Sie sind auf Seite 1von 46

Schedule A - Tender Prices for Giza North

1500 MW Combined Cycle Power Project


Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material
2.1
2.1.1
2.1.1.1
L.S. 1 3000000
2.1.1.2
M
3
500000
2.1.1.3
M
3
250000 12
2.1.2
2.1.2.1
L.S. 1
2.1.2.2
L.S. 1
2.1.2.3
L.S. 1
2.1.2.4
L.S. 1
2.1.2.5
L.S. 1
2.1.2.6
L.S. 1
2.1.2.7
L.S. 1
Description
Total Tender Price Unit Prices
Site Development
Site Preparation for Construction Phase
Temporary Construction Offices Facilities
Survey and Initial Site Activities
Lump Sum Price for the following Items
Lump Sum Price for designing, furnishing and installing
surveying, control bench marks, settlement monitoring
system during construction stage, rough grading,
temporary plant roads.
Unit price for removal of top soil, organic materials,
waste and unsuitable materials in accordance with
Specification 99999-9-3SS-CE00-00001
Unit price for structural backfill in accordance with
Specification 99999-9-3SS-CE00-00001
Lump Sum Price for designing, furnishing, testing of
grounding system.
Lump Sum Price for designing, furnishing, installation
and testing of telephone and computer outlets
Lump Sum Price for designing, furnishing, installation,
and testing of a potable water system.
Lump Sum Price for designing, furnishing, installation
and testing of a sewage water system.
Lump Sum Price for the following Items
Lump Sum Price for designing, furnishing, and erection
of Prefabricated Caravans including concrete for
foundations and finishing works.
Lump Sum Price for designing, furnishing, installation,
testing and commissioning of the Air Conditioning
system.
Lump Sum Price for designing, furnishing, testing of the
Lighting and power receptacles system (Lighting fixtures,
switches, receptacles, cable / wiring, computer nodes
and distribution panels).
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 1 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.2.8
L.S. 1
2.1.2.9
L.S. 1
2.1.3
2.1.3.1
L.S. 1
2.1.3.2
L.S. 1
2.1.3.3 L.S. 1
2.1.4
Class Diameter mm
2.1.4.1 3SD 63
L.M. 50
2.1.4.2 3SD 75
L.M. 50
2.1.4.3 3SD 90
L.M. 50
2.1.4.4 3SD 100
L.M. 50
2.1.4.5 3SD 110
L.M. 50
2.1.4.6 3SD 150
L.M. 50
2.1.4.7 3SD 160
L.M. 100
2.1.4.8 3SD 180
L.M. 100
2.1.4.9 3SD 200
L.M. 100
2.1.4.10 3SD 250
L.M. 50
2.1.4.11 3SD 300
L.M. 100
2.1.4.12 3SD 315
L.M. 50
Underground Piping
Lump Sum Price for temporary yard lighting
Lump Sum Price for the following Items
Lump Sum Price for designing, furnishing, delivery and
set up of the Furniture.
Any other items required for proper completion of works
for Item 2.1.2 (Contractor must clarify and provide
breakdown Items for all works / services to be performed
and / or materials to be supplied and constructed and/ or
installed under this Item No 2.1.2.9, which are not
mentioned or included within the listed Items above Nos
2.1.2.1 through 2.1.2.8).
Sub Total of items 2.1.2.1 through 2.1.2.9
Completion of Site Development
Temporary Construction power
Lump Sum Price for Istallation, test, operartion and
maintenance during construction stage
Lump Sum Price for design, furnished and install all
required cables
Sub Total of items 2.1.3.1 through 2.1.3.3
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 2 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.4.13 3SQ 63
L.M. 40
2.1.4.14 3SQ 75
L.M. 100
2.1.4.15 3SQ 110
L.M. 100
2.1.4.16 3SQ 125
L.M. 100
2.1.4.17 3SQ 150
L.M. 50
2.1.4.18 3SQ 160
L.M. 50
2.1.4.19 3SQ 200
L.M. 50
2.1.4.20 3SQ 250
L.M. 50
2.1.4.21 3SQ 300
L.M. 50
2.1.4.22 C1D 65
L.M. 300
2.1.4.23 C1D 80
L.M. 320
2.1.4.24 C1D 100
L.M. 300
2.1.4.25 C1D 125
L.M. 150
2.1.4.26 C1D 150
L.M. 150
2.1.4.27 C1D 200
L.M. 50
2.1.4.28 C1D 250
L.M. 50
2.1.4.29 C1D 300
L.M. 50
2.1.4.30 C1D 350
L.M. 50
2.1.4.31 C1D 400
L.M. 10
2.1.4.32 C1D 450
L.M. 50
2.1.4.33 C1D 800
L.M. 10
2.1.4.34 C3D 350
L.M. 10
2.1.4.35 C3D 400
L.M. 10
2.1.4.36 C3D 450
L.M. 10
2.1.4.37 CED 40
L.M. 200
2.1.4.38 CED 80
L.M. 100
2.1.4.39 CED 100
L.M. 250
2.1.4.40 CED 150
L.M. 800
2.1.4.41 CED 200
L.M. 50
2.1.4.42 CED 300
L.M. 100
2.1.4.43 CED 400
L.M. 100
2.1.4.44 CED 450
L.M. 100
2.1.4.45 CED 500
L.M. 100
2.1.4.46 ESD 50
L.M. 100
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 3 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.4.47 ESD 63
L.M. 1000
2.1.4.48 ESD 90
L.M. 600
2.1.4.49 ESD 100
L.M. 200
2.1.4.50 ESD 125
L.M. 800
2.1.4.51 ESD 150
L.M. 100
2.1.4.52 ESD 180
L.M. 600
2.1.4.53 ESD 200
L.M. 200
2.1.4.54 ESD 250
L.M. 50
2.1.4.55 ESD 300
L.M. 50
2.1.4.56 ESD 350
L.M. 50
2.1.4.57 ESD 450
L.M. 50
2.1.4.58 ESD 500
L.M. 50
2.1.4.59 ESD 560
L.M. 50
2.1.4.60 ESD 600
L.M. 50
2.1.4.61 ESD 630
L.M. 150
2.1.4.62 ESD 710
L.M. 150
2.1.4.63 ESD 800
L.M. 10
2.1.4.64 ESQ 40
L.M. 100
2.1.4.65 ESQ 50
L.M. 50
2.1.4.66 ESQ 63
L.M. 200
2.1.4.67 ESQ 90
L.M. 100
2.1.4.68 ESQ 110
L.M. 100
2.1.4.69 ESQ 125
L.M. 100
2.1.4.70 ESQ 160
L.M. 100
2.1.4.71 ESQ 180
L.M. 100
2.1.4.72 ESQ 300
L.M. 100
2.1.4.73 ESQ 100
L.M. 100
2.1.4.74 ESQ 150
L.M. 50
2.1.4.75 GED 25
L.M. 50
2.1.4.76 GED 40
L.M. 50
2.1.4.77 GED 50
L.M. 50
2.1.4.78 GED 80
L.M. 50
2.1.4.79 GED 100
L.M. 50
2.1.4.80 ISQ 100
L.M. 1600
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 4 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.4.81 ISQ 150
L.M. 900
2.1.4.82 ISQ 200
L.M. 100
2.1.4.83 JFF 80
L.M. 10
2.1.4.84 JFF 100
L.M. 30
2.1.4.85 JFF 150
L.M. 400
2.1.4.86 JFF 200
L.M. 60
2.1.4.87 JFF 250
L.M. 40
2.1.4.88 JFF 300
L.M. 1200
2.1.4.89 JFF 350
L.M. 50
2.1.4.90 PSD 40
L.M. 50
2.1.4.91 PSD 50
L.M. 50
2.1.4.92 PSD 63
L.M. 50
2.1.4.93 PSD 75
L.M. 50
2.1.4.94 PSD 90
L.M. 50
2.1.4.95 PSD 110
L.M. 50
2.1.4.96 PSD 160
L.M. 50
2.1.4.97 PSD 180
L.M. 50
2.1.4.98 PSD 200
L.M. 50
2.1.4.99 PSD 225
L.M. 50
2.1.4.100 PSD 250
L.M. 50
2.1.4.101 PSQ 63
L.M. 50
2.1.4.102 PSQ 75
L.M. 50
