Sie sind auf Seite 1von 55

Engineering

Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS


RPNC101660

DATE
August 13, 2014


Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION FOR
CIVIL WORKS
TECHNICAL
SPECIFICATION

REV



0









TECHNICAL SPECIFICATION
FOR
CIVIL WORKS

ANNEXURE-III


























13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

3 | P a g e 5 0

0






CONTENTS



SL.NO.


DESCRIPTION

01.
02.
03.
04.
05.
06
07
08
09

10.
11.

12.
13.
14.
15.


GENERAL
REFERENCE STANDARDS
EARTH WORK
PLAIN AND REINFORCED CONCRETE WORK
STEEL REINFORCEMENT
FORM WORK
BRICK WORK
WOOD WORK
STEEL /ALUMINIUM DOORS, WINDOWS &
VENTILATORS
FLOORING AND PAVING
PLASTERING
WHITE / COLOUR WASHING AND CEMENT
PAINTING
GLAZING
DISMANTLING AND DEMOLISHING.
DRAINAGE AND SANITATION.







Engineering
Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS


RPNC101660

DATE
August 13, 2014


Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION FOR
CIVIL WORKS
TECHNICAL
SPECIFICATION

REV



0

1.0 GENERAL

1.1 Specifications of materials and workmanship shall be as described in the Central
Public Works Department Specifications Vol. I to VI (Latest) including latest
amendments, unless otherwise specified. These CPWD Specifications shall be
deemed to form part of this contract. The Contractor shall procure and maintain
copies of the latest CPWD Specifications at site for reference.

1.2 These technical Specifications shall be supplementary to the specifications contain in
the CPWD Specifications, wherever at variance, these particular Specifications shall
take precedence over the provisions in the CPWD Specifications.

1.3 Site clearing - Site clearing means the cleaning of site before and after starting
refurbishing works. The unserviceable materials shall be removed from the site area
at the Contractors expenses and responsibility and shall be disposed off as outside
Refinery premises. The serviceable materials to be deposited with the Civil
maintenance off site office as directed by Engineer-In-Charge.

2.0 REFERENCE STANDARDS

2.1 Wherever reference of BIS Specifications or BIS Codes of Practice are made in the
Specifications/Schedule of Rates or Preambles, reference shall be to the latest edition
of BIS (Bureau of Indian Standards).

2.2 Latest editions to be referred.

2.2.1 CARRIAGE OF MATERIALS

IS 4082 Recommendation of stacking and storage of construction of materials
at sites.

2.2.2 EARTH WORK

IS 1200 (Part-I) Methods of measurement of building and Civil Engineering works:
(Part-I) Earth work.
IS 4081 Safety code for Blasting and related drilling operations.
IS 6313 (Part-I) Code of Practice for Anti-termite measure in Buildings: Part-I
Constructional and measures.
IS 6313 (Part-II) Code of Practice for Anti-termite measure in Buildings: Part-II- Pre-
Constructional Chemical treatment measures.
IS 6313 (Part-III) Code of Practice for Anti-termite measure in Buildings: Part-III-
Treatment for existing building.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

2 | P a g e 5 0

0


2.2.3 PLAIN CEMENT CONCRETE

IS 196 Atmospheric condition of testing.
IS 269 Specifications for 33 grade ordinary Portland Cement.
IS 306 Tin bronze ingots and castings.
IS 383 Specifications for Coarse and fine aggregate from natural source for
concrete.
IS 455 Specifications for Portland slag cement.
IS 456 Code of practice for plain and reinforced concrete.
IS 460 (Part-1) Test sieves: (Part-I) Wire cloth test sieves.
IS 516 Method of test for strength of concrete.
IS 650 Specifications for Standard sand for testing of cement.
IS 712 Building limes.
IS 1199 Method of sampling and analysis of concrete.
IS 1200 (Part-2) Methods of measurement of building and Civil Engineering works:
(Part-2) Concrete works.
IS 1322 Bitumen felt for water proofing and damp proofing.
IS 1344 Calcined clay pozzolana cement.
IS 1489 (Part-I) Specifications for Portland pozzolana cement: (Part-I) Fly ash based.
IS 1489 (Part-II) Portland pozzolana cement: (Part-I) Calcined clay based.
IS 1542 Sand for Plaster.
IS 1514 Methods of sampling and test for quick lime and hydrated lime.
IS 1727 Methods for test for pozzolanic materials.
IS 1791 Batch type concrete mixers.
IS 1911 Schedule of unit weights of building materials.
IS 2116 Sand for masonry mortars
IS 2250 Code of practice for preparation and use of masonry mortar.
IS 2386 (Part-1) Methods of test for aggregate for concrete: (Part-1) Particle size and
shape.
IS 2386 (Part-2) Methods of test for aggregate for concrete: (Part-2) Estimation of
deleterious materials and organic impurities.
IS 2386 (Part-3) Methods of test for aggregate for concrete: (Part-3) Specific gravity,
density, voids, absorption and bulking.
IS 2386 (Part-4) Methods of test for aggregate for concrete: (Part-4) Mechanical
properties.
IS 2386 (Part-5) Methods of test for aggregate for concrete: (Part-5) Soundness.
IS 2386 (Part-6) Methods of test for aggregate for concrete: (Part-6) Measuring mortar
making properties of fine aggregates.
IS 2386 (Part-7) Methods of test for aggregate for concrete: (Part-7) Alkali aggregate
reactivity.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

3 | P a g e 5 0

0

IS 2386 (Part-8) Methods of test for aggregate for concrete: (Part-8) Petrographic
examination.
IS 2430 Methods of sampling of aggregates for concrete.
IS 2438 Roller fan mixer.
IS 2505 General requirements for concrete vibratos- Immersion type.
IS 2506 General requirements for screed board concrete vibratos.
IS 2580 Jute sacking bags for packing cement.
IS 2645 Specifications for Integral cement water proofing components.
IS 2686 Specifications for Cinder as fine aggregate for use in Lime concrete.
IS 2770 (Part-1) Methods of testing bond in reinforced concrete: (Part-1) Pullout test.
IS 3025 Method of sampling and test for water.
IS 3068 Specifications for Broken brick (burnt clay) coarse aggregates for use
in lime concrete.
IS 3085 Methods of test for permeability of cement mortar and concrete.
IS 3182 Specifications for Broken brick (burnt clay) coarse aggregates for use
in lime mortar.
IS 3466 Specifications for Masonry cements.
IS 3535 Methods of sampling hydraulic cement.
IS 3812 Fly ash for use as pozzolana and admixture.
IS 4031 Methods of Physical test for hydraulic cement (Part-1) to (Part-13).
IS 4032 Methods of Chemical analysis of hydraulic cement.
IS 4098 Lime pozzolana mixture.
IS 4643 Section wrenches for fire bridge use.
IS 4656 Form vibrators for concrete.
IS 5816 Methods of test for splitting tensile strength of concrete cylinders.
IS 6452 Specifications for high alumina cements for structural purposes.
IS 6491 Method of sampling fly ash.
IS 6909 Specifications for supersulphated cement.
IS 6925 Method of test for determination of water soluble chlorides in concrete
admixtures.
IS 6932 (Part-1) Method of test for building limes: (Part-1) Determination of insoluble
residue, loss on ignition, insoluble matter, silicon dioxide, ferric and
aluminium oxide, calcium oxide and magnesium oxide.
IS 6932 (Part-2) Method of test for building limes: (Part-2) Determination of carbon
dioxide content.
IS 6932 (Part-3) Method of test for building limes: (Part-3) Determination of residue on
on slacking of quick lime.
IS 6932 (Part-4) Method of test for building limes: (Part-4) Determination of fineness
of hydrated lime.
IS 6932 (Part-5) Method of test for building limes: (Part-5) Determination of
unhydrated oxide.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

4 | P a g e 5 0

0

IS 6932 (Part-6) Method of test for building limes: (Part-6) Determination of volume
yield of quicklime.
IS 6932 (Part-7) Method of test for building limes: (Part-7) Determination of
compressive and transverse strength.
IS 6932 (Part-8) Method of test for building limes: (Part-8) Determination of
workability.
IS 6932 (Part-9) Method of test for building limes: (Part-9) Determination of
soundness.
IS 6932 (Part-10) Method of test for building limes: (Part-10) Determination of popping
and putting of hydrated lime.
IS 6932 (Part-11) Method of test for building limes: (Part-10) Determination setting time
of hydrated lime.
IS 7861 (Part-1) Code of practice for extreme weather concreting: (Part-1)
Recommended practice for hot weather concreting.
IS 7861 (Part-2) Code of practice for extreme weather concreting: (Part-2)
Recommended practice for cold weather concreting.
IS 8041 Specifications for Rapid hardening Portland cement.
IS 8042 Specifications for white Portland cement.
IS 8043 Specifications for Hydrophobic hardening Portland cement.
IS 8112 Specifications for 43 grade ordinary Portland cement.
IS 8142 Methods of test for determining setting time of concrete by penetration
resistance.
IS 9013 Method of making, curing and determining compressive strength of
accelerated cured concrete test specimens.
IS 9103 Specifications for Admixtures for concrete.
IS 9142 Specifications for artificial lightweight aggregates for concrete
masonry units.
IS 9284 Method of test for resistance of concrete.
IS 11652 Woven sacks for packing cement high density polyethylene /
polypropylene (HDPE).
IS 11653 Polypropylene (PP) woven sacks for packing cement.
IS 12174 Jute synthetic union bags for packing cement.
IS 12269 53 grade ordinary Portland cement.

2.2.4 REINFORCED CEMENT CONCRETE

IS 432 (Part-1) Mild steel and medium tensile steel bars and hard drawn steel wire for
concrete. Reinforcement: (Part-1) Mild steel and medium tensile steel
bars.
IS 432 (Part-2) Mild steel and medium tensile steel bars and hard drawn steel wire for
concrete. Reinforcement: (Part-2) Hard drawn steel wire.
IS 1200 (Part-5) Methods of measurement of building and Civil Engineering works:
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

5 | P a g e 5 0

0

(Part-5) Form work.
IS 1343 Code of practice for Pre-stressed concrete.
IS 1566 Hard drawn steel fabric for concrete reinforcement.
IS 1599 Method for bend test.
IS 1608 Method for tensile testing of steel products.
IS 1786 High strength deformed steel bars and wires for concrete
reinforcement.
IS 2751 Recommended practice for welding of mild steel plain and deformed
bars for reinforced construction.
IS 4925 Concrete batching and mixing plant.
IS 4996 Specifications for reinforced concrete fence posts.
IS 5751 Specifications for pre-cast concrete coping blocks.
IS 5758 Specifications for pre-cast concrete kerb.
IS 5820 Specifications for pre-cast concrete cable covers.
IS 6072 Specifications for auto-claved reinforced cellular concrete wall slabs.
IS 6073 Specifications for auto-claved reinforced cellular concrete floor & roof
slabs.
IS 6441 (Part-1) Methods of test for auto-claved reinforced cellular concrete products:
(Part-1) Determination of unit weight or bulk density and moisture
content.
IS 6441 (Part-2) Methods of test for auto-claved reinforced cellular concrete products:
(Part-2) Determination of drying shrinkage.
IS 6441 (Part-4) Methods of test for auto-claved reinforced cellular concrete products:
(Part-4) Corrosion protection of steel reinforcement in auto claved
cellular concrete.
IS 6441 (Part-5) Methods of test for auto-claved reinforced cellular concrete products:
(Part-5) Determination of compressive strength.
IS 6441 (Part-6) Methods of test for auto-claved reinforced cellular concrete products:
(Part-6) Strength, deformation and cracking of flexural members
subject to bending short duration loading test.
IS 6441 (Part-7) Methods of test for auto-claved reinforced cellular concrete products:
(Part-7) Strength, deformation and cracking of flexural members
subject to bending sustained loading test.
IS 6441 (Part-8) Methods of test for auto-claved reinforced cellular concrete products:
(Part-8) Loading test for flexural members in diagonal tension.
IS 6441 (Part-9) Methods of test for auto-claved reinforced cellular concrete products:
(Part-9) Jointing of auto-claved reinforced cellular concrete elements.
IS 6523 Specifications for Pre-cast reinforced concrete door, window frames.
IS 9872 Specifications for Pre-cast concrete septic tanks.
IS 9893 Specifications for Pre-cast concrete blocks for lintels and sills.
IS 10262 Recommended guidelines for concrete mix design.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

6 | P a g e 5 0

0

IS 13311 (Part-1) Non-destructive testing of concrete: (Part-1) Method of test for
ultrasonic Pulse Velocity.
IS 13311 (Part-2) Non-destructive testing of concrete: (Part-1) Method of testing by
Rebound hammer.
SP 23 Hand book on concrete mixes.



