoid corrective interventions.
Usually the operator's staff do not carry out all maintenance tasks; the operator normally entrusts
contractors and several options are consequently available:
It is possible to contract only those maintenance tasks related to a specific technical level. The
operator can thus contract tasks that present no technical complexity (cleaning, washing, ...) or it
can contract only very complex tasks (supervision system, radio retransmission equipment, ...)
It is possible to contract all tasks of one or more equipment groups (all ventilation systems, all
remote surveillance installations, etc.).
The Technical Report 05.06.B in its chapter 7 "Cost of maintenance ", the Technical report 05.13.B
in its chapter 4 "Maintenance and operation" and the Technical Report 2007R04 in its chapter 6
"Organising operating staff", give more complete information on the subject of maintenance.
http://tunnels.piarc.org/en/operation-maintenance/maintenance.htm 12 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.9. Operation during maintenance and refurbishment works

Maintenance tasks are not very different from one tunnel to another for similar equipment. However,
some tunnels have specific features (dense and non-stop traffic, very long diversion route, etc.) that
make total or even partial closures of the tunnel very difficult. In this case, the operator may have to
maintain a certain operational level, while maintenance interventions are being carried out. This is
possible only by deploying special measures that should take into account not only the safety offered
to the user but also the safety of the maintenance staff.
The Technical report 2008R15 in its chapter 2 "Operation of existing urban road tunnels" defines the
conditions for carrying out maintenance when the tunnel is in operation.
The same difficulties as those mentioned above are likely to be encountered during a refurbishment of
equipment in a tunnel that cannot be closed down easily. With regard to maintenance interventions,
this type of works may require several weeks, or even several months to be completed. Consequently,
more elaborate (and often costlier) measures have to be planned.
The Technical report 05.13.B discusses aspects relating to refurbishment in its chapter 6 "Renovation
of tunnels" .
http://tunnels.piarc.org/en/operation-maintenance/refurbishment.htm 13 / 14
PIARC ROAD TUNNELS MANUAL PIARC

4.10. Short tunnels and/or very low trafficked tunnels

The recommendations presented in sections 4.1 to 4.9 above are not always relevant (or even difficult
to implement) for short tunnels, or very low trafficked tunnels, or scattered tunnels situated in areas
with low population densities.
For these particular tunnels, it is recommended to carry out for each tunnel (or group of tunnels
located on the same road network) a detailed specific analysis taking into account:
geographical and climatic conditions,
local or regional resources available in the neighbourhood: authorities, operator, emergency
services, etc.,
economic context,
exposure to risk and level of risk.
This analysis will then make it possible to organise and to implement the most suitable operating
system, according to the specific conditions of these tunnels.
http://tunnels.piarc.org/en/operation-maintenance/short-tunnels.htm 14 / 14








ROAD TUNNELS MANUAL




5. ENVIRONMENTAL ISSUES LINKED WITH
OPERATION








All rights reserved. World Road Association (PIARC).
PIARC ROAD TUNNELS MANUAL PIARC

5. Environmental issues linked with operation
Increasingly, road designers select tunnels as a good alternative, considering the ability of road tunnels
to reduce some components of the environmental impact such as visual intrusion of infrastructures and
noise pollution. Nevertheless some impacts remain or are even increased by such a choice. Despite all
policy efforts to try to control and even reduce traffic, it is expected that traffic will increase during the
next decades; so environmental issues linked to road traffic need to be considered.
The PIARC tunnel committee deeply and specifically investigated air pollution phenomena
considering:
1. Pollution inside tunnels as the technical basis for the dimensioning of road tunnel ventilation
systems;
2. Pollution outside of the tunnel as direct evolution of know-how within the committee.

In fact, when considering air pollution, choices concerning the type of ventilation system determine
the basis for designing the locations and flowrates of exhaust air; the operation regime and air
quality set points for the ventilation control can often be more effective in delivering the required
targets for local pollutant concentration than the selection of more complex ventilation systems.

Road traffic and (consequently) vehicle emissions constitute a serious environmental concern
particularly in confined spaces as tunnels. These emissions are characterized by the presence of
various pollutants, which, at high concentrations, can cause adverse effects and consequences. The
PIARC tunnel committee traditionally assesses vehicle-induced emissions and air quality inside
tunnels. To this purpose, common modelling theories are reviewed, relevant air quality standards are
defined and existing conditions are characterized. Measured and simulated pollutant concentrations are
compared with air quality standards. Finally, mitigation measures are proposed to insure proper air
quality management inside the tunnel (Section 8.5).
Tunnel emissions affect the air quality within a relative short distance from the points where
emissions are dispersed, however the adjacent road network inuences the environment in a broader
area. Accordingly the air quality implications of tunnels should be examined in the context of the
outside road network of which they are a part (Section 5.1).
Other important environmental issues are noise and vibration. Noise pollution can arise during the
phase of construction causing environmental hazards, because a high noise level is often generated. In
addition, high volumes of vehicles during normal traffic operation can generate large noise levels,
which may be above permitted levels. Increasingly, noise pollution tends to be a problem adjacent
highly trafficked roadways.
The strategies for noise abatement follow long-established standard procedures in the planning and
construction process. Major steps forward have been made to abate noise at the source: the use of
special noise-absorbing pavements can reduce it, sound insulating and sound proofing barriers have
become more and more efficient, as well as the use of combined features and the deployment of
improved construction machines can minimize the generation of noise and vibration (Section 5.2).
Water impact is another aspect that has to be analyzed during the life cycle of an infrastructure such
as a tunnel. Detailed investigation of surface and subsurface hydrology should take place before and
during construction. The least damaging route and structural elements should be chosen to get
minimum interruption and alteration of hydrology patterns and processes. Drying up caused by the
manner of building infrastructure is a topic which is becoming more and more important. Several
studies can be carried out, which give insight into the effects of infrastructure on the hydrology of
areas in the surroundings of tunnel and how to mitigate these effects. Water pollution caused by the
leakage of construction materials during worksites can be reduced using containers that are designed
to exclude leakage (Section 5.3).
The final objective of tunnel designers and managers is to achieve sustainable operation from both a
functional and an environmental point of view, in order deliver a reasonable level of safety and to
http://tunnels.piarc.org/en/environmental-issues/ 2 / 8
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/environmental-issues/ 3 / 8
reduce as far as possible any negative impacts on environment. Different elements in order to improve
the operational sustainability of tunnel are considered and analyzed (Section 5.4).
Contributors
This Chapter was written by Working Group 4 of the C4 committee (2008-2011) in which:
Roberto Arditi (Italy) authored section 5.0 and coordinated the work
Antoine Mos (France) and Hans Huijben (The Netherlands) authored Section "5.1 Tunnel
impact on outside air quality"
Antoine Mos (France) authored Section "5.2 Noise and vibration"
Manuel Romana (Spain), authored Section "5.3 Water impact"
Fathi Tarada (UK) reviewed the full chapter.
PIARC ROAD TUNNELS MANUAL PIARC

5.1. Tunnel impact on outside air quality
In the field of road tunnels, air quality is traditionally considered in relation to the level of
concentrations of vehicle exhaust inside a tunnel. However, the concentrations of pollutants outside a
tunnel can be harmful or annoying to people. Such pollutant concentrations rapidly reduce from a
portal or exhaust shaft to the surrounding environment according complex mechanisms such as the
speed and direction of the wind and the neighbouring topography. Consequently, it is recognized that
air quality in the vicinity of tunnel portals or other exhaust points is of interest when the traffic
intensity increases and when tunnels are constructed in an urban environment.
Above a tunnel, the air quality is expected to be better than if an open air road section was situated at
the same location. However at the portals and shafts, polluted air is set free, when a longitudinal or
transverse airflow is discharged by the piston effect of traffic and/or by ventilation systems.
Depending upon background concentrations and other sources localized close to a tunnel portal or
shaft, the concentration levels of pollutants can exceed the maximum levels set by authorities. In that
case measures must be taken to improve the air quality in the vicinity of the tunnel. Measures may
include civil or mechanical works, planning of the land use around the tunnel, etc. Most often it may
be possible reduce the pollution concentrations based on operational measures such as changes in the
ventilation regime.
PIARC has published the Technical Report 2008 R04 "Road Tunnels: A Guide to Optimizing the Air
Quality Impact upon the Environment", which focuses on outside air quality related to tunnels and it is
a guide to enhancing the urban environment by altering the emissions from vehicles and changing
their spatial distribution within the space surrounding a tunnel. The guide considers a wide range of
design and operation opportunities to mitigate the impact of tunnels on outside air: from the selection
of the most optimum location of a tunnel, to gradients, ventilation type, air discharge management,
traffic management, tunnel maintenance and finally (if still useful) contaminant removal techniques.
http://tunnels.piarc.org/en/environmental-issues/outside-air-quality.htm 4 / 8
PIARC ROAD TUNNELS MANUAL PIARC

5.2. Noise and vibration
Noise is generally regarded as one of the key nuisances perceived by humans, which can significantly
affect urban areas. It should therefore be taken into account in the design of tunnels, especially for
those urban tunnels that have a high concentration of acoustical receptors in the immediate vicinity of
portals and shafts.
Traffic-generated noise is not specific to tunnels. Underground infrastructures are generally regarded
as having a positive influence on the acoustic environment, but there might be specific issues near the
portals in some configurations. In most developed countries, noise impact studies are performed for
every new infrastructure project (or significant modification), and the existence of tunnels is, of
course, to be taken into consideration at that stage.
The main source of noise impacting the environment surrounding tunnels is the traffic. Part of the
noise from vehicles running inside tunnels is reflected by the tunnel lining and reaches the portal that
itself becomes a source of noise. Under certain conditions the noise level near the portal of a tunnel
can be higher than the noise level of a related open air section. However, this kind of effect is
significant only for those acoustic receptors lying in the immediate vicinity of the tunnel portal:
moving away from the portal noise levels rapidly diminish, since the noise coming from the tunnel is
attenuated by the prevailing effect of noise generated by vehicles in the open air sections.
There are also sources of noise that are associated with the tunnel infrastructure, the main one of
which is the ventilation system. In the case of transverse ventilation, or longitudinal ventilation with
extraction shafts, fans and air flow through inlets and outlets may generate significant noise, and in
some cases they have to function even at night time when noise environmental standards are set at
lower targets. One solution may be to reduce the use of the ventilation system by optimising its
control, but this can only be achieved to a limited extent.
The most effective solution is to take these problems into account at the design stage. Considering that
the most prominent noise effects are geographically limited, air inlets/outlets may be located as far
away as possible from neighbouring buildings, but this may result in significant increases in cost. The
air velocity should be kept at relatively low values at air inlets/outlets to reduce noise generation by
making the size of these openings large enough. Additionally, silencers are most often necessary to
prevent the noise generated by the fans from "leaking" out of the ventilation plant.
In the case of longitudinal ventilation, the noise impact from fans on the environment is generally
moderate because, on the one hand, jet fans should not be located too close to the portals for maximum
efficiency (consequently the noise of fans is "diluted" within the traffic noise), and on the other hand,
silencers are usually fitted to the fans to maintain an acceptable noise level inside the tunnel. However,
for particularly sensitive configurations, it might be necessary to select specific designs or operational
measures.
Traffic-generated vibration is rarely a significant issue in the operation phase of a road tunnel (unlike
rail tunnels, because trains generate much more vibration than road vehicles). Should such a problem
occur, there is generally little that can be done apart from prohibiting access to the heaviest vehicles.
Another source of vibration is the fans. These should be carefully balanced to avoid excessive
vibration. However, fan vibration is generally not perceivable in the environment; it affects primarily
the machine itself, and can compromise its longevity. It can also become a safety issue because jet
fans, for example, may lose parts or even fall down from the tunnel ceiling due to excessive vibration.
Vibration monitoring is crucial for the reliability and safety of jetfans.
Vibration is much more problematic during the construction phase, especially when explosives are
used. Tunnel construction and related environmental measures are outside the scope of the PIARC
committee on road tunnel operation; specific recommendations are published by the ITA.
http://tunnels.piarc.org/en/environmental-issues/noise-vibration.htm 5 / 8
PIARC ROAD TUNNELS MANUAL PIARC