2.1.4.103 PSQ 110
L.M. 50
2.1.4.104 PSQ 160
L.M. 50
2.1.4.105 QSJ 800
L.M. 100
2.1.4.106 QSJ 1800
L.M. 200
2.1.4.107 QSJ 2500
L.M. 1500
2.1.4.108 S1D 150
L.M. 50
2.1.4.109 S1D 200
L.M. 50
2.1.4.110 S1D 250
L.M. 50
2.1.4.111
FD-1 100
Units 150
Floor Drain Ref. DWG 99999-9-P0-0000-00002, Detail 9,
Cast Iron
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 5 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.4.112
FD-1 100
Units 10
2.1.4.113
FD-2 100
Units 12
2.1.4.114
FD-3 100
Units 10
2.1.4.115
FD-4 100
Units 10
2.1.4.116
ED-1 100
Units 80
2.1.4.117
ED-2 100
Units 10
2.1.4.118
ED-4 100
Units 80
2.1.4.119
CO-1 100
Units 40
2.1.4.120
CO-2 100
Units 20
2.1.4.121
CO-3 100
Units 20
2.1.4.122
U / G Valve 100
Units 5
Floor Drain Ref. DWG 99999-9-P0-0000-00002, Detail 9,
Acid Resistant Epoxy Coated Cast Iron
Floor Drain Ref. DWG 99999-9-P0-0000-00002, Detail
10, Cast Iron
Floor Drain Ref. DWG 99999-9-P0-0000-00002, Detail
11, Cast Iron
Floor Drain Ref. DWG 99999-9-P0-0000-00002, Detail
12, Cast Iron
Equipment Drain Ref. DWG 99999-9-P0-0000-00002,
Detail 1, Pipe Class ESD, ISQ, 1SQ & PSQ
Outdoor Clean Out Ref. DWG 99999-9-P0-0000-00002,
Detail 8
U / G Gate Valve w / curb box, and T-Handle Wrench,
Ref. DWG 99999-9-P0-0000-00002, Detail 17
Equipment (Funnel) Drain Ref. DWG 99999-9-P0-0000-
00002, Detail 2, Pipe Class CED, S1D, FSQ & PSQ
Equipment Drain Ref. DWG 99999-9-P0-0000-00002,
Detail 4, SS Grate
Floor Clean Out Ref. DWG 99999-9-P0-0000-00002,
Detail 6
Floor Clean Out Ref. DWG 99999-9-P0-0000-00002,
Detail 7 Pipe Class ISQ, PSQ & ESD
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 6 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.4.123
Valve 50
Units 5
2.1.4.124
Valve 80
Units 5
2.1.4.125
Valve 100
Units 10
2.1.4.126
Cond. Pot
Units 5
JFF 150
Units 40
2.1.4.127
JFF 150
Units 40
2.1.4.128
JFF 150
Units 60
2.1.4.129
JFF 150
Units 60
2.1.4.130
Units 2 Pieces
2.1.4.131
Units 29
JFF 200
Units 14
2.1.4.132
JFF 200
Units 14
2.1.4.133
Post Indicator Valve
Post Indicator Valve U / G Gate Valve with post
Fire Hydrant
Fire Hydrant Hose Cabinet Fully Equipped per
Specification 10063-3PS-CG00-00001.
Post indicator valve
CPVC Ball Valve, (for chemical drain), Detail 20, Asahi /
America Type 21, ANSI Class 150, flanged ball valbe, w
/ viton O-Rings Cushion, "T" Operating nut, and provided
with a 600 high, type BV - A valve steam extension, or
equal.
CPVC Ball Valve, (for chemical drain), Detail 20, Asahi /
America Type 21, ANSI Class 150, flanged ball valbe, w
/ viton O-Rings Cushion, "T" Operating nut, and provided
with a 600 high, type BV - A valve steam extension, or
equal.
CPVC Ball Valve, (for chemical drain), Detail 20, Asahi /
America Type 21, ANSI Class 150, flanged ball valbe, w
/ viton O-Rings Cushion, "T" Operating nut, and provided
with a 600 high, type BV - A valve steam extension, or
equal.
U / G Air Line Condensate Pot, Ref. DWG 99999-9-P0-
0000-00002, Detail 16
Post Indicator Valve U / G Gate Valve with post
U / G Gate Valve w / curb box, and T-Handle Wrench
(Fire Hydrant VA)
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 7 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
JFF 250
Units 5
2.1.4.134
JFF 250
Units 5
2.1.4.135
JFF 300
Units 35
2.1.4.136
JFF 300
Units 35
2.1.4.137 Units 88
2.1.4.138
Units 4
2.1.4.139
L.M. 140
2.1.4.140
L.M. 70
2.1.5
2.1.5.1 L.M. 10
2.1.5.2 L.M. 390
2.1.5.3 L.M. 230
2.1.5.4 L.M. 100
2.1.5.5 L.M. 20
2.1.5.6 L.M. 250
2.1.5.7 L.M. 10
2.1.5.8 L.M. 75
2.1.5.9 L.M. 40
2.1.5.10 L.M. 400
2.1.5.11 L.M. 220
2.1.5.12 L.M. 20
2.1.5.13 L.M. 320
2.1.5.14 L.M. 550
Five (5) Conduits Yard Duct Bank
Six (6) Conduits Yard Duct Bank
Sixteen (16) Conduits Yard Duct Bank
Ten (10) Conduits Yard Duct Bank
Twelve (12) Conduits Yard Duct Bank
Fourteen (14) Conduits Yard Duct Bank
Fifteen (15) Conduits Yard Duct Bank
Seven (7) Conduits Yard Duct Bank
Eight (8) Conduits Yard Duct Bank
Nine (9) Conduits Yard Duct Bank
Two (2) Conduits Yard Duct Bank
Three (3) Conduits Yard Duct Bank
Four (4) Conduits Yard Duct Bank
Unit Price for Yard Storm Drainage concrete culvert of
400 mm diameter.
(Item 2.1.4.1 through 2.1.4.140)
Underground Electrical Duct Bank
Unit Price for Electrical Yard Duct Bank Types Six
inches (6) conduits including stub-ups lengths as
follows:-
One (1) Conduit Yard Duct Bank
Condensate Pump Can per Drawing 10063-9-DB-2111-
00001.
Post Indicator Valve U / G Gate Valve with post
Post Indicator Valve U / G Gate Valve with post
Unit Price for Yard Storm Drainage concrete culvert of
300 mm diameter.
Post Indicator Valve
Subtotal for Underground Piping
Post Indicator Valve
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 8 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.5.15 L.M. 270
2.1.5.16 L.M. 120
2.1.5.17 L.M. 70
2.1.5.18 L.M. 100
2.1.5.19 L.M. 20
2.1.5.20 L.M. 120
2.1.5.21 L.M. 25
2.1.5.22 L.M. 10
2.1.5.23 L.M. 10
2.1.5.24 L.M. 10
2.1.5.25 Each 500
2.1.5.26 Each 450
2.1.5.27 Each 50
2.1.6
2.1.6.1
L.S. 1
2.1.6.2
L.S. 1
2.1.6.3
L.S. 1
2.1.6.4
L.M. 700
2.1.6.5 L.S. 1
2.1.6.6
L.S. 1
Lump Sum and Unit Price for the following Items
Thirty Three (30) Conduits Yard Duct Bank
Permanent yard lighting
Grounding systen including exposed and embedded
cables and connections of groundings to the steel
structural, tanks, piping and equipments.
Lump Sum Price for designing, furnishing and installing
finish grading including all earthworks.
Lump Sum Price for designing, furnishing and installing
permanent plant roads, and parking area sub base,
asphalt paving or concrete paving
Lump Sum Price for designing, furnishing and installing
storm water drainage system including concrete
trenches, grating covers, concrete ditches, storm
drainage ponds, collection pit with mechanical oil
separator, rip rap for ponds and slope protection.
