Sie sind auf Seite 1von 4

GAO REPORT (GAO-10-119, OCTOBER 2009) TO CONGRESS: ARMY BODY ARMOR TESTING:

COMPARISON OF GAO CONCLUSIONS & RECOMMENDATIONS,


DOD COMMENTS, AND GAO RESPONSES TO DOD COMMENTS

GAO Conclusions/Recommendations DOD Comment/Position GAO Response to DOD Comment

1. Questionable if Army met its FAT objectives 1. GAO report points out some weaknesses 1. Several deviations to testing protocols call
for armor designs fully meeting Army and discrepancies in testing, but findings have testing results into question. Until independent
requirements before armor purchased no significant impact on test results and expert evaluates impact of deviations on testing,
subsequent contracting actions. Do not concur DOD can’t be assured plates that passed testing
-- Observed several instances in which actual PDM and FAT may not have achieved testing can defeat the threat.
test practices deviated from established test objectives
protocols -- DOT&E led the integrated product team for
--PDM: Army followed “deliberative internal testing and approved test plans, but when GAO
-- Four of five designs that passed FAT would process,” consulted with DOT&E, and was at ATC for PDM and FAT we did not observe
have failed either during PDM or FAT if modified contract solicitation for PDM to use DOT&E monitoring testing beyond incidental
established protocols has been fully followed point of aim for measuring back-face visits during VIP events and other demonstrations
deformation. Did not bias test results. Design
-- It’s possible deviations had no significant models passed in accordance with modified --PDM: Disagree with DOD/Army statement that
net effect or may have resulted in armor being solicitation PDM testing achieved objectives: (1) Test
tested to more rigorous standard Protocols called for measurement of back-face
--FAT: Achieved objective of verifying deformation at deepest point of depression in clay
-- Also possible some deviations may have contracted vendors could produce plates that backing. (2) DOD-Army claim solutions passed
resulted in armor being tested to less stringent passed PDM in full-rate capacity because protocols were modified, but this
requirement than required overlooks Army had to modify solicitation because
--Multi-Phase Test concept included PDM, it deviated from testing protocols laid in out
-- Unable to determine full effect of FAT, and extended ballistic testing. Army purchase descriptions. Army Research Lab and
deviations—can only be made by thorough refined procedures lessons learned in PDM for NIJ-certified labs use benchmark process of
assessment of test data by independent FAT measuring back-face deformation at deepest point,
ballistics testing experts not point of aim.

-- IVO uncertainty and critical need for --FAT: Restates FAT may not have achieved its
confidence, Army would take unacceptable objectives, because of questions regarding scoring
risk to field designs without additional steps to methods. Two solutions that passed FAT would
gain needed confidence have failed if back-plate deformation had not been
rounded and had been scored as it was in PDM.
Third would have failed if a complete penetration
had been scored as stated in purchase description.
Recommendation 1: SECDEF should direct Non-concur. DOD maintains FAT objectives Disagree PDM and FAT achieved objectives.
Army to provide for independent evaluation of were achieved. DOD satisfied FAT was Found numerous deviations from protocols that
FAT results before armor is fielded under properly scored despite process discrepancies allowed solutions to pass that otherwise would
solicitation. GAO cited issues/deviations and documentation issues noted by GAO. have failed. Majority seem to make testing easier
associated with: DOD will review test processes, with “external to pass and favor vendors. NIJ-
assistance” in selected areas. DOD does not certified labs consistently proven to be capable of
believe NIJ-certified labs should be considered following Army test protocols. NIJ labs conducted
external experts to critique DOD policies and previous Army FAT and LAT. NIJ certification
procedures. DOD will continue to scrutinize includes independent peer review of controls, mgt
procedures and pursue more open practices, and lab practices. NIJ certification of lab
collaboration …primarily with PEO Soldier, and NIJ certification of body armor are two
ATEC, and DOT&E. different things.

