Sie sind auf Seite 1von 9

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management 23 (2005) 591–599
www.elsevier.com/locate/ijproman

Intervening conditions on the management of project risk:


Dealing with uncertainty in information technology projects
E. Kutsch a, M. Hall b,*

a
University of Surrey, School of Management, Guildford, Surrey GU2 7XH, United Kingdom
b
University of Bristol, Department of Management, Lewis Wing, Wills Memorial Building, Queens Road, Bristol BS8 1RJ, United Kingdom

Received 18 June 2004; received in revised form 27 July 2004; accepted 10 June 2005

Abstract

A review of the outcome of many information technology (IT) projects reveals that they fail to meet the pre-specified project
objectives of scope, time and budget. Despite well-established project risk management processes, project managers perceive their
application as ineffective to manage risk. This failure may well be attributed to the inadequate application of those risk management
processes. The purpose of this research was to investigate how project managers responsible for the management of risk in IT pro-
jects actually managed risk and to relate this back to established project risk management processes. In undertaking this investiga-
tion, we were seeking to understand the ways in which the project managersÕ approaches and behaviours, when considering risk in
IT projects, differed from what might be expected. Results show that because of environment-related and decision maker-related
conditions, project managers tend to deny, avoid, ignore and delay dealing with risk, with the consequence of those actions having
an adverse influence on their perceived effectiveness of risk management and the project outcomes. If project risk management, and
its underlying processes are not to be discredited, the behaviour of project managers when confronted by uncertainty should be con-
sidered and actions need to be taken to discourage project managersÕ irrational actions.
Ó 2005 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Risk management; Expected utility theory; Irrationality; Stakeholder behaviour

1. Introduction practitioners surveyed [2], IT project failure was most


commonly attributed to lack of top management
Projects may be considered to have failed when involvement, a weak business case and inadequate risk
expected scope, cost and time targets are not met, management. The highest ranked factor for project
expected benefits are not realised, or a stakeholder is failure was risk management. The Project Management
dissatisfied with an aspect of the process or outcome. Institute [4] defined risk management in a project envi-
In particular, IT projects (the provision of a service ronment as the systematic process of identifying, anal-
to implement systems and solutions, including a variety ysing, and responding to uncertainty as project-related
of hardware and software products [1]) have a high events or conditions which are not definitely known
rate of failure [2,3]. In one study, it was found that a with the potential of adverse consequences on a project
third of all software projects were terminated before objective. Despite well established and accepted project
completion while more than 50% of the projects cost risk management processes being available, including
approximately double the estimate [2]. According to PMI 2000, Prince 2 or PRAM, project managers com-
monly perceive these as not effective for managing pro-
*
Corresponding author. Tel.: +44 117 954 5699. ject uncertainties [2,5]. In the area of decision making
E-mail address: Mark.Hall@bris.ac.uk (M. Hall). under uncertainty, expected utility theory (EUT) has

0263-7863/$30.00 Ó 2005 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2005.06.009
592 E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599

been the dominant normative and descriptive model. Expected Utility Theory
However, research has shown that conditions in project
risk management deviate from the claims according to Choice Probability Utility
this theorem. Kahneman and Tversky [6], for example,
established in their research that the procedure of Risk
O
materialises
‘‘framing’’ violates the EUT model. Elsewhere (e.g.

-P
[8,9]) it was revealed that psychological factors play Risk

1
an important part in decision making under uncer- mitigation
tainty but are not adequately captured by EUT. action
PxA P
Although much work has been done to date examin- Risk does not
ing the response of individuals to risk in various settings, A
materialise
such as in the oil industry or in education, little research
has been carried out to ascertain the impact of interven-
ing conditions on the management of risk by project
managers, their impact on the project outcome and the
perceived effectiveness of risk management systems Risk
G
and processes in the context of project management. materialises

-Q
The purpose of this research was to investigate how No risk

1
intervening conditions deviated from those one might mitigation
presume under expected utility theory, how they influ- action
G + (Q x A) Q
enced actions taken by project managers and how pro-
Risk does not
ject managersÕ perceptions of the effectiveness of A+ G
materialise
project risk management ultimately contribute to pro-
ject success and/or failure in the delivery of IT projects.
The goal was to better understand how, under condi-
tions of uncertainty, the application of risk management Fig. 1. Expected utility theory.
techniques by project managers might be improved.