5.3. Water impact
The impact of road infrastructure on water quality can be very significant during both normal
operation (leaking of hydrocarbon products, tyre wear, etc.) and accidental situations (spilling of large
quantities of pollutants).
The existence of a tunnel does not change the problem very much. As on any road, there is a need for
water treatment (decanting, removal of pollutants) before releasing it into the environment. A few
tunnel-specific facts should however be taken into account when designing water management
systems. First, tunnels need to be cleaned on a regular basis, as often as every month for heavily
trafficked urban tunnels. This generates large amounts of waste water containing cleaning products.
Second, tunnels in which dangerous goods transports are allowed are generally equipped with specific
gutters in order to limit the spread of flammable liquids on the pavement. If an accidental spill occurs,
the flow rate of pollutant liquid in these gutters may be higher than what is encountered on a regular
road surface, and the water management system should be capable of coping with these flow rates.
Very challenging issues related to water may be encountered during the construction phase in sensitive
environments, for example regarding the turbidity of the construction site effluent. Appropriate
measures should then be taken. In some cases, they represent significant constraints and cost for the
construction works. Tunnel construction and related issues are outside the scope of the PIARC
committee dedicated to road tunnel operation. The reader is therefore encouraged to consult ITA
recommendations for further details.
Water impact is another aspect that has to be analyzed during the life cycle of an infrastructure as
tunnel.
Most of the impact of tunnels on water (and water on tunnels) happens during their construction, but
some of the impacts remain for a long time and can become a hindrance to the tunnel operation and
maintenance. Due attention must be given to these processes during the tunnel planning and design
stages, in order to avoid adverse, and costly, consequences. Detailed investigation of surface and
subsurface hydrology should take place before and during construction. The least damaging route (and
structural elements) should be chosen to obtain minimum interruption and alteration of hydrological
patterns and processes.

Fig. 5.3.1 : Water ingress in a tunnel built
with segments
Theoretically, tunnels can be: impermeable
(allowing no ingress of water and developing
the full water pressure on the lining) and
permeable or semi-permeable (allowing some
ingress of water and avoiding the development
of full water pressure on the lining). In practice
most tunnels are permeable during their
construction and semi-permeable during their
operation. Fig. 5.3.1 shows water ingress in a
tunnel built with segments and designed to be
impermeable.








http://tunnels.piarc.org/en/environmental-issues/water-impact.htm 6 / 8
PIARC ROAD TUNNELS MANUAL PIARC

Fig. 5.3.2 : Water flowing through a
permeable basalt layer
In non lined tunnels (or with a permeable
lining) water ingress can be important. Fig.
5.3.2 shows water flowing through a
permeable basalt layer in Canada.














The drying up of groundwater levels caused by the manner of building infrastructure is a topic which
is becoming more and more important. The effect usually does not finish during tunnel operation, and
the groundwater original levels almost invariably go down, with an irreversible impact on water
supply wells.

Fig. 5.3.3 : Drainage water flowing and lime calcium hydroxyls Fig. 5.3.4 : Similar effect in
precipitating in concrete lined tunnel construction joint

The water entering a tunnel can dissolve the free lime hydroxide in the concrete lining, becoming more
alkaline and releasing solid deposits in the drainage systems. This effect is more frequent in old
tunnels with out-dated drainage systems. Fig. 5.3.3 shows drainage water flowing and lime calcium
hydroxyls precipitating in a concrete lined tunnel. Fig. 5.3.4 shows a similar effect in a construction
joint.
http://tunnels.piarc.org/en/environmental-issues/water-impact.htm 7 / 8
PIARC ROAD TUNNELS MANUAL PIARC

5.4. Sustainable tunnel operation
The current international trend is to demand from road operators and road authorities that they should
promote an efficient use of energy and to adopt sustainable methods for the construction and operation
of public roads.
PIARC throughout its history has published several reports aiming at improving the efficiency of
tunnel operations, the reduction of operating costs, and the mitigation of environmental impacts.
The "sustainable tunnel operation" as a whole will be a basic topic to be dealt by PIARC during next
cycle (2012-2015).
http://tunnels.piarc.org/en/environmental-issues/sustainable-operation.htm 8 / 8








ROAD TUNNELS MANUAL




6. GEOMETRY









All rights reserved. World Road Association (PIARC)
PIARC ROAD TUNNELS MANUAL PIARC

6. Geometry

As mentioned extensively in the Chapter 1 "Strategic issues" of this Manual, the geometric
characteristics have to be defined at the most early stage of the conception of a tunnel, and even of a
road link comprising possibly one or more tunnels.
These characteristics are of very different natures, and can be grouped in the following categories:
the relation between construction method and cross-section
the theoretical notions related to traffic capacity
the general alignment of the road comprising the tunnel : number of carriageways and lanes, off-
carriageway provisions (lateral and possibly central), headroom, maximal slopes, minimal
horizontal and vertical radiuses, transverse slopes, the detailed characteristics of the transverse
profile inside the tunnel : width of lanes and off-carriageway provisions, headroom taking into
account the construction method and the equipment to be installed the space needs for safety
features as part of the cross-section : lay-bys, emergency stopping lanes, emergency service
recesses, safety fences and barriers, safety recesses, etc.
the specific geometric characteristics of other features located out of the cross-section:
emergency exits, evacuation galleries, by-passes, cross-connections, etc.
the influence of the geometrical characteristics on safety.
This chapter is mainly based on the Technical Reports 05.11.B " Cross section geometry in
Unidirectional road tunnels" and 05.12.B "Cross section design for bi-directional road tunnels".
Section 6.1 recalls the relation between construction method and cross section.
Section 6.2 gives a summary of the theoretical notions related to traffic capacity.
Section 6.3 recalls the main rules concerning the general alignments of roads, including the main
figures used in some countries, and insists on the need to maintain the largest geometrical
characteristics of the outside road in the tunnel itself (with the important exception of the maximum
slope, which has to be limited).
Section 6.4 deals specifically with the transverse profile of the carriageway of road tunnels, for uni- as
well as bidirectional ones.
Section 6.5 concerns the vertical clearance of the tunnel.
Section 6.6 concerns the emergency lanes and the off-carriageway features, as well as the various
safety features that have to be found along the tunnel.

Contributors
This chapter of the manual was written by Willy De Lathauwer (Belgium), associate member of C4
committee as ITA representative.
Fathi Tarada (UK), reviewed this Chapter.
http://tunnels.piarc.org/en/geometry/ 2 / 11
PIARC ROAD TUNNELS MANUAL PIARC

6.1. Relation between construction method and cross section

For road tunnels the cross sectional shape is typically rectangular or circular and depends mostly on
the method of construction. In table 6.1-1 some typical cross sections and corresponding construction
methods are indicated.
The dimensions of the shapes employed are dependent on the dimensions of the cross section
necessary for traffic. These vary due to:
1. Traffic volumes and the importance of the tunnel
2. Design speeds, safe stopping distances and sight distances
3. Space for in-tunnel equipment such as: signs, traffic and environment monitoring
4. Cost of the facility balanced against the required safety standards
5. The traffic management required to respond to an incident in the tunnel
6. The usual local norms and the financial possibilities.
Internationally the response to the above differences varies greatly. In individual countries the
response to the different situations has varied and evolves with time.
N Cross Section
Typical Construction
method
Comment
1 Circular
Tunnel Boring
Machine (TBM)
Recently extended in J apan to rectangular cross
section
2 Rectangular Immersed Tube Tunnel In USA circular cross sections are common
3 Rectangular Cut and cover tunnel
Precast technology sometimes leads to circular
cross sections above the carriageway
4 Horse-shoe Blasting Applied in hard rock
5
Circular Crown and
Elliptical Invert
Excavation
sustainment methods
In hard rock, horse-shoe shapes are usual
Table 6.1-1: Cross Sections and Typical Construction Methods

http://tunnels.piarc.org/en/geometry/method-and-cross-section.htm 3 / 11
PIARC ROAD TUNNELS MANUAL PIARC

6.2. Theoretical and practical tunnel traffic capacity

The theoretical capacity of a road section is defined as the maximum through-flow of vehicles per
hour. It is determined by measuring the maximum number of passenger cars in a fifteen-minute period
and multiplying this by a peak hour factor. This is not an absolute maximum, but rather refers to
reasonable repeatability. Expressed in this way, the capacity only depends on the number and width of
lanes and off-carriageways, and the slope of the section. It does not depend on the percentage of heavy
vehicles, since it is clear that this intensity will be a maximum when traffic is formed exclusively by
light vehicles and regular drivers. If there is no element that limits it, this theoretical capacity is
approximately 2,200 vehicles per hour per lane (v/h/l). More information is available in Chapter 4
"Capacity and speed in relation to the geometry of roads and roads tunnels" of Report 05.11.B and in
Chapter 3 "Traffic speed and densities" of Report 05.12.B.
The practical capacity of a section is calculated based on the theoretical capacity without the
previously mentioned restrictions (2,200 v/h/l). Limiting factors are applied based on the actual
characteristics of the roadway. These main factors are:
F
w
: Lane width factor, which reduces the capacity depending on the width of the lanes and the
off-carriageways. It is considered that a lane does not limit the practical capacity if the width is
equal to or greater than 3.60 m.
F
hv
: Heavy vehicle factor, which adjusts the theoretical capacity depending on the percentage of
heavy vehicles and the inclination and length of the ramp or slope of the roadway.
F
c
: Correction factor due to the predominant type of driver. This factor adjusts the capacity
based on whether the drivers are regular drivers along the route and if the type of traffic is that
of a working day.
The practical capacity of a carriageway in one direction, C
p ,
is calculated then by:
C
p
= 2200 . N . F
w
. F
hv
. F
c
in which N is the number of lanes.
The factors can further be calculated and adapted according to formulas and tables given in Chapter 4
"Capacity and speed in relation to the geometry of roads and roads tunnels" of Report 05.11.B and in
Chapter 3 "Traffic speed and densities" of Report 05.12.B.
More information can also be found in the HCM (Highway Capacity Manual) issued by the
Transportation Research Board (USA).

http://tunnels.piarc.org/en/geometry/traffic-capacity.htm 4 / 11
PIARC ROAD TUNNELS MANUAL PIARC

6.3. General alignment of roads and national examples

6.3.1 Horizontal alignment
Small curves should be avoided, especially if they are connected to a straight alignment. A minimal
curvature of 550-600 m should be observed. The lateral clearances must also allow for longitudinal
visibility in curves.
In urban tunnels, it should be adequate to consider design speeds close to the actual speed in fluid and
uncongested traffic flow.

6.3.2 Longitudinal profile
Due to the influence on speed, longitudinal downgrade profiles cause more accidents, especially with
high traffic volumes (increase of speed downwards).

6.3.3 Cross section
Reduced cross-sections are dangerous and may cause accidents.
Attention should be given to the point that, if the width of the carriageway and/or off-carriageway area
in the tunnel and in the approach to the tunnel is less than on the open road, these changes should be
implemented well before the tunnel portal and as smoothly as possible: see Chapter 4.7 "Design of
tunnel portals" of Report 2008R17.

6.3.4 Height clearance
Accidents involving oversized vehicles are often recorded in rectangular tunnels or tunnels with a
ceiling for ventilation purposes.
It is advised to install outside the tunnel, ahead of each portal, a signed escape route as well as a
system to stop physically oversized vehicles.
More information is available in Section IV.2.6 "Height clearance" of Report 05.04.B.

