Beruflich Dokumente
Kultur Dokumente
THIRD EDITION
2013
VOLUME 3
B2P_manual_05.indd 4
8/16/13 2:51 PM
THIRD EDITION
2013
VOLUME 3.1
B2P_manual_05.indd 5
8/16/13 2:51 PM
Overview
Abney & Auto Level Survey
2.4
2.5
2.6
2.7
2.8
2.9
need not be referenced for non-engineer designers, as all modular designs have already considered the following
codes and assumptions. For typical bridge project use, skip to Section 2: Bridge Design Process.
1.1
Minimum Freeboard
= 3.0 m (gorges)
Minimum Setback
Maximum Span
= 120 m
Design Sag
The Design Sag, B d , is assumed 5% throughout this manual. B d is a percentage value that must be
h sag , discussed later in this section.
Design Sag, B d is used in the Distance to the Lowest Point of Cable (f) calculation, which in turn is
considered to ensure proper freeboard above the High Water Level.
Note: while preparing for construction, the Hoisting Sag B h is used when calculating the Distance to the
Lowest Point of Cable (f). This allows for cable hoisting at a higher elevation than expected due to the
elastic stretch of the cable. No structural cable stretch is assumed, as cable is assumed repurposed.
= Span
25
2
= Q4B - H V measured from low side
16B d
d
Deck Width
= 1.0 m
Walkway Width
= 1.5 m
Design Loads
= 7850 kg/m3
= 2400 kg/m3
= 1900 kg/m3
= 900 kg/m3
= 1800 kg/m3
= 490 lb/cf
= 150 lb/cf
= 120 lb/cf
= 60 lb/cf
= 110 lb/cf
Dead Load
Actual Dead Load of the bridge to be based on material takeoff. For both the B2P Suspension and
Suspended bridges,100 kg/m (for 1m wide deck) is a reasonable assumption.
DL = 100 kg / m
Live Loads
Note: newer versions increase the design live load to 90 psf, a measure not adopted by B2P.
Distributed Live Loads:
Assuming 1.0 meter deck:
LL = 415 $ T 0.25 +
4.57
Y
L
DL + LL
DL + LL + WL
DL + WL
Steel Pipe:
f 'c = 15 MPa
f 'c = 10.3 MPa
fy = 240 MPa
Steel Reinforcing:
fy = 275 MPa
= 40 ksi
Timber:
fb = 3.96 MPa
= 575 psi
Material Properties
Concrete:
fv = 1.44 MPa
= 210 psi
= 3,000 psf
= 112 pcf
Soil:
= 33 degrees
Cable / Wire Rope
attained through load testing the cable at its section showing greatest wear.
1.2
Cable Analysis
Overview
in the main-span and backstays at full load. The increased sag at full load, decreases the overall tension in
the cables, thus decreasing the demand on the cables. Reference: Hanes Supply Catalog; Modulus of Elasticity for 6x19
IWRC, or other appropriate cable section.
The geometry of the cable between the two towers on a suspended bridge is that of a catenary cable. For
simplicity, the geometry can be assumed as a parabolic curve. The following equations and diagrams describe the
theory governing the geometry of the main span cables and the resulting forces.
Horizontal Tension:
Where:
Ph =
W c $ L2
(equal throughout cable)
8 $ h sag
Wc
= total distributed load
h sag = B d $ 100 = sag height (distance unit)
L
= span
Ph
cos (i)
Ptm =
Ph
cos (})
Ptb =
Pv = Pvm + Pvb
Cable Design
To determine the required number of cables, take the maximum tension in the cable per the above outlined
process, multiply by the factor of safety (minimum 3.0) and divide by the breaking strength of the cables available.
B2P provides a spreadsheet to assist in the determination of main cables. This topic is covered in greater detail in
Section 2.7 of this Volume.
Total Number of Cables Required:
= Maximum Calculated Tension x FS
The geometry of the layout is also critical for the tower, tier and foundation design, and should be considered
bearing capacity kairn of the foundation as the resultant force (R) must not exceed maximum allowable eccentricity.
Eccentricity is measured from the center of the tower. Equations dictating allowable eccentricity are as follows:
1.3
Anchor Analysis
Overview
This section describes the details of the deadman anchor design and associated assumptions. Rock anchor
design discussion is beyond the scope of this manual. Refer to licensed Professional Engineer for rock anchor
analysis support.
The anchorages secure the ends of the main cables and transfer the force into the ground. The direction of the
horizontal forces, which often results in large anchorage structures ideally, the design should utilize the ground
as much as practically possible i.e. be buried below ground, and a large mass of in-situ earth in front, to utilize the
passive resistance of the earth and thus increase the horizontal resistance.
Some of the general assumptions used throughout the design process that may be of interest to the Professional
Engineer verifying or otherwise modifying B2P modular designs:
Soil wall friction ( d
Friction on the base of the foundation and approach walls is considered ONLY when a compression
n = 0.30,
between the earth and these components is recommended
Soil is conservatively assumed to be sand and therefore assumed cohesionless (i.e. c = 0).
No consideration of earthquake design has been taken into account.
The forces acting on the anchor cause an active lateral pressure to develop behind the deadman (i.e. the earth
exerts a force on the anchor an additional force to the pull from the cable), and a passive pressure to develop
in front of the deadman (i.e. the anchor exerts a force on the earth the earth creates a resisting force to the pull
from the cables). Since soils have a greater passive resistance, the earth pressures are not the same for active
and passive conditions.
For a cohesion-less soil, the earth pressure theory of Rankine provides expressions for the active and passive
the lateral earth pressure to the vertical earth pressure or unit weight of the soil.
1 - sin (z)
K a = 1 + sin
1 + sin (z)
11 +
sin (z)
+ sin
Kp =
1 - sin (z)
(unitless)
(unitless)
1
Ka
2
H 12 [ kN
m ]
1
Kp
2
H 12 [ kN
m ]
The resultant forces on the anchor due to the pressures act at 1 the height from the base of the anchor, and are
3
given as:
Force due to Pa : F Q K aV = Pa $ L !kN $
10
F Q Ff V = W total $n
F (K p )
F Q K aV + Ph
1.5
If the water-table rises above the base of the deadman anchor, the unit weights of the soil and concrete must be
taken as buoyant unit weights i.e. the saturated unit weights of the soil/concrete minus the unit weight of water.
Depending on the duration of the submerged case, the factor of safety may be reduced. For a Temporary Case
(referring to a single event in a season), FS = 1.0. For a Long Term Case (referring to the entire rainy season), FS
must remain = 1.5. Seek support from a Professional Engineer for all saturated cases.
Anchor: Check Against Uplift
A check of the deadman anchor for safety against uplift is calculated by resolving the forces acting on the anchor
and ensuring that the vertical resisting forces are at least 1.5 times greater than the vertical driving forces (i.e. a
factor of safety of 1.5).
Factor of Safety (Uplift):
QW soil + W conc.V
Pv
1.5
If the water-table rises above the base of the deadman anchor, the unit weights of the soil and concrete must be
taken as buoyant unit weights i.e. the saturated unit weights of the soil/concrete minus the unit weight of water.
Depending on the duration of the Submerged Case, the factor of safety may be reduced. For a Temporary Case
(referring to a single event in a season, FS = 1.0). For a Long Term Case (referring to the entire rainy season, FS
must remain = 1.5).
1.4
Foundation Analysis
Overview
All of the vertical forces generated in the cables are transferred through the towers and tiers into the foundation,
in addition to the extra loading generated from the self-weight of the towers. To perform satisfactorily, the total
distributed load generated must not exceed the bearing capacity of the soil, also known as shear failure. The load
11
per unit area of the foundation at which shear failure in soil occurs is called the ultimate bearing
capacity ( q u ).
Some of the general assumptions used throughout the design process that may be of interest to the Professional
Engineer verifying or otherwise modifying B2P modular designs:
No consideration of earthquake design has been taken into account.
Design has been completed assuming foundations constructed on level ground.
Design has been completed assuming foundations are in non-saturated conditions. Where saturated
conditions are of concern, deduct the buoyant force of the soil.
Design Calculations
The allowable soil bearing capacity q allow is the maximum bearing stress that can be applied to the foundation
your soil. The designs in this manual assumes allowable soil bearing, q allow = 3,000 psf.
The maximum bearing stress ( q max ) is calculated by summing the total vertical load on the foundation (total
vertical tension at the towers plus the self weight of the foundation, tiers, and towers) and dividing by the area of
the foundation.
Maximum Bearing Stress: q = W foundation + W tiers + W towers + Vc
max
Total bearing area of Foundation
The allowable bearing capacity is calculated from the ultimate bearing capacity, using a factor of safety
of 2.0.
Factor of Safety (Shear):
1.5
q allowable
q max
2.0
1.6
12
Vdistributed = W c L
2
P
V po int = 2
W c L2
Maximum Moment Due to Distributed Load: M distributed = 8
Maximum Moment Due to Point Load:
PL
M po int = 4
All assume the structure is simply supported, 1m lenghts which is a conservative assumption.
Check against Bending Moment
To design both the crossbeams and the decking, the actual stress in the member due to bending must be less
than or equal to the allowable stress of the given material. Timber material properties for the actual types of
timber should be referenced from local suppliers. B2P assumes Fb = 3.96 MPa for allowable stress in bending.
Stress due to bending: fb
F b'
CfC
F bl = Fb C d C m C t C L C F C v C
ui C irC
CrcC
CcfC f
fu
Fb = allowable stress in bending
C d = load duration factor (assume 1.25)
C f = shape factor (assume 1.2)
Cm C
CL
= tmoisture
factor (assume 0.97 for moisture >19%)
=c other factors (assume 1.0)
Cffuu C i C r C
Cm Ct CL C F Cv C
fb = actual stress in bending
M
fb = Smax (where greater of M dist. or M po int is used)
2
S = Section Modulus = bd
6
Where:
fv
F v'
F vl = Fv C d C m C t C i
Fv = allowable stress in shear
C d = load duration factor (assume 1.25)
Cm C
CL
= tmoisture
factor (assume 0.97 for moisture >19%)
C m C t C i = other factors (assume 1.0)
fv = actual stress in shear
fv = V $ 3 (where greater of Vdist or V po int is used for rectangular
2bd
members)
13
1.7
Factors of Safety
Overview
1.8
Manual Limitations
The suspended bridge is intended for pedestrians, livestock and narrow transportation aids (bicycles,
wheelbarrows) capable of crossing on the 1.0 meter wide deck. Widening the deck up to 1.5 meters is possible
with further engineering of the anchor, tower and decking plans, but any additional width in excess of 1.50m risks
the inadvisable use by small cars. It is recommended that any bicycles, animals or motorbikes be walked across,
but all are considered acceptable for crossing.
Wood decking changes the deadload depending on the weight of the wood being used. If a steel deck is chosen,
the corresponding deadload also changes. Note that the original Helvetas Nepal design included the steel deck
Although the lateral wind loadings proportionally increase with increased span, there is a design limit of 120
meters without additional wind guy structures. The longitudinal rigidity of the bridge is compromised beyond 120
as two (2) additional cables and four (4) additional anchors are required. Contact Bridges to Prosperity for
Wind-guy Design guides and tools.
14
2.1
Overview
Designing the suspended cable bridge requires minimal technical background. The following section will provide
a step by step guide to designing a bridge following the completion of the site survey as outlined in Volume 2
Feasibility & Topographic Survey.
2.2
2.2
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.3
15
16
2.4
17
40
45
50
55
Span (m)
60
65
70
75
80
85
90
95
1.75 2.00 2.25 2.50 2.75 3.00 3.25 3.50 3.75 4.00 4.05 4.09 4.32 4.55 4.77 5.00 5.23
1.63 1.88 2.13 2.38 2.63 2.88 3.13 3.38 3.63 3.88 3.93 3.97 4.19 4.42 4.65 4.88 5.10
1.51 1.76 2.10 2.26 2.51 2.76 3.00 3.25 3.50 3.75 3.80 3.84 4.07 4.30 4.53 4.75 4.98
1.40 1.64 1.89 2.14 2.39 2.64 2.89 3.14 3.38 3.63 3.68 3.72 3.95 4.18 4.41 4.63 4.86
1.29 1.53 1.78 2.03 2.27 2.52 2.77 3.02 3.27 3.52 3.57 3.61 3.83 4.06 4.29 4.51 4.74
1.18 1.42 1.67 1.91 2.16 2.41 2.66 2.90 3.15 3.40 3.45 3.49 3.72 3.94 4.17 4.39 4.62
1.08 1.32 1.56 1.81 2.05 2.30 2.54 2.79 3.04 3.29 3.34 3.38 3.60 3.83 4.05 4.28 4.50
0.98 1.22 1.46 1.70 1.94 2.19 2.43 2.68 2.93 3.17 3.22 3.26 3.49 3.71 3.94 4.16 4.39
1.36 1.60 1.84 2.08 2.33 2.57 2.82 3.06 3.11 3.15 3.38 3.60 3.83 4.05 4.28
1.50 1.74 1.98 2.22 2.47 2.71 2.95 3.00 3.04 3.27 3.49 3.71 3.94 4.16
1.64 1.88 2.12 2.36 2.60 2.85 2.90 2.94 3.16 3.38 3.60 3.83 4.05
2.02 2.26 2.50 2.74 2.79 2.83 3.05 3.27 3.50 3.72 3.94
2.16 2.40 2.64 2.69 2.73 2.95 3.17 3.39 3.61 3.83
2.30 2.54 2.59 2.63 2.85 3.07 3.29 3.51 3.73
2.44 2.49 2.53 2.75 2.96 3.18 3.40 3.62
2.43 2.65 2.86 3.08 3.30 3.52
2.55 2.77 2.98 3.20 3.42
2.88 3.10 3.32
3.00 3.22
Verify adequate slope angle or distance from slope (Volume 2 Topographic Survey)
18
updated Freeboard value. If the Freeboard ( Fb ) exceeds minimum, move forward with design.