2.2.5 BRICK WORK & STONE WORK

IS 712 Specifications for building limes.
IS 737 Wrought aluminium and aluminium alloy steel and strips for general
engineering purposes.
IS 1077 Common burnt clay bricks.
IS 1121 (Part-1) Methods of test for determination of properties and strengths of natural
building stones: (Part-1) Compressive strength.
IS 1121 (Part-2) Methods of test for determination of properties and strengths of natural
building stones: (Part-2) Transverse strength.
IS 1121 (Part-3) Methods of test for determination of properties and strengths of natural
building stones: (Part-3) Shear strength.
IS 1121 (Part-4) Methods of test for determination of properties and strengths of natural
building stones: (Part-4) Tensile strength.
IS 1122 Methods of test for determination of specific gravity of natural building
stones.
IS 1123 Methods of identification of natural building stones.
IS 1124 Methods of test for determination of water absorption, apparent
specific gravity and porosity of natural building stones.
IS 1125 Methods of test for determination of weathering of natural building
stones.
IS 1126 Methods of test for determination of durability of natural building
stones.
IS 1127 Recommendations for dimensions and workmanship of natural
building stones for masonry work.
IS 1128 Specifications for Lime stones (slab & tiles).
IS 1129 Recommendations for dressing of natural building stones.
IS 1130 Specifications for Marble (blocks, slabs and tiles).
IS 1200 (Part-3) Methods of measurement of building and Civil Engineering works:
(Part-3) Brick works.
IS 1200 (Part-4) Methods of measurement of building and Civil Engineering works:
(Part-4) Stone work.
IS 1597 (Part-1) Code of practice for construction of stone masonry: (Part-1) Rubble
stone masonry.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

7 | P a g e 5 0

0

IS 1597 (Part-2) Code of practice for construction of stone masonry: (Part-2) Ashlar
stone masonry.
IS 1624 Method of field testing of building lime.
IS 1706 Method of determination of resistance to wear by abrasion of natural
building stones.
IS 1805 Glossary of terms relating to stones, quarrying and dressing.
IS 2180 Specification for heavy duty burnt clay building bricks.
IS 2222 Specification for burnt clay perforated building bricks.
IS 2185 (Part-1) Concrete masonry units: (Part-1) Hollow and solid concrete blocks.
IS 2185 (Part-2) Concrete masonry units: (Part-2) Hollow and solid lightweight concrete
blocks.
IS 2185 (Part-3) Concrete masonry units: (Part-3) Autoclaved cellular (aerated) concrete
blocks.
IS 2212 Code of practice for brick work.
IS 2572 Code of practice for construction of hollow concrete block masonry.
IS 2691 Specification for burnt clay facing bricks.
IS 3102 Classification of burnt clay solid bricks.
IS 3316 Specifications for structural granite.
IS 3495 (Part:1) Method of test for burnt clay building bricks (Part-1) Determination of
compressive strength.
IS 3495 (Part:2) Method of test for burnt clay building bricks (Part-1) Determination of
water absorption.
IS 3495 (Part:1-4) Method of test for clay building bricks (Part-1 to 4 in one volume).
IS 3622 Sand stone (slab & tiles).
IS 3952 Specifications for burnt hollow blocks for walls and partitions.
IS 4101 (Part-1) Code of practice for external facings and veneers: (Part-1) Stone
facings.
IS 4101 (Part-2) Code of practice for external facings and veneers: (Part-2) Cement
concrete facing.
IS 4121 Method of test for determination of water transmission rate by capillary
action through natural building stones.
IS 4348 Method of test for determination of permeability of natural building
stones.
IS 5218 Method of test for toughness of natural building stones.
IS 5454 Method of sampling of clay building bricks.
IS 6909 Specification for supersulphated Cement.
IS 12440 Pre-cast concrete stone blocks.
IS 12894 Fly-ash lime bricks.

2.2.6 WOOD WORK.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

8 | P a g e 5 0

0

IS 204 (Part-1) Specification for tower bolts: (Part-1) Ferrous metal.
IS 204 (Part-2) Specification for tower bolts: (Part-2) Non-ferrous metal.
IS 205 Specification for non-ferrous metal butt hinges.
IS 206 Specification for Tee and strap hinges.
IS 207 Gate and shutter hooks and eyes.
IS 208 Specification for door handles.
IS 281 Specification for mild steel door bolts for use with padlocks.
IS 287 Recommendations for maximum permissible moisture content of
timber used for different purposes.
IS 303 Specification for plywood for general purposes.
IS 362 Specification for plywood for general purposes.
IS 363 Specification for hasps and staples.
IS 364 Specification for fanlight catch.
IS 401 Code of practice for preservation of timber.
IS 419 Putty for use on window frames.
IS 451 Technical supply condition for wood screws.
IS 452 Specifications for door spring rat-tail type.
IS 453 A specification for double acting springs hinges.
IS 723 Specifications for steel counter sunk head wire nails.
IS 729 Specifications for drawer locks, cupboard locks and box locks.
IS 848 Specifications for synthetic resin adhesives for plywood (phenolic and
amino plastic).
IS 851 Specifications for synthetic resin adhesives for construction work (non-
structural) in wood.
IS 852 Specifications for animal glue for general woodworking purposes.
IS 1003 (Part-1) Specifications for timber paneled and glazed shutters: (Part-1) Door
shutters.
IS 1003 (Part-2) Specifications for timber paneled and glazed shutters: (Part-2)
Windows and ventilator shutters.
IS 1200 (Part-14) Methods of measurement of building and Civil Engineering works:
(Part-14) Glazing.
IS 1200 (Part-12) Methods of measurement of building and Civil Engineering works:
(Part-12) Wood work and joinery.
IS 1328 Specifications for veneered decorative plywood.
IS 1341 Specifications for steel butt hinges.
IS 1378 Specifications for oxidized copper finishes.
IS 1568 Specifications for wire cloth for general purpose.
IS 1658 Specifications for fibre hard boards.
IS 1659 Specifications for block boards.
IS 1708(Part:1-18) Method of testing of small clear specimens of timber.
IS 1734(Part:1-20) Method of test for plywood.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

9 | P a g e 5 0

0

IS 1761 Transparent steel glass for glazing and framing purposes. Superseded
by IS 2835.
IS 1823 Specifications for floor door stoppers.
IS 1837 Specifications for fanlight pivots.
IS 1868 Specifications for anodic coating on aluminium and its alloys.
IS 2095 Specifications for Gypsum plaster boards.
IS 1998 Methods of test for thermosetting synthetic resin bonded laminated
sheets.
IS 2036 Specifications for phenolic laminated sheets.
IS 2046 Specifications for decorative thermosetting synthetic resin bonded
laminated sheets.
IS 2076 Specifications for unsupported flexible bonded vinyl film and sheeting.
IS 2096 Specifications for asbestos cement flat sheets.
IS 2202 (Part-1) Specifications for wooden flush door shutters (Solid core type): (Part-
1) Plywood faces panels.
IS 2202 (Part-2) Specifications for wooden flush door shutters (Solid core type): (Part-
2) Particle board face panels and hard board face panels..
IS 2209 (Part-1) Specifications for mort ice locks: (Part-1) Verticle type.
IS 2380 (Part:1-
23)
Methods of test for wood particle boards from other lingnocellulosic
material: (Part-1 to 230.
IS 2508 Specifications for low density polyethylene films.
IS 2547 (Part:1) Gypsum building plaster: (Part-1) Excluding pre-mixed lightweight
plaster.
IS 2547 (Part:2) Gypsum building plaster: (Part-1) Pre-mixed lightweight plaster.
IS 2681 Specification for flat transparent sheet glass.
IS 2835 Specification for non-ferrous metal sliding door bolts for use with pad
locks.
IS 3087 Specification for wood particle boards (Medium density) for general
purposes.
IS 3097 Specification for vennered particle boards.
IS 3400 (Part-2) Methods of test for Vulcanized rubbers: (Part-1) Hardness.
IS 3400 (Part-4) Methods of test for Vulcanized: (Part-4) Accelerated ageing.
IS 3400 (Part-9) Methods of test for Vulcanized: (Part-9) Density.
IS 3564 Methods of test for Vulcanized: (Part-9) Density.
IS 3618 Phosphate treatment of iron and steel for protection against corrosion.
IS 3813 Specification for C hooks for use with swivels.
IS 3828 Specification for door closers (Hydaulically regulated).
IS 3847 Specification for mortice night latches.
IS 4835 Specification for polyvinyl acetate dispersion based adhesives for
wood.
IS 4948 Specification for welded steel wire fabric for general use.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

10 | P a g e 5 0

0

IS 4992 Specification for door handles for mortice lock (verticle type).
IS 5187 Specification for flush bolts.
IS 5523 Method of testing anodic coating on aluminium and its alloys.
IS 5930 Specification for mortice latch.
IS 6307 Specification for pigid PVC sheets.
IS 6381 Specification for plastic window Stays and fastners.
IS 6607 Specifications for rebated mortice lock (verticle type).
IS 6760 Specification for sloted countersunk head wood screws.
IS 7196 Specification for hold fast.
IS 7534 Specification for sliding locking bolts for use with padlocks.
IS 8756 Specification for mortice ball catches for use in wooden almirah.
IS 12406 Specification for medium density fibreboards for general purposes.



2.2.7 STEEL WORK.

IS 63 Specification for whiting for paints and putty.
IS 277 Specification for galvanized steel sheets (Plain and corrugated).
IS 800 Code of practice for use of structural steel in general in steel
construction.
IS 806 Code of practice for use of steel tubes in general building construction.
IS 812 Glossary of terms relating to welding and cutting of metals.
IS 813 Scheme of symbols for welding.
IS 814 Covered electrodes for manual metal arc welding of carbon and carbon
manganese steel.
IS 815 Classification and coding of covered electrodes for metal arc welding
of structural steel. Superseded by IS 8141-1991
IS 816 Code of practice for use of metal arc welding for generalconstruction in
mild steel.
IS 817 Code of practice for training and testing of metal arc welders.
IS 818 Code of practice for safety and healthy requirements in electric and gas
welding and cutting operations.
IS 822 Code of procedure for inspection of welds.
IS 823 Code of procedure for Manual for metal arc welding in mildsteel.
IS 1038 Steel doors, windows and ventilators.
IS 1081 Code of practice for fixing and glazing of metal (Steel and aluminium)
doors, windows and ventilators.
IS 1148 Hot rolled steel rivet bars (upto 40mm diameter) for structural
purposes.
IS 1161 Steel tubes for structural purposes.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

11 | P a g e 5 0

0

IS 1182 Recommended practice for radiographic examination of fusion welded
butt joints in steel plates.
IS 1200 (Part 8) Methods of measurement of building and Civil Engineering works:
(Part-8) Steel steel & iron works.
IS 1363 (Part 1) Hexagon head bolts, screws and nuts of product grade C: (Part-1)
Hexagon head bolts (Size range M5 to M64).
IS 1363 (Part 2) Hexagon head bolts, screws and nuts of product grade C: (Part-2)
Hexagon head screws (Size range M5 to M64).
IS 1363 (Part 3) Hexagon head bolts, screws and nuts of product grade C:
(Part3)Hexagon head Nuts (Size range M5 to M64).
IS 1367(Part:1-19) Technical supply conditions for threaded steel fastners.
IS 1599 Method of bend test for steel products other than sheet, strips, wire and
tube.
IS 1608 Method of tensile testing of steel products.
IS 1821 Dimension for clearance holes for bolts and screws.
IS 1852 Rolling and cutting tolerances for hot rolled steel products.
IS 1894 Method for tensile testing of steel tubes.
IS 1977 Structural steel ordinary quality.
IS 2062 Steel for general structural purposes.
IS 2074 Ready mixed paint, air drying red oxide zinc chrome, primer.
IS 4351 Specification for steel door frames.
IS 4454 Steel wires for cold formed springs: (Part-1) Patented and cold drawn
steel wires unalloyed.
IS 4736 Hot dip zinc coatings on mild steel tubes.
IS 6248 Metal rolling shutters and rolling grills.
IS 7452 Specifications for hot rolled steel sections for doors, windows and
ventilators.


2.2.8 FLOORING.

IS 210 Grey iron castings.
IS 653 Specifications for linoleum sheets and tiles.
IS 702 Specifications for industrial bitumen..
IS 809 Specifications for rubber flooring materials for general purposes.
IS 1141 Code of practice for seasoning of timber.
IS 1197 Code of practice for laying rubber floors.
IS 1198 Code of practice for laying, fixing and maintenance of linoleum floor..
IS 1200 (Part 11) Methods of measurement of building and Civil Engineering works:
(Part-11) Paving, floor finishes, dado and skirting.
IS 1237 Specifications for cement concrete flooring tiles.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

12 | P a g e 5 0

0

IS 1443 Code of practice for laying and finishing of cement concrete flooring
tiles.
IS 1580 Specifications for bituminous compounds for water proofing
andcaulking purpose.
IS 2078 Method of tensile testing of grey cast iron.
IS 2114 Code of practice for laying in-situ terrazzo floor finish.
IS 2571 Codes of practice for laying in-situ cement concrete flooring.
IS 2571 Codes of practice for laying in-situ cement concrete flooring.
IS 3461 Specifications for PVC asbestos floor tiles.
IS 3462 Specifications for unbacked flexible PVC flooring.
IS 3670 Code of practice for construction of timber floors.
IS 5318 Code of practice for laying flexible PVC sheet and tile flooring.
IS 5766 Code of practice for lying of burnt clay brick flooring.
IS 8042 Specification for white Portland cement.
IS 12330 Specification for supphate resisting Portland cement.