6.3.5 Uni- or bidirectional tunnels
Bidirectional tunnels cause more accidents than unidirectional ones. Nevertheless users observe fairly
well the prohibition to overtake in tunnels with average longitudinal gradients. In case of steep
gradients it should be adequate, however, to plan an additional lane for slow vehicles.
It is strongly advised against changing the traffic direction to absorb daily traffic peaks.
Bidirectional tunnels may be economic for the phased construction of motorway tunnels, where
economic considerations require bidirectional traffic operation to be planned at a first stage, then
unidirectional at a second stage. However, this is under the proviso that the usable tunnel width is
designed with bidirectional traffic requirements in mind and is thus wide enough, in order to absorb a
number of traffic peaks (e.g. summer or winter holidays). Even if such an arrangement may be
acceptable from a safety viewpoint, it must be avoided as often as possible. For urban tunnels it must
be prohibited.

6.3.6 Interchanges
http://tunnels.piarc.org/en/geometry/alignment.htm 5 / 11
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/geometry/alignment.htm 6 / 11
Underground interchanges (slip roads in and out) may cause accidents. They must thus be correctly
designed. The lighting equipment should lay emphasis on these singular points and on the geometric
challenges faced by the driver. Consideration must be given to the drivers visual perception.
Inside the tunnel, the traffic exits must be located at a distance from the portal. A number of accidents,
mostly injury accidents, have occurred in tunnels where the slip road is located directly after the
tunnel. In the case of tunnels with restricted space conditions, it should be adequate to plan an
additional lane inside the tunnel for the exit slip road.

PIARC ROAD TUNNELS MANUAL PIARC

6.4. Carriage way geometry

The terminology has to be defined as follows:
1. Carriageway, comprising the area inside the inner edges of the outermost traffic lane markings
2. Off-carriageway, comprising those areas in plan outside the carriageway, including edge lane
markings, clearances, emergency lanes, sidewalks and safety barriers.
Fig. 6.4-1 : Example of cross section
More information is available in Chapter 2 "Terminology" of Report 05.11.B.
To aid good management, roads are classified on a hierarchical basis according to function. Road
networks of highest classification are interstate connections such as the Trans European Road Network
or the Interstate Highways in the USA. National networks consist of roads that connect urban regions
and national economic centres. Regional networks provide connections between regional towns.
Functional requirements to the distinct functional networks or roads are formulated such as speed,
congestion level, distances between intersections.
Most countries have their own directives and guidelines regarding requirements to carriageway
geometry. A comparison of international guidelines is given in the Chapter 5 "Traffic lanes and
carriageway" of Report 05.11.B.
Country and name of
guidelines or other
source
Design Speed or
Reference Speed
[km/h]
Width of
Traffic Lane
[m]
Width of Traffic
Lane Marking
[m]
Width of
Carriageway [m]
Austria RVS 9.232 80 - 100 3.50 0.15 7.00
Denmark (practise) 90 - 120 3.60 0.10 7.20
France CETU 80 - 100 3.50 ? 7.00
Germany 100 (26T, 26Tr) 3.50 0.15 7.00
Germany RAS-Q 1996 70 (26t) 3.50 0.15 7.00
Germany RABT 94 110 (29.5T) 3.75 0.15 7.50
Japan 80 - 120 3.50 7.00
Japan Road Structure
Ordinance
60 3.25 6.50
Fig. 6.4-2 : Comparison of international guidelines (Excerpt of table 5.1 of the Report 05.11.B)
It is recommended that the width of traffic lanes in tunnels with design velocities of 100 km/h shall not
be less than 3.50 m. When it is acceptable/necessary to impose speed limits (80 or even 60 km/h) in
tunnels on roads (i.e. unavoidable sharp curves, noise reduction in built up area, limited capacity
necessary, cost reduction) a restriction of the width of traffic lanes (for example to 3.25 m) may help
http://tunnels.piarc.org/en/geometry/carriage-way.htm 7 / 11
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/geometry/carriage-way.htm 8 / 11
drivers to reduce speed and thus act as a psychological support of the speed limit. This generally has to
be enforced with frequent controls and high fines. In some urban tunnels, where only light vehicles are
allowed, narrower lanes are accepted; in curves attention has to be given to the influence of the
bending of the pavement on the width of the structure.
More information is available in Chapter V "Traffic lanes and carriageway" of Report 05.11.B and
Sections 7.1 to 7.5 of Chapter 7 "Geometric cross section" of Report 05.12.B.

PIARC ROAD TUNNELS MANUAL PIARC

6.5. Vertical clearance

The minimum headroom above the carriageways is at least equal to the maximum (design) height of
heavy good vehicles (HGV) that are allowed on the road, with additional clearance necessary to allow
for movements of the vehicles due to irregularities of the pavement and the vehicle.
The minimum headroom depends on the maximum height of heavy good vehicles and varies from
country to country. In most European countries the maximum height of heavy good vehicles is 4.0 m;
certain countries allow higher values (UK, USA): see table 7.1 in Chapter 7 "Maintained headroom" of
the Report 05.11.B.
In the European Union the maximum height of heavy good vehicles is 4.00 m, although the Geneva
conventions allow a maximum of 4.3 m. If a margin of 0.20 m is added to these maximum heights in
order to absorb vertical movements of the HGV, the minimum vertical clearances required are 4.20 m
(4.50 m).
Above these minimum clearances, additional headroom is necessary for drivers of HGV's to feel
comfortable. This comfort margin is related to the object distance. The minimum height plus the
comfort margin yields the maintained headroom. If a value of 0.30m is taken for the comfort margin,
the maintained headroom is 4.50 m (Geneva convention 4.80 m, UK 5.35 m, USA 4.90 m on
freeways, 4.30 m on other highways).
To prevent damage of equipment mounted above the carriageway by loose tarpaulins for instance, an
additional allowance is often applied.
Finally, allowance has to be made for inaccuracies in the construction, bending of the roof and
possible later paving overlays see Chapter 7 "Maintained headroom" of the Report 05.11.B and
Chapter 7.8 "Vertical clearances" of the Report 05.12.B.
The specific case of the geometric design of reduced height urban tunnels is treated separately, as they
are normally reserved to cars and some restricted categories of (light) vans.
The full study has been made for France and implies the following specific points due to the presence
mainly of cars, available in the article "Reduced height urban tunnels geometric design"
(Routes/Roads 288 - 1995):
slopes : higher limits are possible : I.3, p 40
interdistance of interchanges : II.1, p 41
definition of the height : II.3, pp 43-44
horizontal and lateral alignment : III.1, pp 45-46
cross-section : III.2, pp 46-50

http://tunnels.piarc.org/en/geometry/vertical-clearance.htm 9 / 11
PIARC ROAD TUNNELS MANUAL PIARC

6.6. Emergency lane, off-carriageway geometry and special elements

To facilitate and clarify communication and comparison it is necessary to define a minimal set of
terms regarding carriageway and off-carriageways. The working group which produced the Technical
Report 05.11.B decided to apply the following terminology:
1. Carriageway, comprising the area inside the inner edges of the outermost traffic lane
markings;
2. Off-carriageway, comprising those areas in plan outside the carriageway, including edge lane
markings, clearances, emergency lanes, sidewalks and safety barriers : see graphs in Chapter 2
of the Report 05.11.B : Terminology
The distinction is justified in that there appears to be general agreement about the use and dimensions
of the carriageway, while the dimensions of and requirements for elements of the off-carriageway
differ greatly between countries. The emergency lane is defined as an "area of hard clearance to park
vehicles in case of emergency".
On roads of the motorway type in the open air usually an emergency lane is provided. Hard clearances
in tunnels are often restricted for economic reasons. This restriction can make it impossible for
broken-down vehicles to park on the hard clearance adjacent to the driving lane without occupying
part of the driving lane and thus disrupting traffic flow.
The geometry of off-carriageways varies between different countries, e.g. no general rules or figures
can be given. In many countries, due to costs, the width of the hard clearance is too small to park a
vehicle adequately. Therefore at certain distances lay-bys are provided. However in Norwegian and
Spanish experience only 40 % of the broken down vehicles effectively reach or use the lay-bys. This
demonstrates that lay-bys cannot completely replace emergency lanes: see Sections 8 to 10 of Chapter
III "Breakdowns" of Report 05.04.B.
The hard clearance should give the possibility to park a stranded car outside the carriageway.
Therefore the width measured from the outer side of the edge lane marking should be at least the width
of a passenger car (1.75 m) plus a width of 0.50 m. to enable motorists to descend, resulting in a hard
clearance of 2.45 m.
In case also heavy trucks should be parked outside the carriageway a width of (2.50 +0.50 +0.20 =)
3.20 m is required as explained in Chapter 6 "The off-carriageway" of the Report 05.11.B.
Safety barriers are commonly referred to as "massive construction to guide vehicles colliding with the
tunnel side-wall safely back in the direction of traffic". It differs from guard rails, which are a flexible
or frangible beam type construction supported on poles to prevent vehicles colliding with the tunnel
side-wall.
Figure 6.6-1 : Typical alignment of safety barriers in the off-carriageway
http://tunnels.piarc.org/en/geometry/special.htm 10 / 11
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/geometry/special.htm 11 / 11
In the case of tunnels it is questionable whether object distance is determined by the distance between
the inner side of the edge lane marking and the kerb of walkways, the front of safety barriers or guide
rails, or the tunnel side-wall. There is general agreement that in case low level walkways are employed
the distance to the tunnel wall is a good measure. When no walkways are present the distance to the
base or to the top level of the safety barriers has to be considered.
Especially in tunnels drivers prefer a certain distance to the wall (or walkway, guide rail or safety
barrier) due to smaller movements of the eye-angle when fixed on objects. Experience shows that
where object distance in tunnels is smaller than on the adjoining road motorists change course to keep
distance from the tunnel wall: see Chapter 6 "The off-carriageway" of the Report 05.11.B.
If vehicles crossing the edge lane marking cannot be redirected in time then the consequences of
collision with the wall must be minimized. This can be achieved by means of safety barriers or guard
rails. Safety barriers require less space than guard rails. When vehicles collide with safety barriers at
small (acute) angles they can be guided back in the direction of traffic and there is a chance of
preventing major accidents. When vehicles collide with safety barriers at large (obtuse) angles the
results of the collision may be more serious. Guard rails are not as effective as safety barriers at
correcting/redirecting errant vehicles; however, they cause less damage in a collision at an obtuse
angle. That is why safety barriers are to be preferred in case of narrow hard clearances and guard rails
in case of broad hard clearances.
As guard rails require bending space this would mean extra width of the tunnel, which in many cases
is not feasible from an economic point of view. Especially at restricted speed, safety barriers perform
well. Moreover, barriers need less maintenance.