OKAY
19
2.6
1G60
2G60
3G60
1G120
2G120
3G120
anchors do not lend themselves to more than one tier. This is due to the short distance between the
anchor and the saddles, required due to sloped rock conditions. There are two sizes of drum anchors;
small and medium. Small (0 - 40 meters) and Medium (41 - 60 meters) anchors are included in 1D60.
Note: 60-120 meter projects in rock require design support from a Professional Engineer. A summary of
Drum Anchor Plans found in Volume 3 Part 2: Suspended Bridge Drawings are as follows:
0 - 60 m
2.7
1D60
20
Step 2
Input Breaking Strength values (in pounds) and desired number of cables (red text), as shown in the
following diagram.
Step 3
Modify combinations until desired deck width has value at least as long as bridge span (yellow).
Example
handrail cables. The span highlighted in yellow, beneath the 100cm deck width results in a span
less than our 60 meter span. Try again with 4 walkway cables and 2 handrail cables. The allowable
span shown is 64m, longer than our actual span, so this is acceptable.
crossbeam.
Step 4
Calculate quantity of cable. Refer to Section 3.1 Material Quantities, Cable & Clamps.
21
2.8
For a given span, geologic conditions and number of tiers, two (2) Abutment Tier & Anchor drawings must be
selected, one for each side of the river. The Tower drawing details the 1.0 meter deck width tower and is required.
Three (3) Decking drawings must be selected for either 3 or 5 walkway cables, with alternatives between
crossbeam nailers or no nailers respectively.
Abutment Tier & Anchor (Right and Left side required)
Gravity Anchors
0 - 60 m
1 Tier
0 - 60 m
2 Tier
0 - 60 m
3 Tier
61 - 120 m
1 Tier
61 - 120 m
2 Tier
61 - 120 m
3 Tier
Rock Drum Anchors
0 - 60 m
1 Tier
1G60
2G60
3G60
1G120
2G120
3G120
Tower
T1
3 walkway cables
5 walkway cables
W3.1
W5.1
W3.2
W5.2
1D60
Decking
Decking Plan
Decking Detail
With Nailer
3 walkway cables
5 walkway cables with Nailer
No Nailer
3 walkway cables No Nailer
5 walkway cables No Nailer
W3.3
W5.3
W3.4
W5.4
22
2.9
Include the following critical dimensions and select the following drawings;
Critical Dimensions
Span
Depth to anchor
Distance to back of anchor
Deck width
Free board from HWL
Sag (design and hoisting)
Height differential between abutments
2.10
Drawings
Right Side Anchor
Left Side Anchor
Tower
Decking Plan
Decking Section
Decking Detail
(G series)
(G series)
(T series)
(D series part 1)
(D series part 2)
(D series part 3)
Design Example
Point L Elevation (low side) = 100.0 meters
Point R Elevation (high side) = 102.0 meters
HWL = 96.5 meters
for a valley. Start by assuming one tier (1.0 meter tier height plus 0.4 meter saddle height above tier).
Span (L) = 60 meters
Elevation low side walkway saddle = 100m + 1.40m = 101.4m
Elevation high side walkway saddle = 102m + 1.40m = 103.4m
L
60
DH < 25 = 25 = 2.4 > 2.0
16B d
23
35
0.0
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
4.25
4.50
40
45
50
55
60
65
70
75
80
85
90
95
1.75 2.00 2.25 2.50 2.75 3.00 3.25 3.50 3.75 4.00 4.05 4.09 4.32 4.55 4.77 5.00 5.23
1.63 1.88 2.13 2.38 2.63 2.88 3.13 3.38 3.63 3.88 3.93 3.97 4.19 4.42 4.65 4.88 5.10
1.51 1.76 2.10 2.26 2.51 2.76 3.00 3.25 3.50 3.75 3.80 3.84 4.07 4.30 4.53 4.75 4.98
1.40 1.64 1.89 2.14 2.39 2.64 2.89 3.14 3.38 3.63 3.68 3.72 3.95 4.18 4.41 4.63 4.86
1.29 1.53 1.78 2.03 2.27 2.52 2.77 3.02 3.27 3.52 3.57 3.61 3.83 4.06 4.29 4.51 4.74
1.18 1.42 1.67 1.91 2.16 2.41 2.66 2.90 3.15 3.40 3.45 3.49 3.72 3.94 4.17 4.39 4.62
1.08 1.32 1.56 1.81 2.05 2.30 2.54 2.79 3.04 3.29 3.34 3.38 3.60 3.83 4.05 4.28 4.50
0.98 1.22 1.46 1.70 1.94 2.19 2.43 2.68 2.93 3.17 3.22 3.26 3.49 3.71 3.94 4.16 4.39
1.36 1.60 1.84 2.08 2.33 2.57 2.82 3.06 3.11 3.15 3.38 3.60 3.83 4.05 4.28
1.50 1.74 1.98 2.22 2.47 2.71 2.95 3.00 3.04 3.27 3.49 3.71 3.94 4.16
1.64 1.88 2.12 2.36 2.60 2.85 2.90 2.94 3.16 3.38 3.60 3.83 4.05
2.02 2.26 2.50 2.74 2.79 2.83 3.05 3.27 3.50 3.72 3.94
2.16 2.40 2.64 2.69 2.73 2.95 3.17 3.39 3.61 3.83
2.30 2.54 2.59 2.63 2.85 3.07 3.29 3.51 3.73
2.44 2.49 2.53 2.75 2.96 3.18 3.40 3.62
2.43 2.65 2.86 3.08 3.30 3.52
2.55 2.77 2.98 3.20 3.42
2.88 3.10 3.32
3.00 3.22
60
60
1
13
23
33
24
SECTION 3:
MATERIAL ESTIMATE
The following section details material quantity take-offs. This section is intended for use only with B2P suspended
3.1
3.2
Spacing
(mm)
102
114
121
132
144
160
160
171
Drop-Forge clamps
# of clamps
Torque (foot-lbs)
3
95
4
130
4
225
5
225
6
225
7
360
7
360
8
360
25
Suspenders (hangers)
- 2 x (Span + 1), minimum 10 mm ribbed rebar (#3), cut to 1.80 m length
Small/Medium anchor
(up to 60m span)
Large Anchor
(up to 120m span)
20mm z x 2.9 m
10mm z x 2.2 m
11
bent into square 0.5m per side
N/A
10mm z x 3.4 m
N/A
20mm z x 3 m
11
bent into square 0.8m per side
3
bent into U-shape for erection
hooks
3
bent into U-shape for erection
hooks
3.3
CONCRETE
This is to be used to calculate all concrete materials - cement, sand and aggregate
Masonry:
The numbers below are given to the 3G series and should be adjusted based on the drawing used. They also include the
2 bags poured in each tier and the capping of that tier.
Foundation
Tier 3
Tier 2
Tier 1
18 bags
16 bags
14 bags
12 bags
Towers (masonry)
Approach walls
Approach cap
8 bags
16 bags (for 2m height)
16 Bags
26
Poured concrete:
sand: aggregate) and should be revised when needed based on the materials available. The sum
voids between the coarse aggregate. The materials normally have 30 to 50% greater volume than
the concrete mix.
If accelerant is to be used to expedite the curing time, take care to note the affective 28 day strength
minimum time. It is recommended to error on the side of additional time for anchor pours. The
3.4
DECKING
Bridges to Prosperity is using wood decking when a sustainable source of wood is a viable option.
If you choose to use metal or plastic decking please research and design according to the material
you use.
width as the decking panels, and is attached to the top of a narrower cross-beam to increase the
and allows for a smaller crossbeam size while increases the total length of decking panels required.
Decking panels are cut to 3.0 meters for any span over 60 meters and preferably all spans. If the
bridge is shorter than 60 meter span, 2.0 meter decking panels are allowable. The total number of
decking panels is equal to [span divided by length of each board (either 2.0 or 3.0)] multiplied by
additional (Span plus one) meters of decking panels will be required, cut at 1.0 meters.
Quantities
Crossbeams: (Span + 1)
Decking: (Span / length of each board (either 2.0 or 3.0) x 5)
Nailers (optional): (Span + 1)
27
3.5
OTHER MATERIALS
Flexible plastic tubing: 3 diameter*
Flexible plastic tubing: 3 diameter*
Tie- wire
Galvanized tie-wire
U-nails
Screws: 5/16 x 10 cm (4)
Anti-corrosive paint
Fencing: 1.20 m high
Handrail saddles or tier rims
67cm 3 angle iron / walkway saddles
Sand / gravel
Masonry block / Bricks
* The best product for this purpose is reinforced tube, often found at plumbing stores.
28
3.6
Unit
Units required
m
piece
391.04
64.00
bags of 40kg
unit
(9m)
(9m)
(9m)
unit
unit
kg
mts
gal
173.66
180.00
6.00
11.00
4.00
4.00
4.00
10.00
20.00
8.00
piece
piece
unit
kg
(9m)
gal
mts
kg
kg
62.00
155.00
62.00
26.00
32.00
1.00
76.00
6.00
20.00
m
m
m
m
40.00
10.00
80.00
40.00
Transportation of materials
per trip
6.00
Mason
Supervision
Logistical Support
daily
daily
per visit
180.00
90.00
12.00
Cable 26mm
Clamps 26mm
Sand
Gravel
River rock
Dressed Stone
Note: For pricing estimate, local material and labor costs must be considered.
Volume 3: Suspended Bridge
29
THIRD EDITION
2013
VOLUME 3. 2
B2P_manual_05.indd 6
8/16/13 2:51 PM
THIRD EDITION
2013
VOLUME 3. 3
B2P_manual_05.indd 7
8/16/13 2:51 PM
Volume 3: Suspended
We build to INNOVATE by developing and sharing engineering solutions that are safe, replicable,
and locally viable. We build to EDUCATE by providing educational programs that teach footbridge
construction to reach the greatest number of people in need. We build to INSPIRE by providing opportunities for leadership development and personal growth through international collaboration.
Bridges to Prosperity (B2P) provides isolated communities with access to essential health care, education and economic opportunities by building footbridges over impassable rivers. We envision a world
where poverty caused by rural isolation no longer exists.
INTRODUCTION
Volume 3: Suspended
3.3
3.1
3.2
2.1
2.2
2.3
2.4
Section 2: Safety
Excavation Layout
Excavation in Soil
Excavation in Rock
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
Section 6: Construction
5.1
5.2
5.3
4.1
Volume 3: Suspended
Responsibilities
Community
Labor
Implementing Agency
Supervision - 5 days
Masons
Responsibilities
Community
Labor
River rock
Implementing Agency
Supervision - 5 days
Sand, gravel and blocks
Construction materials
Cement, rebar and misc. items
Construction
Total time required: variable, 2 to 4 months
Preparation
SECTION 1:
CONSTRUCTION OVERVIEW
Volume 3: Suspended
Responsibilities
Community
Labor
Implementing Agency
Supervision - 2 days
Masons
Responsibilities
Community
Labor
Implementing Agency
Supervision - 3 days
Masons
Responsibilities
Community
Labor
Implementing Agency
Supervision - 5 days
Masons
Volume 3: Suspended
Responsibilities
Community
Coordination
Implementing Agency
Attendance
Responsibilities
Community
Labor
Implementing Agency
Supervision - 2 days
Responsibilities
Community
Labor
Implementing Agency
Supervision - 3 days
2.3
Volume 3: Suspended
nize the potential hazards and determine what safety measures need to be taken.
Whole project level - What actions contribute to a culture of safety over the duration of the entire project?
Planning for project safety should take place before the ground breaking of a project and should encompass a broad perspective of a culture of safety. Considerations may include: the location of water, latrines and other sanitation needs for workers, the location of the nearest emergency medical attention, relations with the
local community especially regarding safety concerns, resources that may be available for safety training for workers, etc.
