Sie sind auf Seite 1von 818

A Note

B Quick
C BSR 1 -Standard BSR
D Concrete misallanious
E Termite Treatment
Water proofing
F Plumbing - Gauge 600
G Electrical Work
H Doors & Window - 01 (Red Balow)
K Doors & Window - 02 (Teak)
L Doors & Window - 03
M Roof Work / Canopy
Roof plumbing
Roof insulation
N Roof Fram Work
O Special Floor Finishes
P Special Wall Finishes
Q Special Ceiling Finishes
R Special Man Holes
S Sanitary Fittings
T Timber Work
U Metal work
V Type of boundary walls
W Misallanious
X Painting
Y
Z Material Index
MAIN INDEX
a
Conversion
Steel
Level to level
Concrete grade
General notes
Formulas
Triangle
Circle
Ellipse
Traprzoid
Hexagon
Sphere
Pyramide
Cone
CONVERSION
Note
1 Perch = 272.25 ft
2
1 Perch = 0.25 Rood
1 Rood = 40 Perch
1Rood = 0.25 Acres
1 Acres = 0.405 Hectares
1 Acres = 4 Rood
1 Acres = 160 Perch
1 Hectares = 2.47 Acres
1 Hectares = 9.88 Rood
1 Hectares = 395.37 Perch
1 m
2
= 10.76 ft2
=
=
=
=
=
1 ft = 30.48 cm
1 m = 3.28 L.ft
1 m = 1.094 Yards
1 miles = 1.61 Km
3 ft = 1 Yards
1 miles = 5280 ft
=
=
=
=
1 Kg = 35.27 Ounce
1 Kg = 2.21 Pound
1 Pound = 16 Ounce
1 Tone = 2204.6 Pound
1 Tone = 1000 kg
1 Cwt = 50 Kg
=
=
=
=
=
1 m
3
= 35.315 ft
3
1 m
3
= 220 Gallon
A
r
e
a
D
i
s
t
a
n
c
e
M
a
s
s
V
o
l
u
m
e
A
D
M
1 m
3
= 1000 Liter
1 Cube = 2.83 m3
1 Cube = 100 ft
3
1 Gallon = 4.54 Liter
=
=
=
=
=
6 mm Dia. 1 m = 0.222 Kg
10 mm Dia. 1 m = 0.617 Kg
12 mm Dia. 1 m = 0.889 Kg
16 mm Dia. 1 m = 1.58 Kg
20 mm Dia. 1 m = 2.469 Kg
25 mm Dia. 1 m = 3.858 Kg
32 mm Dia. 1 m = 6.321 Kg
Unit Ground To First Floor Ground To Second Floor
Concrete Cube 3% 5%
9" Brick Work Sqr 5% 7%
9" Brick Work Cube 5% 7%
4
1
/
2
" Brick Work Sqr 5% 7%
Reinforcement Cwt 2.50% 5%
LEVEL TO LEVEL
STEEL
V
o
l
u
m
e
V
Plastering Sqr 5% 10%
Painting Sqr 3% 6%
Floor Tiling Sqr 2% 4%
Wall Tilling Sqr 2% 4%
Roof Calicut Tiles Sqr 3% 6%
Roof Asbestos Sqr 3% 5%
Ceiling Work Sqr 3% 5%
1 : 3 : 6 = Grade- 10
1 : 2
1
/
2
: 5 = Grade- 15
1 : 2 : 4 = Grade- 20
1 : 1
1
/
2
: 3 = Grade- 25
1 : 1 : 2 = Grade- 30
@
@
FORMULAS
1 m
3
OF CONCRETE NEED FOR 100 Kg STEEL
1 TRACTOR LOAD HAVE TO 0.75 Cube
CONCRETE GRADES
GENERAL NOTES
*** Triangles
Area of all Triangles
Area = Base X Perpendicular Height
2
Area = bc Sin C = ab Sin C = ac Sin B
2 2 2
Area of equilateral Triangle
Area = 0.433 x Side
2
*** Circle
Circumference of a Circle
C = d = 2 r
Area of a Circle
Area = r
2
= circumferenece x r
2
Area of a Sector of a Circle
A = arc x r
2
A = x r ( = angle in degrees )
360
A
B
c
b
a
h

d
r
A = r ( = angle in radians )
2
*** Ellipse
Area of Ellipse
A = x Dd
4
Circumference of Trapeziod
Approx. Circumference = ( D+d)
2
*** Trapezoid
Area of trapeziod
A = a+b h
2
D
d
a
b
h
r
*** Hexagon
Area of Hexagon
A = 2.6 s
Where S = Length of one side
*** Sphere
Total surface area of sphere
A = 4 r
2
Surface area of segment
A
s
= dh
Volume
V = 4 r
3
3
Volume of segment
V
s
= h
2
( 3r -h)
3
V
s
= h (h
2
- 3a
2
)
6
Where a = radius of segment base
*** Pyramid
Volume of pyramid
s
h
r
V = Base Area X Perpendicular Height
3
Volume of frustum
V
F
= h ( A + a + Aa )
Where h = Perpendicular height
*** Cone
Area of curved surface of cone
A = DL
2
Area of curved surface of frustum
A
F
= ( D+d ) L
2
Volume of cone
V = Base Area X Perpendicular Height
3
Volume of frustum
V
F
= Perpendicular Height x ( R
2
+ r
2
+Rr )
3
a
A
h
L
D
d
D
Tor Steel Mild Steel
(6 x 6) /162
(10 x 10) /162
270 270
(12 x 12) /162
187 187
(16 x 16) /162
105 105
(20 x 20) /162
67 67
(25 x 25) /162
43 43
(32 x 32) /162 26 26
Ground To Third Floor
7%
9%
10%
10%
7.50%
LEVEL TO LEVEL
No. of 6m rods per
metric Ton (Average)
STEEL
15%
9%
6%
6%
9%
7%
7%
C
a
segment
triangle
arc
Frustum
L
GRADE Item Discription Unit
EXCAVATION &
EARTHWORK EXCAVATION & EARTHWORK
EXCAVATION &
EARTHWORK A 01
Clearing site & grubbing up all small trees not exceeding 500mm
girth & including bushes scrubs, undergrowth hedges etc. Sqr
EXCAVATION &
EARTHWORK A 02
Excavation of top soil of average depth of 6'' and carting away
surplus soil Sqr
EXCAVATION &
EARTHWORK A 03
Drains, earth in any soil except rock requiring blasting cut to
gradient & shape as directed & depositing soil within site Cube
EXCAVATION &
EARTHWORK A 04
Excavate trench for wall foundation in ordinary soil & part
return fill in ram & depoisting surplus excavated material within
site as derected.(not exceeding 5'- 0" deep.) Cube
EXCAVATION &
EARTHWORK A 05
Excavate trench for wall foundation in ordinary soil & part
return fill in ram, & depoisting surplus excavated material within
site as directed.(exceeding 5'-0" but not exceeding
10'-0") Cube
EXCAVATION &
EARTHWORK A 06
Excavate pit for column foundation in any material except rock
requiring blasting, part return fill in ram, & depoisting surplus
excavated material within site as directed.(not exceeding 5'- 0"
deep.) Cube
EXCAVATION &
EARTHWORK A 07
Excavate pit for column foundation in any material except rock
requiring blasting, part return fill in ram, & depoisting surplus
excavated material within site as directed.(exceeding 5'-0" but
not exceeding 10'-0"deep) Cube
EXCAVATION &
EARTHWORK A 08
Cutting & levlling site in any material except rock requiring
blasting including transporting up to 1/4 mile depositing &
leveling Cube
Quick
EXCAVATION &
EARTHWORK A 09
Filling under floors with gravel or other approved quality of
filling, spread, Watered & well rammed in 3'' thick layers.
(Earth available at site) Cube
EXCAVATION &
EARTHWORK A 10
Filling under floors with gravel or other approved quality of
filling, spread, Watered & well rammed in 3'' thick layers.
(earth not avilable at site) Cube
EXCAVATION &
EARTHWORK A 11
Filling under floors with gravel or other approved quality of
filling, spread, Watered & well rammed in 3'' thick
layers.(within Colombo Municipal limits) Cube
EXCAVATION &
EARTHWORK A 12 Earth work support in trenches up to 5' 0'' deep.(open planking) Sqr
EXCAVATION &
EARTHWORK A 13 Earth work support in trenches up to 5' 0'' deep.(close planking) Sqr
EXCAVATION &
EARTHWORK A 14
Earth work support in trenches up to 10' 0'' deep. (close
planking) Sqr
CONCRETE WORK CONCRETE WORK
CONCRETE WORK
CONCRETE WORK
CONCRETE WORK B 01 Concrete 1:3:6 (2") grade 10 Cube
CONCRETE WORK B 02 Concrete 1:3:6 (1") grade 10 Cube
CONCRETE WORK B 03 Concrete 1:2:5 (1") grade 15 Cube
CONCRETE WORK B 04 Concrete 1:2:4 (3/4") grade 20 Cube
CONCRETE WORK B 05 Concrete 1:11/2:3 (3/4") grade 25 Cube
CONCRETE WORK B 05a Concrete1 :1:2 (3/4") grade 30 Cube
CONCRETE WORK B 06
2" thick blinding layer under wall / column foundation (1:3:6 -2")
grade 10 Sqr
CONCRETE WORK B 07
2" thick blinding layer under wall/ column foundation (1:3:6 -1")
grade 10 Sqr
CONCRETE WORK B 08
3" thick blinding layer under wall/ column foundation (1:3:6 -1")
grade 10 Sqr
CONCRETE WORK B 09 4" thick ground floor slab (1:3:6 -1") Grade10 Sqr
CONCRETE WORK B 10
Cement Concrete 1:2:4(3/4) lintol size 41/2'' x 6'' with &
including formwork (reinforcement paid separately) L.ft
CONCRETE WORK B 11
Cement Concrete 1:2:4(3/4") lintol size 6'' x 9'' with &
including formwork (reinforcement paid separately) L.ft
CONCRETE WORK B 12
Cement Concrete 1:2:4(3/4") lintol size 9'' x 9'' with &
including formwork L.ft
CONCRETE WORK B 13
Cement Concrete 1:2:4(3/4") lintol size 9'' x 12'' with &
including formwork L.ft
CONCRETE WORK B 14
Cement Concrete 1:2:4(3/4") lintol size 6'' x 13' 6'' with &
including formwork L.ft
CONCRETE WORK B 15
Cement Concrete 1:2:4(3/4") lintol size 9'' X 13' 6'' with &
including formwork L.ft
CONCRETE WORK B 16
Cement Concrete 1:2:4(3/4") lintol size 12'' x 13' 6'' with
& including formwork L.ft
CONCRETE WORK B 17
Cement Concrete 1:2:4(3/4")lintol size 4 1/2" x4 1/2" with &
including formwork.(rein forcement paid seperately) L.ft
CONCRETE WORK B 18 Concrete column in ground floor (1:2:4 3\4") Cube
CONCRETE WORK B 19 9" x 9" Concrete columns in first floor Cube
CONCRETE WORK B 20 9" x 9" Concrete columns in second floor Cube
CONCRETE WORK B 21 9" x 9" Concrete columns in third floor Cube
CONCRETE WORK B 22
Concrete columns in ground floor 10 no 12"x12" columns each 5'
0" high Cube
CONCRETE WORK B 23 12" x 12" Concrete columns in first floor Cube
CONCRETE WORK B 24 12" x 12" Concrete columns in second floor Cube
CONCRETE WORK B 25 12" x 12" Concrete columns in third floor Cube
CONCRETE WORK B 26 9" x 9" Concrete beams in ground floor level Grade 20 Cube
CONCRETE WORK B 27 9" x 9" Concrete beam in first floor Cube
CONCRETE WORK B 28 9" x 9" Concrete beam in second floor Cube
CONCRETE WORK B 29 9" x 9" Concrete beam in third floor Cube
CONCRETE WORK B 30 Concrete beams in ground floor level Grade 20 Cube
CONCRETE WORK B 31 Concrete beam in first floor Cube
CONCRETE WORK B 32 Concrete beam in second floor Cube
CONCRETE WORK B 33 Concrete beam in third floor Cube
CONCRETE WORK B 34 Concrete beams in ground floor level Cube
CONCRETE WORK B 35 Concrete beam in first floor Cube
CONCRETE WORK B 36 Concrete beam in second floor Cube
CONCRETE WORK B 37 Concrete beam in third floor Cube
CONCRETE WORK B 38 4" thick Concrete slab in first floor Grade 20 Sqr
CONCRETE WORK B 39 4" thick Concrete slab in second floor Sqr
CONCRETE WORK B 40 4" thick Concrete slab in third floor Sqr
CONCRETE WORK B 41 5" thick Concrete slab in first floor Sqr
CONCRETE WORK B 42 5" thick Concrete slab in second floor Sqr
CONCRETE WORK B 43 5" thick Concrete slab in third floor Sqr
CONCRETE WORK B 44 6" thick Concrete slab in first floor Sqr
CONCRETE WORK B 45 6" thick Concrete slab in second floor Sqr
CONCRETE WORK B 46 6" thick Concrete slab in third floor Sqr
CONCRETE WORK B 47
Cement Concrete 1:11/2:3(3/4") lintol size 4' 6''x 6'' with
& including formwork (reinforcement paid seperately) L.ft
CONCRETE WORK B 48
Cement Concrete 1:11/2:3(3/4") lintol size 6'' x 9'' with &
including formwork (reinforcement paid seperately) L.ft
CONCRETE WORK B 49
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 9'' with &
including formwork (reinforcement paid separately) L.ft
CONCRETE WORK B 50
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 12'' with &
including formwork (reinforcement paid separately) L.ft
CONCRETE WORK B 51
Cement Concrete 1:11/2:3(3/4") lintol size 6'' x 13' 6'' with &
including formwork (reinfrcement paid separately) L.ft
CONCRETE WORK B 52
Cement Concrete 1:11/2:3(3/4") lintol size 9'' x 13 ' 6''
with & including formwork (reinforcement paid separately) L.ft
CONCRETE WORK B 53
Cement Concrete 1:11/2:3 (3/4") lintol size 12'' x 13' 6''
with & including formwork (reinforcement paid separately) L.ft
CONCRETE WORK B 54
Cement Concrete 1:11/2:3(3/4") lintol size 4' 6'' x 4' 6''
with & including formwork (reinforcement paid separately) L.ft
CONCRETE WORK B 55
Concrete colomns in ground floor 1 : 1 1/2 : 3(3/4") 16
no 9" x 9" columns each 5'0" high Cube
CONCRETE WORK B 56 9" x 9" Concrete colomns in first floor Cube
CONCRETE WORK B 57 9" x 9" Concrete colomns in second floor Cube
CONCRETE WORK B 58 9" x 9" Concrete colomns in third floor Cube
CONCRETE WORK B 59 Concrete colomns in ground floor Cube
CONCRETE WORK B 60 12" x 12" Concrete colomns in first floor Cube
CONCRETE WORK B 61 12" x 12" Concrete colomns in second floor Cube
CONCRETE WORK B 62 12" x 12" Concrete colomns in third floor Cube
CONCRETE WORK B 63 9" x 9" Concrete beams in ground floor level Cube
CONCRETE WORK B 64 9" x 9" Concrete colomns in first floor Cube
CONCRETE WORK B 65 12" x 12" Concrete colomns in second floor Cube
CONCRETE WORK B 66 12" x 12" Concrete colomns in third floor Cube
CONCRETE WORK B 67 Concrete beam in ground floor level 9" x 12" Cube
CONCRETE WORK B 68 Concrete beam in first floor 9" x 12" Cube
CONCRETE WORK B 69 Concrete beam in second floor 9" x 12" Cube
CONCRETE WORK B 70 Concrete beam in third floor 9" x 12" Cube
CONCRETE WORK B 71 Concrete beam in ground floor level 12" X 12" Cube
CONCRETE WORK B 72 Concrete beam in first floor 12" x 12" Cube
CONCRETE WORK B 73 Concrete beam in second floor 12" x 12" Cube
CONCRETE WORK B 74 Concrete beam in third floor 12" x 12" Cube
CONCRETE WORK B 75 4" thick Concrete slab in first floor Cube
CONCRETE WORK B 76 4" thick Concrete slab in second floor Cube
CONCRETE WORK B 77 4" thick Concrete slab in third floor Cube
CONCRETE WORK B 78 5" thick Concrete slab in first floor Sqr
CONCRETE WORK B 79 5" thick Concrete slab in second floor Sqr
CONCRETE WORK B 80 5" thick Concrete slab in third floor Sqr
CONCRETE WORK B 81 6" thick Concrete slab in first floor Sqr
CONCRETE WORK B 82 6" thick Concrete slab in second floor Sqr
CONCRETE WORK B 83 6" thick Concrete slab in third floor Sqr
FORM WORK FORM WORK
FORM WORK
FORM WORK
B 84
&
B 85 Sawn formwork in sides of column foundation up to D.P.C level Sqr
FORM WORK B 86 Sawn formwork in 9"X 9" column in ground floor Sqr
FORM WORK B 87 Sawn from work in 9"x9" column in first floor Sqr
FORM WORK B 88 Sawn from work in 9"x9" column in Second floor Sqr
FORM WORK B 88a Sawn from work in 9"x9" column in third floor Sqr
FORM WORK B 89 Sown form work in 9"x 12" beam in ground floor 20'-0" long Sqr
FORM WORK B 90 Sawn from work in 9"x12" column in first floor Sqr
FORM WORK B 91 Sawn from work in 9"x12" column in Second floor Sqr
FORM WORK B 92 Sawn from work in 9"x12" column in third floor Sqr
FORM WORK B 93 Sawn formwork for sofit of first floor slab Sqr
FORM WORK B 94 Sawn formwork in soffit of slab second flor Sqr
FORM WORK B 95 Sawn formwork in soffit of slab third flor Sqr
REINFORCEMENT REINFORCEMENT
REINFORCEMENT
REINFORCEMENT B 96
25 mm & 20mm dia tor steel reinforcement in fdn, Ground &
first level. kg
REINFORCEMENT
B 98
16mm dia tor steel reinforcement up to first level. kg
REINFORCEMENT
B 99
12mm dia &10mm dia tor steel reinforcement up to first level. kg
REINFORCEMENT
B 111
25mm dia &20mm dia tor steel reinforcement in second floor kg
REINFORCEMENT
B 113
16mm dia tor steel reinforcement in second floor level & third
floor level kg
REINFORCEMENT
B 114
12mm & 10mm dia tor steel reinforcement in second floor level
& third floor level kg
REINFORCEMENT
B 116
10mm & 6mm dia mild steel reinforcement up to first floor level kg
REINFORCEMENT
B122
10mm & 6mm dia mild steel reinforcement in second floor level &
third floor level kg
BRICK WORK BRICK WORK
BRICK WORK C 01
01- One brick thick brick wall in common brick in cement &
sand 1:5 in ground floor level Cube
BRICK WORK C 02
One brick thick brick wall in common brick in cement & sand 1:5
in first floor Cube
BRICK WORK C 03
One brick thick brick wall in common brick in cement & sand 1:5
in second floor Cube
BRICK WORK C 04
Half brick thick brick wall in common brick in cement & sand 1:5
in ground floor Sqr
BRICK WORK C 05
Half brick thick brick wall in common brick in cement & sand 1:5
in first floor Sqr
BRICK WORK C 06
Half brick thick brick wall in common brick in cement & sand 1:5
in second floor Sqr
BRICK WORK C 07 9''X 9'' Brick column in cement & sand 1: 5 in ground floor L.ft
BRICK WORK C 08 9''X 9'' Brick column in cement & sand 1: 5 in first floor L.ft
BRICK WORK C 09 9''X 9'' Brick column in cement & sand 1: 5 in second floor L.ft
BRICK WORK C 10 12''X 12'' Brick column in cement & sand 1: 5 in ground floor L.ft
BRICK WORK C 11 12''X 12'' Brick column in cement & sand 1: 5 in first floor L.ft
BRICK WORK C 12 12''X 12'' Brick column in cement & sand 1: 5 in second floor L.ft
BRICK WORK C 13
One brick thick brick wall in common brick in cement & sand 1:5
in ground floor level Sqr
BRICK WORK C 14
One brick thick brick wall in common brick in cement & sand 1:5
in first floor level Sqr
BRICK WORK C 15
One brick thick brick wall in common brick in cement & sand 1:5
in second floor level Sqr
RUBBLE WORK RUBBLE WORK
RUBBLE WORK
RUBBLE WORK D 01
6" X 9" Random rubble Masonry in cement & sand 1:5 in
foundation Cube
RUBBLE WORK D 02
6" X 9" Random rubble Masonry in cement & sand 1:5 in 1' 6"
thick wall Sqr
RUBBLE WORK D 03
6" X 9" Random rubble Masonry in cement & sand 1:5 in 2' 0"
thick wall Sqr
RUBBLE WORK D 04
6" X 9" Random rubble Masonry in cement & sand 1:5 in 2' 6"
thick wall Sqr
RUBBLE WORK D 05
8" thick Solid block work in cement & sand 1;5 in ground floor
(cavites un filled)
Sqr
RUBBLE WORK D 06
4" thick Solid block work in cement & sand 1:5 in ground floor (
cavite un filled)
Sqr
RUBBLE WORK D 07
6" thick Solid block work in cement & sand 1;5 in ground floor
(Cavity un filled)
Sqr
RUBBLE WORK D 08
8" thick Solid block work in cement & sand 1;5 in first
floor(cavities un filled)
Sqr
RUBBLE WORK D 09
4" thick Solid block work in cement & sand 1;5 in first
floor(cavities un filled)
Sqr
RUBBLE WORK D 10
6" thick Solid block work in cement & sand 1;5 in first
floor(cavities un filled)
Sqr
RUBBLE WORK D 11
8" thick Solid block work in cement & sand 1;5 in second
floor(cavities un filled)
Sqr
RUBBLE WORK D 12
4" thick Solid block work in cement & sand 1;5 insecond
floor(cavities un filled)
Sqr
RUBBLE WORK D 13
6" thick Solid block work in cement & sand 1;5 in second
floor(cavities un filled)
Sqr
RUBBLE WORK D 14
8" thick Hollow block work in cement & sand 1;5 in ground floor
(cavites un filled)
Sqr
RUBBLE WORK D 15
4" thick Hollow block work in cement & sand 1:5 in ground floor
( cavite un filled)
Sqr
RUBBLE WORK D 16
6" thick Hollow block work in cement & sand 1;5 in ground floor
(Cavity un filled)
Sqr
RUBBLE WORK D 17
8" thick Hollow block work in cement & sand 1;5 in first
floor(cavities un filled)
Sqr
RUBBLE WORK D 18
4" thick Hollow block work in cement & sand 1;5 in first
floor(cavities un filled)
Sqr
RUBBLE WORK D 19
6" thick Hollow block work in cement & sand 1;5 in first floor
(cavities un filled)
Sqr
RUBBLE WORK D 20
8" thick Hollow block work in cement & sand 1;5 in second
floor(cavities un filled)
Sqr
RUBBLE WORK D 21
4" thick Hollow block work in cement & sand 1;5 insecond
floor(cavities un filled)
Sqr
RUBBLE WORK D 22
6" thick Hollow block work in cement & sand 1;5 in second
floor(cavities un filled)
Sqr
ROOF WORK ROOF WORK
ROOF WORK
ROOF WORK E 01
Calicut pattern tile hip roof in single storey building consisting of
wall plate ridge plate beam struct rafters & reepers. Sqr
ROOF WORK E 02
Calicut pattern ridge tile hip tile on single storey building in
cement lime & sand 1;1;5 coloured to match tile L.ft
ROOF WORK E 03
Corrugated asbastos cement sheet roofing with Timber fram in
single storeyed building. Sqr
ROOF WORK E 04
Asbastos ajestable close fitting ridge fixed complete with
roofing screws or bolts L.ft
ROOF WORK E 05
Corrugated asbastos cement sheet rooing with Timber frame in
single storeyed building. Sqr
ROOF WORK E 06 Half round tile on asbastos sheet roof (crest only ) Sqr
ROOF WORK E 07
3/4" thick 9" high valance board fixed with brass screws to end
of rafters with & including one coat of primer & two coats of
enamel paint L.ft
ROOF WORK E 08
Asbastos cement plian sheet ceiling with class 1 Timber frame
consisting of 4''x2"joist 2"x2" & 2"x1" battens 11/2" x11/2"
cove moulding & 1/2"x1/2" beadings with painting Sqr
ROOF WORK E 09
3/4" thick class 1 Timber ceiling with class 1 Timber frame
consisting of 4''x2"joist 2"x2" & 2"x1" battens 11/2" x11/2"
cove moulding with painting Sqr
PLUMBING WORK PLUMBING WORK
PLUMBING WORK
PLUMBING WORK F 01 20mm diameter pvc pipe fixed to wall or slab L.ft
PLUMBING WORK F 02 25mm diameter pvc pipe fixed to wall or slab L.ft
PLUMBING WORK F 03 32mm diameter pvc pipe fixed to wall L.ft
PLUMBING WORK F 04 32mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 05 40mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 06 40mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 07 50mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 08 50mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 09 63mm diameter pvc pipefix to wall L.ft
PLUMBING WORK F 10 63mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 11 75mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 12 75mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 13 90mm diameter pvc pipe fix to wall L.ft
PLUMBING WORK F 14 90mm diameter pvc pipe laying trench L.ft
PLUMBING WORK F 15 Supplying & fixing PVC bend 20mm dia. No
PLUMBING WORK F 16 Supplying & fixing PVC bend 25mm dia. No
PLUMBING WORK F 17 Supplying & fixing PVC bend 32mm dia. No
PLUMBING WORK F 18 Supplying & fixing PVC bend 40mm dia. No
PLUMBING WORK F 19 Supplying & fixing PVC bend 50mm dia. No
PLUMBING WORK F 20 Supplying & fixing PVC bend 63mm dia. No
PLUMBING WORK F 21 Supplying & fixing PVC elbow 20mm .dia. No
PLUMBING WORK F 22 Supplying & fixing PVC elbow 25mm .dia. No
PLUMBING WORK F 23 Supplying & fixing PVC elbow 32mm .dia. No
PLUMBING WORK F 24 Supplying & fixing PVC elbow 40mm .dia. No
PLUMBING WORK F 25 Supplying & fixing PVC elbow 50mm .dia. No
PLUMBING WORK F 26 Supplying & fixing PVC elbow 63mm .dia. No
PLUMBING WORK F 27 Supplying & fixing PVC tee 20mm .dia. No
PLUMBING WORK F 28 Supplying & fixing PVC tee 25mm .dia. No
PLUMBING WORK F 29 Supplying & fixing PVC tee 32mm .dia. No
PLUMBING WORK F 30 Supplying & fixing PVC tee 40mm .dia. No
PLUMBING WORK F 31 Supplying & fixing PVC tee 50mm .dia. No
PLUMBING WORK F 32 Supplying & fixing PVC tee 63mm .dia. No
PLUMBING WORK F 33 Supplying & fixing PVC faucet socket 20 mm dia No
PLUMBING WORK F 34 Supplying & fixing PVC faucet socket 25 mm dia No
PLUMBING WORK F 35 Supplying & fixing PVC faucet socket 32 mm dia No
PLUMBING WORK F 36 Supplying & fixing PVC faucet socket 40 mm dia No
PLUMBING WORK F 37 Supplying & fixing PVC faucet socket 50 mm dia No
PLUMBING WORK F 38 Supplying & fixing PVC faucet socket 63 mm dia No
PLUMBING WORK F 39 Supplying & fixing PVC Value socket 20 mm dia No
PLUMBING WORK F 40 Supplying & fixing PVC value socket 25 mm dia No
PLUMBING WORK F 41 Supplying & fixing PVC value socket 32 mm dia No
PLUMBING WORK F 42 Supplying & fixing PVC value socket 40 mm dia No
PLUMBING WORK F 43 Supplying & fixing PVC value socket 50 mm dia No
PLUMBING WORK F 44 Supplying & fixing PVC value socket 63 mm dia No
PLUMBING WORK F 45 Supplying & fixing PVC socket 20 mm dia No
PLUMBING WORK F 46 Supplying & fixing PVC socket 25 mm dia No
PLUMBING WORK F 47 Supplying & fixing PVC socket 32 mm dia No
PLUMBING WORK F 48 Supplying & fixing PVC socket 40 mm dia No
PLUMBING WORK F 49 Supplying & fixing PVC socket 50 mm dia No
PLUMBING WORK F 50 Supplying & fixing PVC socket 63 mm dia No
PLUMBING WORK
F.51 Supplying & fixing PVC socket 63 mm dia No
PLASTER WORK PLASTER WORK
PLASTER WORK
PLASTER WORK G 01
3/4" Thick plaster in cement lime & sand 1:1:5 finished smooth
with neat lime in internal wall in ground floor Sqr
PLASTER WORK G 02
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi
rough in external wall in ground floor Sqr
PLASTER WORK G 03
3/4" Thick plaster in cement lime & sand 1:1:5 finished smooth
in internal wall in first floor Sqr
PLASTER WORK G 04
3/4" Thick plaster in cement lime & sand 1;1;5 finished semi
rough in external wall in first floor Sqr
PLASTER WORK G 05
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi
rough in internal wall in second floor Sqr
PLASTER WORK G 06
3/4" Thick plaster in cement lime & sand 1:1:5 finished semi
rough in external wall in second floor Sqr
PLASTER WORK G 07
1/2" Thick sides & soffits plaster in first floor slab in
cement lime & sand 1:1:5 finished smooth with neat lime. Sqr
PLASTER WORK G 08
1/2" Thick sides & soffits plaster in second floor slab in
cement lime & sand 1;1;5 finished smooth with neat lime Sqr
PLASTER WORK G 09
3/4" thick D.P.C. in cement and sand 1:3 finished with two
coats of hot tar and blinded with sand. Sqr
PLASTER WORK G 10
1/2" Thick sides & soffits plaster in first floor beam in
cement lime & sand 1:1:5 finished smooth with neat lime Sqr
PLASTER WORK G 11
1/2" Thick sides & soffits plaster in second floor beam in
cement lime & sand 1:1:5 finished smooth with neat lime Sqr
PAVING WORK PAVING WORK
PAVING WORK
PAVING WORK H 01
3" Thick brick paving lime & sand 1:5 with & including 1/2" thick
cement & sand 1:3 rendering finished smooth with neat cement Sqr
PAVING WORK H 02
1/2" Thick cement rendering in cement & sand 1':3 finished
smooth with neat cement Sqr
PAVING WORK H 03
6" X6" White glazed tile including joint and point with tile grout
& including 3/4" tk cement ^& sand 1;3 screed backing on
ground floor Sqr
PAVING WORK H 04
8" X8" White glazed tile including joint and point with tile grout
& including 3/4" tk cement & sand 1;3 screed backing on ground
floor Sqr
PAVING WORK H 05
12" X12" White glazed tile including joint and point with tile
grout & including 3/4" tk cement & sand 1;3 screed backing on
ground floor Sqr
PAVING WORK H 06
6" X6" White glazed wall tile including joint and point with tile
grout & including 3/4" tk cement & sand 1;3 screed backing on
wall Sqr
PAVING WORK H 07
8" X12" White glazed wall tile including joint and point with tile
grout & including 3/4" tk cement & sand 1;3 screed backing on
wall Sqr
PAVING WORK H 08
8" X8" White glazed wall tile including joint and point with tile
grout & including 3/4" tk cement & sand 1;3 screed backing on
wall Sqr
PAINTING WORK PAINTING WORK
PAINTING WORK
PAINTING WORK J 01
Prepare & apply approved type one coat of filler & two of
emulsion paint to specified colour in ground floor internally Sqr
PAINTING WORK J 02
Prepare & apply approved type one coat of filler & two of
emulsion paint to specified colour in first floor internally Sqr
PAINTING WORK J 03
Prepare & apply approved type one coat of filler & two of
weathershield paint to specified colour up to first floor level
externally(ground floor) Sqr
PAINTING WORK J 04
Prepare & apply approved type one coat of filler & two of
weathershield paint to specified colour above first floor level
Externally Sqr
PAINTING WORK J 05
Prepare & apply approved type one coat of filler & two of
emulsion paint to specified colour in sides and soffit of beam and
slab in first floor level Sqr
PAINTING WORK J 06
Prepare & apply approved type one coat of filler & two of
emulsion paint to specified colour in sides and soffit of beams
and slabs in second floor level Sqr
ELECTRICAL WORK ELECTRICAL WORK
ELECTRICAL WORK
ELECTRICAL WORK K 01 Pendent lamp without bulb and shade Point
ELECTRICAL WORK K 02 wall bracket with out bulb and shade Point
ELECTRICAL WORK K 03 5 amp socket outlets Point
READY MIX
CONCRETE READY MIX CONCRETE
READY MIX
CONCRETE
READY MIX
CONCRETE L 01
Suppying & placing ready mixed Concrete grade 20 (1:2:4 -3/4"
) in 125mm thick first floor slab Cube
READY MIX
CONCRETE L 02
Suppying & placing redy mixed Concrete grade 20 (1:2:4 -3/4" )
in 225 x225mm columns in ground floor Cube
READY MIX
CONCRETE L 03
Suppying & placing ready mixed Concrete grade 25 (1:1 1/2:3 -
3/4" ) in 125mm thick first floor slab Cube
READY MIX
CONCRETE L 04
Suppying & placing redy mixed Concrete grade 25(1:11/2:3-3/4)
in 225mmx225mm columns in ground floor. Cube
READY MIX
CONCRETE L 05
Suppying & placing ready mixed Concrete grade 20 (1:2:4-3/4)
in 125mm thick first floor slab Cube
READY MIX
CONCRETE L 06
Suppying & placing redy mixed Concrete grade 20(1:2:4-3/4") in
225mmx225mm columns in ground floor Cube
READY MIX
CONCRETE L 07
Suppying & placing redy mixed Concrete grade 25 (1:11/2:3-
3/4) in 125mm thick first floor slab Cube
READY MIX
CONCRETE L 08
Suppying & placing redy mixed Concrete grade 25(1:11/2:3-
3/4") in 225mmx225mm columns in ground floor Cube
DOORS &
WINDOWS DOORS & WINDOWS
DOORS &
WINDOWS
DOORS &
WINDOWS M 01
singal hung door size 3'-6"x 7'-0" high overall with 4''x3''
class 1 Timber door frame and including 11/4" tk ordinary
plywood door sash with and door lock with and including
ironmongrey and painting Nos
DOORS &
WINDOWS M 02
singal hung door size 3'-6"x 7'-0" high overall with 4''x3''
class 1 Timber door frame and including 11/4" tk flush panneld
door sash with and door lock with and including ironmongrey and
painting Nos
DOORS &
WINDOWS M 03
window size 5'-0"x 6'-0" high overall with 4''x3'' class 1
Timber window frame and mullion comprising 1 tk glased window
casement and including ironmongrey and painting Nos
HOT WATER
PLUMBING HOT WATER PLUMBING
HOT WATER
PLUMBING
HOT WATER
PLUMBING N 01
supplying & laying hot Water pipe 20mm dia
L.ft
Basic Rate
Rate with
Priliminery
Rate with
O/H &
Profit
Rate with
priliminery,
O/H &
Profit Unit Basic Rate
Rate with
Priliminery
1.10 1.05 1.15
669.50 736.45 702.98 846.92 m2 72.04 79.24
836.88 920.56 878.72 1,058.65 m2 90.05 99.05
1,171.63 1,288.79 1,230.21 1,482.11 m3 414.00 455.40
1,339.00 1,472.90 1,405.95 1,693.84 m3 473.14 520.46
1,673.75 1,841.13 1,757.44 2,117.29 m3 591.43 650.57
1,506.38 1,657.01 1,581.69 1,905.56 m3 532.29 585.52
1,841.13 2,025.24 1,933.18 2,329.02 m3 650.57 715.63
1,815.42 1,996.96 1,906.19 2,296.50 m3 641.49 705.64
1,506.38 1,657.01 1,581.69 1,905.56 m3 532.29 585.52
4,141.63 4,555.79 4,348.71 5,239.16 m3 1,463.47 1,609.82
4,141.63 4,555.79 4,348.71 5,239.16 m3 1,463.47 1,609.82
4,609.25 5,070.18 4,839.71 5,830.70 m2 495.96 545.55
7,835.63 8,619.19 8,227.41 9,912.07 m2 843.11 927.42
6,414.33 7,055.76 6,735.04 8,114.12 m2 690.18 759.20
27,414.83 30,156.32 28,785.57 34,679.76 m3 9,687.22 10,655.94
27,414.83 30,156.32 28,785.57 34,679.76 m3 9,687.22 10,655.94
28,154.83 30,970.32 29,562.57 35,615.86 m3 9,948.70 10,943.57
31,114.83 34,226.32 32,670.57 39,360.26 m3 10,994.64 12,094.10
34,814.83 38,296.32 36,555.57 44,040.76 m3 12,302.06 13,532.27
40,734.83 44,808.32 42,771.57 51,529.56 m3 14,393.93 15,833.33
4,852.84 5,338.13 5,095.49 6,138.85 m2 522.17 574.38
4,852.84 5,338.13 5,095.49 6,138.85 m2 522.17 574.38
6,706.36 7,376.99 7,041.68 8,483.54 m2 721.60 793.76
9,404.31 10,344.74 9,874.53 11,896.45 m2 1,011.90 1,113.09
258.88 284.77 271.82 327.48 m 849.12 934.03
401.38 441.51 421.44 507.74 m 1,316.51 1,448.16
512.96 564.25 538.61 648.89 m 1,682.51 1,850.76
640.23 704.25 672.24 809.89 m 2,099.95 2,309.95
571.58 628.74 600.16 723.05 m 1,874.79 2,062.27
698.41 768.25 733.33 883.49 m 2,290.78 2,519.86
686.27 754.90 720.58 868.13 m 2,250.96 2,476.06
210.86 231.94 221.40 266.73 m 691.61 760.77
33,093.02 36,402.32 34,747.67 41,862.67 m3 11,693.65 12,863.01
33,743.02 37,117.32 35,430.17 42,684.92 m3 11,923.33 13,115.66
34,068.02 37,474.82 35,771.42 43,096.05 m3 12,038.17 13,241.99
32,383.80 35,622.18 34,002.99 40,965.51 m3 11,443.04 12,587.34
32,383.80 35,622.18 34,002.99 40,965.51 m3 11,443.04 12,587.34
33,033.80 36,337.18 34,685.49 41,787.76 m3 11,672.72 12,839.99
33,358.80 36,694.68 35,026.74 42,198.88 m3 11,787.56 12,966.32
33,683.80 37,052.18 35,367.99 42,610.01 m3 11,902.40 13,092.64
33,268.95 36,595.84 34,932.39 42,085.22 m3 11,755.81 12,931.39
33,918.95 37,310.84 35,614.89 42,907.47 m3 11,985.49 13,184.04
34,243.95 37,668.34 35,956.14 43,318.59 m3 12,100.33 13,310.37
34,568.95 38,025.84 36,297.39 43,729.72 m3 12,215.18 13,436.69
32,542.13 35,796.34 34,169.23 41,165.79 m3 11,498.99 12,648.88
33,192.13 36,511.34 34,851.73 41,988.04 m3 11,728.67 12,901.53
33,517.13 36,868.84 35,192.98 42,399.17 m3 11,843.51 13,027.86
33,842.13 37,226.34 35,534.23 42,810.29 m3 11,958.35 13,154.18
32,542.13 35,796.35 34,169.24 41,165.80 m3 11,498.99 12,648.89
33,192.13 36,511.35 34,851.74 41,988.05 m3 11,728.67 12,901.54
33,517.13 36,868.85 35,192.99 42,399.17 m3 11,843.51 13,027.86
33,842.13 37,226.35 35,534.24 42,810.30 m3 11,958.35 13,154.19
11,499.93 12,649.92 12,074.92 14,547.41 m2 1,237.39 1,361.13
11,933.26 13,126.58 12,529.92 15,095.57 m2 1,284.02 1,412.42
12,474.93 13,722.42 13,098.67 15,780.78 m2 1,342.30 1,476.53
13,678.00 15,045.80 14,361.90 17,302.67 m2 1,471.75 1,618.93
14,328.00 15,760.80 15,044.40 18,124.92 m2 1,541.69 1,695.86
14,653.00 16,118.30 15,385.65 18,536.05 m2 1,576.66 1,734.33
17,272.40 18,999.64 18,136.02 21,849.58 m2 1,858.51 2,044.36
17,922.40 19,714.64 18,818.52 22,671.83 m2 1,928.45 2,121.30
18,247.40 20,072.14 19,159.77 23,082.96 m2 1,963.42 2,159.76
265.72 292.30 279.01 336.14 m 871.57 958.73
395.25 434.78 415.01 499.99 m 1,296.42 1,426.07
533.79 587.17 560.48 675.24 m 1,750.83 1,925.91
667.98 734.78 701.38 844.99 m 2,190.97 2,410.07
592.30 651.53 621.92 749.26 m 1,942.75 2,137.03
689.49 758.44 723.96 872.20 m 2,261.52 2,487.67
727.71 800.48 764.09 920.55 m 2,386.88 2,625.57
215.93 237.52 226.72 273.15 m 708.24 779.06
36,978.02 40,675.82 38,826.92 46,777.20 m3 13,066.44 14,373.08
37,628.02 41,390.82 39,509.42 47,599.45 m3 13,296.12 14,625.73
37,953.02 41,748.32 39,850.67 48,010.57 m3 13,410.96 14,752.06
38,278.02 42,105.82 40,191.92 48,421.70 m3 13,525.80 14,878.38
36,268.80 39,895.68 38,082.24 45,880.03 m3 12,815.83 14,097.41
36,918.80 40,610.68 38,764.74 46,702.28 m3 13,045.51 14,350.06
37,243.80 40,968.18 39,105.99 47,113.41 m3 13,160.35 14,476.39
37,568.80 41,325.68 39,447.24 47,524.53 m3 13,275.19 14,602.71
37,153.95 40,869.34 39,011.64 46,999.74 m3 13,128.60 14,441.46
37,803.95 41,584.34 39,694.14 47,821.99 m3 13,358.29 14,694.11
38,128.95 41,941.84 40,035.39 48,233.12 m3 13,473.13 14,820.44
38,453.95 42,299.34 40,376.64 48,644.24 m3 13,587.97 14,946.76
32,542.13 35,796.35 34,169.24 41,165.80 m3 11,498.99 12,648.89
33,192.13 36,511.35 34,851.74 41,988.05 m3 11,728.67 12,901.54
33,517.13 36,868.85 35,192.99 42,399.17 m3 11,843.51 13,027.86
33,842.13 37,226.35 35,534.24 42,810.30 m3 11,958.35 13,154.19
36,427.13 40,069.85 38,248.49 46,080.32 m3 12,871.78 14,158.96
37,077.13 40,784.85 38,930.99 46,902.57 m3 13,101.46 14,411.61
37,402.13 41,142.35 39,272.24 47,313.70 m3 13,216.30 14,537.93
37,727.13 41,499.85 39,613.49 47,724.82 m3 13,331.14 14,664.26
36,762.56 40,438.81 38,600.68 46,504.63 m3 12,990.30 14,289.33
38,062.56 41,868.81 39,965.68 48,149.13 m3 13,449.67 14,794.63
38,730.28 42,603.31 40,666.80 48,993.81 m3 13,685.61 15,054.17
15,822.70 17,404.97 16,613.84 20,015.72 m2 1,702.52 1,872.78
16,255.99 17,881.59 17,068.79 20,563.83 m2 1,749.14 1,924.06
16,472.05 18,119.26 17,295.65 20,837.15 m2 1,772.39 1,949.63
19,214.89 21,136.37 20,175.63 24,306.83 m2 2,067.52 2,274.27
19,648.18 21,612.99 20,630.58 24,854.94 m2 2,114.14 2,325.56
19,864.89 21,851.37 20,858.13 25,129.08 m2 2,137.46 2,351.21
6,206.25 6,826.88 6,516.56 7,850.91 m2 667.79 734.57
9,880.58 10,868.64 10,374.61 12,498.94 m2 1,063.15 1,169.47
10,177.00 11,194.70 10,685.85 12,873.91 m2 1,095.05 1,204.55
10,275.81 11,303.39 10,789.60 12,998.90 m2 1,105.68 1,216.24
10,374.61 11,412.07 10,893.34 13,123.88 m2 1,116.31 1,227.94
26,469.55 29,116.50 27,793.02 33,483.98 m2 2,848.12 3,132.94
27,263.63 29,990.00 28,626.81 34,488.49 m2 2,933.57 3,226.92
27,528.33 30,281.16 28,904.74 34,823.33 m2 2,962.05 3,258.25
27,793.02 30,572.33 29,182.67 35,158.17 m2 2,990.53 3,289.58
12,878.19 14,166.01 13,522.10 16,290.91 m2 1,385.69 1,524.26
13,393.32 14,732.65 14,062.98 16,942.54 m2 1,441.12 1,585.23
13,522.10 14,874.31 14,198.20 17,105.45 m2 1,454.98 1,600.48
152.15 167.37 159.76 192.47 cwt 7,607.68 8,368.44
146.81 161.49 154.15 185.71 cwt 7,340.43 8,074.47
161.51 177.66 169.58 204.31 cwt 8,075.43 8,882.97
156.47 172.12 164.30 197.94 cwt 7,823.68 8,606.04
151.13 166.24 158.68 191.18 cwt 7,556.43 8,312.07
165.83 182.41 174.12 209.77 cwt 8,291.43 9,120.57
162.49 178.74 170.62 205.55 cwt 8,124.60 8,937.06
170.73 187.81 179.27 215.98 cwt 8,536.60 9,390.26
20,846.00 22,930.60 21,888.30 26,370.19 m3 7,366.08 8,102.69
21,710.00 23,881.00 22,795.50 27,463.15 m3 7,671.38 8,438.52
22,317.50 24,549.25 23,433.38 28,231.64 m3 7,886.04 8,674.65
9,094.00 10,003.40 9,548.70 11,503.91 m2 978.51 1,076.37
9,526.00 10,478.60 10,002.30 12,050.39 m2 1,025.00 1,127.50
9,958.00 10,953.80 10,455.90 12,596.87 m2 1,071.48 1,178.63
150.33 165.36 157.85 190.17 m 493.08 542.39
153.84 169.22 161.53 194.61 m 504.60 555.05
162.48 178.73 170.60 205.54 m 532.93 586.23
119.86 131.85 125.85 151.62 m 393.14 432.45
124.99 137.49 131.24 158.11 m 409.97 450.96
129.81 142.79 136.30 164.21 m 425.78 468.36
15,874.00 17,461.40 16,667.70 20,080.61 m2 1,708.04 1,878.85
17,345.50 19,080.05 18,212.78 21,942.06 m2 1,866.38 2,053.01
17,521.00 19,273.10 18,397.05 22,164.07 m2 1,885.26 2,073.79
17,298.75 19,028.63 18,163.69 21,882.92 m3 6,112.63 6,723.90
25,701.00 28,271.10 26,986.05 32,511.77 m2 2,765.43 3,041.97
33,544.00 36,898.40 35,221.20 42,433.16 m2 3,609.33 3,970.27
41,482.00 45,630.20 43,556.10 52,474.73 m2 4,463.46 4,909.81
18,241.46 20,065.61 19,153.53 23,075.45 m2 1,962.78 2,159.06
9,966.32 10,962.95 10,464.64 12,607.39 m2 1,072.38 1,179.61
13,208.84 14,529.72 13,869.28 16,709.18 m2 1,421.27 1,563.40
18,576.88 20,434.56 19,505.72 23,499.75 m2 1,998.87 2,198.76
10,301.72 11,331.89 10,816.80 13,031.67 m2 1,108.46 1,219.31
13,544.24 14,898.66 14,221.45 17,133.46 m2 1,457.36 1,603.10
18,883.13 20,771.44 19,827.28 23,887.16 m2 2,031.82 2,235.01
10,607.99 11,668.79 11,138.39 13,419.10 m2 1,141.42 1,255.56
14,171.34 15,588.47 14,879.91 17,926.75 m2 1,524.84 1,677.32
14,570.10 16,027.11 15,298.61 18,431.18 m2 1,567.74 1,724.52
8,027.60 8,830.36 8,428.98 10,154.91 m2 863.77 950.15
10,952.04 12,047.24 11,499.64 13,854.33 m2 1,178.44 1,296.28
14,905.52 16,396.07 15,650.79 18,855.48 m2 1,603.83 1,764.22
8,363.00 9,199.29 8,781.14 10,579.19 m2 899.86 989.84
11,287.44 12,416.18 11,851.81 14,278.61 m2 1,214.53 1,335.98
15,211.77 16,732.94 15,972.36 19,242.88 m2 1,636.79 1,800.46
8,669.27 9,536.19 9,102.73 10,966.62 m2 932.81 1,026.09
11,914.54 13,105.99 12,510.27 15,071.89 m2 1,282.00 1,410.20
35,536.10 39,089.71 37,312.91 44,953.17 m2 3,823.68 4,206.05
136.17 149.79 142.98 172.25 m 446.63 491.30
20,407.33 22,448.07 21,427.70 25,815.28 m2 2,195.83 2,415.41
852.00 937.20 894.60 1,077.78 m 2,794.56 3,074.02
6,477.33 7,125.07 6,801.20 8,193.83 m2 696.96 766.66
10,266.76 11,293.44 10,780.10 12,987.45 m2 1,104.70 1,215.17
374.16 411.57 392.86 473.31 m 1,227.23 1,349.95
17,918.16 19,709.98 18,814.07 22,666.47 m2 1,927.99 2,120.79
29,123.50 32,035.85 30,579.68 36,841.23 m2 3,133.69 3,447.06
57.54 63.29 60.42 72.79 m 188.73 207.60
83.14 91.45 87.30 105.17 m 272.70 299.97
107.37 118.11 112.74 135.82 m 352.18 387.39
114.70 126.17 120.44 145.10 m 376.22 413.84
147.50 162.25 154.88 186.59 m 483.81 532.19
154.83 170.32 162.57 195.86 m 507.85 558.64
201.42 221.56 211.49 254.79 m 660.65 726.71
208.75 229.62 219.18 264.06 m 684.69 753.16
310.59 341.65 326.12 392.89 m 1,018.73 1,120.60
317.92 349.71 333.81 402.17 m 1,042.77 1,147.05
513.76 565.13 539.44 649.90 m 1,685.12 1,853.63
521.09 573.20 547.14 659.17 m 1,709.17 1,880.08
653.76 719.14 686.45 827.01 m 2,144.33 2,358.77
661.09 727.20 694.14 836.28 m 2,168.38 2,385.21
1,062.89 1,169.18 1,116.03 1,344.56 No 1,062.89 1,169.18
56.72 62.39 59.56 71.75 No 56.72 62.39
50.10 55.11 52.61 63.38 No 50.10 55.11
65.10 71.61 68.36 82.35 No 65.10 71.61
130.80 143.88 137.34 165.46 No 130.80 143.88
203.50 223.85 213.68 257.43 No 203.50 223.85
322.62 354.88 338.75 408.11 No 322.62 354.88
26.82 29.50 28.16 33.93 No 26.82 29.50
41.10 45.21 43.16 51.99 No 41.10 45.21
54.10 59.51 56.81 68.44 No 54.10 59.51
85.80 94.38 90.09 108.54 No 85.80 94.38
136.50 150.15 143.33 172.67 No 136.50 150.15
221.62 243.78 232.70 280.35 No 221.62 243.78
35.45 39.00 37.22 44.84 No 35.45 39.00
53.73 59.10 56.42 67.97 No 53.73 59.10
77.50 85.25 81.38 98.04 No 77.50 85.25
115.92 127.51 121.72 146.64 No 115.92 127.51
188.76 207.64 198.20 238.78 No 188.76 207.64
289.00 317.90 303.45 365.59 No 289.00 317.90
31.82 35.00 33.41 40.25 No 31.82 35.00
42.10 46.31 44.21 53.26 No 42.10 46.31
50.10 55.11 52.61 63.38 No 50.10 55.11
86.80 95.48 91.14 109.80 No 86.80 95.48
117.50 129.25 123.38 148.64 No 117.50 129.25
177.62 195.38 186.50 224.69 No 177.62 195.38
31.82 35.00 33.41 40.25 No 31.82 35.00
42.10 46.31 44.21 53.26 No 42.10 46.31
46.10 50.71 48.41 58.32 No 46.10 50.71
82.50 90.75 86.63 104.36 No 82.50 90.75
111.20 122.32 116.76 140.67 No 111.20 122.32
175.32 192.85 184.09 221.78 No 175.32 192.85
27.82 30.60 29.21 35.19 No 27.82 30.60
37.10 40.81 38.96 46.93 No 37.10 40.81
48.10 52.91 50.51 60.85 No 48.10 52.91
70.80 77.88 74.34 89.56 No 70.80 77.88
106.20 116.82 111.51 134.34 No 106.20 116.82
162.32 178.55 170.44 205.33
4,517.00 4,968.70 4,742.85 5,714.01 m2 486.03 534.63
3,788.24 4,167.06 3,977.65 4,792.12 m2 407.61 448.38
4,949.00 5,443.90 5,196.45 6,260.49 m2 532.51 585.76
4,257.50 4,683.25 4,470.38 5,385.74 m2 458.11 503.92
5,381.00 5,919.10 5,650.05 6,806.97 m2 579.00 636.90
4,689.50 5,158.45 4,923.98 5,932.22 m2 504.59 555.05
5,637.50 6,201.25 5,919.38 7,131.44 m2 606.60 667.25
5,663.00 6,229.30 5,946.15 7,163.70 m2 609.34 670.27
5,578.00 6,135.80 5,856.90 7,056.17 m2 600.19 660.21
5,744.00 6,318.40 6,031.20 7,266.16 m2 618.05 679.86