2.2.9 FINISHING.

IS 16 (Part-1) Shellac: (Part-1) Hand made shellac.
IS 16 (Part-2) Shellac: (Part-2) Machine made shellac.
IS 75 Linseed oil raw and refined.
IS 77 Linseed oil boiled for paints.
IS 82 Method of sampling and test for thinners and solvents for paints.
IS 101 Methods of test for Ready mixed paint & enamels.
IS 102 Specification for Ready mixed paint, brushing, red lead, nonsetting,
and priming.
IS 104 Specification for ready mixed paint, brushing, zinc chrome, priming.
IS 109 Specification for Ready mixed paint, brushing, priming plaster of
Indian standard colour no.361, 631 White and off white.
IS 110 Specification for Ready mixed paint, brushing, and grey filler, for
enamels, for use over primers.
IS 111 Specification for Ready mixed paint, brushing, undercoating, exterior,
to Indian Standard colours no.101, 216, 352, 358, 443, and 632.
IS 112 Specification for Ready mixed paint, spraying, undercoating, exterior,
to Indian Standard colours no.101, 216, 352, 358, 443, and 632.
IS 113 Specification for Ready mixed paint, brushing, undercoating, interior,
to Indian Standard colours no.101, 216, 352, 358, 443, and 632.
IS 114 Specification for Ready mixed paint, spraying, undercoating, interior,
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

13 | P a g e 5 0

0

to Indian Standard colours no.101, 216, 352, 358, 443, 632.
IS 115 Specification for Ready mixed paint, brushing, undercoating, exterior,
matt finish, to Indian Standard colours no.352 & 632.
IS 116 Specification for Ready mixed paint, spraying, undercoating, exterior,
matt finish, to Indian Standard colours no.352 & 632.
IS 117 Specification for Ready mixed paint, brushing, finishing exterior,
semi-gloss for general purposes to Indian standard colours Light
Colours No.101, 102, 174, 216, 217, 275, 281, 352, 353, 354, 358,
361, 364, 365, 384, 385, 386, 387, 388, 397, 442, 443, 628, 629, 630,
631, 693, 694 & 697; Dark Colours No.103, 104, 169, 219, 278, 280,
283, 359, 360, 362, 363, 410, 444, 632, 635 and 692.
IS 120 Specification for Ready mixed paint, brushing, finishing, semi-gloss
for general purposes to Indian standard colours No.537, 538, 540, 541,
570 & 574.
IS 121 Specification for Ready mixed paint, brushing, finishing, semi-gloss
for general purposes to Indian standard colours No.414
IS 122 Specification for Ready mixed paint, brushing, finishing, and semi-
gloss for general purposes to Indian standard colours No.411, 412 and
413.
IS 123 Specification for Ready mixed paint, brushing, finishing, semi-gloss
for general purposes to Indian standard colours No.445, 446, 448, 449,
451 and 473.
IS 124 (3Parts) Specification for Ready mixed paint, brushing, finishing, semi gloss
for general purposes.
IS 126 Specification for Ready mixed paint, brushing, and finishing, exterior,
semi-gloss for general purposes to Indian standard colours No.671.
IS 127 Specification for Ready mixed paint, brushing, and finishing, exterior,
semi-gloss for general purposes, white.
IS 128 Specification for Ready mixed paint, brushing, and finishing, exterior,
semi-gloss for general purposes, black.
IS 129 Specification for Ready mixed paint, brushing, finishing, interior, oil-
gloss for general purposes to Indian standard colours No.101, 102,
103, 104, 169, 216, 217, 219, 352, 353, 354, 358, 359, 360, 361, 362,
363, 364, 410, 443, 444, 628, 629, 630, 631, 632, 633, 634 & 635.
IS 133 Specifications for Enamel, Interior (a) Undercoating (b) Finishing.
IS 137 Specifications for Ready mixed paint, brushing, matt or egg shell flat,
finishing interior to Indian standard colour as required.
IS 155 Specifications for Ready mixed paint, brushing, matt, and black, for
use on woods.
IS 156 Specifications for Ready mixed paint, brushing, for use on floors
colour as required.
IS 158 Specifications for Ready mixed paint, brushing, Bitumenous black,
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

14 | P a g e 5 0

0

lead free, acid, alkali and heat resisting.
IS 162 Specifications for Ready mixed paint, brushing, fire resisting silicate
type for use on woods colour as required.
IS 168 Specifications for Ready mixed paint, brushing, air drying, semi-
glossy/matt, for general purposes.
IS 197 Methods of sampling and test for vrnishes and lacquers.
IS 217 Specification for cutback bitumen.
IS 218 Specification for Creosote and anthracene oil for use as wood
preservatives.
IS 290 Specifications for Coal tar black paint.
IS 324 Specifications for ordinary denatured spirit.
IS 337 Specifications for Varnish, Finishing interior.
IS 340 Specifications for varnish mixing.
IS 341 Specifications for Black Japan paint, Type A, B & C.
IS 345 Specifications for wood filler, transparent, liquid.
IS 346 Specifications for varnish, spirit, clear, hard.
IS 347 Specifications for Varnish, shellac for general purposes.
IS 348 Specifications for French polish.
IS 349 Specifications for lacquer, cellulose, nitrate, clear, finishing, glossy
for metal.
IS 419 Specifications for Putty for use on window frames.
IS 421 Specifications for jointing paste, for bedding mouldings, on coaching
stock.
IS 423 Specifications for plastic wood, for joiners filler.
IS 424 Specifications for plastic asphalt.
IS 427 Specification for Distemper, dry, colour as required.
IS 428 Specification for Distemper, oil emulsion, colour as required.
IS 524 Specifications for Varnish, finishing, Exterior, synthetic air drying.
IS 525 Specifications for Varnish, finishing, Exterior and general purposes.
IS 533 Specifications for gum spirit of turpentine (oil of turpentine).
IS 533 Specifications for Varnish medium for aluminium paints.
IS 641 Specifications for ready mixed paint, brushing, finishing, interior,
semi-gloss, for general purpose, white.
IS 642 Gum spirit of Turpentine (Oil of turpentine).
IS 712 Specification for building limes.
IS 871 Specifications for ready mixed paint, brushing, finishing, egg shell
gloss, for interior use, to Indian Standard colours Class A No.218
and Class B No.221.
IS 872 Specifications for ready mixed paint, brushing, finishing, egg shell
gloss, for interior use, to Indian Standard colours 412 & 413.
IS 1188 Specifications for ready mixed paint, brushing, oil gloss, genuine zinc
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

15 | P a g e 5 0

0

oxide, for general purpose.
IS 1200 (Part-12) Method of measurements of building and Civil Engineering works:
(Part-12) Plastering and pointing.
IS 1200 (Part-13) Method of measurements of building and Civil Engineering works:
(Part-13) White washing, colour washing, distempering and painting
of building surfaces.
IS 1200 (Part-15) Method of measurements of building and Civil Engineering works:
(Part-15) Painting, polishing, varnishing etc.
IS 1232 Specifications for ready mixed paint, brushing, yellow ochre, semi-
gloss, for general purpose.
IS 2074 Specifications for ready mixed paint, red oxide zinc chrome, priming.
IS 2075 Specifications for ready mixed paint, stoving, red oxide zinc chrome,
priming.
IS 2339 A specification for Aluminium paints for general purposes, in dual
container.
IS 2932 Specifications for Enamel, synthetic, exterior (a) Undercoating (b)
Finishing.
IS 2933 Specifications for Enamel, exterior (a) Under coating (b) Finishing.
IS 3536 Specifications for ready mixed paint, brushing, wood primer, pink.
IS 3537 Specifications for ready mixed paint, finishing, interior for general
purposes to Indian Standard colours.
IS 3539 Specifications for ready mixed paint, undercoating, for use under oil
finishes, to Indian Standard, colours as required.
IS 3585 Specifications for ready mixed paint, aluminium, brushing, priming,
water resistant for wood work.
IS 3678 Specifications for ready mixed paint, thick white, for lettering.
IS 3709 Specifications for mastic cement for bedding of metal windows.
IS 5410 Specification for Cement paints.
IS 5411 (Part-1) Specification for Plastic emulsion Paint: (Part-1) For interior use.
IS 5411 (Part-2) Specification for Plastic emulsion Paint: (Part-2) For exterior use.
IS 6278 Specification for stopper.
IS 7164 Code of practice for white washing and colour washing.
IS 8662 Specifications for enamel, synthetic, exterior (a) Undercoating (b)
Finishing, for railways.
IS 9862 Specifications for ready mixed paint, brushing, bituminous black, lead
free, acid, alkali, water and chlorine resisting.


2.2.9 DISMANTLING AND DEMOLITION.

IS 1200 (Part-18) Method of measurements of building and Civil Engineering works:
(Part-18) Demolishion and dismantling.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

16 | P a g e 5 0

0

IS 4130 Demolition of buildings Code of safety.



2.2.10 SANITARY INSTALLATIONS

IS 771 (Part-1) Glazed fire clay sanitary appliances: (Part-1) General requisites.
IS 771 (Part-2) Glazed fire clay sanitary appliances: (Part-2) Specific requirements of
kitchen and laboratory sinks.
IS 771 (Part-3-I) Glazed fire clay sanitary appliances: (Part-3/Sec.-I) Specific
requirements of urinals: Slab urinals.
IS 771 (Part-3-II) Glazed fire clay sanitary appliances: (Part-3/Sec.-II) Specific
requirements of urinals: Small urinals.
IS 772 General requirements for enameled cast iron sanitary appliances.
IS 774 Flushing cistern for water closets and urinals (other than plastic
cistern).
IS 775 Cast iron brackets and supports for wash basins and sinks.
IS 1300 Phenolin moulding materials.
IS 1703 Copper alloy float valves (horizontal plunger type) for water supply
fittings.
IS 1729 Sand cast iron spigot and socket soil waste and ventilating pipes,
fittings and accessories.
IS 1795 Pillar taps for water supply purposes.
IS 2267 Polystyrene moulding materials.
IS 2326 Automatic flushing cistern for urinals.
IS 2548 (Part-1) Plastic seat and covers for water closets: (Part-1) Thermoset seats and
covers.
IS 2548 (Part-2) Plastic seat and covers for water closets: (Part-2) Thermo plastic seats
and covers.
IS 2556 (Part-1) Specifications for vitreous sanitary appliances: (Part-1) General
requirements.
IS 2556 (Part-2) Specifications for vitreous sanitary appliances: (Part-2) Specific
requirements of wash down water closets..
IS 2556 (Part-3) Specifications for vitreous sanitary appliances: (Part-3) Specific
requirements of squatting pans.
IS 2556 (Part-4) Specifications for vitreous sanitary appliances: (Part-3) Specific
requirements of wash basins.
IS 2556 (Part-5) Specifications for vitreous sanitary appliances: (Part-3) Specific
requirements of laboratory sinks.
IS 2556 (Part-6-I) Specifications for vitreous sanitary appliances: (Part-3/Sec.-I) Specific
requirements of urinals: Bowl type.
IS 2556 (Part-6-II) Specifications for vitreous sanitary appliances: (Part-3/Sec.-II)
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

17 | P a g e 5 0

0

Specific requirements of urinals: Half stall urinals.
IS 2556 (Part-6-III) Specifications for vitreous sanitary appliances: (Part-3/Sec.-III)
Specific requirements of urinals: Squatting plates.
IS 2556 (Part-6-IV) Specifications for vitreous sanitary appliances: (Part-3/Sec.-IV)
Specific requirements of urinals: Partition slabs.
IS 2556 (Part-10) A specific requirement of foot rests.
IS 2556 (Part-14) Specific requirements of integrated squatting pans.
IS 2556 (Part-15) Specific requirements of universal water closets.
IS 2963 Copper alloy waste fittings for wash basins and sinks.
IS 3076 Low density polyethylene pipes for potable water supplies.
IS 3389 Urea-formaldehyde moulding materials.
IS 3489 Specifications for enamelled steel bath tubs.
IS 3989 Specifications for centrifugally cast (spun) iron spigot and socket soil,
waste and ventilating pipes, fittings and accessories.
IS 4827 Electro plated coatings of nickel and chromium on copper and copper
alloys.
IS 4984 High density polyethylene pipes for potable water supplies, sewage
and industrial effluents.
IS 4985 Specifications for unplasticised PVC pipes for potable water supplies.
IS 6411 Specifications for gel-coated glass fibre reinforced polyester resin bath
tub.
IS 7231 Plastic flushing cisterns (valve siphonic type) for water closets and
urinals.
IS 13983 Stainless steel sinks for domestic purposes specifications.