-- Rounding of back-face deformation -- Non-concur. Procedure used by NIJ- -- DOD cited ASTM E-29 as basis for rounding
measurements: (Army was inconsistent: was certified labs since 1999. IPT agreed to use down, but this is not referenced in protocols.
not spelled out in testing protocols. common rounding-down method cited in Detailed test plans state solutions will incur a
Measurements were not rounded down to ASTM E-29 for FAT and subsequent LAT. penalty for deformation greater than 43mm. Army
nearest whole number in PDM, but were in Policy not prohibited by any DOD or NIJ did not round down in PDM, but did in FAT. This
FAT). Rounding down lowered requirements standard. favored vendors.
and favored vendors.

-- Scoring of complete penetration of a -- Non-concur. First layer behind plate serves -- DOD position not consistent with testing
plate: Tear in Kevlar fibers in rear of plate as a “witness plate.” If not penetrated—as protocols. No witness plate required to determine
appear to show evidence of perforation and determined by breaking of threads on first if penetration occurred. Do not state that
ATC found particles in soft backing material layer of soft armor—test is not scored as a “breaking of threads” is the criterion for
behind plate. Test protocols define complete complete penetration iaw PEO scoring criteria. determining penetration. Testing protocols, not
penetration as occurring when projectile, Breaking of a thread in deeper layers not a undocumented criteria, should be used in scoring
fragment, or fragment of armor material is penetration since force of impact can cause to determine penetration/results. Multiple
embedded or passes into soft undergarment deformation. Scorers can examine with observations and thorough inspection in soft armor
behind protective plates—not when threads are microscope. Three independent SMEs agreed in question revealed particles had penetrated at
broken. and scored as partial penetration. ATC SME least three Kevlar layers. Shot should have been
found only dust particles and discoloration. ruled a complete penetration.

-- Laser Scanner Certification: Was not -- Non-concur. Laser scanner provides -- Once properly certified, tested, and evaluated
properly performed—was certified to standard superior tool. Army’s TMDE Activity laser may eliminate human error. Maintains Army
that did not meet requirement of test protocols. conducted study leading to certification. used scanner as a new method to measure back-
Army testers said software modifications were Certification testing performed in both lab and plate deformation without adequate certification.
designed to change measurements reported by on actual range. Software upgrades did not Do not agree software upgrades did not affect
laser. Was certified to wrong standard and affect measurement in laser scanner—they measurement. Was told that upgrades made after
certification study was not performed in actual improved post-processing of data and FAT corrected software laser malfunction during
test environment using actual shots. DOD can’t enhanced graphical interface of system. subsequent LAT. Vendors say studies show laser
validate its assertions without side-by-side Upgrades had no effect on measurement overestimates back-plate deformation by about 2
comparison of laser with mechanical calipers process. millimeters.
-- Exposure of clay to cold, heavy rain: May -- Non-concur. Do not agree with GAO -- Exposure to cold, heavy rain may have had an
have affected test results during one day of statistical analyses. ATEC analyses show poor impact on test results. Supported by statistical
testing. Army, NIJ-certified labs, and clay performance in question was caused by analyses of test results and conversations with
manufacturer said water may contaminate clay, marginal performance against most formidable industry experts, including clay manufacturer.
change its chemical bonding, and cause rapid threat round, not exposure of clay to cold, Witnessed unusually high number of clay
and uneven cooling. heavy rain. Although this had no effect on test calibration failures during testing of plates from
results, ATC completed planned installations multiple vendors—not just example cited by
of new clay conditioning chambers inside Army. In addition to cold water’s effect on clay
ranges to preclude environmental interaction. bonding and temperature, Army lowered
temperatures of clay conditioning trailers, saying
ovens and clay were too hot. Failure rate of plates
were very high this day—of both complete
penetration and back-face deformation.