6,176.00 6,793.60 6,484.80 7,812.64 m2 664.54 730.99
8,179.38 8,997.31 8,588.34 10,346.91 m2 880.10 968.11
2,835.50 3,119.05 2,977.28 3,586.91 m2 305.10 335.61
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
20,372.75 22,410.03 21,391.39 25,771.53 m2 2,192.11 2,411.32
7,772.75 8,550.03 8,161.39 9,832.53 m2 836.35 919.98
2,539.67 2,793.63 2,666.65 3,212.68 m2 273.27 300.59
2,796.17 3,075.78 2,935.98 3,537.15 m2 300.87 330.95
2,965.50 3,262.05 3,113.78 3,751.36 m2 319.09 351.00
3,390.83 3,729.92 3,560.38 4,289.40 m2 364.85 401.34
2,971.67 3,268.83 3,120.25 3,759.16 m2 319.75 351.73
3,144.47 3,458.91 3,301.69 3,977.75 m2 338.34 372.18
1,729.31 1,902.25 1,815.78 2,187.58 Point 1,729.31 1,902.25
1,548.05 1,702.85 1,625.45 1,958.28 Point 1,548.05 1,702.85
3,919.74 4,311.71 4,115.73 4,958.47 Point 3,919.74 4,311.71
32,023.90 35,226.29 33,625.10 40,510.24 m3 11,315.87 12,447.45
33,038.88 36,342.77 34,690.83 41,794.19 m3 11,674.52 12,841.97
31,031.28 34,134.41 32,582.84 39,254.57 m3 10,965.12 12,061.63
34,085.46 37,494.01 35,789.74 43,118.11 m3 12,044.33 13,248.77
33,007.21 36,307.93 34,657.57 41,754.12 m3 11,663.33 12,829.66
34,149.06 37,563.97 35,856.51 43,198.56 m3 12,066.81 13,273.49
34,341.55 37,775.71 36,058.63 43,442.07 m3 12,134.83 13,348.31
35,483.41 39,031.75 37,257.58 44,886.51 m3 12,538.31 13,792.14
20,475.67 22,523.24 21,499.45 25,901.72 Nos 20,475.67 22,523.24
28,021.67 30,823.84 29,422.75 35,447.41 Nos 28,021.67 30,823.84
18,388.56 20,227.42 19,307.99 23,261.53 Nos 18,388.56 20,227.42
58.35 64.19 61.27 73.81 m 191.39 210.53
Rate with
O/H &
Profit
Rate with
priliminery,
O/H &
Profit
75.64 91.13
94.55 113.91
434.70 523.71
496.80 598.53
621.00 748.16
558.90 673.34
683.10 822.98
673.56 811.48
558.90 673.34
1,536.65 1,851.29
1,536.65 1,851.29
520.75 627.38
885.27 1,066.54
724.69 873.08
10,171.58 12,254.33
10,171.58 12,254.33
10,446.14 12,585.11
11,544.37 13,908.22
12,917.16 15,562.11
15,113.63 18,208.33
548.27 660.54
548.27 660.54
757.68 912.83
1,062.50 1,280.06
891.58 1,074.14
1,382.34 1,665.39
1,766.63 2,128.37
2,204.95 2,656.44
1,968.53 2,371.61
2,405.32 2,897.83
2,363.51 2,847.47
726.19 874.89
12,278.33 14,792.46
12,519.50 15,083.01
12,640.08 15,228.29
12,015.19 14,475.44
12,015.19 14,475.44
12,256.36 14,765.99
12,376.94 14,911.27
12,497.52 15,056.54
12,343.60 14,871.10
12,584.77 15,161.65
12,705.35 15,306.92
12,825.93 15,452.20
12,073.93 14,546.22
12,315.10 14,836.76
12,435.68 14,982.04
12,556.27 15,127.31
12,073.94 14,546.22
12,315.10 14,836.77
12,435.69 14,982.04
12,556.27 15,127.31
1,299.26 1,565.30
1,348.22 1,624.28
1,409.42 1,698.01
1,545.34 1,861.77
1,618.78 1,950.24
1,655.50 1,994.48
1,951.44 2,351.02
2,024.87 2,439.49
2,061.59 2,483.73
915.15 1,102.54
1,361.24 1,639.98
1,838.37 2,214.80
2,300.52 2,771.58
2,039.89 2,457.58
2,374.60 2,860.82
2,506.23 3,019.41
743.65 895.92
13,719.76 16,529.04
13,960.93 16,819.59
14,081.51 16,964.87
14,202.09 17,110.14
13,456.62 16,212.03
13,697.79 16,502.57
13,818.37 16,647.85
13,938.95 16,793.12
13,785.03 16,607.68
14,026.20 16,898.23
14,146.78 17,043.50
14,267.37 17,188.78
12,073.94 14,546.22
12,315.10 14,836.77
12,435.69 14,982.04
12,556.27 15,127.31
13,515.37 16,282.80
13,756.53 16,573.35
13,877.12 16,718.62
13,997.70 16,863.89
13,639.82 16,432.73
14,122.15 17,013.83
14,369.89 17,312.30
1,787.65 2,153.69
1,836.60 2,212.67
1,861.01 2,242.08
2,170.90 2,615.41
2,219.85 2,674.39
2,244.33 2,703.89
701.18 844.76
1,116.31 1,344.89
1,149.80 1,385.23
1,160.96 1,398.68
1,172.12 1,412.13
2,990.53 3,602.88
3,080.25 3,710.96
3,110.15 3,746.99
3,140.06 3,783.02
1,454.98 1,752.90
1,513.18 1,823.02
1,527.73 1,840.55
7,988.06 9,623.71
7,707.45 9,285.64
8,479.20 10,215.41
8,214.86 9,896.95
7,934.25 9,558.88
8,706.00 10,488.65
8,530.83 10,277.62
8,963.43 10,798.80
7,734.38 9,318.09
8,054.95 9,704.29
8,280.34 9,975.84
1,027.44 1,237.82
1,076.25 1,296.62
1,125.05 1,355.42
517.74 623.75
529.82 638.31
559.58 674.16
412.80 497.32
430.47 518.61
447.07 538.62
1,793.44 2,160.67
1,959.69 2,360.97
1,979.52 2,384.85
6,418.26 7,732.48
2,903.70 3,498.27
3,789.80 4,565.81
4,686.64 5,646.28
2,060.92 2,482.92
1,125.99 1,356.56
1,492.33 1,797.91
2,098.82 2,528.57
1,163.89 1,402.21
1,530.23 1,843.56
2,133.42 2,570.26
1,198.49 1,443.90
1,601.08 1,928.92
1,646.13 1,983.19
906.96 1,092.67
1,237.36 1,490.73
1,684.03 2,028.85
944.85 1,138.32
1,275.25 1,536.38
1,718.63 2,070.53
979.45 1,180.01
1,346.10 1,621.74
4,014.87 4,836.96
468.96 564.99
2,305.62 2,777.72
2,934.29 3,535.12
731.81 881.66
1,159.94 1,397.45
1,288.59 1,552.44
2,024.39 2,438.91
3,290.37 3,964.12
198.17 238.74
286.33 344.96
369.78 445.50
395.03 475.92
508.00 612.02
533.25 642.43
693.68 835.72
718.92 866.13
1,069.66 1,288.69
1,094.91 1,319.10
1,769.38 2,131.68
1,794.62 2,162.09
2,251.55 2,712.58
2,276.79 2,742.99
1,116.03 1,344.56
59.56 71.75
52.61 63.38
68.36 82.35
137.34 165.46
213.68 257.43
338.75 408.11
28.16 33.93
43.16 51.99
56.81 68.44
90.09 108.54
143.33 172.67
232.70 280.35
37.22 44.84
56.42 67.97
81.38 98.04
121.72 146.64
198.20 238.78
303.45 365.59
33.41 40.25
44.21 53.26
52.61 63.38
91.14 109.80
123.38 148.64
186.50 224.69
33.41 40.25
44.21 53.26
48.41 58.32
86.63 104.36
116.76 140.67
184.09 221.78
29.21 35.19
38.96 46.93
50.51 60.85
74.34 89.56
111.51 134.34
510.33 614.83
428.00 515.63
559.14 673.63
481.01 579.51
607.95 732.43
529.82 638.31
636.92 767.34
639.81 770.81
630.20 759.24
648.96 781.84
697.76 840.64
924.11 1,113.33
320.35 385.95
878.17 1,057.98
878.17 1,057.98
878.17 1,057.98
878.17 1,057.98
2,301.71 2,773.02
878.17 1,057.98
286.93 345.68
315.91 380.60
335.04 403.65
383.10 461.54
335.74 404.49
355.26 428.01
1,815.78 2,187.58
1,625.45 1,958.28
4,115.73 4,958.47
11,881.66 14,314.57
12,258.24 14,768.26
11,513.37 13,870.87
12,646.55 15,236.08
12,246.49 14,754.11
12,670.15 15,264.51
12,741.57 15,350.55
13,165.22 15,860.96
21,499.45 25,901.72
29,422.75 35,447.41
19,307.99 23,261.53
200.96 242.11
STANDARD BSR
Caterary Description Qty Unit
Excavation & earthwork
A1 Clearing site & grubbing up all small trees
not exceeding 500mm girth & including
bushes scrubs, undergrowth hedges etc.
Excavation & earthwork Labour
Excavation & earthwork Un/skilled Labour 1.00 day
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A2 Excavation of top soil of average depth of
6'' and carting away surplus soil
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.25 day
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A3 Drains, earth in any soil except rock
requiring blasting cut to gradient & shape
as directed & depositing soil within site
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.75 days
Main Index
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
A4 Excavate trench for wall foundation in
ordinary soil & part return fill in ram &
depoisting surplus excavated material within
site as derected.(not exceeding 5'- 0"
deep.)
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.00 days
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
A5 Excavate trench for wall foundation in
ordinary soil & part return fill in ram, &
depoisting surplus excavated material within
site as directed.(exceeding 5'-0" but not
exceeding 10'-0")
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.50 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A6 Excavate pit for column foundation in any
material except rock requiring blasting, part
return fill in ram, & depoisting surplus
excavated material within site as
directed.(not exceeding 5'- 0" deep.)
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.25 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A7 Excavate pit for column foundation in any
material except rock requiring blasting,
part return fill in ram, & depoisting surplus
excavated material within site as
directed.(exceeding 5'-0" but not exceeding
10'-0"deep)
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.75 day
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A8 Cutting & levlling site in any material except
rock requiring blasting including transporting
up to 1/4 mile depositing & leveling
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Cutting & loading earth to tractor
Excavation & earthwork
Excavation & earthwork Un / skilled Labour 2.50 days
Excavation & earthwork
Excavation & earthwork Transporting earth
Excavation & earthwork tractor 0.17 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
A9 Filling under floors with gravel or other
approved quality of filling, spread, Watered
& well rammed in 3'' thick layers. (Earth
available at site)
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 2.25 days
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A10 Filling under floors with gravel or other
approved quality of filling, spread, Watered
& well rammed in 3'' thick layers. (earth
not avilable at site)
Excavation & earthwork Materials
Excavation & earthwork Earth with transport 1.35 Cube
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.75 day
Excavation & earthwork Add
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A11 Filling under floors with gravel or other
approved quality of filling, spread, Watered
& well rammed in 3'' thick layers.(within
Colombo Municipal limits)
Excavation & earthwork Materials
Excavation & earthwork Earth with transport 1.35 Cube
Excavation & earthwork Labour
Excavation & earthwork Un / skilled Labour 1.75 day
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork Cost for 1 Cube with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A12 Earth work support in trenches up to 5' 0''
deep.(open planking)
Excavation & earthwork Assume 1.2 Sqr
Excavation & earthwork Note
Excavation & earthwork
Consider trench 12'-0" long 3'-0" wide and 5'-
0" deep open planking to both side. (class II
Timber)
Excavation & earthwork
Excavation & earthwork Materials
Excavation & earthwork 1'' thick planks 40.00 Sq.ft
Excavation & earthwork 2'' x 6'' joist 40.00 l ft
Excavation & earthwork 2'' x 4'' joist 40.00 l ft
Excavation & earthwork Wire nails 0.50 kg
Excavation & earthwork
Excavation & earthwork 3% westege
Excavation & earthwork Cost for 4 uses
Excavation & earthwork
Excavation & earthwork for single use
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Skilled Labour 0.50 day
Excavation & earthwork Un / skilled Labour 0.50 day
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A13 Earth work support in trenches up to
5' 0'' deep.(close planking)
Excavation & earthwork Note
Excavation & earthwork
Consider trench 10'-0" long 3'-0" wide and 5'-
0" deep closed planking to both side (class II
Timber)
Excavation & earthwork
Excavation & earthwork Materials
Excavation & earthwork 1" thick planks 110.00 Sq.ft
Excavation & earthwork 2'' x 6'' joist 40.00 l ft
Excavation & earthwork 2'' x 4'' joist 24.00 l ft
Excavation & earthwork Wire nails 0.50 kg
Excavation & earthwork Cost for 4 uses
Excavation & earthwork
Excavation & earthwork For single use
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Skilled labour 0.75 day
Excavation & earthwork Un /Skilled labour 1.50 day
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork
A14 Earth work support in trenches up to 10'
0'' deep. (close planking)
Excavation & earthwork assume 2 Sqr
Excavation & earthwork Materials
Excavation & earthwork 1" thick planks 220.00 Sq.ft
Excavation & earthwork 12' 0'' long joist (2''x6'') 6.00 no
Excavation & earthwork 4' 0'' long props (2''x4'') 12.00 no
Excavation & earthwork Wire nails 2.00 kg
Excavation & earthwork
Excavation & earthwork Westage 3%
Excavation & earthwork Cost for 4 uses
Excavation & earthwork
Excavation & earthwork For single use
Excavation & earthwork
Excavation & earthwork Labour
Excavation & earthwork Skilled labour 2.00 day
Excavation & earthwork Un /Skilled labour 3.00 day
Excavation & earthwork
Excavation & earthwork Add
Excavation & earthwork Tools
Excavation & earthwork 3% of labour Cost for tools
Excavation & earthwork
Excavation & earthwork Cost for one Sqr
Excavation & earthwork Preliminaries
Excavation & earthwork
Excavation & earthwork
Excavation & earthwork Cost for 1 Sqr with Preliminaries
Concrete work B1 Concrete 1:3:6 (2") grade 10
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 13.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture(14/10) 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
5% of labour Cost for scaffolding for
scafolding
Concrete work Curing
Concrete work
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B2 Concrete 1:3:6 (1") grade 10
Concrete work
Concrete work MIXING Cost
Concrete work
Concrete work Materials
Concrete work Cement 13.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture (14/10) 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
5% of labour Cost for scaffolding for
scafolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B3 Concrete 1:2:5 (1") grade 15
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 14.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture (14/10) 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
5% of labour Cost for scaffolding for
scafolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B4 Concrete 1:2:4 (3/4") grade 20
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 18.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
5% of labour Cost for scaffolding for
scafolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B5 Concrete 1:11/2:3 (3/4") grade 25
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 23.00 bags
Concrete work Sand 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture 14/10 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
5% of labour Cost for scaffolding for
scafolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B5a Concrete1 :1:2 (3/4") grade 30
Concrete work MIXING Cost
Concrete work Materials
Concrete work Cement 31.00 bags
Concrete work Sand -rough 0.60 Cube
Concrete work Metal 1.00 Cube
Concrete work Water 125.00 gal
Concrete work
Concrete work Labour
Concrete work Mixer operator 0.33 day
Concrete work Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Concrete mixture 0.33 day
Concrete work
Concrete work Cost for one Cube (mixing only)
Concrete work
Concrete work LAYING Cost
Concrete work Mason 0.75 day
Concrete work Vibrator operator 0.75 day
Concrete work 6 Un / skilled Labour 4.50 day
Concrete work
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.75 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tool
Concrete work
5% of labour Cost for scaffolding for
scafolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal.
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B6 2" thick blinding layer under wall / column
foundation (1:3:6 -2") grade 10
Concrete work
Concrete work Materials
Concrete work mixed Concrete 0.17 Cube
Concrete work (As per item B.01)
Concrete work 10% for Wastage
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 1.00 day
Concrete work
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
B7 2" thick blinding layer under wall/ column
foundation (1:3:6 -1") grade 10
Concrete work Materials
Concrete work mixed Concrete 0.17 Cube
Concrete work (As per item B.02)
Concrete work Add
Concrete work 10 % for Wastage
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 1.00 day
Concrete work
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
B8 3" thick blinding layer under wall/ column
foundation (1:3:6 -1") grade 10
Concrete work Materials
Concrete work mixed Concrete 0.25 Cube
Concrete work (As per item B.02)
Concrete work Add
Concrete work 10 % for Wastage
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 1.00 day
Concrete work
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
B9 4" thick ground floor slab (1:3:6 -1")
Grade10
Concrete work
Concrete work Materials
Concrete work mixed Concrete (As per item no 2) 0.33 Cube
Concrete work Add
Concrete work 10 % for Wastage
Concrete work
Concrete work Labour
Concrete work Skilled Labour 0.33 day
Concrete work Un / skilled Labour 1.33 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.25 day
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B10 Cement Concrete 1:2:4(3/4) lintol size
41/2'' x 6'' with & including formwork
(reinforcement paid separately)
Concrete work Assume 10 L.ft
Concrete work Materials
Concrete work Concrete (B.04) 0.02 Cube
Concrete work Sawn form work 13.70 S.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 L.ft with Preliminaries
Concrete work
Concrete work
B11 Cement Concrete 1:2:4(3/4") lintol size
6'' x 9'' with & including formwork
(reinforcement paid separately)
Concrete work Assume 10 L.ft
Concrete work
Concrete work Materials
Concrete work Concrete (B.04) 3.75 c.ft
Concrete work Sawn form work 20.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 L.ft with Preliminaries
Concrete work
Concrete work
Concrete work
B12 Cement Concrete 1:2:4(3/4") lintol size
9'' x 9'' with & including formwork
Concrete work
Concrete work Materials
Concrete work
Concrete work Concrete (B.04) 5.63 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1.0 l.ft with perlimanary
Concrete work
Concrete work
Concrete work
B13 Cement Concrete 1:2:4(3/4") lintol size
9'' x 12'' with & including formwork
Concrete work Materials
Concrete work Concrete (B.04) 7.50 c.ft
Concrete work Sawn form work 27.72 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work Cost for 10 L.ft
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1.0 l.ft with perlimanary
Concrete work
Concrete work
Concrete work
B14 Cement Concrete 1:2:4(3/4") lintol size
6'' x 13' 6'' with & including formwork
Concrete work
Concrete work Materials
Concrete work
Concrete work Concrete (B 04) 5.60 c.ft
Concrete work Sawn form work 27.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft
Concrete work
Concrete work
Concrete work
B15 Cement Concrete 1:2:4(3/4") lintol size
9'' X 13' 6'' with & including formwork
Concrete work Materials
Concrete work Concrete (B 04) 8.40 c.ft
Concrete work Sawn form work 30.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft
Concrete work
Concrete work
B16 Cement Concrete 1:2:4(3/4") lintol size
12'' x 13' 6'' with & including formwork
Concrete work Materials
Concrete work Concrete (B 04) 11.20 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B17 Cement Concrete 1:2:4(3/4")lintol size 4
1/2" x4 1/2" with & including
formwork.(rein forcement paid seperately)
Concrete work Materials
Concrete work Concrete (B 04) 1.37 c.ft
Concrete work Sawn form work 11.20 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
Concrete work
B18 Concrete column in ground floor
(1:2:4 3\4")
Concrete work 16no 9" x 9" columns each 5'-0" high
Concrete work .45 Cube (80 L.ft)
Concrete work
Concrete work Materials
Concrete work Mixed Concrete (As per item B.04) 0.45 Cube
Concrete work Add
Concrete work 5% Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
5% of labour Cost for scaffolding for
scaffolding
Concrete work
Concrete work Curing
Concrete work Water 50.00 gal
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for .45 Cubes
Concrete work Cost for 1 Cubes
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B19 9" x 9" Concrete columns in first floor
Concrete work 9" x 9" Concrete columns in ground floor
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B20 9" x 9" Concrete columns in second floor
Concrete work
Concrete work Cost of 9" x 9" columns
Concrete work
Concrete work Add
Concrete work Un /Skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B21 9" x 9" Concrete columns in third floor
Concrete work Cost of 9" x 9" columns
Concrete work
Concrete work Add
Concrete work Un /Skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B22 Concrete columns in ground floor 10 no
12"x12" columns each 5' 0" high
Concrete work
Concrete work Materials
Concrete work As per item B 04
Concrete work Mixed Concrete 0.50 Cube
Concrete work
Concrete work Add
Concrete work 5% Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
5% of labour Cost for scaffolding for
scaffolding
Concrete work
Concrete work Curing
Concrete work Water 50.00 gal
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work
Concrete work Cost for one Cube without prelimineries
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B23 12" x 12" Concrete columns in first floor
Concrete work Cost of 12" x 12" columns
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B24 12" x 12" Concrete columns in second floor
Concrete work Cost of 12" x 12" columns
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B25 12" x 12" Concrete columns in third floor
Concrete work Cost of 12" x 12" columns
Concrete work Add
Concrete work 4 Un /Skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B26 9" x 9" Concrete beams in ground floor level
Grade 20
Concrete work Assume 0.45 Cube
Concrete work Note 8 nos 9"x9' beam 10 ft long
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.45 Cube
Concrete work Add 5% Wastage
Concrete work
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work Add
Concrete work 3%of labour Cost for tools
Concrete work 5%of labour Cost for scaffolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un /Skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B27 9" x 9" Concrete beam in first floor
Concrete work Cost of 9"x 9" beam
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B28 9" x 9" Concrete beam in second floor
Concrete work Cost of 9" x 9" beam
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B29 9" x 9" Concrete beam in third floor
Concrete work Cost of 9" x 9" beam
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B30 Concrete beams in ground floor level Grade
20
Concrete work 6 nos 9" x12" beam 10ft long 0.5 Cube
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work
Concrete work
Concrete work Tools
Concrete work Scaffolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B31 Concrete beam in first floor
Concrete work Cost of 9" x 12" beam
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B32 Concrete beam in second floor
Concrete work Cost of 9" x 12" beam
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B33 Concrete beam in third floor
Concrete work Cost of 9" x 12" beam
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B34 Concrete beams in ground floor level
Concrete work 5 nos 12"x12" beam 10 ft long
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Tools
Concrete work Scaffolding
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un /Skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B35 Concrete beam in first floor
Concrete work Cost of 12" x 12" beam
Concrete work Add
Concrete work 2 Un /Skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B36 Concrete beam in second floor
Concrete work Cost of 12" x 12" beam
Concrete work Add
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B37 Concrete beam in third floor
Concrete work Cost of 12" x 12" beam
Concrete work Add
Concrete work 4 Un /Skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B38 4" thick Concrete slab in first floor Grade
20
Concrete work
Concrete work
Concrete work Materials
Concrete work Mixed Concrete (As per item no 4) 0.33 Cube
Concrete work Add
Concrete work 5% Wastage
Concrete work
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labourfor Vibrator operator 0.50 day
Concrete work 2 Un /Skilled Labour 1.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work Scaffolding
Concrete work Tools
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un /Skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B39 4" thick Concrete slab in second floor
Concrete work 4" thick Concrete slab in ground floor
Concrete work 2 Un /Skilled Labour 0.67 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B40 4" thick Concrete slab in third floor
Concrete work 4" thick Concrete slab in ground floor
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B41 5" thick Concrete slab in first floor
Concrete work MIXING Cost
Concrete work Materials
Concrete work Mixed Concrete
Concrete work As per item B 04 0.42 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Skilled Labourfor Vibrator operator 0.50 day
Concrete work 3 Un /Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work Scaffolding
Concrete work Tools
Concrete work
Concrete work Curing
Concrete work Water
Concrete work Un / skilled Labour 100.00 gal
Concrete work 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B42 5" thick Concrete slab in second floor
Concrete work 5" thick Concrete slab in ground floor
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work B43 5" thick Concrete slab in third floor
Concrete work 5" thick Concrete slab in ground floor
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B44 6" thick Concrete slab in first floor
Concrete work 0.5 Cube
Concrete work MIXING Cost
Concrete work Materials
Concrete work Mixed Concrete
Concrete work As per item B 04 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.67 day
Concrete work Vibrator operator 0.67 day
Concrete work 3 Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Vibrator operator 0.67 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work Cost for 1 Sqr
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B45 6" thick Concrete slab in second floor
Concrete work 6" thick Concrete slab in first floor
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work B46 6" thick Concrete slab in third floor
Concrete work 6" thick Concrete slab in first floor
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B47 Cement Concrete 1:11/2:3(3/4") lintol size
4' 6''x 6'' with & including formwork
(reinforcement paid seperately)
Concrete work
Concrete work Materials
Concrete work Concrete (As per the item B 05) 1.85 c.ft
Concrete work Sawn form work 13.70 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un / skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B48 Cement Concrete 1:11/2:3(3/4") lintol size
6'' x 9'' with & including formwork
(reinforcement paid seperately)
Concrete work Materials
Concrete work Assume 10L.ft
Concrete work
Concrete work Concrete As per item B 05 3.75 c.ft
Concrete work Sawn form work 20.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un /Skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B49 Cement Concrete 1:11/2:3(3/4") lintol size
9'' x 9'' with & including formwork
(reinforcement paid separately)
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 5.63 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
B50 Cement Concrete 1:11/2:3(3/4") lintol size
9'' x 12'' with & including formwork
(reinforcement paid separately)
Concrete work
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work As per item B 05
Concrete work Concrete 7.50 c.ft
Concrete work Sawn form work 27.72 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
B51 Cement Concrete 1:11/2:3(3/4") lintol size
6'' x 13' 6'' with & including formwork
(reinfrcement paid separately)
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 5.60 c.ft
Concrete work Sawn form work 27.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B52 Cement Concrete 1:11/2:3(3/4") lintol size
9'' x 13 ' 6'' with & including formwork
(reinforcement paid separately)
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 8.40 c.ft
Concrete work Sawn form work 30.00 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un /Skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
Concrete work
B53 Cement Concrete 1:11/2:3 (3/4") lintol size
12'' x 13' 6'' with & including formwork
(reinforcement paid separately)
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 11.20 c.ft
Concrete work Sawn form work 22.50 s.ft
Concrete work
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.25 day
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
B54 Cement Concrete 1:11/2:3(3/4") lintol size
4' 6'' x 4' 6'' with & including formwork
(reinforcement paid separately)
Concrete work Assume 10L.ft
Concrete work Materials
Concrete work
Concrete work Concrete As per item B 05 1.37 c.ft
Concrete work Sawn form work 11.20 s.ft
Concrete work
Concrete work Add
Concrete work Extra Cost of labour
Concrete work Skilled Labour 0.13 day
Concrete work Un /Skilled Labour 0.13 day
Concrete work
Concrete work
Concrete work Cost for one L.ft
Concrete work Preliminaries
Concrete work
Concrete work Cost for one L.ft with prelimineries
Concrete work
Concrete work
Concrete work
Concrete work
B55 Concrete colomns in ground floor 1 :
1 1/2 : 3(3/4") 16 no 9" x 9" columns each
5'0" high
Concrete work
Concrete work Materials
Concrete work Mixed Concrete As per item B 05 0.45 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator operator 0.50 day
Concrete work Un Skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
5% of labour Cost for scaffolding for
scaffolding
Concrete work
Concrete work
Concrete work Water 50.00 gal
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work Cost for 0.45 Cubes
Concrete work Cost for one Cube
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B56 9" x 9" Concrete colomns in first floor
Concrete work
Cost for one Cube 9" x 9" colomns in ground
floor
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B57 9" x 9" Concrete colomns in second floor
Concrete work
Cost for one Cube 9" x 9" colomns in ground
floor
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B58 9" x 9" Concrete colomns in third floor
Concrete work
Cost for one Cube 9" x 9" colomns in ground
floor
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B59 Concrete colomns in ground floor
Concrete work
10 no 12" x 12" colomns each 5' 0" high 0.50
Cube
Concrete work
Concrete work Materials
Concrete work Mixed Concrete As per item B 05 0.50 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work
Concrete work Mason 0.50 day
Concrete work Skilled Labour for Vibrator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
5% of labour Cost for scaffolding for
scaffolding
Concrete work
Concrete work Curing
Concrete work
Concrete work Water 50.00 gal
Concrete work Un / skilled Labour 0.25 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 0.45 Cubes
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B60 12" x 12" Concrete colomns in first floor
Concrete work Cost for one Cube 12" x 12" colomns
Concrete work
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B61 12" x 12" Concrete colomns in second floor
Concrete work Cost for one Cube 12" x 12" colomns
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B62 12" x 12" Concrete colomns in third floor
Concrete work Cost for one Cube 12" x 12" colomns
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
B63 9" x 9" Concrete beams in ground floor level
Concrete work 8 no 9" x 9" beam 10' 0" ft long 0.45 Cube
Concrete work
Concrete work Materials
Concrete work Mixed Concrete As per item no 5 0.45 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work
Concrete work Mason 0.50 day
Concrete work Vibrator operator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
5% of labour Cost for scaffolding for
scaffolding
Concrete work 3% of labour Cost for tools for tool
Concrete work Curing
Concrete work
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work Cost for 0.45 Cubes
Concrete work Cost for one Cube
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B64 9" x 9" Concrete colomns in first floor
Concrete work
Cost of one Cube in 9" x 9" beam in ground
floor
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B65 12" x 12" Concrete colomns in second floor
Concrete work
Cost of one Cube in 9" x 9" beam in ground
floor
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B66 12" x 12" Concrete colomns in third floor
Concrete work
Cost of one Cube in 9" x 9" beam in ground
floor
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B67 Concrete beam in ground floor level 9" x
12"
Concrete work
6 no 9" x 12" beam 10' 0" ft long 0.50 Cube
Concrete work Materials
Concrete work
Concrete work Mixed Concrete As per item B 04 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B68 Concrete beam in first floor 9" x 12"
Concrete work For one Cube 9" x 12" beam in ground floor
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B69 Concrete beam in second floor
9" x 12"
Concrete work For one Cube 9" x 12" beam in ground floor
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B70 Concrete beam in third floor
9" x 12"
Concrete work For one Cube 9" x 12" beam in ground floor
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B71 Concrete beam in ground floor level 12" X
12"
Concrete work
5 no 12" x 12" beam 10' 0" ft long 0.50 Cube
Concrete work Materials
Concrete work mixed Concrete As per item B 05 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work for one Cube without Preliminaries
Concrete work
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work
B72 Concrete beam in first floor
12" x 12"
Concrete work
For one Cube 12" x 12" beam in ground floor
Concrete work Add
Concrete work 2 Un / skilled Labour 1.00 day
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B73 Concrete beam in second floor 12"
x 12"
Concrete work
For one Cube 12" x 12" beam in ground floor
Concrete work Add
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
B74 Concrete beam in third floor
12" x 12"
Concrete work
For one Cube 12" x 12" beam in ground floor
Concrete work Add
Concrete work 4 Un / skilled Labour 2.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B75 4" thick Concrete slab in first floor
Concrete work 0.33 Cube Grade 25
Concrete work Materials
Concrete work mixed Concrete As per item B 05 0.33 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.33 day
Concrete work Skilled Labourfor Vibrator operator 0.33 day
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.33 day
Concrete work Add
Concrete work
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work For one Sqr without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work For one Cube without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B76 4" thick Concrete slab in second floor
Concrete work
Concrete work
Cost for 4"thick Concrete slab in ground floor
Concrete work
Concrete work 2 Un / skilled Labour 0.66 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work For one Cube without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work
Concrete work B77 4" thick Concrete slab in third floor
Concrete work
Concrete work
Cost for 4"thick Concrete slab in ground floor
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work For one Cube without Preliminaries
Concrete work Preliminaries
Concrete work Cost for 1 Cube with Preliminaries
Concrete work
Concrete work B78 5" thick Concrete slab in first floor
Concrete work MIXING Cost
Concrete work 0.42 Cube
Concrete work
Concrete work Materials
Concrete work mixed Concrete As per item no 05 0.42 Cube
Concrete work Add
Concrete work Wastage 5%
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.50 day
Concrete work Vibrator operator 0.50 day
Concrete work 3 Un / skilled Labour 1.50 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.50 day
Concrete work
Concrete work Add
Concrete work
Concrete work
Concrete work
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work B79 5" thick Concrete slab in second floor
Concrete work
Cost for 5"thick Concrete slab in ground floor
Concrete work
Concrete work Un / skilled Labour 0.67 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B80 5" thick Concrete slab in third floor
Concrete work
Cost for 5"thick Concrete slab in ground floor
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work B81 6" thick Concrete slab in first floor
Concrete work MIXING Cost
Concrete work 0.50 Cube
Concrete work Materials
Concrete work mixed Concrete As per item no 05 0.50 Cube
Concrete work Add
Concrete work Wastage
Concrete work
Concrete work LAYING Cost
Concrete work Labour
Concrete work Mason 0.67 day
Concrete work Vibrator operator operator 0.67 day
Concrete work 3 Un / skilled Labour 2.00 day
Concrete work
Concrete work Plant & Equipment
Concrete work Add
Concrete work Vibrator operator 0.67 day
Concrete work
Concrete work Add
Concrete work 3% of labour Cost for tools for tools
Concrete work
5% of labour Cost for scaffolding for
scaffolding
Concrete work Curing
Concrete work Water 100.00 gal
Concrete work Un / skilled Labour 0.33 day
Concrete work
Concrete work Preliminaries
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B82 6" thick Concrete slab in second floor
Concrete work
Cost for 6"thick Concrete slab in ground floor
Concrete work 2 Un / skilled Labour 0.67 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
Concrete work
Concrete work B83 6" thick Concrete slab in third floor
Concrete work
Cost for 6"thick Concrete slab in ground floor
Concrete work 3 Un / skilled Labour 1.00 day
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost for 1 Sqr with Preliminaries
Concrete work
FORM WORK
Formwork
B84 &
B85
Sawn formwork in sides of column foundation
up to D.P.C level
Formwork
Formwork Materials
Formwork 1" thick plank 100.00 s.ft
Formwork 2"x1" 100.00 l.ft
Formwork 2"x2" 20.00 l.ft
Formwork Wire nails 1.00 kg
Formwork
Formwork Add
Formwork for Wastage 5%
Formwork Cost for for use
Formwork
Formwork Cost for one use
Formwork Mould oil 4.00 liter
Formwork
Formwork Labour
Formwork Skilled Labour 1.00 day
Formwork u/ Skilled Labour 1.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
B86 Sawn formwork in 9"X 9" column in ground
floor
Formwork Assume 15 Sq.ft
Formwork Making mould
Formwork Materials
Formwork 1" thick plank class 11 18.00 s.ft
Formwork 2"x1" 9.00 l.ft
Formwork wire nails 0.50 kg
Formwork
Formwork Add
Formwork Wastage 5%
Formwork
Formwork Labour
Formwork Skilled Labour 0.25 day
Formwork u/ Skilled Labour 0.25 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Mouilding Cost for four uses
Formwork
Formwork Mouilding Cost for one uses
Formwork
Formwork B Assembling (Per one use)
Formwork Materials
Formwork 4"x2" Timber - 10 use 9.00 L.ft
Formwork 4"x2" Timber for props-10 use 48.00 L.ft
Formwork 16mm bolt - 20 use 6.00 no
Formwork Mould Oil 0.50 Liter
Formwork
Formwork Labour
Formwork Skilled Labour 0.06 Day
Formwork Un/ Skilled Labour 0.06 Day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork Labour Cost 5%
Formwork B Assebling Cost
Formwork
Formwork C Dismantling cleaning & repairing Cost
Formwork Labour
Formwork Skilled Labour 0.13 Day
Formwork Un/ Skilled Labour 0.13 Day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork labour Cost 5%
Formwork Dismantling cleaning & repairing Cost
Formwork
Formwork Total Cost per use 15 s.ft
Formwork
Formwork
Formwork
Formwork
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
Formwork
Formwork
B.87 Sawn from work in 9"x9" column in first
floor
Formwork Fost for ground floor
Formwork
For column in first floor add 3% to ground
floor rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.88 Sawn from work in 9"x9" column in Second
floor
Formwork Cost for ground floor
Formwork
For column in first floor add 4% to ground
floor rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
B.88a Sawn from work in 9"x9" column in third
floor
Formwork Cost for ground floor
Formwork
For column in first floor add 5% to ground
floor rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.89 Sown form work in 9"x 12" beam in ground
floor 20'-0" long
Formwork A Making mould
Formwork Materials
Formwork 1" thick plank class 11 60.00 s.ft
Formwork 2"x1" 25.00 l.ft
Formwork Wire nails 1.00 kg
Formwork
Formwork Add
Formwork Wastage 5%
Formwork
Formwork Labour
Formwork Skilled Labour 1.00 day
Formwork Un/ Skilled Labour 1.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
5% of labour Cost for scaffolding for
scaffolding (Scaffolding)
Formwork A moulding Cost for one use
Formwork
Formwork B Assembling
Formwork 4"x2" Timber - 15 use 110.00 l.ft
Formwork 4"x2" Timber for props-10 use 22.00 l.ft
Formwork Mould Oil 0.50 liter
Formwork
Formwork Labour
Formwork Skilled Labour 0.50 day
Formwork u/ Skilled Labour 2.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
5% of labour Cost for scaffolding for
scaffolding
Formwork B assembling Cost
Formwork
Formwork C Dismantling cleaning & repairing Cost
Formwork Labour
Formwork Skilled Labour 0.25 day
Formwork u/ Skilled Labour 0.25 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
5% of labour Cost for scaffolding for
scaffolding
Formwork Dismantling cleaning & repairing Cost
Formwork
Formwork Total Cost per use 55 s.ft
Formwork
Formwork
Formwork
Formwork Total Cost per use Sqr.
