Eni S.p.A.

Exploration & Production Division


06225.DOC.PRC.PRG
Rev. 3 J anuary 2005
Sh. 2 of 8


INDEX

1. SCOPE 3
2. APPLICABILITY 3
3. RESPONSIBILITY 3
4. REFERENCE DOCUMENTS 3
5. PROJECT PHASE AND ISSUE SCOPE 4
6. CONTENT 4
6.1 DOCUMENT INDEX 4
6.2 CONTENT DESCRIPTION 4
7. INFORMATION SUPPLY AT DIFFERENT PROJECT DEVELOPMENT PHASES 6
8. FINAL DATA SUPPLY FOR DBIMP CORPORATE DATABASE 7
9. SUPPLY OF DOCUMENT 7
10. SUGGESTED LOOP AND INSTRUMENT LIST FORMAT 8


Eni S.p.A.
Exploration & Production Division
06223.DOC.PRC.PRG
Rev. 3 J anuary 2005
Sh. 3 of 8

1. SCOPE
Scope of this document is to define the contents of the project document called
Loop & Instrument List, which represents the complete list of the process and
utility instrumentation belonging to the plants under development in the project.

2. APPLICABILITY
The requirements of this document will be applied to all the Eni E&P oil & gas and
utilities development projects, with the only exceptions of Eni E&P written
specification applicable to a specific project.


3. RESPONSIBILITY
The responsibility for the Loop & Instrument List preparation and issuing is in
charge of the Project Team/Contractor responsible for the plant development, as
foreseen in the related OPDS/TMS development phases.


4. REFERENCE DOCUMENTS

1) 20198.COO.GEN.SDS ITEM NUMBERING

2) 20189.COO.GEN.SDS TECHNICAL DOCUMENTS IDENTIFICATION
AND CLASSIFICATION

3) 06215.DOC.GEN.SDS FACILITY FUNCTIONAL UNITS

4) 20259.DOC.GEN.SDS P&ID

5) 20203.DOC.GEN.SDS TECHNICAL DATA OF PLANT COMPONENTS
FOR DBIMP CORPORATE DATABASE

6) 05428.DOC.GEN.SDS TECHNICAL DOCUMENTS FORMAT


Eni S.p.A.
Exploration & Production Division
06223.DOC.PRC.PRG
Rev. 3 J anuary 2005
Sh. 4 of 8

5. PROJECT PHASE AND ISSUE SCOPE
The plant Loop & Instrument List is normally produced at each issue of the related
the Process and Instrumentation diagram (PID).
Therefore the same criteria for project phases and issues scopes apply to both
documents.


6. CONTENT
The Loop & Instrument List is produced during the definition of instrumentation and
control of process and utility in the PIDs, aiming at listing all the loop and
instruments belonging to the plant, included those which are not shown in the above
diagrams. All physical entities under control will be listed together with the required
instrumentation functions.


6.1 DOCUMENT INDEX
The Loop & Instrument List document issued in the project phases shall always be
structured according to the here below index, and its content shall be as described
in the next paragraph.

Index
1. Scope
2. Reference documents
3. Reference tables
4. Loop and instrument list


6.2 CONTENT DESCRIPTION
In the following paragraphs the description of the Loop & Instrument List content.

1) Scope
Clear indication of the scope of the document, with wording like:
The scope of this document is to list all the measured physical entities and their
functions belonging to the plant/s as represented
in the reference P&IDs or other documents.

2) Reference documents
Indication of the P&IDs or other documents with the first tagging for loops and
instruments.

3 ) Reference tables .
Tagging of loops and of instruments requires availability of plant reference tables for
facility and subfacility and for functional units.
Tagging is in accordance with ISA best practice. This practice, however, has an
extended range of discretion due also to the fact that it has not been updated since
long, there fore not taking into account new technologies.
Therefore tables for physical entities and for functions have been compiled.

Tagging is normally in accordance with ISA best practice however, due to the lack
of updating of these best practice, the list of measured physical entities and their
functions will be defined according to the reference tables contained in the
reference document 1.
Eni S.p.A.
Exploration & Production Division
06223.DOC.PRC.PRG
Rev. 3 J anuary 2005
Sh. 5 of 8

4) Loop & Instrument List information
Here below the complete list of information required during the project development
phases, whilst the specific data required in each phase are described in the
following paragraph.