Bridges to Prosperity has developed the B2P Health and Safety Program with the aim to develop the same culture of safety that is paramount to success in the
construction industry. Daily actions, like the use of personal protective equipment or fall protection, are critical to safety on any work site, however developing a
Safety must be considered at multiple
levels:
In conjunction with our partners and industry experts, Bridges to Prosperity developed the B2P Health and Safety Plan to address the hazards that may be encountered on a bridge site. In many of the countries where B2P operates, safety standards that are commonplace in many western countries are largely absent or, at
best, lackadasically enforced. National organizations focused on safety in those countries, like OSHA in the United States, are generally too weak to be effective, or
may not exist at all. B2P values the health and wellbeing of all personnel on bridges sites, both local community members and visiting volunteers, and expects the
Health and Safety Plan to be applied comprehensively on site. This often means that foreign volunteers have the opportunity to share their experiences in work site
safety with local laborers to ensure a safer workplace for all. This exchange of ideas in safety culture awareness is a keystone in the Build to Educate component of
B2Ps mission. Please reference the B2P Health and Safety booklet for more detailed information on the topics listed.
2.2
All team members and community members working on site must abide by the B2P Health and Safety Plan, and actively engage with the Safety Manager, aligning
with all safety plans and protocols.
2.1
SECTION 2: SAFETY
communicated in the local language to any community members involved in that task.
The Safety Manager is responsible for ensuring a translator conveys the necessary
information and answers any questions that come up. Note: A language barrier should
never be grounds for exclusion of community members in a construction task. Ultimately, it
is their bridge and they should be able to help in any task. The Project Manager and Safety
Manager must coordinate a translator as necessary.
Communication
Communication and working safely go hand in hand; workers that are uninformed have the
highest potential for injury. The Safety Manager on site needs to ensure that everyone on
site knows and accepts the expectations. This includes both local community members
Commitment
Safety is a function of leadership. As a result, safety must start from the top of an organization
and be consistent throughout. Expectations need to be set and met by all people on the
team without exception.
Each of these will be further explained in the following sections. Refer to the B2P Safety
Training PowerPoint presentation for additional information before completing the B2P Safety
Training Quiz, found at Bridgestoprosperity.org/Resourses..
This safety system was developed to better understand the aspects of safety. There are 6
different elements to this Safety System .
1. Commitment
2. Communication
3. Planning
4. Education
5. Evaluate/Modify
6. Reinforcement
Safety System
ON-SITE SAFETY
Volume 3: Suspended
2.4
REQUIRED ON SITE
Daily
Daily
Daily (when applicable)
Daily (when applicable)
Daily
Daily
Daily
FREQUENCY
Volume 3: Suspended
No workers health and safety is ever more valuable than another workers. Safety standards are to be applied equally to all personnel working on site. It
is possible that language barriers and cultural differences will require more time is spent on training.
Education
On most projects, each person brings a different level of safety training and experience. It is essential that everyone on the work site can effectively identify
hazards and knows the best measures to protect themselves. A bridge project is an opportunity for better safety-educated workers to teach those who
have less knowledge and experience. This includes both local community members and visiting volunteers. Safety managers should organize all training
sessions necessary to ensure that all personnel thoroughly understand the hazards associate with all tasks, and how those hazards can be mitigated.
FORM NAME
has used industry standard material and the assistance of safety professionals to ensure our Safety Program achieves the same culture of safety that is
a keystone to success in the construction industry.
Planning
Thorough planning is critical to achieving two goals of a robust safety plan: 1) eliminating incidents and problems that can create disruptions in work, and
Volume 3: Suspended
be injured unnecessarily.
10
The information gathered from those Near Hits can be used to modify bridge building procedures in order to avoid similar dangerous situations in the
A near hit is an event that did not result in injury, illness or damage but had the potential to. Near hits are important because they can teach a great deal
without injury, illness or damage occurring. Many people do not report there Near Hits for a fear of punishment or lack of understanding of their importance.
Near Hits
Bridges to Prosperitys goal is to develop a safety culture as strong as the safety culture of our partners on their projects in developed countries. A strong
safety culture is a product of shared safety values, attitudes, goals and practices, where commitment, communication, and planning occurs on a daily
basis. It is important that all personnel on B2P bridge sites support one another in safe work practices. Furthermore, the Safety Manager on site must
share any feedback regarding the safety on site and ways that the safety culture can be improved.
Safety Culture
Volume 3: Suspended
face shield does not provide much protection from impacts though. It is to be worn with safety
glasses underneath. Face shields must be worn when cutting rebar ,cables or during other
activities involving the grinder.
Face Shield
The face shield provides more complete protection of the face than safety glasses. It is to be
Safety Glasses
Safety glasses are required when any of the following are present;
Hard Hats
Hard hats are most important when there is a possibility of hitting your head on low hanging
objects or when there is the possibility of falling objects. Even if these hazards are not present, it is still a good idea to wear a hard hat when possible.
The goal of a safety program is to eliminate many of the hazards through engineering and
work practices. However, not all hazards can be eliminated so personal protective equipment
is still necessary. Personal protective equipment or PPE is worn to act as the last line of defense against injury or illness. There are many different kinds of PPE depending on the work
and the equipment involved.
11
Volume 3: Suspended
Tools are essential for all Bridges to Prosperity Projects. While tools are very helpful
and in some cases essential, they can also be very dangerous. This section will discuss
the hazards associated with tools and ways to prevent possible hazards.
Hand Protection
Hand protection, typically gloves, can protect hands from cuts, crushing, abrasions, heat
and cold and chemicals. There are different types of gloves depending on the application
they are needed for. Leather, fabric, coated fabric and rubber are some of the more common ones. Leather gloves are best for protecting against cuts, burns and heat. The fabric
and the coated fabric gloves are best for protecting against dirt and abrasion. Rubber
gloves are best at protecting against chemical burns
Work Boots
Work boots should be worn at all times while on bridge sites but are most important when
heavy falling objects, sharp objects, hot surfaces and/or wet surfaces are present. Work
boots are typically made of leather and provide ankle support. Some work boots have a
steel reinforced toe as well but this is not a requirement of B2P.
Hearing Protection
There are many different types of hearing protection. These include ear plugs, canal caps
and ear muffs. The rule of thumb is that if you have to speak loudly with a colleague, from
two feet away, you need to wear hearing protection.
12
Volume 3: Suspended
13
Volume 3: Suspended
Best Practices:
Operate within design limits
Use gloves, safety glasses and safety shoes
Store in a dry place
Dont use in wet locations unless approved for that
Keep work areas well lit
Ensure cords dont present a tripping hazard
they are eager to help and learn new construction methods, but they may be unfamiliar with the hazards
of such tools. If community members will be using power tools, then patient, clear instruction and close
supervision are absolutely required.
Power Tools
As the size and complexity of B2Ps bridges grow, the use of power tools on site is becoming more
prevalent. This necessitates that extra care is taken in not only using those power tools, but in making
14
Volume 3: Suspended
Harnesses must be inspected before each use. Bridges to Prosperity has an inspection
Harnesses
Harnesses are devices that are worn over your clothes and they are designed to catch and
support you when you fall. There is a main ring or the D-ringon the harness that when
worn properly, is located on your back between your shoulder blades. This ring is where
you connect your lanyard or retractable meaning this is what catches you if you fall.
Overview
It takes a person approximately 1/3 of a second to become aware that they are falling. It
takes an additional 1/3 of a second for the body to react. In that 2/3 of a second, the human
body can fall up to 7 feet!
Fall prevention is a series of reasonable steps taken to eliminate or control the potential effects of an unintentional fall while accessing or working at heights. This is applicable when
constructing the deck and when working on the towers for a suspension project.
Fall Protection
D-Ring
15
Volume 3: Suspended
Rescue Plan
With fall protection, it is important to not only protect against falling but to also to have a
plan of how to safely rescue the individual from their position after the fall. It is likely that an
individual that just fell will not be able to pull himself or herself up. Also, when the individual
is suspended in the harness, it does not take long before the straps will start cutting off the
circulation to legs. Some harnesses have straps that the individual can put their feet into to
Anchorage Points
Equally as important as the harness and the connection is the anchorage point or the point
that you are tying off to. Keep in mind that an anchorage point must be able to support
5,000 lb (2300 kg) per person or twice the intended load when using a horizontal lifeline. If
a retractable is being used, the bearing capacity of the anchorage point can be reduced to
3,000 lb (1400 kg) per person. It is always best to tie off to a point that is at or above D-ring
height. Also, make sure that the anchorage point is convenient for the individual. In the
picture to the right, note that the workers are tied off to a cable that is set higher than the
main cables to serve only as a tie off point.
a seat belt. If you pull slowly, it will release slack but if you pull quick, it locks up minimizing free-fall distance to a couple of feet. These work best in vertical applications. It is not
okay to connect two retractables in a series. They are not designed for this application
and therefore may not function properly. Also, if used in more of a horizontal application,
although the retractable will lock up, it is likely that the individual will swing. This is called
a Swing fall and it could be dangerous depending on what the individual might swing into.
Self-Retracting Lifeline
A Self-Retracting Lifeline (also known as Retractable or Yo-yo) is also used to connect a
Lanyards
The simplest of connections from a harness to an anchorage point, lanyards come in many
different styles and lengths. It is important that the lanyard being used will in fact provide
the desired protection. For example, if an individual is working 6 feet above the ground
and they are using a 6 ft (~2m) lanyard, they will likely hit the ground before the lanyard is
engaged. With a 6 ft lanyard, a minimum of 18.5 ft (5.6m) of clearance is needed between
the individual and the ground.
16
Volume 3: Suspended
Type B Soil
square foot or greater. Examples a cohesive soil are clay, silty clay, sandy clay and clay
Type A Soil
with vertical sides and remain intact while exposed. While this does produce the most
stable type of excavation and is best for foundations, it is not very common for B2P sites.
Stable Rock
as stable rock. The type of soil is what dictates the allowable slopes of the excavation
(see the following diagram).
tion that is narrow in relation to its length below the surface of the ground. In general,
the depth is greater than the width, but the overall width of a trench is not greater than 15
ft (4.6 m).
Background
An excavation is any man made cut, cavity, trench, or depression in an earth surface,
help take pressure off the leg straps. If a plan is not made ahead of time, there may not be
enough time to rescue the person before they go into shock. Also it may take more than
one person to lift the fallen individual so plan accordingly.
17
Volume 3: Suspended
a generic procedure for most penetrometers. First, a sample of undisturbed soil must be collected. The
easiest way to get this is to dig a hole and use the penetrometer on the shear face of the small excavation.
Next, on the penetrometer, move the ring to the lowest reading on the scale which should correspond to
the lower edge of the instrument handle. Slowly push the piston into the soil up to the groove that should
be located 1/4 away from the end of the instrument. Once the end has penetrated the soil up to that
point, pull the instrument away from the soil and read the value marked by the location of the ring. This
value will give you the compressive strength of you soil in ton per square foot (tsf) or kg per square centimeter (kg/cm^2).
Pocket penetrometer
A handheld device that is used to measure the bearing capacity of the soil at a given location. It is best
Plasticity Test
For this test, collect a small sample of soil and add water until it is moist. Roll the soil into a ball and next into a
1/8 diameter thread. If this can be done, hold the sample by an end. If it remains suspended without tearing, the
soil is cohesive.
Type C Soil
Class C soil consists of soil that has a compressive strength of 0.5 ton per square foot or less. It
stable.
and 1.5 ton per square foot. They can also be granular, non-cohesive soils such as angular gravel
(crushed rock), silt, silty loam and sandy loam. Previously disturbed soils can also qualify as well
18
Volume 3: Suspended
Class B Soil
19
Requirements
If working completely independent of B2P, the following items are still highly recommended.
world countries. This section will assist in making sure that all construction methods are done properly.
This section is not meant to be a hindrance but rather an aid for individuals that lack experience working
in these types of remote areas.
As with any construction project, there must be an aspect of quality control. It is imperative that these
Volume 3: Suspended
3.2
3.1
20
Volume 3: Suspended
A. Site
D. Towers
Left side
A2- Location of foundations with marked center line D1- Rebar installation in Tower
D2- Complete Tower
B. Excavations
D3- Saddle alignment
Left side D4- Walkway hump
B1- Complete excavations
Right side
B2- Distance from back anchor to front tower
D5- Rebar installation in Tower
B3- Anchor depth
D6- Complete Tower
B4- Foundation depth
D7- Saddle alignment
Right side D8- Walkway hump
B5- Complete excavations
B6- Distance from back anchor to front tower
E. Anchors
B7- Anchor depth
Left side
B8- Foundation depth
E1- Completed rebar cage
E2- Cross-section of cable (for size)
C. Foundation and Tiers
E3- Cable position in excavation
Left side
E4- Completed anchor
C1- Completed foundation
Right side
I. Completed Bridge
Left side
G1- Thickness of approach walls
G. Approaches
F. Sag Setting
F1- Handrail cables aligned
F2- Walkway cables aligned
F3- Clamp spacing
F4- Torque technic used
F5- Representative photo of clamped cable
21
The following is a list of photos that MUST be taken during construction. These photos are to ensure that each step of the process was properly executed. Upload to the bridge
appropriate Flickr folder, named: QC_[Name of bridge].