-- Improper clay conditioning and use of -- Partially Concur. Concurs using written -- On Nov 13, there were seven calibration drops
additional clay calibration drops: Army standard when first series of drops doesn’t pass not within specifications. Some boxes were
followed orally agreed procedures that specifications; non-concurs that failed clay discarded iaw testing protocols, but others were
deviated from test protocols. Used clay that blocks were used in testing. repaired, redropped, and used if they passed
had failed initial clay calibration test. Several All clay used passed calibration standard in second drop series. Calibration called for “a series
clay calibration drops were not within effect at that time. NIS does not address of drops” of one series of three drops, not multiple
specifications. Protocols only allow for one specifically the issue of repeated test, but series of three drops. An external entity needs to
series of drops per clay box, but additional would recommend only one series of drops for evaluate the impact of Army practice on FAT
series of drops were used when first series clay calibration—but this is not a NIJ standard. results.
were outside specifications. DOD will partner with NIST to conduct
experiments to improve understanding of clay
performance.

Recommendation 2: Army should document -- Concur. DOD recognizes need for No comment
all key decisions made to clarify or change documentation and proper approvals to support
testing protocols. any significant change to testing protocols.
DOD will publish series of standard test
protocols for PPE, beginning with soft and
hard body armor. Will include detailed
documentation requirements and remediate
process discrepancies noted by the GAO.

Recommendation 3: Based on results of -- Partially concur. Inconsistencies in --Do not agree that inconsistencies in procedures
GAO-recommended external review of test procedures to implement test protocols in FAT did not alter test results. Observations clearly show
results, Army should determine if practices did not alter results. DOD recognizes need to that if measurement of deepest point of
that deviated from protocols will be continued update protocols necessitated by new deformation was used in PDM testing, two designs
and change the protocols to reflect revised technology and improved test procedures. that passed would have failed. If Army had not
procedures DOD will use DOT&E to promulgate standard rounded deformation measurements down in FAT,
test protocols across DOD. two designs that passed would have failed. Four of
five designs that passed PDM and FAT would have
failed if testing protocols had been followed.
Recommendation 4: Based on the results of -- Partially concur. DOD does not concur -- GAO does not agree that an adequate,
GAO-recommended external expert review of with GAO conclusion regarding independent certification of the laser measurement
test results, Army should reevaluate and inconsistencies and need to recertify the laser system and process was conducted. GAO continues
recertify laser scanner. measurement system. DOD does concur with to assert that the software changes added after
concept of an independent certification of the certification did affect the measurement system in
laser measurement system and processes. the laser.
States this was done with Army TM&DE
Agency calibration and CG ATEC certification
for use during Army testing. Software changes
reported by GAO did not affect measurement
system in the laser scanner.

Recommendation 5: Army should provide an -- Partially concur. DOD will conduct -- GAO agrees that a review conducted by panel of
external independent peer review of Aberdeen independent evaluation of ATC’s test external experts that also includes DOD members
Test Center’s body armor test protocols, protocols, facilities, and instrumentation by could satisfy its recommendation, however, to
facilities, and instrumentation. subject matter experts. DOD in discussion with maintain independence of the panel the DOD
NIST to form team of SMEs to review DOD members should not be composed of those
testing procedures. Review will be broad and personnel from organizations involved in the body
include measurement processes, clay armor testing (such as the DOT&E, the Army Test
conditioning, and other areas. DOD will Center, or PEO Soldier).
include experts from within the DOD as part of
this team.
Matter for Congressional Consideration:
DOD asserted issues GAO identified do not
alter the effects of testing. GAO maintains that
its analyses and findings provide sufficient
evidence to raise questions as to whether issues
it identified had an impact on testing results.
GAO continues to believe it is necessary to
have an independent external review of test
results and the overall effect of the testing
deviations on those results before armor is
fielded. Without independent review, FAT
results remain questionable, undermining
confidence of the public and those who rely on
armor for protection.

Congress should consider directing OSD either


to require independent external review of body
armor test results or that DOD officially amend
its testing protocols to reflect revised test
procedures and repeat FAT to ensure only
properly tested designs are fielded.

Das könnte Ihnen auch gefallen