2.2.11 WATER SUPPLY.

IS 554 Dimensions for pipe threads where pressure tight joints are required
on the threads.
IS 554 Dimensions for pipe threads where pressure tight joints are required
on the threads.
IS 778 Specifications for copper alloy gate, and check valves for water works
purposes.
IS 779 Specifications for water meters (domestic types).
IS 780 Specifications for sluice valves for water works purposes.
IS 781 Specifications for cast copper alloy screw down bib taps and stop
valves for water services.
IS 782 Specifications for caulking lead.
IS 909 Specifications for underground fire hydrants, sluice valve type.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

18 | P a g e 5 0

0

IS 1239 (Part-1) Specifications for mild steel tubes, tubulars and other wrought steel
fittings: (Part-1) Mild steel tubes.
IS 1239 (Part-2) Specifications for mild steel tubes, tubulars and other wrought steel
fittings: (Part-1) Mild steel tubulars and other wrought steel pipe
fittings.
IS 1536 Specifications for centrifugally cast (spun) iron pressure pipes for
water, gas and sewage.
IS 1537 Specifications for vertically cast (spun) iron pressure pipes for water,
gas and sewage.
IS 1538 Specifications for cast iron fittings for pressure pipes for water, gas
and sewage.
IS 2556 (Part-11) Specifications for vitreous sanitary appliances (vitreous China): (Part-
11) Specific requirements of shower rose.
IS 2692 Specifications for ferrules for water services.
IS 2906 Specifications for sluice valves for water works purposes.
IS 4736 Hot-dip zinc coatings on mild steel tubes.
IS 4827 Electro-plated coatings of nickel and chromium on copper and copper
alloys.
IS 5382 Rubber sealing rings for gas mains, water mains and sewers.
IS 9762 Specifications for polyethylene floats (spherical) for float valves.









2.2.12 DRAINAGE.

IS 458 Specification for pre-cast concrete pipes (with and without
reinforcement).
IS 784 Specification for prestressed concrete pipes (including fittings).
IS 651 Specification for salt glazed stone ware pipes and fittings.
IS 1726 Specification for cast iron manhole covers and frames.
IS 1729 Sand cast iron spigot and socket soil waste and ventilating pipes,
fittings and accessories.
IS 1916 Specification for steel cylinder reinforced concrete pipes.
IS 3597 Methods of test for concrete pipes.
IS 4350 Specifications for concrete porous pipes for under drainage.
IS 7319 Specifications for perforated concrete pipes.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

19 | P a g e 5 0

0

IS 7322 Specifications for specials for steel cylinder reinforced concrete pipes.


2.2.13 FIRE PROTECTION

IS 3808 1979 Method of test for non-combustibility of building materials.
IS 3809 1979 Fire resistance test of structures.
IS 8757 1978 Glossary of terms associated with fire safety.























3.0 EARTHWORK

3.1 EXCAVATION

3.1.1 Excavation shall be carried out in soil of any nature and consistency, in the presence
of water or in the dry, met on the site to the lines, levels and contours shown on the
detailed drawings and contractor shall remove all excavated materials to soil heaps
on site or transport for use in filling on the site or stack them for reuse as directed by
the Owner.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

20 | P a g e 5 0

0

3.1.2. Surface dressing shall be carried out on the entire area occupied by the buildings
including plinth protection as directed without any extra cost. The depth of
excavation shown on the drawings is the depth after surface dressing.

3.1.3 The site around all buildings and structures to a width of 3 metres beyond the edge of
plinth protection, ramps, steps, etc., shall be dressed and sloped away from the
buildings.

3.1.4 Black cotton soil, and other expansive or unsuitable soil excavated shall not be used
for filling in foundations, and plinths of buildings or in other structures including
manholes, septic tanks etc., and shall be disposed off within the contract area marked
on the drawings, as directed, levelled and neatly dressed.

3.1.5 In case of trenches exceeding 2.0 metres depth or where soil is soft or slushy, the
sides of trenches shall be protected by timbering and shoring. The contractor shall be
responsible to take all necessary steps to prevent the sides of trenches from caving in
or collapsing. The extent and type of timbering and shoring shall be as directed by
the Owner.

3.1.6 Where the excavation is to be carried out below the foundation level of adjacent
structure, the precautions to be taken such as under pinning, shoring and strutting
etc., shall be determined by Owner. No excavation shall be done unless such
precautionary measures are carried out as per directions of Owner.

3.1.7 Specification for Earthwork shall also apply to excavation in rock in general. The
excavation in rock shall be done such that extra excavation beyond the required
width and depth as shown in drawings is not made. If the excavation done in depth
greater than required / ordered. The contractor shall fill the extra excavation with
concrete of mix 1:5:10 as the foundation concrete at his own cost.

3.1.8 Contractor shall make all necessary arrangements for dewatering/defiling as required
to carry out proper excavation work by bailing or pumping out water, which may
accumulate in the excavation pit from any cause / source whatsoever.

3.1.9 Contractor shall provide suitable draining arrangements at his own cost to prevent
surface water entering the foundation pits from any source.

3.1.10 The contractor is forbidden to commence the construction of structures or to carry
out concreting before Owner has inspected, accepted and permitted the excavation
bottom.


13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

21 | P a g e 5 0

0

3.1.11 Excavation in disintegrated rock means rock or boulders including brickbats that
may be quarried or split with crowbars. This will also include laterite and hard
conglomerate.

3.1.12 Excavations in hard rock - meant excavation made in hard rock to be done manually,
or by blasting using only explosives and / or pneumatic hammers. In case of blasting,
control blasting should be adopted depending on site conditions. For using
explosives contractor shall follow all provisions of Indian Explosive Act/Rules 1983,
corrected/ revised upto date.

3.1.13 In case of hard rock excavation to be carried out using explosive the contractor shall
obtain the written approval in advance.

3.1.14 The measurements for excavations shall be restricted and limited to minimum
excavation line as per drawing for payment purposes.

3.2 FILLING.

3.2.1 Back filling of excavations in trenches, foundations and elsewhere shall consist of
one of the following materials approved by Owner.

i) Soil
ii) Sand
iii) Moorum
iv) Hard-core
v) Stone / gravel.

All back filling materials shall be approved by the Owner /Consultant.

3.2.2 Soil filling - Soil material shall be free from rubbish, roots, hard lumps and any other
foreign organic material. Filling shall be done in regular horizontal layers each not
exceeding 20 cm. Depth.

3.2.3 Back filling around completed foundations, structures, and trenches and in plinth
shall be done to the lines and levels shown on the drawings.

3.2.4 Back filling around pipes in the trench shall be done after hydro testing is done.

3.2.5 Back filling around liquid retaining structures shall be done only after leakage testing
is completed and approval of Owner is obtained.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

22 | P a g e 5 0

0

3.2.6 Sand used for filling under foundation concrete, around foundation and in plinth etc.,
shall be fine / course, strong, clean, free from dust, organic and deleterious matter.
The sand filling under foundation shall be rammed with Mechanical compactor.
Sand material shall be approved by Owner.

3.2.7 Moorum for filling, where ordered, shall be obtained from approved pits and
quarries, which contain siliceous material and natural mixture of clay. Moorum shall
not contain any admixture of ordinary earth. Size of Moorum shall vary from dust to
10 mm.

3.2.8 Hard-core shall be of broken stone of 90 mm to 10 mm size suitable for providing a
dense and compact sub grade. Stone shall be sound, free from flakes, dust and other

Impurities. Hard core filling shall be spread and levelled in layers. 15 cm. Thick,
watered and well compacted with ramming or with mechanical / hand compacts
including hand packing wherever required.

4.0 PLAIN AND REINFORCED CONCRETE WORK

This specifications deals with cement concrete, plain or reinforced, for general use,
and covers the requirements for concrete materials, their storage, grading mix design,
strength and quality requirements, pouring at all levels, reinforcements, protection,
curing, form work, finishing, painting, admixtures, inserts and other miscellaneous
works.

4.1 Materials: All requirements shall conform to as laid down in section-2, clause-5 of
IS: 456.

4.1.1 Cement: Any of the following cements may be used as required and shall conform to
the requirements as laid down in clause 5.1 of IS: 456

IS - 269 Ordinary Portland cement, 33 Grade.
IS - 8041 Rapid hardening Portland cement.
IS - 455 Portland slag cement.
IS - 8112 43 Grade ordinary Portland cement.
IS - 12330 Sulphate resistant ordinary Portland cement.
IS - 12269 53 Grade ordinary port land cement.
IS - 6909 Specifications for super Sulphate cement.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

23 | P a g e 5 0

0

4.1.2 Water: Water used for mixing and curing concrete and water shall conform to the
requirements as laid down in clause 5.4 of IS: 456. Seawater shall not be used for
concrete work.

4.1.3 Aggregates: Coarse and fine aggregates for cement concrete plain and reinforced
shall conform to the requirements of ARE: 383 and / or IS: 515. Before using, the
aggregates shall be tested as per IS: 2386.

Coarse aggregate: Coarse aggregate for all cement concrete work shall be broken or
crushed hard stone, black trap stone obtained from approved quarries or gravel.

Sand: Fine aggregate for concrete work shall be coarse sand from approved sources.
Grading of coarse sand shall be within grading zones I, II or III laid down in IS: 383,
table-4. If required the aggregates (both fine and coarse) shall have to be thoroughly
washed and graded as per direction of Owner.

4.2 Mixing

All cement concrete plain or reinforced shall be machine mixed. Mixing by hand
may be employed where quantity of concrete involved is small, with the specific
prior permission of the Owner, 10 % extra cement shall be added in case of hand
mixing as stipulated in IS - 456.

4.3 Water Cement Ratio

Once a mix, including its water-cement ratio, has been determined and specified for
use by the Owner, that water cement ratio shall be maintained.

4.4 Laying

Concreting shall be commenced only after the Owner /Consultant has inspected and
passed the sub-base / base or the cantering, shuttering and reinforcement. Concrete in
Slab beams, columns, footings etc., shall be laid gently in layers not exceeding 15
cm and shall be properly consolidated by means of approved mechanical vibrators.

4.5 Curing:

a) After the concrete has begun to harden, it shall be protected with moist gunny
bags, sand or any other material approved by the Owner /Consultant against
quick drying. After 24 hours of laying concrete, the surface shall be cured by
flooding with water or by covering with wet absorbent materials for 7 days as
per the direction of Owner.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

24 | P a g e 5 0

0


b) Approved curing compounds may be used in lieu of moist curing with the
permission of the Owner /Consultant. Such compounds shall be applied to all
exposed surfaces of the concrete as soon as possible after the concrete has
set. No extra payment shall be made for the same.

4.6 Grades of Concrete: All requirements shall conform to as laid down in section-2,
clause-6 of IS: 456.

4.6.1 Grades of Cement concrete shall be as given below:

Group Grade Designation Specified Characteristic compressive
strength of 150mm Cube at 28 days
(N / mm
2
)
Ordinary
Concrete


Standard
Concrete






High
Strength
Concrete
M - 10
M - 15
M - 20

M - 25
M 30
M 35
M - 40
M 45
M 50
M 55

M 60
M 65
M 70
M - 75
M 80
10.0
15.0
20.0

25.0
30.0
35.0
40.0
45.0
50.0
55.0

60.00
65.00
70.00
75.00
80.00

NOTES:
1. In the designation of concrete mix M refers to the mix and the number
to the specified compressive strength of 150mm size cube at 28 days,
expressed in N/mm
2
.
2. For concrete of compressive strength greater than M55, design
parameters given in the standard may not be applicable and the values
may be obtained from specialized literatures and experimental results.


13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

25 | P a g e 5 0

0

4.6.2 Grades lower than M-15 shall not be used in reinforced concrete.

4.6.3 M-7.5 grades of concrete may be used for lean concrete bases and simple foundation
for masonry walls.

4.6.4 A sieve analysis test of aggregates shall be carried out as and when the source of
supply is charge without extra charge not withstanding the mandatory test required to
be carried out as per CPWD Specification.

4.6.5 All tests in support of mix design shall be maintained as a part of records of the
contract. Test cubes for mix design shall be prepared by the contractor under his own
arrangements and at his costs, but under the supervision of the Owner.

4.7 Nominal Mix Concrete.

4.7.1 All concrete work (P.C.C. / R.C.C.) Shall be with nominal mix concrete unless
specified otherwise. The proportions of materials used for concrete of grades M-5,
M-7.5, M-10, M-15 and M-20 shall be as per the following table.

Proportions for Nominal Mix of Concrete


Grade
of
Concrete
Total Quantity of
Dry Aggregate by Mass
per 50 Kg of Cement, to
be taken as sum of the
individual masses of
fine and Coarse
Aggregates, Kg.
Max.
Proportion of Fine
Aggregate to Coarse
aggregate

(by Mass)
Quantity of water
per
50 Kg of cement


Maximum in
Litres.
M - 5
M-7.5
M - 10
M - 15
M - 20
800
625
480
330
250
Generally 1.2
Subject to an
Upper limit of 1: 1.5
and
a lower limit of 1: 2 .5
60
45
34
32
30

Notes: 1. The proportions of the fine aggregates should be adjusted from upper limit to lower
limit progressively as the grading of the fine aggregates become finer and the
maximum size of coarse aggregate becomes larger. Graded coarse aggregate as per
IS: 383 may be used.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

26 | P a g e 5 0

0

2. This Table envisages batching by weight. Volume batching when done, the nominal
mixes would roughly be 1: 3: 6, 1: 2.5: 5 and 1: 1.5: 3 for M-10, M-15 and M-20
respectively.