Volume 3: Suspended
22
AS-Built reports are markups done to the construction drawings that better represent how something was actually built. During construction the construction of a bridge, there
The included forms are designed to help ensure quality control standards are met.
Volume 3: Suspended
23
Volume 3: Suspended
24
Volume 3: Suspended
25
Also, note that there are different types of cement and varying levels of quality.
Ensure that the cement being used if of good quality and it is the desired type.
Materials
Check the availability and quality of required materials. Locate the source for cement, sand, gravel and water on the job site or elsewhere if necessary.
Ensure the following;
Cement should be fresh (no older than 60 days) and from a reliable source
Sand and gravel should be clean and free of debris (sticks, leaves, trash, etc.)
Sand should be course, not round or shiny
Sand should not contain silt or clay particles
Water should be clean and transparent
Gravel should be no larger than 5 cm
Gravel should be relatively round yet jagged (note: round refers to the overall shape and not the surface)
26
that if for some reason, this person cannot be present throughout the duration of the project, the head mason for the project, in most cases a local, should be trained
and held responsible for concrete mixed on site without the QC person.
quality of concrete on the job and must be submitted upon project completion
The intention of this section is to serve as a guideline for standard and replicable concrete mixing techniques for use on all projects. It is to be used as an outline and
Concrete
The quality of bridge projects is completely dependent on the materials used. During the project, it is important to use the best materials available. This section can
be used as an aid in sourcing materials for construction. If the materials used are in question, it is best to consult experienced personnel before using them.
Volume 3: Suspended
3.3
Sand ( m 3 )
0.5
Gravel ( m 3 )
0.75
Yield ( m 3 )
1.0*
Volume 3: Suspended
The water amount will likely vary from site to site based on the characteristics of the aggregates. As a starting
value for the volume of water, it is recommended that the water necessary for a minimum slump is added and
then water is added in small amounts until the desired consistency is reached. For a 1 - 2 in (2.5 - 5 cm) slump
with 5 cm gravel, the recommended water is 0.15 cubic meters per cubic meter of concrete*. This means that for
the diagram below, it is recommend to start with about one half of a bucket of water and continue to add water
until the desired consistency is met. A slump test is very useful for this application and is covered in a following
section.
*Note that it is assumed that there is a 33% reduction from the summation of the volumes of the components to
the volume of concrete produced.
Cement ( m 3 )
0.25 (8 x 42 kg bags)
Materials Needed for 1 Cubic Meter of Concrete Using a 1:2:3 Mix Design
For all B2P projects, a 1:2:3 volumetric mix ratio is recommended. This means that one bucket of cement is
mixed with two buckets of sand and 3 of gravel. Note the size of the bucket does not matter as long as it is
consistent. Below is a table representing the amount of cement, sand and gravel needed for 1 cubic meter of
concrete. Note that the below table is more useful in estimating total materials needed rather than for use when
mixing concrete.
Mix Ratio
27
Gloves
Cement
Gravel
Water
Safety Glasses
Volume 3: Suspended
Placing Concrete
Concrete should always be placed within 1 hour of mixing. If this time limit is exceeded, the concrete
should be discarded.
details on how to preform the slump test are included later in this section but a slump of 3-4 inches
(7.5-10 cm) is recommended. .
The method of sifting water is superior to the Volcano Method or cone method that is commonly used.
The puddle of water in the middle of the cone shape does not produce an even and consistent product
as when water is mixed slowly and evenly into the mixture.
that is well mixed, add the cement and gently mix the pile so no cement is lost (cement is very light).
Using shovels, mix the dry components thoroughly. Do so by shoveling into a single pile, then moving
the pile twice (back and forth). After the dry materials are well mixed, add water using the same
method stated above. During this process, continue moving the pile to ensure uniformity.
28
required. When the use of a portable mixer is not feasible, a manual method of concrete mixing is required. In order to ensure material strength properties assumed in
the design, it is important to use only clean and fresh materials and mix them using the sifting method. Before starting, pour a thin concrete pad where the concrete
mixing will take place. This will limit the amount of unwanted constituents in the mix (i.e. soil, grass, sticks,etc.) and will allow less water to escape the mix.
(i.e. 0.6 buckets of water for 1 bucket of cement). Following that, all dry materials should be added. Let materials become well mixed and slowly add water until the
Recommended Materials
Shovels
Buckets
Sand
Flat clean working area
recommended since it usually produces much stronger concrete in comparison to hand mixing.
Volume 3: Suspended
If 3 cubic meters of concrete is needed for the anchor and the anchor needs to be loaded as soon a
possible, how much sika accelerant is needed?
1. Identify how many kilograms of cement is needed for the 3 cubic meters of concrete. In this case,
8-42 kg bags per cubic meter so 8*42*3=1008 kg
2. Look at the manufacturers recommendation for milliliters needed per kg of cement. In this case it
is 520-1950 mL per 100 kg of cement Lets say 1000 mL per 100 kg
3. Take 1,008kgs of cement *(1,000 mL /100 kg cement). The result is 5,242 mL min. and 19,660
mL max. Note this is for 8 bags and a more useful number would be per bag of cement. Take
these values divided by 24 bags to get 220mL min. and 820 mL max.
4. Lets say 500 mL per 42 kg bag of cement and we will need 12 liters totoal. For this, cut the top
off of a 1 liter bottle of water and mark the 500mL line. Use for adding to the mixes.
Example:
29
Also note that many accelerants contain Calcium Chloride. There is a lot of data and experience that states that these types of accelerants increase drying shrinkage, increase potential for reinforcement corrosion and increase potential for scaling. If the accelerant available contains calcium chloride, it is recommend that a
professional engineer be consulted to determine how to proceed. The following example uses Sika Rapid-1, a non-chloride containing accelerant.
Admixtures - Accelerators
Curing
Fresh concrete will crack when it is allowed to dry rapidly, thus curing the concrete is essential. After the concrete is placed, covering the concrete will help reduce the
amount of moisture lost due to evaporation and to help ensure consistent hydration. Wet burlap sacks or plastic sheeting works best, but anything that helps reduce
water loss is acceptable. Moistening the empty cement bags and covering the fresh concrete with them is another good option for curing. Whichever is used, add water
each day to the surface of the concrete to better hydrate the concrete.
Volume 3: Suspended
Also, the use of concrete admixtures, such as liquid accelerants, can affect the slump of the concrete.
If an admixture is used refer to the manufacturers data to verify if and how the slump will be affected.
The slump for any batch of concrete (excluding grout mixes) should be from 3-4 in (7.5-10 cm) should
be no more than 11 cm (5). If a batch of concrete exceeds this amount either discard the batch or use
on a non-critical part of the bridge (listed on the QC checklist).
Concrete Scoop
Tamping Rod - (~1.58 cm dia (5/8) x 40-50 cm (16-18) long, smooth steel rod)
Tape Measure
Tools Required
Slump Cone - (20 cm (8) base dia. x 10 cm (4) top dia. x 30 cm (12) tall)
Slump Test
If there is a standard slump cone available on site, take one slump test per batch of concrete made. A
slump test is used to help verify the workability and mix proportioning of a single batch of concrete. It
is also useful to determine consistency between multiple batches of the same mix of concrete. In order
to perform the test you will need some basic tools listed below. The slump cone needs to be exactly as
30
Volume 3: Suspended
Step 4
Slowly pull the cone upwards (should take about 5 seconds to completely remove the cone). Then, turn
the cone over (small side down) and measure the distance between the top of the cone, and the center
of the top of the slumped concrete. This measurement is your slump.
the remainder of the way, and repeat tamping 25 times, just barely penetrating the second layer. Use the
rod to smooth off and remove any excess concrete from the top of the cone.
Step 3
Fill the cone a third of the way with concrete (to a height of 2-5/8). Then, use the tamping rod to
consolidate the concrete in the cone by use of an up and down motion, 25 times. Fill the cone another
Step 2
Place the slump cone (large side down) on the slump board and secure it in place by standing on the
Step 1
Moisten the slump cone, tamp rod, scoop and slump board so that they are wet to the touch.
31
Concrete Scoop
Tamping Rod - (~1.58 cm dia (5/8) x 40-50 cm (16-18) long, smooth steel rod with rounded end)
Volume 3: Suspended
Step 4
Because little information of strength of concrete mixed in these areas is available, testing results from
all groups is appreciated. Break test cylinders after 28 days and send results to Bridges to Prosperity
at info@bridgestoprosperity.org.
Step 3
layer 25 times with the tamping rod (When rodding the second and thrid layers, the rod should just
nate voids in the mold. Strike off the top of the cylinder using any straight edge you have and put the
cap on.
Step 2
Step 1
Tools Required
Plastic cylinder molds - (10 cm (4) dia. x 20 cm (8) talll)
32
Compressive Test
It is encouraged to make concrete cylinders that can be used for strength testing. The results will be useful in developing future mix proportioning guidelines and in
bridge evaluations. Note that grout mixes use a different testing method that is not outlined here.
Is it transparent?
Volume 3: Suspended
NOTES:
Source of water?
Country:
Bridge Name:
33
Location on
Bridge
Accelerator
used? If yes,
how much?
Mix Proportion
Volume 3: Suspended
Date
Measured
Slump
Were
cylinders
taken?
34
Competent
person
Approval
Chisel
Trowel
Level
Hammer
Plumb Bob
String
Square
gaps.
Always stagger each layer of masonry as shown below.
Try to place large stones so that their large face is facing down.
without assistance.
Volume 3: Suspended
Unreinforced, stone masonry walls should not exceed 2 meters in height. If walls larger than this are
Good masonry uses 5cm or less of mortar between joints. Staggering the layers (alternating joints) so
that joints are not above each other is also key to strong masonry structures.
There are some important factors that contribute to a masonry structure being strong and long lasting.
Use as many stones as possible and as little mortar.
Tools Required
Stone/Rubble masonry
35
Trowel
Level
Plumb Bob
String
Wood formwork
Square
Nails
Hammer
gaps
Volume 3: Suspended
Also, be aware of the quality of the CMUs that are available locally. The quality and therefore strength of
these can vary greatly from site to site. In most cases, these blocks are used as formwork so as long as
they can withstand the lateral pressures from the wet concrete.
Note the size of locally available block, and plan wall dimensions accordingly. It is ideal to use whole
In some instances, masonry walls will need to be reinforced for additional stability. In the case of most
suspension bridges, this is not needed. If additional reinforcement is deemed necessary i.e. working
There are some important factors that contribute to a masonry structure being strong and long lasting.
Make sure blocks are wet before applying (in order for mortar to bond)
Mix as little mortar as possible at a time to ensure freshness
Mortar between blocks should not be thicker than 1-2cm
Tools Required
C.M.U Masonry
36
Volume 3: Suspended
*Consult the Wire rope users manual for more information on how to take care of and inspect wire rope.
Take care when unwinding the cable from the spool. Kinks in the cable are detrimental to the material
strength and are a point of weakness. Furthermore, take care not to lay the cable in sandy areas. Sand
may get in between the cable strands and cause damage. Use heavy tie wire to wrap around the loose
ends of the cable to stop unraveling if any cuts in the cable are made (note that the wire should be placed
on both sides of the cut).
Unwrapping Cable
Cable Inspection
It is imperative that the cable that is to be used is thoroughly checked. This can be more of an issue
when using donated cable. Note that if cable from B2P is being used, it is recycled cable.
If using repurposed wire rope, all cables must be inspected before they are considered adequate for use
on a B2P bridge project.
37
Red is Dead
Never
Saddle a Dead
Horse
Volume 3: Suspended
38
(Malleable clamps are inferior and are not suggested for any bridge use. If no drop-forged clamps are available, no clamp size greater than 1 1/8 is recommended.
Note that the required torque for malleable clamps is far less than drop-forged and over tightening malleable clamps will lead to clamp failure. The use of malleable
clamps requires re-tightening and additional clamps. As such, when using malleable clamps, leave at least half of the clamps permanently above ground.)
DROP-FORGED CLAMPS ARE OF SUPERIOR QUALITY AND MUST BE USED ON ALL B2P PROJECTS!.
There are two types of clamps that are readily available for cable terminations; Forged and malleable
clamps. Note the these clamps can be referred to as clips, U-bolts, bulldog clamps, etc. Forged
clamps are made from a solid piece of steel that is heated up until the metal is soft and then bent
to shape. With malleable clamps, the metal is heated until it is liquid and then poured into a form.
In this process, there are chances of voids being created or imperfections existing in the clamps
that cannot be easily detected. For this reason, malleable clamps are not allowed for use on the
main cables and are not permitted on B2P projects for use on the main cables. Note that Crosby
clamps are forged clamps and are used on all B2P projects. Also note that drop-forged is a type of
forging process.