Site Activities for Completion of Site Development
Sub Total for Electrical Duct Bank
Item 2.1.5.1 Through 2.1.5.27
Fifty Four (54) Conduits Yard Duct Bank
Eighteen (18) Conduits Yard Duct Bank
Twenty (20) Conduits Yard Duct Bank
Twenty Four (24) Conduits Yard Duct Bank
Twenty Seven (27) Conduits Yard Duct Bank
Thirty Two (32) Conduits Yard Duct Bank
Unit Price for 6" Coring in Concrete Walls - Each
Thirty Three (33) Conduits Yard Duct Bank
Thirty Six (36) Conduits Yard Duct Bank
Forty (40) Conduits Yard Duct Bank
Unit Price for PVC Elbows 1.5R - Each
Unit Price for Rigid Steel Elbows 1.0R - Each
Unit price for Designing, Furnishing, and construction of
chain link fence
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 9 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.6.7
L.S. 1
2.1.6.8
L.S. 1
2.1.6.9
L.S. 1
2.1.7
2.1.7.1
L.S. 1
2.1.7.2
L.S. 1
2.1.7.3 L.S. 1
2.1.7.4
L.S. 1
DECT System
Landscaping lighting
Sub Total of items 2.1.6.1 through 2.1.6.9
Lump Sum Price for the following Items
Lump Sum Price for designing, furnishing and
installation of landscaping works including, but not
limited to, 80 mm thick, colored interlocking concrete
paving blocks, on clean compacted soil and sand, and
100 mm thick plain concrete layer, including, but not
limited to, excavation, finish grading, concrete
curbstones, mortar, and all other related works and all
required accessories per item 7.2 of Design Criteria for
Architectural Works specification 10063-9-3DR-A01-
00001, and in accordance with specification 10063-9-
3PS-ALL0-00001
Lump Sum Price for designing, furnishing and laying of
100 mm thick of gravel in the project area except the
paved and planted areas.
PA/Paging system in the control building including all
required interfaces/connection
PABX located in the construction building and including
all required interfaces/connection
Landscaping
Lump Sum Price for furnishing and planting for items of
plants ,palms,trees,flowering,grass,lawn ..etc as
breakdown in schedule B including, but not limited to,
excavation, finish grading, protection, fertilizing,
drainage, and all other related works and all required
accessories.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 10 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.7.5
L.S. 1
2.1.7.6
L.S. 1
2.1.7.7
L.S. 1
2.1.7.8
2.1.7.8.1
L.S. 1
2.1.7.8.2
M
3
500
2.1.7.8.3
Tonnes 35
2.1.7.8.4
Tonnes 35
2.1.7.8.5
Tonnes 10
2.1.7.8.6
Tonnes 5
2.1.7.8.7
Tonnes 5
Structural Steel
Unit Price for foundations,equipment pads, grade slabs,
sumps, pits, pipe trench, cable tray trench and pipe
supports pads for Miscellaneous Structures
Unit Price for the following Items
Concrete Works
Reinforcing Steel
Miscellaneous Structures
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Any other items required for proper completion of work
for item 2.1.7 (Contractor must clarify and provide
breakdown Items for all works / services to be performed
and/ or materials to be supplied and constructed and/ or
installed under this Item No 2.1.7.5, which are not
mentioned or included within the listed Items above Nos
2.1.7.1 through 2.1.7.4).
Lump Sum Prices for irrigation system including pumps
in accordance with Technical specification 10063-9-3PS-
P000-00001
Lump Sum Prices for Sanitary waste lift stations in
accordance with Technical specification 10063-9-3PS-
MPGL-00001 and Drawing No. 10063-9-M6-XN-00001
Lump Sum Price for parking sunshades as indicated in
drawings in Exhibit E
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 11 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.1.7.8.8
M
2
500
2.1.7.8.9
M
2
500
2.2
2.2.1
2.2.1.1
L.M 5400
2.2.1.2
M
3
2850
2.2.1.3
Tonnes 670 860
2.2.1.4 L.S. 1
2.2.2
2.2.2.1
L.M 5400
Electrical Works
Civil Works
Unit Prices for the following Items:
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Unit Price for HRSG, Bypass and Main Stack Module I
foundations including pile caps, piers, trenches, curbs,
auxillary equipment pad, sumps, pits, duct banks, and
foundations.
Piling Works
Concrete Works
Lump Sum Prices for Electrical Items
Piling Works
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Unit Price for 12 mm galvanized Checkered floor plates.
Civil Works
Power Generating Facilities
Heat Recovery Steam Generator Area Module I
Facility Nos. 11
1A
- 11
1B
Sub Total of items 2.1.7.1 through 2.1.7.8
Unit Prices for the following Items:
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Heat Recovery Steam Generator Area Module II
Facility Nos. 11
2A
- 11
2B
Sub Total of items 2.2.1.1 through 2.2.1.4
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 12 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.2.2
M
3
2850
2.2.2.3
Tonnes 670
2.2.2.4 L.S. 1
2.2.3
2.2.3.1
M
3
90
2.2.3.2
Tonnes 13
2.2.3.3 L.S. 1
2.2.4
2.2.4.1
M
3
90
Sub Total of items 2.2.2.1 through 2.2.2.4
Sub Total of items 2.2.3.1 through 2.2.3.3
Concrete Works
Reinforcing Steel
Lump Sum Prices for Electrical Items
Lump Sum Prices for Electrical Items
Unit Price for Boiler Feed Water Pumps Area including
pile caps, piers, trenches, curbs, reinforced concrete
mat, sumps, pits, duct banks, and foundations.
Electrical Works
Reinforcing Steel
Boiler Feed Water Pumps Area Module II
Facility Nos. 12
1
Unit Prices for the following Items:
Civil Works
Electrical Works
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Facility Nos. 12
1
Boiler Feed Water Pumps Area Module I
Unit Price for HRSG, Bypass and Main Stack Module II
foundations including pile caps, piers, trenches, curbs,
auxillary equipment pad, sumps, pits, duct banks, and
foundations.
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Concrete Works
Civil Works
Unit Prices for the following Items:
Concrete Works
Unit Price for Boiler Feed Water Pumps Area including
pile caps, piers, trenches, curbs, reinforced concrete
mat, sumps, pits, duct banks, and foundations.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 13 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.4.2
Tonnes 13
2.2.4.3 L.S. 1
2.2.5
2.2.5.1
L.M 7650
2.2.5.2
M
3
2950
2.2.5.3
M
3
1700
2.2.5.4
M
3
2050
2.2.5.5
M
3
550
2.2.5.6
Tonnes 1150
2.2.5.7 Tonnes 850
2.2.5.8
Tonnes 320
2.2.5.9 Tonnes 95
2.2.5.10
Tonnes 70
Sub Total of items 2.2.4.1 through 2.2.4.3
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Electrical Works
Unit Price for Combustion Turbine Building (CTG)
Elevated Slab.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Lump Sum Prices for Electrical Items
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Combustion Turbine Generator CTG Area Module I
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Facility Nos. 14
1A 1B
Civil Works
Unit Price / Lump Sum Prices for the following Items:
Piling Works
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Concrete Works
Unit Price for Module I Combustion Turbine Generator
Building Foundations including pile caps, column piers,
walls and grade beams
Unit Price for Module I Combustion Turbine Generator
Pedestal Foundations including piers
Unit Price for Combustion Turbine Building (CTG) Grade
Slab including sumps, pits, trenches, and equipment
pads on top of grade slab.
Reinforcing Steel
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 14 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.5.11 Tonnes 25
2.2.5.12
Tonnes 20
2.2.5.13
L.M 1000
2.2.5.14
M
2
680
2.2.5.15
M
2
220
2.2.5.16
M
2
1850
2.2.5.17
M
2
100
2.2.5.18
M
2
300
2.2.5.19
M
2
7000
Unit Price for Monorail Beams.
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for Platform and stair Handrails and
Guardrails, including toe plates .
Unit Price for 12 mm galvanized Checkered floor plates.