ROAD TUNNELS MANUAL




7. STRUCTURAL FACILITIES
RELATED TO OPERATION AND SAFETY








All rights reserved. World Road Association (PIARC).
PIARC ROAD TUNNELS MANUAL PIARC

7. Structural facilities related to operation and safety

In addition to the basic cross-section and alignment geometry required for traffic operations, special
facilities are provided in most road tunnels to cater for the particular operational and safety demands
of the tunnel environment.
Emergency exits are provided in all except the shortest tunnels to allow tunnel users to evacuate on
foot from the traffic tube to a place of safety.The different types of emergency exits for pedestrians are
considered in Section 7.1. These include cross-connections and cross-passages between tubes, refuges
where the public can remain safely during an emergency, and safety galleries (passages) constructed
alongside the traffic tubes or perhaps under the carriageway and leading to the surface.
Section 7.2 considers the facilities provided for vehicles.These include lay-bys, turning bays and
cross-connections between tubes for vehicles.These cater for situations such as vehicle breakdowns or
to allow vehicles to turn around or cross into an adjacent tube, which could be useful for maintenance,
for manoeuvring emergency vehicles during an incident, or for traffic management following an
incident.
Section 7.3 considers the geometrical aspects of safety recesses, which may be provided at intervals
along the walls of a tunnel, to allow the occupants of a broken down vehicle to move away from the
carriageway and minimise the risk of being struck by moving traffic.
Drainage is important to minimise the size of pools that may otherwise form in the event of a spillage
from a road tanker or during routine wall washing. In the event of a spillage of flammable liquid, the
drainage system can have a major effect on the size of a resulting fire. Section 7.4 considers the
different types of drainage systems provided in road tunnels.
Section 7.5 describes other facilities that may be provided within or at the portals of a tunnel.

Contributors
This Chapter was written by Robin Hall (UK).

http://tunnels.piarc.org/en/structural-facilities/ 2 / 9
PIARC ROAD TUNNELS MANUAL PIARC

7.1. Emergency exits

Emergency exits are provided in all except the shortest tunnels to allow tunnel users to evacuate on
foot from the traffic tube to a place of safety in an emergency. In short tunnels, the portals are
adequate as emergency exits. In most tunnels, however, additional emergency exits are required in
order to limit how far tunnel users have to travel to reach a place of safety.
Emergency exits may be provided in different ways, including:
Cross-connections or cross-passages between tubes (which may be used by vehicles as well as
pedestrians).In some cut and cover tunnels, the cross-connection may simply comprise a single
doorway between the tubes.For bored tunnels, the tubes are usually spaced some distance apart,
and cross passages (of a measurable length) are created.
Exits may lead into shelters where the public can remain safely during an emergency. However
these shelters have to be connected to the surface directly or by an escape gallery, in order to
make possible in a second stage the escape under the control of the fire brigade. Shelters are
specially equipped enclosures with a separate special fresh air supply and an emergency
telephone. Some welfare facilities may be provided. The psychological effects associated with
the use of shelters should be considered in the design and the procedures for their use (see
Report 2008R17 "Human factors and road tunnel safety regarding users" ).
Safety galleries (passages) constructed alongside the traffic tubes or perhaps under the
carriageway and leading to the surface or other safe place.
Escape passages leading directly from an emergency exit doorway to the surface or other safe
place.Such passages are generally feasible only for tunnels with little cover (cut and cover
tunnels for instance).
Figure 7.1-1 shows a typical escape pattern for a uni-directional tunnel with longitudinal ventilation.

Fig. 7.1-1 : Typical escape pattern for uni-directional tunnel with longitudinal ventilation
The appropriate spacing between emergency exits depends on:
types of vehicles using the tunnel, which dictates the nature of incidents that could occur;
traffic volume and the number of tunnel users that may need to use the exits;
the capability of tunnel ventilation system to maintain tenable conditions for evacuation in the
tunnel;
incident detection and warning systems;
the nature of the protected routes beyond the emergency exits (including their dimensions and
the presence of significant gradients or stairs); and
http://tunnels.piarc.org/en/structural-facilities/emergency-exits.htm 3 / 9
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/structural-facilities/emergency-exits.htm
human behaviour.
The optimal distance between two emergency exits is generally estimated to be between 100 and
500 m.
The following design principles are important:
emergency exits should be clearly signed as such to distinguish them from equipment room
access. The recommended colour of the doors (very often the "emergency exit" colour green)
must be considered in combination with the type of tunnel lighting;
doors and openings should be sized to handle a large number of people in a short time as well as
the passage of rescue workers with equipment or stretchers;
emergency exits should be visible either directly or by visible and recognisable signs from any
position in the tunnel;
the luminance of access floors, doorsteps, etc. and the room just behind the emergency exit
should be "inviting" and be designed to prevent people from falling or stumbling;
curb lighting/markers should not be obstacles for walking people;
emergency exit doors should not be locked.
Figure 7.1-2 shows a possible design of an emergency exit.
Fig. 7.1-2 : Design of an emergency exit (Mont Blanc tunnel : France - Italy)

Further discussion of emergency exits is provided in the Technical Report 1999 05.05.B "Fire and
smoke control in road tunnels" and, in more detail, in the more recent Technical Report 2007 05.16.B
"Systems and equipment for fire and smoke control in road tunnels".

4 / 9
PIARC ROAD TUNNELS MANUAL PIARC

7.2. Facilities for vehicles

The large majority of road tunnels have no emergency lane. This creates a likelihood that tailbacks can
occur - depending on the traffic intensity, the presence of broken down vehicles or other problems
causing drivers to stop. According to some German and French statistics, tunnels without emergency
lanes are less safe than tunnels with emergency lanes (see Technical Report 2008R17: "Human factors
and road tunnel safety regarding users").
Lay-bys allow vehicles to stop in a tunnel without blocking the carriageway.This reduces traffic
disruption and the risk of a collision.It is easier and safer for the occupants to get out of their vehicle in
a lay-by, for example in order to use an emergency telephone.The shelter from traffic can be
particularly beneficial for disabled drivers.Lay-bys are also very important for the maintenance of the
tunnel and ensure the safe parking of the maintenance vehicles.
The distances between lay-bys vary from tunnel to tunnel. In some national guidelines these distances
depend on the classification of the roads the tunnels form part of the Technical Report 1995 05.04.B
"Road safety in tunnels" noted that their utilisation rate was generally low. In tunnels with lay-bys,
only 20% of faulty vehicles stopped in a lay-by.Recommendations were given to improve this.
In longer tunnels, facilities may also be provided to allow vehicles to turn around or cross into an
adjacent tube.These could be useful for maintenance, for manoeuvring emergency vehicles during an
incident, or for traffic management following an incident.More specifically, some countries provide
turning bays for vehicles. This is because, although cars and vans can turn easily at standard lay-bys,
heavy goods vehicles and buses require more space. These turning bays usually measure 4 m by 17 m
or larger (see the Technical Report 1999 05.05.B: "Fire and Smoke Control in Road Tunnels" ). When
they are provided, they should be located every 1-2 kilometres.

Fig. 7.2 : Example of turning gallery
http://tunnels.piarc.org/en/structural-facilities/facilities-vehicles.htm 5 / 9
PIARC ROAD TUNNELS MANUAL PIARC

7.3. Safety recesses

Most road tunnels have emergency stations located at intervals along their length, typically equipped
with emergency telephones and portable fire extinguishers (and sometimes fire hoses), to be used by
tunnel users in case of breakdowns or incidents.
There is great variety in the housing and location of these emergency stations, ranging from simple
boxes attached to the tunnel wall to recesses or rooms with or without doors for separation from the
traffic tubes.Recesses allow the occupants of broken down vehicles to move away from the
carriageway and minimise the risk of being struck by moving traffic.
To prevent feelings of claustrophobia within enclosed emergency stations the use of appropriately
specified glass door panes is recommended. A good alternative is to avoid doors and to guarantee
good voice communication by means of noise cancellation technology.
The Technical Report 2008R17: "Human factors and road tunnel safety regarding users" considers the
human factors associated with the design of such facilities, which need to be highly conspicuous and
identified by clear signs.
The equipment provided at emergency stations is discussed in Chapter 8.

http://tunnels.piarc.org/en/structural-facilities/safety-recesses.htm 6 / 9
PIARC ROAD TUNNELS MANUAL PIARC

7.4. Tunnel drainage

Road tunnels are equipped with a drainage
system to deal with surface water from
portals, groundwater infiltration through the
lining, wall washing water, spillages from a
road tanker and fire fighting water.
Where the transport of dangerous goods is
permitted, the drainage of flammable and
toxic liquids is a key concern. Drainage is
important to minimise the size of pools that
may otherwise form in the event of a spillage
from a road tanker. In the event of a spillage
of flammable liquid, the drainage system can
have a major effect on the size of a resulting
fire.
Drainage systems typically consist of
gulleys, channels, pipes, sump and pumps,
oil/water separators and control systems for
collection, storage, separation and disposal
of effluent that might otherwise collect on
the roadway. Some authorities specify the
use of slot gutters in order to maximise
drainage performance. Sump and pumps are
generally provided at the portals and at low
points.
The impact of water on tunnel construction
and operations is discussed in Section 5.3.
Fig. 7.4-1: Example of a mid tunnel sump and pumps

http://tunnels.piarc.org/en/structural-facilities/drainage.htm 7 / 9
PIARC ROAD TUNNELS MANUAL PIARC

7.5. Other facilities

Other structures may be provided within or at the portals of a tunnel are described below.

7.5.1. Emergency recesses
Emergency or fire-fighting recesses
contain fire hydrants, hose reels
(sometimes) and special equipment
for use by the fire brigade. They are
located at intervals along the tunnel
length.
They may be combined with the
safety recesses, containing
emergency telephones and portable
fire extinguishers, discussed in
Section 7.3.
Fig. 7.5.1-1 : Example of an emergency recess

7.5.2. Plant rooms within a tunnel
In many tunnels, electrical sub-
stations and mechanical, electrical,
communications and control
equipment may be housed in plant
rooms located within the tunnel.
The layout and sizing of plant rooms
follow the same principles as for
plant rooms in service buildings. For
example, adequate space is needed
for opening of cabinet doors and
access to switchgear. Allowance for
cable runs and bend radii is
important and can be more
problematic compared to external
buildings because of tunnel
construction and space constraints in
the tunnel bore.
Fig. 7.5.2-1 : Example of a tunnel plant room
Consideration should be given to safe access to tunnel plant rooms
This may be possible during bore closures only. In some tunnels, lay-bys may be provided adjacent to
plant rooms to allow maintenance vehicles to stop safely, even without tunnel closure.

7.5.3. Splitter walls
Between the exit portal and the neighbouring entry portal of two uni-directionally used tubes, a
substantial air recirculation may take place, depending on the local geometry and wind direction. The
same problem exists between exit portal and fresh air intake of a semi-transverse ventilation station.
http://tunnels.piarc.org/en/structural-facilities/other-facilities.htm 8 / 9
PIARC ROAD TUNNELS MANUAL PIARC

In short tunnels with high self-ventilation this may be of no concern, but in longer tunnels this effect
should be reduced. Depending on the circumstances, the splitter wall may need to extend
approximately 20 to 40 m from the portal. Further details are given in Section IV.2.3 "Recirculation"
of report 1995 05.02.B "Road tunnels emissions, environment, ventilation".

http://tunnels.piarc.org/en/structural-facilities/other-facilities.htm 9 / 9








ROAD TUNNELS MANUAL




8. EQUIPMENT AND SYSTEMS










All rights reserved. World Road Association (PIARC)

PIARC ROAD TUNNELS MANUAL PIARC

8. Equipment and systems

If tunnels are longer than a few hundred metres, specific equipment is required to enhance safety to the
users, both in normal situations and in case of accidents.
To reduce the risks of accidents and limit the possible consequences, but also to keep an adequate
level of comfort to the users, a large variety of equipment can be installed. Chapter 7 of the report
05.06.B "Reduction of operating costs of road tunnels" discusses road tunnel equipment and Chapter 3
of the report 2008R15 "Urban road tunnels" provides details for the design and refurbishment of
equipment.
A significant amount of electric power is required to feed the equipment installed in the tunnel. The
electrical power supply systems (Section 8.1) must provide enough power in the case of normal and
emergency conditions. This also means that the system must work even in the case of blackouts, in
order to feed at least the equipment which is absolutely necessary. The status of this equipment should
also be monitored. For this reason, a SCADA system (Section 8.2) may be implemented.
A first type of equipment is the communication and alert systems (Section 8.3). This includes systems
used to check periodically the conditions in the tunnel and also to make the operator aware of a
possible danger or an accident. Together with systems for surveillance and control of traffic (Section
8.8), some detection systems can be installed. These include automatic incident detection and
smoke/fire detection. This information may also come directly from people involved, through alarm
push button or emergency telephones. The latter also allows a communication between people in the
tunnel and control personnel. This is useful for the control personnel to have additional information
with respect to locations, status of people, etc. but also to supply information to people in the tunnel.
This kind of equipment also includes systems used to alert the users in the tunnel or to coordinate the
intervention. Loudspeakers and radio-retransmission of public FM broadcasts, frequencies of operators
and emergency services can be used for these purposes.
To guarantee comfort to the users and reduce the risks of accident it is important to obtain adequate
visibility and reduced concentration of contaminants. For these purposes, an adequate lighting system
(Section 8.4) and ventilation system (Section 8.5) are necessary. Ventilation is also crucial in the case
of emergency conditions, as it affects both the fire development and smoke propagation. Depending on
the traffic and the tunnel length the ventilation can be only natural, only mechanical or mixed
natural/mechanical (i.e. natural in ordinary conditions and mechanical in emergency conditions). An
additional element to manage risk is signalling (Section 8.9). This is important in order to highlight
possible obstacles or danger, but also to help finding the emergency exits, alarm pushbutton,
extinguishers, etc.
In the case of accidents, equipment is required to extinguish fire. This includes fire-fighting equipment
available in the tunnel to the users and the emergency teams (Section 8.6) and fixed fire fighting
systems (Section 8.7), which automatically intervene. In these conditions, barriers (Section 8.10) are
important to prevent users outside the tunnel at the time of accident from entering the tunnel.