Formwork Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
Formwork
Formwork
B.90 Sawn from work in 9"x12" column in first
floor
Formwork Cost for ground floor
Formwork
for column in first floor add 3% to ground
floor rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.91 Sawn from work in 9"x12" column in Second
floor
Formwork Cost for ground floor
Formwork
for column in first floor add 4% to ground
floor rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.92 Sawn from work in 9"x12" column in third
floor
Formwork Cost for ground floor
Formwork
for column in first floor add 5% to ground
floor rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork B93 FORM WORK
Formwork
Sawn formwork for sofit of first floor slab
Formwork
Formwork Making mould
Formwork Materials
Formwork 1" thick plank class 11 100.00 s.ft
Formwork 2"x4" 55.00 l.ft
Formwork wire nails 2.00 kg
Formwork
Formwork Add
Formwork Wastage 5%
Formwork
Formwork Labour
Formwork Skilled Labour 0.75 day
Formwork u/ Skilled Labour 0.75 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
Formwork Mouilding Cost for four uses
Formwork
Formwork Mouilding Cost for one uses
Formwork
Formwork B Assembling (Per one use)
Formwork Materials
Formwork 4"x2" Timber props- (10 uses) 250.00 l.ft
Formwork 2"x1" Timber for props-(10 uses) 50.00 l.ft
Formwork Base plate (10 uses) 20.00 no
Formwork Mould Oil 0.50 liter
Formwork
Formwork Labour
Formwork Skilled Labour 1.50 day
Formwork 2 u/ Skilled Labour 3.00 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
5% of labour Cost for scaffolding for
scaffolding
Formwork B Assebling Cost
Formwork
Formwork C Dismantling cleaning & repairing Cost
Formwork Labour
Formwork Skilled Labour 0.25 day
Formwork 2 u/ Skilled Labour 0.50 day
Formwork
Formwork Add
Formwork 3% of labour Cost for tools for tools
Formwork
5% of labour Cost for scaffolding for
scaffolding
Formwork Dismantling cleaning & repairing Cost
Formwork
Formwork
Formwork
Formwork
Formwork Total Cost per use 1Sqr
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
Formwork
B. 94 Sawn formwork in soffit of slab second flor
Formwork Cost for ground floor
Formwork
For beam in second floor add 4%to ground
floor rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
Formwork
B.95 Sawn formwork in soffit of slab third flor
Formwork Cost for ground floor
Formwork
For beam in third floor add 5%to ground floor
rate
Formwork Cost for 1 Sqr with Preliminaries
Formwork Add Preliminaries
Formwork
Formwork Cost for 1 Sqr with Preliminaries
Formwork
Formwork
REINFORCEMENT
Reinforcement B96,B97,B101,B102,B106,&B107
Reinforcement
B 96 25 mm & 20mm dia tor steel reinforcement
in fdn, Ground & first level.
Reinforcement
Reinforcement Material
Reinforcement 25 dia Bars 50.00 Kg
Reinforcement Binding wire 0.25 Kg
Reinforcement
Reinforcement Wastage 10%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.00 day
Reinforcement Un Skilled Labour 1.00 day
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement B98,B103,&B108
Reinforcement
B 98 16mm dia tor steel reinforcement up to
first level.
Reinforcement
Reinforcement Material
Reinforcement 16 dia Bars 50.00 Kg
Reinforcement Binding wire 0.25 Kg
Reinforcement
Reinforcement Wastage 5%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.00 day
Reinforcement Un Skilled Labour 1.00 day
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement B99,B100,B104,B105,B109&B110
Reinforcement
B 99 12mm dia &10mm dia tor steel
reinforcement up to first level.
Reinforcement
Reinforcement Material
Reinforcement 16 dia Bars 50.00 Kg
Reinforcement Binding wire 0.75 Kg
Reinforcement
Reinforcement Wastage 10%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.25 day
Reinforcement Un Skilled Labour 1.25 day
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement B111&B112
Reinforcement
B 111 25mm dia &20mm dia tor steel
reinforcement in second floor
Reinforcement
Reinforcement Ground floor rate
Reinforcement
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.13 day
Reinforcement Un Skilled Labour 0.13 day
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement For scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
B 113 16mm dia tor steel reinforcement in second
floor level & third floor level
Reinforcement
Reinforcement ground floor rate
Reinforcement
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.13 day
Reinforcement Un Skilled Labour 0.13 day
Reinforcement
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement for scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement B114 & B115
Reinforcement
B 114 12mm & 10mm dia tor steel reinforcement
in second floor level & third floor level
Reinforcement
Reinforcement ground floor rate
Reinforcement
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.13 day
Reinforcement Un Skilled Labour 0.13 day
Reinforcement
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement for scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement B116,B117,B118,B119,B120&B121
Reinforcement
B 116 10mm & 6mm dia mild steel reinforcement
up to first floor level
Reinforcement
Reinforcement Material
Reinforcement 6mm dia Bars 50.00 Kg
Reinforcement Binding wire 1.00 Kg
Reinforcement
Reinforcement Wastage 5%
Reinforcement
Reinforcement Spacers & Chairs 1.5%
Reinforcement
Reinforcement
Reinforcement Labour
Reinforcement Skilled Labour 1.25
Reinforcement Un Skilled Labour 1.25
Reinforcement
Reinforcement
Reinforcement 3% of labour Cost for tools for tools
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement B122 & B123
Reinforcement
B122 10mm & 6mm dia mild steel reinforcement
in second floor level & third floor level
Reinforcement
Reinforcement ground floor rate
Reinforcement
Reinforcement Add extra for
Reinforcement Labour
Reinforcement Skilled Labour 0.25 day
Reinforcement Un Skilled Labour 0.25 day
Reinforcement
Reinforcement Add
Reinforcement 3% of labour Cost for tools for tools
Reinforcement for scaffolding 5%of labour Cost
Reinforcement
Reinforcement Cost of 50 Kg
Reinforcement Cost for one Kg
Reinforcement
Reinforcement
Reinforcement Cost for one Kg with Preliminaries
Reinforcement
Reinforcement
Reinforcement
Reinforcement
Masonary work BRICK WORK
Masonary work
C.01 One brick thick brick wall in common brick
in cement & sand 1:5 in ground floor level
Masonary work
Masonary work Materials
Masonary work Bricks 1650.00 No
Masonary work Cement 4.00 bag
Masonary work Sand 0.25 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.50 day
Masonary work Un / skilled Labour 3.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
C.02 One brick thick brick wall in common brick
in cement & sand 1:5 in first floor
Masonary work Materials
Masonary work Bricks 1650.00 No
Masonary work Cement 4.00 bag
Masonary work Sand 0.25 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 3.00 day
Masonary work Un / skilled Labour 3.50 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
Masonary work
Masonary work
C 03 One brick thick brick wall in common brick
in cement & sand 1:5 in second floor
Masonary work Materials
Masonary work Bricks 1650.00 No
Masonary work Cement 4.00 bag
Masonary work Sand 0.25 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 3.25 day
Masonary work Un / skilled Labour 4.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
C.04 Half brick thick brick wall in common brick
in cement & sand 1:5 in ground floor
Masonary work Materials
Masonary work Bricks 660.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 75.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.25 day
Masonary work Un/skilled Labour 2.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
C.05 Half brick thick brick wall in common brick
in cement & sand 1:5 in first floor
Masonary work Materials
Masonary work Bricks 660.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 75.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un/skilled Labour 2.25 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
C.06 Half brick thick brick wall in common brick
in cement & sand 1:5 in second floor
Masonary work Materials
Masonary work Bricks 660.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 75.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.75 day
Masonary work Un / skilled Labour 2.50 day
Masonary work
Masonary work Add
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
C.07 9''X 9'' Brick column in cement & sand 1:
5 in ground floor
Masonary work 10nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 475.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 1.25 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.08 9''X 9'' Brick column in cement & sand 1:
5 in first floor
Masonary work 10nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 475.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un/skilled Labour 1.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.09 9''X 9'' Brick column in cement & sand
1: 5 in second floor
Masonary work
Masonary work 10nos column 5'-0" high
Masonary work Materials
Masonary work Bricks 475.00 No
Masonary work Cement 1.50 bag
Masonary work Sand 0.10 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.75 day
Masonary work Un / skilled Labour 1.75 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.10 12''X 12'' Brick column in cement & sand
1: 5 in ground floor
Masonary work 6nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 415.00 No
Masonary work Cement 1.10 bag
Masonary work Sand 0.08 Cube
Masonary work Water 60.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.00 day
Masonary work Un / skilled Labour 1.00 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.11 12''X 12'' Brick column in cement & sand
1: 5 in first floor
Masonary work
Masonary work 6nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 415.00 No
Masonary work Cement 1.10 bag
Masonary work Sand 0.08 Cube
Masonary work Water 60.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.25 day
Masonary work Un / skilled Labour 1.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.12 12''X 12'' Brick column in cement & sand
1: 5 in second floor
Masonary work
Masonary work 6nos column 5'-0" high
Masonary work
Masonary work Materials
Masonary work Bricks 415.00 No
Masonary work Cement 1.10 bag
Masonary work Sand 0.08 Cube
Masonary work Water 50.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.25 day
Masonary work Un/skilled Labour 1.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 L.ft with Preliminaries
Masonary work
Masonary work
C.13 One brick thick brick wall in common brick
in cement & sand 1:5 in ground floor level
Masonary work Materials
Masonary work Bricks 1240.00 No
Masonary work Cement 3.00 bag
Masonary work Sand 0.20 Cube
Masonary work Water 125.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.00 day
Masonary work Un/skilled Labour 2.25 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
C.14 One brick thick brick wall in common brick
in cement & sand 1:5 in first floor level
Masonary work
Masonary work Materials
Masonary work Bricks 1240.00 No
Masonary work Cement 3.00 bag
Masonary work Sand 0.20 Cube
Masonary work Water 125.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.75 day
Masonary work Un/skilled Labour 3.25 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
C.15 One brick thick brick wall in common brick
in cement & sand 1:5 in second floor level
Masonary work
Masonary work Materials
Masonary work Bricks 1240.00 No
Masonary work Cement 3.00 bag
Masonary work Sand 0.20 Cube
Masonary work Water 125.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.75 day
Masonary work Un/skilled Labour 3.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.01 6" X 9" Random rubble Masonry in cement &
sand 1:5 in foundation
Masonary work
Masonary work Materials
Masonary work Rubble 1.35 Cube
Masonary work Cement 5.00 bag
Masonary work Sand 0.40 Cube
Masonary work Water 100.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 3.00 day
Masonary work Un / skilled Labour 3.50 day
Masonary work
Masonary work Add
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Cube with Preliminaries
Masonary work
Masonary work
Masonary work
D.02 6" X 9" Random rubble Masonry in cement &
sand 1:5 in 1' 6" thick wall
Masonary work
Masonary work Materials
Masonary work Rubble 2.00 Cube
Masonary work Cement 7.50 bag
Masonary work Sand 0.60 Cube
Masonary work Water 150.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 4.50 day
Masonary work Un / skilled Labour 4.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.03 6" X 9" Random rubble Masonry in cement &
sand 1:5 in 2' 0" thick wall
Masonary work Materials
Masonary work Rubble 2.70 Cube
Masonary work Cement 10.00 bag
Masonary work Sand 0.80 Cube
Masonary work Water 200.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 5.50 day
Masonary work Un / skilled Labour 5.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.04 6" X 9" Random rubble Masonry in cement &
sand 1:5 in 2' 6" thick wall
Masonary work Materials
Masonary work Rubble 3.50 Cube
Masonary work Cement 12.00 bag
Masonary work Sand 1.00 Cube
Masonary work Water 300.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 6.50 day
Masonary work Un / skilled Labour 6.50 day
Masonary work
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.05 8" thick Solid block work in cement & sand
1;5 in ground floor (cavites un filled)
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.85 bag
Masonary work Sand 0.08 Cube
Masonary work Water 100.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.25 day
Masonary work Un / skilled Labour 2.50 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.06 4" thick Solid block work in cement & sand
1:5 in ground floor ( cavite un filled)
Masonary work Materials
Masonary work Block 112.00 no
Masonary work Cement 0.40 bag
Masonary work Sand 0.05 Cube
Masonary work Water 80.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 1.50 day
Masonary work
Masonary work Tools 3% of labour Cost for tools
Masonary work
Scaffolding 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.07 6" thick Solid block work in cement & sand
1;5 in ground floor (Cavity un filled)
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.65 bag
Masonary work Sand 0.07 Cube
Masonary work Water 90.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 2.00 day
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.08 8" thick Solid block work in cement & sand
1;5 in first floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled Labour 0.33 day
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.9 4" thick Solid block work in cement & sand
1;5 in first floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.10 6" thick Solid block work in cement & sand
1;5 in first floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor 7.00
Masonary work
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.11 8" thick Solid block work in cement & sand
1;5 in second floor(cavities un filled)
Masonary work
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
D.12 4" thick Solid block work in cement & sand
1;5 insecond floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
Masonary work
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
D.13 6" thick Solid block work in cement & sand
1;5 in second floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.50 day
Masonary work Un/skilled Labour 0.75 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.14 8" thick Hollow block work in cement & sand
1;5 in ground floor (cavites un filled)
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.85 bag
Masonary work Sand 0.08 Cube
Masonary work Water 100.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 2.25 day
Masonary work Un / skilled Labour 2.50 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.15 4" thick Hollow block work in cement & sand
1:5 in ground floor ( cavite un filled)
Masonary work Materials
Masonary work Block 112.00 no
Masonary work Cement 0.40 bag
Masonary work Sand 0.05 Cube
Masonary work Water 80.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 1.50 day
Masonary work
Masonary work Tools 3% of labour Cost for tools
Masonary work
Scaffolding 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.16 6" thick Hollow block work in cement & sand
1;5 in ground floor (Cavity un filled)
Masonary work Materials
Masonary work block 112.00 no
Masonary work Cement 0.65 bag
Masonary work Sand 0.07 Cube
Masonary work Water 90.00 gal
Masonary work
Masonary work Labour
Masonary work Mason 1.50 day
Masonary work Un / skilled Labour 2.00 day
Masonary work
Masonary work Add
Masonary work 3% of labour Cost for tools
Masonary work 5% of labour Cost for scaffolding
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.17 8" thick Hollow block work in cement & sand
1;5 in first floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled Labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
D.18 4" thick Hollow block work in cement & sand
1;5 in first floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
D.19 6" thick Hollow block work in cement & sand
1;5 in first floor
(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor 7.00
Masonary work
Masonary work add
Masonary work Extra labour Cost
Masonary work Skilled labourer 0.13 day
Masonary work Un/skilled labour 0.33 day
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.20 8" thick Hollow block work in cement & sand
1;5 in second floor(cavities un filled)
Masonary work
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
Masonary work
Masonary work
Masonary work
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
D.21 4" thick Hollow block work in cement & sand
1;5 insecond floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.33 day
Masonary work Un/skilled Labour 0.50 day
Masonary work
Masonary work
Masonary work Add
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
D.22 6" thick Hollow block work in cement & sand
1;5 in second floor(cavities un filled)
Masonary work Materials
Masonary work Block work Cost for ground floor
Masonary work
Masonary work Extra labour Cost
Masonary work Mason 0.50 day
Masonary work Un/skilled Labour 0.75 day
Masonary work
Masonary work
Masonary work Add
Masonary work Preliminaries
Masonary work
Masonary work Cost for 1 Sqr with Preliminaries
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Masonary work
Roofwork
E.01 Calicut pattern tile hip roof in single storey
building consisting of wall plate ridge plate
beam struct rafters & reepers.
Roofwork Materials
Roofwork Class 1 Timber 5.55 c.ft
Roofwork Wastage 5%
Roofwork Reepers 2" x 2" 110.00 l.ft
Roofwork Wire nails 1.50 kg
Roofwork Calicut tiles 125.00 no
Roofwork Woodpreservitive 1.50 liter
Roofwork
Roofwork Labour
Roofwork Mason 2.00 day
Roofwork Un/skilled Labour 3.00 day
Roofwork
Roofwork Add
Roofwork Tools 3% of labour Cost for tools
Roofwork
Roofwork
Scaffolding 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
Roofwork
E.02 Calicut pattern ridge tile hip tile on single
storey building in cement lime & sand 1;1;5
coloured to match tile
Roofwork Materials
Roofwork Ridge tile 14.00 no
Roofwork sand 2.50 c.ft
Roofwork cement 0.35 bag
Roofwork lime 8.00 kg
Roofwork colouring powder 0.05 kg
Roofwork
Roofwork Labour
Roofwork s/k labourer 0.50 day
Roofwork Un/skilled Labour 0.50 day
Roofwork
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost per one L ft with Preliminaries
Roofwork
Roofwork
E.03 Corrugated asbastos cement sheet roofing
with Timber fram in single storeyed
building.
Roofwork
Roofwork Materials
Roofwork Class 1 Timber 3.50 c.ft
Roofwork wire nails 1.00 kg
Roofwork asbastos sheet 115.00 sq.ft
Roofwork J bolt 20.00 no
Roofwork woodpreservitive 1.00 liter
Roofwork
Roofwork Labour
Roofwork s/k labour 1.50 day
Roofwork Un/skilled Labour 2.50 day
Roofwork
Roofwork .
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.04 Asbastos ajestable close fitting ridge fixed
complete with roofing screws or bolts
Roofwork Materials
Roofwork Ridge 4.00 pair
Roofwork Roofing screws 16.00 no
Roofwork
Roofwork Labour
Roofwork s/k labourer 0.25 day
Roofwork Un/skilled Labour 0.25 day
Roofwork
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost per one L ft with Preliminaries
Roofwork
Roofwork
Roofwork
E.05 Corrugated asbastos cement sheet rooing
with Timber frame in single storeyed
building.
Roofwork Materials
Roofwork Asbastos sheet 115.00 s.ft
Roofwork J bolt 20.00 no
Roofwork woodpreservitive 1.00 liter
Roofwork
Roofwork Labour
Roofwork s/k labourer 0.50 day
Roofwork 2 Un/skilled Labour 0.50 day
Roofwork
Roofwork Add
Roofwork Tools
Roofwork 3% of labour Cost for tools
Roofwork
Roofwork Scaffolding
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.06 Half round tile on asbastos sheet roof
(crest only )
Roofwork Materials
Roofwork half round tile 500.00 no
Roofwork Labour
Roofwork 2 Un/skilled Labour 0.38 day
Roofwork
Roofwork Add
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.07 3/4" thick 9" high valance board fixed with
brass screws to end of rafters with &
including one coat of primer & two coats of
enamel paint
Roofwork Materials
Roofwork Class 1 Timber 100.00 l.ft
Roofwork Wastage 5%
Roofwork Brass screws 100.00 no
Roofwork Wood primer 2.00 lit
Roofwork Enamel paint 4.00 lit
Roofwork Brush 0.10 no
Roofwork sand paper 3.00 no
Roofwork wood preservitive 2.00 lit
Roofwork
Roofwork Labour
Roofwork painter 1.00 day
Roofwork carpenter 3.00 day
Roofwork Un/skilled Labour 3.00 day
Roofwork
Roofwork Add
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost per one L.ft with Preliminaries
Roofwork
Roofwork
Roofwork
E.08 Asbastos cement plian sheet ceiling with
class 1 Timber frame consisting of
4''x2"joist 2"x2" & 2"x1" battens 11/2"
x11/2" cove moulding & 1/2"x1/2" beadings
with painting
Assume 1.2 Sqr
Roofwork Materials
Roofwork 4"x2" 48.00 l.ft
Roofwork 2"x2" 72.00 l.ft
Roofwork 2"x1" 18.00 l.ft
Roofwork asbastos ceiling sheet 138.00 s.ft
Roofwork wire nails 1.50 kg
Roofwork 11/2" x 11/2" cove mouilding 44.00 l.ft
Roofwork 1/2" x 1/2" beading 48.00
Roofwork primer 1.50 l.ft
Roofwork Emlusion paint 1.75 l.ft
Roofwork Brush 0.07 no
Roofwork sand paper 2.00 no
Roofwork wood preservitive 1.00 lit
Roofwork
Roofwork
Roofwork Labour
Roofwork painter 1.25 day
Roofwork carpenter 2.25 day
Roofwork Un/skilled Labour 2.00 day
Roofwork
Roofwork
Roofwork Add
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork
Roofwork Preliminaries
Roofwork
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Roofwork
Roofwork
E.09 3/4" thick class 1 Timber ceiling with class
1 Timber frame consisting of 4''x2"joist
2"x2" & 2"x1" battens 11/2" x11/2" cove
moulding with painting
Roofwork Materials
Roofwork 4"x2" 48.00 l.ft
Roofwork 2"x2" 72.00 l.ft
Roofwork 2"x1" 18.00 l.ft
Roofwork 3/4" tk class 1 Timber ( Lumumidella ) 138.00 s.ft
Roofwork wire nails 1.00 kg
Roofwork 11/2" x 11/2" cove mouilding 44.00 l.ft
Roofwork primer 1.50 lit
Roofwork Emlusion paint 1.75 lit
Roofwork Brush 0.06 no
Roofwork sand paper 2.00 no
Roofwork wood preservitive 1.00 lit
Roofwork
Roofwork
Roofwork Labour
Roofwork painter 1.25 day
Roofwork Skilled labour 2.50 day
Roofwork Un/skilled Labour 2.50 day
Roofwork
Roofwork 3% of labour Cost for tools
Roofwork 5% of labour Cost for scaffolding
Roofwork
Roofwork Preliminaries
Roofwork Cost for 1 Sqr with Preliminaries
Roofwork
Plumbing PVC Pipe type 1000
Plumbing
F .01 20mm diameter pvc pipe fixed to wall or
slab
Plumbing Materials
Plumbing 20mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
F.02 25mm diameter pvc pipe fixed to wall or
slab
Plumbing Materials
Plumbing 25mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.03 32mm diameter pvc pipe fixed to wall
Plumbing Materials
Plumbing 32mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.04 32mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 32mm pipe 50.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Others
Plumbing
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.05 40mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 40mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 100.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.06 40mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 40mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Others
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.07 50mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 50mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.08 50mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 50mm pipe 50.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.09 63mm diameter pvc pipefix to wall
Plumbing Materials
Plumbing 63mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing clipe & nails
Plumbing Others
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.10 63mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 63mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing Others
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.11 75mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 75mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 100.00 grms
Plumbing Other
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.12 75mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 75mm pipe 50.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing Other
Plumbing
Plumbing Labour
Plumbing excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.13 90mm diameter pvc pipe fix to wall
Plumbing Materials
Plumbing 90mm pipe 50.00 l.ft
Plumbing clipe & nails
Plumbing solvent cement 150.00 grms
Other
Plumbing
Plumbing Labour
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing
Plumbing F.14 90mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 90mm pipe 50.00 l.ft
Plumbing solvent cement 150.00 grms
Other
Plumbing
Plumbing Labour
Plumbing Excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.15 110mm diameter pvc pipe laying trench
Plumbing Materials
Plumbing 110mm pipe 50.00 l.ft
Plumbing solvent cement 150.00 grms
Other
Plumbing
Plumbing Labour
Plumbing Excavation 0.75 day
Plumbing Skilled labourer 0.75 day
Plumbing Un/skilled Labour 0.75 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Lft with Preliminaries
Plumbing
Plumbing F.16 Supplying & fixing PVC bend 20mm dia.
Plumbing Materials
Plumbing bend 10.00 Nos
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.17 Supplying & fixing PVC bend 25mm dia.
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.18 Supplying & fixing PVC bend 32mm dia.
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.19 Supplying & fixing PVC bend 40mm dia.
Plumbing
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.20 Supplying & fixing PVC bend 50mm dia.
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.21 Supplying & fixing PVC bend 63mm dia.
Plumbing Materials
Plumbing bend 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing ELBOW
Plumbing F.22 Supplying & fixing PVC elbow 20mm .dia.
Plumbing
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.23 Supplying & fixing PVC elbow 25mm .dia.
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.24 Supplying & fixing PVC elbow 32mm .dia.
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.25 Supplying & fixing PVC elbow 40mm .dia.
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.26 Supplying & fixing PVC elbow 50mm .dia.
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.27 Supplying & fixing PVC elbow 63mm .dia.
Plumbing Materials
Plumbing elbow 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing TEE
Plumbing F.28 Supplying & fixing PVC tee 20mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.50 hrs
Plumbing Un/skilled Labour 1.50 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.29 Supplying & fixing PVC tee 25mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 60.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.50 hrs
Plumbing Un/skilled Labour 1.50 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.30 Supplying & fixing PVC tee 32mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.31 Supplying & fixing PVC tee 40mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 90.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.32 Supplying & fixing PVC tee 50mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 120.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing F.33 Supplying & fixing PVC tee 63mm .dia.
Plumbing Materials
Plumbing tee 10.00 l.ft
Plumbing solvent cement 200.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing FAUCET SOCKET
Plumbing
F.34 Supplying & fixing PVC faucet socket 20 mm
dia
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.35 Supplying & fixing PVC faucet socket 25 mm
dia
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.36 Supplying & fixing PVC faucet socket 32 mm
dia
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un /Skilled labourer 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.37 Supplying & fixing PVC faucet socket 40 mm
dia
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.38 Supplying & fixing PVC faucet socket 50 mm
dia
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.39 Supplying & fixing PVC faucet socket 63 mm
dia
Plumbing Materials
Plumbing Faucet socket 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing VALUE SOCKET
Plumbing
F.40 Supplying & fixing PVC Value socket 20 mm
dia
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.41 Supplying & fixing PVC value socket 25 mm
dia
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing 3% of labour Cost for tools
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.42 Supplying & fixing PVC value socket 32 mm
dia
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.43 Supplying & fixing PVC value socket 40 mm
dia
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
F.44 Supplying & fixing PVC value socket 50 mm
dia
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing
F.45 Supplying & fixing PVC value socket 63 mm
dia
Plumbing Materials
Plumbing value socket 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing SOCKET
Plumbing F.46 Supplying & fixing PVC socket 20 mm dia
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 40.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.47 Supplying & fixing PVC socket 25 mm dia
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un /Skilled labourer 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.48 Supplying & fixing PVC socket 32 mm dia
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 50.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.49 Supplying & fixing PVC socket 40 mm dia
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 75.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 1.00 hrs
Plumbing Un/skilled Labour 1.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.50 Supplying & fixing PVC socket 50 mm dia
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 100.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1Nos with Preliminaries
Plumbing
Plumbing
Plumbing
Plumbing F.51 Supplying & fixing PVC socket 63 mm dia
Plumbing Materials
Plumbing socket 10.00 l.ft
Plumbing solvent cement 140.00 grms
Plumbing
Plumbing Labour
Plumbing Skilled labourer 2.00 hrs
Plumbing Un/skilled Labour 2.00 hrs
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing Scaffolding
Plumbing 5% of labour Cost for scaffolding
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 Nos with Preliminaries
Plumbing
Plumbing
Finishes
Finishes
G.01 3/4" Thick plaster in cement lime & sand
1:1:5 finished smooth with neat lime in
internal wall in ground floor
Finishes Internal wall
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 1.50 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Cost for 1 Sqr without Preliminaries
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.02 3/4" Thick plaster in cement lime & sand
1:1:5 finished semi rough in external wall in
ground floor
Finishes External wall
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 30.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.33 day
Finishes un /Skilled labourer 1.33 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Cost for 1 Sqr without Preliminaries
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.03 3/4" Thick plaster in cement lime & sand
1:1:5 finished smooth in internal wall in
first floor
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.75 day
Finishes un /Skilled labourer 1.75 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Cost for 1 Sqr without Preliminaries
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.04 3/4" Thick plaster in cement lime & sand
1;1;5 finished semi rough in external wall in
first floor
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 30.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 1.75 day
Finishes
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
Finishes
G.05 3/4" Thick plaster in cement lime & sand
1:1:5 finished semi rough in internal wall in
second floor
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.00 day
Finishes un /Skilled labourer 2.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
G.06 3/4" Thick plaster in cement lime & sand
1:1:5 finished semi rough in external wall in
second floor
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 30.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.75 day
Finishes un /Skilled labourer 2.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
G.07 1/2" Thick sides & soffits plaster in first
floor slab in cement lime & sand 1:1:5
finished smooth with neat lime.
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.06 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.25 hrs
Finishes un /Skilled labourer 2.00 hrs
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.08 1/2" Thick sides & soffits plaster in
second floor slab in cement lime & sand
1;1;5 finished smooth with neat lime
Finishes
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.04 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.25 day
Finishes un /Skilled labourer 2.25 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
Finishes
G.09 3/4" thick D.P.C. in cement and sand 1:3
finished with two coats of hot tar and
blinded with sand.
Finishes Materials
Finishes Cement 2.00 bags
Finishes Sand 0.11 Cube
Finishes Tar 8.00 Ltr
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 2.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.10 1/2" Thick sides & soffits plaster in first
floor beam in cement lime & sand 1:1:5
finished smooth with neat lime
Finishes Materials
Finishes Cement 0.85 bags
Finishes Lime 60.00 kg
Finishes Sand 0.04 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.50 day
Finishes un /Skilled labourer 2.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
G.11 1/2" Thick sides & soffits plaster in
second floor beam in cement lime & sand
1:1:5 finished smooth with neat lime
Finishes Materials
Finishes cement 0.85 bags
Finishes lime 60.00 kg
Finishes sand 0.04 Cube
Finishes Water 20.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 2.75 hrs
Finishes un /Skilled labourer 2.25 hrs
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes 5% of labour Cost for scaffolding
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes H.01 PAVING
Finishes
3" Thick brick paving lime & sand 1:5 with
& including 1/2" thick cement & sand 1:3
rendering finished smooth with neat cement
Finishes brick 360.00 Nos
Finishes cement 2.00 bag
Finishes lime 30.00 Kg
Finishes sand 0.18 Cube
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.50 day
Finishes un /Skilled labourer 1.75 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H.02 1/2" Thick cement rendering in cement &
sand 1':3 finished smooth with neat cement
Finishes Materials
Finishes Cement 1.25 bags
Finishes Sand 0.04 Cube
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 1.00 day
Finishes un /Skilled labourer 1.00 day
Finishes
Finishes Add
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
H.03 6" X6" White glazed tile including joint and
point with tile grout & including 3/4" tk
cement ^& sand 1;3 screed backing on
ground floor
Finishes Fixing only
Finishes Materials
Finishes Tile 400.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
H4 8" X8" White glazed tile including joint and
point with tile grout & including 3/4" tk
cement & sand 1;3 screed backing on
ground floor
Finishes Materials
Finishes Tile 225.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
H5 12" X12" White glazed tile including joint
and point with tile grout & including 3/4" tk
cement & sand 1;3 screed backing on
ground floor
Finishes Materials
Finishes Tile 100.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H6 6" X6" White glazed wall tile including joint
and point with tile grout & including 3/4" tk
cement & sand 1;3 screed backing on wall
Finishes Materials
Finishes Tile 400.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H7 8" X12" White glazed wall tile including
joint and point with tile grout & including
3/4" tk cement & sand 1;3 screed backing
on wall
Finishes Materials
Finishes Tile 150.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Finishes
Finishes
H8 8" X8" White glazed wall tile including joint
and point with tile grout & including 3/4" tk
cement & sand 1;3 screed backing on wall
Finishes Materials
Finishes Tile 225.00 no
Finishes Wastage 5%
Finishes Cement 3.00 bag
Finishes Sand 0.08 Cube
Finishes Tile grout 0.75 kg
Finishes Water 25.00 gal
Finishes
Finishes Labour
Finishes Skilled labourer 3.00 day
Finishes un /Skilled labourer 3.00 day
Finishes
Finishes Add
Finishes Tools
Finishes 3% of labour Cost for tools
Finishes
Finishes
Finishes Preliminaries
Finishes Cost for 1 Sqr with Preliminaries
Finishes
Painting PAINTING
Painting
J-01 Prepare & apply approved type one coat of
filler & two of emulsion paint to specified
colour in ground floor internally
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 0.75 day
Painting un /Skilled labourer 0.75 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
J-02 Prepare & apply approved type one coat of
filler & two of emulsion paint to specified
colour in first floor internally
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.00 day
Painting un /Skilled labourer 0.75 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Painting
J-03 Prepare & apply approved type one coat of
filler & two of weathershield paint to
specified colour up to first floor level
externally(ground floor)
Painting Materials
Painting weathersheld paint 1.65 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.10 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 0.75 day
Painting un /Skilled labourer 0.75 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Painting
J-04 Prepare & apply approved type one coat of
filler & two of weathershield paint to
specified colour above first floor level
Externally
Painting Materials
Painting Weathersheld paint 1.65 Lit
Painting Filler 1.00 Lit
Painting Sand paper 1.00 no
Painting Brush 0.08 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.00 day
Painting un /Skilled labourer 1.00 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Painting
J-05 Prepare & apply approved type one coat of
filler & two of emulsion paint to specified
colour in sides and soffit of beam and slab
in first floor level
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting sand paper 1.00 no
Painting brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.00 day
Painting un /Skilled labourer 1.00 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
J-06 Prepare & apply approved type one coat of
filler & two of emulsion paint to specified
colour in sides and soffit of beams and
slabs in second floor level
Painting Materials
Painting Emulsion paint 1.50 Lit
Painting Filler 1.00 Lit
Painting sand paper 1.00 no
Painting brush 0.07 no
Painting Water 25.00 gal
Painting
Painting Labour
Painting Skilled labourer 1.10 day
Painting un /Skilled labourer 1.10 day
Painting
Painting Add
Painting Tools
Painting 3% of labour Cost for tools
Painting 5% of labour Cost for scaffolding
Painting
Painting
Painting Preliminaries
Painting Cost for 1 Sqr with Preliminaries
Painting
Painting
Electrical Electrical
Electrical K.01 Pendent lamp without bulb and shade
Electrical
Electrical Materials
Electrical 1/044 wire 0.25 coil
Electrical conduit pipe 5/8" 5.00 l.ft
Electrical Bend 1.00 no
Electrical ceiling rose 1.00 no
Electrical Holders 1.00 no
Electrical Switches 1.00 no
Electrical Switch box 1.00 no
Electrical Round block 1.00 no
Electrical Brass screws 1" 1.00 no
Electrical Brass screws 1/2" 2.00 no
Electrical Flexible wire 2 core 6.00 no
Electrical cement lime and sand
Electrical clips and wire nails
Electrical
Electrical Labour
Electrical un Skilled labour for chasing wall 0.13 day
Electrical Electricion 0.33 day
Electrical un Skilled labour 0.33 day
Electrical Mason for prepare surface 0.13 day
Electrical
Electrical Add
Electrical Tools
Electrical 3% of labour Cost for tools
Electrical 5% of labourer Cost
Electrical
Electrical
Electrical Preliminaries
Electrical Cost for one Point with Preliminaries
Electrical
Electrical
Electrical
Electrical K.02 wall bracket with out bulb and shade
Electrical Materials
Electrical 1/044 wire 0.25 coil
Electrical conduit pipe 5/8" 10.00 l.ft
Electrical Bend 2.00 no
Electrical Holders 1.00 no
Electrical Switches 1.00 no
Electrical Switch box 1.00 no
Electrical cement lime and sand
Electrical clips and wire nails
Electrical
Electrical Labour
Electrical un Skilled labour for chasing wall 0.13 day
Electrical Electricion 0.13 day
Electrical un Skilled labour 0.33 day
Electrical Mason for prepare surface 0.33 day
Electrical
Electrical
Electrical Add
Electrical Tools
Electrical 3% of labour Cost for tools
Electrical 5% of labourer Cost
Electrical
Electrical
Electrical Preliminaries
Electrical Cost for one Point with Preliminaries
Electrical
Electrical
Electrical
Electrical K.03 5 amp socket outlets
Electrical Materials
Electrical 5 amp socket outlets 1.00 no
Electrical 1/044 wire 0.25 coil
Electrical 7/044 earth wire 0.10 coil
Electrical conduit pipe 5/8" 10.00 l.ft
Electrical Bend 2.00 no
Electrical Switch box 1.00 no
Electrical cement lime and sand
Electrical clips and wire nails
Electrical
Electrical Labour
Electrical un Skilled labour for chasing wall 0.13 day
Electrical Electricion 0.13 day
Electrical un Skilled labour 0.33 day
Electrical Mason for prepare surface 0.33 day
Electrical
Electrical Add
Electrical 3% of labour Cost for tools
Electrical 5% of labourer Cost
Electrical
Electrical
Electrical Preliminaries
Electrical Cost for one Point with Preliminaries
Electrical
Concrete work
L.01 Suppying & placing ready mixed Concrete
grade 20 (1:2:4 -3/4" ) in 125mm thick
first floor slab
Concrete work
Concrete work Materials
Concrete work Ready mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator 3.00 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
12.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
18.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 3.00 day
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.02 Suppying & placing redy mixed Concrete
grade 20 (1:2:4 -3/4" ) in 225
x225mm columns in ground floor
Concrete work 30 m3 in Colombo Municipal area
Concrete work
222 no columns size 300x300mm &1500mm
high.