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Unit Price for Two-Hours Fire-Rated Siding, field
assembled Fire-Wall Assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 99999-9-3SS-ATPR-00001, and standard
drawings 99999-9-A3-0000-00002 and in accordance
with Architectural Design Criteria Specification 10063-9-
3DR-A01-00001, Item No. 7.1
Unit Price for One-Hour Fire-Rated Siding, field
assembled Fire-Wall assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 99999-9-3SS-ATPR-00001, and standard
drawings 99999-9-A3-0000-00002, and in accordance
with Architectural Design Criteria Specification 10063-9-
3DR-A01-00001, Item No. 7.1
Unit Price for Double Skinned, Insulated Metal
Corrugated Sheet Panels for walls and roofs including
accessories, flashing, sealant, insulation, additional steel
supports, coating, etc, per Technical Specification
99999-9-3SS-ATPR-00001, and standard drawings
99999-9-A3-0000-00002, and in accordance with
Architectural Design Criteria Specification 10063-9-3DR-
A01-00001, Item No. 4.3, and 4.4.1, and 4.4.2.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 15 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.5.20
L.S. 1
2.2.5.21 L.S. 1
2.2.5.22 L.S. 1
2.2.6
.
2.2.6.1
L.M 7650
2.2.6.2
M
3
2950
2.2.6.3
M
3
1700
2.2.6.4
M
3
2050
2.2.6.5
M
3
550
2.2.6.6
Tonnes 1150
2.2.6.7 Tonnes 850
Unit Price for Combustion Turbine Building (CTG)
Elevated Slab.
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001.
Mechanical Works
Architectural Works
Lump Sum Prices for Mechanical Items
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.2.5.1 through 2.2.5.22
Combustion Turbine Generator CTG Area Module
II
Facility Nos. 14
2A 2B
Civil Works
Unit Price / Lump Sum Prices for the following Items:
Piling Works
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Concrete Works
Unit Price for Module II Combustion Turbine Generator
Building Foundations including pile caps, column piers,
walls and grade beams
Unit Price for Module II Combustion Turbine Generator
Pedestal Foundations including piers
Unit Price for Combustion Turbine Building (CTG) Grade
Slab including sumps, pits, trenches, and equipment
pads on top of grade slab.
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 16 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.6.8
Tonnes 320
2.2.6.9 Tonnes 95
2.2.6.10
Tonnes 70
2.2.6.11 Tonnes 25
2.2.6.12
Tonnes 20
2.2.6.13
L.M 1000
2.2.6.14
M
2
680
2.2.6.15
M
2
220
2.2.6.16
M
2
1850
2.2.6.17
M
2
100
2.2.6.18
M
2
300
Unit Price for Two-Hours Fire-Rated Siding, field
assembled Fire-Wall Assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 99999-9-3SS-ATPR-00001, and standard
drawings 99999-9-A3-0000-00002 and in accordance
with Architectural Design Criteria Specification 10063-9-
3DR-A01-00001, Item No. 7.1
Unit Price for One-Hour Fire-Rated Siding, field
assembled Fire-Wall assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 99999-9-3SS-ATPR-00001, and standard
drawings 99999-9-A3-0000-00002, and in accordance
with Architectural Design Criteria Specification 10063-9-
3DR-A01-00001, Item No. 7.1
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Unit Price for Monorail Beams.
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for Platform and stair Handrails and
Guardrails, including toe plates .
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Unit Price for 12 mm galvanized Checkered floor plates.
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 17 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.6.19
M
2
7000
2.2.6.20
L.S. 1
2.2.6.21 L.S. 1
2.2.6.22 L.S. 1
2.2.7
2.2.7.1
L.M 5650
2.2.7.2
M
3
1850
2.2.7.3
M
3
4500
2.2.7.4
M
3
750
Unit Price for Double Skinned, Insulated Metal
Corrugated Sheet Panels for walls and roofs including
accessories, flashing, sealant, insulation, additional steel
supports, coating, etc, per Technical Specification
99999-9-3SS-ATPR-00001, and standard drawings
99999-9-A3-0000-00002, and in accordance with
Architectural Design Criteria Specification 10063-9-3DR-
A01-00001, Item No. 4.3, and 4.4.1, and 4.4.2.
Civil Works
Unit Price for Module I Steam Turbine Pedestal
Foundations including pile caps, column, piers and top
slab beams
Unit Price for Steam Generator Building (STG) Grade
Slab including sumps, pits, trenches, and equipment
pads on top of grade slab.
Architectural Works
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Mechanical Works
Lump Sum Prices for Mechanical Items
Concrete Works
Unit Price / Lump Sum Prices for the following Items:
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.2.6.1 through 2.2.6.22
Unit Price for Module I Steam Turbine Building
Foundations including pile caps, column piers, walls and
grade beams
Piling Works
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Steam Turbine Generator STG Area Module I
Facility Nos. 21
1
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 18 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.7.5
M
3
355
2.2.7.6
Tonnes 1200
2.2.7.7 Tonnes 600
2.2.7.8
Tonnes 250
2.2.7.9
Tonnes 70
2.2.7.10
Tonnes 65
2.2.7.11 Tonnes 25
2.2.7.12
Tonnes 35
2.2.7.13
L.M 1200
2.2.7.14
M
2
1650
2.2.7.15 M
2
200
2.2.7.16
M
2
1350
2.2.7.17
M
2
400
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for 12 mm galvanized Checkered floor plates.
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Reinforcing Steel
Unit Price for Steam Generator Building (STG) Elevated
Slabs
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for Platform and stair Handrails and
Guardrails, including toe plates .
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Monorail Beams.
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Unit Price for Two-Hours Fire-Rated Siding, field
assembled Fire-Wall Assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 99999-9-3SS-ATPR-00001, and standard
drawings 99999-9-A3-0000-00002 and in accordance
with Architectural Design Criteria Specification 10063-9-
3DR-A01G-00001, Item No. 7.1
Structural Steel
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 19 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.7.18
M
2
100
2.2.7.19
M
2
6500
2.2.7.20
L.S. 1
2.2.7.21 L.S. 1
2.2.7.22 L.S. 1
2.2.8
2.2.8.1
L.M 5650
Unit Price for One-Hours Fire-Rated Siding, field
assembled Fire-Wall Assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 10063 99999-9-3SS-ATPR-00001, and
standard drawings 99999-9-A3-0000-00002 and in
accordance with Architectural Design Criteria
Specification 10063-9-3DR-A01G-00001, Item No. 7.1
Unit Price for Double Skinned, Insulated Metal
Corrugated Sheet Panels for walls and roofs including
accessories, flashing, sealant, insulation, additional steel
supports, coating, etc, per Technical Specification 10063
99999-9-3SS-ATPR-00001, and standard drawings
99999-9-A3-0000-00002, and in accordance with
Architectural Design Criteria Specification 10063-9-3DR-
A01-00001, Item No. 4.3, and 4.4.1, and 4.4.2.
Architectural Works
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Mechanical Works
Lump Sum Prices for Mechanical Items
Sub Total of items 2.2.7.1 through 2.2.7.22
Steam Turbine Generator STG Area Module II
Piling Works
Facility Nos. 21
2
Civil Works
Unit Price / Lump Sum Prices for the following Items:
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Lump Sum Prices for Electrical Items
Electrical Works
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 20 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.8.2
M
3
1850
2.2.8.3
M
3
4500
2.2.8.4
M
3
750
2.2.8.5
M
3
355
2.2.8.6
Tonnes 1200
2.2.8.7 Tonnes 600
2.2.8.8
Tonnes 250
2.2.8.9 Tonnes 70
2.2.8.10
Tonnes 65
2.2.8.11 Tonnes 25
2.2.8.12
Tonnes 35
2.2.8.13
L.M 1200
2.2.8.14
M
2
1650
2.2.8.15
M
2
200
2.2.8.16
M
2
1350
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for Platform and stair Handrails and
Guardrails, including toe plates .
Unit Price for Stean Turbine Building (STG) Grade Slab
including sumps, pits, trenches, and equipment pads on
top of grade slab.
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Structural Steel
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Unit Price for Monorail Beams.
Unit Price for 12 mm galvanized Checkered floor plates.
