Beruflich Dokumente
Kultur Dokumente
At the September 15 Public Works Committee meeting, a BART spokesperson declared that Oakland has no
stake in the OAC. Subsequent comments from BART and other regional agency staff reflected on the
environmental/traffic benefits of the project—but the benefits they cited are based on dubious ridership
assumptions and ignore the negative environmental effects of concrete construction.
Since the project’s costs began exploding, causing private partners to step away from a Public/Private
Partnership that would have cost $100 million less than the current proposal, no analysis has been done to see
if alternatives could provide the identified goals of supporting Oakland Airport growth, increasing BART
ridership, supporting local economic development and upgrading the successful AirBART system.
“City Staff prefers the [OAC] along the Hegenberger Road median with two intermediate stations. …
this option would stimulate transit-oriented development and job creation within their immediate
vicinity.”
At the same time, the Council adopted a resolution that reflected their support because:
“An elevated system running on a guideway above traffic will reliably make the trip in less than half the
time it takes the AirBART shuttle. … intermediate stations will provide direct access to [OIA] and to
the regional BART system, thereby encouraging high quality transit oriented development near those
stops … [and] the [OAC] will increase ridership on the region’s existing transit systems.”
The money currently attached to the OAC project could fund a successful, self-supporting BRT solution while
freeing up hundreds of millions of transportation dollars for priority projects in Oakland and elsewhere in the
East Bay and the Bay Area.
That the intermediate station was excluded from the original RFP, despite being required in the 2006 City of
Oakland agreement with BART, indicates the level of seriousness with which BART has treated the
intermediate station. That its cost will not be included in the evaluation process for bids proves that
intermediate stops are not only an afterthought, but not even on the table. Whether it’s $15 million or $100
million, BART will not use the feasibility of an intermediate stop as a selection criterion. This is not a
problem for BART, as documentation from BART to the City Council has been clear that the City of
Oakland will be responsible for paying the cost of the intermediate stop.
The OAC fare gates are not set up to accommodate intermediate stop riders
The RFP clearly states that only the Coliseum station will have fare gates for BART/OAC.
In 2002, both the intermediate stop and the Airport station would have had fare gates, allowing OAC riders
to board at Coliseum BART without the use of a fare card, then exit at either stop and pay the appropriate
fare. ($6 for Airport, significantly less for non-airport users). The current design puts fare gates at Coliseum
BART, before riders board the OAC2 headed to the airport, and no fare gates at the intermediate station at
Doolittle.3 This suggests that BART intends for riders travelling between the Airport and Doolittle to pay no
fare ($0) and riders between Doolittle and Coliseum BART to pay the same $6 fare that airport riders will
be paying.
TransForm believes that this is an explicit indication that BART has no intention of an intermediate stop
being built at Doolittle—or, if BART is proposing a system where the users of Doolittle pay the same as
airport passengers, that the Doolittle stop is destined for failure. The rationale for a “service fee” for airport
riders is that they are discretionary riders who can afford airline tickets and therefore the small incremental
cost of an additional fee, which, in relation to airfare, will not be a deterrent to use.
The out-and-out revolt against BART’s SFO service fee increase, in which airport workers stopped riding the
SFO extension because of the $4 surcharge, shows that it is highly unlikely that employees on Hegenberger
would use an OAC with a $6 surcharge. This practice would be overtly unfair to the Oakland riders
(residents or employees) who use this stop. The inability of BART to differentiate the fares for the
intermediate stop is a major and fatal flaw to this project.
1
OAC RFP Addendum #9, item 4
2
OAC RFP Addendum #9, attachment 13A
3
OAC RFP Addendum #9, item 11
BART told their supporters to inflate these numbers when speaking to the Council
On September 8, Kerry Hamill , BART Department Manager of Government and Community Relations,
sent out an email to supporters of the OAC with talking points about jobs. In it, she states, “BART’s
very conservative projections show that the OAC Project will create 2542 total direct jobs. These jobs
will start immediately in January 2010 and peak at 1800 jobs by mid-2011.” 2 This represents 4 times as
many jobs as BART reported to the FTA.