Concrete work
Concrete work Materials
Concrete work Redy mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator 4.00 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
16.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
24.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 4.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.03 Suppying & placing ready mixed Concrete
grade 25 (1:1 1/2:3 -3/4" ) in 125mm
thick first floor slab
Concrete work 30m3 in Columbo Municipal area
Concrete work
Concrete work Materials
Concrete work Redy mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 3.00 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
12.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
18.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 3.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.04 Suppying & placing redy mixed Concrete
grade 25(1:11/2:3-3/4) in 225mmx225mm
columns in ground floor.
Concrete work 30m3 in Columbo Municipal area
Concrete work
222 no columns size 300x300mm &1500mm
high.
Concrete work Materials
Concrete work Redy mixed Concrete at site 30.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 1.00 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
16.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
24.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 4.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.05 Suppying & placing ready mixed Concrete
grade 20 (1:2:4-3/4) in 125mm thick first
floor slab
Concrete work 20m3 in Columbo Municipal area
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.00 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
8.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
12.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
L.06 Suppying & placing redy mixed Concrete
grade 20(1:2:4-3/4") in 225mmx225mm
columns in ground floor
Concrete work 20m3 in Columbo Municipal area
Concrete work
148 no columns size 300x300mm &1500mm
high.
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.75 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
11.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
16.50 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.75 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
L.07 Suppying & placing redy mixed Concrete
grade 25 (1:11/2:3-3/4) in 125mm thick
first floor slab
Concrete work 20m3 in Columbo Municipal area
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.00 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
8.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
12.00 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.00 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Concrete work
Concrete work
Concrete work
L.08 Suppying & placing redy mixed Concrete
grade 25(1:11/2:3-3/4") in 225mmx225mm
columns in ground floor
Concrete work 20m3 in Columbo Municipal area
Concrete work
148 no columns size 300x300mm &1500mm
high.
Concrete work Materials
Concrete work Redy mixed Concrete at site 20.00 m3
Concrete work Pumping car charges
Concrete work Pumping car Wastage 0.50 m3
Concrete work
Concrete work Labour
Concrete work 1.00 Vibrator operator operator 2.75 day
Concrete work
4.00 Skilled labour for placing Concrete &
prepairing top surface
11.00 day
Concrete work
6.00 un Skilled labour for placing Concrete &
prepairing top surface
16.50 day
Concrete work
Concrete work Add
Concrete work Tools
Concrete work 3% of labour Cost for tools
Concrete work
Concrete work Plant
Concrete work Vibrator operator 2.75 day
Concrete work
Concrete work Curing
Concrete work un Skilled 2.00 day
Concrete work Water 800.00 gal
Concrete work
Concrete work
Concrete work
Concrete work Preliminaries
Concrete work
Concrete work Cost per 1 m3 wth Preliminaries
Concrete work
Wood work
M 01 singal hung door size 3'-6"x 7'-0" high
overall with 4''x3'' class 1 Timber door
frame and including 11/4" tk ordinary
plywood door sash with and door lock with
and including ironmongrey and painting
Wood work
Wood work Materials
Wood work 4''x3" Timber 20.00 l.ft
Wood work Plywood door sash 1.00 no
Wood work 4"x3" butt hinges 1.50 pair
Wood work 3/4" brass screws 24.00 no
Wood work 6" iong barrel boilt 1.00 no
Wood work 12" long barrel boilt 1.00 no
Wood work 1/2" brass screws 12.00 no
Wood work mortice lock 1.00 no
Wood work enamel paint 1.25 ltr
Wood work wood primer 0.50 ltr
Wood work 4" brush 0.10 no
Wood work hold fast 6.00 no
Wood work sand paper 2.00 no
Wood work
Wood work labour
Wood work painter 0.33 day
Wood work carpainter 2.00 day
Wood work un skilld labourer 2.00 day
Wood work
Wood work Add
Wood work Tools
Wood work 3% of labour Cost for tools
Wood work 5% of labourer Cost
Wood work
Wood work
Wood work Preliminaries
Wood work Cost for door with Preliminaries
Wood work
Wood work
Wood work
Wood work
Wood work
Wood work
M 02 singal hung door size 3'-6"x 7'-0" high
overall with 4''x3'' class 1 Timber door
frame and including 11/4" tk flush panneld
door sash with and door lock with and
including ironmongrey and painting
Wood work
Wood work Materials
Wood work 4''x3" Timber 20.00 l.ft
Wood work 11/4" Timber plank 24.50 no
Wood work Wastage 5%
Wood work 4"x3" b utt hinges 1.50 pair
Wood work 3/4" brass screws 24.00 no
Wood work 6" long barrel bolt 1.00 no
Wood work 12" long barrel bolt 1.00 no
Wood work 1/2" brass screws 12.00 no
Wood work Mortice lock 1.00 no
Wood work Enamel paint 1.25 ltr
Wood work Wood primer 0.50 ltr
Wood work 4" brush 0.10 no
Wood work Hold fast 6.00 no
Wood work Sand paper 2.00 no
Wood work
Wood work Labour
Wood work painter 0.50 day
Wood work carpainter 3.50 day
Wood work un skilld labourer 2.50 day
Wood work
Wood work Add
Wood work Tools
Wood work 3% of labour Cost for tools
Wood work 5% of labourer Cost
Wood work
Wood work
Wood work Preliminaries
Wood work Cost for door with Preliminaries
Wood work
Wood work
Wood work
Wood work
Wood work
Wood work
M 03 window size 5'-0"x 6'-0" high overall with
4''x3'' class 1 Timber window frame and
mullion comprising 1 tk glased window
casement and including ironmongrey and
painting
Wood work Materials
Wood work 4''x3" Timber 30.00 l.ft
Wood work 1" Timber plank 6" wide. 23.00 no
Wood work Wastage 5%
Wood work glaze sheet 16.00 s ft
Wood work 4"x2" butt hinges 2.00 pair
Wood work 3/4" brass screws 32.00 no
Wood work casement fastner 2.00 no
Wood work casement stay 2.00 no
Wood work 1/2" brass screws 16.00 no
Wood work enamel paint 0.75 ltr
Wood work wood primer 0.25 ltr
Wood work 4" brush 0.10 no
Wood work hold fast 6.00 no
Wood work sand paper 1.00 no
Wood work
Wood work
Wood work labourer
Wood work painter 0.50 day
Wood work carpenter 3.50 day
Wood work un skilld labourer 2.50 day
Wood work
Wood work Add
Wood work Tools
Wood work 3% of labour Cost for tools
Wood work 5% of labourer Cost
Wood work
Wood work
Wood work Preliminaries
Wood work Cost for door with Preliminaries
Wood work
Wood work
Plumbing
N01 supplying & laying hot Water pipe 20mm dia
Plumbing Assume 15 L.ft
Plumbing
Plumbing Polybuthelene pipe 20.00 l.ft
Plumbing elbow 3.00 no
Plumbing faucet socket 2.00 no
Plumbing value socket 2.00 no
Plumbing cement sand and lime
Plumbing
Plumbing labour for placing pipe
Plumbing unSkilled labourer for chasing wall 0.33 day
Plumbing plumber 0.50 day
Plumbing Mason 0.13 day
Plumbing
Plumbing Add
Plumbing Tools
Plumbing 3% of labour Cost for tools
Plumbing 5% of labourer Cost
Plumbing
Plumbing
Plumbing Preliminaries
Plumbing
Plumbing Cost for 1 L.ft with Preliminaries
Plumbing
Rate Amount Amount
1 Sqr 736.45
650.00 650.00
19.50
669.50
66.95
736.45
1 Sqr 920.56
650.00 812.50
24.38
836.88
83.69
920.56
1 Cube 1,288.79
650.00 1,137.50
34.13
1,171.63
117.16
1,288.79
1 Cube 1,472.90
650.00 1,300.00
39.00
1,339.00
133.90
1,472.90
1 Cube 1,841.13
650.00 1,625.00
48.75
1,673.75
167.38
1,841.13
1 Cube 1,657.01
650.00 1,462.50
43.88
1,506.38
150.64
1,657.01
1 Cube 2,025.24
650.00 1,787.50
53.63
1,841.13
184.11
2,025.24
1 Cube 1,996.96
650.00 1,625.00
850.00 141.67
48.75
1,815.42
181.54
1,996.96
1 Cube 1,657.01
650.00 1,462.50
43.88
1,506.38
150.64
1,657.01
1 Cube 4,555.79
2,200.00 2,970.00
650.00 1,137.50
34.13
4,141.63
414.16
4,555.79
1 Cube 4,555.79
2,200.00 2,970.00
650.00 1,137.50
34.13
4,141.63
414.16
4,555.79
1 Sqr 5,070.18
125.00 5,000.00
165.00 6,600.00
165.00 6,600.00
160.00 80.00
18,280.00
548.40
18,828.40
4,707.10
950.00 475.00
650.00 325.00
800.00
24.00
5,531.10
4,609.25
553.11
6,084.21
5,070.18
1 Sqr 8,619.19
125.00 13,750.00
165.00 6,600.00
165.00 3,960.00
160.00 80.00
24,390.00
6,097.50
950.00 712.50
650.00 975.00
1,687.50
50.63
7,835.63
783.56
8,619.19
1 Sqr 7,055.76
125.00 27,500.00
780.00 4,680.00
160.00 1,920.00
160.00 320.00
34,420.00
1,032.60
35,452.60
8,863.15
950.00 1,900.00
650.00 1,950.00
3,850.00
115.50
12,828.65
6,414.33
1,282.87
14,111.52
7,055.76
1 Cube 30,156.32
740.00 9,620.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
18,682.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
21,062.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
27,414.83
2,741.48
30,156.32
1 Cube 30,156.32
740.00 9,620.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
18,682.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
21,062.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
27,414.83
2,741.48
30,156.32
1 Cube 30,970.32
740.00 10,360.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
19,422.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
21,802.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
28,154.83
2,815.48
30,970.32
1 Cube 34,226.32
740.00 13,320.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
22,382.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
24,762.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
31,114.83
3,111.48
34,226.32
1 Cube 38,296.32
740.00 17,020.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
26,082.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67 766.67
28,462.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
34,814.83
3,481.48
38,296.32
1 Cube 44,808.32
740.00 22,940.00
7,000.00 4,200.00
4,800.00 4,800.00
0.50 62.50
32,002.50
950.00 313.50
650.00 1,300.00
1,613.50
2,300.00 766.67
34,382.67
950.00 712.50
950.00 712.50
650.00 2,925.00
4,350.00
1,850.00 1,387.50
130.50
217.50
348.00
0.50 50.00
650.00 216.67
266.67
40,734.83
4,073.48
44,808.32
1 Sqr 5,338.13
14,000.00
21,062.67 3,580.65
358.07
3,938.72
950.00 237.50
650.00 650.00
887.50
26.63
4,852.84
485.28
5,338.13
1 Sqr 5,338.13
21,062.67 3,580.65
358.07
3,938.72
950.00 237.50
650.00 650.00
887.50
26.63
4,852.84
485.28
5,338.13
1 Sqr 7,376.99
21,062.67 5,265.67
526.57
5,792.23 5,792.23
950.00 237.50
650.00 650.00
887.50 887.50
26.63
6,706.36
670.64
7,376.99
1 Sqr 10,344.74
31,347.70
21,062.67 7,020.89
702.09
7,722.98
950.00 316.67
650.00 866.67
1,183.33
1,850.00 462.50
35.50
9,404.31
940.43
10,344.74
1 L.ft 284.77
31,114.83 575.62
13,234.77 1,813.16
2,388.79
950.00 118.75
650.00 81.25 200.00
2,588.79
258.88
25.89
284.77
1 L.ft 441.51
31,114.83 1,166.81
13,234.77 2,646.95
3,813.76
950.00 118.75
650.00 81.25 200.00
4,013.76
401.38
40.14
441.51
1 L.ft 564.25
31,114.83 1,751.77
13,234.77 2,977.82
4,729.59
950.00 237.50
650.00 162.50 400.00
5,129.59
512.96
51.30
564.25
1 L.ft 704.25
31,114.83 2,333.61
13,234.77 3,668.68
6,002.29
950.00 237.50
650.00 162.50 400.00
6,402.29
640.23
64.02
704.25
1 L.ft 628.74
31,114.83 1,742.43
13,234.77 3,573.39
5,315.82
950.00 237.50
650.00 162.50 400.00
5,715.82
571.58
57.16
628.74
1 L.ft 768.25
31,114.83 2,613.65
13,234.77 3,970.43
6,584.08
950.00 237.50
650.00 162.50 400.00
6,984.08
698.41
69.84
768.25
1 L.ft 754.90
31,114.83 3,484.86
13,234.77 2,977.82
6,462.69
950.00 237.50
650.00 162.50
400.00
6,862.69
686.27
68.63
754.90
1 L.ft 231.94
31,114.83 426.27
13,234.77 1,482.29
1,908.57
950.00 118.75
650.00 81.25 200.00
2,108.57
210.86
21.09
231.94
1 Cube 36,402.32
24,762.67 11,143.20
557.16
11,700.36
950.00 475.00
950.00 475.00
650.00 975.00
1,925.00
1,850.00 925.00
57.75
96.25
154.00
0.50 25.00
650.00 162.50
187.50
14,891.86
33,093.02
3,309.30
36,402.32
1 Cube 37,117.32
33,093.02
650.00 650.00 650.00
33,743.02
3,374.30
37,117.32
1 Cube 37,474.82
33,093.02
650.00 975.00 975.00
34,068.02
3,406.80
37,474.82
1 Cube 37,832.32
33,093.02
650.00 1,300.00 1,300.00
34,393.02
3,439.30
37,832.32
1 Cube 35,622.18
24,762.67 12,381.33
619.07 13,000.40
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00 925.00
57.75
96.25 154.00
0.50 25.00
650.00 162.50 187.50
16,191.90
32,383.80
3,238.38
35,622.18
1 Cube 36,337.18
32,383.80
650.00 650.00 650.00
33,033.80
3,303.38
36,337.18
1 Cube 36,694.68
32,383.80
650.00 975.00 975.00
33,358.80
3,335.88
36,694.68
1 Cube 37,052.18
32,383.80
650.00 1,300.00 1,300.00
33,683.80
3,368.38
37,052.18
1 Cube 36,595.84
24,762.67 11,143.20
557.16 11,700.36
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
57.75
96.25
0.50 50.00
650.00 216.67 266.67
14,971.03
33,268.95
3,326.89
36,595.84
1 Cube 37,310.84
33,268.95
650.00 650.00 650.00
33,918.95
3,391.89
37,310.84
1 Cube 37,668.34
33,268.95
650.00 975.00 975.00
34,243.95
3,424.39
37,668.34
1 Cube 38,025.84
33,268.95
650.00 1,300.00 1,300.00
34,568.95
3,456.89
38,025.84
1 Cube 35,796.34
24,762.67 12,381.33
619.07 13,000.40
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.66 266.66
16,271.06
32,542.13
1,627.11
17,898.17
35,796.34
1 Cube 36,511.34
32,542.13
650.00 650.00 650.00
33,192.13
3,319.21
36,511.34
1 Cube 36,868.84
32,542.13
650.00 975.00 975.00
33,517.13
3,351.71
36,868.84
1 Cube 37,226.34
32,542.13
650.00 1,300.00 1,300.00
33,842.13
3,384.21
37,226.34
1 Cube 35,796.35
24,762.67 12,381.33
0.05 619.07
13,000.40
950.00 475.00
950.00 475.00
650.00 975.00
1,925.00
1,850.00 925.00
57.75
96.25
154.00
0.50 50.00
650.00 216.67
266.67
16,271.07
32,542.13
1,627.11
17,898.17
35,796.35
1 Cube 36,511.35
32,542.13
650.00 650.00 650.00
33,192.13
3,319.21
36,511.35
1 Cube 36,868.85
32,542.13
650.00 975.00 975.00
33,517.13
3,351.71
36,868.85
1 Cube 37,226.35
32,542.13
650.00 1,300.00 1,300.00
33,842.13
3,384.21
37,226.35
1 Sqr 12,649.92
24,762.67 8,171.68
408.58
8,580.26
950.00 475.00
950.00 475.00
650.00 650.00
1,600.00
1,850.00 925.00 925.00
80.00
48.00
128.00
0.50 50.00
650.00 216.66
266.66
11,499.93
1,149.99
12,649.92
1 Sqr 13,126.58
11,499.93
650.00 433.33 433.33
11,933.26
1,193.33
13,126.58
1 Sqr 13,722.42
11,499.93
650.00 975.00 975.00
12,474.93
1,247.49
13,722.42
1 Sqr 15,045.80
24,762.67 10,400.32
520.02 10,920.34
950.00
950.00 475.00
650.00 975.00
1,450.00
1,850.00 925.00
0.03 43.50
0.05 72.50 116.00
0.50 50.00
650.00 216.66 266.66
13,678.00
1,367.80
15,045.80
1 Sqr 15,760.80
13,678.00
650.00 650.00 650.00
14,328.00
1,432.80
15,760.80
1 Sqr 16,118.30
13,678.00
650.00 975.00 975.00
14,653.00
1,465.30
16,118.30
1 Sqr 18,999.64
24,762.67 12,381.33
0.05 619.07 13,000.40
950.00 633.33
950.00 633.33
650.00 1,300.00 2,566.67
1,850.00 1,233.33
0.03 77.00
0.05 128.33 205.33
0.50 50.00
650.00 216.67 266.67
17,272.40
1,727.24
18,999.64
1 Sqr 19,714.64
17,272.40
650.00 650.00 650.00
17,922.40
1,792.24
19,714.64
1 Sqr 20,072.14
17,272.40
650.00 975.00 975.00
18,247.40
1,824.74
20,072.14
1 L.ft 292.30
34,814.83 644.07
13,234.77 1,813.16
2,457.24
950.00 118.75
650.00 81.25 200.00
2,657.24
265.72
26.57
292.30
1 L.ft 434.78
34,814.83 1,305.56
13,234.77 2,646.95
3,952.51
950.00 118.75
650.00 81.25
200.00
3,952.51
395.25
39.53
434.78
1 L.ft 587.17
34,814.83 1,960.08
13,234.77 2,977.82 4,937.90
950.00 237.50
650.00 162.50 400.00
5,337.90
533.79
53.38
587.17
1 L.ft 734.78
34,814.83 2,611.11
13,234.77 3,668.68 6,279.79
950.00 237.50
650.00 162.50 400.00
6,679.79
667.98
66.80
734.78
1 L.ft 651.53
34,814.83 1,949.63
13,234.77 3,573.39 5,523.02
950.00 237.50
650.00 162.50 400.00
5,923.02
592.30
59.23
651.53
1 L.ft 758.44
34,814.83 2,924.45
13,234.77 3,970.43 6,894.88
950.00 237.50
650.00 162.50
400.00
6,894.88
689.49
68.95
758.44
1 L.ft 800.48
34,814.83 3,899.26
13,234.77 2,977.82 6,877.09
950.00 237.50
650.00 162.50 400.00
7,277.09
727.71
72.77
800.48
1 L.ft 237.52
34,814.83 476.96
13,234.77 1,482.29 1,959.26
950.00 118.75
650.00 81.25 200.00
2,159.26
215.93
21.59
237.52
1 Cube 38,642.03
28,462.67 12,808.20
640.41
13,448.61
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
57.75
96.25
154.00
0.50 25.00
650.00 162.50
187.50
16,640.11
36,978.02
1,664.01
38,642.03
1 Cube 41,390.82
36,978.02
650.00 650.00 650.00
37,628.02
3,762.80
41,390.82
1 Cube 41,748.32
36,978.02
650.00 975.00 975.00
37,953.02
3,795.30
41,748.32
1 Cube 42,105.82
36,978.02
650.00 1,300.00 1,300.00
38,278.02
3,827.80
42,105.82
1 Cube 39,895.68
28,462.67 14,231.33
5% 711.57 14,942.90
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
57.75
96.25
0.50 25.00
650.00 162.50 187.50
18,134.40
36,268.80
1,813.44
19,947.84
39,895.68
1 Cube 40,610.68
36,268.80
650.00 650.00 650.00
36,918.80
3,691.88
40,610.68
1 Cube 40,968.18
36,268.80
650.00 975.00 975.00
37,243.80
3,724.38
40,968.18
1 Cube 41,325.68
36,268.80
650.00 1,300.00 1,300.00
37,568.80
3,756.88
41,325.68
1 Cube 40,869.34
28,462.67 12,808.20
5% 640.41 13,448.61
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.05 96.25
0.03 57.75
154.00
0.50 50.00
650.00 216.67 266.67
16,719.28
37,153.95
3,715.39
40,869.34
1 Cube 41,584.34
37,153.95
650.00 650.00 650.00
37,803.95
3,780.39
41,584.34
1 Cube 41,941.84
37,153.95
650.00 975.00 975.00
38,128.95
3,812.89
41,941.84
1 Cube 42,299.34
37,153.95
650.00 1,300.00 1,300.00
38,453.95
3,845.39
42,299.34
1 Cube 35,796.35
24,762.67 12,381.33
0.05 619.07 13,000.40
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.67 266.67
16,271.07
32,542.13
3,254.21
35,796.35
1 Cube 36,511.35
32,542.13
650.00 650.00 650.00
33,192.13
3,319.21
36,511.35
1 Cube 36,868.85
32,542.13
650.00 975.00 975.00
33,517.13
3,351.71
36,868.85
1 Cube 37,226.35
32,542.13
650.00 1,300.00 1,300.00
33,842.13
3,384.21
37,226.35
1 Cube 40,069.85
28,462.67 14,231.33
0.05 711.57 14,942.90
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.67 266.67
18,213.57
36,427.13
3,642.71
40,069.85
1 Cube 40,784.85
36,427.13
650.00 650.00 650.00
37,077.13
3,707.71
40,784.85
1 Cube 41,142.35
36,427.13
650.00 975.00 975.00
37,402.13
3,740.21
41,142.35
1 Cube 41,499.85
36,427.13
650.00 1,300.00 1,300.00
37,727.13
3,772.71
41,499.85
1 Sqr 13,344.81
1 Cube 40,438.81
28,462.67 9,392.68
0.05 469.63 9,862.31
950.00 316.67
950.00 316.67
650.00 650.00 1,283.33
1,850.00 616.67
0.03 38.50
0.05 64.17 102.67
0.50 50.00
650.00 216.66 266.66
12,131.64
1,213.16
13,344.81
36,762.56
3,676.26
40,438.81
1 Sqr 26,377.35
1 Cube 41,868.81
12,131.64
650.00 429.00 429.00
12,560.64
1,256.06
26,377.35
38,062.56
3,806.26
41,868.81
1 Sqr 69,443.40
1 Cube 42,603.31
12,131.64
650.00 649.35 649.35
12,780.99
1,278.10
69,443.40
38,730.28
3,873.03
42,603.31
1 Sqr 17,404.97
28,462.67 11,954.32
597.72 12,552.04
950.00 475.00
950.00 475.00
650.00 975.00 1,925.00
1,850.00 925.00
0.03 57.75
0.05 96.25 154.00
0.50 50.00
650.00 216.67 266.67
15,822.70
1,582.27
17,404.97
1 Sqr 17,881.59
15,822.70
650.00 433.29 433.29
16,255.99
1,625.60
17,881.59
1 Sqr 18,119.26
15,822.70
650.00 649.35 649.35
16,472.05
1,647.21
18,119.26
1 Sqr 21,136.37
28,462.67 14,231.33
0.05 711.57 14,942.90
950.00 633.33
950.00 633.33
650.00 1,300.00 2,566.65
1,850.00 1,233.33
0.03 77.00
0.05 128.33 205.33
0.50 50.00
650.00 216.67 266.67
19,214.89
1,921.49
21,136.37
1 Sqr 21,612.99
19,214.89
650.00 433.29 433.29
19,648.18
1,964.82
21,612.99
1 Sqr 21,851.37
19,214.89
650.00 650.00 650.00
19,864.89
1,986.49
21,851.37
1 Sqr 6,826.88
125.00 12,500.00
33.00 3,300.00
55.00 1,100.00
160.00 160.00
17,060.00
853.00
17,913.00
4,478.25
20.00 80.00
950.00 950.00
650.00 650.00 1,600.00
48.00
6,206.25
620.63
6,826.88
1 Sqr 10,868.64
125.00 2,250.00
33.00 297.00
160.00 80.00
2,627.00
131.35
950.00 237.50
650.00 162.50
400.00
12.00
3,170.35
A 792.59
165.00 148.50
40.00 192.00
50.00 15.00
20.00 10.00 365.50
950.00 59.38
650.00 40.63 100.00
3% 3.00
5% 5.00
B 473.50
950.00 118.75
650.00 81.25 200.00
3% 6.00
5% 10.00
C 216.00
.
A+B+C 792.59
473.50
216.00
1,482.09
9,880.58
988.06
10,868.64
1 Sqr 11,194.70
9,880.58
296.42
10,177.00
1,017.70
11,194.70
1 Sqr 11,303.39
9,880.58
395.22
10,275.81
1,027.58
11,303.39
1 Sqr 11,412.07
9,880.58
494.03
10,374.61
1,037.46
11,412.07
1 Sqr 29,116.50
125.00 7,500.00
33.00 825.00
160.00 160.00 8,485.00
424.25
950.00 950.00
650.00 650.00 1,600.00
48.00
80.00
A 10,637.25
165.00 1,210.00
160.00 352.00
20.00 10.00 1,572.00
950.00 475.00
650.00 1,300.00 1,775.00
53.25
88.75
B 3,489.00
950.00 237.50
650.00 162.50 400.00
12.00
20.00
C 432.00
A+B+C 10,637.25
3,489.00
432.00
14,558.25
26,469.55
2,646.95
29,116.50
1 Sqr 29,990.00
26,469.55
794.09
27,263.63
2,726.36
29,990.00
1 Sqr 30,281.16
26,469.55
1,058.78
27,528.33
2,752.83
30,281.16
1 Sqr 30,572.33
26,469.55
1,323.48
27,793.02
2,779.30
30,572.33
1 Sqr 14,166.01
125.00 12,500.00
33.00 1,815.00
160.00 320.00
14,635.00
731.75
950.00 712.50
650.00 487.50
1,200.00
36.00
16,602.75
A 4,150.69
165.00 4,125.00
33.00 165.00
175.00 175.00
20.00 10.00 4,475.00
950.00 1,425.00
650.00 1,950.00 3,375.00
0.03 101.25
0.05 168.75
B 8,120.00
950.00 237.50
650.00 325.00 562.50
0.03 16.88
0.05 28.13 45.00
C 607.50
4,150.69
8,120.00
607.50
A+B+C 12,878.19
1,287.82
14,166.01
1 Sqr 14,732.65
12,878.19
515.13
13,393.32
1,339.33
14,732.65
1 Sqr 14,874.31
12,878.19
643.91
13,522.10
1,352.21
14,874.31
1 Cwt 7,607.68
106.40 5,320.00
100.00 25.00
5,345.00
0.10 534.50
80.18
5,959.68
950.00 950.00
650.00 650.00
1,600.00
48.00
7,607.68
152.15
15.22
167.37
1 Cwt 7,340.43
106.40 5,320.00
100.00 25.00
5,345.00
0.05 267.25
80.18
5,692.43
950.00 950.00
650.00 650.00
1,600.00
48.00
7,340.43
146.81
14.68
161.49
1 Cwt 8,075.43
106.40 5,320.00
100.00 75.00
5,395.00
0.10 539.50
80.93
6,015.43
950.00 1,187.50
650.00 812.50
2,000.00
60.00
8,075.43
161.51
16.15
177.66
1 Cwt 7,823.68
7,607.68
950.00 118.75
650.00 81.25
200.00
6.00
10.00
7,823.68
156.47
15.65
172.12
1 Cwt 7,556.43
7,340.43
950.00 118.75
650.00 81.25
200.00
6.00
10.00
7,556.43
151.13
15.11
166.24
1 Cwt 8,291.43
8,075.43
950.00 118.75
650.00 81.25
200.00
6.00
10.00
8,291.43
165.83
16.58
182.41
1 Cwt 8,124.60
106.40 5,320.00
100.00 100.00
5,420.00
0.05 271.00
81.30
5,772.30
950.00 1,187.50
650.00 812.50
2,000.00
60.00
8,124.60
162.49
16.25
178.74
1 Cwt 8,536.60
8,124.60
950.00 237.50
650.00 162.50
400.00
12.00
20.00
8,536.60
170.73
17.07
187.81
1 Cube 22,930.60
7.00 11,550.00
700.00 2,800.00
7,000.00 1,750.00
0.50 75.00
16,175.00
950.00 2,375.00
650.00 1,950.00
4,325.00
129.75
216.25
20,846.00
2,084.60
22,930.60
1 Cube 23,881.00
7.00 11,550.00
700.00 2,800.00
7,000.00 1,750.00
0.50 75.00
16,175.00
950.00 2,850.00
650.00 2,275.00
5,125.00
153.75
256.25
21,710.00
2,171.00
23,881.00
1 Cube 24,549.25
7.00 11,550.00
700.00 2,800.00
7,000.00 1,750.00
0.50 75.00
16,175.00
950.00 3,087.50
650.00 2,600.00
5,687.50
170.63
284.38
22,317.50
2,231.75
24,549.25
1 Sqr 10,003.40
7.00 4,620.00
700.00 1,050.00
7,000.00 700.00
0.50 37.50
6,407.50
950.00 1,187.50
650.00 1,300.00
2,487.50
74.63
124.38
9,094.00
909.40
10,003.40
1 Sqr 10,478.60
7.00 4,620.00
700.00 1,050.00
7,000.00 700.00
0.50 37.50
6,407.50
950.00 1,425.00
650.00 1,462.50
2,887.50
86.63
144.38
9,526.00
952.60
10,478.60
1 Sqr 10,953.80
7.00 4,620.00
700.00 1,050.00
7,000.00 700.00
0.50 37.50
6,407.50
950.00 1,662.50
650.00 1,625.00
3,287.50
98.63
164.38
9,958.00
995.80
10,953.80
1 L.ft 165.36
50 L.ft
7.00 3,325.00
700.00 1,050.00
7,000.00 700.00
0.50 25.00
5,100.00
950.00 1,425.00
650.00 812.50
2,237.50
67.13
111.88
7,516.50
150.33
15.03
165.36
1 L.ft 169.22
7.00 3,325.00
700.00 1,050.00
7,000.00 700.00
0.50 25.00
5,100.00
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
7,692.00
153.84
15.38
169.22
1 L.ft 178.73
7.00 3,325.00
700.00 1,050.00
7,000.00 700.00
0.50 25.00
5,100.00
950.00 1,662.50
650.00 1,137.50 2,800.00
84.00
140.00
8,124.00
162.48
16.25
178.73
1 L.ft 131.85
7.00 2,905.00
700.00 770.00
7,000.00 560.00
0.50 30.00
4,265.00
950.00 950.00
650.00 650.00 1,600.00
48.00
80.00
5,993.00
119.86
11.99
131.85
1 L.ft 137.49
7.00 2,905.00
700.00 770.00
7,000.00 560.00
0.50 30.00
4,265.00
950.00 1,187.50
650.00 650.00
1,837.50
55.13
91.88
6,249.50
124.99
12.50
137.49
1 L.ft 142.79
7.00 2,905.00
700.00 770.00
7,000.00 560.00
0.50 25.00
4,260.00
950.00 1,187.50
650.00 975.00 2,162.50
64.88
3.24
6,490.62
129.81
12.98
142.79
1 Sqr 17,461.40
7.00 8,680.00
700.00 2,100.00
7,000.00 1,400.00
0.50 62.50
12,242.50
950.00 1,900.00
650.00 1,462.50 3,362.50
100.88
168.13
15,874.00
1,587.40
17,461.40
1 Sqr 19,080.05
7.00 8,680.00
700.00 2,100.00
7,000.00 1,400.00
0.50 62.50 12,242.50
950.00 2,612.50
650.00 2,112.50 4,725.00
141.75
236.25
17,345.50
1,734.55
19,080.05
1 Sqr 19,273.10
7.00 8,680.00
700.00 2,100.00
7,000.00 1,400.00
0.50 62.50 12,242.50
950.00 2,612.50
650.00 2,275.00 4,887.50
146.63
244.38
17,521.00
1,752.10
19,273.10
1 Cube 19,028.63
4,200.00 5,670.00
700.00 3,500.00
7,000.00 2,800.00
0.50 50.00
12,020.00
950.00 2,850.00
650.00 2,275.00
5,125.00
153.75
17,298.75
1,729.88
19,028.63
1 Sqr 28,271.10
4,200.00 8,400.00
700.00 5,250.00
7,000.00 4,200.00
0.50 75.00
17,925.00
950.00 4,275.00
650.00 2,925.00 7,200.00
216.00
360.00
25,701.00
2,570.10
28,271.10
1 Sqr 36,898.40
4,200.00 11,340.00
700.00 7,000.00
7,000.00 5,600.00
0.50 100.00
24,040.00
950.00 5,225.00
650.00 3,575.00 8,800.00
264.00
440.00
33,544.00
3,354.40
36,898.40
1 Sqr 45,630.20
4,200.00 14,700.00
700.00 8,400.00
7,000.00 7,000.00
0.50 150.00 30,250.00
950.00 6,175.00
650.00 4,225.00 10,400.00
312.00
520.00
41,482.00
4,148.20
45,630.20
1 Sqr 20,065.61
115.83 12,972.96
700.00 595.00
7,000.00 560.00
0.50 50.00
14,177.96
950.00 2,137.50
650.00 1,625.00
3,762.50
112.88
188.13
18,241.46
1,824.15
20,065.61
1 Sqr 10,962.95
59.86 6,704.32
700.00 280.00
7,000.00 350.00
0.50 40.00
7,374.32
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
9,966.32
996.63
10,962.95
1 Sqr 14,529.72
82.82 9,275.84
700.00 455.00
7,000.00 490.00
0.50 45.00
10,265.84
950.00 1,425.00
650.00 1,300.00 2,725.00
81.75
136.25
13,208.84
1,320.88
14,529.72
1 Sqr 20,434.56
18,241.46
950.00 118.75
650.00 216.67 335.42
18,576.88
1,857.69
20,434.56
1 Sqr 11,331.89
9,966.32
950.00 118.75
650.00 216.65
335.40
10,301.72
1,030.17
11,331.89
1 Sqr 14,898.66
13,208.84
950.00 118.75
650.00 216.65 335.40
13,544.24
1,354.42
14,898.66
1 Sqr 20,771.44
18,241.46 18,241.46
950.00 316.67
650.00 325.00 641.67
18,883.13
1,888.31
20,771.44
1 Sqr 11,668.79
9,966.32 9,966.32
950.00 316.67
650.00 325.00
641.67
10,607.99
1,060.80
11,668.79
1 Sqr 15,588.47
13,208.84 13,208.84
950.00 475.00
650.00 487.50 962.50
14,171.34
1,417.13
15,588.47
1 Sqr 16,027.11
83.05 9,301.60
700.00 595.00
7,000.00 560.00
0.50 50.00
10,506.60
950.00 2,137.50
650.00 1,625.00
3,762.50
112.88
188.13
14,570.10
1,457.01
16,027.11
1 Sqr 8,830.36
42.55 4,765.60
700.00 280.00
7,000.00 350.00
0.50 40.00
5,435.60
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
8,027.60
802.76
8,830.36
1 Sqr 12,047.24
62.67 7,019.04
700.00 455.00
7,000.00 490.00
0.50 45.00
8,009.04
950.00 1,425.00
650.00 1,300.00
2,725.00
81.75
136.25
10,952.04
1,095.20
12,047.24
1 Sqr 16,396.07
14,570.10
950.00 118.75
650.00 216.67 335.42
14,905.52
1,490.55
16,396.07
1 Sqr 9,199.29
8,027.60
950.00 118.75
650.00 216.65
335.40
8,363.00
836.30
9,199.29
1 Sqr 12,416.18
10,952.04
950.00 118.75
650.00 216.65
335.40
11,287.44
1,128.74
12,416.18
1 Sqr 16,732.94
14,570.10 14,570.10
950.00 316.67
650.00 325.00
641.67
15,211.77
1,521.18
16,732.94
1 Sqr 9,536.19
8,027.60 8,027.60
950.00 316.67
650.00 325.00
641.67
8,669.27
866.93
9,536.19
1 Sqr 13,105.99
10,952.04 10,952.04
950.00 475.00
650.00 487.50
962.50
11,914.54
1,191.45
13,105.99
1 Sqr 39,089.71
3,240.00 17,982.00
899.10
55.00 6,050.00
160.00 240.00
45.00 5,625.00
388.00 582.00
31,378.10
950.00 1,900.00
650.00 1,950.00
3,850.00
115.50
192.50
35,536.10
3,553.61
39,089.71
1 L.ft 149.79
45.00 630.00
75.00 187.50
700.00 245.00
14.50 116.00
0.50 0.03
1,178.53
950.00 475.00
650.00 325.00
800.00
24.00
40.00
136.17
13.62
149.79
1 Sqr 22,448.07
3,240.00 11,340.00
160.00 160.00
45.83 5,270.83
5.00 100.00
242.50 242.50
17,113.33
950.00 1,425.00
650.00 1,625.00
3,050.00
91.50
152.50
20,407.33
2,040.73
22,448.07
1 L.ft 937.20
45.00 180.00
15.00 240.00
420.00
950.00 237.50
650.00 162.50
400.00
0.03 12.00 12.00
0.05 20.00 20.00
852.00
85.20
937.20
1 Sqr 7,125.07
45.83 5,270.83
5.00 100.00
242.50 242.50
5,613.33
950.00 475.00
650.00 325.00
800.00
24.00
40.00
6,477.33
647.73
7,125.07
1 Sqr 11,293.44
20.00 10,000.00 10,000.00
650.00 247.00 247.00
7.41
12.35
10,266.76
1,026.68
11,293.44
1 L.ft 411.57
217.00 21,700.00
1,085.00
8.35 835.00
2,077.00 4,154.00
622.00 2,488.00
400.00 40.00
42.50 127.50
388.00 776.00
31,205.50
950.00 950.00
950.00 2,850.00
650.00 1,950.00
5,750.00
172.50
287.50
37,415.50
374.16
37.42
411.57
1 Sqr 19,709.98
135.50 6,504.00
55.00 3,960.00
33.00 594.00
23.75 3,277.50
160.00 240.00
- -
- -
312.75 469.13
550.00 962.50
400.00 26.67
42.50 85.00
388.00 388.00
16,506.79
950.00 1,187.50
950.00 2,137.50
650.00 1,300.00
4,625.00
138.75
231.25
21,501.79
17,918.16
1,791.82
19,709.98
1 Sqr 32,035.85
135.50 6,504.00
55.00 3,960.00
33.00 594.00
56.00 7,728.00
160.00 160.00
- -
2,077.00 3,115.50
550.00 962.50
400.00 24.00
42.50 85.00
388.00 388.00
23,521.00
950.00 1,187.50
950.00 2,375.00
650.00 1,625.00
5,187.50
155.63
259.38
29,123.50
2,912.35
32,035.85
1 L.ft 63.29
12.00 600.00
160.00
2.28 171.00
650.00
. 1,581.00
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
2,877.00
57.54
5.75
63.29
1 L.ft 91.45
33.00 1,650.00
160.00
2.28 171.00
880.00
2,861.00
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
4,157.00
83.14
8.31
91.45
1 L.ft 118.11
49.23 2,461.54
160.00
2.28 171.00
1,280.00
4,072.54
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
5,368.54
107.37
10.74
118.11
1 L.ft 126.17
49.23 2,461.54
2.28 171.00
1,280.00
3,912.54
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
5,735.04
114.70
11.47
126.17
1 L.ft 162.25
72.92 3,646.15
160.00
2.28 228.00
2,045.00
6,079.15
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
7,375.15
147.50
14.75
162.25
1 L.ft 170.32
72.92 3,646.15
2.28 228.00
2,045.00 5,919.15
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
0.03 50.63 50.63
84.38
7,741.65
154.83
15.48
170.32
1 L.ft 221.56
105.08 5,253.85
160.00
2.28 171.00
3,190.00
8,774.85
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
10,070.85
201.42
20.14
221.56
1 L.ft 229.62
105.08 5,253.85
2.28 171.00
3,190.00
8,614.85
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
10,437.35
208.75
20.87
229.62
1 L.ft 341.65
177.31 8,865.38
2.28 228.00
160.00
4,980.00
14,233.38
950.00 712.50
650.00 487.50 1,200.00
60.00
36.00
15,529.38
310.59
31.06
341.65
1 L.ft 349.71
177.31 8,865.38
2.28 228.00
4,980.00
14,073.38
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
15,895.88
317.92
31.79
349.71
1 L.ft 565.13
363.08 18,153.85
160.00
2.28 228.00
5,850.00
24,391.85
950.00 712.50
650.00 487.50 1,200.00
36.00
60.00
25,687.85
513.76
51.38
565.13
1 L.ft 573.20
363.08 18,153.85
2.28 228.00
5,850.00
24,231.85
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
26,054.35
521.09
52.11
573.20
1 L.ft 719.14
427.80 21,390.00
160.00
2.28 342.00
9,500.00
31,392.00
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
32,688.00
653.76
65.38
719.14
1 L.ft 727.20
427.80 21,390.00
2.28 342.00
9,500.00
31,232.00
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
33,054.50
661.09
66.11
727.20
1 L.ft 1,169.18
639.60 31,980.00
2.28 342.00
19,000.00
51,322.00
650.00 487.50
950.00 712.50
650.00 487.50
1,687.50
50.63
84.38
53,144.50
1,062.89
106.29
1,169.18
1 Nos 62.39
26.00 260.00
2.28 91.20
351.20
118.75 118.75
81.25 81.25
200.00
6.00
10.00
567.20
56.72
5.67
62.39
1 Nos 55.11
36.00 360.00
2.28 114.00
474.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
501.00
50.10
5.01
55.11
1 Nos 71.61
51.00 510.00
2.28 114.00
624.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
651.00
65.10
6.51
71.61
1 Nos 143.88
111.00 1,110.00
2.28 171.00
1,281.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,308.00
130.80
13.08
143.88
1 Nos 223.85
178.00 1,780.00
2.28 228.00
2,008.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
2,035.00
203.50
20.35
223.85
1 Nos 354.88
288.00 2,880.00
2.28 319.20
3,199.20
118.75 14.84
81.25 10.16
25.00
0.03 0.75 0.75
0.05 1.25 1.25
3,226.20
322.62
32.26
354.88
1 Nos 29.50
10 Nos
15.00 150.00
2.28 91.20 241.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
268.20
26.82
2.68
29.50
1 Nos 45.21
27.00 270.00
2.28 114.00
384.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
411.00
41.10
4.11
45.21
1 Nos 59.51
40.00 400.00
2.28 114.00
514.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
541.00
54.10
5.41
59.51
1 Nos 94.38
66.00 660.00
2.28 171.00
831.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
858.00
85.80
8.58
94.38
1 Nos 150.15
111.00 1,110.00
2.28 228.00
1,338.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,365.00
136.50
13.65
150.15
1 Nos 243.78
187.00 1,870.00
2.28 319.20
2,189.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
2,216.20
221.62
22.16
243.78
1 Nos 39.00
20.00 200.00
2.28 114.00
314.00
118.75 22.27
81.25 15.23
37.50
1.13
1.88
354.50
35.45
3.55
39.00
1 Nos 59.10
36.00 360.00
2.28 136.80
496.80