Unit Price for Module II Steam Turbine Building
Foundations including pile caps, column piers, walls and
grade beams
Unit Price for Stean Turbine Building (STG) Elevated
Slabs
Unit Price for Module II Steam Turbine Pedestal
Foundations including pile caps, column, piers and top
slab beams
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Concrete Works
Reinforcing Steel
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 21 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.8.17
M
2
400
2.2.8.18
M
2
100
2.2.8.19
M
2
6500
2.2.8.20
L.S. 1
2.2.8.21 L.S. 1
2.2.8.22 L.S. 1
2.2.9
Sub Total of items 2.2.8.1 through 2.2.8.22
Lump Sum Prices for Electrical Items
Mechanical Works
Lump Sum Prices for Mechanical Items
Architectural Works
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Electrical Building
Facility Nos. 31
1
Electrical Works
Unit Price for Double Skinned, Insulated Metal
Corrugated Sheet Panels for walls and roofs including
accessories, flashing, sealant, insulation, additional steel
supports, coating, etc, per Technical Specification 10063
99999-9-3SS-ATPR-00001, and standard drawings
99999-9-A3-0000-00002, and in accordance with
Architectural Design Criteria Specification 10063-9-3DR-
A01-00001, Item No. 4.3, and 4.4.1, and 4.4.2.
Unit Price for Two-Hours Fire-Rated Siding, field
assembled Fire-Wall Assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 10063 99999-9-3SS-ATPR-00001, and
standard drawings 99999-9-A3-0000-00002 and in
accordance with Architectural Design Criteria
Specification 10063-9-3DR-A01G-00001, Item No. 7.1
Unit Price for One-Hours Fire-Rated Siding, field
assembled Fire-Wall Assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Specification 10063 99999-9-3SS-ATPR-00001, and
standard drawings 99999-9-A3-0000-00002 and in
accordance with Architectural Design Criteria
Specification 10063-9-3DR-A01G-00001, Item No. 7.1
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 22 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.9.1
M
3
500
2.2.9.2
M
3
330
2.2.9.3
Tonnes 90
2.2.9.4 Tonnes 105
2.2.9.5
Tonnes 70
2.2.9.6 Tonnes 9
2.2.9.7
M
2
1500
2.2.9.8
L.S. 1
2.2.9.9 L.S. 1
2.2.9.10 L.S. 1
2.2.10
2.2.10.1
L.M 1850
Electrical Works
Sub Total of items 2.2.9.1 through 2.2.9.10
Civil Works
Structural Steel
Architectural Works
Unit Price for Electrical Building Roof Slab including
equipment pads on top of slab.
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Unit Price for Beams (Gr. A50) - painted.
Reinforcing Steel
Lump Sum Prices for Electrical Items
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Civil Works
Unit Price / Lump Sum Prices for the following Items:
Concrete Works
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Lump Sum Prices for Mechanical Items
Mechanical Works
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Piling Works
Unit Price for Electrical Building Foundations including
column piers, walls and grade beams
Unit Price / Lump Sum Prices for the following Items:
Control Building
Facility Nos. 31
2
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 23 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.10.2
M
3
1500
2.2.10.3
M
3
600
2.2.10.4
Tonnes 320
2.2.10.5 Tonnes 230
2.2.10.6
Tonnes 145
2.2.10.7 Tonnes 70
2.2.10.8
Tonnes 45
2.2.10.9
L.M 385
2.2.10.10
M
2
220
2.2.10.11
M
2
3300
2.2.10.12
M
2
200
2.2.10.13
L.S. 1
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Unit Price for Platform and stair Handrails and
Guardrails, including toe plates .
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Reinforcing Steel
Unit Price for Control Building Elevated Slabs including
equipment pads on top of slabs.
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Architectural Works
Unit Price for Control Building Foundations mat
Structural Steel
Concrete Works
Unit Price for Two-Hours Fire-Rated Siding, field
assembled Fire-Wall Assembly, for walls, including
accessories, flashing, sealant, insulation, subgirts,
additional steel supports, coating, etc, per Technical
Standard Specification 10063 99999-9-3SS-ATPR-
00001, and standard drawings 99999-9-A3-0000-00002
and in accordance with Architectural Design Criteria
Specification 10063-9-3DR-A01G-00001, Item No. 7.1.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 24 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.10.14 L.S. 1
2.2.10.15 L.S. 1
2.2.11
`
2.2.11.1
L.M 3000
2.2.11.2
M
3
3850
2.2.11.3
Tonnes 560
2.2.11.4 Tonnes 25
2.2.11.5
Tonnes 6
2.2.11.6 Tonnes 4
Facility Nos. 32
1A 1B -
33
1A 1B -
33
1 -
34
1A 1B
Sub Total of items 2.2.10.1 through 2.2.10.15
Concrete Works
Unit Price / Lump Sum Prices for the following Items:
Mechanical Works
Lump Sum Prices for Mechanical Items
Electrical Works
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Piling Works
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Civil Works
Module I: Generator Circuit Breaker / CTG Main
Transformer / STG Main Transformer / CTG Auxiliary
Transformer / Four CTG Excitation Transformers /
Two STG Excitation Transformer / Iso-phase bus
Unit Price for Combustion / Steam Transformers, cable
tray, Isophase Bus supports and Generator Circuit
Breaker for Main STG / CTG Transformers and Auxiliary
CTG Transformers foundations including fire walls.
Reinforcing Steel
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Lump Sum Prices for Electrical Items
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 25 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.11.7
L.S. 1
2.2.11.8 L.S. 1
2.2.12
2.2.12.1
L.M 3000
2.2.12.2
M
3
3850
2.2.12.3
Tonnes 560
2.2.12.4 Tonnes 25
2.2.12.5
Tonnes 6
2.2.12.6 Tonnes 4
Sub Total of items 2.2.11.1 through 2.2.11.8
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Facility Nos. 32
2A 2B -
33
2A 2B -
33
2 -
34
2A 2B
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Combustion / Steam Transformers, cable
tray, Isophase Bus supports and Generator Circuit
Breaker for Main STG / CTG Transformers and Auxiliary
CTG Transformers foundations including fire walls.
Piling Works
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Concrete Works
Module II: Generator Circuit Breaker / CTG Main
Transformer / STG Main Transformer / CTG Auxiliary
Transformer / Four CTG Excitation Transformer /
Two STG Excitation Transformer / Iso-phase bus
Civil Works
Unit Price / Lump Sum Prices for the following Items:
Electrical Works
Lump Sum Price for Designing, Furnishing, and Placing
of Crushed Stones in the Transformer Pits
Miscellaneous Items
Lump Sum Prices for Electrical Items
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 26 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.12.7
L.S. 1
2.2.12.8 L.S. 1
2.2.13
2.2.13.1
L.M 3750
2.2.13.2
M
3
2400
2.2.13.3
Tonnes 630
2.2.13.4 Tonnes 310
2.2.13.5
Tonnes 205
2.2.13.6 Tonnes 115
2.2.13.7
Tonnes 11
2.2.13.8
Tonnes 25
2.2.13.9
Tonnes 30
2.2.13.10
L.M 715
2.2.13.11
M
2
1550
Concrete Works
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Civil Works
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for ladders including cages, treads and
landings.
Electrical Works
Lump Sum Prices for Electrical Items
Miscellaneous Items
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Unit Price / Lump Sum Prices for the following Items:
Yard Structure Pipe Rack Module I
Sub Total of items 2.2.12.1 through 2.2.12.8
Piling Works
Lump Sum Price for Designing, Furnishing, and Placing
of Crushed Stones in the Transformer Pits
Facility Nos. 12
1
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Platform, Handrails and Guardrails,
including toe plates .
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for Yard Structure Pipe Rack Foundations mat
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 27 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.13.12
Tonnes 5
2.2.13.13 L.S. 1
2.2.14
2.2.14.1
L.M 3750
2.2.14.2
M
3
2400
2.2.14.3
Tonnes 630
2.2.14.4 Tonnes 310
2.2.14.5
Tonnes 205
2.2.14.6 Tonnes 115
2.2.14.7
Tonnes 11
2.2.14.8
Tonnes 25
2.2.14.9
Tonnes 30
2.2.14.10
L.M 715
2.2.14.11
M
2
1550
Unit Price for Monorail Beams.