Volume 3: Suspended
Since the torque required for the clamps will reduce the cross-sectional area of the wire rope, it is important
that the clamps are properly oriented. Clamps must be placed such that the saddle is around the live or loadbearing cable and the pinched side is the loose or dead cable as shown in the diagram below. The common
expression for remembering this is Never saddle a dead horse.
is not available, tighten until the cross-sectional area of the dead cable is reduced approximately 25%. This
reduction in area is what makes this type of connection work.
If a torque wrench is available, read the amount of torque applied by tightening the nuts similar to a typical
The table to the right is from the Crosby Group and is intended to be used in conjunction with Crosby clamps.
It is always recommended that manufacturers guidelines be followed for the clamps that will be used on any
given project. Even if Crosby Clamps are used, information from the manufacturer should be used when
determining proper torque and spacing.
could cause failure as a result The required torque varies depending on the quality of the clamp (drop-forged
Ensuring that the cable clamps are properly tightened is the single most important quality control issue for
39
Volume 3: Suspended
On most suspension projects, the materials needed for construction will be divided into two groups;
materials that are readily available on or near site and materials that will require transportation to site.
40
Grain sacks
Chisels
Volume 3: Suspended
as formwork, the inside dimensions of the walls must be kept the same as well as the height to ensure the
same amount of concrete is poured.
Consult the drawings in Volume 4.2 to determine how many of each dressed stone type will be needed to
Face Stones :
The face of one side (of a generally four sided stone)
needs to be cleanly chiseled
straight and square as it will be placed facing out from the masonry work. Stones should be
approximately 20 cm x 28 cm.
Corner Stones:
Two adjacent sides of a stone need to be cleanly chiseled and square for use at the corners
of the towers. Stones should be approximately 20 cm x 28 cm.
Dressed Stone
In some areas, dressed stones are widely used in construction. If this is the case, dressed stones can be
used in place of cinder blocks. The decision to use these should be based solely on the area where the
bridge will be and the local construction techniques. Dressed stone is dressed to be square with hammers
and chisels. There are two types of dressed stones:
Broken Stone
Local Materials
Hammers
Buckets
Local Materials
41
The water used for concrete is often times not potable water. This being said, it is important that the
water is relatively clean. Many times, the only water available in the quantities needed is river water.
In this case, make sure that the water has a low turbidity and is transparent. If the water has a higher
turbidity (cloudy), it should not be used directly. One way to deal with turbid water is to have a holding
container for the river water on both sides. While the water is in the container, some of the impurities
will settle to the bottom, making the water on top clearer. There are many other ways to deal with
high turbidity so do what makes sense for a given site.
thoroughly mixed with coarser sand from another location. Sand can be collected from river deposits
or from a quarry. The quality of the sand should be assessed before collection. Check the content of
impurities such as mud, clay, debris, silt, sand, etcetera and avoid sand with a high content of these
materials to reduce the need for washing. Sand with silt must be washed out in grain sacks at river
before use.
The sand will be used for the concrete mixture and the sand sizes should be well graded. The best
design has 50% medium size particles (~2mm) with decreasing amounts of very large and very small
The coarse aggregate (gravel) will be used in the concrete mixture and should be rough and clean
with broken faces; rounded particles will not adhere well in the mixture and should be avoided
if possible. Dirt and organics in the mixture will also decrease mix strength, and any aggregate
containing soils must be washed until clean. Riverside gravel should be broken with a hammer to
form rougher surfaces. Maximum gravel size is always 5 cm, but is usually smaller and dependent on
the formwork and dimensions of the rebar. Aggregates larger than 7 cm will usually reduce concrete
strength. Gravel can be collected from river deposits or by breaking boulders into the necessary size.
Volume 3: Suspended
Water
Sand
Gravel
42
The cable (wire rope) must be sourced in-county from either B2P, a local supplier or a local importation
company. Once in country , the cable must be delivered to site. Develop of rough estimate of how much the
cable will weigh before arranging transportation , as the size of the truck size will be dependant on the total
weight of volume.
When silt-free sand cannot be found on site, sand will have to be purchased. This is necessary only if there is
Volume 3: Suspended
ONLY drop forged clamps are permitted for use on B2P projects. Drop forged clamps are usually not available
locally and should be brought from the United States or Europe.`
Cable Clamps
Cable
Gravel
It is important to buy cement from a trusted store in the area. It is more likely that the cement is stored properly
and is not stored for very long. If cement is not properly stored, there can be sizable decreases in the strength.
Even when properly stored, the cement can lose up to 50% of its strength in 18 months of storage! Check
for hard spots in the cement bag. This is an indication that the cement has been exposed to moisture. If hard
Cement
43
The recommended crossbeams are two 1.75 steel angle pieces that have been welded or bolted together. These
must be fabricated in a shop and delivered to site. It is recommended that the crossbeams are painted in some type of
anticorrosive paint after they are fabricated.
delays in getting the timber are not uncommon, it is best to plan accordingly.
Timber will be needed for both the decking and the nailers. B2P standard decking boards for these bridges are not
Volume 3: Suspended
C.M.U Blocks are typically used for the pedestals and approach ramp. Take note of the their dimensions as they may
but rebar from bigger cities tends to be of better quality. Also take note of maximum lengths of rebar available.
Reinforcement steel
Timber
44
Local Materials
Volume 3: Suspended
Sand
Stones
Gravel (crushed stone)
Material item
site
Date of
Notes
45
2
1
Volume 3: Suspended
Pliers
Abney Level
1
1
2 kg sledgehammer
4 kg sledgehammer (if stone work)
1
1
1
1
1
1
1
Flagging stakes
Vice grips
1
2
Wheelbarrow
20 liter (5 gallon) buckets
Machete
Measuring tape, 5 meters
Masonry tools (if not provided by mason)
Woodsaw and blades
Hacksaw and extra blades
Rice sacks
4 screws or lag bolts
Suspender rebar
Rebar
Calculator with Sine & Cosine
Rock chisel
1
2
6
1
2
Material item
Hammers
100 meter tape
Quantity
4
2
Shovel
Pick
Material item
20
2
1
4
5
1
46
Tools Required
Spray Paint
String & Picks
Wood saw
EXCAVATION LAYOUT
Shovels
Stakes
Hammer
Volume 3: Suspended
47
Find the distance between the front of the foundation to the back of the anchor in your plans and place another stake at that point. Finally, go back a 2.00 m further and place
Step 2
Using the markers R and L on the right and left side of the river respectively, as marked in the survey, measure the distance from R (or L ) to the front of the tower, according
to your design. If an automatic level is available, use it to establish the bridge centerline from side to side, then set all subsequent points off of the established center line. Place
a stake at the point of front of Foundation, named FOF(R) - Front of Foundation Right.
Step 1
5.1
SECTION 5:
SITE PREPARATION
Volume 3: Suspended
Extend string around these four stakes at each of the towers and anchors. These are your excavation areas.
Step 6
The four corners of the foundation and anchor blocks respectively are found from the centerline Using a 12 meter
string, connect at FOF(R), and have one person hold the 4.0 meter mark of the string along the centerline. The second
person holds the string at 9.0 meters, repositioning until the remaining 3.0 meters can reach back to the start point,
creating a 3-4-5 triangle. The relative dimensions of the triangle create a right angle along the 3m leg. Stake this point,
1. Repeat for all corner points for both foundation and anchor.
Measure the distance from front of foundation (FOF) to front of anchor (FOA) and mark FOA(R).
Step 4
Repeat the process on the other side of the river. If an automatic level is available, verify both sides are square to each
other. Run a string between the permanent center line stakes.
Step 3
48
EXCAVATION IN SOIL
Volume 3: Suspended
Step 3
Dig the anchor trench according to the measurements given in the plans.
Step 2
Step 1
5.2
49
EXCAVATION IN ROCK
Volume 3: Suspended
Soft rock anchors require excavation to one meter (1m) depth, but do not need to be at the same level as the
tower excavation. Excavate a soft rock anchor according to the dimensions in your design. Since stakes are
hard to use, use spray paint to mark the excavation area.
Foundation placed on solid rock bed do not require excavation to one meter (1m) depth. Ensure the rock
The method of marking fron of foundation (FOF(R)) and front of anchor (FOA(R)) is the same as described in
section 5.2 - Excavation in Soil
5.3
50
Volume 3: Suspended
Excavation
Layout
Centerline established using automatic level (if available) and marked with stringline?
51
Volume 3: Suspended
6.1
SECTION 6:
CONSTRUCTION
52
Sand
Materials Required
Cement
Tools Required
String
Shovels
Square
Plumb bob
Buckets
Water level
Masonry tools
Volume 3: Suspended
Pour a foundation layer (25 mm) of concrete onto the soil at the base of the foundation.
In the case of hard rock, pour a thick mortar mixture to roughened rock area.
Step 2
Ensure that the foundation excavation is level from front to back, side to side. Ensure that the foundations on
either side of the river are square to one another. Always use the centerline for positioning.
Step 1
6.2
53
Volume 3: Suspended
Continue with the masonry layers until the tier has reached 1.00m in height.
Step 5
Fill the layer of masonry stones between the corner stones, around the perimeter of the foundation tier,
placing stones as closely together as possible. The wall should be 30 cm thick.
Step 4
plans). Ensure the stones are placed square using a plumb bob and level using a water level.
Step 3
54
Volume 3: Suspended
* reinforcing with wire mesh can be added to distribute the load of the above tier or tower
the edges as a base for the next course of stone masonry to sit on.
Make a watery grout of concrete/sand mix in 1:2 proportion out of 2 cement bags and pure over the
Step 8
Step 7
gaps with smaller stone, then another layer of bigger stones and so on.
Step 6
55
Volume 3: Suspended
drawings. Each tier reduces in width from the one below it, per
the following dimensions.
56
AS YOU BUILD UP THE TIERS, RECONFIRM THAT EACH TIER IS TRUE TO THE CENTER LINE BEFORE CONSTRUCTION BY MARKING THE CENTER LINE ON THE
FOUNDATION OR TIER BELOW.
Step 10
* If river stones are not available tiers may be built of CMUs. In the case
of block masonry a reinforced concrete wall will be constructed on the
inside of the masonry wall. Place vertical bars (12mm) the full height of
the foundation/tier wall (1.00m) at each corner and every 50cm along
the inside of the wall. Wrap and tie (to the vertical bars) horizontal bars
(12mm) around the inside wall at 20cm, 50cm, and 80cm. With wood,
Repeat 3-8 for to build all needed tiers. Verify each tier is correctly
sized and straight.
Step 9
Volume 3: Suspended
Tier/s
Foundation
57
Steel hacksaw
Masonry tools
Level
Materials Required
Cement
Sand
Gravel
Hammer dressed stone
Tubing
Tying Wire
4 x 13 half-tire rims for handrail saddles.
4 pieces of steel rebar, 20 mm (#6) x 4.50 meters
67cm long, 7.5cm (3) angle iron
rebar guides for walkway cables: (optional)
# of walkway cables + 1, 16 mm x 20 cm each
Tools Required
String
Plumb bob
Shovels
Buckets
Square
Wire cutters
TOWER CONSTRUCTION
Volume 3: Suspended
6.3
58
Volume 3: Suspended
Place the four outside corner-blocks ensuring they are level and square relative to the centerline. Create
a second tower centerline to work from, and verify correctness of dimensions from centerline are level and
square.
Step 2
Set Corners
The base of the two symmetrical towers is dimensioned 1.00 meter long x 2.80 meters wide.
The alignment of the towers, perpendicular to the bridge centerline, is extremely important, as the cable
running over the saddles must not impose a side or lateral force on the towers. Even if the tiers are skewed,
it is crucial the towers will be parallel to one another and perpendicular to the centerline. For that, all
measurements should be based on the centerline.
Step 1
Align Towers
59
Volume 3: Suspended
For each side, 2 pieces of 20 mm rebar should be bent in U shape per diagram below.
Place the two rebar into the cavity formed from Step 3 and cover with concrete .
Step 4
Insert Steel Rebar
of a tower (2.80 x 1.00). When using CMUs 20cm is the height of one block.
Step 3
Build Tower Base
60
Volume 3: Suspended
as a frictionless surface for the walkway cables, as the elastic cable is expected to stretch under loading
conditions.
of tower). Insert the 67cm long x 7.5cm (3) angle iron at the top of the hump. Make sure the placement is
Step 6
Complete the Walkway Hump and Install Angle Iron
(use of fabricated saddles, go to step 7)
the needed height. Fill to 10cm below the top of the towers. The rebar should be slightly extending from
tower.
side.
Step 5
Complete Tower Construction and Fill
61
Volume 3: Suspended
accordingly.
Cut a used tier-rim in half. Install the tire rims (or prefabricated handrail saddles) so that the cable will
cross at 25 cm from the inside of the tower and 40 cm from the front of the tower on the anchor side. Build
up to the hump with concrete 1:2:3. Make sure handrail saddles are level side to side. Make sure the inside
Step 8
Form Tire Rim (Handrail saddle)
cm from either side of center point (center between the 2 towers) and
place the fabricated saddle, this is the inner-most dimension for the
saddle. From the center line the guides should be placed at 58cm,
63cm, and 68cm respectively. This steel surface of the saddle will act
as a frictionless surface for the walkway cables, as the elastic cable is
expected to stretch under loading conditions.
