Machhakuta Coal Block

Developer Mahaguj Collieries Limited , a JV of MSPGCL and GSECL


Mine Capacity 30MTPA
Location Talcher coalfields,Chhendipada,Angul,Orissa
Geological Reserve 1400.65 Million Tonnes (considered for executlon-1231.88 MT),Mineable Reserve1170.34 Million tonnes
Number of seams 24
Mode of Implementation OC
Stripping ratio ( m3 / tonne) 2.5:1
Life of mine 46 years including construction period (2-years)
Grade of Coal B/C/D/E/F/G
Estimated cost Rs 3400 crores
Type of mining Opencast by shovel dumper combination
Month of achieving rated capacity -
Man Power 2000 (Mine : 1800 & Coal Washery: 200)
End Use for power generation at linked power plants at Koradi, Chandrapur, Parli, Paras and Bhusawal in Maharashtra
and Ukai and Wanakbori in Gujarat
Commercial Production -

Approvals and Clearances
S.
No.
Approval Particular
Date of
Approval
1.
Approval of mining plan
Accorded
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
1 of 18 11/1/2012 10:53 AM
2.
Environmental clearance by MOEF
yet to be
achieved
3.
Forest land clearance from MOEF
Yet to be
achieved

Back Ground:
Ministry of Coal (MOC) has allotted Machhakuta coal block on February 6, 2006 to Maharashtra State Power Generation Company Limited (MSPGCL) and
Gujarat State Electricity Corporation Limited (GSECL) for developing an opencast coal mine for power generation at linked power plants at Koradi, Chandrapur,
Parli, Paras and Bhusawal in Maharashtra and Ukai and Wanakbori in Gujarat.Mahaguj Collieries Limited (MGCL), a Joint venture of MSPGCL and GSECL
signed a MOU on December 30, 2005 to extract coal from Machhakuta Coal Block, Talcher Coalfields, Machhakuta, Tehsil Chhendipara, District Angul,
Orissa.The total estimated cost of the integrated project is about Rs. 3400 Crores.
Salient Features of Coal Mine:
Coal Block Area 2043.00-ha
Lease Period 30-years
Ultimate Depth 320-m
Total Over Burden Generation
2926.52 million m3 (External 1-408.70- million m3, Internal -2517.82- million m3)
Upto 7th year only external dumping. From 8th to 16th year OB will be dumped internally as well as externally. Concurrent
backfilling will start from 17th year of operation. From 20th year re-handling of external dump will also start till 39th year of
operation
Total External Dump Area,
Height l and overall slope
526.46-ha, 90-m in three stages of 30-m each. Around 26
Average Seam Gradient 3-5
Maximum Bench Height 13-16-m
Bench Width Over Burden: 22-42-m Coal: 22-40- m
Water Requirement for Mine
Operation
6800-m3/day excluding 7200-m3/day for Washery
Mine Discharge Till mine discharge Is available, ground water will be used for mining as well as washery projects
Power Requirement and
Source
38-MW from Rengali sub-station, GRIDCO (22-km)
Manpower Requirement Total: 2000 (Mine : 1800 & Coal Washery: 200)
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
2 of 18 11/1/2012 10:53 AM

Location MAP
Study Area MAP (10-KM Radius)
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
3 of 18 11/1/2012 10:53 AM


Locational details:
Particulars Details
Nearest Highway
NH-42(42-km, SE)
SH-63 (2.0-km, E)
Nearest Railway Station Jarpada (20-km), Angul (42-km, SE)
Nearest Air Port Bhubaneswar (250-km, S)
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
4 of 18 11/1/2012 10:53 AM
Nearest Major Town Chhendipada (5-km, E)
Reserved / Protected Forest
Debinagar PF (adjacent, S), Chhendipada RF (1.6-km,E),
Kanloi PF (3.0-km, W), Dungapal PF (6.5-km,NW),
Kankurupal RF (7.7-km,ENE), Nunmati PF (7.9-km.NW),
Kosala PF (8.1-km, SE)
National Parks, Wildlife Sanctuaries, Biospheres, Tiger Reserves, Elephant Habitat/Reserves None In 15-km
Water Bodies
Baosajura nala within ML area
Aunli river (2.6-km,NNW)
Gauduni nala (4.3, E)
Nuhurani nadi (5.9,NW)
Batshili / Singhoria nala (7.0-km, SSE)
Tikra river (8.6-km,NNE)
Other Mines or Industries
Chhendipada OCP (0.5-MTPA Capacity) of MCL
(5.0-km.SE)
Socio-Economic Factors
3531-families will be relocated In a phased manner,
compensation will be as per R&R Policy, 2006 of Govt. of
Orissa/National R&R Policy