The probability of avoiding risks in a project through


2. Background the execution of risk response actions is P and without
risk actions Q, with P larger than Q and 1 Q larger
The dominant paradigm underlying project risk pro- than 1 P. The utility if avoiding risks (relative to the
cesses such as defined by the Project Management Insti- cost of materialised risk) is A and the utility of no ac-
tute [4] and CCTA [9] is the expected utility theorem tions (relative to the cost of those actions) is G while
[10,5]. Expected utility is ‘‘a weighted average of the util- A is assumed to be greater than G. The utility of scenario
ities of all the possible outcomes that could flow from a 1 is the worst and, therefore, set at 0.
particular decision, where higher-probability outcomes The utility of scenarios 1 and 3 depends on the cost of
count more than lower-probability outcomes in calculat- uncertainty materialising and adversely affecting the
ing the average’’ [11, p. 21]; the utility of decision- project outcome. In contrast, the utility of scenarios 1
making choices are weighted by their probabilities and and 2 depends on the cost to execute actions, the com-
outcomes [7,12,11]. mitment of ‘‘scarce’’ project resources such as time
In order to understand this, one might consider the and money. Therefore, the decision by the project man-
following simplified example, as displayed in Fig. 1. A ager to take actions or not depends on the utility of
project manager facing risk in a project has the choice avoiding uncertainty (benefit) while committing re-
to apply project risk management to mitigate project sources (cost) and the relative magnitude of the objec-
risk or may choose not to manage it. tive or subjective probabilities.
According to Fig. 1, four scenarios may unfold: Expected utility has been generally accepted in risk
literature as a model of rational choice for taking risky
1. project manager proactively executes risk mitigation decisions [13] and is considered to be a very robust
actions and risks materialise; framework for decision making under conditions of
2. project manager proactively executes risk mitigation uncertainty [14]. Rationality can be defined as ‘‘agree-
actions and risks do not materialise; able to reason; not absurd, preposterous, extravagant,
3. project manager does not proactively executes risk foolish, fanciful, or the like; intelligent, sensible’’ [15].
mitigation actions and risks materialise; According to EUT, rational actions of risk actors (indi-
4. project manager does not proactively executes risk viduals who influence and/or own the risk process) can
mitigation actions and risks do not materialise. be defined as follows [13, p. 43]:
E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599 593

 rational actors can choose between different possible  cognitive and emotional overload that results from
actions. Actions may differ in kind and scale; awareness of risk in many (of not most) behaviours;
 rational actors assign (objective or subjective) proba-  the complex and varied dynamics associated with per-
bilities to various outcomes; forming any given behaviour.
 rational actors can order possible actions according to
their preferences;
 rational actors try to choose an action, which is opti-
mal according to their preferences. 3. Methodology