118.75 22.27
81.25 15.23
37.50
1.13
1.88
537.30
53.73
5.37
59.10
1 Nos 85.25
55.00 550.00
2.28 171.00
721.00
118.75 29.69
81.25 20.31
50.00
1.50
2.50
775.00
77.50
7.75
85.25
1 Nos 127.51
90.00 900.00
2.28 205.20
1,105.20
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,159.20
115.92
11.59
127.51
1 Nos 207.64
156.00 1,560.00
2.28 273.60
1,833.60
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,887.60
188.76
18.88
207.64
1 Nos 317.90
238.00 2,380.00
2.28 456.00
2,836.00
118.75 29.69
81.25 20.31
50.00
0.03 1.50 1.50
0.05 2.50 2.50
2,890.00
289.00
28.90
317.90
1 Nos 35.00
20.00 200.00
2.28 91.20
291.20
118.75 14.84
81.25 10.16
25.00
0.03 0.75 0.75
0.05 1.25 1.25
318.20
31.82
3.18
35.00
1 Nos 46.31
28.00 280.00
2.28 114.00
394.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
421.00
42.10
4.21
46.31
1 Nos 55.11
36.00 360.00
2.28 114.00
474.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
501.00
50.10
5.01
55.11
1 Nos 95.48
67.00 670.00
2.28 171.00
841.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
868.00
86.80
8.68
95.48
1 Nos 129.25
92.00 920.00
2.28 228.00
1,148.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,175.00
117.50
11.75
129.25
1 Nos 195.38
143.00 1,430.00
2.28 319.20
1,749.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
1,776.20
177.62
17.76
195.38
1 Nos 35.00
20.00 200.00
2.28 91.20 291.20
118.75 14.84
81.25 10.16
25.00
0.75
1.25
318.20
31.82
3.18
35.00
1 Nos 46.31
28.00 280.00
2.28 114.00
394.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
421.00
42.10
4.21
46.31
1 Nos 50.71
32.00 320.00
2.28 114.00
434.00
118.75 14.84
81.25 10.16
25.00
0.75
1.25
461.00
46.10
4.61
50.71
1 Nos 90.75
60.00 600.00
2.28 171.00
771.00
118.75 29.69
81.25 20.31
50.00
1.50
2.50
825.00
82.50
8.25
90.75
1 Nos 122.32
83.00 830.00
2.28 228.00
1,058.00
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,112.00
111.20
11.12
122.32
1 Nos 192.85
138.00 1,380.00
2.28 319.20
1,699.20
118.75 29.69
81.25 20.31
50.00
1.50
2.50
1,753.20
175.32
17.53
192.85
1 Nos 30.60
16.00 160.00
2.28 91.20 251.20
118.75 14.84
81.25 10.16 25.00
0.75
1.25
278.20
27.82
2.78
30.60
1 Nos 40.81
23.00 230.00
2.28 114.00 344.00
118.75 14.84
81.25 10.16 25.00
0.75
1.25
371.00
37.10
3.71
40.81
1 Nos 52.91
34.00 340.00
2.28 114.00 454.00
118.75 14.84
81.25 10.16 25.00
0.75
1.25
481.00
48.10
4.81
52.91
1 Nos 77.88
51.00 510.00
2.28 171.00 681.00
118.75 14.84
81.25 10.16 25.00
0.75
1.25
708.00
70.80
7.08
77.88
1 Nos 116.82
78.00 780.00
2.28 228.00 1,008.00
118.75 29.69
81.25 20.31 50.00
1.50
2.50
1,062.00
106.20
10.62
116.82
1 Nos 178.55
125.00 1,250.00
2.28 319.20 1,569.20
118.75 29.69
81.25 20.31 50.00
1.50
2.50
1,623.20
162.32
162.32
1,785.52
178.55
1 Sqr 4,968.70
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 1,425.00
650.00 975.00 2,400.00
72.00
120.00
4,517.00
451.70
4,968.70
1 Sqr 4,167.06
700.00 595.00
14.50 435.00
7,500.00 450.00
0.50 10.00 1,490.00
950.00 1,263.50
650.00 864.50 2,128.00
63.84
106.40
3,788.24
378.82
4,167.06
1 Sqr 5,443.90
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 1,662.50
650.00 1,137.50 2,800.00
84.00
140.00
4,949.00
494.90
5,443.90
1 Sqr 4,683.25
700.00 595.00
14.50 435.00
7,500.00 450.00
0.50 10.00 1,490.00
950.00 1,425.00
650.00 1,137.50 2,562.50
76.88
128.13
4,257.50
425.75
4,683.25
1 Sqr 5,919.10
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 1,900.00
650.00 1,300.00 3,200.00
96.00
160.00
5,381.00
538.10
5,919.10
1 Sqr 5,158.45
700.00 595.00
14.50 435.00
7,500.00 450.00
0.50 10.00 1,490.00
950.00 1,662.50
650.00 1,300.00 2,962.50
88.88
148.13
4,689.50
468.95
5,158.45
1 Sqr 6,201.25
700.00 595.00
14.50 870.00
7,500.00 450.00
0.50 10.00 1,925.00
950.00 2,137.50
650.00 1,300.00 3,437.50
103.13
171.88
5,637.50
563.75
6,201.25
1 Sqr 6,229.30
700.00 595.00
14.50 870.00
7,500.00 300.00
0.50 10.00 1,775.00
950.00 2,137.50
650.00 1,462.50 3,600.00
108.00
180.00
5,663.00
566.30
6,229.30
1 Sqr 6,135.80
700.00 1,400.00
7,500.00 825.00
50.00 400.00
0.50 10.00 2,635.00
950.00 1,425.00
650.00 1,300.00 2,725.00
81.75
136.25
5,578.00
557.80
6,135.80
1 Sqr 6,318.40
700.00 595.00
14.50 870.00
7,500.00 300.00
0.50 10.00 1,775.00
950.00 2,375.00
650.00 1,300.00 3,675.00
110.25
183.75
5,744.00
574.40
6,318.40
1 Sqr 6,793.60
700.00 595.00
14.50 870.00
7,500.00 300.00
0.50 10.00 1,775.00
950.00 2,612.50
650.00 1,462.50 4,075.00
122.25
203.75
6,176.00
617.60
6,793.60
1 Sqr 8,997.31
7.00 2,520.00
700.00 1,400.00
9.00 270.00
7,500.00 1,350.00
0.50 12.50 5,540.00
950.00 1,425.00
650.00 1,137.50 2,562.50
76.88
8,179.38
817.94
8,997.31
1 Sqr 3,119.05
700.00 875.00
7,500.00 300.00
0.50 12.50 1,187.50
950.00 950.00
650.00 650.00 1,600.00
48.00
2,835.50
283.55
3,119.05
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 22,410.03
80.00 12,000.00
600.00
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 15,428.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
20,372.75
2,037.28
22,410.03
1 Sqr 8,550.03
- -
-
700.00 2,100.00
7,500.00 600.00
155.00 116.25
0.50 12.50 2,828.75
950.00 2,850.00
650.00 1,950.00 4,800.00
144.00
7,772.75
777.28
8,550.03
1 Sqr 2,793.63
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50 1,243.67
950.00 712.50
650.00 487.50 1,200.00
36.00
60.00
2,539.67
253.97
2,793.63
1 Sqr 3,075.78
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50
1,243.67
950.00 950.00
650.00 487.50
1,437.50
0.03 43.13 43.13
0.05 71.88 71.88
2,796.17
279.62
3,075.78
1 Sqr 3,262.05
750.00 1,237.50
337.00 337.00
42.50 42.50
400.00 40.00
0.50 12.50
1,669.50
950.00 712.50
650.00 487.50
1,200.00
36.00
60.00
2,965.50
296.55
3,262.05
1 Sqr 3,729.92
750.00 1,237.50
337.00 337.00
42.50 42.50
400.00 33.33
0.50 12.50
1,662.83
950.00 950.00
650.00 650.00
1,600.00
48.00
80.00
3,390.83
339.08
3,729.92
1 Sqr 3,268.83
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50
1,243.67
950.00 950.00
650.00 650.00
1,600.00
48.00
80.00
2,971.67
297.17
3,268.83
1 Sqr 3,458.91
550.00 825.00
337.00 337.00
42.50 42.50
400.00 26.67
0.50 12.50
1,243.67
950.00 1,045.00
650.00 715.00
1,760.00
52.80
88.00
3,144.47
314.45
3,458.91
1 Point 1,902.25
1850.00 462.50
6.23 31.15
16.00 16.00
35.00 35.00
65.00 65.00
108.00 108.00
32.00 32.00
20.00 20.00
10.00 10.00
5.00 10.00
25.00 150.00
sum
sum 939.65
650.00 81.25
950.00 316.67
650.00 214.50
950.00 118.75 731.17
21.94
36.56
1,729.31
172.93
1,902.25
1 Point 1,702.85
1850.00 462.50
6.23 62.31
16.00 32.00
65.00 65.00
108.00 108.00
32.00 32.00
sum
sum 761.81
650.00 81.25
950.00 118.75
650.00 214.50
950.00 313.50
728.00
21.84
36.40
1,548.05
154.80
1,702.85
1 Point 4,311.71
307.00 307.00
1850.00 462.50
18,100.00 1,810.00
49.00 490.00
16.00 32.00
32.00 32.00
sum
sum 3,133.50
650.00 81.25
950.00 118.75
650.00 214.50
950.00 313.50
728.00
21.84
36.40
3,919.74
391.97
4,311.71
1 m3 12,447.45
9,545.00 286,350.00
14,375.00
9,545.00 4,772.50
305,497.50
950.00 2,850.00
950.00 11,400.00
650.00 11,700.00
25,950.00
778.50
1,850.00 5,550.00 5,550.00
650.00 1,300.00
0.50 400.00
1,700.00
339,476.00
11,315.87
33,947.60
373,423.60
12,447.45
1 m3 12,841.97
9,545.00 286,350.00
14,375.00
9,545.00 4,772.50
305,497.50
950.00 3,800.00
950.00 15,200.00
650.00 15,600.00
34,600.00
1,038.00
1,850.00 7,400.00 7,400.00
650.00 1,300.00
0.50 400.00
1,700.00
350,235.50
11,674.52
35,023.55
385,259.05
12,841.97
1 m3 12,061.63
9,200.00 276,000.00
14,375.00
9,200.00 4,600.00
294,975.00
950.00 2,850.00
950.00 11,400.00
650.00 11,700.00
25,950.00
778.50
1,850.00 5,550.00
650.00 1,300.00
0.50 400.00
1,700.00
328,953.50
10,965.12
32,895.35
361,848.85
12,061.63
1 m3 13,248.77
10,005.00 300,150.00
14,375.00
10,005.00 5,002.50
319,527.50
950.00 950.00
950.00 15,200.00
650.00 15,600.00
31,750.00
952.50
1,850.00 7,400.00 7,400.00
650.00 1,300.00
0.50 400.00
1,700.00
361,330.00
12,044.33
36,133.00
397,463.00
13,248.77
1 m3 12,829.66
9,545.00 190,900.00
14,375.00
9,545.00 4,772.50 210,047.50
950.00 1,900.00
950.00 7,600.00
650.00 7,800.00 17,300.00
519.00
1,850.00 3,700.00 3,700.00
650.00 1,300.00
0.50 400.00
1,700.00
233,266.50
11,663.33
23,326.65
256,593.15
12,829.66
1 m3 13,273.49
9,545.00 190,900.00
14,375.00
9,545.00 4,772.50
210,047.50
950.00 2,612.50
950.00 10,450.00
650.00 10,725.00
23,787.50
713.63
1,850.00 5,087.50 5,087.50
650.00 1,300.00
0.50 400.00
1,700.00
241,336.13
12,066.81
24,133.61
265,469.74
13,273.49
1 m3 13,348.31
10,005.00 200,100.00
14,375.00
10,005.00 5,002.50
219,477.50
950.00 1,900.00
950.00 7,600.00
650.00 7,800.00
17,300.00
519.00
1,850.00 3,700.00 3,700.00
650.00 1,300.00
0.50 400.00
1,700.00
242,696.50
12,134.83
24,269.65
266,966.15
13,348.31
1 m3 13,792.14
10,005.00 200,100.00
14,375.00
10,005.00 5,002.50
219,477.50
950.00 2,612.50
950.00 10,450.00
650.00 10,725.00
23,787.50
0.03 713.63 713.63
1,850.00 5,087.50 5,087.50
650.00 1,300.00
0.50 400.00
1,700.00
250,766.13
12,538.31
25,076.61
275,842.74
13,792.14
1 no 1 Nos 22,523.24
214.00 4,280.00
5,000.00 5,000.00
360.00 540.00
5.58 133.92
490.00 490.00
550.00 550.00
- -
2,910.00 2,910.00
553.00 691.25
555.00 277.50
400.00 40.00
280.00 1,680.00
42.50 85.00
16,677.67
950.00 316.67
950.00 1,900.00
650.00 1,300.00
3,516.67
0.03 105.50 105.50
0.05 175.83 175.83
20,475.67
2,047.57
22,523.24
1 Nos 30,823.84
214.00 4,280.00
450.00 11,025.00
360.00
5.58 133.92
490.00 490.00
550.00 550.00
- -
2,910.00 2,910.00
553.00 691.25
555.00 277.50
400.00 40.00
280.00 1,680.00
42.50 85.00
22,162.67
950.00 475.00
950.00 3,325.00
650.00 1,625.00
5,425.00
162.75
271.25
28,021.67
2,802.17
30,823.84
1 Nos 20,227.42
214.00 6,420.00
100.00 2,300.00
115.00
75.00 1,200.00
275.00
5.58 178.56
- -
- -
- -
553.00 414.75
555.00 138.75
400.00 40.00
280.00 1,680.00
42.50 42.50
12,529.56
950.00 475.00
950.00 3,325.00
650.00 1,625.00
5,425.00
0.03 162.75 162.75
0.05 271.25 271.25
18,388.56
1,838.86
20,227.42
1 L.ft 64.19
-
-
-
-
-
650.00 216.67
950.00 475.00
950.00 118.75
810.42
24.31
40.52
875.25
58.35
87.53
962.78
64.19
CONCRETE MISSALANIOUS ITEM
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
15%
1 3" thick blinding layer with reinforcement Grade 10
Consider 1 Sqr
Materials
Concrete 25.00 Cu.ft 274.15 6,853.71
Wastege 10% 10% 685.37
Reinforcement (6 mm) 22.00 Kg 146.81 3,229.79
10,768.87
Labour
Skilled labourer 0.25 Day 950.00 237.50
Un skilled labourer 1.00 Day 650.00 650.00
887.50
Add: 3% tools 3% 26.63
11,682.99 1,752.45 13,435.44
Preliminaries 10% 10% 1,168.30
Cost for 1 Sqr 12,851.29 1,927.69 14,778.98
Main Index
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
2 9"x 9" concrete beams in ground floor
level
Grade 25
Consider .45 Cube
Materials
Mixed concrete
0.45 Cube 28,462.67 12,808.20
(As per item B.05)
Add wastage 5%
5% 640.41
13,448.61
LAYING COST
Labour
Mason
0.50 Day 950.00 475.00
Skilled labour for vibrator
0.50 Day 650.00 325.00
3 U/sk labour
1.50 Day 650.00 975.00
1,775.00
Add: 3% tools
3% 53.25
Plant & equipment
Vibrator
0.50 Day 1,850.00 925.00
Curing
Water
100.00 Gal 0.50 50.00
U/sk labour
0.33 Day 650.00 216.67
266.67
16,468.53
36,596.73 5,489.51 42,086.23
Preliminaries
10% 1,646.85
18,115.38
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
Cost per 1 Cube 40,256.40 6,038.46 46,294.86
3 9"x 9" Concrete Column in ground floor
level
Grade 25
Consider .45 Cube ( 80 L.ft)
Materials
Mixed Concrete
0.45 Cube 28,462.67 12,808.20
(As per item B.04)
Add wastage 5%
5% 640.41
13,448.61
LAYING COST
Labour
Mason
0.50 Day 950.00 475.00
Skilled labour for vibrator
0.50 Day 950.00 475.00
3 U/sk labour
1.50 Day 650.00 975.00
1,925.00
Add: 3% tools
3% 57.75
Add: 5% scaffolding
5% 96.25
Plant & equipment
Vibrator
0.50 Day 1,850.00 925.00
Curing
Water
50.00 Gal 0.50 25.00
U/sk labour
0.25 Day 650.00 162.50
187.50
16,640.11
36,978.02 5,546.70 42,524.72
Preliminaries
10% 1,664.01
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
18,304.12
Cost per 1 Cube 40,675.82 6,101.37 46,777.20
4 9''x 12'' plinth beam with & including
formwork and reinforcement
Grade 20
Consider 10 L.ft
Materials
Concrete 7.50 Cu.ft 311.15 2,333.61
Sawn form work 20.00 Sq.ft 264.70 5,293.91
Reinforcement 10.00 Kg 146.81 1,468.09
9,095.61
Add Extra cost of labour
Skilled labourer 0.25 Day 950.00 237.50
Un skilled labourer 0.25 Day 650.00 162.50
400.00
9,495.61
949.56 142.43 1,091.99
Preliminaries 10% 10% 949.56
Cost for 10.0 l.ft 10,445.17
Cost for1 L.ft 1,044.52 156.68 1,201.19
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
5 9''x9'' Plinth beam with & including
formwork and reinforcement
Grade 20
Consider 10 L.ft
Materials
Concrete 5.63 Cu.ft 311.15 1,750.21
Sawn form work 15.00 Sq.ft 264.70 3,970.43
Reinforcement 10.00 Kg 146.81 1,468.09
7,188.73
Add Extra cost of labour
Skilled labourer 0.25 Day 950.00 237.50
Un skilled labourer 0.25 Day 650.00 162.50
400.00
Cost for 10.0 l.ft 7,588.73
758.87 113.83 872.70
Preliminaries 10% 10% 758.87
Cost for 10.0 l.ft 8,347.60
Cost for1 L.ft 834.76 125.21 959.97
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
6 6'' x 9'' lintol with & including formwork
& reinforcement
Grade 25
Consider 10 L.ft
Materials
Concrete 4.50 Cu.ft 311.15 1,400.17
Sawn form work 17.50 Sq.ft 264.70 4,632.17
Reinforcement 5.00 Kg 146.81 734.04
6,766.38
Add Extra cost of labour
Skilled labourer 0.13 Day 950.00 118.75
Un skilled labourer 0.13 Day 650.00 81.25
200.00
6,966.38
696.64 104.50 801.13
Preliminaries 10% 10% 696.64
Cost for 10.0 L.ft 7,663.02
Cost for 1 L.ft 766.30 114.95 881.25
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
7 6'' x 4
1
/
2
'' lintol with & including
formwork & reinforcement
Grade 25
Consider 10 L.ft
Materials
Concrete 1.88 Cu.ft 311.15 584.96
Sawn form work 12.50 Sq.ft 264.70 3,308.69
Reinforcement 5.00 Kg 146.81 734.04
4,627.69
Add Extra cost of labour
Skilled labourer 0.13 Day 950.00 118.75
Un skilled labourer 0.13 Day 650.00 81.25
200.00
4,827.69
482.77 72.42 555.18
Preliminaries 10% 10% 482.77
Cost for 10.0 l.ft 5,310.46
Cost for 1 l.ft 531.05 79.66 610.70
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
8 LAYING CHIP CONCRETE Kiri
Consider 1 Sqr
MIXING COST
Materials
Cement 2.37 Bags 740.00 1,753.80
Chip Metal 0.17 Cube 3,750.00 637.50
Water 21.00 Gal 0.50 10.50
Labour
Mixer operator 0.06 Day 950.00 57.00
U/sk labour 0.34 Day 650.00 221.00
Plant & equipment
Concrete mixture (14/10) 0.06 Day 2,300.00 138.00
2,817.80
Add Wastage 10% 0.10 281.78
Labour
Sk labour 0.25 Day 950.00 237.50
Un sk labour 1.00 Day 650.00 650.00
887.50
Add 3% for tools 0.03 26.63
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
4,013.71 602.06 4,615.76
Preliminaries 10% 401.37
Cost for 1 Sqr 4,415.08 662.26 5,077.34
8.0 Grage 15 Chip Concrete Queens
MIXING Cost Assume 3" thick
Materials
Cement 14.00 bags 740.00 10,360.00
Sand 0.60 Cube 7,000.00 4,200.00
Metal (Chip) 1.00 Cube 3,750.00 3,750.00
Water 125.0 gal 0.50 62.50
18,372.50
Labour
Mixer operator 0.33 day 950.00 313.50
Un / skilled Labour 2.00 day 650.00 1,300.00
1,613.50
Plant & Equipment
Concrete mixture (14/10) 0.33 day 2,300.00 759.00
Cost for one Cube 20,745.00
mixed Concrete (G15) 0.08 Cube 20,745.00 1,659.60
Add 10 % for Wastage 165.96
1,825.56
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
Labour
Skilled Labour 0.75 day 950.00 712.50
Un / skilled Labour 3.00 day 650.00 1,950.00
2,662.50
3% of labour Cost for Tool 79.88
Cost for one Sqr 4,567.94 685.19 5,253.13
Preliminaries 10% 456.79
Cost for 1 Sqr 5,024.73 753.71 5,778.44
10.0 3" thick flr conc. Including BRC mesh Queens
Consider 1 Sqr
Materials
mixed Concrete (G15) 0.25 Cube 28,154.83 7,038.71
Add 10 % for Wastage 703.87
7,742.58
BRC Mesh 100.0 Sq.ft 45.24 4,523.81
Labour
Skilled Labour 0.25 day 950.00 237.50
Un / skilled Labour 1.00 day 650.00 650.00
887.50
3% of labour Cost for Tool 26.63
13,180.51 1,977.08 15,157.59
Preliminaries 10% 1,318.05
Cost for 1 Sqr 14,498.56 2,174.78 16,673.35
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
B1 Supply and fix 50x150mm precast
pergolas.including two coats of filler and
two coats of weather shied paint 10 L.ft
Materials
50x 150mm pergolas 10.00 L.ft 90.00 900.00
Add 10% trance port 90.00
Sand 0.00 cube 7,000.00 7.00
Metal 0.01 cube 4,800.00 24.00
1,021.00
Labour
Sk labour 0.25 day 950.00 237.50
U/sk labour 0.25 day 650.00 162.50
400.00
Add
3% of labour cost for tool 12.00
5% of labour cost for scafolding 20.00
32.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
Add
Painting 13.30 Sq.ft 29.66 394.41 394.41
1,847.41 277.11 2,124.52
212.45 L.ft
Preliminaries 184.74 696.84 Lm
Cost for one cube with preliminaries 2,032.15 304.82 2,336.98
Kerbs
Laid 9" below ground,and bedded on grade
15 concrete 8"x4" base and 4"x4" haunch on
either side;excavation ,backfilling,disposal
of surplus,formwork
Assume 10 L.ft
4" x 12" path edgings 10.00 L.ft 125.00 1,250.00
Transport 5% 62.50
Excavation 17.55 cu.ft 14.00 245.70
2" thick screed (grade 15) 2.18 cu.ft 285.00 620.73
2,178.93
Labour
Skill
0.25 Day 950.00 237.50
Un Skill
0.25 Day 650.00 162.50
400.00
3% of labour Cost for tools
12.00
2,590.93
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
Per L.ft 259.09 38.86 297.96
2 VANITY COUNTERS
8' 0"x2' 0" ,2" thick, cantilevered from wall,
reinforced with 10mm rods @ 8" c/c both
ways all faces cement rendered, exposed
faces finished with cut & polish 1:10
Titanium and cement floating with cut out
for basins. 8.00 2.00 0.17
Material
Concrete (grade 25) 2.72 Cu.ft 368.58 1,002.54
Formwork
18.04 Sq.ft 88.00 1,587.52
Reinforcement
9.12 kg 160.00 1,459.95
Cement rendering
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
34.04 Sq.ft 60.00 2,042.40
Titanium Cut & polish
ddt for basin 17.04 Sq.ft 207.50 3,535.80
Cost for one Vanity Counter 9,628.20 1,444.23 11,072.44
C
Precast reinforced concrete pipes laid 2'
below ground
Assume 10 L.ft
9" Dia Concrete pipe 10.00 L.ft 362.50 3,625.00 3,625.00
Transport 5% 181.25
Joint
Cement 0.50 Bag 785.00 392.50
sand 0.01 Cube 5,500.00 55.00 447.50
Wastage 10% 44.75
Excavation 56.88 Cu.ft 14.00 796.25
Back fill 20.63 Cu.ft 15.00 309.38
Disposal 56.88 Cu.ft 10.00 568.75
6" thick concrete bed and hounch 17.50 Cu.ft 285.00 4,987.50
15.00 Cu.ft 285.00 4,275.00 10,936.88
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
Labour
Skill 1.00 Day 950.00 950.00
Un Skill 2.00 Day 650.00 1,300.00 2,250.00
67.50
17,552.88
Per L.ft 1,755.29
A
RCC semi circular open drain size 18"
wide x 12" deep
Assume 10 L.ft
18"x 12" RCC semi circular drain
10.00 L.ft 325.00 3,250.00 3,250.00
Transport 5% 162.50
Joint
Cement 0.50 Bag 785.00 392.50
sand 0.01 Cube 5,500.00 55.00 447.50
Wastage 10% 44.75
Labour
Un/sk for excavation 0.25 Day 650.00 162.50
Skill 0.50 Day 950.00 475.00
Un Skill 1.00 Day 650.00 650.00 1,287.50
Tools 3% 19.50 669.50
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
5,861.75
Per L.ft 586.18
B4 Concrete 1:2:4 (3/4") grade 20 1 Cube 53,247.30 1 m3 18,815.30
MIXING Cost
Materials
Cement 42.00 bags 740.00 31,080.00
Sand 0.50 Cube 7,000.00 3,500.00
Metal 0.50 Cube 3,500.00 1,750.00
Water 125.00 gal 0.50 62.50
36,392.50
Labour
Mixer operator 0.33 day 950.00 313.50
Un / skilled Labour 2.00 day 650.00 1,300.00
1,613.50
Plant & Equipment
Concrete mixture 0.33 day 2,300.00 766.67
Cost for one Cube (mixing only) 38,772.67
LAYING Cost
Mason 0.75 day 950.00 712.50
Vibrator operator 0.75 day 950.00 712.50
6 Un / skilled Labour 4.50 day 650.00 2,925.00
4,350.00
Plant & Equipment
Vibrator operator 0.75 day 1,850.00 1,387.50
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount O/H &
profit
Remarks
Add
3% of labour Cost for tools for tool 130.50
5% of labour Cost for scaffolding for
scafolding
217.50
348.00
Curing
Water 100.00 gal. 0.50 50.00
Un / skilled Labour 0.33 day 650.00 216.67
266.67
45,124.83
O/H and profit 8,122.47
Cost for 1 Cube with Preliminaries 53,247.30
5546.59398
TERMITE TRETMENT / WATER PROOPING
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount O/H &
profit
Remarks
15%
A1 Anti termite tretment 1 Sqr
Sub Contrctor's price 1.00 Sqr 1,975.00 1,975.00
Add
Attendance
7% of price 138.25
2,113.25 316.99 2,430.24 Sqr
Add 261.49 m2
Preliminaries 21.13
Cost per one sqr wth preliminaries 2,134.38 320.16 2,454.54 Sqr
A1 Water proofing 1 m2
Sub Contrctor's price 1.00 m2 875.00 875.00
Add
Attendance
7% of price 61.25
Main Index
936.25 140.44 1,076.69
Add
Preliminaries 9.36
Cost per one sqr wth preliminaries 945.61 141.84 1,087.45
Add
Protective Screed 1.00 m2 533.00 533.00 533.00
1,609.69 1m2
PLUMBING GAUGE 600
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
1 32mm diameter pvc pipe fixed to wall
Consider 50 L.ft
Materials
32mm pipe
50.00 L.ft 20.92 1,046.15
Clipe & nails
160.00
Solvent cement
75.00 Grms 2.28 171.00
Others
1,280.00
2,657.15
Labour
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
3,953.15
79.06 11.86 90.92
Preliminaries
10% 395.32
Cost per 50 L.ft
4,348.47
Cost per 1 L.ft 86.97 13.05 100.01
2 32mm diameter pvc pipe laying trench
Main Index
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Consider 50 L.ft
Materials
32mm pipe
50.00 L.ft 20.92 1,046.15
Solvent cement
75.00 Grms 2.28 171.00
Others
1,280.00
2,497.15
Labour
U/sk labour
0.75 Day 650.00 487.50
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
4,319.65
86.39 12.96 99.35
Preliminaries
10% 431.97
Cost per 50 L.ft
4,751.62
Cost per 1 L.ft 95.03 14.25 109.29
3 40mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
40mm pipe
50.00 L.ft 51.00 2,550.00
Clipe & nails
300.00
Solvent cement
100.00 Grms 2.28 228.00
Others
2,045.00
5,123.00
Labour
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
6,419.00
128.38 19.26 147.64
Preliminaries
10% 641.90
Cost per 50 L.ft 7,060.90
Cost per 1 L.ft 141.22 21.18 162.40
4 40mm diameter pvc pipe laying trench
Consider 50 L.ft
Materials
40mm pipe
50.00 L.ft 51.00 2,550.00
Solvent cement
100.00 Grms 2.28 228.00
Others
2,045.00
4,823.00
Labour
U/sk labour
0.75 Day 650.00 487.50
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
6,645.50
132.91 19.94 152.85
Preliminaries
10% 664.55
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Cost per 50 L.ft
7,310.05
Cost per 1 L.ft 146.20 21.93 168.13
5 50mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
50mm pipe
50.00 L.ft 68.15 3,407.69
Clipe & nails
300.00
Solvent cement
100.00 Grms 2.28 228.00
Others
3,190.00
7,125.69
Labour
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
8,421.69
168.43 25.27 193.70
Preliminaries
10% 842.17
Cost per 50 L.ft
9,263.86
Cost per 1 L.ft 185.28 27.79 213.07
6 50mm diameter pvc pipe laying trench
Consider 50 L.ft
Materials
50mm pipe
50.00 L.ft 68.15 3,407.69
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Solvent cement
100.00 Grms 2.28 228.00
Others
3,190.00
6,825.69
Labour
U/sk labour
0.75 Day 650.00 487.50
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
8,648.19
172.96 25.94 198.91
Preliminaries
10% 864.82
Cost per 50 L.ft 9,513.01
Cost per 1 L.ft 190.26 28.54 218.80
7 63mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
63mm pipe
50.00 L.ft 112.92 5,646.15
Clipe & nails
360.00
Solvent cement
100.00 Grms 2.28 228.00
Others
4,980.00
11,214.15
Labour
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Add: 5% Scaffolding 5% 60.00
12,510.15
250.20 37.53 287.73
Preliminaries
10% 1,251.02
Cost per 50 L.ft 13,761.17
Cost per 1 L.ft 275.22 41.28 316.51
8 63mm diameter pvc pipe laying trench
Consider 50 L.ft
Materials
63mm pipe
50.00 L.ft 112.92 5,646.15
Solvent cement
100.00 Grms 2.28 228.00
Others
4,980.00
10,854.15
Labour
U/sk labour
0.75 Day 650.00 487.50
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
12,676.65
253.53 38.03 291.56
Preliminaries
10% 1,267.67
Cost per 50 L.ft
13,944.32
Cost per 1 L.ft 278.89 41.83 320.72
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
9 75mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
75mm pipe
50.00 L.ft 222.92 11,146.15
Clipe & nails
360.00
Solvent cement
100.00 Grms 2.28 228.00
Other
8,916.92
20,651.08
Labour
Plumber
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
21,947.08
438.94 65.84 504.78
Preliminaries
10% 2,194.71
Cost per 50 L.ft
24,141.78
Cost per 1 L.ft 482.84 72.43 555.26
10 75mm diameter pvc pipe laying trench
Consider 50 L.ft
Materials
75mm pipe
50.00 L.ft 222.92 11,146.15
Solvent cement
100.00 Grms 2.28 228.00
Other
8,916.92
20,291.08
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Labour
Excavation
0.75 Day 650.00 487.50
Skilled labourer
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
22,113.58
442.27 66.34 508.61
Preliminaries
10% 2,211.36
Cost per 50 L.ft
24,324.93
Cost per 1 L.ft 486.50 72.97 559.47
11 90mm diameter pvc pipe fix to wall
Consider 50 L.ft
Materials
90mm pipe
50.00 L.ft 274.65 13,732.50
Clipe & nails
390.00
Solvent cement
150.00 Grms 2.28 342.00
Other
9,500.00
23,964.50
Labour
Skilled labourer
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
25,260.50
505.21 75.78 580.99
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Preliminaries
10% 2,526.05
Cost per 50 L.ft 27,786.55
Cost per 1 L.ft 555.73 83.36 639.09
12 90mm diameter pvc pipe laying trench
Consider 50 L.ft
Materials
90mm pipe
50.00 L.ft 274.65 13,732.50
Solvent cement
150.00 Grms 2.28 342.00
Other
9,500.00
23,574.50
Labour
Excavation
0.75 Day 650.00 487.50
Skilled labourer
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
25,397.00
507.94 76.19 584.13
Preliminaries
10% 2,539.70
Cost per 50 L.ft
27,936.70
Cost per 1 L.ft 558.73 83.81 642.54
13 110mm diameter pvc pipe fix to wall
Consider 50 L.ft
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Materials
110mm pipe
50.00 L.ft 402.30 20,115.00
Clipe & nails
390.00
Solvent cement
150.00 Grms 2.28 342.00
Other
19,000.00
39,847.00
Labour
Skilled labourer
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,200.00
Add: 3% Tools 3% 36.00
Add: 5% Scaffolding 5% 60.00
41,143.00
822.86 123.43 946.29
Preliminaries
10% 4,114.30
Cost per 50 L.ft
45,257.30
Cost per 1 L.ft 905.15 135.77 1,040.92
14 110mm diameter pvc pipe laying trench
Consider 50 L.ft
Materials
110mm pipe
50.00 L.ft 402.30 20,115.00
Solvent cement
150.00 Grms 2.28 342.00
Other
19,000.00
39,457.00
Labour
Excavation
0.75 Day 650.00 487.50
Skilled labourer
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
1,687.50
Add: 3% Tools 3% 50.63
Add: 5% Scaffolding 5% 84.38
41,279.50
825.59 123.84 949.43
Preliminaries
10% 4,127.95
Cost per 50 L.ft
45,407.45
Cost per 1 L.ft 908.15 136.22 1,044.37
ELECTRICAL INSTALLATION
Unit Qty Rate Remarks
Wire
1/1.13 mm Cu/PVC/PVC 1mm2 m 100.00 1,850.00 Kalani cable
7/0.67 mm Cu/PVC earth 1.5mm2 m 100.00 5,540.00
Conduit
PCV conduit pipe 1"
Lft 13.00 167.00 S-Lon
PCV conduit pipe 3/4""
L.ft 13.00 121.00
Bend
1"
Nr 1.00 24.00 S-Lon
3/4"
Nr 1.00 20.00
Ceiling rose
Holders
Switches
one gang one way
Nr 1.00 109.09 Orange
two gang one way
Nr 1.00 184.07
three gang one way
Nr 1.00 263.94
four gang one way
Nr 1.00 349.64
Description
Main Index
362/818
Switch box
Round block
Socket outlet Orange
5A switched socket outlet Nr 1.00 303.87
13A switched socket outlet Nr 1.00 321.40
15A switched socket outlet Nr 1.00 373.02
Nr
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
1 Earth cable is
not required if
fitting is not
Metal
Rate for 4 Nos points
Materials
1mm2 Live 0.45 coil 1,850.00 832.50
1mm2 Nutral 0.35 coil 1,850.00 647.50
2.5mm Earth wire 0.25 coil 5,540.00 1,385.00
Wiring and installation (including supply of all materials) of the light points using approved type PVC insulated PVC
sheathed 1 mm2 copper cable and 2.5mm2 Earth cable drawn through securely fixed concealed PVC conduit.
(Switches shall be ABB / Clipsal / Orange / Tenby or equivalent)
363/818
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
PCV conduit pipe 1" 50.00 l.ft 12.85 642.31
PCV conduit pipe 3/4"" 20.00 l.ft 9.31 186.15
Bend 4.00 no 25.00 100.00
Ceiling rose 4.00 no 35.00 140.00
Holders 4.00 no 65.00 260.00
Switches -four gang one way 1.00 no 349.64 349.64
Switch box 1.00 no 40.00 40.00
Round block 4.00 no 20.00 80.00
Brass screws 1" 4.00 no 10.00 40.00
Brass screws 1/2" 8.00 no 5.00 40.00
Flexible wire 2 core 24.00 no 25.00 600.00 5,343.10
cement lime and sand 15% from
meterial cost
15% sum 801.47
clips and wire nails 6% from
meterial cost
6% sum 320.59
Labour
un skilled labour for chasing wall 1.00 day 650.00 650.00
Electricion 1.50 day 950.00 1,425.00
un skilled labour 1.50 day 650.00 975.00
Mason for prepare surface 1.00 day 950.00 950.00
4,000.00
Add for Tools
3% of labour cost 3% 120.00
5% of labourer cost 5% 200.00
10,785.15
For 1 Point 2,696.29 404.44 3,100.73
364/818
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
3
Rate for 4 Nos points
Materials
2.5mm2 Live 0.45 coil 1,850.00 832.50
2.5mm2 Nutral 0.35 coil
2.5mm2 Earth wire 0.25 coil 5,540.00 1,385.00
Conduit pipe 5/8" 80.00 l.ft 10.00 800.00
5 amp socket outlets 1.00 no 303.87 303.87
Bend 2.00 no 25.00 50.00
Switch box 1.00 no 40.00 40.00 3,411.37
Cement lime and sand 15% from
meterial cost
15% sum 511.71
Clips and wire nails 6% from
meterial cost
6% sum 204.68
Labour
Un skilled labour for chasing wall
1.00 day 650.00 650.00
Electricion 2.00 day 950.00 1,900.00
Un skilled labour 2.00 day 650.00 1,300.00
Mason for prepare surface 1.00 day 950.00 950.00
4,800.00
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
9,311.76
Supply & installation of 5A fused shuttered switched socket outlet to comply with relevant BS standard (Clipsal,
Orange, Crabtree/ Tenby/ABB or equivalent). Wiring (including supply of earth wire & all other material required ) of
above socket outlet using approved type 2.5mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through
securely fixed concealed PVC conduit in a ring circuit.
365/818
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
For 1 Point 2,327.94 349.19 2,677.13
4
Materials
2.5mm2 Live 0.45 coil 1,850.00 832.50
2.5mm2 Nutral 0.35 coil
2.5mm2 Earth wire 0.25 coil 5,540.00 1,385.00
Conduit pipe 1" 65.00
Conduit pipe 3/4" 25.00 l.ft 10.00 250.00
13 amp socket outlets 4.00 no 345.00 1,380.00
Bend 4.00 no 25.00 100.00
Switch box 4.00 no 40.00 160.00 1,890.00
Cement lime and sand 15% from
meterial cost
15% sum 283.50
Clips and wire nails 6% from
meterial cost
6% sum 113.40
Labour
un skilled labour for chasing wall 1.00 day 650.00 650.00
Electricion 2.00 day 950.00 1,900.00
un skilled labour 2.00 day 650.00 1,300.00
Mason for prepare surface 1.00 day 950.00 950.00 4,800.00
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
7,470.90
Supply & installation of 13A fused shuttered switched socket outlet to comply with relevant BS standard (Clipsal,
Orange, Crabtree/ Tenby/ABB or equivalent). Wiring (including supply of earth wire & all other material required ) of
above socket outlet using approved type 2.5mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through
securely fixed concealed PVC conduit in a ring circuit.
366/818
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
For 1 Point 1,867.73 280.16 2,147.88
4
Materials
2.5mm2 Live 0.45 coil 1,850.00 832.50
2.5mm2 Nutral 0.35 coil
2.5mm2 Earth wire 0.25 coil 5,540.00 1,385.00
Conduit pipe 5/8" 80.00 l.ft 10.00 800.00
15 amp socket outlets 1.00 no 345.00 345.00
Bend 2.00 no 25.00 50.00
Switch box 1.00 no 40.00 40.00 1,235.00
Cement lime and sand 15% from
meterial cost
15% sum 185.25
Clips and wire nails 6% from
meterial cost
6% sum 74.10
Labour
un skilled labour for chasing wall 1.00 day 650.00 650.00
Electricion 2.00 day 950.00 1,900.00
un skilled labour 2.00 day 650.00 1,300.00
Mason for prepare surface 1.00 day 950.00 950.00 4,800.00
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
Supply & installation of 15A fused shuttered switched socket outlet to comply with relevant BS standard (Clipsal,
Orange, Crabtree/ Tenby/ABB or equivalent). Wiring (including supply of earth wire & all other material required ) of
above socket outlet using approved type 2.5mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through securely
fixed concealed PVC conduit in a ring circuit.
367/818
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
6,678.35
For 1 Point 1,669.59 250.44 1,920.03
5
Materials
1mm2 Live 0.45 coil - -
1mm2 Nutral 0.35 coil - -
2.5mm Earth wire 0.25 coil - -
PCV conduit pipe 1" 50.00 l.ft 10.00 500.00
PCV conduit pipe 3/4"" 20.00 l.ft
1 Gang switch 1.00 no 100.00 100.00
Bend 2.00 no 25.00 50.00
Switch box 1.00 no 40.00 40.00
Fan hook 1.00 no 250.00 250.00 440.00
cement lime and sand 15% from
meterial cost
15% sum 66.00
clips and wire nails 6% from
meterial cost
6% sum 26.40
Labour
Wiring & installation (including supply of all material, earth wire & switch) for ceiling / wall mounted fans using
approved type 1 mm2 PVC/PVC copper cable & 2.5mm2 earth wire drawn through securely fixed PVC conduits.
368/818
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
un skilled labour for chasing wall 1.00 day 650.00 650.00
Electricion 2.00 day 950.00 1,900.00
un skilled labour 2.00 day 650.00 1,300.00
Mason for prepare surface 1.00 day 950.00 950.00 4,800.00
Add for Tools
3% of labour cost 3% 144.00
5% of labourer cost 5% 240.00
5,716.40
For 1 Point
1,429.10 214.37 1,643.47
Supply & installation of TV socket outlet to comply with relevant BS standard (Crabtree/ Tenby/Clipsal/Orange or
equivalent). Wring (including all material required ) of above socket outlet using approved type two core PVC/PVC
copper cable drawn through securely fixed concealed PVC conduit.