Electrical Works
Lump Sum Prices for Electrical Items
Facility Nos. 12
2
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Yard Structure Pipe Rack Module II
Unit Price / Lump Sum Prices for the following Items:
Sub Total of items 2.2.13.1 through 2.2.13.13
Civil Works
Piling Works
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Unit Price for Yard Structure Pipe Rack Foundations mat
Unit Price for ladders including cages, treads and
landings.
Unit Price for Platform, Handrails and Guardrails,
including toe plates .
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Concrete Works
Reinforcing Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 28 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.2.14.12
Tonnes 5
2.2.14.13 L.S. 1
2.3
2.3.1
2.3.1.1
M
3
30
2.3.1.2
Tonnes 3
2.3.1.3 L.S. 1
2.3.2
2.3.2.1
M
3
640
2.3.2.2
Tonnes 50
2.3.2.3
Tonnes 7
2.3.2.4
Tonnes 1
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Beams (Gr. A50) - painted.
Structural Steel
Concrete Works
Emergency Diesel Generator
Reinforcing Steel
Electrical Works
Lump Sum Prices for Electrical Items
Unit Price for foundations including equipments pads
and curbs
Sub Total of items 2.3.1.1 through 2.3.1.3
Electrical Works
Civil Works
Auxiliary Facilities
Unit Prices for the following Items:
Sub Total of items 2.2.14.1 through 2.2.14.13
Lump Sum Prices for Electrical Items
Facility Nos. 37
1 2
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Fuel Gas Compressors And Conditioning Area
Facility Nos. 61
9B
Civil Works
Unit Prices for the following Items:
Concrete Works
Unit Price for foundations, grade slab, equipment pads
and curbs
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Unit Price for Monorail Beams.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 29 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.2.5
Tonnes 1
2.3.2.6
M
2
55
2.3.2.7 L.S. 1
2.3.3
2.3.3.1
M
3
115
2.3.3.2 M
3
45
2.3.3.3
Tonnes 15
2.3.3.4
L.S. 1
2.3.3.5 L.S. 1
2.3.3.6 L.S. 1
2.3.4
2.3.4.1
M
3
70
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Sub Total of items 2.3.3.1 through 2.3.3.6
Fuel Oil Unloading Pumps
Unit Prices for the following Items:
Facility Nos. 62
9
Concrete Works
Unit Price for foundations including equipment pads and
curbs.
Electrical Works
Civil Works
Reinforcing Steel
Unit Price for columns and roof slab
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Civil Works
Unit Prices for the following Items:
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.2.1 through 2.3.2.7
Fuel Gas Compressors Electrical Building
Facility Nos. 61
9C
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Architectural Works
Electrical Works
Lump Sum Prices for Electrical Items
Concrete Works
Unit Price for foundations, grade slab, grade beams and
equipment pads.
Mechanical Works
Lump Sum Prices for Mechanical Items
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 30 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.4.2
Tonnes 5
2.3.4.3 Tonnes 7
2.3.4.4
Tonnes 1
2.3.4.5 Tonnes 1
2.3.4.6
M
2
55
2.3.4.7 L.S. 1
2.3.5
2.3.5.1
L.M 8000
2.3.5.2
M
3
4000
2.3.5.3 M
2
6500
2.3.5.4
Tonnes 950
2.3.5.5 L.S. 1
2.3.6
Fuel Oil Tanks
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Reinforcing Steel
Facility Nos. 65
9
Civil Works
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Sub Total of items 2.3.4.1 through 2.3.4.7
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Lump Sum Prices for Electrical Items
Electrical Works
Facility Nos. 64
9A - 9B
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.5.1 through 2.3.5.5
Fuel Oil Transfer Pumps
Civil Works
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Electrical Works
Concrete Works
Unit Price for Tanks Foundations And Retaining walls
including liner
Unit Prices for the following Items:
Piling Works
Unit Price for designing, furnishing, installing and testing
of production piles (800 mm diameter).
Unit price for liner between tank and retaining wall
Miscellanous Works
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 31 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.6.1
M
3
30
2.3.6.2
Tonnes 3
2.3.6.3 Tonnes 7
2.3.6.4
Tonnes 1
2.3.6.5 Tonnes 1
2.3.6.6
M
2
55
2.3.6.7 L.S. 1
2.3.7
2.3.7.1
M
3
2750
2.3.7.2
Tonnes 190
2.3.7.3 L.S. 1
2.3.8
Lump Sum Prices for Electrical Items
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Sub Total of items 2.3.6.1 through 2.3.6.7
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for foundations including equipment pads and
curbs
Reinforcing Steel
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Electrical Works
Facility Nos. 71
9A
& 71
9B
Civil Works
Water Treatment Area & Water Treatment Electrical
Building
Unit Prices for the following Items:
Concrete Works
Unit Prices for the following Items:
Concrete Works
Unit Price for foundations,basins, grade slab, unloading
area slab and grade beams
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Sub Total of items 2.3.7.1 through 2.3.7.3
C.W / Fire Water Pump House
Facility Nos. 73
9A
Electrical Works
Lump Sum Prices for Electrical Items
Civil Works
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 32 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.8.1
M
3
14000
2.3.8.2
Tonnes 1400
2.3.8.3 Tonnes 170
2.3.8.4
Tonnes 80
2.3.8.5 Tonnes 40
2.3.8.6
Tonnes 40
2.3.8.7
Tonnes 6
2.3.8.8
L.M 55
2.3.8.9
M
2
110
2.3.8.10
M
2
4200
2.3.8.11
L.S. 1
2.3.8.12 L.S. 1
Unit Prices for the following Items:
Concrete Works
Unit Price for foundations slab, retaining walls, top slab,
grade slab and sumps / pits
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for Profiles (Gr. A36) - painted (Angles or C or
Bent Plates).
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Stair framing, stringers, ladders including
cages, treads and landings.
Unit Price for Platform and stair Handrails and
Guardrails, including toe plates .
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Mechanical Works
Lump Sum Prices for Mechanical Items
Unit Price for Double Skinned, Insulated Metal
Corrugated Sheet Panels for walls and roofs including
accessories, flashing, sealant, insulation, additional steel
supports, coating, etc, per Technical Specification 10063
99999-9-3P SS-ATPR-00001, and standard drawings
99999-9-A3-0000-00002, and in accordance with
Architectural Design Criteria Specification 10063-9-3DR-
A01-00001, Item No. 4.3, and 4.4.1, and 4.4.2.
Architectural Works
Unit Price for 38 mm depth, 5 mm thick floor grating
galvanized.
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 33 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.8.13 L.S. 1
2.3.9
2.3.9.1
M
3
240
2.3.9.2
Tonnes 21
2.3.9.3 Tonnes 30
2.3.9.4
Tonnes 8
2.3.9.5 Tonnes 3
2.3.9.6
M
2
500
2.3.9.7
L.S. 1
2.3.9.8 L.S. 1
2.3.9.9 L.S. 1
2.3.10
2.3.10.1 M
3
210
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.8.1 through 2.3.8.13
Circulating Water Electrical Building
Facility Nos. 73
9B
Civil Works
Unit Prices for the following Items:
Concrete Works
Unit Price for foundations including equipment pads,
grade beams, grade slab, and roof slab
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Architectural Works
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Mechanical Works
Lump Sum Prices for Mechanical Items
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.9.1 through 2.3.9.9
Automatic Self Cleaning Stainers
Facility Nos. 73
9C
Civil Works
Unit Prices for the following Items:
Concrete Works
Unit Price for foundations including equipment pads
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 34 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.10.2
Tonnes 15
2.3.10.3 L.S. 1
L.S. 1
2.3.11
2.3.11.1 M
3
210
2.3.11.2
Tonnes 15
2.3.11.3 L.S. 1
2.3.11.4 L.S. 1
2.3.12
2.3.12.1
M
3
7150
2.3.12.2
Tonnes 800
2.3.12.3
L.S. 1
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.10.1 through 2.3.10.3
Sodium Hypochlorite Area
Facility Nos. 73
9D
Civil Works
Unit Prices for the following Items:
Concrete Works
Unit Price for foundations, grade beams and grade slab
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Mechanical Works
Lump Sum Prices for Mechanical Items
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.11.1 through 2.3.11.4
C.W. Inlet Structure and Culvert
Facility Nos. 74
9A
Civil Works
Unit Prices for the following Items:
Concrete Works
Unit Price for foundations, retaining walls, beams,
columns, grade slab, culvert walls and slabs
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Miscellaneous
Lump Sum price for designing, furnishing and
construction of permanent sheet pile, vanes, sill trap
including bolts, struts, painting and cathodic protection,
as shown in drawings listed in Exhibit E
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 35 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.12.4 L.S. 1
2.3.12.5 L.S. 1
2.3.12.6
L.S. 2
2.3.12.7
L.M 200
2.3.12.8 L.S. 1
2.3.12.9 L.S. 1
2.3.13
2.3.13.1 M
3
4650
2.3.13.2
Tonnes 600
2.3.13.3
L.S. 1
2.3.13.4 L.S. 1
2.3.13.5 L.M 200
2.3.13.6 L.S. 1
2.3.14
Lump Sum Prices for Mechanical Items
Sub Total of items 2.3.12.1 through 2.3.12.9
Mechanical Works
Electrical Works
Lump Sum Prices for Electrical Items
Lump Sum Price For Security Bars
Unit Price for Guardrails, including toe plates.