Contributors
This Chapter was written by Working Group 1 and Working Group 4 of the C4 committee (2008-
2011) in which:
Antonio Valente (Italy) coordinated the work
Jean-Claude Martin (France) authored Sections 8.0, 8.1 and 8.2
Arthur Kabuya (WG4 : Belgium) and Jean-Claude Martin (France) authored Section
8.3 excepts Sections 8.3.4. Automatic incident detection and 8.3.5. Fire/smoke detection :
Purpose of fire and smoke detection that were authored by Arthur Kabuya (WG4 : Belgium)
Jean-Claude MARTIN (France) authored Section 8.4
Antoine Mos (WG4 : France) authored section 8.5 Ventilation
Art Bendelius (WG4 : USA), authored Section 8.6 Fire fighting equipment
http://tunnels.piarc.org/en/equipment-systems/ 2 / 19
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/equipment-systems/ 3 / 19
Arnold Dix (WG4 : Australia) and Fathi Tarada (WG4 : UK) authored Section 8.7 Fixed fire
fighting systems
Jean-Claude MARTIN (France) authored Sections 8.8, 8.9 and 8.10
Fathi Tarada (UK) and Ignacio del Rey (Spain) coordinated and reviewed the WG4 inputs
Jean-Claude MARTIN (France) coordinated and reviewed the WG1 inputs
Fathi Tarada (UK) reviewed the EN version.
PIARC ROAD TUNNELS MANUAL PIARC

8.1. Electrical power supply

Most of the tunnel equipment and systems requires electrical energy to operate. Therefore, equipment
for supplying power to the tunnel must be installed. This installation has to satisfy two essential
requirements:
Supply safe and sufficient power to allow all the equipment to operate
Meet the needs under all operational situations (normal, degraded, critical).
The power required for supplying a tunnel is directly related to the nature and number of equipment
installed in it. Depending on the amount of electrical energy required (kWh), power may be supplied
in low voltage or high voltage.
Each country has its own regulatory requirements with regard to tunnels and a specific structure in
terms of distribution networks: therefore, the architectures retained may be significantly different in
tunnels with similar characteristics. However, some identical principles can be noted, such as:
The presence of a standby power supply (double supply, diesel generator, etc.),
The installation of a device allowing remedying a total loss of power supply. This system
(uninterruptible power supply (UPS), diesel generator...) supplies electricity to equipment
critical for safety, during a limited period of time.

http://tunnels.piarc.org/en/equipment-systems/electrical-power-supply.htm 4 / 19
PIARC ROAD TUNNELS MANUAL PIARC

8.2. Supervisory Control And Data Acquisition systems (SCADA)

In a road tunnel, the equipment plays a vital role for the safety users. The operator therefore has to
monitor such equipment continuously for determining their status (working or fault) and/or their
operating mode (automatic, manual or stopped).
Many devices are servo-controlled by sensors and operate automatically (lighting, ventilation...)
according to pre-determined thresholds. Others are activated or deactivated depending on the operating
conditions. It is thus useful for the operator to be able to remote control them (signalling, variable
message signs, barriers, ventilation, lighting, pumps ...).
Lastly, since the equipment may be operated very differently (continuous, occasional, or very rare), it
is necessary for the operator to have information on the operational duration (hour used) for each of
them.
These functions of surveillance, control-command and data archiving are very often performed by a
single system: the Supervisory Control And Data Acquisition system (SCADA).
Several SCADA systems are available worldwide and their performance is being improved constantly.
The systems installed in road tunnels of comparable characteristics are therefore rarely completely
identical, even for the tunnels of the same operator. Even so, the architectures follow certain rules that
are widely prevalent:
Collection of information via networks in loop
Intelligence (programmable logic control notably) installed near the equipment
Separation of networks: acquisition, transport and supervision
Redundancy of certain sub-assemblies for improving their dependability.
http://tunnels.piarc.org/en/equipment-systems/scada.htm 5 / 1
PIARC ROAD TUNNELS MANUAL PIARC

8.3. Communication and alert systems

It is important for the operator to be able to communicate with the user. It should be possible for this
communication to take place in both directions - operator to user and user to operator. These
exchanges should be possible in all operational situations: normal, degraded or critical.
Several devices allow ensuring this communication function (the alert is considered as a particular
form of communication). They do not all offer the same functionalities: some of them allow
establishing a transmission from user to operator (alarm pushbuttons, automatic alarm while using
certain evacuation systems ...) while others allow a transmission from operator to user (messages
broadcast on FM frequencies, loudspeakers). Only one of them allows a full exchange (emergency
telephones).

8.3.1. Emergency telephones
Emergency telephones allow a user, victim of an accident in tunnel, to contact the control-command
centre in charge of the tunnel. In addition to establishing a voice link, the use of an emergency
telephone by a user also gives his precise location.
These emergency telephones are installed at fixed intervals on boxes or in emergency stations of
different types. The distance between two emergency telephones is often specified by regulations and
therefore varies from one country to another.
The structure of this device is quite simple. The emergency telephones in the tunnel are connected to a
centre that receives the calls made from the tunnel. Usually, this centre is located in the control-
command centre of the tunnel and sometimes in the premises of police services under whose
jurisdiction the tunnel is placed.

8.3.2. Alarm pushbuttons
Alarm pushbuttons allow a user to send an alarm to the control-command centre in case of accident in
tunnel. Being not very expensive equipment, it can be installed at frequent intervals.
This device is not much used because to a certain extent, it duplicates the emergency telephone and
moreover, it does not allow a two-way communication between the user and the control-command
centre.

8.3.3. Automatic alarm when emergency systems meant for users are used
As mentioned above, the user has access to several devices that he can use in tunnel, particularly in
emergencies: emergency telephones and sometimes alarm pushbuttons. He also has fire extinguishers
and, in most tunnels, emergency exits.
It is essential for the operator to be informed as early as possible when a user operates one of these
devices, in order to take adequate actions. This is not difficult when emergency telephone and the
alarm pushbuttons are installed because, very often, the control-command centre receives the call or
the alarm information. When the emergency telephones are terminated in a place other than the
control-command centre, procedures have to be set up so that the service receiving the call informs the
control-command centre at once.
In the case of extinguishers and emergency exits, sensors are very often installed for detecting a
change of status and communicating this information to the control-command centre by using the
SCADA system. The operator is then informed that a user in tunnel is requesting assistance.
For the fire extinguishers, the information taken into account is often the action of removing the
equipment from its support or opening the door in the emergency station etc. For the exits, the
http://tunnels.piarc.org/en/equipment-systems/communication.htm 6 / 19
PIARC ROAD TUNNELS MANUAL PIARC

information taken into account may be the opening of the door or the detection of a presence in the
exit or both of these.

8.3.4. Automatic incident detection
When a tunnel is equipped with a video-surveillance system (refer Section 8.8), the images coming
from the tunnel and its vicinity are shown by displays installed in the control-command centre. It is
difficult for the operator to monitor more than a few displays simultaneously with a constant alertness
during several hours.
For remedying this difficulty, operators are increasingly using automatic systems for detecting an
incident. In certain countries, the use of such equipment is even obligatory for specific tunnels.
Type and Function of Automatic Incident Detection
Automatic incident detection (AID) is normally based on computer-based analysis of video image
streams generated from cameras set up to view tunnel traffic. A number of algorithms are available
which can detect a range of incidents, including:
stopped vehicles
vehicles moving in the wrong direction
speed drop
slow vehicle
pedestrians
debris in road tunnel
smoke
flames
entry into restricted zones
Since serious vehicle fires normally develop after traffic has stopped (e.g. following an accident), it
follows that a'stopped vehicle' alarm from an AID system can be expected to precede alarms triggered
by other systems, such as temperature and smoke detectors. This early warning provided by AID
allows time for tunnel operators to confirm the nature and location of the incident, and to allow
effective intervention., This may be through the choice of an optimal choice of ventilation
configuration, prevention of secondary accidents through operational measures, rapid warning to
motorists upstream of the incident. It also gives opportunity to call the emergency services, closing of
access, messages on variable message signs and on the radio, call to breakdown lorry, advice to exit
the tunnel, etc.
Video smoke detection systems are described in Section 6.3.3 "Currently Used Methods" of report
05.16.B 2006.
Video-based AID systems can provide real-time information on the traffic flow, volume and speed.
They can record pictures at the origin of the incident and can interact with other systems such as the
Supervisory Control and Data Acquisition (SCADA) system. Video-based AID systems normally
include cameras, a video image processing system processing images from one or several cameras,
Internet Protocol (IP) video encoders and decoders on IP to return images to monitors or computer
displays. Furthermore a video management system composed of one or two redundant servers
providing video and othersfunctions (recording of video mass and AID incident, collecting and storing
real-time traffic data and traffic events, interfacing with the tunnel SCADA system), network
equipment and communications lines(optical fibres, coaxial and Unshielded Twisted Pair cables).
Design and Commissioning of AID Systems
The design of AID systems in tunnels should be undertaken with due account of the following issues:
Choice of incidents to be detected
Detection accuracy (i.e. minimisation'false negatives' in detection incidents)
Minimisation of false alarms (i.e. minimisation of'false positives')
http://tunnels.piarc.org/en/equipment-systems/communication.htm 7 / 19
PIARC ROAD TUNNELS MANUAL PIARC

Location of existing cameras in the tunnel
Geometric features of the tunnel
Access for maintenance staff
Bright sunlight'bleaching' near portals
Sunlight movements in the vicinity of portals
Changes caused by the passage of vehicles in the tunnel (lights, occlusion by high vehicles)
Change of lighting regime in the tunnel (lighting on/off)
Reflections in the tunnel
In case of an AID system integrating IP video stream, the capacity of the existing IP network
should be checked to ensure there is sufficient bandwidth available
The 2009 Routes/Roads article "Fire Detection Systems in Road Tunnels - Lessons Learnt from the
International Research Project" concluded that "to deal with obstructions, most manufacturers of field
of view detectors recommend two detectors covering the same area from different angles, such as from
both directions within a tunnel". Multiple cameras may also be required for redundancy purposes, in
case of camera failure. Typically, the camera fields of view are designed to overlap, such that failure
of any one camera can be compensated through the images from neighbouring cameras.
Section IV.2.1. "Traffic Incident Detection Devices" of report 05.15.B 2004 suggests that camera
locations can vary from 30 to 150 meters if they are used for automatic incident detection.
The performance of an AID system performance depends to a great extent on successful
commissioning and calibration, prior to deployment. Experience from tunnel installations indicates
that such commissioning and calibration can take several months to undertake.