An important aspect of EUT is the assumption of a While EUT describes a ÔrationalÕ approach to the
state of perfect knowledge for risk actors [13]. Complete understanding and management of risk, either as threat
certainty implies [16, p.129]: or opportunity [23] the concern of this paper was the
Ôlived realityÕ of project managers involved in IT pro-
 a clear and unambiguous identification of the prob- jects and how this impacted upon the orderly pursuit
lem, its constituent elements and its causes; of a management of risk predicated on EUT. In this
 perfect information about all the relevant variables in sense, it encompassed a decision making process that
terms of both quantity and quality; dealt with uncertainty, encompassing as it does, risk
 a well-developed model of the problem which incorpo- management, but also including the broader processes
rates all the variables likely to influence the decision of decision making in risky and uncertain project envi-
outcome and a perfect understanding of the manner ronments [23]. Essentially, the concern was with beha-
and scale of interaction; viour and activities that interrupted (or intervened
 an exhaustive list of all possible solutions; with) the process of risk management predicted by
 an unambiguous statement of the objectives which is EUT. Beyond this, the concern was to develop an
specific, quantifiable and internally consistent; understanding of how and why these behaviours
 perfect knowledge of the future consequences of each occurred, what their effect tended to be, and what
possible solution and their implications for the project; implications these effects might hold.
 the availability of all the resources and sufficiency of Research has previously been conducted into behav-
reliability in all the structures and systems necessary iour when managing risk in disciplines such as in psy-
for the successful implementation of the chosen chology and general management [6,21,24]. However,
solution; this paper focuses upon intervening conditions and their
 the presence of perfectly rational and experienced effect on risk management in the context of IT projects.
decision-makers with unlimited analytical and cogni- As the objective was to develop an understanding of
tive abilities. how these conditions arose, an exploratory research ap-
proach using semi-structured interviews was adopted.
For the purposes of clarity, we have assumed that the This involved an iterative process of proposing and
project manager is the main risk actor. However, project checking for patterns, both during the interviews and
management literature suggests that various stakehold- in subsequent analysis, in order to develop insights into
ers, which may include individuals and organisations, behaviours and approaches adopted by IT project man-
may be directly or indirectly involved in the process of agers in practice.
managing risk. While recognising the involvement of During analysis, the approach was one of seeking and
these stakeholders, the focus for our research was on evaluating similarities and differences between the cases
the project manager as the main risk actor, although or groups of cases, each interview representing a specific
the contributions of other risk actors were relevant to case. This entailed selecting categories, categorising each
some aspects of the research, as will become apparent. case and looking for similarities and differences both
In the context of project risk management, the prefer- within groups and between groups. In this study, catego-
ences of project managers should only relate to the ac- ries included
tive mitigation of that risk with adverse consequences
on project objectives of time, cost and quality [4,9,17].  the overestimation of risk compared with its
However, although this describes how managers should underestimation;
make decisions when undertaking risk management, evi-  high-perceived risk as opposed to low-perceived risk;
dence shows that their actions often deviate from EUT  success of a project compared with failure of a project.
(e.g. [18,14,19,20]. Deviation from EUT may derive
from, for example [21, p. 251]: The approach taken was to examine the findings
and create categories. The literature was then revisited
 the uncertainty associated with taking any given action to establish whether the issue had previously been
and whether or not negative outcomes will result; addressed elsewhere.
594 E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599

Table 1
Characteristics of the interviewees and their projects
Interviewee ref. Organisation Position Approx. project volume (£m) Duration (months)
Interviewee 1 Company A IT project manager 15 36
Interviewee 2 Company B IT consultant n.a. 18
Interviewee 3 Company C IT project manager n.a. 1
Interviewee 9 Company C IT project manager 10 2
Interviewee 4 Company D IT project manager 0.08 0.25
Interviewee 5 Company E IT project manager 18 12
Interviewee 6 Company F IT project manager 1 12
Interviewee 7 Company G IT project manager 30–40 18
Interviewee 10 Company H IT project manager 3 14
Interviewee 11 Company I IT project manager n.a. 18
Interviewee 12 Company J IT project manager 10 18
Interviewee 13 Company J IT project manager 150 48
Interviewee 14 Company J IT project manager 1–2 1
Interviewee 15 Company J IT project manager 40 6
Interviewee 16 Company J IT project manager 100 6
Interviewee 17 Company J IT project manager 1000 120
Interviewee 18 Company J IT project manager 30 n.a.
Interviewee 19 Company K IT project manager 8 36
n.a., this information was unavailable or undisclosed.