Details of Machhakuta Coal Block:
Total Project Area and ML
Area
3023.00-ha and 2103.73-ha Approval of the concerned authorities will be obtained for diversion of
forest land and agricultural land as per law
Forest Land 53.0591-ha
N on-Forest Govt Land 321.0496-ha
Total Government Land 374.1087-ha
Total Private Land 2646.6913-ha
Villages In Mine Lease Area Bagadia, Machhakuta, Ghutuilposi, Sapoinali, Basantpur, Podapada, Simllipal and Machhakuta jungle
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
5 of 18 11/1/2012 10:53 AM
Co-ordinates of Coal Block
Elevation
21 06'26" N 21 04'09"N 84 48' 36" E 84 47' 04"E 21 03'U"N 21 05 19" N 84 50'18 E
8450'22"E 145-m(NE}-210-m(SW)
Co-ordinates of Coal
Washery
21 02'50" N 84 49 03" E
21 03' 22" N 84 50' 10 "E (Elevation: 206-m)
Block Boundaries
East Western boundary of Battarani West Block
West New Patrapada Block by Balshi nala /Shagarhia nala
North District road from Chhendipada to Nuagaon and southern boundary of Mahanadi Block
South Surface trace of major fault F1-F1
Present Land Use (ha)
Government Land (Forest & Non-Forest Land) 374.1087
Forest Land 53.0591
Non-Forest Land 321.0496
Private Land 2648.8913
Total Project Area (ha) 3023.0000
Details of Projects Land Requirement (ha):
Particulars Forest Non-Forest Total
Mine Excavation 15.22 2088.12 2103.34
Land required for Safety Zone 0.71 49.86 50.57
External Dumps 14.95 511.51 526.46
Infrastructure including Work Shop, Project Office, Coal
Handling Plant, Railway Corridor
22.1791 203.4809 225.66
Coal Washery (30-MTPA Capacity) - 87.00 87.00
Rationalization of Boundaries - 29.97 29.97
Total Project Area (ha) 53.0591 2969.9409 3023.00
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
6 of 18 11/1/2012 10:53 AM
Proposed Production Programme:
Year Coal Production (in million tonnes) OB Production (in million m3) Stripping Ratio Cum / tonne
1st - - -
2nd - - -
3rd 2.0 7.54 3.77
4th 7.0 28.73 4.10
5th 14.0 36.84 2.63
6th 22.0 49.60 2.25
7th 30.0 82.15 2.74
8th year to end of Mine Life 1095.34 2721.66 2.49
Total 1170.34 2926.52 2.50
Grade-wise Coal Reserves:
Coal Grade Reserves (Million Tonnes)
B 1.58
C 10.81
D 92.85
E 227.06
F 497.35
G 340.69
Total 1170.34
Flow Sheet - Coal Mining:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
7 of 18 11/1/2012 10:53 AM
Topographical Plan-Mine Lease Area:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
8 of 18 11/1/2012 10:53 AM
Mine Lease Land Use Pattern:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
9 of 18 11/1/2012 10:53 AM
Geological Plan:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
10 of 18 11/1/2012 10:53 AM
Surface Plan of Mine Lease Area:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
11 of 18 11/1/2012 10:53 AM
Final Stage Dump Plan:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
12 of 18 11/1/2012 10:53 AM
Post Mining Landuse Plan:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
13 of 18 11/1/2012 10:53 AM
Coal Washery- Plant Layout:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
14 of 18 11/1/2012 10:53 AM
Process Flow Sheet - Coal Washery:
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
15 of 18 11/1/2012 10:53 AM
Salient Feature of Coal Washery:
Total Rated Capacity 30-MTPA (ROM Coal)
Washery Capacity 425 TPH capacity of four parallel circuits of three identical units (each-10-MTPA capacity)
Land Requirement 87-ha (Non-Forest Land)
Capital Cost Rs.265 Crores
Process Wet process comprising crushing, screening, washing and materials handling
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
16 of 18 11/1/2012 10:53 AM
Clean Coal 21.6-MTPA (Ash Content: About 32%)
Coal Rejects and Fines 8.4-MTPA (Ash Content: About 60%)
Shifts per day Three
Power Requirement &
Source
17 MVA from Rengali sub-station, GRIDCO
Water Requirement 7200-m3/day
Wastewater Generation
Washery wilt be designed with closed water circuit, process water clarified in the thickener/slime ponds & circulated back in
process, zero effluent discharge.
Mode of Transport Coal transportation from CHP to washery by closed belt conveyor and washed coal to end users by rail
Railway Siding 20-km railway track to be laid up to Jarpada station (Angul - Sambalpur)
Washery Process
Raw Coal Receiving, Crushing and Storage Section
Receiving ROM coal through CHP and stocking in two stock yards of 25,000 Tonnes capacity each
Transportation of ROM coal to hoppers (2 no) of 1000 T capacity
Conveying of (-)100 mm raw coal by two parallel belts of 1200-mm width & 1000 TPH capacity each to screen-cum-crusher house to crush below
50-mm size & conveying to washery building
a.
Washery Section
Screening of (-) 50 mm raw coal at 13-mm & washing of 50-13 mm size fraction in two- product electronically controlled jigs to produce clean coal &
rejects
b.
Beneficiation & Recovery of Fines
Separation of coarser fines (-0.5 mm) from slurry in hydrocylones. Dewatering underflow slurry from hydrocylones in high frequency screens
Thickening or overflow slurry from hydrocylones in two 25 m dia thickeners.
Dewatering of thickened slurry in two nos. belt filter press
Recirculation of under & over flow waters from thickener / slime ponds in washery circuit
c.
Loading of Washed Coal
(-13mm) coal fraction and coarser fines will be mixed with & then conveyed to clean coal stock yard
d.
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
17 of 18 11/1/2012 10:53 AM
Reclaiming & conveying clean coal from stock pile to loading point through Rapid loading system for dispatch by Rail
Disposal of Rejects
Conveying of rejects to 2 nos. of hoppers of 300 tonne capacity each for onward use in rejects based power plant
e.
profile details of Machhakuta coal block http://www.infraline.com/coal/captive/machhakuta.aspx
18 of 18 11/1/2012 10:53 AM