8.3.5. Fire/smoke detection : Purpose of fire and smoke detection
Fire and smoke detectors are always an integral part of a control loop which is set up by sensors, alarm
triggering equipment, transmission cabling, evaluation units, etc., and which taken together are
generally referred to as a fire alarm system.
Fire and smoke alarm systems in road tunnels are designed to detect fires and smoke production as fast
as possible so that safety equipment and procedures can be activated without delay. Their main
objectives should be:
informing tunnel users at the earliest opportunity so to enable them to organize their self-
evacuation and self-rescuing;
passing on all the possible fire parameters to the operational tunnel staff in order to enable them
to change ongoing tunnel operations (traffic control and ventilation systems) according to the
emergency procedures (so-called fire mode), and to call in the rescue services, medical staff, fire
brigade, police, etc.
to identify the locations of the fire or incident, in order to direct rescue service resources to the
appropriate places to assist motorists, for example.
Principles of fire detection
Basically, the fire detection principles are based on the perceived parameters determined by the fire
i.e. heat, smoke, radiation and production of typical chemical substances. Therefore, the fire detecting
sensors can be classified as :
Heat detectors : all material the characteristics of which are sensitive to an increase of heat
energy whenever this implies a temperature rise. Examples are sensors which measure
temperature differences with a reference temperature or rate of temperature rise, glass-fibre
cables where its light transmission characteristics are a function of temperature, linear sensor
cable with built in electronic circuit, etc.;
Flame detectors based on their sensitivity of infrared and/or ultraviolet wavelength spectrum;
Smoke detectors which measure the extinction of a infrared light beam through CO and CO
2

ionisation areas;
http://tunnels.piarc.org/en/equipment-systems/communication.htm 8 / 19
PIARC ROAD TUNNELS MANUAL PIARC

Detectors which combine different types of sensors.
Each of these detectors has their own specific application domain, related to its response time,
robustness, reliability, etc.
Recently video AID systems have proven to be very efficient and fast in detecting fires. In fact, they
detect incident any object or vehicle which does not conform to the normal expected traffic stream.
The cameras can be automatically turned towards the incident scene, which enables the operator to
discover the very early start of a fire.
Fire/smoke detection systems are described in Section 6.3 "Fire detection" of the report 2006 05.16.B.
Requirements for Fire detection system
In a general way, fire detectors in road tunnels must be designed to withstand the following
environmental conditions: air velocities up to 10 m/s, reduced visibility resulting from diesel exhaust
fumes and abrasive wear stemming from tires and the road surface, increased and short-term
fluctuating concentrations of pollutants (carbon monoxide (CO), carbon dioxide (CO2), nitrogen
oxides and hydrocarbons), changing headlight intensities, engine heat and hot fumes vehicle exhaust
gases, electromagnetic interferences, mixed vehicular traffic (i.e., cars, small lorries, heavy load
lorries, buses and tankers) that will result in varying degrees of tunnel cross section obstruction.
It cannot be stressed enough that they must have a high degree of fail-safe operation and be able to
locate the fire as close as possible. It is advisable that the systems of fire detection possess certain
level of intelligence to avoid false alarms, because false alarms could entail significant expense to
rectify and even worse, may discourage the operators after a while run from paying attention to the
alarms.
Furthermore, it is imperative that the fire detection/alarm installation is reasonably priced, has low
operating costs and simple to maintain: refer Section 6.3 "Fire detection" of the report 2006 05.16.B.
Parameters dictated by Codes and Standards
The following parameters for automatic fire detectors are specified in national and international codes
and standards : maximum time for a fire to be detected, determination of the fire site location,
minimum fire load to be detected, approved detection methods, assembly points for fire alarms, details
pertaining to which tunnels should be provided with automatic fire alarm installations (e.g. length of
tunnel, tunnels with mechanical ventilation, tunnels that are not permanently monitored by personnel,
short tunnels with particularly high traffic densities).
A list of detailed reference material regarding fire detector parameters are described in codes and can
be found in Section 10 "References" of the report 2006 05.16.B.
Fire/smoke detectors currently in use
The efficiency of fire detection is not only based on the type of devices (temperature, light beam
extinction, ionisation, etc.), but also on the detection strategy which and been developed, which
includes the number of sensors and their level of surveillance in the tunnel.
Automatic incidents detection, analysis of video images including AID systems, closed-circuit
television (CCTV) observation, equipment such as fire extinguishers which activate alarms by the
removal, as well as the emergency telephones are generally good means to raise an alarm.
Many detectors in use are based on heat and on the rate of temperature rise. When well calibrated, this
type of system generates only few false alarms, but may have a slow reaction rate. Detectors based on
smoke obscuration give early signals but have suffer more false alarms because of smoke exhaust
from diesel vehicles: refer to Section VI.3.1 "Fire detection" of report 05.05.B 1999.
The 2009 Routes/Roads article "Fire Detection Systems in Road Tunnels - Lessons Learnt from the
International Research Project" deals with fire/smoke systems of road tunnels such as linear detection
of the heat, optical detection of flames, detection by video imaging, punctual detection of heat and
http://tunnels.piarc.org/en/equipment-systems/communication.htm 9 / 19
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/equipment-systems/communication.htm 10 / 19
smoke detection by air sampling system. It concludes that the system of air sampling gives a good
performance in terms of response time and ability to accurately locate and monitor a fire and the effect
on road environment, when taking into account overall performance including false alarms,
maintenance and fire detection. The information from this study can be used to determine the most
appropriate technology for tunnel fire detection.

8.3.6. Radio-retransmission of public FM broadcasts, frequencies of operators and
emergency services
A tunnel is a closed and confined space that very often does not allow the propagation of radio waves
from broadcasters outside the tunnel. For re-establishing this propagation, it is necessary to install the
equipment that allows the retransmission of the needed frequencies. Several types of services can be
retransmitted:
Rescue services (fire brigade, police...)
Operator (patrols, maintenance crews, taxis, bus companies ...)
Public FM broadcasts
Public DAB broadcasts (Digital Audio Broadcasting)
Cell phones.
There are a very large number of services whose frequencies can be retransmitted but they are not all
of them covered, because of problems of cost, not to mention feasibility. As a general rule, one can
find certain frequencies used by the rescue services, frequencies used by the operator, a few FM and or
DAB frequencies and frequencies of cell phone operators.
When one or more Radio frequencies are retransmitted, a device is installed that allows inserting pre-
recorded messages. In case of need, these radio broadcasters are interrupted and messages regarding
the tunnel are broadcasted for the attention of users, in order to give them indications regarding the
steps the operator wants them to follow.
A radio-retransmission installation in tunnel is essentially composed of:
An antenna
A transmission/reception unit that allows transmitting from the outside into the tunnels technical
room that needs to be cooled.
A transmission/reception unit that allows transmitting from the tunnel to the outside (not for
public broadcasters but for emergency services etc.)
A radiating unit in tunnel (radiating cables or antennas).

8.3.7. Loudspeakers
There are not many devices that allow addressing the user directly for giving information or asking the
tunnel users to behave in a particular manner. For solving this problem, some tunnels are equipped
with loudspeakers. In practice, depending on how they are used, the loudspeakers offer different
functionalities. The following points can be mentioned in particular:
Loudspeakers installed at fixed intervals in the tunnel, to give information and instructions to
users whose vehicle has stopped inside the tunnel
Loudspeakers (or sirens) installed at fixed intervals inside the tunnel that emit a sound signal
indicating a danger
Loudspeakers (or sound beacons) installed near emergency exits that providing information to
users about to use an exit and where it is located.
These devices are not however widely used at present. Their use must be studied for each case and
often, they are suited for very specific tunnels (very dense traffic, length, etc.).
PIARC ROAD TUNNELS MANUAL PIARC

8.4. Lighting

In the majority of tunnels the natural penetration of light does not allow satisfactory conditions of
visibility for the users. It is therefore necessary to install artificial lighting offering satisfactory
conditions of visibility and comfort to the users.
In terms of functionalities, the lighting installation must allow for:
A normal lighting that provides appropriate visibility to the users, day and night
A standby lighting that provides minimum visibility to the users for allowing them to leave the
tunnel in their vehicles in case of power outage.
A lighting installation should be designed respecting several criteria, notably those relating to:
Level of luminosity and lighting on the pavement
Level of luminosity and lighting on the side walls and columns
Values of uniformity for the different operating regimens
Values of glare.
Several types of installations are possible; the most common are symmetrical lighting and counter-
flow lighting. Depending on the characteristics of the tunnel and the objectives defined, the lighting
fittings may be installed in one or more lines, above the road, on top of walls of the tunnel...
http://tunnels.piarc.org/en/equipment-systems/lighting.htm 11 / 19
PIARC ROAD TUNNELS MANUAL PIARC

8.5. Ventilation

Ventilation in tunnels has two functions:
In normal operation, it ensures sufficient air quality in the tunnel, generally by diluting
pollutants;
In a fire situation, it should make the environment as safe as possible to the tunnel users and
rescue services by controlling the flow of smoke in an appropriate way : see Sections 1.6 & 1.7
of the Report 05.16.B : "Role of the ventilation system during the self-evacuation phase" and
"Role of the ventilation system during the fire-fighting phase".
Historically, the first reason for installing ventilation systems in tunnels was the reduction of pollution
levels. Although the emissions of pollutants by road vehicles have decreased dramatically over the last
decades, this function is still important and must be paid close attention at the design stage. In some
cases, natural ventilation due to the piston effect of moving vehicles may be sufficient to fulfil the air
quality requirements in normal operation. The need for a mechanical ventilation system is assessed
considering the length of the tunnel and the traffic type (bidirectional or unidirectional) and conditions
(possibility of congestion) : see Technical Report 2004 05.14.B : Road tunnels: Vehicle emissions and
air demand for ventilation. This report will be replaced by a new report to be published soon.
The same factors determine the requirements for ventilation in emergency situations, especially fire.
The presence of other equipment or facilities, emergency exits for example, should also be taken into
account. Natural ventilation might be sufficient in some cases, but mechanical ventilation is often
required for tunnels over a few hundred meters in length.
Different ventilation strategies may be used in tunnels. The choice between them is generally guided
essentially by fire safety considerations; the use of the system in normal operation is adjusted to suit :
see Chapter V "Ventilation for fire and smoke control" of report 05.05.B 1999
The longitudinal strategy consists in creating a longitudinal air flow in the tunnel, in order to push all
the smoke produced by a burning vehicle on one side of the fire. If users are present on that side, they
may be affected by the toxic gases and reduced visibility, so the use of this strategy in bidirectional
and/or congested tunnels requires great caution. The minimum air velocity for successful smoke
control depends on the design fire size and tunnel geometry (slope, cross-sectional area).
The transverse strategy takes advantage of the buoyancy of fire smoke: smoke tends to concentrate in
the upper part of the tunnel space, from where it can be mechanically extracted. The system is
designed so as to preserve a fresh air layer in the lower part of the cross-section (correct visibility, low
toxicity) which allows self-evacuation. It is therefore important to keep the longitudinal air flow as
low as possible in the fire region to avoid de-stratification and excessive longitudinal spread of smoke.
This strategy is applicable to any tunnel, but the design, construction and operation of the system are
more difficult and expensive.
The ventilation design process includes the computation of the minimum acceptable capacity of the
system in terms of thrust and/or flow rates, the design of the ventilation network and the choice of
appropriate ventilation equipment Chapter 4 of the Report 2006 05.16.B : Ventilation and its
appendices 12.3 "J et Fan calculation procedure", 12.4. "Smoke dampers" and 12.6. "Sound impact of
jet-fans". Ventilation equipment should meet a number of specifications, including resistance to fire
and acoustic performance.
The design of appropriate ventilation control scenarios for each possible fire situation is a very
important part of the process : see Technical Report 2011 R02 : Road tunnels: Operational strategies
for ventilation. These scenarios can be simple, especially when the longitudinal strategy is applied, or
involve a large number of measurement and ventilation devices in complex, transverse-ventilated
tunnels. The optimisation of ventilation control for air quality considerations during normal operation
is crucial to reduce energy consumption; it is an important issue since this consumption represents a
significant part of the operational cost of a tunnel.
http://tunnels.piarc.org/en/equipment-systems/ventilation.htm 12 / 19
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/equipment-systems/ventilation.htm 13 / 19
The interactions of the ventilation system design with other elements of a tunnel are numerous and
diverse. In the case of transverse ventilation, for example, the required flow rates may impact the
excavated section, with a potentially important impact on the construction cost. Ventilation also
accounts for a large part of a tunnel's power supply requirements. It interacts closely with other safety
equipment such as fire detection and fire fighting systems : see Chapter 5 "Fixed fire fighting systems
in the context of tunnel safety systems" of the Report 2008 R07.
The environmental issues linked to ventilation, besides the energy consumption and the related carbon
footprint, are linked to the localised, concentrated discharge of polluted air from the portals and stacks.
Reducing their impact on the tunnel surroundings is part of good environmental design : see
Section 4.3. "Tunnel air dispersion technique", Section 4.6. "Operational aspects" and Appendix
D. "Overview of dispersion modeling in designing ventilation systems" of the Report 2008 R04.
Finally, other parts of a tunnel than the main traffic space may require ventilation, most notably the
emergency exits : see Section 5.3. "Escape route design" of report 05.16.B 2006.
PIARC ROAD TUNNELS MANUAL PIARC