3. For under water concreting the quantity of coarse aggregate, either by volume or
mass, shall not be less than 1.5 times and not more than twice that of the fine
aggregates.

4.7.2 The cement content of the mix specified for any nominal mix shall be
proportionately increased if the quantity of water in a mix has to be increased to
overcome the difficulties of placement and compaction, so that water-cement ratio is
not exceeded. In case of vibrated concrete, the limits specified, above may suitably
be reduced to avoid segregation.

4.7.3 if the nominal the nominal mix concrete made in accordance with the proportion
given for a particular grade does not yield the specified strength, such concrete shall
be classified as belonging to lower grade. However, if the strength results of test are
higher than those specified for the grade in the nominal mix of concrete it shall not
be placed in a higher grade.

4.8 Design mix concrete.

4.8.1 Design mix shall be allowed for major works where it is contemplated to be used by
installing weigh batch-mixing plant as per IS-4925.

At the time of tendering, the contractor, after taking into account the type of
aggregates, plant and method of laying he intends to use, shall allow in his tender for
the design mix i.e., aggregate/cement and water/cement ratios which he consider will
achieve the strength requirements specified, and workability for concrete, to be
properly furnished.

4.8.2 Soon after the contractor gets L.O.I. to commence the work, he shall carry out
preliminary tests for design mix on trial mixes proposed by him in design of mix to
satisfy the Owner that the characteristic strength specified in clause 3.6.1 is obtained.
Prior to this may ask the contractor has to get design mix done as per IS: 10262
through Government approved / reputed institute and contractor shall arrange the
same at his own cost. The concrete mix to be actually used shall be approved by the
Owner.

4.8.3. Notwithstanding the above, the following shall be the maximum combined weight of
coarse and fine aggregate per 50 Kg of cement.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

27 | P a g e 5 0

0

Sl.
No.
Grade of
Concrete
Maximum weight of the fine and coarse aggregate
Together per 50 kg of cement (for nominal mix only).
1.
2.
3.
M - 10
M - 15
M - 20
480 kg.
330 kg.
250 kg.


4.8.4 The workability of concrete produced shall be adequate, so that the concrete can be
properly placed and compacted. The slump shall be as follows, when vibrators are
used.

Placing conditions Deree of
workability
Slump (mm)
Blinding concrete, Shallow Concrete, Pavement
using pavers.

Mass concrete, Lightly reinforced sections in
slabs, beams, walls, columns, floors, hand placed
pavements, Canal lining, Strip footing

Heavily reinforced sections in slabs, beams, walls,
columns, slipform work, pumped concrete

Trench Fill, In-situ piling

Tremie concrete
Very Low



Low



Medium


High

Very High

Refer Clause
7.1.1 of IS:456


25 75



50 - 100
75 - 100

100 150

Refer Clause
7.1.1 of IS:456



4.8.5 The minimum consumption of the cement irrespective of design mix shall not be less
than the following:

SL. No. Grade of Concrete. Minimum consumption of Cement.

1.

M - 7.5 ( 1 : 4 : 8 )

170 Kg / C.um.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

28 | P a g e 5 0

0

2.
3.
4.

M - 10 ( 1 : 3 : 6 )
M 15 ( 1: 2: 4 )
M 20 ( 1:1.5:3)
220 Kg / C.um.
320 Kg / C.um.
400 Kg / C.um.

4.9. Testing of Concrete.

4.9.1 Testing of concrete, sampling and acceptance criteria shall be in accordance with
Clauses 14 and 15 of IS: 456.

4.9.2 A slump test shall be taken at each mixer at least once in every fifty batches mixed.
Any batch for which a slump test is being made shall not be transferred to the place
of lying until the slump test has been completed. Any batch, which gives a slump in
excess of that described at the time of preliminary tests, shall be rejected and
removed from the site.

4.9.3 At least six cubes shall be taken for every 30 Cu.m. Metres of concrete or part
thereof deposited in the work on any day. Three cubes shall be tested for 28 days
strength.

4.9.4 If a test for particular work does not meet the specified requirements, the Owner in
his absolute discretion may accept the work at a correspondingly reduced rate
provided the average strength at 28 days is not less than 85% of the specified
strength.


4.9.5 If the results are poorer than 85% of the specified strength, the Owner may order
further testing of any kind as may be deemed necessary in his opinion, including load
tests. The load tests shall be carried on the portion of the structure involving concrete
represented by the unsatisfactory works test and such other adjoining elements of a
building as the Owner may decide.

If the results of the load tests are not satisfactory, the contractor shall at his own cost
undertake remedial measures including dismantling and reconstruction according to
the directions and to the satisfaction of the Owner. If the load test is successful, the
Owner may exercise his judgement before accepting or rejecting the work and shall
still have the power to apply a reduction in rate as herein stated before, in case the
work in question is accepted.


4.10 Proportioning:
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

29 | P a g e 5 0

0


Mixes of cement concrete shall be as ordered. Where the concrete is specified by
grade, it shall be prepared by mixing cement, sand and coarse aggregate by weight as
per mix design. In case the concrete is specified as volumetric mix, then dry volume
Batching shall be done, making proper allowances for dampness in aggregate and
bulking in sand. Equivalent volume batching for concrete specified by grade may
however be allowed by the Owner at his discretion.


4.11 Pre cast concrete.

The specifications for precast concrete will be similar as for the cast-in-situ concrete.
All precast work shall be carried out in a yard made for the purpose. This yard shall
be dry, properly levelled and having a hard and even surface. If the ground is to be
used as a soft former of the units, shall be paved with concrete or masonry and
provided with a layer of plaster (1:2 proportion) with smooth neat cement finish or a
layer of M.S. sheeting. The casting shall be over suitable vibrating tables or by using
form vibrators as per directions of Owner.

The yard, lifting equipment, curing tank, finished material storage space etc, shall be
designed such that the units are not lifted from the mould before 7 (seven) days of
curing and can be removed for erection after 28 (Twenty Eight) days of curing. The
moulds shall preferably be of steel or of timber lined with G.I. Sheet metal. The yard
shall preferably be fenced.

Lifting hooks, wherever necessary or as directed by Owner shall be embedded in
correct position of the units to facilitate erection, even though they may not be so on
the drawings and shall be burnt off and finished after erection.

Precast concrete units, when ready shall be transported to site by suitable means
approved by Owner. Care shall be taken to ensure that no damage occurs during
transportation. All adjustments, levelling and plumbing shall be done as per the
instructions of the Owner. The contractor shall render all help with instruments,
materials and staff to the Owner for checking the proper erection of the precast units.

After erection and alignment the joints shall be filled with grout or concrete as
directed by Owner. If shuttering has to be used for supporting the precast unit they
shall not be removed until the joint has attained sufficient strength and in no case
before 14 (fourteen) days. The joint between precast roof planks shall be pointed
with 1:2 (1 cement: 2 sand) mortar where called for in the drawings.

4.12 Protection of Concrete:
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

30 | P a g e 5 0

0


All concrete shall be protected from damaged by rain or by workmen, equipment,
overload or any other causes. All edges, corners and projections of concrete
members likely to be damaged, shall be protected by means of wooden cover fillets.

4.13 Construction Joints:

Construction joints shall be made only where shown on the drawings or as approved
by the Owner. The procedure given in Clause 12.4 of IS-456 shall be followed for
general guidance.

4.14 Separation Joint:

Separation joint shall be obtained by using an approved alkathene sheet struck on the
surface against which concrete shall be placed. Adequate care should be taken to
cause no damage to the sheet.

4.15 Damp Proof Courses:
Damp proof course shall consist of cement concrete or R.C.C. of specified
proportions and thickness. Surface of brick or stone masonry shall be levelled and
prepared before laying the cement concrete.

4.16 Sampling of Concrete:

Sampling and strength Test of concrete. Acceptance criteria and Inspection and
Testing of Structure: These shall be as per the requirements laid down in clause Nos.
14, 15 and 16 of IS-456.

5.0 STEEL REINFORCEMENT:

5.1 Steel reinforcement shall comprise:

i) Mild steel bars conforming to IS-432, Part-I.
ii ) TISCON CRS bars.
iii ) Hard drawn steel wire fabric conforming to IS-1566.
iv ) Cold twisted bars conforming to IS - 1786.
v) TMT bars.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

31 | P a g e 5 0

0

5.2 All joints in reinforcement shall be lapped adequately to develop the full strength of
the reinforcement, unless reinforcement are as per provision of IS - 456 as per
instruction of Owner.

Following procedure shall be followed for welding of Tor steel reinforcement bars.

i ) Welding of Tor steel reinforcement bars shall be taken up only after specific
approval by Owner.

ii ) Lap welding with longitudinal beads shall only be adopted.

iii ) The thickness of weld bead should be 0.2 x diameter of bar and the length of
the longitudinal bead required shall be 10 x diameter of bar, however, the
maximum length of continuous bead shall be limited to 5 x diameter of bar
with intermediate gap. When welding is done on both sides bead length shall
be 5 x diameter of bar on each side.

iv ) Stripper at closer spacing shall be provided in the lap welded joints as
directed by Owner.

5.3 M.S. round bars shall be hooked at ends as specified. Ribbed Tor-steel shall be bent
at right angles at ends as indicated or directed.

6.0 FORM WORK.

6.1 The shuttering or formwork shall conform to the shape, lines and dimensions as
shown on the drawings and be so constructed as to remain sufficiently rigid during
placing and compacting of the concrete and shall be sufficiently tight to prevent loss
of liquid from the concrete. The surface that becomes exposed on the removal of
forms shall be examined by Owner or his authorised representative before any
defects are made good. Work that has sagged or bulged out or contains
honeycombing, shall be rejected. All shuttering shall be plywood or steel shuttering.

6.2 The Contractor shall be responsible for sufficiency and adequacy of all formwork.
Cantering and formwork shall be approved by the Owner /Consultant, before placing
of reinforcement and concreting.

6.3 Stripping Time:

Form shall not be struck until the concrete has reached a strength at least twice the
stress to which the concrete may be subjected at the time of removal of formwork.
The strength referred to shall be that of concrete using the same cement and
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

32 | P a g e 5 0

0

aggregates, with the same proportions and cured under conditions of temperature and
moisture similar to those existing on the work. Where possible, the formwork shall
be left longer as it would assist the curing.

Note: In normal circumstances and where ordinary Portland cement is used forms
may generally be removed after the expiry of the following periods:

SL.NO. I T E M S PERIOD
1. Vertical form work to columns, walls,
beams.
16 to 24 hours
2. Soffit form work to Slabs (props to be
re-fixed immediately after removal of
form work)
3 days.
3. Soffit form work to Beams (props to
be re-fixed immediately after removal
of form work)
7 days.
4. Props to slabs
i ) Spanning upto 4.5 m
ii ) Spanning over 4.5 m


7 days.
14 days.
5. Props to beams and arches.
i ) Spanning upto 6.0 m
ii ) Spanning over 6.0 m

14 days.
21 days.
For other types of cements, the striping time recommended for ordinary Portland
Cement may be suitably modified.

7.0 BRICK WORK:

7.1 Bricks:

All bricks shall conform to class 75 as designated in CPWD Specifications unless
specified otherwise.

7.2 Mortar:

7.2.1 Cement and water shall conform to the requirements laid down for cement concrete
work.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

33 | P a g e 5 0

0

7.2.2 Sand for masonry mortar shall be coarse sand conforming to IS: 2116. Maximum
quantities of clay, fine dust shall not be more than 5% by weight. Organic impurities
shall not exceed the limits laid down in IS: 2116.

7.2.3 Mix of mortar for building brickwork shall be as specified in the item of work.

7.2.3 Mixing of mortar shall be done a mechanical mixer. When quantity involved is
small, hand mixing may be permitted by the Owner. Any mortar remaining unused
for more than 30 minutes after mixing shall be rejected.

7.3 Brick Masonry:

Brickwork shall be built in English bond, unless otherwise specified. The thickness
of joints shall be 10 mm 3 mm. Thickness of joints shall be kept uniform. In case
of foundations and manholes etc. joints upto 15 mm may be accepted.

7.4 Half Brick Masonry:

All courses shall be laid with stretchers. Reinforcement comprising 2 Nos. 6.0 mm
dia M.S. bars shall be provided over the top of the first course and thereafter at every
third course.

7.5 Laying:

All iron fixtures, pie spouts, hold fasts of doors and windows, which are required to
be built into the wall shall be embedded in cement concrete blocks 1: 2: 4 (1 cement:
2 coarse sand: 4 graded stone aggregate 20 mm nominal size) 150 mm x 100 mm x
100 mm size unless otherwise indicated in the item.