Even more worrying, Hamill’s email goes on to lay out three additional job calculation numbers for the
OAC. She encourages meeting participants to “use whatever number you prefer,” even though three of
the numbers are larger than the supposed “BART projection” she cites in the same email, and all are
larger than the number presented to the FTA the same month—in a grant application for which jobs
creation is important.3
At the September 15 Oakland City Council Public Works Committee meeting, BART’s spokesperson
stated that BART is focusing on 2,500 as their preferred number because it is “conservative.”4
The Port of Oakland’s MAPLA agreement has “requirements.”6 BART’s OAC Project Stabilization
Agreement (PSA), written this summer, has “goals,”7 with no identified remedies if the goals are not
attained.
1
OAC Tiger Grant Application, page 16
2
Kerry Hamill, email to OAC Supporters, 9/8/09
3
Kerry Hamill, email to OAC Supporters, 9/8/09
4
City of Oakland Public Works Committee meeting webcast for 9/15/09, at 3:29 into the broadcast
5
City of Oakland Public Works Committee meeting webcast for 9/15/09, 3:45 into the broadcast
6
Port of Oakland Maritime and Aviation Project Labor Agreement (MAPLA)
7
OAC TiFIA Loan Application, page 23
BART is using passenger mode-share assumptions that their consultant said are unlikely
BART’s 2009 ridership report predicts that the OAC will carry 336 to 346 passengers per day per MAP
(PAX/MAP). However, the SFO Airport Extension currently carries only 297 PAX/MAP—despite the fact that
the SFO Airport Extension is more direct, faster and cheaper than the OAC.
In 2007, BART hired Fehr & Peers to conduct a review of their ridership studies. The report states3:
We feel that the daily passengers per annual airport MAP from the [2009 BART] forecasts are slightly higher
than one would expect. The future [OAC] system would be more convenient than AirBART, but it would
have a $5.00 fare. Therefore, we don’t believe it could attract 15-20% more riders per airport passenger (342
in 2011, 356 in 2030) than the SFO connector does today (297).
The projections for the OAC ridership need to be adjusted to more accurately reflect what an independent
consultant report confirms is the likely ridership on the OAC.
BART’s 2009 ridership report purports to calculate AirBART ridership projections, but only does so for “low
estimate” MAP assumptions. Furthermore, the report assumes that future AirBART mode share will be lower
than it has been over the past five years. The 2007 Fehr & Peers report recommends assuming a mode share of
around 10% for AirBART in the future. To remain consistent with our previous conservative recommendations,
TransForm recommends using Fehr and Peer’s recommendation of 275 PAX/MAP (for AirBART), which is
almost exactly 10%, for a BRT solution.
Using correct assumptions, OAC Ridership is only 350 more riders a day than BRT in 2025
Ridership in 2025 for three alternatives would be:
OAC = 5,019
BRT = 4,648
AirBART = 4,073
1
BART, letter to City Council Public Works Committee, 9/14/09
2
OAC TIGER Grant Application, Sept. 15, 2009
3
Fehr & Peers, “BART Oakland Airport Connector Ridership Projections Review,” 5/15/07
436 14TH STREET, SUITE 600, OAKLAND, CA 94612 | T: 510.740.3150 | WWW.TRANSFORMCA.ORG
OAC Alternatives Analysis
BART has not analyzed BRT since 1993
On May 14, BART staff told their Board that they had analyzed a BRT option for the OAC. What was
left out of that presentation was that the analysis was from 1993. In the 2002 Final Environmental Impact
Report (FEIR), BART stated that BRT “is considered infeasible and was not analyzed in the [2001]
[EIR].”1
The configuration of Hegenberger has changed significantly since 1993. Analysis undertaken in 1993 is
therefore completely outdated in 2009. However, presentations by BART staff to the BART Board,
MTC, the Port of Oakland and Oakland City Council have relied heavily on their analysis of their
exclusive lane analysis, which was not a part of the EIR process in 2002 [per the EIR itself].
At that meeting, a motion was passed to hold off approving the loan application. Boardmembers made
clear that the loan application should not be voted on until updated ridership numbers had been
released. A number of Boardmembers also requested information on BRT options and changes to the
project since its EIR was first approved in 2002.
