Beruflich Dokumente
Kultur Dokumente
Further work will be conducted in the future to determine other sources of unaccounted dead
load. Mass corrections will be modified as necessary.
13
Error Screening Process
The most vital part of the development of the finite element model involves verifying the results
to ensure that the structure is being accurately represented. This involves checking the numerical
results, interpreting deflected shapes for compatibility as well as using structural engineering intuition
to ensure that the results make sense. Oftentimes, the results can be compared to previously computed
values if available. (Fisher, 1983)
Approximation of Axial Force in the Lift Span
After the lift span portion and floor system of the bridge were imported into SAP,
approximations were made about the axial forces in the top and bottom chord members. A simplifying
assumption was made to reduce the lift span into a simply supported beam as shown in Figure 16. The
bracing in the face of the truss was assumed to have infinite stiffness thus reducing the structure into a
2D face.
Using the model, the support reactions were applied from the SAP model, which are
represented by R. To put the beam into equilibrium, a uniformly distributed load, w, was spread over
the entire structure to put the beam into equilibrium. The moment diagram from this type of loading is
shown below in Figure 17. A constant height of 65 was assumed over the entire length of the beam.
This is the height from top to bottom chord on the real structure. This 65 acts as a moment arm
between the two chords as shown in Figure 18. By summing the forces about a point, the total axial
compression or tension in the chords could be solved.
Figure 17: Moment Diagram of Simply Supported Beam.
R = 636 kips
w = 2.39 kips/ft
= 533 ft
Figure 16: Approximate Analysis of a Simply Supported Beam.
R = 636 kips
14
Figure 18: Moment Arm Calculation for Approximate Analysis.
Table 1: Comparison of Axial Force in Chord Members for the Simply Supported Beam Approach.
A comparison of the approximate analysis values and SAP results can be found in Table 1. These
results are for axial force in the top and bottom chords. The approximate technique assumed equal
compression and tension in the top and bottom chords. The results were then compared to the SAP
model including the entire floor system. The results showed a major discrepancy in the bottom chord
member. This is due to the floor system acting to stiffen the entire lower portion of the structure. The
top chord member still remained consistent with the approximate analysis. To further validate this
trend, the floor system was removed from the bridge in the SAP model. The results were shown to
agree within 30%. The reduced values of the moment couple was due to the loss of dead load from the
floor system. At this stage in the model development, this was considered to be acceptable given the
amount of simplifying assumptions that were being made.
Approximation of Deflection in the Lift Span
Another form of approximate analysis was performed for the lift span portion of the bridge by
determining if the deflection in the model was reasonable. A simplification was made to reduce the
structure to a simply supported beam as shown in Figure 19. Figure 20 also shows a cross section view
of lift span of the bridge where the moment of inertia was calculated for each of the chord members.
The results of this analysis are shown in
Table 2.
Hand Calculation SAP with Floor
System
SAP without
Floor System
Top Chord (kips) 652 (c) 693 (c) 530 (c)
Bottom Chord (kips) 652 (t) 176 (t) 457 (t)
15
The hand approximate analysis was then compared to the SAP model and AASHTO allowable
deflection. The results agreed closely, but further investigation must be completed to verify these
results.
Table 2: Approximate
Analysis of Lift Span Deflection.
Knowing there is 44% of the actual load missing in the model, the deflections are expected to
increase. Since deflection is directly related to the distributed load, it is expected that the deflection will
increase by a factor of 1.81. This will still allow the deflection to satisfy the AASHTO limit.
Future Work
The future work of the project can be simplified into two categories. These are completion of
the model and the final design phase of the project. Further information about project scheduling may
be found in Appendix A: Project Schedule.
Model Development
Currently, the SAP model is at 90% completion. Two vital tasks must be completed to further
validate the model. The first is to perform an in-depth analysis of unaccounted dead weight of the
structure. The current dead weight of the lift span is 1400 kips, while the true dead weight of the span is
Hand Calculation SAP Model
AASHTO Allowable
Deflection (l/800)
2.8 2.9 8
Figure 19: Maximum Deflection of Simply Supported Beam.
Figure 20: Chord Member Cross Sectional Area Diagram.
16
known to be 2,536 kips. (Moon, Aktan, & Lowdermilk, 2010) Mass multipliers will be determined with
more confidence and assigned as necessary to the appropriate frame sections.
A mesh sensitivity study must be completed particularly for the shell elements of the deck. This
entails reaching a careful balance between discretization and computing time. The mesh will reach an
acceptable level of discretization at the point when further increase in shell elements yields no further
change in results.
Final Design Phase
After the performance of the model is validated, the final design stage can begin. During this
stage, a load rating as per AASHTO will be performed. This will ensure that the bridge currently rates as
it stands today. A load rating will then be performed per the American Railway Engineering and
Maintenance-of-Way Association (AREMA) loading configuration. At this point, the behavior of the
bridge under the train loading will be known and retrofits can be performed as necessary. The final
alignment of the tracks will be selected and construction costs will be determined.
17
Bibliography
Ash-Howard-Needles & Tammen. (1930). Burlington Bristol Bridge: Original Construction Drawings. New
York, New York.
DMJM Harris/AECOM. (2006, March). New Jersey Long-Range Transportation Plan 2030. Philadelphia,
Pennsylvania. Retrieved Novemeber 2011, 25
Fisher, T. A. (1983). Long-Span Bridge Computer Modeling. Journal Of Structural Engineering, 1402.
Goulet, J. A., Kripakaran, P., & Smith, I. F. (2009). Estimation of Modelling Errors in Structural System
Identification. Lausanna, Switzerland: cole Polytechnique Fdrale de Lausanne.
Howard-Needles-Tammen & Bergendoff. (1976). Burlington Bristol Bridge: Reconstruction of the Bridge
Deck. Fairfield, New Jersey.
Industrial Engineering Works. (1988). Deck Replacement at Beam and Truss Spans. Trenton, New Jersey.
Keystone Structure Steel Co. (1993). Burlington Bristol Bridge: Lift Span Deck Replacement. Newtown,
PA.
Moon, F. L., Aktan, A. E., & Lowdermilk, D. S. (2010). Model Experiment Correlation I. Philadelphia, PA:
Intelligent Infrastructure Systems.
Pennoni Associates. (2010). Burlington Bristol Bridge: In-Depth and Fracture Critical Member Bridge
Inspection Report. Haddon Heights, New Jersey.
18
Appendix A: Project Schedule
10/1/2011 11/30/2011 1/29/2012 3/29/2012 5/28/2012
Conduct Surveys
Collect Site Data
Proposal Preparation
Construct CAD Model of Truss
Construct CAD Model of Deck
Insert Section Properties
Progress Report Preparation
Select Alignment
Contact Permitting Agencies
Develop Operational Plans
Stakeholders Meetings
Phase 1 Phase 2 Phase 3
19
Appendix B: Tower Span Model
Figure 21: 2D CAD Model of Tower Span.
Figure 22: 3D CAD Model of Tower Span with Lateral Members.
20
Figure 23: 3D CAD Model of Tower Span with Floor System.
Figure 24: SAP Model of Tower Span.
21
Appendix C: Floor System Photographs
Figure 25: Lift Span during Bridge Opening. Figure 26: Underside of Lift Span.
Figure 28: Lift Span in Open Position.
Figure 27: Lift Span Guiderail.