Supply & installation of telephone socket outlet to comply with relevant BS standard (Crabtree/
Tenby/Clipsal/Orange or equivalent). Wring (including all material required ) of above socket outlet using approved
type two core PVC/PVC copper cable drawn through securely fixed concealed PVC conduit.
369/818
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
370/818
DOORS AND WINDOWS
Specification:
Materil
Frame -Teak
Frame 6" x4" 1.00 L.ft 1,100.00
4" x3" 1.00 L.ft 550.00
Sash -Teak
Sash 11/2" thick 1.00 Sq.ft 1,200.00
11/4" thick 1.00 Sq.ft 1,000.00
1" thick 1.00 Sq.ft 575.00
Louver
1/2" louver blade 1.00 Sq.ft 400.00
Glass - clear
6mm thick 1.00 Sq.ft 100.00
3mm thick 1.00 Sq.ft
Glazing beads 1.00 L.ft 5.00
Iron mongery -Stainless steel
6"x4" Hinges 1.00 Nos 550.00
4"x3" Hinges 1.00 Nos 350.00
1 1/4" screws 1.00 Nos 8.35
1' 6" High brass barolt bolt 1.00 Nos 2,300.00
6" High brass barolt bolt 1.00 Nos 380.00
Union Lock Good quality 1.00 Nos 6,900.00
Union Lock Normal 1.00 Nos 2,900.00
Casement stay 1.00 Nos 380.00
Window Fasterners 1.00 Nos 325.00
Window Rings 1.00 Nos 35.00
Main Index
Wood Seasion
6" x4" 1.00 L.ft 43.00
4' x3" 1.00 L.ft 22.00
11/2" sash 1.00 Sq.ft
11/4" sash 1.00 Sq.ft 27.00
1'-0" x 1'-0" x 1'-0" 1.00 Cu.ft 263.00
Wood Painting
Wood treatment 1.00 Sq.ft 20.00
Water base 1.00 Sq.ft 88.00
Spray paint 1.00 Sq.ft 88.00
Labour
Frame Planking 1.00 L.ft 10.00
Sash Planking 1.00 Sq.ft 10.00
Frame making 6" x 4" 1.00 L.ft 110.00
4" x 3" 1.00 L.ft 100.00
Sash making
Solid timber "v" grove panel 1.00 Sq.ft 450.00
Timber / glass 1.00 Sq.ft 225.00
Frame fixing to wall -small 1.00 Nos 750.00
Frame fixing to wall -big 1.00 Nos 1,000.00
Description
Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
1 0-4" x 0'-3" frame with 1 1/4" thick sash local teak
door
Overall size 3'-0" x 7'-0" Single sash with Horizontal
vertical timber battens with "V" groove as per detail
drawing
Overall size ,3' -0" x 7'- 0" , type D3 21.00 Sq.ft
Material
4"x3" frame. 19.00 L.ft 550.00 10,450.00
1 1/4" thick Teak timber sash ( 2'-6" x 6'-9") 16.88 sq.ft 1,000.00 16,875.00
27,325.00
Wastage 10% 2,732.50
Transport 7% 1,912.75
Wood Season 19.00 l.ft 22.00 418.00
Wood Season 16.88 sq.ft 27.00 455.63
873.63
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Iron mongery -Stainless steel
6"x4" Hinges 4.00 Nr 550.00 2,200.00
1 1/4" screws 32.00 Nr 8.35 267.20
1' 6" High brass barolt bolt 1.00 Nr 2,300.00 2,300.00
6" High brass barolt bolt 1.00 Nr 380.00 380.00
Union Lock Good quality 1.00 Nr 6,900.00 6,900.00
12,047.20
Labour
Making frame
Carpenter 1.5 Days 1,000.00 1,500.00
Un/Sk 1.5 Days 675.00 1,012.50
frame fixing to wall
Mason 0.75 Days 1,000.00 750.00
Un/Sk 0.75 Days 675.00 506.25
Making sash
Carpenter 2.5 Days 1,000.00 2,500.00
Un/Sk 2.5 Days 675.00 1,687.50
Sash fixing to frame with iron mongery
Carpenter 1 Days 1,000.00 1,000.00
Un/Sk 1 Days 675.00 675.00
9,631.25
Tools 3% 288.94
56,311.26
O/H and profit 18% 10,136.03
Total cost 66,447.29
Total cost for 1 Sq.ft 3,164.16
Add water base painting ( both side ) 247.50
Sq.ft Rate with water base paint 3,411.66
2 0-4" x 0'-3" frame with 1 1/4" thick sash local teak
and 6mm glass
Overall size 12'-0" x 7'-0" Timber glazed sliding door as
per detail drawing
Overall size ,12' -0" x 7'- 0" , type SD1 84.00 Sq.ft
Material
4"x3" frame. 42.00 L.ft 550.00 23,100.00
1 1/4" thick Teak timber sash ( 2'-6" x 6'-9") 33.12 sq.ft 1,000.00 33,120.00
6mm glass 46.50 sq.ft 100.00 4,650.00
104,188.24
Wastage 10% 10,418.82
Transport 7% 7,293.18
Wood Season 42.00 l.ft 22.00 924.00
Wood Season 33.12 sq.ft 27.00 894.24
1,818.24
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Iron mongery -Stainless steel
Sliding gear 1.00 Item 40,000.00 40,000.00
6" High brass barolt bolt 1.00 Nos 380.00 380.00
40,380.00
Labour
Making frame
Carpenter 1.5 Days 1,000.00 1,500.00
Un/Sk 1.5 Days 675.00 1,012.50
frame fixing to wall
Mason 1.25 Days 1,000.00 1,250.00
Un/Sk 1.25 Days 675.00 843.75
Making sash
Carpenter 6 Days 1,000.00 6,000.00
Un/Sk 6 Days 675.00 4,050.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
18,006.25
Tools 3% 540.19
184,144.92
O/H and profit 18% 33,146.09
Total cost 217,291.00
Total cost for 1 Sq.ft 2,586.80
Add water base painting 110.00
Sq.ft Rate with water base paint 2,696.80
3 0-4" x 0'-3" frame with 1 1/4" thick sash local teak
and 6mm glass
Overall size 10'-0" x 8'-0" Timber glazed french
windoor as per detail drawing
3 Overall size ,10' -0" x 8'- 0" , type FW 80.00 Sq.ft
Material
4"x3" frame. 29.00 L.ft 550.00 15,950.00
1 1/4" thick Teak timber sash ( 2'-6" x 6'-9") 32.24 sq.ft 1,000.00 32,240.00
6mm glass 41.38 sq.ft 100.00 4,138.00
52,328.00
Wastage 10% 5,232.80
Transport 7% 3,662.96
Wood Season 29.00 l.ft 22.00 638.00
Wood Season 32.24 sq.ft 27.00 870.48
1,508.48
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Labour
Making frame
Carpenter 1.75 Days 1,000.00 1,750.00
Un/Sk 1.75 Days 675.00 1,181.25
frame fixing to wall
Mason 1 Days 1,000.00 1,000.00
Un/Sk 1 Days 675.00 675.00
Making sash
Carpenter 6 Days 1,000.00 6,000.00
Un/Sk 6 Days 675.00 4,050.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
18,006.25
Tools 3% 540.19
82,778.68
O/H and profit 18% 14,900.16
Total cost 97,678.84
Total cost for 1 Sq.ft 1,220.99
Add water base painting 110.00
Sq.ft Rate with water base paint 1,330.99
7 0-4" x 0'-3" frame with 1 1/4" thick sash local teak
and 6mm glass
Overall size 8'-0" x 5'-0" Timber glazed openable door
as per detail drawing
Overall size ,8' -0" x 5'- 0" , type W1 40.00 Sq.ft
Material
4"x3" frame. 26.00 L.ft 550.00 14,300.00
1 1/4" thick Teak timber sash 16.83 sq.ft 1,000.00 16,830.00
6mm glass 24.42 sq.ft 100.00 2,442.00
33,572.00
Wastage 10% 3,357.20
Transport 7% 2,350.04
Wood Season 26.00 l.ft 22.00 572.00
Wood Season 16.83 sq.ft 27.00 454.41
1,026.41
Holdpast ( flat iron / concrete / formwors) 6.00 Nr 250.00 1,500.00 1,500.00
Iron mongery -Stainless steel
6"x4" Hinges
4"x3" Hinges
1 1/4" screws
1' 6" High brass barolt bolt
6" High brass barolt bolt
Union Lock Good quality
Union Lock Normal
Casement stay
Window Fasterners
Window Rings
Labour
Making frame
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
frame fixing to wall
Mason 1 Days 1,000.00 1,000.00
Un/Sk 1 Days 675.00 675.00
Making sash
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
11,725.00
Tools 3% 351.75
53,882.40
O/H and profit 18% 9,698.83
Total cost 63,581.23
Total cost for 1 Sq.ft 1,589.53
Add water base painting - Area consider single side 110.00
Sq.ft Rate with water base paint 1,699.53
8 0-5" x 0'-4" frame with 1 1/4" thick sash local teak
louver sash panel and fixed glass panel with 6mm
glass
Overall size ,3' -0" x 6'- 6" , type W1 26.00 Sq.ft
Material
5"x4" frame. 22.00 L.ft 1,100.00 24,200.00
1 1/4" thick Teak timber sash 20.00 sq.ft 1,000.00 20,000.00
6mm glass 17.18 sq.ft 100.00 1,718.00
45,918.00
Wastage 10% 4,591.80
Transport 7% 3,214.26
Wood Season 22.00 l.ft 43.00 946.00
Wood Season 20.00 sq.ft 27.00 540.00
1,486.00
Holdpast ( flat iron / concrete / formwors) 4.00 Nr 250.00 1,000.00 1,000.00
Iron mongery -Stainless steel
6"x4" Hinges
4"x3" Hinges
1 1/4" screws
1' 6" High brass barolt bolt
6" High brass barolt bolt
Union Lock Good quality
Union Lock Normal
Casement stay
Window Fasterners
Window Rings
Labour
Making frame
Carpenter 1.5 Days 1,000.00 1,500.00
Un/Sk 1.5 Days 675.00 1,012.50
frame fixing to wall
Mason 1.25 Days 1,000.00 1,250.00
Un/Sk 1.25 Days 675.00 843.75
Making sash
Carpenter 3 Days 1,000.00 3,000.00
Un/Sk 3 Days 675.00 2,025.00
Sash fixing to frame with iron mongery
Carpenter 2 Days 1,000.00 2,000.00
Un/Sk 2 Days 675.00 1,350.00
12,981.25
Tools 3% 389.44
69,580.75
O/H and profit 18% 12,524.53
Total cost 82,105.28
Total cost for 1 Sq.ft 3,157.90
Add water base painting 220.00
Sq.ft Rate with water base paint 3,377.90
1 0-6" x 0'-4" frame with 1 1/2" thick sash
local teak
Overall size 6'-0" x 9'-4" Double sash 0'-5"
width timber stile with vertical timber battens
with "V" groove as per detail drawing
Overall size ,6' 0" x 9' 4" , type D1 6.00 9.33 55.98 Sq.ft
0.5 0.33
5.33 9.00
Material
6"x4" frame. 24.66 L.ft 1,100.00 27,126.00
1 1/2" thick Teak timber sash 47.98 sq.ft 1,200.00 57,578.67
Wood presavative 8.87 Cu.ft 263.00 2,332.05
Wood treatment 124.57 sq.ft 20.00 2,491.40
89,528.12
Wastage 10% 8,952.81
Transport 7% 6,266.97
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 110.00 2,712.60
Frame fixing to wall 1 Item 1,000.00 1,000.00
Sash planking 47.98 sq.ft 10.00 479.82
Timber Sash making 47.98 sq.ft 450.00 21,592.00
Water base paint 167.94 sq.ft 88.00 14,778.72
Locks & ironmongary fixing 2,500.00 43,309.74
Tools 3% 1,299.29
Total cost 149,356.94
Total cost for 1 Sq.ft 2,668.04
2 0-4" x 0'-3" frame with 1 1/4" thick sash
local teak
Overall size 3'-0" x 9'-4", 3'-0" x 8'-0" Side
hung, Single sash 0'-4" width timber stile with
vertical timber battens with "V" groove with 3'-
0" x 1'-2" fixed glass above as per detail
drawing
Overall size ,3' 0" x 9' 4" , type D2 3.00 9.33 27.99 Sq.ft
frame 0.33 0.25
sash 2.50 8.83 22.08
glass 2.50 1.17 2.93
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
1 1/4" thick Teak timber sash 19.15 sq.ft 1,000.00 19,150.00
Wood presavative 3.95 Cu.ft 263.00 1,038.71
Wood treatment 60.74 sq.ft 20.00 1,214.81
34,966.52
Wastage 10% 3,496.65
3mm Glass arae 2.93 sq.ft - - -
Glazing beads 7.34 L.ft 5.00 36.70 36.70
38,499.87
Transport 7% 2,694.99
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 22.08 sq.ft 10.00 220.75
Timber Sash making 22.08 sq.ft 225.00 4,966.88
Water base paint 162.09 sq.ft 88.00 14,263.92
Locks & ironmongary fixing 2,500.00 25,414.15
Tools 3% 762.42
Total cost 67,371.43
Total cost for 1 Sq.ft 2,406.98
3 Overall size 3'-0" x 9'-4", 3'-0" x 8'-0" Side
hung, Single sash 'flush panel sash with 3'-0" x
1'-2" fixed glass above as per detail drawing
Overall size ,3' 0" x 9' 4" , type D3 3.00 9.33 27.99 Sq.ft
frame 0.33 0.25
sash 2.50 8.83 22.08
glass 2.50 1.17 2.93
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
1 1/4" thick Teak timber sash 19.15 sq.ft 1,000.00 19,150.00
Wood presavative 3.95 Cu.ft 263.00 1,038.71
Wood treatment 60.74 sq.ft 20.00 1,214.81 34,966.52
Wastage 10% 3,496.65
3mm Glass arae 2.93 sq.ft - - -
Glazing beads 7.34 L.ft 5.00 36.70 36.70
38,499.87
Transport 7% 2,694.99
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 22.08 sq.ft 10.00 220.75
Timber Sash making 19.15 sq.ft 225.00 4,308.75
Water base paint 162.09 sq.ft 88.00 14,263.92
Locks & ironmongary fixing 2,500.00 24,756.02
Tools 3% 742.68
Total cost 66,693.56
Total cost for 1 Sq.ft 2,382.76
Overall size 4'-0" x 9'-4", 4'-0" x 8'-0" Side
hung, double sash 0'-4" width timber stile with
vertical timber battens with "V" groove with 4'-
0" x 1'-2" fixed glass above as per detail
drawing
4 Overall size ,4' 0" x 9' 4" , type D4 / D5 4.00 9.33 37.32 Sq.ft
frame 0.33 0.25
sash 3.50 8.83 30.91
glass 3.50 1.17 4.10
Material
4"x3" frame. 26.66 L.ft 550.00 14,663.00
1 1/4" thick Teak timber sash 26.81 sq.ft 1,000.00 26,810.00
Wood presavative 4.88 Cu.ft 263.00 1,283.56
Wood treatment 77.88 sq.ft 20.00 1,557.61 44,314.17
Wastage 10% 4,431.42
3mm Glass arae 4.10 sq.ft - - -
Glazing beads 9.34 L.ft 5.00 46.70 46.70
48,792.29
Transport 7% 3,415.46
Labour
Frame Planking 26.66 L.ft 10.00 266.60
Frame making 26.66 L.ft 100.00 2,666.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 30.91 sq.ft 10.00 309.05
Timber Sash making 26.81 sq.ft 225.00 6,032.25
Water base paint 215.73 sq.ft 88.00 18,984.24
Locks & ironmongary fixing 2,500.00 31,508.14
Tools 3% 945.24
Total cost 84,661.13
Total cost for 1 Sq.ft 2,268.52
1 1/2" thick Frame
1 1/4" thick sash local teak
Overall size 12'-3" x 9'-4", Four sash, two
sashes sliding and two sash fixed on either side
SD1, SD2,
SD5,SD6,SD8,SD9,SD11,SD12,SD13,SD14,SD1
5
5 Overall size ,12' 3" x 9' 4" 12.25 9.33 114.29 Sq.ft
glass 9.25 7.83 72.43
Material
9" timber plank 23.18 sq.ft 1,200.00 27,819.00 16.28
1 1/4" thick Teak timber sash 51.20 sq.ft 1,000.00 51,195.00 8.62
Wood presavative 7.21 Cu.ft 263.00 1,895.16
Wood treatment 125.34 sq.ft 20.00 2,506.81 83,415.97
Wastage 10% 8,341.60
6mm Glass arae 72.43 sq.ft 100.00 7,242.75 7,242.75
Glazing beads 99.60 L.ft 5.00 498.00 498.00
Sliding gears 24.50 L.ft - -
99498.319
Transport 7% 6,964.88
Labour
9" thk plak Planking 23.18 Sq.ft 10.00 231.83
9" thk plak fixing to wall 1 Item 750.00 750.00
Sash planking 51.20 sq.ft 10.00 511.95
Timber Sash making 114.29 sq.ft 225.00 25,715.81
Water base paint 102.39 sq.ft 88.00 9,010.32
Locks & ironmongary fixing 2,500.00 38,719.91
Tools 3% 1,161.60
Total cost 146,344.71
Total cost for 1 Sq.ft 1,280.44
1 1/4" thick sash local teak
Overall size 6'-0" x 9'-4", Two sash, glass
sliding and two sash fixed on either side
SD3, SD4, SD7,SD10,SD16
6 Overall size ,6' 0" x 9' 4" 6.00 9.33 55.98 Sq.ft
glass 4.50 7.83 35.24
Material 16.16
9" timber plank 18.50 sq.ft 1,200.00 22,194.00 8.50
1 1/4" thick Teak timber sash 25.41 sq.ft 1,000.00 25,410.00
Wood presavative 4.21 Cu.ft 263.00 1,106.06
Wood treatment 69.13 sq.ft 20.00 1,382.60 50,092.66
Wastage 10% 5,009.27
6mm Glass arae 35.24 sq.ft 100.00 3,523.50 3,523.50
Glazing beads 49.32 L.ft 5.00 246.60 246.60
Sliding gears 12.00 L.ft - -
58872.0267
Transport 7% 4,121.04
Labour
9" thk plak Planking 18.50 Sq.ft 10.00 184.95
9" thk plak fixing to wall 1 Item 750.00 750.00
Sash planking 50.82 sq.ft 10.00 508.20
Timber Sash making 55.98 sq.ft 225.00 12,595.50
Water base paint 50.82 sq.ft 88.00 4,472.16
Locks & ironmongary fixing 2,500.00 21,010.81
Tools 3% 630.32
Total cost 84,634.20
Total cost for 1 Sq.ft 1,511.87
1 1/4" thick sash local teak
Overall size 6'-0" x 9'-4", single sash, glass
sliding door
SD3a, SD17
7 Overall size ,6' 0" x 9' 4" 6.00 9.33 55.98 Sq.ft
glass 5.00 7.83 39.15
Material 21.66
9" timber plank 18.50 sq.ft 1,200.00 22,194.00 14.00
1 1/4" thick Teak timber sash 16.83 sq.ft 1,000.00 16,830.00
Wood presavative 3.35 Cu.ft 263.00 880.41
Wood treatment 51.97 sq.ft 20.00 1,039.40 40,943.81
Wastage 10% 4,094.38
6mm Glass arae 39.15 sq.ft 100.00 3,915.00 3,915.00
Glazing beads 35.66 L.ft 5.00 178.30 178.30
Sliding gears 12.00 L.ft - -
49131.4873
Transport 7% 3,439.20
Labour
9" thk plak Planking 18.50 Sq.ft 10.00 184.95
9" thk plak fixing to wall 1 Item 750.00 750.00
Sash planking 33.66 sq.ft 10.00 336.60
Timber Sash making 55.98 sq.ft 225.00 12,595.50
Water base paint 33.66 sq.ft 88.00 2,962.08
Locks & ironmongary fixing 2,500.00 19,329.13
Tools 3% 579.87
Total cost 72,479.70
Total cost for 1 Sq.ft 1,294.74
0-4" x 0'-3" frame with 1 1/4" thick sash
local teak stile with timber louver and fixed
glass above
Overall size 3'-0" x 6'-4", 3'-0" x 4'-0" single
sash glazed window with 3'-0" x 1'-2" fixed
glass above as per detail drawing
8 Overall size ,3' 0" x 6' 4" , type W1 3.00 6.33 18.99 Sq.ft
frame 0.33 0.25
sash 2.50 5.58 13.95
glass 3mm 2.50 1.17 2.93
Louver 1.50 4.58 6.87
Material
4"x3" frame. 21.66 L.ft 550.00 11,913.00
1 1/4" thick Teak timber sash 11.03 sq.ft 1,000.00 11,025.00
12.5mm louver 6.87 sq.ft 400.00 2,748.00
Wood presavative 3.16 Cu.ft 263.00 832.20
Wood treatment 53.77 sq.ft 20.00 1,075.36 27,593.55
Wastage 10% 2,759.36
3mm Glass arae 2.93 sq.ft - - -
Glazing beads 7.34 L.ft 5.00 36.70 36.70
30,389.61
Transport 7% 2,127.27
Labour
Frame Planking 21.66 L.ft 10.00 216.60
Frame making 21.66 L.ft 100.00 2,166.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 22.05 sq.ft 10.00 220.50
Timber Sash making 13.95 sq.ft 225.00 3,138.75
Water base paint 37.98 sq.ft 88.00 3,342.24
Locks & ironmongary fixing 2,500.00 12,334.09
Tools 3% 370.02
Total cost 45,220.99
Total cost for 1 Sq.ft 2,381.31
0-4" x 0'-3" frame with 1 1/4" thick sash
local teak stile with timber louver and fixed
glass above
Overall size 4'-0" x 6'-4", 4'-0" x 4'-0" double
sash glazed window with 4'-0" x 1'-2" fixed
glass above as per detail drawing
9 Overall size ,4' 0" x 6' 4" , type W2 4.00 6.33 25.32 Sq.ft
frame 0.33 0.25
sash 3.50 5.58 19.53
glass 3mm 3.50 1.17 4.10
Louver 1.50 4.58 6.87
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
1 1/4" thick Teak timber sash 15.44 sq.ft 1,000.00 15,435.00
12.5mm louver 6.87 sq.ft 400.00 2,748.00
Wood presavative 3.85 Cu.ft 263.00 1,013.27
Wood treatment 65.08 sq.ft 20.00 1,301.56 34,060.83
Wastage 10% 3,406.08
3mm Glass arae 4.10 sq.ft - - -
Glazing beads 9.34 L.ft 5.00 46.70 46.70
37,513.61
Transport 7% 2,625.95
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 30.87 sq.ft 10.00 308.70
Timber Sash making 19.53 sq.ft 225.00 4,394.25
Water base paint 50.64 sq.ft 88.00 4,456.32
Locks & ironmongary fixing 2,500.00 15,121.87
Tools 3% 453.66
Total cost 55,715.09
Total cost for 1 Sq.ft 2,200.44
0-4" x 0'-3" frame with 1 1/4" thick sash
local teak stile with timber louver and fixed
glass above
Overall size 4'-0" x 6'-4", 4'-0" x 4'-0" ,4"
width timber stile with two sash glazed window
with 4'-0" x 1'-2" fixed glass above as per
detail drawing
10 Overall size ,4' 0" x 6' 4" , type W3 4.00 6.33 25.32 Sq.ft
frame 0.33 0.25
sash 3.50 5.58 19.53
glass 3mm 3.50 1.17 4.10
glass 6mm 1.50 4.58 6.87
Material
4"x3" frame. 24.66 L.ft 550.00 13,563.00
1 1/4" thick Teak timber sash 8.57 sq.ft 1,000.00 8,565.00
Wood presavative 2.89 Cu.ft 263.00 760.32
Wood treatment 37.60 sq.ft 20.00 751.96 23,640.28
Wastage 10% 2,364.03
6mm Glass arae 6.87 sq.ft 100.00 687.00 687.00
3mm Glass arae 4.10 sq.ft - - -
Glazing beads 30.66 L.ft 5.00 153.30 153.30
26,844.60
Transport 7% 1,879.12
Labour
Frame Planking 24.66 L.ft 10.00 246.60
Frame making 24.66 L.ft 100.00 2,466.00
Frame fixing to wall 1 Item 750.00 750.00
Sash planking 8.57 sq.ft 10.00 85.65
Timber Sash making 19.53 sq.ft 225.00 4,394.25
Water base paint 50.64 sq.ft 88.00 4,456.32
Locks & ironmongary fixing 2,500.00 14,898.82
Tools 3% 446.96
Total cost 44,069.51
Total cost for 1 Sq.ft 1,740.50
Timber Felmet
L2.55
1" thick, 8" height timber felmet fixed with
nut & bolts to RCC beam and finished with
applying with 2 coat of water based
lacquer.(Spray paint) Queens
Assume 10 L.ft
Materials
1" thick, 8" height timber felmet 10.00 L.ft 575.00 5,750.00
Nut & bolts 5.00 No 10.00 50.00
5,800.00
Transport 7% 406.00
Labour
Skilled Labour 1.00 day 950.00 950.00
Un / skilled Labour 1.00 day 650.00 650.00
1,600.00
Paint
Tmber planking 10.00 L.ft 10.00 100.00
Tmber painting ( water base spry) 13.40 Sq.ft 115.00 1,541.00
1,641.00
9,447.00
Total cost for 1 L.ft 944.70
DOORS AND WINDOWS
Specification:
Materil
Frame -Red Balaw
Frame 6" x4" 1.00 L.ft 458.00
4" x3" 1.00 L.ft 214.00
Sash -Mahoganie
Sash 1 1/2" thick 1.00 Sq.ft 420.00
1 1/4" thick 1.00 Sq.ft 350.00
1 3/4" thick 1.00 Sq.ft 400.00
3' 0" x 7' 0" plywood door 1.00 Nos 3,600.00
Glass - clear
6mm thick 1.00 Sq.ft 100.00
3mm thick 1.00 Sq.ft
Iron mongery -Brass
6"x4" Hinges 1.00 Nos 550.00
4"x3" Hinges 1.00 Nos 350.00
1 1/4" screws 1.00 Nos 8.35
1' 6" High brass barolt bolt 1.00 Nos 2,300.00
6" High brass barolt bolt 1.00 Nos 380.00
Union Lock Good quality 1.00 Nos 6,900.00
Union Lock Normal 1.00 Nos 2,900.00
Casement stay 1.00 Nos 380.00
Window Fasterners 1.00 Nos 325.00
Main Index
Window Rings 1.00 Nos 35.00
Wood Seasion
1' 0" x 1' 0" x 1' 0" 1.00 Cu.ft 263.20
Labour
Frame making 6" x 4" 1.00 L.ft 110.00
4" x 3" 1.00 L.ft 100.00
Sash making
Solid timber "v" grove panel 1.00 Sq.ft 450.00
Timber / glass 1.00 Sq.ft 225.00
frame planking 1.00 L.ft 10.00
Sash planking 1.00 Sq.ft 10.00
Frame fixing to wall -small 1.00 Nos 750.00
Frame fixing to wall -big 1.00 Nos 1,000.00
Lock and ironmongary fixing 2,500.00
Item Discreption No No No No Length
Widt
h
Heigh
t
Qty Unit Rate Amount Total Amount
O/H &
Profit
15%
D1 Double sash timber battened door -4"
x3" frame and 11/4" thick sash ( finish
size )
Size of door 4'-0" x 9'-0"
1 4.00 9.00 36.00
Material
Timber
1 1/4" thick timber sash
3.50 8.75 30.63 Sq.ft 350.00 10,718.75
(3.5 x
10718.75
Wastage 10%
0.1 1071.88
4"x3" frame
22.00 L.ft 214.00 4,708.00
Ironmongary
6"x4" Hinges
4 4.00 Nr 550.00 2,200.00
1 1/4" screws
3 2 8 48 48.00 Nr 8.35 400.80
1' 6" High brass barolt bolt
1 1.00 Nr 2,900.00 2,900.00
6" High brass latch
1 1.00 Nr 380.00 380.00
Union Lock
1 1.00 Nr 380.00 380.00
Flat iron
Item 1,500.00
24,259.43
Transport 5%
0.05 1,212.97
Labour
Frame making
22 22.00 L.ft 100.00 2,200.00
Frame fixing to wall
1.00 Item 750.00 750.00
Sash making & fixing
30.63 30.63 Sq.ft 450.00 13,781.25
Frame planking
22 22.00 l.ft 10.00 220.00
Sash planking
30.63 30.63 Sq.ft 10.00 306.25
All iron mongary fixing including locks
1.00 Per Unit 2,500.00 2,500.00
17,257.50
42,729.90
Sq.ft. Rate 1,186.94 178.04
D2 Double sash panelleded door
Size of door
1 5.00 10.00 50.00
Size of frame
0.33 0.50
Sash
0.50 0.15
Material
6"x4" door frame
2 10 20
1 6 6
26
26.00 458.00 11,908.00
1 1/4" thick timber sash
4.33 9.67 41.90 350.00 14,663.87
26571.87
Wastage 10%
0.1 2657.19
6"x4" Hinges
3 3.00 550.00 1,650.00
1 1/4" screws
3 2 8 48 48.00 8.35 400.80
1' 6" High brass latch
1 1.00 2300.00 2,300.00
6" High brass latch
1 1.00 380.00 380.00
Union Lock
1 1.00 2900.00 2,900.00
Flat iron
item 1,500.00
38,359.86
Transport 5%
0.05 1,917.99
Labour
Frame making
26.00 26.00 110.00 2,860.00
Frame fixing to wall
item 1.00 750.00 750.00
Sash making & fixing
41.90 41.90 450.00 18,853.55
Locks fixing
item 1.00 2500.00 2,500.00
Frame planking
26.00 26.00 10.00 260.00
Sash planking
41.90 41.90 10.00 418.97
25,642.52
65,920.37
Sq.ft. Rate 1,318.41 197.76
D 3 Single sash panelleded door
Size of door
1 4.66 8.83 41.15
Size of frame
0.33 0.41
Sash
0.41 0.13
Material
6"x4" door frame
2 8.83 17.66
2 3.84 7.68
25.34
25.34 458.00 11,605.72
1 3/4" thick timber sash
3.99 8.50 33.94 400.00 13,574.81
25180.53
Wastage 10%
0.1 2518.05
6"x4" Hinges
3 3.00 550.00 1,650.00
1 1/4" screws
3 2 8 48 48.00 8.35 400.80
1' 6" High brass latch
1 1.00 2300.00 2,300.00
6" High brass latch
1 1.00 380.00 380.00
Union Lock
1 1.00 2900.00 2,900.00
Flat iron
item 1,500.00
36,829.38
Transport 5%
0.05 1,841.47
Labour
Frame making
25.34 25.34 110.00 2,787.40
Frame fixing to wall
item 1.00 750.00 750.00
Sash making & fixing
33.94 33.94 450.00 15,271.66
Locks fixing
item 1.00 2500.00 2,500.00
Frame planking
25.34 25.34 10.00 253.40
Sash planking
33.94 33.94 10.00 339.37
21,901.83
60,572.68
Sq.ft. Rate 1,472.08 220.81
W 1 Sliding glazed window
Size of window
1 15.66 10.16 159.11
Size of frame
0.33 0.50
Sash
0.50 0.16
Material
6"x4" window frame
2 10.16 20.32
1 14.66 14.66
2 9.16 18.32
53.30
53.30 458.00 24,411.40
1 3/4" thick timber sash
4 3.67 9.83 144.11 400.00 57,643.12
6mm thick plan glass
4 2.67 8.83 94.13 100.00 9,412.78
91467.30
Wastage 10%
0.1 9146.73
3"x4" Hinges
12 12.00 350.00 4,200.00
1 1/4" screws
12 2 8 192 192.00 8.35 1,603.20
1' 6" High brass latch
3 3.00 2300.00 6,900.00
6" High brass latch
3 3.00 380.00 1,140.00
Flat iron
item 1,500.00
115,957.23
Transport 5%
0.05 5,797.86
Labour
Frame making
53.30 53.30 110.00 5,863.00
Frame fixing to wall
item 1.00 750.00 750.00
Sash making & fixing
144.11 144.11 450.00 64,848.51
Locks fixing
item 1.00 2500.00 2,500.00
Frame planking
53.30 53.30 10.00 533.00
Sash planking
144.11 144.11 10.00 1,441.08
74,494.51
196,249.60
Sq.ft. Rate 1,233.46 185.02
D 4 Single sash plywood door
Size of door
1 3.00 7.00 21.00
Size of frame
0.25 0.50
Sash
0.50 0.13
Material
3"x4" door frame
2 7.00 14.00
1 2.00 2.00
16.00
16.00 214.00 3,424.00
Plywood door
3,600.00 3,600.00
7024.00
Wastage 10%
0.1 702.40
6"x4" Hinges
3 3.00 550.00 1,650.00
1 1/4" screws
3 2 8 48 48.00 8.35 400.80
1' 6" High brass latch
1 1.00 2300.00 2,300.00
Union Lock
1 1.00 2900.00 2,900.00
Flat iron
item 1,500.00
16,477.20
Transport 5%
0.05 823.86
Labour
Frame making
16.00 16.00 100.00 1,600.00
Frame fixing to wall
item 1.00 750.00 750.00
Locks fixing
item 1.00 2500.00 2,500.00
Frame planking
16.00 16.00 10.00 160.00
5,010.00
22,311.06
Sq.ft. Rate 1,062.43 159.36
W 1 Glazed timber window
Size of window
1 6.75 8.50 57.38
Size of frame
0.25 0.33
Sash
0.33 0.16
Material
4"x3" window frame
3 6.75 20.25
4 8.50 34.00
54.25
54.25 205.00 11,121.25
1 1/4" thick timber sash
1 5.75 6.50 37.38
11.50 150.00 1,725.00
6mm thick plan glass
3 1.50 3.67 16.52
3 1.50 2.08 9.36
25.88 100.00 2,587.50
Beading
12 1.50 18.00
6 3.67 22.02
6 2.08 12.48
52.50 1.00 52.50
15486.25
Wastage 10%
0.1 1548.63
Steel gril
27 1.5 40.50 30 1,215.00
3"x4" Hinges
6 6.00 350.00 2,100.00
1 1/4" screws
6 2 4 48 48.00 8.35 400.80
1' 6" High brass latch
3 3.00
6" High brass latch
3 3.00 380.00 1,140.00
Casement stay
3 3.00 380.00 1,140.00
Window Fasterners
3 3.00 325.00 975.00
Window Rings
3 3.00 35.00 105.00
Flat iron
item 1,500.00
25,610.68
Transport 5%
0.05 1,280.53
Labour
Frame making
54.25 54.25 100.00 5,425.00
Frame fixing to wall
item 1.00 1000.00 1,000.00
Sash making & fixing
11.50 11.50 225.00 2,587.50
Locks fixing
item 1.00 2500.00 2,500.00
Frame planking
54.25 54.25 10.00 542.50
Sash planking
11.50 11.50 10.00 115.00
12,170.00
39,061.21
Sq.ft. Rate 680.81 102.12
Paimting
88.00
768.81
OH 18%
907.19
Amount
with profit
1,364.98
1,516.17
1,692.89
1,418.47
1,221.80
782.93
Doors Windows
Item Discription Qty Unit Rate Amount
Specification:
Materil
Frame -Teak
Frame 6" x4" 1.00 L.ft 1,100.00
4" x3" 1.00 L.ft 720.00
Sash -Mahoganie
Sash 1 1/2"
thick
1.00 Sq.ft 1,200.00
1 1/4"
thick
1.00 Sq.ft 1,000.00
1 3/4" thick 1.00 Sq.ft
3' 0" x 7' 0" plywood door 1.00 Nos 3,600.00
Glass - clear
6mm thick Sand blast glass 1.00 Sq.ft 215.00
3mm thick 1.00 Sq.ft
Iron mongery -Brass
6"x4" Hinges 1.00 Nos 550.00
4"x3" Hinges 1.00 Nos 350.00
1 1/4" screws 1.00 Nos 8.35
1' 6" High brass barolt bolt 1.00 Nos 2,300.00
6" High brass barolt bolt 1.00 Nos 380.00
Union Lock Good quality 1.00 Nos 6,900.00
Union Lock Normal 1.00 Nos 2,900.00
Casement stay 1.00 Nos 380.00
Window Fasterners 1.00 Nos 325.00
Window Rings 1.00 Nos 35.00
Hold past 1.00 Item 1,500.00
429/818
Doors Windows
Item Discription Qty Unit Rate Amount
Wood Seasion
1' 0" x 1' 0" x 1' 0" 1.00 Cu.ft 263.20
Wood Painting
Wood treatment 1.00 Sq.ft 20.00
Water base 1.00 Sq.ft 88.00
Spray paint 1.00 Sq.ft 88.00
Labour
Frame making 6" x 4" 1.00 L.ft 110.00
4" x 3" 1.00 L.ft 100.00
Sash making
Solid timber With louver
1.00 Sq.ft 500.00
Solid timber "v" grove
panel
1.00 Sq.ft 450.00
Timber / glass 1.00 Sq.ft 225.00
frame planking 1.00 L.ft 10.00
Sash planking 1.00 Sq.ft 10.00
Frame fixing to wall -
small
1.00 Nos 750.00
Frame fixing to wall -big
1.00 Nos 1,000.00
Lock and ironmongary
fixing
2,500.00
D1 Timber panel door
Size of door 4.00 8.50 34.00
Size of frame 0.44 0.25
Sash 0.33 0.15
Material
5"x3" door frame 1 5.50 5.50
3 8.50 25.50
31.00 31.00 L.ft 1,100.00 34,100.00
Sash area 1 1/4" Timber panel 3.00 8.25 24.75 24.75 Sq.ft 1,000.00 24,750.00
Wastage 10%
Wood treatment 10%
Transport 10%
3"x4" Hinges 5 5.00 Nos 350.00 1,750.00
1 1/4" screws 5 2 8 80 80.00 Nos 8.35 668.00
430/818
Doors Windows
Item Discription Qty Unit Rate Amount
Hold past
1,500.00
Labour
Labour
Frame Planking 31.00 L.ft 10.00 310.00
Sash Planking 24.75 Sq.ft 10.00 247.50
Frame making 31.00 L.ft 100.00 3,100.00
Sash making 24.75 Sq.ft 450.00 11,137.50
Frame fixing to wall 1.00 Nos 1,000.00 1,000.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
Water base paint
Total cost
Total cost for 1 Sq.ft
D2 Timber panel door
Size of door 3.00 7.00 21.00
Size of frame 0.44 0.25
Sash 0.33 0.15
Material
4"x3" door frame 1 4.50 4.50
2 7.00 14.00
18.50 18.50 L.ft 720.00 13,320.00
Sash area 1 1/4" Timber panel
3.00 6.75 20.25 20.25 Sq.ft 1,000.00 20,250.00
Wastage 10%
Wood treatment 5%
Transport 10%
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past
1,500.00
Labour
Frame Planking 18.50 L.ft 10.00 185.00
Sash Planking 20.25 Sq.ft 10.00 202.50
431/818
Doors Windows
Item Discription Qty Unit Rate Amount
Frame making 18.50 L.ft 100.00 1,850.00
Sash making 20.25 Sq.ft 450.00 9,112.50
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
Water base paint
Total cost
Total cost for 1 Sq.ft
D3
Louver door with Timber
Frame & Fixed Glass above
Size of door 3.00 7.00 21.00
Size of frame 0.33 0.25
Sash 0.33 0.15
Size of Fixed glass 3.00 1.50
Size of frame 0.33 0.25
Material
4"x3" door frame 1 4.50 4.50
2 7.00 14.00
4"x3" Fixed glass frame 2 4.50 9.00
2 1.50 3.00
30.50 30.50 L.ft 720.00 21,960.00
Sash area 2.50 6.75 16.88
Timber for sash 2 6.5 0.25 3.25
1 2.5 0.25 0.63
1 2.5 0.75 1.88 5.75 Sq.ft 1,000.00 5,750.00
2" x 1/2" timber horizontals
fixed to sash (on both sides) 4.00 26.00 0.83 0.17 14.67 Sq.ft 1,000.00 14,674.40
6mm thick Sand blast glass
2.50 1.00 2.50 2.50 Sq.ft 215.00 537.50
Wastage 10%
Wood treatment 5.%
Transport 10%
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past
1,500.00
Labour
432/818
Doors Windows
Item Discription Qty Unit Rate Amount
Frame Planking 30.50 L.ft 10.00 305.00
Sash Planking 20.42 Sq.ft 10.00 204.24
Frame making 30.50 L.ft 100.00 3,050.00
Sash making 16.88 Sq.ft 500.00 8,437.50
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
Water base paint
Total cost
Total cost for 1 Sq.ft
D4
Timber panel door with
Timber Frame & Fixed Glass
above
Size of door 2.75 7.00 19.25
Size of frame 0.44 0.25
Sash 0.33 0.15
Size of Fixed glass 2.75 1.50
Size of frame 0.33 0.25
Material
4"x3" door frame 1 4.25 4.25
2 7.00 14.00
4"x3" Fixed glass frame 2 4.25 8.50
2 1.50 3.00
29.75 29.75 L.ft 720.00 21,420.00
Sash area 1 1/4" Timber panel 3.00 6.75 20.25 20.25 Sq.ft 1,000.00 20,250.00
6mm thick Sand blast glass
2.25 1.00 2.25 2.25 Sq.ft 215.00 483.75
Wastage 10%
Wood treatment 5%
Transport 10%
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past
1,500.00
Labour
Frame Planking 29.75 L.ft 10.00 297.50
Sash Planking 20.25 Sq.ft 10.00 202.50
Frame making 29.75 L.ft 100.00 2,975.00
433/818
Doors Windows
Item Discription Qty Unit Rate Amount
Sash making 20.25 Sq.ft 450.00 9,112.50
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
Water base paint
Total cost
Total cost for 1 Sq.ft
D5
Door with Milky White fixed
glass
Size of door 3.00 10.00 30.00
Size of frame 0.42 0.25
Sash 0.33 0.15
Material
5"x3" door frame 1 4.50 4.50
2 10.00 20.00
24.50 24.50 L.ft 720.00 17,640.00
Sash area 2.50 9.75 24.38
Glass Area 4 1.84 1.92 14.13
Timber for sash 10.24 Sq.ft 1,000.00 10,243.80
6mm thick Sand blast glass 14.13 Sq.ft 215.00 3,038.21
Wastage 10%
Wood treatment 5%
Transport 10%
3"x4" Hinges 5 5.00 Nos 350.00 1,750.00
1 1/4" screws 5 2 8 80 80.00 Nos 8.35 668.00
Hold past
1,500.00
Labour
Frame Planking 24.50 L.ft 10.00 245.00
Sash Planking 10.24 Sq.ft 10.00 102.44
Frame making 24.50 L.ft 100.00 2,450.00
Sash making 10.24 Sq.ft 450.00 4,609.71
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
434/818
Doors Windows
Item Discription Qty Unit Rate Amount
Water base paint
Total cost
Total cost for 1 Sq.ft
W1
Louver window with timber
frame
Size of window 3.00 3.00 9.00
Size of frame 0.33 0.25
Sash 0.33 0.15
Material
4"x3" window frame 2 4.50 9.00
2 3.00 6.00
15.00 15.00 L.ft 720.00 10,800.00
Sash area 2.50 2.50 6.25
Louver Area 1.18 1.84 2.17
Timber for sash 4.08 Sq.ft 1,000.00 4,078.80
2" x 1/2" timber horizontals
fixed to sash (on both sides)
2 2.17 4.34 Sq.ft 1,000.00 4,342.40
Wastage 10% 0.1
Wood treatment 5% 0.05
Transport 10%
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past
1,500.00
Labour
Labour
Frame Planking 15.00 L.ft 10.00 150.00
Sash Planking 8.42 Sq.ft 10.00 84.21
Frame making 15.00 L.ft 100.00 1,500.00
Sash making 8.42 Sq.ft 450.00 3,789.54
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
Water base paint
Total cost
435/818
Doors Windows
Item Discription Qty Unit Rate Amount
Total cost for 1 Sq.ft
W1
Louver window with timber
frame & Fixed Glass above
Size of window 2.75 4.25 11.69 Sq ft
Size of frame 0.33 0.25
Sash 0.33 0.15
Size of Fixed glass 2.75 1.50
Size of frame 0.33 0.25
Material
4"x3" window frame 2 4.25 8.50
2 4.25 8.50
4"x3" Fixed glass frame 2 4.25 8.50
2 1.50 3.00
28.50 28.50 L.ft 720.00 20,520.00
Sash area 2.25 3.75 8.44
Timber for sash 2 1.75 0.25 0.88
3 3.25 0.25 2.44 3.31 Sq.ft 1,000.00 3,312.50
2" x 1/2" timber horizontals
fixed to sash (on both sides) 4 16.00 0.67 0.18 7.72 Sq.ft 1,000.00 7,718.40
6mm thick Sand blast glass
2.25 1.00 2.25 2.25 Sq.ft 215.00 483.75
Wastage 10% 0.1
Wood treatment 5% 0.05
Transport 10%
3"x4" Hinges 4 4.00 Nos 350.00 1,400.00
1 1/4" screws 4 2 8 64 64.00 Nos 8.35 534.40
Hold past
1,500.00
Labour
Frame Planking 28.50 L.ft 10.00 285.00
Sash Planking 11.03 Sq.ft 10.00 110.31
Frame making 28.50 L.ft 100.00 2,850.00
Sash making 9.97 Sq.ft 450.00 4,485.78
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
Water base paint
436/818
Doors Windows
Item Discription Qty Unit Rate Amount
Total cost
Total cost for 1 Sq.ft
Louver window with timber
frame (Water tank room
door)
Size of window 2.83 2.58 7.30
Size of frame 0.33 0.25
Sash 0.33 0.15
Material
4"x3" window frame 2 4.33 8.66
2 2.58 5.16
13.82 13.82 L.ft 720.00 9,950.40
Sash area 2.33 2.08 4.85
Louver Area 1.01 1.42 1.43
Timber for sash 1.98 Sq.ft 1,000.00 1,978.00
2" x 1/2" timber horizontals
fixed to sash (on both sides)
2 1.43 2.87 Sq.ft 1,000.00 2,868.40
Wastage 10% 0.1
Wood treatment 5% 0.05
Transport 10%
3"x4" Hinges 2 2.00 Nos 350.00 700.00
1 1/4" screws 2 2 8 32 32.00 Nos 8.35 267.20
Hold past
1,500.00
Labour
Labour
Frame Planking 13.82 L.ft 10.00 138.20
Sash Planking 4.85 Sq.ft 10.00 48.46
Frame making 13.82 L.ft 100.00 1,382.00
Sash making 4.85 Sq.ft 450.00 2,180.88
Frame fixing to wall 1.00 Nos 750.00 750.00
Locks & ironmongary fixing item 2,500.00
Tools 3%
437/818
Doors Windows
Item Discription Qty Unit Rate Amount
Water base paint
Total cost
Total cost for 1 Sq.ft
438/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
15%
439/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
Sq ft
58,850.00
5,885.00
2,942.50
5,885.00
3'-0"
1
0
'
-
0
"

440/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
3,918.00
18,295.00
548.85
96,324.35
2,833.07 424.96 ####
Sq ft
33,570.00
3,357.00
1,678.50
3,357.00
3,434.40
3'-0"
7
'
-
0
"

441/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
14,600.00
438.00
60,434.90
2,877.85 431.68 ####
Sq ft
42,921.90
4,292.19
2,146.10
4,292.19
3,434.40
3'-0"
7
'
-
0
"

442/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
15,246.74
457.40
72,790.92
3,466.23 519.94 ####
Sq ft
42,153.75
4,215.38
2,107.69
4,215.38
3,434.40
3'-0"
7
'
-
0
"

443/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
15,837.50
475.13
72,439.21
3,763.08 564.46 ####
Sq ft
30,922.01
3,092.20
1,546.10
3,092.20
3,918.00
10,657.15
319.71
3'-0"
1
0
'
-
0
"

444/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
53,547.37
1,784.91 267.74 ####
Sq ft
19,221.20
1,922.12
961.06
1,922.12
3,434.40
8,773.75
263.21
36,497.86
4'-6"
3
'
-
0
"

445/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
4,055.32 608.30 ####
32,034.65
3,203.47
1,601.73
3,203.47
3,434.40
10,981.09
329.43
2.75
4
'
-
3
"

446/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
54,788.23
4,687.76 703.16 ####
Sq ft
14,796.80
1,479.68
739.84
1,479.68
2,467.20
6,999.54
209.99
2.75
4
'
-
3
"

447/818
Doors Windows
Amount
O/H &
Profit
Amount
with
profit
28,172.73
3,858.54 578.78 ####
448/818
TYPE OF ROOF / ROOF PLUMBING / CANOPIES
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
15%
1
1 Asbestos roof with exposed rafters
and lunumiddala ceiling. Rate include
to tar sheet and insulation
( Roof timber is bigger than in normal
size )
Consider 15.34 Sqr
Materials
Frame work
Red balaw timber
4''x8'' Ridge plate 48.00 L.ft 665.00 31,920.00
4''X6'' Purling 213.50 L.ft 458.00 97,783.00
3''X6'' Rafter 962.51 L.ft 285.00 274,315.35
2''X2'' Runers 501.50 L.ft 55.00 27,582.50
431,600.85
Wastage 10% of timber 10% 43,160.09
Wood preservative 181 Cu.ft 263.00 47,510.27
Nails & screws 15 kg 160.00 2,400.00
49,910.27
Roof Covering
TIMBER ROOF
Main Index
Asbestors Roof covering 15.34 Sqr 3,510.42 53,849.79
Wastage 10% of roof covering 10% 5,384.98
J bolts 300 No 5.00 1,500.00
60,734.77
Timber ceiling
6" thick Lunumidella plank 15.34 Sqr 5,600.00 85,904.00
Wastage 20% of timber ceiling 20% 17,180.80
Wood preservative 767 Cu.ft 263.00 201,721.00
304,805.80
Tar sheet 15.34 Sqr 1,000.00 15,340.00
Mackfoil 5mm double side 15.34 Sqr 1,775.09 27,229.93 42,569.93
Wastage 10% 10% 4,256.99
937,038.69
Transport 10% 10% 93,703.87
Labour
Planking charges for frame work 1,726 L.ft 10.00 17,255.10
Planking charges for timber ceiling 1534 Sqr 10.00 15,340.00
labour 15.34 Sqr 15,000.00 230,100.00
262,695.10
Add for tools 3% of labour 3% 6,903.00
Add for scaffolding 5% of labour 5% 11,505.00
1,311,845.66
85,517.97 12,827.70 98,345.67
Preliminaries 10% 131,184.57
Cost per 15.34 Sqs 1,443,030.23
Cost per 1 Sqs 94,069.77 14,110.47 108,180.23
2 Asbestos roof with exposed rafters
and lunumiddala ceiling.