Lump Sum Price For wrip wrap
Lump Sum Price For flooting booms and warning as in
indicatrd in drawings in Exhibit E
C.W. Discharge Structure and Culvert
Facility Nos. 74
9B
Civil Works
Unit Prices for the following Items:
Unit Prices for the following Items:
C.W. Discharge Seal Well
Facility Nos. 74
9C
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Concrete Works
Unit Price for foundations, slab, top slab and walls
Reinforcing Steel
Lump Sum price for designing, furnishing and
construction of permanent sheet pile including bolts,
struts, painting and cathodic protection, as shown in
drawings listed in Exhibit E
Miscellaneous
Civil Works
Electrical Works
Lump Sum Prices for Electrical Items
Lump Sum Price For wrip wrap
Unit Price for Guardrails, including toe plates.
Sub Total of items 2.3.13.1 through 2.3.13.6
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 36 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.14.1 M
3
1650
2.3.14.2
Tonnes 165
2.3.14.3
L.M 110
2.3.14.5 L.S. 1
2.3.15
2.3.15.1 M
3
40
2.3.15.2
Tonnes 4
2.3.15.3 L.S. 1
2.3.16
2.3.16.1 M
3
380
2.3.16.2
Tonnes 25
2.3.16.3 L.S. 1 Lump Sum Prices for Electrical Items
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Waste Water Collection Basin
Facility Nos. 77
9
Electrical Works
Civil Works
Unit Price for Tank foundations, walls and top slab
Reinforcing Steel
Concrete Works
Sub Total of items 2.3.14.1 through 2.3.14.5
Unit Price for Ladders, Handrails and Guardrails,
including toe plates.
Unit Prices for the following Items:
Demineralized Water Storage Tanks
Electrical Works
Lump Sum Prices for Electrical Items
Facility Nos. 76
1 - 2
Civil Works
Structural Steel
Concrete Works
Unit Price for foundations, walls and top slab
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Reinforcing Steel
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.15.1 through 2.3.15.3
Unit Prices for the following Items:
Concrete Works
Unit Price for Tank foundations
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 37 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.17
2.3.17.1
M
3
125
2.3.17.2
Tonnes 11
2.3.17.3 L.S. 1
2.3.18
2.3.18.1
M
3
190
2.3.18.2
Tonnes 15
2.3.18.3 Tonnes 25
2.3.18.4
Tonnes 6
2.3.18.5 Tonnes 4
2.3.18.6
M
2
200
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Unit Price for foundations, grade beams, grade slab,
column pier and roof beams
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Structural Steel
Civil Works
Facility Nos. 92
9A
Lump Sum Prices for Electrical Items
Concrete Works
Sub Total of items 2.3.17.1 through 2.3.17.3
Hydrogen Generation Building and Storage Area
Unit Prices for the following Items:
Unit Price for Tank foundations including equipment pad
and curbs
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Unit Prices for the following Items:
Sub Total of items 2.3.16.1 through 2.3.16.3
Closed Cooling Water Equipment
Facility Nos. 78
1 - 2
Civil Works
Concrete Works
Electrical Works
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 38 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.3.18.7
L.S. 1
2.3.18.8 L.S. 1
2.3.18.9 L.S. 1
2.3.19
2.3.19.1
M
3
55
2.3.19.2
Tonnes 4
2.3.19.3 Tonnes 7
2.3.19.4
Tonnes 1
2.3.19.5 Tonnes 1
2.3.19.6
M
2
200
2.3.19.7 L.S. 1
2.4
2.4.1
2.4.1.1 L.S. 1
Unit Price for 2" (50 mm) depth, 18 gauges (1.2 mm) or
equivalent thickness galvanized steel deck.
Electrical Works
Facility Nos. 81
9
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.19.1 through 2.3.19.7
Structural Steel
Unit Price for Beams (Gr. A50) - painted.
Unit Price for Columns (Gr. A50) w/Base Plate and/or
Splice Plate - painted.
Unit Price for Bracing (Gr. A50) - painted (WT or W).
Lump Sum Prices for the following Items:
Civil Works
Ancillary Facilities
Office Building
Concrete Works
Unit Price for foundations including equipment pads and
column piers
Reinforcing Steel
Unit Price for delivering, fabricating and installation of
reinforcing steel from 10 mm, to 32 mm, bars.
Foam Equipment
Facility Nos. 96
9
Civil Works
Unit Prices for the following Items:
Lump Sum Prices for Mechanical Items
Electrical Works
Lump Sum Prices for Electrical Items
Sub Total of items 2.3.18.1 through 2.3.18.9
Architectural Works
Lump Sum Prices for Architectural Items, as specified in
Desing Criterial for Architectural Works 10063-9-3DR-
A01-00001
Mechanical Works
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 39 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.4.1.2
L.S. 1
2.4.1.3 L.S. 1
2.4.1.4 L.S. 1
2.4.2
2.4.2.1 L.S. 1
2.4.2.2
L.S. 1
2.4.2.3 L.S. 1
2.4.2.4 L.S. 1
2.4.3
2.4.3.1 L.S. 1
2.4.3.2
L.S. 1
2.4.3.3 L.S. 1
2.4.3.4 L.S. 1
2.4.4
2.4.4.1 L.S. 1
Mechanical Works
Sub Total of items 2.4.3.1 through 2.4.3.4
Facility Nos. 82
9C
Lump Sum Prices for the following Items:
Civil Works
Electrical Works
Sub Total of items 2.4.1.1 through 2.4.1.4
Lube Oil Storage Structure
Warehouse Building
Facility Nos. 82
9A
Lump Sum Prices for the following Items:
Civil Works
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Sub Total of items 2.4.2.1 through 2.4.2.4
Electrical Works
Mechanical Works
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Electrical Works
Mechanical Works
Lump Sum Prices for the following Items:
Civil Works
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Workshop Building
Facility Nos. 82
9B
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 40 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.4.4.2
M
2
600
2.4.4.3
L.S. 1
2.4.4.4 L.S. 1
2.4.4.5 L.S. 1
2.4.5
2.4.5.1 L.S. 1
2.4.5.2
L.S. 1
2.4.5.3 L.S. 1
2.4.5.4 L.S. 1
2.4.6
2.4.6.1 L.S. 1
2.4.6.2
L.S. 1
2.4.6.3 L.S. 1
2.4.6.4 L.S. 1
2.4.7
Lump Sum Prices for the following Items:
Civil Works
Electrical Works
Facility Nos. 84
9
Sub Total of items 2.4.6.1 through 2.4.6.4
Sub Total of items 2.4.5.1 through 2.4.5.4
Fire Fighting Station
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Mechanical Works
Electrical Works
Sub Total of items 2.4.4.1 through 2.4.4.5
Main And Secondary Security Office
Lump Sum Prices for the following Items:
Civil Works
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Mechanical Works
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Unit Price for Single Skinned, Un-Insulated Metal
Corrugated Sheet Panels for walls and roofs, including
accessories, flashing, sealant, additional steel supports,
coating, etc, per Technical Specification 10063 99999-9-
3P SS-ATPR-00001, and standard drawings 99999-9-A3-
0000-00002, and in accordance with Architectural
Design Criteria Specification 10063-9-3DR-A01-00001,
Item No. 4.3, and 4.4.1.