In total, 19 IT project managers and consultants were vening conditions are the broad and general conditions
interviewed from eleven separate companies (Table 1). bearing upon action. . . [they]. . .. either facilitate or con-
The interviews were semi-structured in nature, including strain action’’. These are summarised in Table 2 and
questions such as: subsequently discussed in detail, drawing on indicative
quotations from the interviews in order to illustrate par-
 Why were risks overlooked? ticular points.
 Why did risks that were expected to materialise not, in
fact, materialise? 4.1. Denial of uncertainty
 Were any project risk management stages ineffective?
If so, why? The first condition that emerged related to risk as an
ÔobjectÕ of ÔaweÕ; an ÔobjectÕ to be ÔfearedÕ by those in-
In selecting the sample, the aim was to acquire data volved in projects. It seemed that project managers were
from a range of IT projects, large and small, complex unwilling to expose their customers to risks because
and less-complex. This was reflected in the sample. An- those risks might have created anxiety and doubts
other feature of the sampling approach was to achieve among the stakeholders about the competency of the
data saturation [25]. In this sense, we identified catego- service provider:
ries and themes arising from the interview, until no
‘‘We presented ourselves in such a way that we would
new categories emerged. The project managers either
seem as reasonable and competent as possible. And
discussed projects they were currently involved with,
problems and risks donÕt go down so well. We wanted
or ones on which they had recently been working. The
to come across as people who could get the project
projects were of a wide variety of values and timescales.
under way and complete it. The first aim was to win
The interviews were each of between one and two hours
the tender, no matter what the cost. . . I didnÕt want to
duration. The interviews were then transcribed and
be the doomsayer in the euphoric preliminary phase. . .
analysed.
Problems were kept to a minimum, simply in order to
come across as a competent provider.’’ (Interviewee 5)
4. Findings The refusal to admit that risks existed, or their con-
cealment, in order to avoid exposing stakeholders to
In the analysis of the interviews, a fourfold typology an object perceived as a ‘‘dread’’ and, consequently,
emerged, describing behaviours and activities that pro- threat to the viability of the project, was categorised as
ject managers were either aware of, or were implied by denial of uncertainty. This can be defined as a refusal
their comments, which intervened, or interrupted the ra- by project managers to expose other project stakehold-
tional and orderly management of risk during IT pro- ers to negative discomforting risk related information.
jects. We called these Ôintervening conditionsÕ, drawing The underlying condition of denial was the refusal of
on Strauss and CorbinÕs [26, p.103] definition: ‘‘Inter- project managers to believe in uncertainties with
E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599 595

Table 2
Overview of behaviours intervening in project risk management process
Intervening condition Definition Description
Denial of uncertainty The refusal by risk actors to reveal to other Risk as a ‘‘taboo’’
stakeholders risk related information that may  Denial of uncertainty in order not to expose stakeholders to
hold negative or discomforting connotations something perceived as negative
 Denial of uncertainty in order not to jeopardise long-term
relationships with stakeholders
 Denial of uncertainty in order not to be perceived as a
‘‘doomsayer’’
 Denial of uncertainty in order to present the project as being
‘‘certain’’ and ‘‘certainly’’ successful for stakeholders
Avoidance of uncertainty Lack of attention to risk related information due Distrust in risk estimates
to insufficient trust or belief in the efficacy of that  Avoidance of uncertainty because of mistrust between risk actors
information  Avoidance of uncertainty because of conflicting confidence levels
about risk estimates between stakeholders
 Avoidance of uncertainty because of conflicting perceptions of
stakeholders about the legitimacy or ability of others to manage
certain risks
Delay of uncertainty Failure to consider or resolve risk due to apathy, Different risk management preference
lack of interest or general approach to project  Delay of uncertainty because of different expectations of
management stakeholders about how to manage risk (active or reactive)
Ignorance of uncertainty The complete lack of awareness of risk related Unawareness of threats
information by stakeholders  Ignorance of uncertainty because of the unwillingness to spend
(more) resources on the scanning of the environment
 Ignorance of uncertainty because of the inability to scan and
interpret the environment because of factors such as complexity
and dynamics

possible adverse consequences on the project outcome, ‘‘The question is how specific you want to go. Pulling
rooted in the desire not to expose themselves or other out a generic risk is fine and people can see the red flag
stakeholders to something that was perceived as go up but unless an absolute showstopper sat right in
‘‘worrisome’’. my arena of operations then I would not necessarily
This attitude to risk has been described as one of think it was my case to raise it. Informally I would
treating it as ÔtabooÕ. ‘‘Taboo matters are literally what say it to the project risk assessor: Ôyou need to talk
people must not know or even inquire about. Taboos to so and so because I think they have an issueÕ.’’
function as guardians of purity and safety through so- (Interviewee 13)
cially enforced sanctioned rules of (ir)relevance’’ [27,
In summary, it was found that, project managers
p. 8].
responsible for the management of risk acted to reduce
In another instance,
anxiety and consternation among customers and other
‘‘His words to me [were] ÔYouÕre the project manager, a stakeholders by not confronting them with uncertain-
professional project manager, you must have seen this ties and risks; in other words, they concealed or denied
problem happening before nowÕ. I had no choice but to the presence of risk and uncertainty. This behaviour
say ÔYes David, I did see it happening before now, but was either purposeful (they would make a decision
there were very good reasons why I chose not to escalate not to mention specific, project-related risks) or uncon-
to you about that at a different timeÕ.’’ (Interviewee 9) scious (they did not dwell on the presence of risk,
thereby not having to mention it as an issue). Schneid-
In this particular case, the risk was not actively man- ermann [28, p. 22] hypothesised that, because of the
aged because it was seen that in mentioning the very ‘‘fear of the unknown’’ risk actors tend to be unwilling
subject of risk, the customer would become aware of it to manage risks. The finding here seemed to suggest
and this awareness would jeopardise the relationship be- that their unwillingness related to the temptation to
tween the customer and the project management team. give people the answers they wanted to hear; and the
The relationship between the understanding of and per- answer is certainty or a safe and predictable world
ception of risk appeared to lead to cautiousness among [29]. Because risk actors may perceive risk (manage-
project managers in developing more understanding ment) to be a gloomy and negative affair [30], they
about specific risks and their implications for their par- may downgrade their own perception of risk to a de-
ticular projects. Another interviewee elaborated on this sired external accepted level [31] that can be engaged
issue: through risk management.
596 E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599

