Beruflich Dokumente
Kultur Dokumente
K
/
a
0
2
4
6
8
10
12
S
A
S
m
a
k
e
t
/
d
Increased aeration costs K/a Increased OPEX (exc sludge) K/d SAS make t/d
3.4.4 Contingency Planning
If the Primary Settlement Tank (PST) sludge blanket levels get too high and are in danger of weiring
over or going septic, the sludge blanket levels can be brought down quickly by over pumping into a
disused tank if available or removal by tanker off site. For Activated Sludge Plants additional aeration
can also be utilised in anticipation of this additional load.
For sites with percolating filters is it essential that sludge is not allowed to be discharged on to the
filters. If there is a danger that raw sludge will spill over from the Primary Settlement Tank (PST) on to
the percolating filters arrange for the sludge to be removed and taken by tanker off site before the
sludge spills onto the filters.
Where sludge has built up to excessive levels recirculation flows can be increased to thin the Settled
Sewage down until the sludge can be removed from the Primary Settlement Tank (PST).
DO NOT ALLOW SLUDGE TO GO ONTO PERCOLATING FILTERS
THAMES WATER Asset Management
Internal Company and Partners Asset Standards
Technical Lead: Bryan Bleeker Issue 1.1
AM-PRO-WWT-WWT 3.1 Primary Treatment-SEC3 Page 20 of 21
UNCONTROLLED WHEN PRINTED
3.4.5 Plant Release / Taking out of and Bringing into service
Taking out of service - Planned
When Primary Settlement Tank(s) are being taken out of service the Plant Release procedure needs
to be followed together with site process risk assessment and plant availability. If a Primary
Settlement Tank cannot be taken out of service due to process risk then this needs to be highlighted
in the Risk Register for potential investment / capital delivery purposes.
The frequency for removing Primary Settlement Tanks from service must be set at a level that
ensures the performance of the tank is maintained and inspection of the scraper can be made prior to
any damage occurring. As a guide, this should be initially set at four years.
Draining of Primary Settlement Tanks for inspection is normally carried out in summer months or
during periods of low inlet flow to the works when plenty of time needs to be allowed for draining.
Primary Settlement Tanks can also be taken out of service in the summer months to improve settled
sewage quality due to septicity and reduced flows. This should be linked to any Odour Management
Plans.
The rapid return of sewage when draining Primary Settlement Tanks may overload the other Primary
Settlement Tanks in service and flush out sludge. The alternative is to pump off the top water to a
balancing or other tank for slow return to main flow. In small works where there is only one Primary
Settlement Tank the top water can be taken off by a tanker.
Increase the de-sludging run time and / or frequency on the other Primary Settlement Tanks, as the
higher loading on these tanks will result in an increase in sludge production.
Taking out of service - Unplanned
The Primary Settlement Tank may well have a lot of sludge in it that will need removing. This must be
removed in a controlled way either to the Sludge Holding Tank, directly into the sludge stream or if
unavoidable to the inlet works. The following points must be taken into account when taking a Primary
Settlement Tank out of service to maintain site operation, maintenance and compliance.
Always protect effluent quality.
Review operation of upstream processes, i.e. screens which may be causing problems
Control the Primary Settlement Tank pump down to protect the treatment process.
Be aware of Primary Settlement Tank flotation risk.
Plan flow diversion needs i.e. Tanker, pumping station etc.
Isolation of Primary Settlement Tank inflow.
When Primary Settlement Tank(s) are taken out of service ensure flow split and de-sludging is
redistributed among the other Primary Settlement Tanks.
De-sludge to water prior to emptying the Primary Settlement Tank.
Sludge Holding Tank capacity.
Primary Settlement Tank cleaning.
Health & Safety
Inspections required
Monitor downstream processes
Alarms that could lead to needless Call Outs, i.e. not temporarily disabled during outage.
Odour
THAMES WATER Asset Management
Internal Company and Partners Asset Standards
Technical Lead: Bryan Bleeker Issue 1.1
AM-PRO-WWT-WWT 3.1 Primary Treatment-SEC3 Page 21 of 21
UNCONTROLLED WHEN PRINTED
Bringing into service
Check Primary Settlement Tank (PST) alarms before leaving site. Check that all Primary Settlement
Tanks have equal flow distribution to ensure optimal operation. Tanks should be brought back into
service slowly or there is a risk of solids carry over.
More than one tank on site
Fill Primary Settlement Tank by passing a proportion of the incoming flow through it. It is important
that the other Primary Settlement Tanks still receive flow.
One tank only on site
Fill with Humus Tank effluent / final effluent before restoring flow to the Primary Settlement Tank.
General
It is advisable that an inspection of the Primary Settlement Tank and its de-sludging system is carried
out within a few days of being put back in service.
Lessons Learnt
In the case example of Esher STW, due to a capital project, there was a requirement to carry out
works shutdowns during dry weather; this resulted in having to return strong (undiluted) sewage from
the storm tanks.
When this was being done, there was no account made for the increase in solids loading into the
Primary Settlement Tanks, hence no increase in de-sludging times were made. This resulted in
solids being carried over into the aeration plant. Initially this meant that the back-up aerators had to
run extra hours to maintain Dissolved Oxygen (DO) levels and ammonia treatment.
However, after a short period of time, this resulted in the Mixed Liquor Suspended Solids (MLSS)
increasing from 2,500mg/l (as target) to 8,000mg/l. This resulted in a breach in consent of ammonia
& solids within the final effluent.
There was also the further impact of requiring additional sludge to be removed from site, incurring
additional tanker cost, not to mention the extra power consumed by both the aerators & the sludge
thickening plant.
This scenario could also occur as a result of heavy rainfall after prolonged dry periods whereby the
network may be cleaned / flushed out resulting in additional solids being washed to the Sewage
Treatment Works. It is important to note that these solids maybe old and septic causing loading and
settlement difficulties within the Primary Settlement Tanks (PSTs).
Regular monitoring of sludge dips and pump timer adjustments can identify and combat this changing
situation.
---- End of section 3 ----