Red balaw timber
Materials
Frame work
3''x 6'' Ridge plate 35.00 L.ft 285.00 9,975.00
3''x 6'' wall plate 70.00 L.ft 285.00 19,950.00
3" x 5" beam 42.00 L.ft 290.00 12,180.00
2" x 6" support 7.50 L.ft 214.00 1,605.00
2 ''x 4'' Rafter 369 L.ft 135.50 49,999.50
2''x 2'' Runers 210.00 L.ft 55.00 11,550.00
105,259.50
Wastage 10% of timber 10% 10,525.95
Wood preservative 45 Cu.ft 263.00 11,819.85
Nails & screws 10 kg 160.00 1,600.00
13,419.85
Roof Covering
Asbestors Roof covering 7.21 Sqr 3,510.42 25,310.10
Wastage 10% of roof covering 10% 2,531.01
J bolts 300 No 5.00 1,500.00
29,341.11
Timber ceiling
6" thick Lunumidella plank 7.21 Sqr 5,600.00 40,376.00
Wastage 20% of timber ceiling 20% 8,075.20
Wood preservative 360.50 Cu.ft 263.00 94,811.50
143,262.70
Labour
Planking charges for frame work 733.50 L.ft 10.00 7,335.00
labour 7.21 Sqr 11,000.00 79,310.00
86,645.00
ADD
Add for tools 3% of labour 3% 2,379.30
Add for scaffolding 5% of labour 5% 3,965.50
394,798.92
54,757.13 8,213.57 62,970.70
Preliminaries 10% 39,479.89
Cost for 7.21 Sqr 434,278.81
Cost per 1 Sqs 60,232.84 9,034.93 69,267.77
3 Asbestos roof with exposed rafters
and lunumiddala ceiling.
( Small structure timber roof )
Tholang timber Consider 600 Sq ft
Material
Frame work
3" x 4" wall plate 52.00 L ft 183.00 9,516.00
2" x 7" ridge plate 25.00 L ft 215.00 5,375.00
2" x 4" Rafters 360.00 L ft 123.50 44,460.00
2" x 2" reepers 150.00 L ft 49.00 7,350.00
66,701.00
ADD 5% wastage 5% 3,335.05
Wood preservative 31.29 Cu.ft 263.00 8,228.22
48.00 Cu.ft 263.00 12,624.00
Nails & screws 8 kg 160.00 1,280.00
22,132.22
ADD 5% wastage 5% 1,106.61
Roof Covering
Asbestos sheet (12' 0" long) 600.00 Sq ft 35.10 21,062.50
J bolts 120.00 no 5.00 600.00
Tar sheet 600.00 Sq ft 10.00 6,000.00
27,662.50
ADD 5% wastage 5% 1,383.13
Timber ceiling
6" thick Lunumidella plank 600.00 Sq ft 56.00 33,600.00 33,600.00
Wastage 20% of timber ceiling 20% 6,720.00
Labour
Labour charges 600.00 Sq ft 110.00 66,000.00
66,000.00
Add for tools 3% of labour 3% 1,980.00
Add for scaffolding 5% of labour 5% 3,300.00
233,920.50
38,986.75 5,848.01 44,834.76
Preliminaries 10% 23,392.05
Cost for 6 Sqr 257,312.55
Cost for 1 Sqr 42,885.43 6,432.81 49,318.24
4 Asbestos sheet roof with exposed
rafters, plywood sloping ceiling and
asbestos sheet covered by half round
tile
Tholang timber Consider 270 Sq ft
Material
Frame work
3" x 4" Wall plate 36.00 L.ft 183.00 6,588.00
2" x 5" Ridge Plate 18.00 L.ft 163.50 2,943.00
2" x 4" rafters 300.00 L.ft 123.50 37,050.00
46,581.00
Wastage 5% 5% 2,329.05
Slooping Ceiling
Asbestos sheet 270.00 Sq.ft 34.38 9,281.25 9,281.25
Wastage 5% 5% 464.06
Roof covering
Plywood sheet (9mm) 9.00 No 2,675.00 24,075.00
Nails and screws 5.00 Kg 160.00 800.00
24,875.00
Wastage 5% 5% 1,243.75
Half round tile covering
Half round tile 1,215 No 18.00 21,870.00 21,870.00
Wastage 5% 5% 1,093.50
Labour
Carpenter 2.00 Day 950.00 1,900.00
For tile cover 2.00 Day 650.00 1,300.00
3,200.00
Add for tools 3% of labour 3% 96.00
Add for scaffolding 5% of labour 5% 160.00
111,193.61
41,182.82 6,177.42 47,360.24
Preliminaries 10% 11,119.36
122,312.97
Cost for 1 sqr 45,301.10 6,795.17 52,096.27
5 Asbestos roof with frame work.
Tholang timber
Consider 13.43 Sqr (49.5' x 27')
Materal
Frame work
4" X 2" Rafters 810.00 L.ft 123.50 100,035.00
4" x 3" wall plate 97.50 L.ft 183.00 17,842.50
6" x 3" purlin 146.25 L.ft 260.00 38,025.00
5" x 5" props 25.40 L.ft 410.00 10,414.00
2" x 2" reepers 250.00 L.ft 49.00 12,250.00
178,566.50
wastage 10% 5% 8,928.33
Transport 7% 7% 12,499.66
Wood Presavative 86.45 Cu.ft 263.00 22,736.97
Nails & screws 14.00 Kg 160.00 2,240.00
Roof covering 72,607.83
Asbestos sheet 1,316.25 Sq.ft 35.10 46,205.86
J bolts 285.00 No 5.00 1,425.00
Labour
Planing charges 1,079.15 L.ft 10.00 10,791.50
Skilled labour 8.00 Day 950.00 7,600.00
Un / sk labour 15.00 Day 650.00 9,750.00
17,350.00
Add for tools 3% of labour 3% 520.50
Add for scaffolding 5% of labour 5% 867.50
302,131.81
22,496.78 3,374.52 25,871.30
Preliminaries 10% 30,213.18
332,345.00
Cost for 1 Sqr (without polish) 24,746.46 3,711.97 28,458.43
6 Half round tile laying on asbestos
roof 137.81
( for two layer )
Consider 1 Sqr
Material
Half round tile 450 Nos 20.00 9,000.00
Wastage 10% 10% 900.00
Transport 10% 10% 900.00
10,800.00
Labour
Skilled labour 1 Day 950.00 950.00
Unskilled labour 1 Day 650.00 650.00
1,600.00
Add for tools 3% of labour 3% 48.00
Add for scaffolding 5% of labour 5% 80.00
12,528.00 1,879.20 14,407.20
Preliminaries
10% 1,252.80
Cost for 1 Sqr 13,780.80 2,067.12 15,847.92
7 Two layers on either side of ridge
For 10 L.ft
Materials
Half round tile (Double layer) 50 Nos 18.00 900.00
Transport 7% 63.00 963.00
Labour
Un/sk labour 0.1 Day 650.00 65.00
Add 3% Tools 1.95
add 5% Scaffolding 3.25 70.20
1,033.20
103.32 15.50 118.82
Priliminary 10% 103.32
1,136.52
Cost for 1 L.ft 113.65 17.05 130.70
8
Asbestos roof without frame work
Consider 102.4Sqr
Materal
Asbestos sheet 10,240 Sq.ft 35.10 359,466.67
Wastage 10% 10% 35,946.67
Transport 7% 7% 25,162.67 420,576.00
Nails & screws 106 Kg 160.00 16,960.00
J bolts 2,173 No 5.00 10,865.00
27,825.00
Labour
Labour 20% 89,680.20
Add for tools 3% of labour 3% 2,690.41
Add for scaffolding 5% of labour 5% 4,484.01
96,854.62
Total Cost for 102.4 Sqr 545,255.62
5,324.76 798.71 6,123.48
Priliminary 10% 54,525.56
599,781.18
Cost for 1 Sqr 5,857.24 878.59 6,735.82
9 Asbastos ajestable close fitting ridge
fixed complete with roofing screws or
bolts
Materials
Ridge 4.00 pair 45.00 180.00
Roofing screws 16.00 no 15.00 240.00
420.00
Labour
S/k labourer 0.25 day 950.00 237.50
Un/skilled Labour 0.25 day 650.00 162.50
400.00
Tools 3% 12.00
Scaffolding 5% 20.00
852.00
85.20 12.78 97.98
Priliminary 10% 85.20
937.20
Cost for 1 L.ft 93.72 14.06 107.78
Tholang timber
Consider 10.60 Sqr (44.2' x 12')*2
Materal
Frame work
4" X 2" Rafters 744.00 L.ft 123.50 91,884.00
4" x 3" wall plate 80.00 L.ft 183.00 14,640.00
4" x 2" colour tile 36.00 L.ft 260.00 9,360.00
2" x 2" reepers 1,408.00 L.ft 55.00 77,440.00
193,324.00
wastage 10% 5% 9,666.20
Transport 7% 7% 13,532.68
Wood Presavative 63.03 Cu.ft 263.00 16,576.00
Nails & screws 14.00 Kg 160.00 2,240.00
18,816.00
Roof covering
Asbestos sheet 742.00 Sq.ft 90.00 66,780.00
J bolts No 5.00 -
66,780.00
Timber ceiling
6" thick Lunumidella plank 1060.00 Sq ft 56.00 59,360.00 59,360.00
Wastage 20% of timber ceiling 30% 17,808.00
Labour
Planing charges 860.00 L.ft 10.00 8,600.00
Skilled labour Day -
Un / sk labour 1,060.00 Day 120.00 127,200.00
127,200.00
Add for tools 3% of labour 3% 3,816.00
Add for scaffolding 5% of labour 5% 6,360.00
525,262.88
49,553.10 7,432.97 56,986.07
Preliminaries 20% 105,052.58
630,315.45
Cost for 1 Sqr (without polish) 59,463.72 8,919.56 68,383.28
4 Asbestos sheet roof with exposed
rafters, plywood sloping ceiling and
asbestos sheet covered by half round
tile
Tholang timber Consider 270 Sq ft
Material
Frame work
3" x 4" Wall plate 36.00 L.ft 183.00 6,588.00
2" x 5" Ridge Plate 18.00 L.ft 163.50 2,943.00
2" x 4" rafters 300.00 L.ft 123.50 37,050.00
46,581.00
Wastage 5% 5% 2,329.05
Slooping Ceiling
Asbestos sheet 270.00 Sq.ft 34.38 9,281.25 9,281.25
Wastage 5% 5% 464.06
Roof covering
Asbestos sheet 17.00 No 380.00 6,460.00
Nails and screws 5.00 Kg 160.00 800.00
7,260.00
Wastage 5% 5% 363.00
Half round tile covering
Half round tile 1,215 No - - -
Wastage 5% 5% -
Labour
Playing charges 300.00 L.ft 10.00 3,000.00
Carpenter 5.00 Day 950.00 4,750.00
For tile cover 5.00 Day 650.00 3,250.00
11,000.00
Add for tools 3% of labour 3% 330.00
Add for scaffolding 5% of labour 5% 550.00
78,158.36
28,947.54 4,342.13 33,289.67
Preliminaries 20% 15,631.67
93,790.04
Cost for 1 sqr 34,737.05 5,210.56 39,947.61
2
1 Zn/Al roof fix to "c" purlin ( Purlin
measured separatly )
Consider 1 m2
Materials
Zn/Al sheet
1.00 m2 970.31 970.31
Add - Lap and wastage 3%
29.11
Add - 10% trance port 97.03
Allow sum for serwes
3.00 Nos 8.35 25.05
Allow sum for bolt & nuts
1.00 Nos 50.00 50.00
1,171.50
Labour
Sk labour
0.25 day 950.00 237.50
U/sk labour
0.25 day 650.00 162.50
400.00
Add
3% of labour cost for tool
12.00
5% of labour cost for scafolding
20.00
ZN / AL ROOF
32.00
1,603.50 240.53 1,844.03
Preliminaries
160.35
Cost for one 1m2 with preliminaries 1,763.85 264.58 2,028.43
11
Grangular coated Zn/ Al roof
Consider 15 Sqr
Materal
Zn/ Al Sheet 1,500 Sq.ft 106.00 159,000.00
Wastage 10% 10% 15,900.00
Transport 7% 7% 11,130.00 186,030.00
Nails & screws 15.00 Kg 160.00 2,400.00
Bolt 200 No 50.00 10,000.00 12,400.00
Labour
Labour 20% 39,686.00
Add for tools 3% of labour 3% 1,190.58
Add for scaffolding 5% of labour 5% 1,984.30 42,860.88
241,290.88
Total Cost for 1 Sqr 16,086.06 2,412.91 18,498.97
Priliminary 10% 24,129.09
265,419.97
Cost for 1 L.ft 17,694.66 2,654.20 20,348.86
12
Granguler coated Zn/Al Ridge caps
Consider 1 L.ft
Materials
Ridge 1.00 L.ft 135.00 135.00
Roofing screws 16.00 no 15.00 240.00
375.00
Labour
S/k labourer 0.125 day 950.00 118.75
Un/skilled Labour 0.125 day 650.00 81.25
200.00
Tools 3% 6.00
Scaffolding 5% 10.00
591.00 88.65 679.65
Preliminaries
59.10
Cost for one 1m2 with preliminaries 650.10 97.52 747.62
3
1 Upvc Gutter
Assume 40 m
Material
Pvc Guter 40 m 221.64 8,865.75
Running joint 10 no 233.00 2,330.00
Pvc Bracket 89 no 44.00 3,916.00
Nail 360 no 8.35 3,006.00
ROOF PLUMBING
Solvent Cement 100 grm 2.28 228.00
18,345.75
Wastage 5% 917.29
Labur
Sk labour 1.25 Day 950.00 1,187.50
UnSk labour 1.25 Day 650.00 812.50
2,000.00
Scaffolding 5% 100.00
Tools 3% 60.00
21,423.04
535.58 80.34 615.91
Priliminary 10% 2,142.30
23,565.35
Cost per 1 m 589.13 88.37 677.50
2 Upvc Gutter Out let
Material
Upvc Gutter Out let 1 No 554.00 554.00
Pvc Bracket 2 no 44.00 88.00
Nail 30 no 8.35 250.50
Solvent Cement 12 grm 2.28 27.36
919.86
Wastage 5% 45.99
Labur
Sk labour 0.125 Day 950.00 118.75
UnSk labour 0.125 Day 650.00 81.25 200.00
Scaffolding 5% 10.00
Tools 3% 6.00
1,181.85 177.28 1,359.13
Priliminary 10% 118.19
1,300.04 195.01 1,495.04
3 Upvc Down pipe
Assume 40 m
Material
Pvc Down pipe 40 m 215.89 8,635.62
Running joint 10 no 233.00 2,330.00
Pvc Bracket 89 no 44.00 3,916.00
Nail 360 no 8.35 3,006.00
Solvent Cement 100 grm 2.28 228.00
18,115.62
Wastage 5% 905.78
Labur
Sk labour 1.25 Day 950.00 1,187.50
UnSk labour 1.25 Day 650.00 812.50 2,000.00
Scaffolding 5% 100.00
Tools 3% 60.00
21,181.40
529.53 79.43 608.97
Priliminary 10% 2,118.14
23,299.54
582.49 87.37 669.86
4 Rain water gutter (Cupper)
Assume 40 L.ft
Material
Copper Gutter 40.00 L ft 4,500.00 180,000.00
Wastage 5% 5% 9,000.00
189,000.00
Labour
Skilled 0.25 day 950.00 237.50
Un skilled 0.25 day 650.00 162.50
400.00
Tools 3% 3% 12.00
Scaffolding 5% 5% 20.00
189,432.00
4,735.80 710.37 5,446.17
Priliminary 10% 18,943.20
208,375.20
5,209.38 781.41 5,990.79
5 Zn/Al flashing for roof end ( front
side )
Assume 10 L.ft
Material
Flashing ( 2'- 2" ) 10.00 L.ft 180.00 1,800.00
Screws 100.00 1,900.00
Wastage 5% 190.00
Labour
Sklled 0.30 Hrs 118.75 35.63
Un skilled 0.30 Hrs 81.25 24.38
60.00
Tools 3% 3% 1.80
Scaffolding 5% 5% 3.00
2,154.80
215.48 32.32 247.80
Priliminary 10% 215.48
2,370.28
237.03 35.55 272.58
5 Zn/Al gutter
Assume 10 L.ft
Material
Flashing ( 2'- 2" ) 10.00 L.ft 157.00 1,570.00
Gutter bracket 6.00 Nr 10.00
Screws 100.00 1,670.00
Wastage 5% 167.00
Transport 3% 50.10
Labour
Sklled 0.30 Hrs 118.75 35.63
Un skilled 0.30 Hrs 81.25 24.38
60.00
Tools 3% 3% 1.80
Scaffolding 5% 5% 3.00
1,951.90
195.19 29.28 224.47
Priliminary 10% 195.19
2,147.09
214.71 32.21 246.92
4
1 Sisalation domestic 100
Assume 1 Sqr
Material
Sisilation domestic 100 1 sqr 1,288.00 1,288.00
Wastage 5% 64.40
Transport 7% 90.16 1,442.56
Labour
Un skilled 1 Day 650.00 650.00
Tools 3% 19.50
Scaffolding 5% 32.50 702.00
Cost for 1 Sqr 2,144.56 321.68 2,466.24
Priliminary 10% 214.46
2,359.02 353.85 2,712.87
Cost for 1 L.ft
HEAT SOLUTION
4 5mm thick double side Macfoil
(double side Al foil with 18 GI mesh
laid over 50x50mm battens )
Consider 5.0 Sqr 5 Sqr
Materal
5mm thick double side Macfoil 500 Sq.ft 26.50 13,250.00
18 GI mesh 500 Sq.ft 6.70 3,350.00
Nail 3 Kg 160.00 480.00
17,080.00
Labour
Skilled labour 2.00 Day 950.00 1,900.00
Un / sk labour 2.50 Day 650.00 1,625.00
3,525.00
Add for tools 3% of labour 3% 105.75
Add for scaffolding 5% of labour 5% 176.25
20,887.00
Total Cost for 1 Sqr 4,177.40 626.61 4,804.01
Priliminary 10% 2,088.70
22,975.70
Cost for 1 L.ft 4,595.14 689.27 5,284.41
Tempered Glass Canopy
Consider 13'-0" x 8'-6" (110.5 Sq.ft)
Material
"U' chanel 2 Length 7,000.00 14,000.00
11/2" x11/2" box bars 7 Nos 1,825.00 12,775.00
Tempered glass 113 Sq.ft 700.00 79,100.00
Weding rods 1 Item 1,500.00
Plate 1.34 Sq.ft 325.00 435.50
Anchor bolt 16 Nos 350.00 5,600.00
Silican gum 8 Nos 250.00 2,000.00
Flashing 33 L.ft 275.00 9,075.00
124,485.50
Transport 5% 6,224.28
Labour
Sk 2 Days 950.00 1,900.00
Un/sk 2 Days 650.00 1,300.00
3,200.00
Small tools 3% 3% 96.00
Scafolding 5% 5% 160.00
134,165.78
O/H and profit 25% 25% 33,541.44
Cost without paint 167,707.22
Allow sum for anticorosive paint 5,000.00
Cost with paint 172,707.22
Ex.38 Placing Acrylic Sheet above Pergolas
Material
Acrylic sheet (Polycarbonate) 3mm
thick
45.00 Sqft 150.00 6,750.00
3" x 2" Timber Pergolas -Teak 33.75 L.ft 175.00 5,906.25 12,656.25
Transport 10% 1,265.63
Wastage 10% 1,265.63
Labour
skilled 2.00 day 950.00 1,900.00
Un skilled 1.00 day 650.00 650.00 2,550.00
Tools 3% 76.50
17,814.00
O/H & Profit 25% 4,453.50
Total Cost 22,267.50
Calicut pattern tile hip roof in single
storey building consisting of wall
plate ridge plate beam struct rafters
& reepers. 1 Sqr 43,873.32
Materials
Class 1 Timber 5.55 c.ft 3,240.00 17,982.00
Wastage 5% 899.10
Reepers 2" x 2" 110.00 l.ft 55.00 6,050.00
Wire nails 1.50 kg 160.00 240.00
Calicut tiles 70.00 no 95.00 6,650.00
Woodpreservitive 1.50 liter 388.00 582.00
32,403.10
Labour
Mason 2.00 day 950.00 1,900.00
Un/skilled Labour 3.00 day 650.00 1,950.00
3,850.00
Add
Tools 3% of labour Cost for tools 115.50
Scaffolding 5% of labour Cost for
scaffolding
192.50
36,561.10
Preliminaries 7,312.22
Cost for 1 Sqr with Preliminaries 43,873.32
ROOF TIMBER COST SEPERATLY
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
TIMBER ROOF FRAME WORK
1 Treated "Kempas" 2"x2" battens
Assumed 3806 L.ft
Material
2"x2" Battens 3,806.00 L.ft 65.00 247,390.00
Wastage 5% 12,369.50
Transport 10% 24,739.00
Wood treatment 3,806.00 L.ft 7.09 26,984.54 311,483.04
Labour
Planking charges 3,806.00 L.ft 10.00 38,060.00
Labour 18% 56,066.95 94,126.95
405,609.99
106.57 15.99 122.56
Priliminary 10% 40,561.00
446,170.99
Cost for 1 L.ft 117.23 17.58 134.81
2 Treated "Kempas" 2"x1" battens
Main Index
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Assumed 547L.ft
Material
2"x1" Battens 547.00 L.ft 28.00 15,316.00
Wastage 5% 765.80
Transport 10% 1,531.60
Wood treatment 547.00 L.ft 3.54 1,936.38 19,549.78
Labour
Planking charges 547.00 L.ft 10.00 5,470.00
Labour 18% 3,518.96 8,988.96
28,538.74
52.17 7.83 60.00
Priliminary 10% 2,853.87
31,392.61
Cost for 1 L.ft 57.39 8.61 66.00
3 Treated "Balaw" 1 1/4"x2 1/2" sealing member
Assumed 651 L.ft
Material
1 1/4"x2 1/2" sealing member 651.00 L.ft 135.50 88,210.50
Wastage 5% 4,410.53
Transport 10% 8,821.05
Wood treatment 651.00 L.ft 10.63 6,920.13 108,362.21
Labour
Planking charges 651.00 L.ft 10.00 6,510.00
Labour 18% 19,505.20 26,015.20
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
134,377.40
206.42 30.96 237.38
Priliminary 10% 13,437.74
147,815.14
Cost for 1 L.ft 227.06 34.06 261.12
4 Treated "Balaw" 4" x 2" collers
Assumed 590 L.ft
Material
4" x 2" collers 590.00 L.ft 135.50 79,945.00
Wastage 5% 3,997.25
Transport 10% 7,994.50
Wood treatment 590.00 L.ft 14.17 8,360.30 100,297.05
Labour
Planking charges 590.00 L.ft 10.00 5,900.00
Labour 18% 18,053.47 23,953.47
124,250.52
210.59 31.59 242.18
Priliminary 10% 12,425.05
136,675.57
Cost for 1 L.ft 231.65 34.75 266.40
5 Treated "Balaw"4" x 3" wall plate / ridge plate
Assumed 509 L.ft
Material
4" x 3" wall plate 509.00 L.ft 214.00 108,926.00
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Wastage 5% 5,446.30
Transport 10% 10,892.60
Wood treatment 509.00 L.ft 21.26 10,821.34 136,086.24
Labour
Planking charges 509.00 L.ft 10.00 5,090.00
Labour 18% 24,495.52 29,585.52
165,671.76
325.48 48.82 374.31
Priliminary 10% 16,567.18
182,238.94
Cost for 1 L.ft 358.03 53.70 411.74
6 Treated "Balaw 5" x 2" rafters
Assumed 5820 L.ft
Material
5" x 2" rafters 5,820.00 L.ft 171.50 998,130.00
Wastage 5% 49,906.50
Transport 10% 99,813.00
Wood treatment 5,820.00 L.ft 17.72 103,130.40 1,250,979.90
Labour
Planking charges 5,820.00 L.ft 10.00 58,200.00
Labour 18% 225,176.38 283,376.38
1,534,356.28
263.64 39.55 303.18
Priliminary 10% 153,435.63
1,687,791.91
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Cost for 1 L.ft 290.00 43.50 333.50
7 Treated "Balaw 5" x 4" corble plates
Assumed 110 L.ft
Material
5" x 4" corble plates 110.00 L.ft 458.00 50,380.00
Wastage 5% 2,519.00
Transport 10% 5,038.00
Wood treatment 110.00 L.ft 35.43 3,897.30 61,834.30
Labour
Planking charges 110.00 L.ft 10.00 1,100.00
Labour 18% 11,130.17 12,230.17
74,064.47
673.31 101.00 774.31
Priliminary 10% 7,406.45
81,470.92
Cost for 1 L.ft 740.64 111.10 851.74
8 Treated "Balaw 6" x 4" pole plates
Assumed 335 L.ft
Material
6" x 4" pole plates 335.00 L.ft 458.00 153,430.00
Wastage 5% 7,671.50
Transport 10% 15,343.00
Wood treatment 335.00 L.ft 42.52 14,244.20 190,688.70
Labour
Planking charges 335.00 L.ft 10.00 3,350.00
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Labour 18% 34,323.97 37,673.97
228,362.67
681.68 102.25 783.93
Priliminary 10% 22,836.27
251,198.93
Cost for 1 L.ft 749.85 112.48 862.32
9 Treated "Balaw 7" x 2" hip rafters / Valley rafters
Assumed 145 L.ft
Material
7" x 2" hip rafters 145.00 L.ft 350.00 50,750.00
Wastage 5% 2,537.50
Transport 10% 5,075.00
Wood treatment 145.00 L.ft 24.80 3,596.00 61,958.50
Labour
Planking charges 145.00 L.ft 10.00 1,450.00
Labour 18% 11,152.53 12,602.53
74,561.03
514.21 77.13 591.35
Priliminary 10% 7,456.10
82,017.13
Cost for 1 L.ft 565.64 84.85 650.48
10 Treated "Balaw 8" x 2" ridge plate
Assumed 218 L.ft
Material
8" x 2" ridge plate 218.00 L.ft 350.00 76,300.00
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Wastage 5% 3,815.00
Transport 10% 7,630.00
Wood treatment 218.00 L.ft 28.34 6,178.12 93,923.12
Labour
Planking charges 218.00 L.ft 10.00 2,180.00
Labour 18% 16,906.16 19,086.16
113,009.28
518.39 77.76 596.15
Priliminary 10% 11,300.93
124,310.21
Cost for 1 L.ft 570.23 85.53 655.76
11.0 Treated "Thulan" 7" x 2" ridge plate
Assume 40L.ft
Material
7" x 2" ridge plate 40.00 L.ft 215.00 8,600.00
Wastage 5% 430.00
Transport 10% 860.00
Wood treatment 40.00 L.ft 24.80 992.00 10,882.00
Labour
Planking charges 40.00 L.ft 10.00 400.00
Labour 18% 1,958.76 2,358.76
13,240.76
331.02 49.65 380.67
Priliminary 10% 1,324.08
14,564.84
Cost for 1 L.ft 364.12 54.62 418.74
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
12.0 Treated "Thulan" 4" x 3" Wall plate
Assume 80L.ft
Material
4" x 3" wall plate 80.00 L.ft 183.00 14,640.00
Wastage 5% 732.00
Transport 10% 1,464.00
Wood treatment 80.00 L.ft 21.26 1,700.80 18,536.80
Labour
Planking charges 80.00 L.ft 10.00 800.00
Labour 18% 3,336.62 4,136.62
22,673.42
283.42 42.51 325.93
Priliminary 10% 2,267.34
24,940.77
Cost for 1 L.ft 311.76 46.76 358.52
13.0 Treated "Thulan" 2" x 6" Exposed rafter
Assume 800L.ft
Material
2" x 6" exposed rafter 800.00 L.ft 198.00 158,400.00
Wastage 5% 7,920.00
Transport 10% 15,840.00
Wood treatment 800.00 L.ft 21.26 17,008.00 199,168.00
Labour
Planking charges 800.00 L.ft 10.00 8,000.00
Labour 18% 35,850.24 43,850.24
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
243,018.24
303.77 45.57 349.34
Priliminary 10% 24,301.82
267,320.06
Cost for 1 L.ft 334.15 50.12 384.27
14.0 Treated "Thulan" 2" x 2" Battens
Assume 1300L.ft
Material
2" x 2" battens 1,300.00 L.ft 49.00 63,700.00
Wastage 5% 3,185.00
Transport 10% 6,370.00
Wood treatment 1,300.00 L.ft 7.09 9,217.00 82,472.00
Labour
Planking charges 1,300.00 L.ft 10.00 13,000.00
Labour 18% 14,844.96 27,844.96
110,316.96
84.86 12.73 97.59
Priliminary 10% 11,031.70
121,348.66
Cost for 1 L.ft 93.35 14.00 107.35
SPECIAL FLOOR FINISHES
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
Supply and lay brick paving on
compacted earth with cement sand
motar. Mansoor
Considering 1 Sqr
Material
Brick 360 Nos 7.00 2,520.00
Cement 2.00 bag 740.00 1,480.00
Lime 30.00 kg 14.50 435.00
Sand 0.18 cube 7,500.00 1,350.00
Water 25.00 gal 0.50 12.50
5,797.50
Labour
Skilled 1.50 Day 950.00 1,425.00
Un skilled 1.75 Day 650.00 1,137.50
2,562.50
Add 3% for tools 3% 76.88
8,436.88 1,265.53 9,702.41
Preliminaries
10% 843.69
Main Index
Cost for 1 Sqr 9,280.56 1,392.08 10,672.65
1 Terrazo floor Mansoor
Consider 1 Sqr
Material
Terrazzo mix (6:5)
Terrazzo chips 4.50 cwt 950.00 4,275.00
Cement 3.75 Bags 740.00 2,775.00
Bedding
Cement 1.25 Bags 740.00 925.00
Sand 0.04 Cube 7,500.00 300.00
8,275.00
Transport 10% 10% 827.50
Machine hire 0.50 Day 3,200.00 1,600.00 1,600.00
Labour
Sepicial mason 1.50 Day 950.00 1,425.00
Un skilled 1.50 Day 650.00 975.00
Bedding
Skilled 1.00 Day 950.00 950.00
Un skilled 1.00 Day 650.00 650.00
4,000.00
Add for tools 3% of labour 3% 120.00
14,822.50 2,223.38 17,045.88
Preliminaries
10% 1,482.25
Cost per 1 Sqr 16,304.75 2,445.71 18,750.46
2 Titanium floor Mansoor
Consider 1 Sqr
Maretial
Cement 6.00 Bags 740.00 4,440.00
White cement 3.00 Bags 1,300.00 3,900.00
Sand 0.30 Cube 7,500.00 2,250.00
Titanium 1.50 kg 525.00 787.50
Wax 1.00 Ltr -
Cotton waste 1.00 kg -
11,377.50
Transport 5% 5% 568.88
Machine hire 0.50 Day 3,200.00 1,600.00 1,600.00
Labour
Skilled 2.00 Day 950.00 1,900.00
Un skilled 4.00 Day 650.00 2,600.00
4,500.00
Add for tools 3% of labour 3% 135.00
18,181.38 2,727.21 20,908.58
Preliminaries
10% 1,818.14
Cost for 1 Sqr 19,999.51 2,999.93 22,999.44
Porcelain Tile
1'-0" x 1'-0" porcelain tile
P.C Sum per sq.ft Rs. 300/=
Materials
1'-0" x 1'-0" porcelain tile
100.00 Sq.ft 150.00 15,000.00
waste 5%
750.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
22,531.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
26,136.00 3,920.40 30,056.40
Preliminaries
10% 2,613.60
Cost for 1 Sqr 28,749.60 4,312.44 33,062.04
0'-8" x 0'-8" non slip Hemogenous
P.C Sum per sq.ft Rs.185/=
CERAMIC TILE / MARBKE FINISH FLOOR
Materials
1'-0" x 1'-0" granite tile
100.00 Sq.ft 185.00 18,500.00
waste 5%
925.00
Cement bedding 100.00 Sq.ft 89.47 8,947.13
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
29,188.38
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
Cost per Sqr 32,793.38 4,919.01 37,712.38
Preliminaries
10% 3,279.34
Cost for 1 Sqr 36,072.71 5,410.91 41,483.62
Supply and lay mosaic tile with
cement sand bedding. 1,047.51
Consider 1 Sqr
Materials
Mosaic tile
100.00 Sq.ft 750.00 75,000.00
Cement
5.00 Bag 740.00 3,700.00
Sand
0.20 Cube 7,500.00 1,500.00
80,200.00
Wastage 5%
4,010.00
Transport 7% for tile
5,250.00
Labour
Mason
3.50 Day 950.00 3,325.00
U/sk labour
3.50 Day 650.00 2,275.00
5,600.00
Add for tools 3% of labour cost
3% 168.00
95,228.00 14,284.20 109,512.20
Preliminaries
10% 9,522.80
Cost for 1 Sqr 104,750.80 15,712.62 120,463.42
1 M2 11,271.19
Homogenious tile 4"x4"
Considering 1 Sqr
Tile 900.00 no 17.00 15,300.00
Cement slurry 1.25 Bag 700.00 875.00
Tile grout
0.75 kg 155.00 116.25 16,291.25
Wastage 5%
814.56
Transport 7%
1,140.39
Water
10.00 gal 0.50 5.00
Labour
Skill 1.25 day 950.00 1,187.50
Un Skill 1.25 day 650.00 812.50 2,000.00
3% of labour Cost for tools
60.00
Cost per Sqr 20,311.20 3,046.68 23,357.88
Preliminaries
10% 2,031.12
Cost for 1 Sqr 22,342.32 3,351.35 25,693.67
Marble Queens
3/4" thk 1:3 cement sand mix,
finished smooth cement rendering, 2'-
0" x 2'-0" Marble with approved
colour and Quality, fixed with specific
adhesive glue very neatly 1 Sqr
( P.C Sum per sq.ft Rs. 2200/=)
Materials
Marble
100.00 Sq.ft 2,200.00 220,000.00
waste 15%
33,000.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
adhesive glue 100.00 Sq.ft 100.00 10,000.00
268,964.75
Labour
Labour for fixing marble with
adhensive
100.00 Sq.ft 125.00 12,500.00
12,500.00
3% of labour cost Tools 375.00
Cost per Sqr 281,839.75 42,275.96 324,115.71
Preliminaries
10% 28,183.98
Cost for 1 Sqr 310,023.73 46,503.56 356,527.28
Scorched Granite
ROUGH TILE FINISH FLOOR
1'-0" x 1'-0" non slip Hemogenous
floor granite tile
P.C Sum per sq.ft Rs. 1350/=
Materials
1'-0" x 1'-0" granite tile
100.00 Sq.ft 1,350.00 135,000.00
waste 5%
6,750.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
148,531.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
152,136.00 22,820.40 174,956.40
Preliminaries
10% 15,213.60
Cost for 1 Sqr 167,349.60 25,102.44 192,452.04
Hand cut granite laying with
cement sand bedding " Mirisgal " Mansoor
Considering 1 Sqr
Materials
Hand cut granite 1' 0"x 1' 0"
100.00 Nos 350.00 35,000.00
Cement
5.00 bag 740.00 3,700.00
Sand
0.20 Cube 7,500.00 1,500.00
40,200.00
Transport 10%
10% 4,020.00
Labour
Skilled 3.50 day 950.00 3,325.00
U/sk labour
3.50 day 650.00 2,275.00
5,600.00
For tools 3% of labour cost
3% 168.00
49,988.00 7,498.20 57,486.20
Preliminaries
10% 4,998.80
Cost for 1 Sqr 54,986.80 8,248.02 63,234.82
Dressed stone
1'-0" x 1'-0" x 0'-2" Assorted
dressed stone
P.C Sum per sq.ft Rs.375
Materials
1'-0" x 1'-0" granite tile
100.00 Sq.ft 375.00 37,500.00
waste 5%
1,875.00
Cement bedding 100.00 Sq.ft 89.47 8,947.13
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
49,138.38
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 40.00 4,000.00
4,000.00
3% of labour cost Tools 120.00
Cost per Sqr 53,258.38 7,988.76 61,247.13
Preliminaries
10% 5,325.84
Cost for 1 Sqr 58,584.21 8,787.63 67,371.84
Supply and lay 1'-0" x 1'-0"
granite tile
Consider 1 Sqr
Materials
1'-0" x 1'-0" granite tile
100.00 Sq.ft 2,500.00 250,000.00
waste 5%
12,500.00
Cement bedding 100.00 Sq.ft 89.47 8,947.13
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
272,263.38
Labour
Labour for fixing marble with
adhensive
100.00 Sq.ft 125.00 12,500.00
12,500.00
Add for tools 3% of labour cost
3% 375.00
Cost per Sqr 285,138.38 42,770.76 327,909.13
Preliminaries
10% 28,513.84
Cost for 1 Sqr 313,652.21 47,047.83 360,700.04
Pressed Cement Tile
1'-0" x 1'-0" Cement tile
P.C Sum per sq.ft Rs. 165/=
Materials
1'-0" x 1'-0" granite tile
100.00 Sq.ft 165.00 16,500.00
waste 5%
825.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
24,106.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
Cost per Sqr 27,711.00 4,156.65 31,867.65
Preliminaries
10% 2,771.10
Cost for 1 Sqr 30,482.10 4,572.32 35,054.42
Pressed cement tile 16"x16"
Tile 57.00 no 250.00 14,250.00
Cement slurry 1.25 Bag 700.00 875.00
Tile grout
0.75 kg 155.00 116.25 15,241.25
Wastage 5%
762.06
Transport 7%
1,066.89
Water
10.00 gal 0.50 5.00
Labour
Skill 1.25 day 950.00 1,187.50
Un Skill 1.25 day 650.00 812.50
2,000.00
3% of labour Cost for tools
60.00
Cost per Sqr 19,135.20 2,870.28 22,005.48
Preliminaries
10% 1,913.52
Cost for 1 Sqr 21,048.72 3,157.31 24,206.03
Grade 20 concrete
12"x12"x1 1/2" paving stone Mirrissa
Assume 1 Sqr
Material
12"x12"x1 1/2" paving stone 100.00 No 85.00 8,500.00 8,500.00
Transport 5% 425.00
1 1/2" Cement & Sand Bed
Cement 6.00 Bag 700.00 4,200.00
Sand 0.16 Cube 7,500.00 1,200.00 5,400.00
Wastage 10% 10% 540.00
Labour
Skill 4.00 Day 950.00 3,800.00
Un Skill 4.00 Day 650.00 2,600.00 6,400.00
Tools 3% 192.00
Cost per Sqr 21,457.00 3,218.55 24,675.55
Preliminaries
10% 2,145.70
Cost for 1 Sqr 23,602.70 3,540.41 27,143.11
3 Coble Stone Paving with cement
sand bedding 648.65 Mansoor
Consider 1 Sqr
Materials
Coble stone 9" x 5"
240.00 Nos 200.00 48,000.00
Cement
5.00 Bag 740.00 3,700.00
Sand
0.20 Cube 7,500.00 1,500.00
53,200.00
Labour
Mason
3.50 Day 950.00 3,325.00
U/sk labour
3.50 Day 650.00 2,275.00
5,600.00
Add for tools 3% of labour cost
3% 168.00
58,968.00 8,845.20 67,813.20
Preliminaries
10% 5,896.80
Cost for 1 Sqr 64,864.80 9,729.72 74,594.52
Rubble Stone paving with cement
sand bedding (Antique Type )
Mansoor
Considering 1 Sqr
Material
Rubble stone (1'0"x1'0" ) 100.00 Sq.ft 3,000.00 300,000.00
Cement 2.00 Bag 740.00 1,480.00
Lime 30.00 Kg 14.50 435.00
Sand 0.18 Cube 7,500.00 1,350.00
Water 25.00 Gal 0.50 12.50
303,277.50
Labour
Skilled 1.00 Day 950.00 950.00
Un skilled 1.50 Day 650.00 975.00
1,925.00
Add 3% for tools 3% 57.75
305,260.25 45,789.04 351,049.29
Preliminaries
10% 30,526.03
Cost for 1 Sqr 335,786.28 50,367.94 386,154.22
Timber Bordered floor
3/4" thick 1:3 cement sand levelled
floor with 2" x2" battens embedded
on levelled rough cement floor & fixed
1" thick 1'-3" width timber plank
"Teak" using brass screws and well
standed to receive smooth surface
and apply wood preservative, stain and
approved polish 1 Sqr 80 L.ft
Materials
1" thick 1'-3" width "Teak" plank
100.00 Sq.ft 600.00 60,000.00
3/4" x2" battens
110.00 L.ft 55.00 6,050.00
Cemifix
5.00 Kg 880.00 4,400.00
brass screws
100.00 no 8.35 835.00
Cement bedding 100.00 Sq.ft 89.47 8,947.13
TIMBER FLOOR
80,232.13
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
Labour for timber work
skilled labourer 0.50 day 950.00 475.00
un /skilled labourer 0.50 day 650.00 325.00 3,200.00
Add 3% of labour cost tools 96.00
Paint
Timber Planking 100.00 Sq.ft 10.00 1,000.00
110.00 L.ft 10.00 1,100.00
wood preservative 11.18 Cu.ft 263.00 2,940.08
wood Treatment 118.70 sq.ft 20.00
5,040.08
Labour for painting
skilled labourer 1.00 day 950.00 950.00 950.00
Polishing 100.00 Sq.ft 95.00 9,500.00 9,500.00
99,018.20 14,852.73 113,870.93
Preliminaries
10% 9,901.82
Cost for 1 Sqr 108,920.02 16,338.00 125,258.03
Timber Skirting
8" high "Teak" Skirting 1 Sqr 150 L.ft
Materials
8" thick Teak Plank
100.00 Sq.ft 600.00 60,000.00
brass screws
150.00 no 8.35 1,252.50
61,252.50
Labour for timber fixing
skilled labourer 0.50 day 950.00 475.00
un /skilled labourer 0.50 day 650.00 325.00 800.00
Add 3% of labour cost tools 24.00
Paint
Timber Planking 100.00 Sq.ft 10.00 1,000.00
wood preservative 8.00 Cu.ft 263.00 2,104.00
wood Treatment 150.00 l.ft 14.17 2,125.50
5,229.50
Labour for painting
skilled labourer 1.00 day 950.00 950.00 950.00
Plishing 100.00 Sq.ft 35.00 3,500.00 3,500.00
Cost per Sqr 71,756.00
Cost per L.ft 478.37 71.76 550.13
Preliminaries
10% 47.84
Cost for 1 L.ft 526.21 78.93 605.14
SPECIAL WALL FINISHES
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
15%
plaster rough plaster
3/4" thick 1:5 rough plaster ( without
Lime )
Materials
cement 0.85 bags 700.00 595.00
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
1,055.00
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
2,400.00
3% of labour cost Tools 72.00
5% of labour cost Scaffolding 120.00
3,647.00 547.05 4,194.05
Preliminaries
10% 364.70
Cost for 1 Sqr 4,131.70 619.76 4,751.46
Main Index
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
EX Isolated Colunm & beam
3/4" thick 1:5 rough plaster ( without
Lime )
Materials
cement 0.85 bags 700.00 595.00
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
1,055.00
Wastage 10% 105.50
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
2,400.00
3% of labour cost Tools
72.00
5% of labour cost Scaffolding
120.00
Cost per Sqr 3,752.50 562.88 4,315.38
Preliminaries
10% 375.25
Cost for 1 Sqr 4,247.75 637.16 4,884.91
EX Reveals & Jamb
Consider 3" reveals 400.00 L.ft
Materials
cement 0.85 bags 700.00 595.00
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
1,055.00
Wastage 15% 158.25
Labour
skilled labourer 4.00 day 950.00 3,800.00
un /skilled labourer 4.00 day 650.00 2,600.00
6,400.00
3% of labour cost Tools
192.00
5% of labour cost Scaffolding
320.00
8,125.25
Cost for one L ft 20.31 3.05 23.36
Preliminaries
10% 812.53
Cost for 8.45 Sqr 8,937.78
22.34 3.35 25.70
INT Reveals & Jamb
Consider 3" reveals 400.00 L.ft
Materials
cement 0.85 bags 700.00 595.00
sand 0.06 cube 7,500.00 450.00
water 20.00 gal 0.50 10.00
1,055.00
Wastage 15% 158.25
Labour
skilled labourer 4.30 day 950.00 4,085.00
un /skilled labourer 4.30 day 650.00 2,795.00
6,880.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
3% of labour cost Tools 206.40
5% of labour cost Scaffolding 344.00
8,643.65
Cost for one L ft 21.61 3.24 24.85
Preliminaries
10% 864.37
Cost for 8.45 Sqr 9,508.02
23.77 3.57 27.34
plaster rough plaster with chiken
mesh
1 3/4" Thick plaster in cement lime &
sand 1:1:5 finished semi rough in
external wall in ground floor including
112.05 Mansoor
Consider 1 Sqr
Material
Cement
0.85 Bag 740.00 629.00
Lime
60.00 kg 14.50 870.00
Sand
0.06 Cube 7,500.00 450.00
Water
20.00 Gal 0.50 10.00
Chicken Mesh
100.00 Sq ft 40.00 4,000.00
5,959.00
Wastage
10% 595.90
Labour
Skilled
2.00 Day 950.00 1,900.00
Un skilled
2.25 Day 650.00 1,462.50
3,362.50
3% of Labour cost
3% 100.88
5% of Labour cost
5% 168.13
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
10,186.40 1,527.96 11,714.36
Preliminaries
10% 1,018.64
Cost for 1 Sqr 11,205.04 1,680.76 12,885.80
15mm (3/4") thk plinth plaster in
1:3 cement sand screed finish
smooth with gray cement floorting.