4.2. Avoidance of uncertainty Elsewhere, differences in perception of the legitimacy


of risk estimates occurred along the supply chain, be-
The second condition effecting behaviour in project tween subcontractors and prime contractors. In some in-
risk management derived from conflicting risk estimates. stances, this led to those risks being left unmanaged.
In one case, where the customer was presented with a One interviewee explained why he thought this was the
risk estimate, he strongly objected to the risks being case:
legitimate. The project manager said:
‘‘[Our] partner has a much wider scope than we have.
‘‘The client did not accept the risks, or rather the risk They are looking at other issues which are much more
analysis, wherever it concerned him. So when we had critical to them in the bigger picture and our issues
a risk that required the client to play an active role, although they are extremely important for us are not
which would have meant investing money or resources, perceived as being important to [them].’’ (Interviewee 10)
he opposed the prevention of that risk. He said it
It was found that lack of trust in estimates of risk was
wasnÕt necessary, the project could run without it.’’
indicative of a more general lack of trust between indi-
(Interviewee 1)
viduals within their own project team, with customers
These conflicting perceptions about the legitimacy of and with subcontractors. One project manager even sug-
risk between the provider and customer can be described gested that the risk management process was used to
as avoidance of uncertainty and can lead to the danger of deliberately deceive other parties:
the risks not being effectively managed. The lack of con-
‘‘A lack of trust means that some of the risk, which
sensus between perceptions of risk among those in-
might have been identified by various parties on the pro-
volved was found elsewhere to relate to the disbelief or
ject, would not necessarily be given much weight, even if
lack of faith in the message (risk) or the source of the
they were raised to project management. If there is a
message (person who manages the risk) [32]; it is a ques-
lack of trust then risks get tainted to peopleÕs belief that
tion of trust. Differing perceptions of risk, influencing
there are hidden agendas behind that.’’ (Interviewee 13)
their treatment, arose elsewhere. In this case, the project
team failed to come to an unambiguous and trustworthy
estimation about risks. Hence, they chose not to manage
4.3. Delay of uncertainty
them.
‘‘This was a problem, though it wasnÕt really possible to In some instances, it was revealed that there was a
assess the risks. We couldnÕt come to any opinion.’’ tendency for the project managers to simply fail to ac-
(Interviewee 5) tively manage certain risks, even where those risks were
not regarded as a threat or ÔtabooÕ and where there was
However, in cases where consensuses about risk esti-
consensus on what constituted a risk and how it should
mates were found, some risks were managed and others
be measured. It manifested itself as an apathy to risk
were avoided.
management, relying instead on trouble-shooting prob-
‘‘We looked for risks that were easily identifiable, but lems if and when they arose. For example, one intervie-
didnÕt actually have serious consequences for the pro- wee noticed how a project culture encouraged this
ject. The project was not really at threat from these approach:
risks.’’ (Interviewee 1)
‘‘In this particular environment, it was one that was
Risks were avoided in this project, because the pro- used to Ôflying by the seat of its pantsÕ and managing
ject manager focused on ‘‘easily’’ assessable risks in or- issues and crises as they arrived rather than actually tak-
der to achieve consensus within the project team. ing the time and stand back and look ahead and say
Another interviewee noted how risks were avoided in ÔWhat can we do to prevent that?Õ. If their focus and cul-
his project: ture is one of fire fighting and crisis management, the
step to take pre-emptive action to prevent a risk or to
‘‘They were internal risks. But they should not have
reduce a risk is never going to be at the top of their per-
been deleted. They should have been managed inter-
sonal priority list.’’ (Interviewee 14)
nally, not just excluded or even ignored. They did not
go even in the internal risk register.’’ (Interviewee 7) Elsewhere, the client did not regard the management
of risk to be particularly important as it felt the project
In this case, the sales department and senior manage-
manager would simply deal with any problems that ar-
ment perceived those risk estimates produced by the
ose due to their brand exposure:
project manager as something unrealistic. Therefore,
the project managerÕs risk estimates were regarded as ‘‘My general feeling, it does come down to the brand.
being Ônon-legitimateÕ; that is to say they were perceived Fundamentally our name is on that piece of hardware
as not worth being mitigated. which is deployed on the end customerÕs desk. They will
E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599 597