7.6 Curing:

Brickwork shall be protected from rain by suitable covering when the mortar is
green. Masonry work shall be kept constantly moist on all faces for a minimum
period of seven days.

7.7 Cement Concrete Block.

Cement concrete block shall be machined made in the proportion of such that mix.
Shall not be leaner than one cement to twelve combined aggregates (by volume) but
having minimum strength of M-7.5. Combined aggregate shall be graded as near as
possible to IS: 383. The fineness modules of combined aggregate shall be between
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

34 | P a g e 5 0

0

3.6 and 4. The concrete block shall be properly cured as per IS-456. The surface of
concrete block shall have even face without any honeycomb and free from cracks.

7.7.1 Mortar:

Cement and water shall confirm to the requirements laid down for cement concrete
work.

7.7.2 Sand for concrete block masonry mortars shall be coarse sand generally conforming
to IS: 2116. Maximum quantities of clay, fine dust, shall not be more than 5% by
weight. Organic impurities shall not exceed the limits laid down in IS: 2116.

7.7.3 Mix of mortar for building concrete block shall be as specified in the item of work.

7.7.4 Mixing of the mortar shall be done in a mechanical mixer. When quantity involved is
small hand mixing may be permitted by Owner. Any mortar remaining unused for
more than 30 minutes after mixing shall be rejected.

7.8 Concrete Block Masonry:

The thickness of joints shall be 10 mm 3 mm. Thickness of joints shall be kept
uniform. In case of foundation and manholes etc., joints upto 15 mm may be
accepted.

7.9 Half Concrete Block:

All courses shall be laid with stretchers. Reinforcement comprising 2 Nos. 6 mm dia
M.S. bars shall be provided over the top of the first course and thereafter at every
fourth course.

7.10 Laying:

All iron fixture, pipes spouts, hold fasts of doors and windows which are required to
be built into the wall shall be embedded in cement concrete blocks 1: 2: 4 mix ( 1
cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size ) 150 mm x
100 mm x 100 mm size unless otherwise indicated in the item.

7.11 Curing:

Concrete block masonry shall be protected from rain by suitable covering when
mortar is green. Masonry work shall be kept constantly moist on all faces for
minimum period of seven days.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

35 | P a g e 5 0

0




8.0 WOOD WORK:

8.1 All materials workmanship for woodwork shall conform to IS: 883, it shall be good
quality well seasoned second class Teak / Sal wood as approved by Owner. The
woodwork shall conform to IS: 4021.


9.0 STEEL / ALUMINIUM DOORS, WINDOWS & VENTILATORS:

9.1 The steel doors, windows, ventilators and sashes shall be of the size and type as
shown on the drawings and/or of the approved make conforming to IS-1361 and
IS-1038. Fixing and glazing shall be done as per IS-1081 and as per manufacturers
instructions. The putty of approved make such as special gold size or equivalent
conforming to IS - 419 shall be used.

9.2 Aluminium doors, windows and ventilators shall be manufactured from wrought
aluminium and aluminium alloy extruded round tube and/or hollow rectangular /
square sections conforming to IS: 1285 and IS: 6477 or equivalent as approved by
Owner.

10.0 FLOORING AND PAVING:

10.1 Sub base of Floor:

10.1.1 The area to be paved shall be divided into suitable panels. Formwork shall be
provided. The boarding / battens shall be fixed in position with their toe at proper
level, giving slope where required. Alternatively base concrete may be deposited in
the whole area at a stretch.

10.1.2 Before placing the base concrete the sub-base shall be properly wetted and rammed.
The concrete of the specified mix shall then be deposited between the forms where
provided, thoroughly tamped and the surface finished level with the top edge of the
forms. The surface of base concrete shall be spread uniformly. The surface shall be
finished rough to provide adequate bond for the topping. Two or three hours after
concrete has been laid the surface shall be brushed with wire brush to remove any
scum or Latinate and swept clean so that coarse aggregate is exposed.

10.2 Cement Concrete Floor Finish.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

36 | P a g e 5 0

0

10.2.1 The surface of base concrete shall be thoroughly cleaned by scrubbing with coir or
steel wire brush. Before laying the topping, the surface shall be soaked with water at
least for 12 hours and surplus water mopped up immediately before the topping is
laid.


10.2.2 The forms shall be fixed over the base concrete dividing into suitable panels. Where
glass-dividing strips are provided, thickness of glass dividing strips shall be 4 mm or
as indicated. Before placing the concrete topping, neat cement slurry at the rate of
2 Kg/Sq.m. shall be then thoroughly brushed into the base concrete just ahead of the
finish. The topping shall then be laid, thoroughly compacted by using screed
board/plate vibrator. The surface floated with a wooden float to a fair and even
surface shall be left for some time till moisture disappears from it. Junctions with
skirting / dado on wall surfaces shall be rounded off using cement mortar 1:2. Curing
shall be carried out for a minimum of 7 days.

11.0 PLASTERING:

11.1 Sand for plastering shall be 50% fine sand and 50% coarse sand from approved
sources.

11.2 Preparation of surface shall be done as per CPWD Specifications.

13.3 Cement mortar shall be of the mix as indicated in the items and shall be mixed as
specified in the CPWD Specifications.

13.4 Joints in walls etc. shall be raked to a depth of 12 mm, brushed clean with wire
brushes dusted and thoroughly washed before starting the plaster work.

13.5 The surface shall be thoroughly washed with water cleaned and kept wet to
saturation point before plastering is commenced.

13.6 Cement mortar as indicated, shall be firmly applied to the masonry walls in a
uniform layer to the thickness specified and will be pressed into the joints. On
concrete surfaces rendering shall be dashed to the roughened surface to ensure
adequate bond. The surface shall be finished even and smooth. Hectoring wherever
required shall be done as per directions of Owner. Nothing extra shall be paid on this
account.

13.7 All plaster work shall be cured for at least 7 days.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

37 | P a g e 5 0

0

13.8 Integral water proofing compound shall be mixed with cement in the proportion
recommended by the manufacturer. Care shall be taken to ensure that the water
proofing material gets well and integrally mixed with cement. All other operations
are the same as for general plaster work.

13.9 For sand face plaster, undercoat of cement plaster 1:4 ( 1 cement : 4 sand ) of
thickness not less than 12 mm shall be applied similar to one coat plaster work.
Before the under coat hardens the surface shall be scared to provide for the top coat.
The top coat also of cement mortar 1:4 shall be applied to a thickness not less than 8
mm and brought to an even surface with a wooden float. The surface shall then be
tapped gently with a wooden float lined with cork to retain a coarse surface texture,
care being taken that the tapping is even and uniform.

14.0 WHITE & COLOUR WASHING AND CEMENT PAINTING:

14.1 White Washing:

14.1.1 Where white wash is indicated, 3 coats of white wash shall be applied. The surface
shall present a smooth and uniform finish.

14.1.2 White wash shall be prepared from lime slaked at site and mixed and stirred with 5
litres of water for one Kg. of unslaked lime to make a thin cream. The cream shall be
screened through a clean, coarse cloth and suitable adhesive such as DDL or
equivalent as per manufacturer specification shall be added. About 1.3 Kg of sodium
chloride in hot water shall also be added for every 10 Kg. Of lime for making the
coat hard and rule resistant. Indigo shall also be mixed @ 3 gm/Kg of lime. Each,
coat shall be allowed to dry before next coat is applied. When dry the wash should
show no sign of cracking, one coat consists of application with brushes in horizontal
stroke followed by vertical stroke.

14.2 Colour Washing:

14.2.1 Where colour wash is indicated one coat of white wash and two coats of colour of
tints approved by the Owner shall be applied. Dados and skirting shall not be white
washed, colour washed or distempered or painted.

14.2.2 Only colour stainer of approved brand not affected by lime. Shall be added to colour
wash. Indigo (Neel) shall, however, not be added in colour wash.

14.2.3 The colour wash shall be applied as described for white wash. After the surface has
been prepared the first primary coat shall be of white wash. Minimum two coats of
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

38 | P a g e 5 0

0

colour wash shall then be applied. The entire surface shall present a smooth and
uniform finish of even tint or shade.

14.3 Distempering:

14.3.1 Where distempering is indicated, two coats of distemper oil emulsion or dry
distemper over a priming coat as specified in the item shall be applied. Each coat of
distemper shall be approved by the Owner /Consultant before next coat is applied.

14.3.2 Distemper oil emulsion shall be as per IS: 248 of approved brand and manufacture.
The distemper shall be diluted with water or a prescribed thinner in the proportion of
4 parts of paste by weight to one part of cold water or in the proportion specified by
the manufacturer, which shall be invariably followed.

14.3.3 The surface to be distempered shall be cleaned of dust, dirt, chalking and other
foreign matter. All cracks, holes and surface defects shall be repaired with gypsum to
give a smooth surface, and papered and wiped clean. The surface shall then be
rubbed down again with sand paper and made smooth. The surface thus prepared
shall be given a coat of alkali resistant priming paint conforming to IS: 109, or any
other primer as specified by the manufacturer and allowed to dry at least for 48
hours.

14.3.4 Dry distemper shall be of approved make and shade conforming to IS: 427 and shall
be prepared as per manufacturers specification. The surface to be distempered shall
be cleaned of dust, dirt, chalking and other foreign matter. All cracks, holes and
surface defects shall be repaired with gypsum to give a smooth surface, and papered
and wiped clean. The surface shall then be rubbed down again with sand paper and
made smooth. The surface thus prepared shall be given a coat of alkali resistant,
priming paint conforming to IS: 109 or any other primer as specified by the
manufacturer and allowed to dry at least for 48 hours.



14.3.5 After the primer coat has dried for at least 48 hours, the surface shall be lightly sand
papered to make it smooth for receiving the distemper, taking care not to rub cut the
priming coat and then dusted off. Prepared distemper shall then be applied with
brushes in horizontal strokes followed immediately by vertical ones, which together
constitute one coat.

14.3.6 Subsequent coats shall be applied in the same way, with time intervals of at least 24
hours between consecutive coats.

13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

39 | P a g e 5 0

0

14.3.7 A uniform finished surface without patches, brush marks, or distemper drops shall be
obtained.

14.4 Cement Painting:

14.4.1 Cement paint: Cement paint shall comply with IS: 5410 specification for cement
paint of colour as required.

14.4.2 Where shown on drawings for external surfaces of sand faced plaster, or any other
surface, two coats of cement paint shall be applied of tint and shade as approved by
the Owner.

14.4.4 On external plastered surfaces, sand faced or plain plastered and concrete surfaces,
cement paint shall be vigorously scrubbed on to work the paint into the voids and
provide a continuous paint film free from pin holes and other openings. Curing shall
be done between the coats and for at least 2 days following the final coat.

15.0 GLAZING

15.1 Sheet glass glazing of doors, windows etc., shall be of selected quality glass
conforming to IS: 2835. Toughened splinter proof industrial safety glass shall
confirm to IS: 2553. No cracked chipped or disfigured glass shall be accepted Glass
shall be in one piece for each pan.

15.2 Glazing shall be fixed with timber or steel / aluminum beading as called for Glass
shall be back puttied and fixed with beading for water tight and rattle free
installation. Sizes of timber /steel / aluminum beading shall be as directed.

.

16.0 DISMANTLING & DISPOSAL:


16.1 Scope
This specification defines the demolition, dismantling of reinforced
concrete, plain concrete, brickwork and structural steel work or any such
other work. Any special requirement as shown or noted on the drawing
shall govern the provision of this specification.
16.1.1 Demolition
The term demolition implies breaking up. This shall consist of demolishing
whole or part of work including all relevant items as specified or shown on
the drawings.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

40 | P a g e 5 0

0

16.1.2 Dismantling
The term dismantling implies carefully removing without damage (up or
down). This shall consist of dismantling one or more part of the building as
specified or shown on the drawings.
16.2.0 General
16.2.1 Precautions
16.2.1.1 All materials obtained from dismantling or demolition shall be the property
of the owner unless otherwise specified and shall be kept in safe custody
until handed over to the engineer-in-charge.
16.2.1.2 The demolition shall always be planned before hand and shall be done in
reverse order of those in which the structure was constructed. The scheme
shall be got approved from the engineer-in-charge before starting the work.
16.2.1.3 Necessary propping and/or under-pinning shall be provided for the safety
of the adjoining work or property before dismantling and demolishing is
taken up and the works shall be carried out in such a way that no damage is
caused to the adjoining work or property. Whenever specified temporary
enclosures or partition shall also be provided.
16.2.1.4 Necessary precautions shall be taken to keep down dust, nuisance.