Step 7
Complete the Walkway Hump and Install
Fabricated Walkway Saddle (optional)
62
Volume 3: Suspended
Construction
Pre-Construction
Angle iron or fabricated walkway saddles aligned with centerline and level?
Height difference on R side between walkway and handrail saddles equal to 1.10 meters
Height difference on L side between walkway and handrail saddles equal to 1.10 meters
63
Sand
Plastic tubing
Plumb bob
Gravel
Water level
3
bent into U-shape for erection
hooks
20mm x 3 meter
11
bent into 0.8m per side
3
bent into U-shape for erection
hooks
Volume 3: Suspended
N/A
N/A
Drop forged cable clamps (for cable clamps size and quality see design guide)
Steel rebar:
Rebar size (dim x length) Small anchor (up to 60m span)
20mm x 2.9 meter
4
11
10mm x 2.2 meter
bent into square 0.5m per side
Materials Required
Cement
Tie wire
Tools Required
String
All Soil and Soft Rock Conditions for spans up to 120 meters
Small Anchor = Spans up to 60 meters
Large Anchor = Spans from 61 to 120 meters
64
There are two anchor types discussed herein; beam and drum. The latter is only used for soft-rock conditions with spans less than 60 meters. All other bridge scenarios require
a beam type anchor.
6.4
Volume 3: Suspended
65
Tie 3 erection hooks ONLY to the anchor that will be adjustable. Again, if two similar anchor types are used
(drum or beam), the lower elevation is adjustable. If one drum and one beam anchor is used, the beam is the
adjustable side. Attach the bent rebar erection hooks 0.80 meters from either end of the rebar cages. A cable
winch will attach to the hooks while setting cable sag, so ensure the hooks are well secured.
* As 3 deck cables are used its advisable to add the third Erection Hook in the middle of the rebar cage.
Step 2
Add Erection Hooks
Tie together the straight steel rebar with square ties per the following quantities and dimensions:
Step 1
Build Beams
Volume 3: Suspended
66
Each cable needs to wrap around the anchor and extend back towards the tower with the loose end sitting in
the approach area. Care needs to be taken to ensure the location of each cable is aligned with its respective
saddle and where it will stay when the bridge is done. A pre-measured alignment board may be helpful. Once
secured, the cable must come off either the walkway or handrail saddle and follow a straight path to the anchor.
Step 5
Pull Cable Over Anchor
Set the anchor beams in the excavation on top of the cables. The anchor should sit at an angle of approximately
45 degrees so the front face with the erection hooks is perpendicular to where the cable will come off the
towers. It is helpful to prop the beam with rocks to allow the anchor to sit at the angle.
Step 4
Place Anchor Beams
Lay out the cable to either side of the river. Drop the cables into the excavation pit, in line with crossing points
at tower.
Step 3
Lay out Cable & Add Tubing
Volume 3: Suspended
On the adjustable side put minimum of 2 clamps per cable and hand-tight fully.
67
Immediately fully torque the non-adjustable anchor side (the side without erection hooks) using a wrench or
breaker bar with a minimum 1 meter extension (cheater bar) until the dead end of the cable has a reduced
cross-sectional area of at least 25% as shown bottom left.
Red is Dead
Never
Saddle a Dead
Horse
ad
Red
is d
e
a
ddle
a
s
er
se
Nev ad hor
de
For information on the number of clamps to use and the spacing between clamps see volume 3.3 section
6.6 CABLE CLAMPS INSTALLATION
WIth the dead end of the cable (cut end) sitting on top of the live end (extending to tower and across bridge)
Step 6
Cable Clamps
Volume 3: Suspended
NOTE: If the excavation is too big, use formwork on the rear side of the anchor.
concrete gets into the tubes and that the tube ends remain exposed.
1:2:3, verify with the concrete mixing guideline in volume 3.3 section 2 - Quality Control.
Step 7
Pure Anchor
68
Gravel
Water level
Wire cutters
Volume 3: Suspended
69
When using a drum anchor on spans greater than 40 meters but less than the maximum 60 meters, the cable is cut into two pieces. As such the cable sag setting procedure
is different for the two types.
NOTE:
Sand
Plastic tubing
Materials Required
Cement
Tie wire
Steel rebar:
Plumb bob
Buckets
Tools Required
String
Shovels
than 40 meters).
165
145
125
100
110
85
Dia. Rod
Inner Drum
5.18
6.25
Total
Volume
(m3)
Volume 3: Suspended
**If large anchors are need, seek additional design guidance from an engineer
180
160
Dia. Drum
Outer Drum
Required Diameters
20
16
Total #
Rods
(25mm)
70
Place the vertical anchor rods as shown in to the diagram below. First tie together the outer rebar cage with 10 mm rebar
Step 2
Build Cages
critical to leave the edge closest to the towers as clean and sharp as possible. The depth of excavation
is also critical to the design.
Step 1
Excavation
Small
0-40 m
Medium
41-60 m
Volume 3: Suspended
Lay out the cable to either side of the river. Thread 4.0 meters of plastic tubing on each of the cables on
the adjustable side. The non-adjustable side does not need tubing. For spans less than 40 meters, both
loose ends must lie on the adjustable end.
from the tower. The outer cage diameter allows the handrail cables to come off the tower and connect to
the anchor at a straight line. The inner drum diameter allows the walkway cables to come off the saddles
and connect to the anchor in a straight line. Frame and pour the inner drum with concrete mix proportion
1:2:4
top of the rebar cage approximately 0.50 meters above ground (on adjustable side, the erection hook must
face towards tower). Place the outer cage around the inner cage, attaching vertical rebar to the backside of
Step 4
Place Rebar Cages and Pour Inner Drum
Step 5
Tie two erection hooks to the anchor that will be adjustable. Attach the bent rebar erection hooks 0.50
meters from the top of the outer cage. A cable winch will attach to the hook while setting cable sag so
ensure the hooks are well secured.
Step 3
Add Erection Hooks
71
Volume 3: Suspended
cable is continuous. Rather, wrap the cable fully around the respective drum and return to adjustable side.
forged, clamp failure will occur if taken to an equivalent torque. For spans less than 40 meters, there are no clamps on the
Tie the walkway cables onto the opposing walkway cable after wrapping behind the anchor. Hand-tighten the cable clamps
so the saddle touches the live-end of the cable (do not saddle a dead horse!). Hand tighten the adjustable side. Tighten
Step 7
Clamp Walkway Cables
Red is Dead
Never
Saddle a Dead
Horse
When using 3 walkway cables the middle one will be wrapped around the anchor drum and tied to itself.
Each walkway cable needs to wrap around the inner anchor and the loose end should be placed into the approach area after
180 degree turn. Once secured, the cable must come off the walkway saddle and follow a straight path to the anchor. The
cable should wrap around the drum below ground level, at least 75 cm from the top of the drum.
Step 6
72
Volume 3: Suspended
Tie the handrail cable onto the opposing handrail cable after wrapping behind the anchor. Hand-tighten the cable
clamps immediately. Torque until the dead end of the cable has a reduced cross-sectional area of at least 25%.
If clamps are malleable rather than drop forged, clamp failure will occur if taken to full torque but cross-sectional
reduction is critical. See Suspended Volume 1: Design & Analysis for additional information.
Step 10
Clamp Handrail Cables
Each handrail must wrap around the outer anchor (both cages should be incased in concrete) and the loose end
should be placed into approach area. Once secured, the cable must come off either the walkway or handrail saddle
and follow a straight path to the anchor. The cable should wrap around the drum at ground level, ensuring there is
50 cm depth from the top of the drum.
Step 9
Pull Handrail Cable around Anchor
no voids form. Repeat for the adjustable side, ensuring no concrete gets into the tubes and that the tube ends
remain exposed. Let both sides cure a minimum 7 days unless concrete curing accelerator is added.
Fill the excavation pit with concrete aggregate, ensuring the entire rebar cage is covered in at least 10 cm of
Step 8
Pour the Anchor
Never
Saddle a Dead
Horse
73
Red is Dead
Cable clamp saddles on live end of cable (the cable in tension from the bridge).
Cable clamps torqued on non-adjustable anchor with minimum 1-meter pipe wrench?
Volume 3: Suspended
Drum anchor:
Construction
74
Volume 3: Suspended
75
The cable sag is the vertical drop that the cable will dip below a line drawn between each towers, measured as the chord at center span. The cable is hoisted to
a lesser sag than is designated due to the elasticity of the cable, as once the cable is set, the self-weight of the bridge will slightly stretch and the bridge will lower
Bh .
Bd
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
The Design Sag, B d , is calculated as 5% of span. This value is used in the Distance to Low Point of Cable (f) calculation, which in turn is considered to ensure
proper freeboard above the High Water Level.
6.5
invite accidents.
Never allow participants or spectators to stand in front of the anchor when cable or cable
winch are under tension.
Never use a cable clamp at the saddle to hold live cable under tension.
Volume 3: Suspended
CABLE CAN SLIP - MAKE SURE IT IS SECURED WITH FULLY TORQUED CLAMPS
NEVER leave a cable not secured! When you are working on a cable to set its sag, and so releasing its
clamps, make sure the tail of this cable is secured to another cable.
Cable Safety:
Never
Saddle a Dead
Horse
76
Red is Dead
Inspection should include: An examination of the chain for wear, twists, excessive dirt, broken links, and proper lubrication; Hooks should be inspected for deformations, cracks,
damage, and properly operating latches.
A thorough inspection of the cable winch intended for use in cable sag setting is mandatory prior to use. A failed winch can seriously injure or even kill a person. Never use a
winch you do not trust or that has been provided by an unknown source, or one that shows excessive rusting or is broken.
Volume 3: Suspended
77
Before tensioning cables and putting any load on the winches, determine Danger Zones which are unsafe and should not be occupied during sag setting. Also determine areas
which are safe Escape Routes that should be used in case of emergency. See the diagram on the next page. Converse those to all workers on the site!
Safe Zones:
45
50
55
60
65
70
75
80
85
Volume 3: Suspended
90
95
3.00 3.22
2.16 2.40 2.64 2.69 2.73 2.95 3.17 3.39 3.61 3.83
2.02 2.26 2.50 2.74 2.79 2.83 3.05 3.27 3.50 3.72 3.94
1.64 1.88 2.12 2.36 2.60 2.85 2.90 2.94 3.16 3.38 3.60 3.83 4.05
1.50 1.74 1.98 2.22 2.47 2.71 2.95 3.00 3.04 3.27 3.49 3.71 3.94 4.16
1.36 1.60 1.84 2.08 2.33 2.57 2.82 3.06 3.11 3.15 3.38 3.60 3.83 4.05 4.28
0.98 1.22 1.46 1.70 1.94 2.19 2.43 2.68 2.93 3.17 3.22 3.26 3.49 3.71 3.94 4.16 4.39
1.08 1.32 1.56 1.81 2.05 2.30 2.54 2.79 3.04 3.29 3.34 3.38 3.60 3.83 4.05 4.28 4.50
1.18 1.42 1.67 1.91 2.16 2.41 2.66 2.90 3.15 3.40 3.45 3.49 3.72 3.94 4.17 4.39 4.62
1.29 1.53 1.78 2.03 2.27 2.52 2.77 3.02 3.27 3.52 3.57 3.61 3.83 4.06 4.29 4.51 4.74
1.40 1.64 1.89 2.14 2.39 2.64 2.89 3.14 3.38 3.63 3.68 3.72 3.95 4.18 4.41 4.63 4.86
1.51 1.76 2.10 2.26 2.51 2.76 3.00 3.25 3.50 3.75 3.80 3.84 4.07 4.30 4.53 4.75 4.98
1.63 1.88 2.13 2.38 2.63 2.88 3.13 3.38 3.63 3.88 3.93 3.97 4.19 4.42 4.65 4.88 5.10
1.75 2.00 2.25 2.50 2.75 3.00 3.25 3.50 3.75 4.00 4.05 4.09 4.32 4.55 4.77 5.00 5.23
40
NOTE:
0.0
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
4.25
4.50
35
78
Volume 3: Suspended
79
Measure the low point f (distance to lowest cable point) relative the low side tower For the handrail cables - measure f from the top of the towers
For the walkway cables - measure f from the top of the walkway hump
Mark clearly on the tower/tier with spray-paint. This is your reference point for visualizing when the cable
has reached the hoisting sag level
Step 2
Mark Low Point f (lowest cable point)
(if using Auto-level refer to volume 2: Feasibility and Topographic Survey)
rigidity and notch out 30 mm guides on either end of the horizontal stick to allow the T-level stick to slide to the middle of the span without slipping off
the cables. Place a plum bob at the center that hangs without touching the T-stick when the stick is completely vertical.