see our brand name every day so the brand name is very project managers may adopt reactive risk management
important and something we want to protect so from as their preferred risk management method. Similarly,
that point of view there is that association that we have it may concern an attitude to project management in
internally and is very strong for us. Form the customerÕs general, which treats it in a procedural manner, this
point of view I suspect that there, they may be aware of influencing responses to risk management.
this, they may be using that to a certain degree in that
way that we will be very protective, that we will always 4.4. Ignorance of uncertainty
jump in to save the situation, so there may be a certain
degree of abuse going on there.’’ (Interviewee 9) The fourth issue that emerged from the interviews can
be labelled ignorance of uncertainty. Ignorance of uncer-
Thus, the customer delayed any active risk mitigation
tainty can be seen as a lack of awareness of risk-related
that may have entailed costs and relied on the supplier,
information on the part of project managers and other
who was contractually obliged to react to any occurring
stakeholders, which could include incomplete knowl-
problems.
edge. Ritchie and Marshall [16, p. 117] noted that ‘‘large
The behaviour noted in these cases can be described
uncertainties, and even ignorance, dominate areas of
as delay of uncertainty by stakeholders in projects. Delay
risk to the extent that the very lack of knowledge is
of uncertainty occurs when decision makers choose to
unsuspected’’. From the interviews, this phenomena ap-
wait until uncertainty resolves itself [33]. While this sug-
peared to be widespread, either being implied or overtly
gests a purposeful decision to Ôwait and seeÕ, the inter-
mentioned by several of the interviewees. For example:
views illustrated that, in some cases it was not a
decision to be reactive to risk but, rather something that ‘‘To a very great extent, with exception of the actual
could be characterised as ÔinattentionÕ: business-related risks, we were able to assess all the tech-
nical risks, but were not always able to assess other,
‘‘The manager was a ÔtechieÕ person. He loved technol-
non-technical risks.’’ (Interviewee 4)
ogy. If it had been technology driven, then I thought
we would not have the issues that we had but because ‘‘Because we did not even know about it. We did not
it was a commercial project, for him, the technology even think about it that it would be wrong and in fact
was standard and mundane. He had no interest at all that the only reason we knew that it was there was when
in proactive risk management.’’ (Interviewee 9) they started producing their invoices.’’ (Interviewee 15)
Elsewhere, risk management was treated as a Ôbox- Explanations for ignorance of risk are varied. A num-
tickingÕ exercise, suggesting that risk management was ber of writers (e.g. [34,35]) suggest that this ignorance
held in low regard as an activity. Risk management may have its cause in organisational contexts of com-
was treated as an administrative task rather than a man- plexity and dynamism. Freudenberg [36] related igno-
agement task: rance of uncertainty to the failure of risk managers to
foresee interactions and interdependencies. In the con-
‘‘I do not think there was a huge driver. I think this
text of project management, a project manager may face
might have been a reason why the project risk assessment
difficulties in forecasting how each component of a pro-
team might not have been really that well regarded. They
ject task may influence others (complexity) and the like-
were interested in finding the risk, the solutions were not
lihood that it will remain stable over the time
really something that they were too bothered with. Their
(dynamism). One interview illustrates this point well:
attitude was, find the risk, rate the risk but then feed that
back into senior management and programme board ‘‘. . . if one went wrong there is a geometric effect because
and let them come up with a solution.’’ (Interviewee 13) another piece of software that was dependent on it was
also delayed which then had a knock-on effect. We did
and elsewhere:
not get down to the level of understanding of all the inter-
‘‘It becomes an administrative process and as long peo- actions between all those components.’’ (Interviewee 18).
ple feel there is a risk register somewhere and lip service
As the project progressed and components of the
is being paid to it on a reasonably frequent basis, then
project such as the amount of IT systems in the project
they are managing risk.’’ (Interviewee 17)
changed, the lack of understanding about the comple-
In summary mitigating activities in response to iden- xity and dynamics of the project caused a sudden
tified risks were delayed or deferred because reactive risk disruption.
management was the preferred mode of operation or Other cases illustrated that project managers some-
there was a lack of interest, or an inattention, in exercis- times also set their own constraints and boundaries
ing active risk management. The reasons may be politi- influenced by their Ôcomfort zoneÕ. Margolis [37, p. 35]
cally or culturally driven: project managers may not pay has argued: ‘‘experts in general learn to concentrate on
attention to active risk management and in other cases what is critical in their experience with the domain at
598 E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599