16.2.1.5 Dismantling shall be done in a systematic manner. All materials which are
likely to be damaged by dropping from a height of demolishing roofs,
masonry etc. shall be carefully removed first. The dismantled articles shall
be passed by hand, where necessary lowered to the ground (and not
thrown) and then properly stacked as directed by the engineer-in-charge.
16.2.1.6 Where fixing is done by nails, screws, bolts etc. dismantling shall be done
by taking out the fixing with proper tools and not by tearing or ripping off.
16.2.1.7 Any serviceable material, obtained during dismantling or demolition, shall
be separated out and stacked properly as directed by the engineer-in-charge
within a lead of 50 metres. All unserviceable materials rubbish etc. shall be
disposed off as directed by the Engineer-in-charge.
16.2.1.8 The contractor shall maintain disconnected services whether temporary or
permanent, if required.
16.2.2.0 Payment
16.2.2.1 All work shall be measured in the decimal system, as fixed in its place,
subject to the following limits unless otherwise stated hereinafter: -
a. Dimensions shall be measured correct to a cm.
b. Areas shall be worked out correct to two places of decimal
c. Cubic contents shall be worked out to the nearest 0.01.
16.2.2.2 Parts of work required to be dismantled and demolished shall be measured
separately.
16.2.2.3 Measurements of all works except hidden work shall be taken before
demolition or dismantling and no allowance for increase in bulk shall be
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

41 | P a g e 5 0

0

allowed.
16.2.2.4 Specifications for deduction for voids, openings etc. shall be on the same
basis as that employed for construction of the work.
16.2.2.5 The rate shall include the cost of all labour involved and tools used in
demolishing including scaffolding. The rate shall also include the charges
for separating out and stacking the serviceable material properly within a
distance of 50 metres and disposing off unserviceable materials as directed
by Engineer-in-charge.

16.3.0 Roofs
Ridges, heaps and valleys shall be girthed and included with the roof area.
Corrugated or semi corrugated surfaces shall be measured flat and not
girthed.
Supporting members, such as rafters, purlins, beams, joints, trusses etc.
shall be measured in metric tonnes.
16.4.0 Concrete and Brick Roofs and suspended Floors.
Demolition of floors and roofs of concrete or brick shall be measured in
cubic metres (M) beams, cantilevers or other subsidiary supports of similar
materials shall be included in the item. In measuring thickness of roofs
provided with water proofing treatments with bitumen felts, the thickness
of water proofing treatment shall be ignored.
16.5.0 Walls and Piers
16.5.1 Taking down walls and independent piers or columns of brick stone or
concrete shall be measured in cubic metres (M). All copings, corbels,
cornices and other projections shall be included with the measurements.
In measuring thickness of plaster, walls, the thickness of plaster shall be
ignored.
16.5.2 Ashlar face stones, dressed stone work, precast concrete article etc. if
required to be taken down shall e so stated, and measured separately in
cubic meters (m)
16.5.3 Cleaning bricks, stacking for measurements including all extra handling
and removed and disposing rubbish as stated shall be enumerated in the
thousand of cleaned bricks.
16.5.4 Cleaning stone obtained from demolished/dismantled stone masonry of any
description including ashlar facing, dressed stone slabs or flanging and
precast concrete blocks including all extra handling and disposing of
rubbish as stated shall be measured in cubic metres (m) of cleaned stone.
16.5.5 Honeycomb work of cavity walls of bricks, stone or concrete as solid.
16.6.0 Reinforced concrete and Brick work
Reinforced concrete structures and reinforced brick roofs and walls shall
be measured in cubic metres and square metres as specified in schedule of
rates and reinforcement if required to be salvaged, shall be stated.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

42 | P a g e 5 0

0


Where reinforcement is required to be separated, scraped, and cleaned, the
work shall be measured separately in metric tonnes (MT) of salvaged steel.
16.7.0 Steel and Iron work
16.7.1 All steel and iron work shall be measured in metric tonnes (MT). The
weight shall be computed from standard tables unless the actual weight can
readily to be determined.
16.7.2 Riveted work, where rivets are required to be cut, shall be measured.
16.7.3 Marking of structural steel required to be re-erected shall be measured
separately.
16.7.4 In framed steel items, the weight of any covering material of filling such as
iron sheets and expanded metal shall be included in the weight of the main
article unless such covering is not ordered to be taken out separately.



17. DRAINAGE AND SANITATION.

17.1.0.0 SCOPE
17.1.1.0 This section covers the layout and construction of drains for roof water,
surface water and sewage together with all fittings and fixtures and
inclusive of ancillary works, such as connections, manholes and inspection
chambers used within the building and from the building to the connection
to a public sewer or to treatment work. Septic tank and soak pit dispersion
trenches.
17.2.0.0 INSTALLATION
17.2.0.1 General
All pipelines, locations of fittings and fixtures, etc., shall be as per
drawings or as directed by the Engineer, Correctness of lines, plumb,
orientation, symmetry and levels shall be strictly ensured. All items shall
be fully secured against movement in any direction and so located as to
allow easy maintenance
17.2.1.0 Rainwater Down corners
Rainwater down corners shall be standard Cast Iron of Asbestos Cement
Pipes. In case where specifically desired. M.S. pipes may also be used.
M.S. pipes shall be painted outside with two coats or anti corrosive paints
under a coat of primer.
Rainwater down corners shall run along and be secured to walls, columns
etc., where desired by the Engineer these may have to be installed in chases
cut in the structure. All pipes shall be wall secured and supported by
adequately strong brackets. The brackets may be wrought iron clevis type,
split ring type of perforated strap iron type as approved by the Engineer.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

43 | P a g e 5 0

0

For vertical runs each pipe shall hang freely on its brackets fixed just below
the socket `suitable spacer blocks shall be provided against the vertical
surface to which the pipe is fixed.
All bends and junctions shall be supplied with watertight clean outs.

Proof and floor drains and vard gullies shall be installed. If required, by
cutting into the structure and grouted with 1:2:4 cement concrete. All
gutters shall be provided with removable grating.
All horizontal pipes shall have a minimum fall of 1 in 100.
17.2.2.0 Gutters
The gutters shall be made of G.I. of A.C. All gutters shall be supplied by
reputable specialised firms. Each section shall be sufficiently rigid, edges
and corners straight and the slopes perfectly uniform G.I. gutters shall have
the edges strengthened by suitable means.
Unless noted otherwise the gutters shall have a minimum fall of 1 in120.
Adequate number of string supports shall be provided so that there is no
deflection even when the gutter is full. Each point must have a support.
Unless otherwise specified the supports shall be fabricated M.S. brackets.
Al junctions shall be thoroughly watertight. The joints may be made by
riveting, bolting or soldering. All joints between successive lengths of
gutters shall have on overlap of at least 5 cm. The drop in the overlap shall
always be in the direction of the fall of the gutter. Ends of gutters shall be
closed watertight. Junction with rainwater down corners shall be made fly
watertight and secured.
17.2.3.0 Soil and Drainage Pipes
17.2.3.1 Gradients
If not specified the minimum gradients of solid and drainage pipe line shall
be as follows:
100 mm nominal dia: 1 in 35
150 mm nominal dia: 1 in 65

230 mm nominal dia: 1 in120
300 mm nominal dia : 1 in 200
17.2.3.2 Relation with water supply pipe lines
Unless specifically cleared by the Engineer, under no circumstances shall
special drainage and soil pipes be allowed to come close to water supply
pipelines.

17.2.3.3 Laying
Each separate pipe shall be individually set for line and for level. Where
lengths of sewer or drain pipes are laid in trench, properly; painted sight
rails shall be fixed across the trench at a height, equal to length of the
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

44 | P a g e 5 0

0

bonding rod fixed across the trench at a height, equal to length of the
bonding rod to be used, above the required invert level of the drain or
sewer at the point where the sight is fixed. More sight rails shall be
required at manholes, change of gradient and intermediate positions if the
distance for sighting is more than 50 ft. the foot of the boning rod shall be
set on a block of wood of the exact, thickness of the wall of the pipe. Each
pipe shall be separately and accurately boned between sight rails.
17.2.3.4 Support and Protection on Pipelines
All pipes shall be laid with sockets leading uphill; Preferably the pipe shall
rest on solid and even foundations for the full length of the barrel.
However, the pipe manufacturers instruction as approved by the Engineer
shall be followed in the matter of support and jointing.
To achieve full and continuous support, concrete for bedding and packing
is the best. Where pipes are not bedded on concrete, the floor shall be left
slightly high and carefully placed so that the pipe barrels rest on
undisturbed ground. If anywhere the excavation has been carried too low
packing shall be done in concrete. Where

laid on rock or very hard ground which cannot be easily excavated to a
smooth surface, the pipes shall be laid on a cradle of fine concrete floor of
gravel and crushed stone over laid with concrete or on a well consolidated
gravel and crushed stone bed as desired by the Engineer. PVC or similar
pipes shall be laid directly on stable solid and packed with selected soil.
The minimum support and protection for glazed stoneware pipes shall be as
follows:
a) When cover is less than 2 meter below ground level and where pipes
are unavoidably exposed above ground surface, the pipes shall be
completely encased or surrounded with concrete.
b) Where pipes are laid on soft solid with the maximum water table
laying at the invert of the pipe, the sewer shall be bedded on concrete.
c) Where the pipes have to be laid on soft solid with the maximum
water table rising above the invert of the pipe, but below the top of
the barrel the pipe sewer shall be hunched.
d) Where maximum water table is likely to rise above the top of the
barrel or wherever the pipe is laid on soft soil the pipe sewers shall be
completely encased or surrounded with concrete.
Vitrified clay pipe shall be laid on a bed of 150 mm thick cement concrete
(1:3:6) nominal mix by volume.
Cast iron pipes and concrete pipes may be supported on suitable concrete
or brick support, where specified. The supports shall be unyielding and
strong enough. At least one support shall be located close to ends. Spacing
of intermediate supports shall be as decided by the engineer, Pipes shall be
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

45 | P a g e 5 0

0

secured to the supports by approved means.
Anchoring of pipes where necessary shall be achieved by suitable concrete
encasing designed for the expected thrust.

17.2.3.5

Manhole and Inspection chambers
The maximum distance between manholes shall be 30 meter unless
specially permitted otherwise. In addition, at every change of alignment
gradient or diameter there shall be a manhole or inspection chamber. The
distance between manhole or inspection chamber and gully chamber shall
not exceed 6 meters unless desired otherwise. Manhole shall be constructed
so as to be water tight under test. The bending at the sides shall be carried
out in such a manner as to provide no lodgement for any splashing in case
of accidental flashing of the chamber. The channel or drain at the bottom of
chamber shall be plastered with 1:2 cement, sand mortar and finished
smooth to the grade. The channels and drains shall be shaped and laid to
provide smooth flow.
Connecting to existing sewer lines shall be through a manhole.
Manholes shall be provided with standard G.I. covers. The covers shall be
close fittings so as to prevent gases from coming out suitable heavy-duty
covers shall be used where necessary as decided by the engineer.
17.2.3.9 Cutting of pipes
Manufacturers instructions shall be followed for cutting of pipes where
necessary. Suitable and approved tools shall be used for the cutting so as to
leave surface clean and squat to the axis of the pipe.
17.2.3.10 Jointing
Jointing of laid pipes shall be so planned as to avoid completely any
movement or strain to the joints already made. If any joint is suspected to
be damaged it shall be opened out and redone.
All joints between pipes, pipes and fittings and manholes shall be gas-tight
when above ground and watertight. When underground

Method of jointing shall be as per instructions of the pipe and fittings
manufacturer and as approved by the Engineer. However, in the absence of
any instruction available from the manufacturer the methods as detailed
here under shall be used.
a) Cast Iron pipes
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

46 | P a g e 5 0

0

Socket and spigot pipes shall be jointed by the cast lead joints. The
spigot shall be entered in the socket of the next pipe by tightly
caulking in sufficient turns of tarred gasket or hemp yarn to have
unfilled half the depth of socket. When the gasket or hemp yarn has
been caulked tightly a jointing shall be placed round the barrel and
tightened against the face of the socket to prevent air lock. Molten
lead shall then be poured in to fill the remainder of the socket and
caulked with suitable tools right round the joint to make up for
shrinkage of the molten metal on cooling and shall be finished 3 mm
behind the socket face.
Joints in cast iron pipes with special jointing arrangements like
`Tyton joints etc., shall follow the instructions of the manufacturers.
In special cases if fanged joints are accepted by the engineer the
joints shall be made lead-proof by inserting approved type of rubber
gaskets. The bolts shall be secured in stages to avoid uneven strain.
b) Concrete pipes
Care shall be taken to place the collar centrally over the joint.
c) Glassed stone water pipes



Tarred gasket or hemp yarn soaked in thick cement slurry shall first
be placed round the spigot of each pipe and the spigot shall then be
placed into the socket of the pipe previously laid. The pipe shall then
be adjusted and fixed in the correct position and the gasket caulked
tightly so as not to fill more than of the total depth of the socket.
The remainder of the socket shall be filled with a stiff mixture of
cement mortar of 1:1 proportion. Then the socket is filled, a fillet
shall be formed round the joint with a trowel, forming an angle of 45
deg. with the barrel of the pipe. The newly made joints shall be
protected, until set and shall be covered with damp cloth or other
suitable materials.
d) Verified clay pipes
These shall be made from refractory clay mixed with crushed pottery
and stone and burnt at a height temperature. These shall e hard,
compact and glazed to make them acid resistant and impervious, and
shall be obtained from approved manufacturer.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