8.6. Fire-fighting equipment for the users and emergency teams

8.6.1. Objectives
The primary objective of fire fighting equipment in a road tunnel is to provide the means to fight a fire
within the tunnel with minimum impact on the users, the emergency responders and the structure.
The World Road Association (PIARC) has addressed the systems required for the fighting of fires in
road tunnels in numerous publications. This has been primarily in two publications; Technical Report
05.05.B 1999 "Fire and Smoke Control in Road Tunnels" and Technical Report 05.16.B 2007
"Systems and Equipment for Fire and Smoke Control in Road Tunnels" . In addition these issues were
also covered in several Committee Reports to World Road Congresses specifically those held in
Vienna (1979), Sydney (1983), Brussels (1987), and Marrakesh (2001).
The systems critical to the ability to fight a fire within a road tunnel include: detection, alarm, radio
communications, emergency telephone, closed circuit television, loudspeakers, water supply and
distribution, fixed fire fighting, portable fire extinguishers and emergency ventilation. These systems
must be planned, evaluated, designed and installed in a careful thorough integrated manner to assure
that the systems are truly compatible and that the fire life safety of the tunnel is not being
compromised or being over provided.
Many of these elements of the tunnel fire fighting systems are addressed in other chapters of this
manual. The systems included in other chapters provide detection (Section 8.3.5), fixed fire fighting
(Section 8.7), fire alarms (Section 8.3), emergency telephones (Section 8.3.1), closed circuit television
(Section 8.2), loudspeakers (Section 8.3.7), radio communications (Section 8.3), emergency
ventilation (Section 8.5).
The systems addressed in this section relate to those systems provided for fire fighting in road tunnels
by the users (motorists), the operating agency and the fire brigade. These include systems designed to
furnish a supply of water through a fire line (standpipe) and fire hydrants (hose valves) and it they
include the installation of portable fire extinguishers within the road tunnel.

8.6.2. Water supply
A water supply system, including water mains, fire lines or standpipes, is required to provide water for
fire fighting within the tunnel (through hydrants or hose valves) and to possibly provide water for a
fixed fire fighting system (Section 8.7) if installed in the tunnel (see Section VI.3.3 "Water supply" of
report 05.05.B 1999). The source of water can be from a water distribution system or from a water
tank.The required system pressure must match the requirements of the responding fire brigade.

8.6.3. Fire hydrants
Fire hydrants (hose valves) are required within the road tunnel to provide a point of connection for the
Fire Brigade to attach fire hose and gain access to the water supply. The hydrants should be installed
at regular interval spacing within the tunnel (see Section VI.3.3 "Water supply" of report 05.05.B
1999).The hydrant connections must be compatible with the responding local fire brigade(s).

8.6.4. Portable fire extinguishers
Portable fire extinguishers are provided at regular intervals within road tunnels to allow the (motorists)
and operating personnel to fight a modest size fire within the tunnel prior to the arrival of the fire
services (see Section VI.3.2 "Fire extinguishers" of report 05.05.B 1999).


http://tunnels.piarc.org/en/equipment-systems/fire-fighting-equipment.htm 14 / 19
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/equipment-systems/fire-fighting-equipment.htm 15 / 19
8.6.5. Fire hose
Fire hose reels are installed in road tunnels in some countries, however this is not a universal trend as
other countries allow the fire brigade to bring their own hose into the tunnel for each incident (see
Section VI.3.3 "Water supply" of report 05.05.B 1999).
PIARC ROAD TUNNELS MANUAL PIARC

8.7. Fixed Fire Fighting Systems

The Technical Report 2008 R07 "Road Tunnels: An Assessment of Fixed Fire Fighting Systems"
summarises the World Road Association's views on Fixed Fire Fighting Systems (FFFS), and its
recommendations pertaining to the applicability, selection and operation of such systems.
In a rapidly developing fire, smoke can quickly compromise the ability of users to self-rescue, while
rapidly elevating temperatures can make the tunnel untenable and destroy safety systems. An FFFS
has the potential to reduce the rates of fire growth and spread, thereby assisting the safety of motorists
and the emergency services during the self-rescue and assisted-rescue phases of a fire. Other potential
benefits of an FFFS are the protection of the tunnel assets from fire damage, and to avoid or reduce the
road network interruptions that may occur while a tunnel is being repaired following a fire incident.
Except where the installation of an FFFS is prescribed by a country's tunnel design guidelines, the
following steps are recommended to support the decision as to whether such a system should be
installed:
a feasibility study,
a risk analysis as outlined in the European Directive 2004/54/EC;
a cost-benefit analysis.
FFFS must be considered in the context of other critical safety systems such as ventilation. Rapid and
accurate incident detection and FFFS response are essential components to achieve the best possible
FFFS performance. The operational performance of FFFS can best be assessed through a system
engineering approach, including appropriate regimes for maintenance, testing and training. Careful
consideration must be made with respect to the effects of such systems on operational procedures and
maintenance budgets
Water-based deluge systems are by far the most common type of FFFS installed in tunnels at present.
Both low-pressure and high-pressure systems are available, with the latter having smaller droplet
sizes. Other water-based systems, including foam systems, have also been installed in tunnels. The
selection of the appropriate FFFS should be based on cost-benefit analysis.
Although tunnel FFFS are used regularly in some countries, they remain the exception rather than the
rule in road tunnels world-wide. While such systems can reduce the rates of fire growth and spread,
they also demand a higher level of maintenance and operational attention to ensure they function in an
optimal manner.
http://tunnels.piarc.org/en/equipment-systems/fixed-fire-fighting-systems.htm 16 / 19
PIARC ROAD TUNNELS MANUAL PIARC

8.8. Systems for surveillance and control of traffic

A traffic surveillance system is often installed when the level of traffic is very dense in a tunnel.
Usually, a video-surveillance system is used, supplemented sometimes with counting devices. A
video-surveillance installation offers the operator the possibility of controlling the traffic conditions in
the tunnel in real time. In case of degraded operation, it allows viewing the concerned incident zone so
that the needs may be rapidly evaluated.
Video-surveillance is thus a very valuable tool for the operator because it allows him, on the one hand,
to watch continuously the incidents inside the tunnel and on the other hand, to react rapidly in case of
need. However, in order to make full use of a video-surveillance installation, it is essential to maintain
a human presence, if possible continuously, at the control-command centre.
A video-surveillance is generally quite simple in its conception. Cameras placed at regular intervals in
the tunnel provide a complete coverage of the tunnel and its surroundings. The images are then
grouped and transmitted by networks that may or may not be dedicated, to the control-command
centre of the tunnel. The images are then received and viewed on the displays.
http://tunnels.piarc.org/en/equipment-systems/traffic-surveillance-control.htm 17 / 19
PIARC ROAD TUNNELS MANUAL PIARC

8.9. Signposting

Signposting is one of the means available with the operator for communicating with the user.
For a given type of road, one can see in a tunnel the same signposting as in open air:
Fixed directional signposting
Fixed police signposting (danger signs, speed limits and destination)
Variable signposting (lane allocation signs, variable message signs).
The different safety devices available to the users in tunnel (emergency telephones, extinguishers,
emergency exits...) require in addition a specific safety signposting.
The principal problem faced for signposting in tunnel is the location. In fact, the geometrical
characteristics of an underground tunnel are optimised and increasing the transversal section will lead
to significant surplus costs. In practice, a compromise must be found between the need for good
visibility of the signs (therefore, panels sufficiently large) and the space available.
http://tunnels.piarc.org/en/equipment-systems/signposting.htm 18 / 19
PIARC ROAD TUNNELS MANUAL PIARC

8.10. Barriers

When a serious event (accident, fire, etc.) occurs in a tunnel, it must be possible to prevent at an early
stage the users from entering into the tunnel. In fact, a device preventing efficiently and rapidly entry
into the tunnel can allow not sending into a potentially dangerous situation users who are outside and
will also help prevent further accidents underground.
In many countries, experience shows that if the tunnel is closed simply by means of a stop signal
placed outside before the entrance, it is not quite effective. Therefore, this stop signal is often
combined with barriers and variable message signs allowing the users to be informed of the reasons
for closure.
The device closing the tunnel can be activated from the control-command centre or automatically in
tunnels that are not monitored continuously.
The closing device is meant for being used in emergency situations but it can also be used in other
situations, particularly during scheduled closures for maintenance interventions.
http://tunnels.piarc.org/en/equipment-systems/barriers.htm 19 / 19








ROAD TUNNELS MANUAL




9. TUNNEL RESPONSE TO FIRE










All rights reserved. World Road Association (PIARC)
PIARC ROAD TUNNELS MANUAL PIARC

9. Tunnel response to fire

The materials used in the structures and equipment of a tunnel should neither burn nor produce large
quantities of toxic smoke if a fire occurs in the tunnel. In addition, in such an event, the structures
must not collapse while users or emergency services personnel remain inside the tunnel and critical
safety equipment must continue to function at least until evacuation and fire-fighting operations are
completed.
These general objectives are dependent upon the reaction to fire of the materials and the resistance to
fire of the structures and equipment:
The reaction to fire of a material characterises its ability to take part in a fire to which it is
exposed, including by its own decomposition (e.g. combustion).This is discussed in Section 9.1.
The resistance to fire of a structure or a piece of equipment characterises its ability to keep on
fulfilling its function despite the development of a fire. Structures are considered in Section 9.2,
while equipment is considered in Section 9.3.