REQUIRED INFORMATION DESCRIPTION
1) Loop identification, as defined in the reference
document 1, comprising:
- Sub-facility (ex Subdivision)
- Facility functional unit
- Train number
- Physical entity
- Sequential
- Redundancy (if required)

Notes
- Redundancy is defined by means of an alphabetic
character,
- Redundant loop apply only to measure in the same
point.
- Loop sequential number may be usefully unique for
facility and functional unit.

Loop identification

2)
Instrument identification as defined in the reference
document 1, comprising loop identification plus :
Instrument function
Instrument sequential number in the loop
Instrument identification
3) Loop information:
- Loop Description (position of measuring element )
- Transducer fluid
- Pressure and temperature of transducer environment
- Loop tagging document
- Loop diagram
- DCS System inclusion (yes/no)

4) Instrument information:
- Instrument function / description
- Instrument tagging document
- Instrument data sheet

5)
Instrument location identification Physical installation of the
instrument (rack - cubicle field)



Eni S.p.A.
Exploration & Production Division
06223.DOC.PRC.PRG
Rev. 3 J anuary 2005
Sh. 6 of 8


7. INFORMATION SUPPLY AT DIFFERENT PROJECT DEVELOPMENT PHASES
Project phases and issues will be in accord the relevant PID.

The basic information will be added in the initial project development phases and
further enriched during the following phases, as described in the here below table.


CONTENT
Feasibility
study
Basic/Feed
Design
Detail
Design
Construction
Loop identification X X X X
Loop information:
- Loop Description (position of measuring element )
- Transducer fluid
- Pressure and temperature of transducer environment
- Loop tagging document
- Loop diagram
- DCS System inclusion (yes/no)
X X X X
Instrument information:
- Instrument function / description
- Instrument tagging document
- Instrument data sheet
X X X
Installation cubicle X X



Eni S.p.A.
Exploration & Production Division
06223.DOC.PRC.PRG
Rev. 3 J anuary 2005
Sh. 7 of 8

8. FINAL DATA SUPPLY FOR DBIMP CORPORATE DATABASE
At the end of the design and construction phases the Contractor will transmit to
Company the loop and instrument detailed information described in the reference
document 5.
These final data will be utilised to feed the DBIMP Corporate Database which will
collect and made available for internal purposes the significant data of plant and
relevant main components.

9. SUPPLY OF DOCUMENT
The Loop & Instrument List document will always be included in the project
document list, and as such it will be always supplied to the Company, at the end of
each project phase, as specifically defined in the project Document Control
Procedure.

If not otherwise defined for the project, the Line List document shall be supplied to
the Company on paper and in electronic file, having format MS Excel and Adobe
Acrobat, the latter obtained from scanning of original document duly filled and
signed in the appropriate revision table.

The document layout will be as suggested in appendix A SUGGESTED LOOP &
AND INSTRUMENT LIST FORMAT and in accordance with the Company standard
format as defined in the reference document 6.


Eni S.p.A.
Exploration & Production Division
06225.DOC.PRC.PRG
Rev. 3 J anuary 2005
Sh. 8 of 8


10. SUGGESTED LOOP AND INSTRUMENT LIST FORMAT
Loop identification Instrument
suffix
Loop and Instrument data
A B C D E F G H
Loop /
Instrument
description
Loop /
Instrument
Tagging
document
Loop fluid
temperature
pressure
Loop
diagram /
instrument
data sheet
Instrument
installation
identification
DCS
system
(yes/no)
onsh 200 1 l 001 Level tank a1
1 Indicator- control
1 Indicator- contr
onsh 200 1 p 001 a Press tank a1
1 Indicator- contr
onsh 200 1 p 001 b Press tank a1
1 Indicator- contr
onsh 200 1 p 002 a Press tank a2
1 Indicator- contr
onsh 200 1 p 002 b Press tank a2
1 Indicator- contr
onsh 200 1 t 001 Temper,tank a1
1 Indicator-
onsh 300 1 l 001 Level tank a3
1 Indicatore- contr
1 Recorder
onsh 300 1 p 001 a Press tank a3
1 Indicatore- contr
onsh 300 1 p 001 b Press tank a3
1 Indicator- contr
onsh 300 1 p 002 a Press tank a4
1 Indicator- contr
onsh 300 1 p 002 b Press tank a4
1 Indicator- contr
onsh 300 1 t 001 Temper,tank a4
1 Indicator-

LEGEND A =Sub Facility E =Loop Number
B =Functional Unit F =Loop redundancy
C =Train G =Instrument function
D =Physical entity H =Instrument number