Sag set T-guide with
Note - when using 3 walkway cables remember to leave space for the middle cable
plum bob
suspended from
center
stick or a level can be used to insure cables alignment. If you choose to use T-level-stick fabricate one using a 1.5 meter minimum length stick as
Step 1
Decide on Sag Setting and Cable Alignment Methods
There are many different ways to set the sag. Below we will describe two of these. You can choose to use any different way as long as at the end of the process All walkway cables are aligned to one another
Both handrail cables are aligned to each other and are 1.1m higher than the walkway cables
The cable low point is at f - low point elevation
Tools Required
Cable hoist with cable winch
Abney Level
Two long straight sticks (#1a, #1b)
1- meter tall stick (#2)
T-level stick: see diagram
Spray paint
Volume 3: Suspended
ing cable and that all participants are standing above the towers, anchors and cable, NOT below towers or cable.
Important Safety Notice: Make sure that only those working on the cables are in the near vicinity when tighten-
Look through Abney level towards cable in center of span to verify its about the marked point.
Raise the cable with the cable winch until the cable is well above the low point (f) marked in Step 2 (lowest cable point).
Step 5
Raise Cable
Step 4
Zero Abney Level
Important Safety Notice: Ensure that the winch you are using is correctly rated and in good working condition,
and that the connection to the cable is secure.
Connect t
chain around the cable, or securing a piece of pipe with a clamp, to ensure no slippage.
Step 3
Attach Cable Winch
80
Volume 3: Suspended
When lowering the cable with a winch and not in the method describe above, mark the cable on the saddle to
Step 10
(when using cable-winch to lower the cables) Mark Cable at Saddle
Step 9
Repeat for all cables
Loosen the clamps slowly a 1/4 turn. Using a large piece of wood, strike the cable just above the clamps. The
cable should slip and lower very slightly with each hit. If the cable does not move at all, loosen the clamps slowly
a 1/4 turn until the cable moves when hit.
Look through the Abney level or Auto-level from the lower sag point at the adjustable side toward the point marked
in Step 2 on the other side. Make sure the Abney level is level by viewing the level bubble or that the Auto level is
set correctly. Lower the cable in this manner until the Abney level sees the bottom point of the cable at the sag
point marked in Step 2. When done, hand-tighten fully minimum of two clamps to hold the cable in place.
Step 8
Hit Live Cable
Step 7
Remove Cable Winch
Attach two (2) cable clamps to hold the cable and hand-tighten the clamps. Secure the tail of the cable to another cable to make sure it does not slip while working on it.
Step 6
Hand-Tighten 2 Clamps
81
Volume 3: Suspended
Add clamps to all cables and tighten them per the information in 6.6 CABLE CLAMP INSTALLATION.
Step 12
Add Clamps - Beam Anchor (for Drum Anchor please go to next page)
82
Red is Dead
Never
Saddle a Dead
Horse
With the T-level stick, or any other method you choose to use (in the picture using a level), make sure all walkway cables are aligned and level, and both handrail cables are
aligned and level. If not, modify the needed cables. (Easiest doing by adjusting the location of the clamp closest to the anchor).
Always slide the T- level stick or the Level to the middle of the bridge and visually verify that the vertical stick of the T is vertical or that the bubble on the level is in the
middle.
Step 11
Cable alignment
Volume 3: Suspended
NOTE: The same apply both to the walkway cables on the inner drum, and the handrail cables on the outer drum.
When using 3 walkway cables the middle cable stay attached to itself.
Remove th
83
Remove the hand-tightened clamps from cable #1 and move the loose cable tail to the opposing cable (#2) and clamp in place. Do the same for cable #2 as shown in
Cut 5 meters of cable as temporary cable and place around the anchor. Attach the temporary cable to the live end of both cables (#1 and #2) to keep the tension as
Use minimum of two (2) clamps and hand-tighten fully.
Cable
clamps and hand-tighten fully.
Step 12
Add Clamps - Drum Anchor
(Rock conditions, for Beam Anchors see Previous Page)
Spacing
(mm)
102
114
121
132
144
160
160
171
Drop-Forge clamps
# of clamps
Torque (foot-lbs)
3
95
4
130
4
225
5
225
6
225
7
360
7
360
8
360
Volume 3: Suspended
84
(Malleable clamps are inferior and are not suggested for any bridge use. If no drop-forged clamps are available, no clamp size greater than 1 1/8 is recommended. Note that
the required torque for malleable clamps is far less than drop-forged and over tightening malleable clamps will lead to clamp failure. The use of malleable clamps requires retightening and additional clamps. As such, when using malleable clamps, leave at least half of the clamps permanently above ground.)
Cable Diameter
(inch)
(mm)
5/8
16
3/4
19
7/8
22
1
25
1 1/8
29
1 1/4
32
1 3/8
35
1 1/2
38
The table below is the Bridges to Prosperity standard for torque requirements for drop-forged cable clamps at given cable and clamp diameters. Cable clamp manufacturers
Proper cable c
DROP-FORGED CLAMPS ARE OF SUPERIOR QUALITY AND MUST BE USED ON ALL B2P PROJECTS!.
6.6
Volume 3: Suspended
Clamps must be placed such that the saddle is around the live or load-bearing cable and the pinched side is
the loose or dead cable as shown in the picture to the right. The cable clamps spacing (G) in the diagram
below is also important and is detailed in the chart on the previous page.
cross-sectional area of the dead cable is reduced approximately 25% as shown to the right.
If a torque wrench is available, read the amount of torque applied by tightening the nuts similar to a typical
The torque required for the drop-forged clamps will require a minimum 1 meter heavy open box wrench with
pipe extension or socket wrench. A typical man is able to reach 100 foot-pound torque, so with a 1-meter
extension he applies just over 300 foot-pounds of torque with his force applied at the very end of the wrench.
If a 1 meter wrench is not available use a breaker bar (cheater bar) with a socket wrench.
Never saddle
a dead horse
Red
is dead
85
potential for corrosion if water enters the underground tubes. A funnel created from a cut-off
soda bottle is ideal for directing the watery grout into the tubes.
After completing the decking and making sure the bridge is aligned and no farther
Take care when unwinding the cable from the spool. Kinks in the cable are detrimental to
the material strength and become points of weakness. Furthermore, take care not to lay the
cable in sandy areas. Sand may get in between the cable strands and cause damage. Use
electrical tape or duct tape and tie-wire to wrap around the loose ends of the cable to stop
unraveling at the ends of the cable.
Unwrapping Cable
CABLE CARE
Volume 3: Suspended
6.7
86
Volume 3: Suspended
87
To add redundancy in the case of potential cable clamp slippage, excess cable should be
wrapped back into the approach area and clamped back onto itself. Care should be taken
to clamp the dead end of the cable (not on the picture on the left clamps were installed
incorrectly).
The cables which remain underground, and all the clamps, must be coated
Volume 3: Suspended
Cable Care
Setting Sag
Care has been taken to insure no kinks or excessive broken threads on cable?
Verify number of clamps used per cable per side: ________ and spacing between clamps : ________
Distance to low point of cables set: f = ___________ (relative to low side) calculated using Bh
88
Plumb bob
Buckets
Sand
Broken stone
Tools Required
String
Shovels
Materials Required
Cement
Tamper
Gravel
Volume 3: Suspended
yer of the approach must be a layer of compacted gravel, 10cm thick. Take care to compact by using
either animals or people jumping on the area. Following compaction, cover the approach with a smooth concrete
slab, 10 cm thick.
Step 3
Concrete Slab
Fill the area with available stone, gravel and sand ensuring the stone is vibrated and tamped into place. Ensure
regular compaction with a tamper to reduce settlement. No soil or organics should be used as they will cause settlement.
Step 2
Backfill Area
CMUs should be used only if there is no other option and should be double layered and are not recommended for
over 2m high walls.
If the wall height exceeds 2 meter (for 3 tier structure) build the wall stepped on the outside. Build 70cm wide wall for
Set a plumb line between the edge of the top tier and the front of the anchor excavation. Dig a 25 cm deep and mini-
Step 1
Build Approach Walls
6.8
89
Volume 3: Suspended
There are three types of crossbeam alternatives; 1) wooden crossbeam with a nailer, 2) wood crossbeam
without a nailer, and 3) steel crossbeam with a nailer. The nailer is the same width as the decking panels,
and is attached to the top of the narrower cross-beam to increase the amount of surface area available for
nailing the decking panels. The nailer improves constructability and allows for a smaller crossbeam size.
Crossbeams
Materials Required
Crossbeams
Deck panels
Nailer Panels*
Galvanized Screws: long enough to hold the wood-width used
Steel ribbed rebar,
- (2 x (Span + 1)) pieces, 10 mm (#3) ribbed, cut to 1.80 meters
Tools Required
Hammers
Wood saw
Wrenches
Hack saw and blades
2cm diameter pipe (for bending suspenders)
6.9
90
Volume 3: Suspended
91
Cut minimum 10mm (#3) diameter ribbed rebar into 1.8 meter long pieces. Using ribbed rebar is recommended
as smooth rebar tend to be of lower quality. The total number of suspenders required is equal to 2x(span + 1). For
example, a 30 meter bridge would require 62 suspenders.
Step 2
Suspender Preparation
wide. If nailers are used, an additional (span plus 1) meters of decking panels will be required, cut at 1.0 meters.
Deck preparation
Cut decking panels to 3.0 meters for any span over 60 meters and preferably all spans. If the bridge is shorter than 60
meter span, 2.0 meter decking panels are allowable. The total number of decking panels is equal to [span divided by
Crossbeam preparation
Cut (span plus 1) crossbeams to 136 cm minimum length and pre-drill for suspender connections. The hole spacing is
based on the number of walkway cables. See Volume 3, Part 2: Suspended Bridge Construction Drawings. The hole
size should be bigger than the suspender size (for example - if a 10mm bar is used, drill a 13mm hole).
Step 1
Decking Preparation
Volume 3: Suspended
Correct
92
Not Correct
meter further so each are at a 1.0 meter spacing on center. Begin with 3 full length deck panels and two (2)
partial decking panels. Start with a full length panel on one side, second panel a shorter piece, third or middle
panel full length, and so on.
Place all decking heart down to minimize cupping, shown below.
Cut one deck panel to allow for deck panel staggering. If using 2.0 meter panels, cut starter pieces into two
(2) 1.0 meter panels. If using 3.0 meter panels, cut into one (1) 1.0 meter panel and one (1) 2.0 meter panel.
Step 5
Start Decking
crossbeams are then attached to the walkway cable by inserting the suspenders through the bottom of the
crossbeam and around the walkway cable. The top of the suspender is bent over the handrail cable.
installation. Insert the suspender and wrap around the crossbeam and handrail cable. Use a temporary clamp
Step 4
Install Crossbeams
If using nailer panels, cut (bridge span plus 1) panels to 1.0 meter. Attach the nailer to the crossbeams with
a minimum four (4) galvanized screws, aligning from the center of each board. The crossbeam should exceed
the length of the nailer by least 36 cm.
Step 3
Attach Nailer Panels to Crossbeams (Nailer Recommended)
Volume 3: Suspended
Continue until the bridge is complete, adding only three (3) or four (4) crossbeams and suspenders at a time.
When all decking is done go back and wrap the suspenders around the handrail.
Step 7
Lay Decking and Wrap Suspenders
93
(or nailer) it lays on using 2 screws. Make sure there is enough room to connect the next deck panel. Place
another screw connecting the panel to the middle crossbeam. It may be necessary to pre-drill screw holes in the
decking. This can be decided onsite based on the quality of materials and tools available.
Step 6
Screw Deck Panels
1 bag cement
Volume 3: Suspended
At the insertion point where the cable enters the approach, a small formed lift will hinder
the ability for water to pool at the connection. A small wedge may be formed with
To ensure a smooth transition between the decking and the ramp approach, additional
formwork was required during tower construction. Each walkway cable was threaded
with tubing, and each cable is aligned between saddles. An additional layer of concrete
was formed over the tubes to an elevation equal to the total depth of the decking. This
The ends of the decking panels end at an elevation above the hump of the tower crest
as shown in the top right picture. There are several design alternatives to mitigate this
potential safety hazard.
Materials Required
Deck panels
Tools Required
Hammers
Wood saw
Wrenches
Hack saw and blades
2cm diameter pipe (for bending suspenders)
94
Volume 3: Suspended
After the fence is placed throughout the span of the bridge, push the top of the fencing over the handrail
cables and tie tightly against itself with galvanized tie-wire. If the fence height exceeds 1.5m, the excess
fencing should wrap over the top cable or under the decking at the base.
Step 3
Attach to Handrail Cable
Lift the fence up. In small sections pull it tightly and connect the bottom of the fencing to the decking
panels near the walkway cables with U-nails or regular nails bent over the edge. Attach the fencing to
each suspender with galvanized tie-wire.