hand and ignore anything else.’’ Thus, it would appear ÔboringÕ was not rational in this sense. That said, from
that ignorance of risk arises for two reasons. Firstly, some perspectives, such actions or inactions might be
project teams are unable to predict risk because of con- considered rational. It might be rational, in some cir-
textual conditions such as complexity and dynamics. cumstance, to keep the client ÔhappyÕ rather than allow
Secondly, they are unwilling to look for risks outside the client to become upset or nervous of risk if that
their defined scope of project management skills. means the project will proceed.

5. Conclusions References

A series of behaviours and conditions were identified [1] Howard J. Computer services: 2001 Market Report, Key Note
during the research that tended to lead to activity and Ltd.; 2001.
[2] Whittaker B. What went wrong? Unsuccessful information
decisions that deviated from, or intervened within, the
technology projects. Inform Manage Comp Secur 1999;7(1):23–9.
risk management process described using expected util- [3] McGrew JF, Bilotta JG. The effectiveness of risk management:
ity theory. In pursuing risk management using the ap- measuring what didnÕt happen. Manage Decis
proach derived from EUT, risk managers and other 2000;38(4):293–300.
project stakeholders could expect the benefits of im- [4] Project Management Institute. PMI 2000: a guide to the project
management body of knowledge. Pennsylvania: Project Manage-
proved certainty in the outcomes of the project with
ment Institute; 2000.
the additional benefits of improved budget setting [5] Pender S. Managing incomplete knowledge: why risk manage-
and reductions in political and financial tension arising ment is not sufficient? Int J Project Manage 2001;19:79–87.
from surprises. However, they failed to avail them- [6] Kahneman D, Tversky A. Prospect theory: an analysis of decision
selves of these benefits because other issues became under risk. Econometrica 1979;47(2):263–91.
[7] Sitkin SB, Weingart LR. Determinants of risky decision-making
paramount – what might be called ‘‘barriers to preven-
behaviour: A test of the mediating role of risk perceptions and
tative action’’ [21, p. 234]. These barriers have been propensity. Acad Manage J 1995;38(6):1573–92.
called intervening conditions [26] and have been found [8] Pablo AL. Reconciling predictions of decision making under risk.
to manifest themselves as conditions of denial, avoid- J Manage Psychol 1997;12(1):4–20.
ance, delay and ignorance of uncertainty. In some in- [9] CCTA. An introduction to managing project risk. Norwich:
CCTA – The Government Centre for Information Systems; 1995.
stances, they were purposeful: the result of
[10] Ekenberg L, Boman M, Linnerooth-Bayer J. General risk
commercial positioning or a lack of interest in certain constraints. J Risk Res 2001;4(1):31–47.
risky aspects of projects. In other instances, they were [11] Borge D. The book of risk. New York: Wiley; 2001.
unconscious behaviours rooted in approaches driven by [12] Arrow KJ. Behaviour under uncertainty and its implications for
culture: a fear of revealing bad news or a tendency to policy. Foundations of utility and risk theory with applications.
In: Stigum BP, Wenstop F, editors. Dordrecht: D Reidel Pub-
tick boxes and follow procedures. Freudenberg [36, p.
lishing Company; 1983. p. 19–32.
249] argued: [13] Jaeger CC, Renn O, Rosa EA, Wehler T. Risk, certainty, and
rational action. London: Earthscan; 2001.
‘‘Instead, the problem is that a variety of factors that are
[14] Einhorn HJ, Hogarth RM. Decision making under ambiguity. J
far more subtle – unseen, unfelt, and yet unfortunate in Bus 1986;59(4):225–50.
their consequences – exert an influence that could scar- [15] Simon H. Rationality as process and as product of thought. Am
cely be more disturbing even if they were based on delib- Econ Assoc 1978;68(2):1–16.
erate malice.’’ [16] Ritchie B, Marshall D. Business risk management. Lon-
don: Chapman & Hall; 1993.
As can be seen from the indicative quotations from [17] BSI. Project management – Part 3: guide to the management of
the interviews, in many cases the project managers were business related project risk. London: British Standards Institu-
tion; 2000.
aware of the conditions (although they lacked a typol-
[18] Cooke S, Slack N. Making management decisions. Hemel
ogy with which to describe them). They were also aware Hempstead: Prentice-Hall International; 1984.
of the negative consequences for the projects they were [19] Bourgeois LJ, Eisenhardt KM. Strategic decision processes in
trying to deliver. In some instances, the intervening con- high velocity environments: four cases in the microcomputer
ditions were beyond the control of the project managers industry. Manage Sci 1988;34(7):816–34.
[20] Neumann PJ, Politser PE. Risk and optimality. In: Yates FJ,
interviewed; they were initiated by a supplier or the cus-
editor. Risk-taking behaviour. West Sussex: Wiley; 1992. p.
tomer. In other instances, the interviewees were aware 27–47.
that the condition was the consequence of their own [21] Adler NE, Kegeles SM, Genevro JL. Risk taking and health. In:
behaviour. They understood how risk management Yates FJ, editor. Risk-taking behaviour. West Sussex: Wiley;
should operate, even where they were unaware of EUT 1992. p. 231–55.
[23] Ward S, Chapman C. Transforming project risk management into
as a theory of action. They were aware that ÔrationalÕ
project uncertainty management. Int J Project Manage
decision making, in the sense that rationality is under- 2003;21:97–105.
stood in EUT, was required and that concealing infor- [24] Holt R. Risk management: The talking cure. Organization
mation or ignoring risks that were ÔuncomfortableÕ or 2004;11(2):251–70.
E. Kutsch, M. Hall / International Journal of Project Management 23 (2005) 591–599 599