47 | P a g e 5 0

0


Special care shall be taken in handling these pipes. The pipes shall
not be jointed until the earth has been partly refilled over the portion
of the pipe between the joint holes. Before laying the second pipe, the
socket of the first pipe laid shall be thinly painted all rounds on the
inside with cement slurry (1 part of cement and 2 parts of clean, sharp
sand). A ring of rope yarn (closely twisted heap or jute dipped in neat
cement paste or tar or bitumen, shall be inserted in the socket or pipe
and driven home with caulking tools. The rope shall fully encircle the
spigot with a slight overlap and shall not occupy more than one fourth
of the total depth of the socket. Where the spigot end of the pipe is
made for receiving the gasket, it shall be wrapped with two or three
turns of tarred spun, as close to the end as possible, before inserting
into the socket. The joint shall then be completely filled with cement
mortar (1:1), which shall have very little water and levelled to form a
splayed fillet at an angle of 45 degrees with the outside pipe. Special
care shall be taken so that any excess mortar etc., left inside the pipe
joints is neatly cleaned off immediately after each joint is made. A
semi-circular wooden scrapper or a rubber disc to which a long
handle is fixed could be used for this purpose.
e) Lead Pipes
No lead pipes shall be used unless specifically mentioned in the
specification. The joints in lead pipes shall be made as wiped solder
joint. The minimum and the maximum length of the wiped solder
joints shall be 8 cm. And 9 cm respectively. The solder shall
generally consist of two parts of lead and one part of tin.

f)

Polyethylene pipes
The joints shall be thermo-welded or bolted as per manufacturers
instructions
j) Jointing cast Iron pipes with stoneware pipes
Where any cast iron soil pipe, ventilating pipe or trap is connected
with a stoneware or semi-vitrified waste pipe or drain communicating
with a sewer, the beaded spigot end of such cast iron soil pipe, waste
or ventilating pipe or trap shall be inserted in to a socket of such
stoneware pipe or drain and the joint made with mortar consisting of
one part of cement and one part of clean shape sand after placing a
ratted gasket or hemp yarn soaked in neat cement slurry round the
joint and inserted in it by means of a caulking tool.
h) Jointing stone ware with Cast Iron pipes
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

48 | P a g e 5 0

0

Where any water closet pan or earthware trap connected to such a pan
is to be jointed with a cast Iron soil pipe, the joint between the
stoneware spigot and the cast iron socket, shall always be of a
flexible nature. Such joint shall be made with admixture of bitumen
and chopped asbestos fibre.
17.2.4.0 Trenches and other excavations
Width of the trench at the bottom shall be such as to provide 200 mm
clearance on either side of the pipe for facility of laying and jointing.
Excavated material shall be stacked sufficiently away from the edge
of the trench and the side of the spoil bank shall not be allowed to
endanger the stability of the excavation. Spoil may be carted away
and used for filling the trench behind the work.
Turf, top soil or other surface material shall be set aside, turf being
carefully rolled and stacked for use in reinstatement.
All excavation shall be properly timbered, where necessary.
Efficient arrangements for de watering during excavation and keeping
it dry till backfiring shall be made to the satisfaction of the Engineer;
sumps for de watering shall be located away from the pipe layout.
Where the excavation proceeds through roads necessary permissions
shall be secured by the contractors from the appropriate authorities.
Special care shall be taken not to damage underground services,
cables etc. These when exposed shall be kept adequately supported
till the trench is backfilled.
The backfilling shall be done only after the pipeline has been tested
and approved by the Engineer. Special care shall be taken under and
sides of the pipe during handpicking with selected material. At least
300 mm over the pipe shall also be filled with soft earth or sand.
Consolidation shall be done in 150 mm layers. The surface water
shall be prevented from getting into the filled up trench. Traffic shall
not be inconvenienced by heaping up unduly the backfilling material
to compensate future settlement. All future settlements shall be made
good regularly to minimize inconvenience of traffic where applicable.
17.2.5.0 Fixtures
The Tenderer shall mention in his bid the type and make of the fixtures he
intends to use enclosing manufacturers current catalogues. In the absence
of any such agreement, the Engineer shall be at liberty to choose any type
and make.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

49 | P a g e 5 0

0


All fixtures and fittings shall be of approved quality and type manufacturer
by well known manufacturers. All items brought to the site must bear
identification marks of the type of the manufacturer. Procurements shall be
made well in advance and inspected and approved immediately by the
Engineer. All fixtures shall be adequately protected, covered and plugged
till handed over.
All fittings, gratings, fasteners, unless specified otherwise, shall e
chromium plated. The connecting lead pipes and bonds shall weigh at least
3 kg per 25 mm dia. Per meter length. Where PVC or similar pipes are
allowed the contractor shall produce the test reports and convince the
Engineer about their durability.
Unless specified in the contract the fixtures shall be as specified herein
after.
17.2.5.1 Water closet
a) Raised type
It shall include glazed vitreous china basin with siphon, open front
solid plastic seat and plastic cover, low level glazed stoneware
flushing cistern with valve less fittings, supply connections and
necessary fittings. All fittings shall be chromium plated. Colour of
basin, cistern, seal and cover shall be as desired by the Engineer.
b) Squatting type
It shall include glazed vitreous china basin with siphon, open front
solid plastic seat and plastic cover, low level glazed stoneware
flushing certain with valve less fittings, supply connections and
necessary fittings. All fittings shall be chromium plated. Colour of
basin, cistern, seal and cover shall be as desired by the Engineer.
17.2.5.2 Urinals

It shall consist of wall type glazed vitreous china urinals, cast iron
automatic flushing cistern complete with supply connections, flush pipe
PVC pipes, gratings, traps and all other necessary fittings. Automatic
flushing shall be approximately once every five minutes for a number
urinals located together may be served by one cistern of adequate capacity.
All fittings shall be chrome plated.
17.2.5.3 Wash basin
It shall be made of glazed vitreous china. The basin shall be flat back, wall
hung by painted cast iron brackets and complete with pillar Cocks. PVC
waste pipes with traps, perforated waste complete with necessary fittings.
All fittings, including facts shall be chromium plated. Hot and cold mixer
waste chain and waste washers shall be provided where specified in the
schedule of items.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

50 | P a g e 5 0

0

171.2.6.3 Soak pit
The soak pit shall be complete as shown on drawing. The pit shall be lined
with stone; brick or concrete blocks set in cement mortar (1:6) and filled
with brickbats. Inlet pipe shall be taken down to a depth of 900 mm from
the top as an anti-mosquito measure.
17.2.6.4 Open joined SW pipe/Dispersion Trenches
Minimum dia. Of the SW pipes shall be 150 mm nominal. The trench for
laying the pipes shall be minimum 600x600 mm. The joints of the pipes
shall be left unsealed. The entire length of the pipe within the trench shall
be buried in 250 mm layer gravel or crushed stone of uniform size. On top
of gravel/crushed stone layer is a 150 mm bed of well graded coarse
aggregate. Ordinary soil is used for filling the top of trench.
17.2.6.5 Commissioning septic tank
After the septic tank has been proved watertight and the seawater system is
checked the tank shall be filled with water to its outlet level before the
sewage is let into the tank. It shall be seeded with well digested sludge
obtained from septic tank or sludge digestion tank. In the absence of
digested sludge a small quantity of decaying organic matter such as
digested cow-dung may be introduced.
17.3.0.0 TESTING AND ACCEPTANCE
17.3.1.0 Inspection before Installation
All pipes, fittings and fixtures shall be inspected, before delivery at the site
to see whether they conform to accepted standards. The pipes shall again
be inspected on site before lying by sounding to disclose cracks. All
defective items shall be clearly marked and forthwith removed from the
site.
17.3.2.0 Testing of pipelines
Comprehensive tests of all pipelines shall be made by simulating
conditions of use. The method of actual tests shall be decided by the
Engineer. All test data shall be recorded and submitted to the Engineer for
review and instruction. The Engineers description regarding tolerance shall
be final.
General guidance for the tests is given below.
a) Smoke test
All soil pipes, waste pipes and vent pipes and all other pipes when
above ground shall be approved gas tight any a smoke test conducted
under a pressure of 25 mm of water and maintained for 15 minutes
after all trap seals have been filled with water. The smoke is produced
by burning oily waste or tar paper or similar material in the
combustion chamber of a smoke machine. Chemical smokes are not
satisfactory.
b) Water test
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

51 | P a g e 5 0

0

For pipes other than Cast Iron Glazed ware and concrete pipes shall be
subjected to a test pressure of at least 1.5 m head of water at the
highest point of the section under tests. The tolerance figure of two
litres per centimetre of diameter per kilometre may be allowed during
a period of 10(ten) minutes. The test shall be carried out by suitably
plugging the low end of the drain and the ends of connections, if any,
and filling the system with water. A knuckle bond shall be temporarily
jointed in at the top end and a sufficient length of the vertical pipe
jointed to it so as to provide required test head or the top end may be
plugged with a connection to a hose ending in a funnel which could be
raised or lowered till the required head is obtained and fixed suitably
for observation.
Subsidence of test water may due to one or more of the following cases:
a) Absorption by pipes and joints
b) Sweating of pipes of joints
c) Leakage at joints or from defective pipes
d) Trapped air.
Allowance shall be made for (a0 by adding water until absorption has
ceased and after which the test proper should commence. Any leakage and
the defective part of the work shall be cut out and made good.
For cast iron pipes
Cast iron sewers and drains shall be tested as for glazed water and concrete
pipes. The drain plug shall be suitably strutted to prevent their being forced
out of the pipe during the test.
c) For straightness

i)

By inserting at the high end of the sewer or drain a smooth ball of a
diameter 13 mm less than the pipe bore. In the absence of obstruction.
Such as yarn or mortar projecting through the joints, the ball with roll
down the invert of the pipe end emerge at the lower end and
ii) By means of a mirror at one end of the line and lamp at the other. If
the pipeline is straight, the full circle of light may be observed. The
mirror will also indicate obstruction in the barrel if the pipeline is not
straight.

17.5.1.0

Trenches
Unless particular items are included in the schedule, no separate
measurement shall be made for lead, lifted dewatering, dressing, storing,
back filling consolidation etc. that may be required in this connection.
17.5.2.0 Concrete, masonry
Unless lumped with other items in the schedule the measurement shall be
on gross area or volume basis as mentioned under relevant items.
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

52 | P a g e 5 0

0

17.5.3.0 No separate measurement shall be made for special supports and fixtures,
cutting chases, holes and rectification unless specially indicated in the
schedule of items. If the specials and separately indicated in the schedule,
the measurement for these shall be over and above the measurement, of the
pipe work as mentioned below:
The pipes of different nominal bores shall be measured separately. The
pipe work shall be measured in length inclusive of sockets specials, fittings
etc. in position.

17.5.4.0 Fittings and fixtures
Measurement for fittings and fixtures where applicable shall be in number
for the complete item inclusive of anchors, brackets and fasteners required.
However, in special cases anchors, brackets and similar items may be
measured separately if included as such in the schedule of items.
17.5.5.0 Chases and holes
No measurement shall be made for cutting chases, holes etc., and making
good for any work within the scope of this specification and shall be
inclusive.
17.5.6.0 Painting
All items likely to rust shall be painted with one coat of primer, which shall
not be measured separately. Where finishing coat of paints are supplied
that shall be measured as indicated in the schedule of items. Usually,
painting of pipes shall be measured in length for each different nominal
diameters without giving any extra allowance for specials sockets, etc.
17.5.7.0 Septic tank, Soak pit
Usually it shall be measured in number for the complete septic tank or soak
pit as per drawing. All earthwork, backfilling masonry, concrete, manhole,
pipes and fittings included. In case, it is intended to pay for individual
items the same shall be indicated in the schedule and measured in number,
length area or volume as appropriate.

18.0 NON-SHRINK GROUT

Non-Shrink type grout using cementitious base material shall be from approved
manufacturer and shall be free flow type. The minimum compressive strength of the
grout shall not be less than 650 Kg/cm2. The grout material shall be expansive to
ensure the full contact between the base plate and grout. It should not shrink during
setting process. Necessary formwork shall be used around the portion to be grouted.
The water cement ratio shall be as per manufacturers specification and in no case
shall be more than 0.18. To achieve the workability for the minimum horizontal flow
of 1000mm, when the grout is poured from one end, necessary plasticizers may be
13/08/2014

Engineering Services
Panipat Naphtha
Cracker
TECHNICAL SPECIFICATIONS
FOR CIVIL WORKS
RPNC101660

DATE
August 13, 2014




Engineering Services
Panipat Naphtha
Cracker


TECHNICAL SPECIFICATION OF
GENERAL CIVIL WORKS
TECHNICAL
SPECIFICATION

REV

53 | P a g e 5 0

0

added as recommended by the manufacturer only and shall not be added by the
contractor at site in the ready mix grout.

Das könnte Ihnen auch gefallen