Facility Nos. 83
9A - 9D
Gasoline Station
Facility Nos. 85
9A
Lump Sum Prices for the following Items:
Mechanical Works
Electrical Works
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 41 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.4.7.1 L.S. 1
2.4.7.2
L.S. 1
2.4.7.3 L.S. 1
2.4.7.4 L.S. 1
2.4.8
2.4.8.1 L.S. 1
2.4.8.2
L.S. 1
2.4.8.3
L.S. 1
2.4.8.4
L.S. 1
2.4.9
2.4.9.1 L.S. 1
2.4.9.2
L.S. 1
2.4.9.3
L.S. 1
2.4.9.4
L.S. 1
2.4.10
2.4.10.1 L.S. 1
2.4.10.2
L.S. 1
2.4.10.3 L.S. 1
Civil Works
Sub Total of items 2.4.8.1 through 2.4.8.4
Toilet Facility Building
Lump Sum Prices for the following Items:
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Electrical Works
Facility Nos. 91
9C/9D/9E/9F
Sub Total of items 2.4.7.1 through 2.4.7.4
Mechanical Works
Civil Works
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Electrical Works
Facility Nos. 91
9A - 9B
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Civil Works
Sanitary Lift Station
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Lump Sum Prices for the following Items:
Mechanical Works
Mechanical Works
Electrical Works
Construction Buildings
Sub Total of items 2.4.9.1 through 2.4.9.4
Facility Nos. 93
9
Lump Sum Prices for the following Items:
Civil Works
Mechanical Works
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 42 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.4.10.4 L.S. 1
2.4.11
2.4.11.1 L.S. 1
2.4.11.2
L.S. 1
2.4.11.3 L.S. 1
2.4.11.4 L.S. 1
2.4.12
2.4.12.1 L.S. 1
2.4.12.2
L.S. 1
2.4.12.3 L.S. 1
2.4.12.4 L.S. 1
2.5
2.5.1
L.S. 1
2.5.2
L.S. 1
2.5.3
L.S 1
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Architectural Works: As specified in Design Criteria for
Architectural Works 10063-9-3DR-A01-00001
Civil Works
Facility Nos. 99
9B - 9L
Mechanical Works
Electrical Works
Sub Total of items 2.4.12.1 through 2.4.12.4
Civil Works
Lump Sum Prices for the following Items:
Miscellaneous Mechanical Works
Guard Dormitory Building
Lump Sum Prices for the following Items:
Guard Towers And Wall Fence
Mechanical Works
Electrical Works
Sub Total of items 2.4.11.1 through 2.4.11.4
Facility Nos. 99
9A
Electrical Works
Sub Total of items 2.4.10.1 through 2.4.10.4
Traveling screens and screen wash system.
Lump Sum Prices for Traveling Water Screens and
screen wash system in accordance with Technical
specification 10063-9-3PS-MLST-00001
Bar screens and trash racks.
Lump Sum Prices for Bar screens and trash racks in
accordance with Technical specification 10063-9-3PS-
MLST-00002
Fire hydrants and post indicator valves
Lump Sum Prices for Fire hydrants and post indicator
valves in accordance with Technical specification 10063-
9-3PS-PY22-00001
Lump Sum Prices for the following Items:
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 43 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.5.4
L.S 1
2.5.5
L.S 1
2.5.6
L.S 1
2.5.7
L.S 1
2.5.8
L.S 1
2.6
L.S 1
2.7
L.S 1
2.8
L.S 1
2.9
L.S 1
2.10
L.S 1
sanitary sweage Lift station equipments
Total Sum Price for furnishing of General Tools and
Equipment as specified in Specification No. 10063-9-
3PS-C00Z-00102 Attachment G
Total Sum Price for furnishing of Electrical Shop
Equipment List as specified in Specification No. 10063-9-
3PS-C00Z-00102 Attachment E
Total Sum Price for furnishing of Maintenance Shop
Equipment as specified in Specification No. 10063-9-
3PS-C00Z-00102 Attachment F
Turbine circulating pump house bridge crane
Lump Sum Price for Turbine building bridge crane in
accordance with Technical specification 10063-9-3-PS-
MJKG-00002
Lump Sum Price for sanitary sweage Lift station
equipments in accordance with Technical specification
10063-9-3-PS-MPGL-00001
Turbine building bridge crane
Lump Sum Price for Turbine building bridge crane in
accordance with Technical specification 10063-9-3-PS-
MJKG-00001
dredge system for intake
Lump Sum Price for dredge system for intake in
accordance with Technical specification 10063-9-3-PS-
MQ00-00001
Fire and jockey pumps
Total Sum Price for furnishing of I & C Shop Equipment
as specified in Specification No. 10063-9-3PS-C00Z-
00102 Attachment D
Lump Sum Price for Fire and jockey pumps in
accordance with Technical specification 10063-9-3-PS-
MPGJ-00001
Total Price for furnishing of Shop Equipment List, as
specified in Specification No. 10063-9-3PS-C00Z-00102
Attachment C
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 44 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
2.11
L.S 1
2.12
L.S 1
6.0
6.1
L.S
6.2
L.S
6.3 Spare CTG Transformer (Optional)
Facility No. 33 9
Civil Works
Lump sum price for Owners recommended operational
spare parts. Tenderer shall complete the unit price
breakdown for this lump sum item on Exhibit C, Section
5, Schedule N, Owners Recommended Operational
Spare Parts Price Breakdown (Option open for two years
after execution of the Contract).
Lump sum price for Owner's recommended list of
operational spare parts for two (2) years. Tenderer shall
provide a unit price breakdown for this lump sum item
indicating the quantity and description of the spare parts
recommended in Exhibit C, Section 5, Schedule O
entitled Tenderers Recommended Operational Spare
Parts Price Breakdown.
(Option open for two years after execution of the
Contract).
OPTIONAL ITEMS
4.0
PROVISIONAL SUM
Tenderer to enter an amount equal to ten percent (10%)
of Item 3.0
5.0
TOTAL TENDER PRICE
(State Total Tender Price in words and figures)
Total of Items No. 3.0 and 4.0
3.0
TENDER PRICE
(without Provisional Sum)
(State Tender Price in words and figures)
Subtotal of Items 2.1 through 2.12
Lump sum price for Temporary construction offices
furniture as specified in Specification No. 10063-9-3PS-
C00Z-00102 Attachment H
Lump sum price for Computers, copiers, printers,
plotters, data show and cad stations as specified in
Specification No. 10063-9-3PS-C00Z-00102 Attachment
I
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 45 of 46
Rev. 0
Schedule A - Tender Prices for Giza North
1500 MW Combined Cycle Power Project
Item No.
Unit Quantities LC FC LC FC % Engineering
% Labor &
Equipment
% Material Description
Total Tender Price Unit Prices
6.3.1
L.M 690
6.3.2
M
3
860
6.3.3
Tonnes 120
6.3.4
L.S. 1
6.3.5
L.M 90
6.3.6 L.S. 1
Unit Price for reinforcing steel from 10 mm, to 32 mm,
bars.
Reinforcing Steel
Unit Price for spare Combustion Turbine Transformers
foundations including fire walls.
Unit Price / Lump Sum Prices for the following Items:
Piling Works
Unit Price for designing, furnishing, installing and testing
of production piles (diameter will be provided later).
Concrete Works
Lump sum price for Designing, Furnishing, and
construction of chain link fence
Electrical Works
Lump Sum Prices for Electrical Items
Miscellaneous Items
Lump Sum Price for Designing, Furnishing, and Placing
of Crushed Stones in the Transformer Pits
Tender No. 10063 - CP-102
Exhibit C
Section 5 - Schedule of Quantities and Prices
Schedule A - Schedule of Quantities and Prices
Giza North Combined Cycle Power Plant
Tender Prices
Page 46 of 46
Rev. 0

Das könnte Ihnen auch gefallen