Two weeks later, May 7, TransForm released the RapidBART proposal and requested that BART staff
include it in the requested analysis of surface transit alternatives.2 Immediately, the OAC Project
Manager wrote, “RapidBART is not the Quality Bus analyzed in the 2002 OAC FEIR/EIS.”3
The next morning, BART staff sent the RapidBART report to four separate paid, private consultants,
asking them for help “discredit[ing]” and “put[ting] holes” in the report to assuage their “worried
boardmembers.”4
On May 12, the OAC Project Manager emailed the four consultants, saying that General Manager
Dugger had “asked that I give the [May 14 Board] presentation and add one slide attacking the TransForm
proposal directly. . . . I need to punch holes in the credibility of this report.”5
1
OAC FEIR – Vol. II, Response to Comments, pages 2-137 and 2-140
2
Stuart Cohen, email to Dorothy Dugger, 5/7/2009
3
Tom Dunscombe, email to Staff, 5/7/2009
4
Tom Dunscombe, email to consultants, 5/8/2009
5
Tom Dunscombe, email to consultants, 5/12/2009
The current proposal has OAC riders walk to the end of the OAC platform at the airport, descend
via an escalator into the parking lot, and then cross three lanes of traffic—just to arrive at the existing
AirBART stop. They will then need to walk to their respective terminals. This walk time is estimated
to be 4 minutes. BART’s stated walk time claims that it will be faster to walk from the OAC to the
terminal than it is from AirBART, despite involving a long walk, an escalator ride, and crossing three
traffic lanes before getting to the AirBART stop.
Furthermore, the trip time would increase significantly for travelers to the future planned Terminal 3,
as the OAC station would be located between Terminals 1 and 2. BART has stated that the walk to a
third terminal would be 6-8 minutes.
1
BART RFP Addendum #6, 7/28/09, #14 and #15
2
BART TiFIA Loan Application, page 7
The Quality Bus and AirBART travel-time analysis has not been recalculated by BART using up-to-
date traffic information. While the 2002 EIR traffic model included many of the roadway upgrades
that were planned for 98th Ave, Hegenberger and Airport Roadway, additional roadway capacity now
exists beyond what was modeled. Furthermore, traffic on the ground is less severe than the model
projected, and this too should have significant bearing on the projected in-vehicle travel time for
AirBART and Quality Bus. Finally, the EIR projected 2005 traffic conditions based on airport usage of
13.1 million passengers, but the City of Oakland has 2007 Hegenberger traffic counts, when OIA had
15 million passengers, showing that traffic in 2007 was less than BART’s EIR projected.
OAC to OAC to
Terminal 1 Terminal 1 AirBART Quality Bus RapidBART
Self
Propelled Cable
In-vehicle time 6.3 8.8 14 12 11
Avg. Wait 2 2.5 2 2 2.5
Headway 4 5 4 4 5
Walking:
BART to OAC 4 4 2 2 2
OAC to Terminal 4 4 2 2 2
Total Trip Time 16.3 19.3 20 18 17.5
Difference - Low 1.7 1.2
Difference - High -1.3 -1.8
Since the EIR was approved in 2002, BART has held no community meetings
regarding the OAC, even as the cost has exploded and the benefits have decreased
In May, BART sent community advocates a list of OAC outreach meetings that had been conducted
since the 2002 EIR.1 However, all but one of the meetings were updates to the BART Board or funding
agencies or meetings with business groups and were held outside of the East Oakland community.
Since 2002, funding for transportation projects has become more scarce and transit service has suffered
declines because of funding. The OAC is being pitched as a benefit to East Oakland residents,2 even
though the project will no longer serve them—members of this community were not consulted as
community-serving stations were being removed from the project and costs started making the service
(and overall BART service) more expensive.
Community groups have filed a Title VI civil rights complaint against the project
because of the lack of required analysis on the community impacts of this project
The complaint,3 filed by Public Advocates Inc. on behalf of TransForm, Urban Habitat and Genesis,
asserts that BART failed to evaluate whether the planned OAC will have a discriminatory impact on
minority and low-income populations. If discriminatory impacts are found, BART is required to explore
less discriminatory alternatives that meet the needs of the project at a lower cost to taxpayers. One
alternative could be the RapidBART bus system proposed by TransForm, which BART has refused to
study seriously.
1
Kerry Hamill, email to community advocates, 5/13/09
2
Comments from Larry Reid and Carol Ward Allen at May 14 BART meeting and others
3
FTA Title VI complaint, filed 9/3/09
It is important to note that the $89 million in Measure B funds could be easily reprogrammed to an OAC
BRT project. The Measure B expenditure plan specifically talks about funding “2 additional corridors” of
Quality Bus service. And unused funds could go to International BRT and local bus services as defined in
the 2000 expenditure plan.
1
Echa Schneider, “How is the Oakland Airport Connector funded?,” A Better Oakland Blog, 2009