Contributors
This Chapter was written by Robin Hall and Working Group 4 of the C4 committee (2008-2011) in
which:
Robin Hall (UK) coordinated the work and wrote the full chapter
Fathi Tarada (UK) and Ignacio del Rey (Spain) reviewed the full chapter.
http://tunnels.piarc.org/en/response-fire/ 2 / 7
PIARC ROAD TUNNELS MANUAL PIARC

9.1. Reaction of Materials to fire

The materials used in tunnel construction have to possess adequate resistance to fire to ensure integrity
during evacuation and fire fighting.
Section VII.3 "Fire reaction of materials" of technical report 05.05.B "Fire and Smoke Control in
Tunnels" discusses the fire properties of tunnel materials, indicating that the specifications set for
materials should include requirements concerning their properties in the event of a fire. Desirable
properties include:
low flammability, which reduces rate of fire spread;
low heat output, which reduces the fire size and hence the structural and life-safety impact; and
minimisation or elimination of toxic products of fire.
Gases generated by a fire cannot be prevented, but the risks can be mitigated by the choice of the
material and also the design of safety features, such as escape routes, to reduce exposure. Attention is
also drawn to the properties of wall-covering materials, including tiles and paints, waterproofing or
lighting equipment. The specifications set for such materials should also include requirements
concerning their properties in the event of a fire.
The possibility that materials might produce chemically corrosive or toxic substances during
combustion and that these might penetrate the surface of the concrete and cause subsequent corrosion
should also be considered. This also applies to any coatings that might be used. In case of
polypropylene fibres being specified to reduce the risk of spalling, the issue of concrete durability after
any significant fire event should be considered. This is because there will be increased porosity within
the concrete where fibres have melted, leading to increased vulnerability to carbonation or chloride
attack.
Road surfaces may be constructed from cement concrete or asphalt. The Route/Roads article "Effects
of Roadway Pavement on Fires in Road Tunnels" discusses the properties of these materials from a
fire safety point of view. Of these, cement concrete is the only one which is not combustible and does
not raise any question as to its use in tunnels. However, studies and experiences from real fires have
shown that, in phases when safety of people is concerned, asphalt does not add significantly to the fire
size (both heat release rate and total fire load) in the case of a road tunnel fire. Open asphalt is not
advisable in tunnels as a fuel spillage will be stored below the road surface.

http://tunnels.piarc.org/en/response-fire/reaction-materials.htm 3 / 7
PIARC ROAD TUNNELS MANUAL PIARC

9.2. Resistance to fire of structures

The fire resistance of a structure can be characterised by the time which elapses between the start of a
fire and the time when the structure does not ensure its function any longer, due to unacceptable
deformation or collapse.
Chapter 7 "Design Criteria for Structure Resistance to Fire" of technical report 2007 05.16.B "Systems
and Equipment for Fire and Smoke Control in Road Tunnels" summarises the objectives of structural
fire resistance in tunnels as follows:
1. people inside the tunnel shall be able to self-evacuate (self-rescue) or be assisted to a safe
place (main objective)
2. rescue operations shall be possible under safe conditions
3. protective measures shall be taken against collapse of tunnel structure and loss of property to
third parties
A supplementary objective is to limit the time during which traffic will be disrupted due to the repairs
after a fire.
An overview of the subject was published in Chapter VII.4 "Fire resistance of structures" of technical
report 1999 05.05.B "Fire and Smoke Control in Tunnels".
The fire resistance of structures is described in relation to different time-temperature curves.
Figure 9.2-1 shows the ISO 834 curve, the Dutch RWS curve, German ZTV curve and a
French'increased' Hydrocarbon curve, HCinc, in which the temperatures are multiplied by a factor of
1300/1100 from the basic Hydrocarbon (HC) curve of Eurocode 1 Part 2-2.
Figure 9.2-1: Temperature versus time curves for ISO, HC
inc
, ZTV and RWS standards (Routes/Roads
No. 324)
Design criteria for resistance to fire in tunnels have been agreed between the World Road Association
(PIARC) and the International Tunnelling Association, as presented in the Routes/Roads article
"PIARC Design Criteria for Resistance to Fire for Road Tunnel Structures" (2004), and published as a
PIARC recommendation in Chapter 7 "Design Criteria for Structure Resistance to Fire" of technical
report 2007 05.16.B. A summary of the proposals is presented in Table 9.2-2.
http://tunnels.piarc.org/en/response-fire/resistance-structures.htm 4 / 7
PIARC ROAD TUNNELS MANUAL PIARC


Table 9.2-2: PIARC and ITA recommendations
Notes
(1) 180 min may be required for very heavy traffic density of lorries carrying combustible goods.
(2) Safety is not a criterion and does not require any fire resistance (other than avoiding progressive
collapse).Taking into account other objectives may lead to the following requirements:
ISO 60 min in most cases;
no protection at all if structural protection would be too expensive compared to cost and
inconvenience of repair works after a fire (e.g. light cover for noise protection).
(3) Safety is not a criterion and does not require any fire resistance (other than avoiding progressive
collapse).Taking into account other objectives may lead to the following requirements:
RWS/HC
inc
120 min if strong protection is required because of property (e.g. tunnel under a
building) or large influence on road network;
ISO 120 min in most cases, when this provides a reasonably inexpensive way to limit property
damage;
no protection at all if structural protection would be too expensive compared to cost and
inconvenience of repair works after a fire (e.g. light cover for noise protection).
(4) Other secondary structures: should be defined on a project-specific basis.
(5) In case of transverse ventilation.
(6) Shelters should be connected to the open air.
(7) A longer time may be considered if there is a very heavy volume of lorries carrying combustible
goods and evacuation from the shelters is not possible within 120 min.
The consequences of failure will influence the requirements for fire resistance. This depends on the
type of tunnel. In an immersed tunnel, for example, a local collapse can cause the whole tunnel to be
flooded whereas local collapse in a cut-and-cover tunnel may have very limited consequences. A basic
requirement is that progressive collapse must be prevented and vital longitudinal systems, such as an
electrical supply or communication cables, are not cut off.
The materials used in tunnel structures involve different precautions for fire protection. Section VII.3
"Fire reaction of materials" of the report 1999 05.05.B "Fire and Smoke Control in Tunnels" discusses
the characteristics of rock tunnel linings versus reinforced concrete. The intensity of the heat generated
during a major fire may cause reinforced concrete to lose its supporting function. The role of
insulation using fire-resistant protection can be applied to prevent early damage to the structure. The
fire resistance of the total construction (type and depth of reinforcement/prestressing, additional
protection, etc.) needs to be considered.
Spalling of concrete is caused by differences in temperature and expansion. It causes a danger for the
reinforcement which is more easily exposed to high temperatures. It will generally not be a danger for
http://tunnels.piarc.org/en/response-fire/resistance-structures.htm 5 / 7
PIARC ROAD TUNNELS MANUAL PIARC

http://tunnels.piarc.org/en/response-fire/resistance-structures.htm 6 / 7
evacuating people, but it may be dangerous for firemen. Various types of fire-resistant protection can
be used to reduce the risk and the effects of spalling, although it never can be completely prevented
due to the high temperatures that may occur.
Attention must be given to the fire resistance of the ventilation system so that its design performance
is not impaired by failure. Therefore it is necessary to examine the consequences of a local collapse of
a duct in case of fire.
Escape routes are only used during the first phase of the fire for the escape of trapped people. It must
be possible to use such routes for a period of at least 30 minutes. In cases where these routes are also
used by the rescue and fire teams, the period may be longer.
To avoid fire spreading into an adjacent tube or escape route, emergency doors, emergency recesses
and other equipment located between two traffic tubes, should remain intact during a specified period
of time. The whole emergency door and surrounding construction, including the door frame, should
resist fire for at least a 30 minute fire exposure. For a door between two traffic tubes, a much longer
resistance is required, for example 1 to 2 hours.
PIARC ROAD TUNNELS MANUAL PIARC

9.3. Resistance of equipment to fire

In terms of resistance to high temperatures, tunnel equipment and cables can be broadly grouped as
either fire-rated or unprotected.
Protected equipment and cables with variable levels of resistance to fire include, for example:
fire-resistant cables capable of withstanding 950C for 3 hours (CWZ specification);
LS0H cables: 250C for 3 hours;
ventilation fans: 250C for 1 or 2 hours
Unprotected items of equipment such as traffic signs, cameras and public address (PA) speakers have
working temperatures typically up to 50C, and are likely to fail at relatively low temperatures.
Materials include:
luminaires - laminated glass (fluorescent) or toughened glass (SON); aluminium alloy or steel
housings (working temperatures for SON luminaires typically about 120C)
traffic signs - polycarbonate screens, stainless steel housings
cameras - lenses, aluminium housings
public address (PA) horn speakers - glass-reinforced polyester (GRP).
Critical temperatures for materials used in such unprotected items include:
polymer-based materials such as polycarbonate will melt at temperatures in the region of 150C
and ignite at temperatures in the order of 300-400C;
silicone sealing - working temperatures typically go up to 200-250C;
glass - working temperatures for toughened glass are typically up to 250-300C, cracks may
develop at temperatures greater than 600C;
aluminium alloy - softens at 400C and melts at 660C.
All fittings used for the fixing of equipment to the structures should be considered in terms of their
behaviour in fires.


http://tunnels.piarc.org/en/response-fire/resistance-equipment.htm 7 / 7








ROAD TUNNELS MANUAL




GLOSSARY










All rights reserved. World Road Association (PIARC)
PIARC ROAD TUNNELS MANUAL PIARC

Glossary

During the 2008-2011 cycle, the Road Tunnels committee reviewed all the terms and definitions
relating to road tunnels which existed in the various PIARC dictionaries, in particular the PIARC
Dictionary (Theme1 5: Tunnels) and the PIARC Lexicon (Theme 6: Bridges and Tunnels). From all
these terms, it retained a first list of 140 terms. These terms and their definitions were reviewed and
validated in French and English. This list of terms served as first version for a new specific PIARC
dictionary: the "Road tunnel operations" dictionary.
This list of 140 terms and definitions was then translated by the committee members in 17 different
languages among those which are used by the Terminology Committee.
The list of all these terms and their definitions are available on the PIARC Web site, at the heading
"Search per theme" in the page "Terminology", while clicking on "Road tunnel operations" in the list
of the dictionaries and while clicking then on "Road tunnel operations" in the list of themes.
This list is also available in an Excel file which will give all the terms and all their definitions in the 19
languages as their availability. This list is available under two forms:
in English alphabetical order;
in French alphabetical order.

Contributors
For the realization of this Glossary,
Pierre SCHMITZ (Belgium), President of the committee, supervised the Glossary;
the various Working Groups reviewed the existing terms and definitions and proposed new
terms;
Bernard FALCONNAT (France) reviewed the terms and definitions of the French version;
Fathi TARADA (U.K.) reviewed the terms and definitions of the English version.
The translations of the terms and definitions starting from the English and French official versions
were carried out by:
Chinese: Wei LIU (People's Republic of China)
Czech: Pavel PRIBYL (Czech Republic)
Danish: Carsten HENRIKSEN (Denmark)
Dutch: Evert WORM (Netherlands)
Finnish: Pauli VELHONOJA (Finland)
German: Rudolf HRHAN (Austria)
Greek: Ioannis BAKOGIANNIS (Greece)
Hungarian: Pl GYRGY (Hungary)
Italian: Romano BORCHIELLINI (Italy) and Carlo BARBETTA
J apanese: Hideto MASHIMO (J apan)
Korean: Nam-Goo KIM (South Korea)
Norwegian: Erik NORSTRM (Norway)
Persian: Reza AKBARI (Iran)
Portuguese: Antonio PINTO DA CUNHA (Portugal)
Slovene: Drago DOLENC (Slovenia)
Spanish: Manuel ROMANA RUIZ (Spain)
Swedish: Bernt FREIHOLTZ (Sweden).