[25] Bryman A, Bell E. Business research methods. Oxford: Oxford [32] Poortinga W, Pidgeon NF. Exploring the dimensionality of trust
University Press; 2003. in risk regulation. Risk Anal 2003;23(5):961–72.
[26] Strauss A, Corbin J. Basics of qualitative research. Lon- [33] Bobbitt HR, Ford JD. Decision-maker choice as a determinant of
don: Sage; 1990. organizational structure. Acad Manage Rev 1980;5(1):13–23.
[27] Smithson M. Ignorance and uncertainty. New York: Springer; [34] Palmer TB, Wiseman RM. Decoupling risk taking from income
1989. stream uncertainty: A holistic model of risk. Strat Manage J
[28] Schneiderman MA. The uncertain risks we run: hazardous 1999;20:1037–62.
materials. In: Schwing RC, Albers WA, editors. Societal risk [35] Jaafari A. Management of risks, uncertainties and opportunities
assessment. New York: Plenum Press; 1980. p. 19–37. on projects: time for a fundamental shift. Int J Project Manage
[29] Fischhoff B, Lichtenstein S, Slovic P, Derby SL, Keeney RL. 2001;19:89–101.
Acceptable risk. Cambridge: Cambridge University Press; [36] Freudenberg WR. Heuristics, biases, and the not-so-general
1981. public: Expertise and error in the assessment of risk. In: Krimsky
[30] Raftery J. Risk analysis in project management. London: Chap- S, Golding D, editors. Social theories of risk. Westport: Praeger
man & Hall; 1994. Publishers; 1992. p. 229–49.
[31] Machlis GE, Rosa EA. Desired risk: broadening the social [37] Margolis H. Dealing with risk. London: The University of
amplification of risk framework. Risk Anal 1990;10(1):161–8. Chicago Press; 2003.

Das könnte Ihnen auch gefallen