Step 2
Pull the Fence Tightly and Connect to Deck and Suspenders
Uncoil the fence onto the ground (or the bridge) and stretch the wire out as much as possible. Several
rolls may need to be used depending on the length of the bridge. Connecting one roll to the other is by
placing the 2 ends one by the other (making sure both ends facing the same direction) and weaving an
opposite direction wire in between. Same method is applied to cut the excess length.
Step 1
Unroll Fencing and Connect Rolls
Materials Required
Galvanized fencing mesh (recommended 1.2 meters high)
U-nails
Galvanized Tie wire
Tools Required
Wire Cutters
Pliers
95
Volume 3: Suspended
Decking
Approach
Decking in place and properly coated with water sealant if not pre-treated?
Was the excess cable stored inside approach unless malleable clamps?
96
97
and following the completion. It is ideal to complete the survey several times throughout the lifespan of the bridge, as the impact of the bridge may not be immediately
Pedestrian bridges have varying impacts on differing communities. Most typically, economic stimulus is evident from the increased access and drastic improvements
in public health and education are seen as well. But bridges may also create problems, unforeseen during the initial bridge assessment (completed before the bridge
project was started--see Volume 2).
SOCIOECONOMIC IMPACT
The Bridge Registry must be completed following the completion of the bridge. The purpose of the registration is to create institutional memory surrounding a project.
This includes technical data such as the size of the cable and clamps, the span and assumptions used in the design. Furthermore, often engineers may opt to modify
the standard design or the construction supervisor may chose to alter materials based on availability. All of this information is critical to document to ensure future
parties involved in the maintenance and upkeep of the bridge are able to do so with a full understanding of the structure. The Registry also includes information
surrounding the personnel involved in the project and information about the geographic location of the bridge.
BRIDGE REGISTRY
Volume 3: Suspended
7.2
7.1
The Bridge Registration includes both a technical As-Built assessment of the bridge as well as a socioeconomic survey evaluating the impact of the bridge on the local
community. The agency responsible for the construction of a bridge needs to keep records of this information for all completed bridge projects. Bridges to Prosperity
also asks to receive a copy. By keeping record of completed projects, this ensures any follow-up quality control inspections and third party monitoring are able to
fully understand the structure as it was built before starting the assessment, and furthermore helps quantify the impact of the bridge on the community. As such, the
submittal of the Bridge Registry to B2P is required for all co-sponsored bridges, and appreciated for all others. Please contect B2P at info@BridgestoProsperity.org
SECTION 7:
BRIDGE COMPLETION
THIRD EDITION
2013
VOLUME 3. 4
B2P_manual_05.indd 8
8/16/13 2:51 PM
Introduction
Maintenance is the essential to the safety of all bridge projects. Following the project completion, the community,
local government, and bridge owners are responsible for monitoring the bridge to ensure safety and for performing
basic maintenance.
Bridges to Prosperity keeps a database of completed bridge projects. This system ensures any follow-up quality
control teams are able to fully understand the as-built structure before starting the assessment. The system also
helps quantify the impact of the bridge on the community. As such, the submittal of the Bridge Registry to B2P is
required for all co-sponsored bridges, and appreciated for all others. Section 1 introduces the bridge registry. All
referenced forms are included in Section 5 of this manual.
Bridge maintenance includes both general annual bridge upkeep and scheduled quality control assessments. The
community is responsible for general bridge upkeep and the local sponsoring institution (typically the government
body) is responsible for returning to the site for thorough bridge inspections.. The Bridge Committee (reference
Volume 1) must designate a person or team of people to inspect the structure after every rainy season. Section 2
of this manual addresses what this team must check annually.
The bridge Construction Manager must specify the party or agency responsible for the quality control reviews
to 10 years after completion. If Bridges to Prosperity is directly involved in the construction of the bridge, B2P
will work with the agency to designate responsibility. Section 3 address the quality control requirements for the
full technical assessments, and Section 4 outlines required maintenance and may be used as a resource for
Bridges to Prosperity (contact at www.BridgestoProsperity.org) immediately, irrespective of our involvement.
Volume 3: Suspended
Bridge Registry
Socioeconomic Implications
Bridge Registration Form
Socioeconomic Survey
Materials Required
Quality Control Overview
Refer to 5.3
Section 4: Maintenance
4.1
4.2
4.3
4.4
4.5
4.6
Volume 3: Suspended
SECTION 1:
AS-BUILT BRIDGE REGISTRATION
1.1
Bridge Registry
1.2
Socioeconomic Implications
Volume 3: Suspended
Volume 3: Suspended
A. Site
D. Towers
Left side
D1- Rebar installation in Tower
D2- Complete Tower
D3- Saddle alignment
D4- Walkway hump
Right side
D5- Rebar installation in Tower
D6- Complete Tower
D7- Saddle alignment
D8- Walkway hump
E. Anchors
Left side
E1- Completed rebar cage
E2- Cross-section of cable (for size)
E3- Cable position in excavation
E4- Completed anchor
Right side
E5- Completed rebar cage
E6- Cross-section of cable (for size)
E7- Cable position in excavation
E8- Completed anchor
F. Sag Setting
F1- Handrail cables aligned
F2- Walkway cables aligned
F3- Clamp spacing
F4- Torque technic used
F5- Representative photo of clamped cable
Left side
G1- Thickness of approach walls
Volume 3: Suspended
Volume 3: Suspended
Volume 3: Suspended
Remove any excess mud and debris from the bridge deck.
Ensure weeds and plants growing beneath the bridge do not obstruct the bridge.
Ensure all bolts, screws and nails are in place and tightened.
Ensure that fencing is secure. Should any wires be loose or fencing missing, repair or replace to original
condition.
Check for erosion. Should erosion or scour occur, causing the water to reroute toward the anchor or approach,
contact the local supporting agency and request assistance with a drainage structure.
Measure the distance between the paint on the cable and the saddle guides (inset bottom right). If more
than half meter, local supporting agency immediately and if possible, Bridges to Prosperity (contact at www.
BridgestoProsperity.org).
Volume 3: Suspended
SECTION 3:
QUALITY CONTROL INSPECTION
To ensure an adequate inspection has been completed for each bridge, a Quality Control Inspection & Picture Inventory
are required for all quality control inspections completed on behalf of Bridges to Prosperity. For those tracking bridges
be inspected without the design engineer on-site and furthermore, by someone without an engineering background.
manual.
To complete the quality control inspection, prepare yourself by reading the As-Built Bridge Registry and spend time
looking through pictures. Take special note of the size of the cables, for this will dictate the size of torque wrench
socket required. If a previous quality control review has been completed, also review the inspectors comments and
concerns. If not familiar with how to use and read a torque wrench, reference Volume 3, Part 3: Construction Manual.
3.1
Materials Required
3 meter measuring tape
Digital Camera
Torque Wrench
Socket (sized to correspond to cable diameter)
Pen & paper
Copy of Quality Control Inspection (Form)
Volume 3: Suspended
10
3.2
Technical Inspection
Following the completion of the bridge, a follow-up quality control inspection must be completed a minimum of
bridge must be reviewed by an engineer to ensure safety of cables, structure and decking.
The Quality Control Inspection Report in Section 5 includes the following items;
Overall Site Evaluation
Foundation Tiers & Towers
Anchors
Cable Condition
Cable Clamps
Approach Walls & Ramp
Decking
For each sub-section, an adjoining chapter is included in Section 4: Maintenance; Section 4 must be referenced for
keep one copy of each report and send a copy to Bridges to Prosperity (contact at www.BridgestoProsperity.org).
Volume 3: Suspended
11
Site Evaluation
Inspect the area surrounding the bridge, on both abutments.
Take special note if erosion has occurred and what the drainage
path of run-off water appears to take. If the erosion has caused
scour, undercutting the anchor, approach or foundation structure,
reference the maintenance section.
For all following sections, reference Section 4: Maintenance to
address any possible concerns. If the manual does not address
www.BridgestoProsperity.org).
Include the following pictures on disk or in printed form and attach
to Quality Control Inspection report;
Left and Right abutment general picture
Pictures of bridge in use (people, livestock etc.)
Notes on site evaluation, include drainage concerns:
Volume 3: Suspended
12
Anchors
Inspect the area surrounding the anchors (far back side of
approach, on both abutments. Take special note if erosion has
occurred and what the drainage path of run-off water appears to
take. If the erosion has caused scour, undercutting the anchor,
reference the maintenance section.
Walk behind the approach, if possible. The view should be
similar to that in the picture to the right. For soil conditions,
the anchor is a large beam, as shown in the picture to the right.
Note if the cable is kinked at the saddles, implying the cable
is not wrapped directly behind the corresponding cable saddle
(handrail on outsides, walkway on inside, as shown to right).
For rock conditions, the anchor is a cylindrical drum. The cables also should come straight off the saddles, as shown in the
diagram to the bottom right. Note is the cable is kinked.
Include the following pictures with report:
Picture from behind abutment & ramp, on either abutment
Volume 3: Suspended
13
Cable Condition
Inspect the cable at all points of insertion into concrete, the approach or the
ground. Inspect general cable condition and note if loose strands occur
anywhere along the cable.
Note the slide of the cable. Reference the colored mark on the cable, which
originated between guides on saddles. If the amount of movement exceeds
1 % of length of cable (see Span on Quality Control Page 1), cable slip or
excessive cable stretch has occurred (assume 2% equally divided between
two sides as an upper limit of concern). Please contact B2P immediately
(contact information at www.BridgestoProsperity.org).
Include the following pictures with report:
Cable insertion into approach, if any corrosion or rust appears
Pictures of all four (4) handrail saddle pictures: look for amount of
slide for mark on cable.
Volume 3: Suspended
14
Volume 3: Suspended
15
Decking
Rate the condition of the deck panels. Note if any longitudinal deck
panels are missing. Note if rot has occurred and to what extent.
Document with pictures, quantity and extent of rot and opinion of current
usability.
Rate condition of cross beams (transverse beams, likely will need to go
below deck). Note if any cracking between suspender drill hole and end
of beam. Note any structural damage (split beams, missing sections of
beams etc.). Note if rot has occurred and to what extent. Document
with pictures, quantity and extent of rot and opinion of current usability.
Include the following pictures with report:
General decking condition
Full-Bridge Photos
Volume 3: Suspended
16
Section 4:
Maintenance
This section includes mandatory upkeep items to be completed during every Quality Control Inspection, as well as solutions
to repair bridge components found to be substandard during inspections.
The Maintenance chapter includes the following sections:
4.1
4.2
4.3
4.4
4.5
4.6
4.1
If the Quality Control Inspection notes that erosion and scour are undermining the bridge structure, a drainage structure may
allow the water to reroute, thus saving the structure from further damage.
recommended to avoid sites where any instability is prevalent. If unavoidable, it is necessary to drain out the runoff and
seepage to ensure the stability of the slope and to avoid under-scour of structures. Water should be collected as closely
as possible to its origin and navigated away from the bridge structures. A surface catch drain on a slope may be required,
drainage around the structure or both.
Below right if an example subsurface drainage systems, and bottom right are example surface drainage systems. For further
details, reference Volume 2.
Subsurface Drainage
Surface Drainage
Volume 3: Suspended
17
4.2
4.3
Anchors
If the Quality Control Inspection notes that erosion and scour are undermining the anchor, a drainage structure may allow the
water to reroute, thus saving the structure from further damage. See section 4.3.1 and reference Volume 2 for further details
on drainage structures.
4.4
If the cable is found to be corroding or fraying, estimate the percentage of the cable cross-section that has been damaged.
If greater than 10% of cable is fraying, evaluate the extent of the damage. If localized in one point, consider a splice.
Reference cable-manufacturing materials for details. If evaluated to have extensive damage, close the bridge until cable can
be replaced with new cables. If this occurs, contact Bridges to Prosperity to describe situation, providing pictures and details
when possible (contact at www.BridgestoProsperity.org).
If the clamps are found to have less than 80% of required torque,
each above-ground clamp must be re-tightened. The picture to the
top right depicts the cross-sectional reduction that is required when
the clamps are fully torqued (assuming drop-forged, not malleable.
For more information, see Volume 3, Part 3). Bottom right shows the
proper length of the breaker bar or torque wrench required to apply the
adequate amount of torque.
If the clamps are found to have less than 60% of the required torque,
additional clamps must be added. In severe cases the approach should
be removed to tighten clamps below ground.
4.5
Volume 3: Suspended
18
4.6
Decking
If any decking panels are rotting through or missing entirely, they must be replaced. The standard thickness of a decking
drawings for complete details. Note that the pattern of laying the deck panels requires an alternation, as shown in the picture
to the right.
If any crossbeams are in need of replacement, either an additional board must be attached to the bottom as reinforcement
or the beam must be replaced.
If replacement is chosen, start by removing the deck panels directly above the crossbeam in question. Unwrap the fencing
in the direct location; cutting may be required. Secondly, unwrap the suspenders from the top of the cable, which likely will
Volume 3, Part 3 Construction for details. Complete the process by screwing and nailing the deck boards back into place.
Replace and repair any damaged fencing before leaving.
Volume 3: Suspended
19
Volume 3: Suspended
20