1 Sqr Queens
Materials
Bedding
cement 1.88 bags 700.00 1,312.50
sand 0.06 cube 7,500.00 450.00
water 37.50 gal 0.50 18.75
Slurry
cement
1.25 bags 700.00 875.00
water
25.00 bags 0.50 12.50
2,668.75
Labour
skilled labourer 1.50 day 950.00 1,425.00
un /skilled labourer 1.50 day 650.00 975.00
Extra Labour for slurry
skilled labourer 0.50 day 950.00 475.00
un /skilled labourer 0.50 day 650.00 325.00
3,200.00
Add 3% of labour cost tools 96.00
Cost per Sqr 5,964.75 894.71 6,859.46
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
Preliminaries
10% 596.48
Cost for 1 Sqr 6,561.23 984.18 7,545.41
2 PLASTERING IN STARICASE
EDGE Mansoor
Consider 12" width layer (10ft)
Material
Cement
0.85 Bag 740.00 629.00
Lime
60.00 kg 14.50 870.00
Sand
0.06 cube 7,500.00 450.00
Water
20.00 gal 0.50 10.00 1,959.00
Material Cost for 10 L ft
195.90
Labour
Skilled
1.50 Day 950.00 1,425.00
Un skilled
2.00 Day 650.00 1,300.00
2,725.00
3% of Labour cost
3% 81.75
5% of Labour cost
5% 136.25
3,138.90
313.89 47.08 360.97
Preliminaries
10% 313.89
Cost for 10 L.ft 3,766.68
Cost for 1 L.ft 376.67 56.50 433.17
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
4 WATER BASE PLASTER ( HIGH
MALL) Mansoor
Consider 1 Sqr
Material
Total coat
1.50 Bucket 2,800.00 4,200.00
Fillet
0.75 Bucket 3,189.00 2,391.75
Cement
6 Kg 14.80 88.80
Paint
5 Ltr 550.00 2,750.00
Sand paper
10 Nos 42.50 425.00
Bruss
0.1 Nos 595.00 59.50
9,915.05
Add: 5% transport
5% 495.75
Labour
Painter
2 Days 950.00 1,900.00
1,900.00
Add: 3% tools
3% 57.00
Add: 5% Scafolding
5% 95.00
12,462.80 1,869.42 14,332.22
Preliminaries
10% 1,246.28
Cost for 1 Sqr 13,709.08 2,056.36 15,765.45
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
3 SUPPLY & FIX GLASS BOXES Mansoor
Consider 1 Sqr
Material
1'-0"x 1'-0" glass blocks
100.00 Nos 1,700.00 170,000.00
Cement
2.00 bag 740.00 1,480.00
Lime
30.00 kg 14.50 435.00
Sand
0.18 cube 7,500.00 1,350.00
Water
25.00 gal 0.50 12.50
173,277.50
Labour
Skilled
1.50 Day 950.00 1,425.00
Un skilled
1.75 Day 650.00 1,137.50
2,562.50
Add 3% for tools
3% 76.88
175,916.88 26,387.53 202,304.41
Preliminaries
10% 17,591.69
Cost for 1 Sqr 193,508.56 29,026.28 222,534.85
1'-0" x 1'-0" GLASS MOSAIC Tile
P.C Sum per sq.ft Rs. 683/=
Materials
1'-0" x 1'-0" GLASS MOSAIC
100.00 Sq.ft 683.00 68,300.00
waste 5%
3,415.00
cement 3.00 bag 700.00 2,100.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
sand 0.08 cube 7,500.00 600.00
adhesive glue 100.00 Sq.ft 100.00 10,000.00
tile grout 0.75 kg 155.00 116.25
water 25.00 gal 0.50 12.50
84,543.75
Labour
skilled labourer 3.00 day 950.00 2,850.00
un /skilled labourer 3.00 day 650.00 1,950.00
4,800.00
3% of labour cost Tools 144.00
Cost per Sqr 89,487.75 13,423.16 102,910.91
Preliminaries
10% 8,948.78
Cost for 1 Sqr 98,436.53 14,765.48 113,202.00
1'-0" x1'-0" Glass mosaic
(P.C.sum per Sqft Rs.1600/=)
Materials
1'-0" x 1'-0" GLASS MOSAIC
100.00 Sq.ft 1,600.00 160,000.00
waste 5%
8,000.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
tile grout 0.75 kg 155.00 116.25
adhesive glue 100.00 Sq.ft 100.00 10,000.00
184,081.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 50.00 5,000.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
5,000.00
3% of labour cost Tools 150.00
Cost per Sqr 189,231.00 28,384.65 217,615.65
Preliminaries
10% 18,923.10
Cost for 1 Sqr 208,154.10 31,223.12 239,377.22
Ceramic Tile
1'-0" x 1'-0" non slip Hemogenous
wall tile
P.C Sum per sq.ft Rs. 215
Materials
tile 100.00 Sq.ft 215.00 21,500.00
waste 5% 1,075.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
29,356.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 35.00 3,500.00
3,500.00
Tools
3% of labour cost 105.00
32,961.00 4,944.15 37,905.15
Preliminaries
10% 3,296.10
Cost for 1 Sqr 36,257.10 5,438.57 41,695.67
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
0'-8" x 0'-8" non slip Hemogenous
wall tile
P.C Sum per sq.ft Rs.185
Materials
tile 100.00 Sq.ft 185.00 18,500.00
waste 5% 925.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
26,206.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 35.00 3,500.00
3,500.00
Tools
3% of labour cost 105.00
Cost per Sqr 29,811.00 4,471.65 34,282.65
Preliminaries
10% 2,981.10
Cost for 1 Sqr 32,792.10 4,918.82 37,710.92
Scorched Granite
2'-0" x1'-0" Non slip Homogenous
floor granite tile
(P.C.sum per Sqft Rs.1350/=)
Materials
2'-0" x1'-0" Non slip granite tile
100.00 Sq.ft 1,350.00 135,000.00
waste 5%
6,750.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
148,531.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 35.00 3,500.00
3,500.00
3% of labour cost Tools 105.00
Cost per Sqr 152,136.00 22,820.40 174,956.40
Preliminaries
10% 15,213.60
Cost for 1 Sqr 167,349.60 25,102.44 192,452.04
Dressed Stone
1'-0" x 1'-0" x 0'-2" Assorted
dressed stone
(P.C.sum per Sqft Rs.1600/=)
Materials
1'-0" x 1'-0" granite tile
100.00 Sq.ft 375.00 37,500.00
waste 5%
1,875.00
Cement bedding 100.00 Sq.ft 59.65 5,964.75
Cement 1.00 Bag 700.00 700.00
tile grout 0.75 kg 155.00 116.25
46,156.00
Labour
Labour for fixing tile with cement
sluarry
100.00 Sq.ft 40.00 4,000.00
4,000.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
3% of labour cost Tools 120.00
Cost per Sqr 50,276.00 7,541.40 57,817.40
Preliminaries
10% 5,027.60
Cost for 1 Sqr 55,303.60 8,295.54 63,599.14
10 4" thick Skirting
Consider 300 L.ft
Materials
Cement 1.25 Bags 740.00 925.00
Sand 0.04 Cube 7,500.00 300.00
Water 25.00 Gal 0.50 12.50
Cement slurry 1.25 Bags 740.00 925.00
2,162.50
Wastage 10% 0.10 216.25
Labour
Skilled labourer 1.00 Day 950.00 950.00
Un skilled labourer 1.00 Day 650.00 650.00
Extra labour
Skilled labourer 5.00 Day 950.00 4,750.00
Un skilled labourer 3.00 Day 650.00 1,950.00
8,300.00
Add: 3% tools 3% 249.00
Cost for 1 Sqr 10,927.75
36.43 5.46 41.89
Preliminaries
10% 1,092.78
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
12,020.53
Cost per 1 L.ft 40.07 6.01 46.08
11 3" thick External Revels
Consider 400 L.ft
Materials
Cement 0.85 Bags 740.00 629.00
Lime 30.00 Kg 14.50 435.00
Sand 0.06 Cube 7,500.00 450.00
Water 20.00 Gal 0.50 10.00
1,524.00
Wastage 10% 0.10 152.40
Labour
Skilled labourer 1.33 Day 950.00 1,263.50
Un skilled labourer 1.33 Day 650.00 864.50
Extra labour
Skilled labourer 4.00 Day 950.00 3,800.00
Un skilled labourer 2.00 Day 650.00 1,300.00
7,228.00
Add: 3% tools 3% 216.84
Add: 3% tools 5% 361.40
Cost per 1 Sqr 9,482.64
23.71 3.56 27.26
Preliminaries
10% 948.26
10,430.90
Cost per 1 L.ft 26.08 3.91 29.99
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Remarks
Laying pebbles in wall with cement
slurry. Mansoor
Consider 187 Sq.ft
Materials
Pebbles (50 Kg)
35.00 Bag 7,500.00 262,500.00
Cement
4.00 Bag 740.00 2,960.00
265,460.00
Labour
Mason
20.00 Day 950.00 19,000.00
U/sk labour
5.00 Day 650.00 3,250.00
22,250.00
For tools 3% of labour cost
3% 667.50
288,377.50
154,212.57 23,131.89 177,344.45
Preliminaries
10% 28,837.75
Cost for 187 Sq.ft 317,215.25
Cost for 1 Sqr 169,633.82 25,445.07 195,078.90
SPECIAL CEILING FINISHES
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
1 Supper flex ceiling with timber fram work Mansoor
Consider 3.3 sqr
Materials
Balaw timber
4"x 2" Joists 199.10 L ft. 135.50 26,978.05
2"x 2" Joists 82.72 L ft. 55.00 4,549.60
2"x 2" Joists 21.00 L ft. 55.00 1,155.00
32,682.65
Wastage 5% of timber 5% 1,634.13
Superflex ceiling sheet 6mm thick 8'-0" 4'-
0"
8.00 Nos 1,840.00 14,720.00
Wire nails 4.13 kg 160.00 660.00
Sand peper 2.00 Nos 42.50 85.00
Wood preservative 14.17 Cu.ft 263.00 3,725.93
19,190.93
Labour
Painter 1.25 days 950.00 1,187.50
Carpenter 2.25 days 950.00 2,137.50
Un skilled labour 2.00 days 650.00 1,300.00
4,625.00
Add for tools 3% of labour 3% 138.75
Add for scaffolding 5% of labour 5% 231.25
Main Index
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
58,502.71
17,728.09 2,659.21 20,387.31
Preliminaries 10% 5,850.27
Cost for 3.3 Sqr 64,352.98
Cost for 1 Sqr 19,500.90 2,925.14 22,426.04
Sloping Ceiling
10mm thick superflex ceiling boards fixed
to exposed rafter
9mm thick gypsum board
4 Nos 1,175.00 4,700.00
Nails
1 kg 160.00 160.00 4,860.00
Transport 10%
486.00
Labour
Skilled labour
1.00 day 950.00 950.00
Un skilled labour
1.00 day 650.00 650.00 1,600.00
Tools 3% 48.00
Cost for 1 Sqr 6,994.00 1,049.10 8,043.10
Preliminaries 10% 699.40
Total Cost 7,693.40 1,154.01 8,847.41
2 Flat asbestos ceiling with timber fram
work.
Consider 156 Sq ft
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Material
Tholang timber
2" x 4" timber 112.00 L ft 123.50 13,832.00
2" x 2" joists 96.00 L ft 49.00 4,704.00
Asbestos ceiling sheet 156.00 Sq.ft 23.75 3,705.00 201.39405
Nails & screws 3.00 kg 160.00 480.00
22,721.00
Wastage 5% 5% 1,136.05
Labour
Carpenter 1.00 Day 950.00 950.00
Un skilled 2.00 Day 650.00 1,300.00
2,250.00
Add for tools 3% of labour 3% 67.50
Add for scaffolding 5% of labour 5% 112.50
26,287.05
16,850.67 2,527.60 19,378.27 2085.1023
Preliminaries 10% 2,628.71
Cost for 1.56 Sqr 28,915.76
Cost for 1 Sqr 18,535.74 2,780.36 21,316.10
3 Flat "tuna" ceiling with timber fram work
Consider 120 Sq ft 10.00 12.00 120.00
Material
Tholang timber
2" x 4" timber 84.00 L ft 123.50 10,374.00
Tuna timber 120.00 Sq.ft 95.00 11,400.00
Wastage 10% 10% 1,140.00
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Nails & screws 3.00 kg 160.00 480.00
23,394.00
Wastage 5% 5% 1,169.70
Labour
Carpenter 2.00 Day 950.00 1,900.00
Un skilled 4.00 Day 650.00 2,600.00
4,500.00
Add for tools 3% of labour 3% 135.00
Add for scaffolding 5% of labour 5% 225.00
29,423.70
24,519.75 3,677.96 28,197.71
Preliminaries 10% 2,942.37 281.98
Cost for 1.2 Sqr 32,366.07
Cost for 1 Sqr 26,971.73 4,045.76 31,017.48
Cost for 1 Sq.ft 269.72
Timber ceiling 6"x 3/4" finished size
TUNA tonuged & grooved planks fixed over
rafters
Consider 102.4 Sqr
Materials
Timber ceiling
102.40 Sqr 9,500.00 972,800.00
Wastage 10% of timber ceiling 10% 97,280.00
Wood preservative 614.40 Cube 263.00 161,587.20 1,231,667.20
Transport 5% 5% 61,583.36
Labour
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
labour 35% 431,083.52
Add for tools 3% of labour 3% 12,932.51
Add for scaffolding 5% of labour 5% 21,554.18
Cost per 102.4 Sqr 1,758,820.76
17,175.98 2,576.40 19,752.38
Preliminaries 10% 1,717.60
Total Cost 18,893.58 2,834.04 21,727.62
4 4'-0" x 4'-0 " Super flex ceiling with
aluminium frame work
Subcontractor's rate
1 Sqr 17,500.00 17,500.00
Add: only Attendance 8% 1,400.00
Total for 1 sqr 18,900.00 2,835.00 21,735.00
Preliminaries 10% 1,890.00
Cost for 1.2 Sqr 20,790.00 3,118.50 23,908.50
A.6 Asbestos ceiling sheet fix to frame work (
frame work measured seperatly ) 1 sqr
4'-0" x4'-0" asbestos ceiling sheet
7 Nos 380.00 2,660.00
Nails
150.00
2,810.00
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Transport 10%
Labour
skilled 1.00 day 950.00 950.00
Un skilled 1.00 day 650.00 650.00 1,600.00
Add for tools 3% of labour 3% 48.00
Add for scaffolding 5% of labour 5% 80.00
4,538.00 680.70 5,218.70
Preliminaries 10% 453.80
Total Cost 4,991.80 748.77 5,740.57
Cement fiber board ceiling with timber
frame
Consider 156 Sq ft
Material
Tholang timber
2" x 4" timber
112.00 L ft 123.50 13,832.00
2" x 2" joists
96.00 L ft 49.00 4,704.00
Cement fiber board
156.00 Sq.ft 200.00 31,200.00
Nails & screws
3.00 kg 160.00 480.00
50,216.00
Wastage 5%
0.05 2,510.80
Labour
Carpenter
1.00 Day 950.00 950.00
Un skilled
2.00 Day 650.00 1,300.00
2,250.00
Add for tools 3% of labour
0.03 67.50
Add for scaffolding 5% of labour
0.05 112.50
Cost for 156 sq.ft
55,156.80
35,356.92 5,303.54 40,660.46
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Preliminaries 10% 3,535.69
Total Cost 38,892.62 5,833.89 44,726.51
5 Operation Theatre Ceiling
Unit Rate
Supply and installation of ceiling system for
operation Theatre at Emergency Trauma
Centre Building, Teaching Hospital,
Karapitiya.
M 4,625.00 *
'Eurometalic' ceiling system comprising of
DuPontAlesta AM powder coated metal
ceiling tiles installed on a concealed
suspension system
modular 'eurometalic' 600x600mm concealed
panels of 0.5mm thick steel sheet accurately
pressed to guarantee diamentional precision
powder coated to 80 microns thickness in
white colour using 'DuPont Alesta AM'
developed to provide an active hygienic
coating system with excellent anti-bacterial
properties
plain surface (not perforated)
edges are specially shaped to be close
mounted
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
vertical edges pressed to form a shape that
will lock into a special spring clip with steel
conduit
the complete system is suspended from the
soffit above using adjusting clips and 4mm
diameter galvanised hanger rods
the panels are individually demountable to
ensure access to any part of the ceiling void
the perimeter manels can easily be cut when
necessary and are fitted to the edge trim
(quoted below)
holes for light fixtures and other shall be
cut.
* Notes:
Rate exclusive of 15% VAT
Mode of Payment
Advance
75%
On progress
20%
At Completion
5%
Valid for 30 days from 19.01.09
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
MANHOLES / SEPTIC TANKS
Item Description
No Length Breath Depth Qty
8'-0" x6'-0" x 5'-0" concrete septic tank
1 Excavation
8 8 5.5 352
2 2" Lean concrete
8 8 64
3 6" thick base concrete
8 8 0.5 32
4 9" thick brick wall
2 8 5
2 6 5
5 Concrete for cover slab
8 8 0.42 26.88
6 Formwork for cover slab
8 6 48
7 Reinforcement for base & wall
12 2.4 28.8
16 1.8 28.8
8 Reinforcement
12 2.4 28.8
16 1.8 28.8
9 Plastering
8 6 48
2 8 5 80
2 6 5 60
MANEHOLE
150
975
75
Main Index
Area 3.00 3.00 2.50
9.84 9.84 8.20
Concrete Bed hight 0.15
Excavation 3.00 3.00 2.50
Screed 2" tk 3.00 3.00
Concrete Bed 3.00 3.00 0.49
Brick work 9" 36.36 2.46
Benching 2.46 2.46
Plastering 9.84 1.61
Plastering in benching 2.46 2.46
Conc. In benching 2.46 2.46 0.39
Copping Beam 36.36 0.74 0.25
14.268 0.36 0.25
Form work to beam 36.36 0.23
0.984 0.23
750
150
200
15.744 0.23
Form work to Slab 36.36 0.23
Concrete cover 36.36 39.36 0.23
600x 600 x 600 mm Manhole
Area 0.60 0.60 0.60
Excavation 0.60 0.60 0.60
Screed 2" tk 0.60 0.60
Concrete Bed 0.60 0.60 0.33
brick walls 2.4 0.27
Formwork 4 0.60 0.27
Reinforcement 8 0.60 0.90
8 0.60 0.90
Benching 0.58 0.58
Plastering 4 0.58 0.27
Plastering in benching 0.58 0.58
Cast iron lid
1500mm dia x 1500mm height sockage pit
Area 3.14 0.75 0.75 1.50
Excavation 3.14 0.75 0.75 1.50
brick walls 3.14 1.5 1.00
Plastering 3.14 1.5 1.00
Cover slab 3.14 0.75 0.75
1500mm dia x 2000mm height sockage pit
Area 3.14 0.75 0.75 2.00
Excavation 3.14 0.75 0.75 2.00
brick walls 3.14 1.5 1.00
Plastering 3.14 1.5 1.00
Cover slab 3.14 0.75 0.75
Q 19
Construction of under ground RC water sump
capacity 6000 Ltr.
( Internal size 7'-0" x 6'-0" x 5'-6" )
double seal CI heavy duty access cover
Area 7.00 6.00 5.50
Excavation 7.00 6.00 5.50
Screed 2" tk 7.00 6.00
Concrete Bed 7.00 6.00 0.33
Concrete walls 26.00 5.17 0.33
Formwork 4 7.00 5.17
Reinforcement 80 5.50 82.55
18 26.00 86.41
22 6.00 25.07
19 7.00 25.26
Benching 6.34 5.34
Waterproofing 2 6.34 5.17 65.56
2 5.34 5.17 55.22
1 6.34 5.34 33.86
Plastering 2 6.34 5.17 65.56
2 5.34 5.17 55.22
Plastering in benching 6.34 5.34
Form work to Slab 4 6.34 0.33
Concrete cover 7.00 6.00 0.33
DDT for CI cover 6.29 1.00 0.33
Reinforcement 8 7.00 10.53
63mm dia swan neck ventilation pipe
Foot valve
Ball valve
2' 0" dia double seal CI heavy duty access cover
Additional labour
W 11
Sewer manhole size internally
2'-0" x 2'-0" & depth not exceeding 3'-0"
with CI Cover
Area 2.00 2.00 3.00
Excavation 2.00 2.00 3.00
Screed 2" tk 2.00 2.00
Concrete Bed 2.00 2.00 0.33
Concrete walls 8.00 2.67 0.42
Formwork 4 2.00 2.67
Reinforcement 13 3.00 7.40
Benching 1.34 1.34
Plastering 4 1.34 2.67
Plastering in benching 1.34 1.34
Form work to Slab 4 1.34 0.33
Cast Iron cover
Additional labour
W 14
Construction of RC grease trap internaly 2'-
0" x1'-6" built in 6" thick RC walls(stainles
steel grease removal tray)
Area 2.66 3.16 1.50
Excavation 2.66 3.16 1.50
Screed 2" tk 2.66 3.16
Concrete Bed 2.66 3.16 0.33
Concrete walls 11.64 1.17 0.33
Formwork 4 2.66 1.17
Reinforcement 19 1.50 5.26
Plastering 4 2.00 1.17
Plastering in benching 2.00 2.50
Form work to Slab 4 2.00 0.33
Checked plate cover
Stainless steel stainer bucket
Stainless steel lifting handle
Additional labour
W15
Construction of CI Storm water manhole
internaly 1'-0" x1'-0" built in 4" thick RC
walls
Area 1.00 1.00 2.00
Excavation 1.00 1.00 2.00
Screed 2" tk 1.00 1.00
Concrete Bed 1.00 1.00 0.33
Concrete walls 4.00 1.67 0.33
Formwork 4 1.00 1.67
Reinforcement 7 2.00 2.66
Benching 0.34 0.34
Plastering 4 0.34 1.67
Plastering in benching 0.34 0.34
Form work to Slab 4 0.34 0.33
M.S. grating and frame
Anticorrosive paint
Additional labour
Total Qty Unit Rate Amount
352.00 Cu.ft 11.72 4,124.12
64.00 Sq.ft 48.53 3,105.82
32.00 Cu.ft 337.43 10,797.77
80.00 Sq.ft 158.74 12,699.20
60.00 Sq.ft 158.74 9,524.40
26.88 Cu.ft 337.43 9,070.12
48.00 Sq.ft 98.81 4,742.68
5.42 Kg 152.15 824.30
5.42 Kg 152.15 824.30
5.42 Kg 152.15 824.30
5.42 Kg 152.15 824.30
48.00 Sq.ft 37.88 1,818.36
80.00 Sq.ft 37.88 3,030.59
60.00 Sq.ft 37.88 2,272.94
64,483.21
112.5
10.5 m3
90.53 Cu.ft
0.49 L.ft
22.50 Cu.ft 11.72 263.62
9.00 Sqr 48.53 436.76
4.43 Cu.ft 337.43 1,494.14
89.45 Sq.ft 158.74 14,198.59
6.05 Sq.ft 37.88 229.25
15.81 Sq.ft 37.88 599.10
6.05 Sq.ft 37.88 229.25
2.38 Cu.ft 337.43 803.73
6.60
1.27
7.87 Cu.ft 337.43 2,654.72
8.35
0.23
900
150
3.61
12.19 Sq.ft 98.81 1,204.34
8.35 Sq.ft 98.81 824.86
328.59 Cu.ft 337.43 110,875.30
133,813.66
0.96 Cu.ft
0.22 m3 625.00 135.00
0.36 m2 566.00 203.76
0.12 m3 13,625.00 1,618.65
0.65 m1 2,200.00 1,425.60
0.65 m2 1,300.00 842.40
1.81 kg 225.00 406.32
0.34 m2 678.00 228.08
0.63 m2 678.00 424.70
0.34 m2 678.00 228.08
1 No 11,696.00 11,696.00
17,208.58
3.48 Cu.ft
2.65 m3 625.00 1,657.37
4.71 m2 2,200.00 10,371.43
4.71 m2 678.00 3,196.29
1.77 No 13,625.00 24,087.05
39,312.13
3.86 m3
3.54 m3 625.00 2,209.82
4.71 m2 2,200.00 10,371.43
4.71 m2 678.00 3,196.29
1.77 No 13,625.00 24,087.05
39,864.59
231.00 Cu.ft
231.00 cu.ft 15.00 3,465.00
42.00 sq.ft 51.27 2,153.34
13.86 cu.ft 358.89 4,974.22
44.36 cu.ft 358.89 15,919.86
144.76 sq.ft 90.00 13,028.40
219.28 kg 140.00 30,699.46
33.86 sq.ft 37.28 1,262.14
154.63 sq.ft 160.00 24,740.29
120.77 sq.ft 37.28 4,502.35
33.86 sq.ft 37.28 1,262.14
8.37 sq.ft 90.00 753.19
13.86
(2.07)
11.79 cu.ft 358.89 4,229.78
10.53 kg 140.00 1,474.78
1,475.00
2,773.00
2,500.00
19,000.00
134,212.93
2,500.00
136,712.93
12.00 Cu.ft
12.00 cu.ft 15.00 180.00
4.00 sq.ft 51.27 205.08
1.32 cu.ft 358.89 473.73
8.97 cu.ft 358.89 3,219.67
21.36 sq.ft 90.00 1,922.40
7.40 kg 140.00 1,036.66
1.80 sq.ft 37.28 66.94
14.31 sq.ft 37.28 533.52
1.80 sq.ft 37.28 66.94
1.77 sq.ft 90.00 159.19
11,600.00
19,464.14
2,500.00
21,964.14
12.61 Cu.ft
12.61 cu.ft 15.00 189.13
8.41 sq.ft 51.27 430.96
2.77 cu.ft 358.89 995.51
4.49 cu.ft 358.89 1,612.92
12.45 sq.ft 90.00 1,120.39
5.26 kg 140.00 736.19
9.36 sq.ft 37.28 348.94
5.00 sq.ft 37.28 186.40
2.64 sq.ft 90.00 237.60
5,000.00
10,858.04
2,500.00
13,358.04
2.00 Cu.ft
2.00 cu.ft 15.00 30.00
1.00 sq.ft 51.27 51.27
0.33 cu.ft 358.89 118.43
2.20 cu.ft 358.89 791.14
6.68 sq.ft 90.00 601.20
2.66 kg 140.00 371.89
0.12 sq.ft 37.28 4.31
2.27 sq.ft 37.28 84.67
0.12 sq.ft 37.28 4.31
0.45 sq.ft 90.00 40.39
2,097.61
2,500.00
4,597.61
SANITARY FITTING AND ACCESSORIES
Rate Rs. Date
New Eurosmart basin mixer Grohe Nr 14,960.00 6/2/2010
New Eurosmart concealed bath mixer Grohe Nr 12,950.00 6/2/2010
Concealed body bath Grohe Nr 12,320.00 6/2/2010
Relaxa head shower buo Grohe Nr 22,810.00 6/2/2010
Lineare basin mixer Grohe Nr 34,510.00 6/2/2010
Lineare bidet mixer Grohe Nr 34,510.00 6/2/2010
Silver metalic bidet spray Grohe Nr 9,130.00 6/2/2010
Coasta sink mixer Grohe Nr 10,570.00 6/2/2010
New Eurostyle sink mixer Grohe Nr 21,340.00 6/2/2010
mintaa sink mixer Grohe Nr 58,400.00 6/2/2010
Angle valve Grohe Nr 1,850.00 6/2/2010
Angle valve Grohe Nr 1,650.00 6/2/2010
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
Fixing of Sanitary fittings with
necessary accessories
Main Index
Material
Flexible hose 1 Nos 325.00 325.00
"S" or "P" trap 1 Nos 500.00 500.00
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 4,325.00
13.01 Water closet
Material
Pedestal type Water closet
1 Nos 18,725.00 18,725.00
Add 15%
2,808.75
Flexible hose
1 Nos 325.00 325.00
"S" or "P" trap
1 Nos 500.00 500.00
Angle valve
1 Nos 750.00 750.00
Transport 2%
462.18
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 26,320.93
Add O/H 18%
4737.7665
31,058.69
13.02 Pedestal wash basin
Material
Pedestal wash basin
1 Nos 10,750.00 10,750.00
Add 15%
1,612.50
Flexible hose
2 Nos 325.00 650.00
Bottel trap
1 Nos 1,350.00 1,350.00
Angle valve
1 Nos 750.00 750.00
Mixer tap
1 Nos 3,000.00 3,000.00
Transport 2%
362.25
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 21,224.75
Add O/H 18%
3820.455
25,045.21
2 Vanity wash basin
Material
Flexible hose 2 Nos 325.00 650.00
Bottle trap 1 Nos 1,350.00 1,350.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Vanity basin tap 1 Nos 250.00 250.00
Total basic cost 6,500.00
13.03 Vanity wash basin
Material
Vanity wash basin
1 Nos 6,365.00 6,365.00
Add 15%
954.75
Flexible hose
2 Nos 325.00 650.00
Bottel trap
1 Nos 1,350.00 1,350.00
Angle valve
1 Nos 750.00 750.00
Mixer tap
1 Nos 3,000.00 3,000.00
Transport 2%
261.40
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 16,081.15
Add O/H 18%
2,894.61
18,975.75
3 Flexible showers
Material
Flexible hose 2 Nos 325.00 650.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 4,900.00
4 Bidet spry
Material
Flexible hose 1 Nos 325.00 325.00
Angle valve 1 Nos 750.00 750.00
Labour
Fixing charges 1 Item 2,750.00 2,750.00
Total basic cost 3,825.00
13.06 Bidet spry
Material
Bidet spry
1 Nos 2,700.00 2,700.00
Flexible hose
1 Nos 325.00 325.00
Angle valve
1 Nos 750.00 750.00
Transport 2%
75.50
Labour
Fixing charges
1 Item 750.00 750.00
Total basic cost 4,600.50
Add O/H 18%
828.09
5,428.59
SUPPLY & FIX MIRRORS Mansoor
Consider 20 Sq.ft
Material
Mirror
20.00 Sq.ft 845.00 16,900.00
Screws & bolts
4.00 Nos 8.35 33.40
16,933.40
Transport
10% 1,693.34
Labour
Skilled
0.25 day 950.00 237.50
Un skilled
0.25 day 650.00 162.50
400.00
19,026.74
Add O/H & profit 25%
25% 4,756.69
Cost for 20 Sq.ft 23,783.43
Cost for 1 Sq.ft 1,189.17
5 1/2" bib tap
Labour
Fixing charges 1 Item 250.00 250.00
Total basic cost 250.00
13.04 Jacuzzi bath
Material
Jacuzzi bath
1 Nos ##### 130,000.00
Add 15%
19,500.00
Flexible hose
2 Nos 325.00 650.00
Angle valve
3 Nos 750.00 2,250.00
Mixer tap
1 Nos 3,000.00 3,000.00
Transport 2%
3,108.00
Labour
Fixing charges
1 Item 3,500.00 3,500.00
Total basic cost 162,008.00
Add O/H 18%
29,161.44
191,169.44
6 Bath tub
Material
Flexible hose 2 Nos 325.00 650.00
Conceal value 1 Nos 1,350.00 1,350.00
Angle valve 2 Nos 750.00 1,500.00
Labour
Fixing charges 1 Item 3,500.00 3,500.00
Total basic cost 7,000.00
13.05 mirror Size 700 x 1100 0.77 m2 3,766.00 2,899.82
Pencil
3.6 L.m 148.00 532.80
Punching
4 Nos 50.00 200.00
Nuts
4 Nos 25.00 100.00
Transport 2%
74.65
Labour
Fixing charges
1 Item 500.00 500.00
Total basic cost 4,307.27
Add O/H 18%
775.31
5,082.58
7 Accessories
Labour
Fixing charges
Paper holder 200.00
Soap holder 200.00
towel rail 200.00
tooth brush holder 200.00
cloth pegs 200.00
1,000.00
8 Builder's work
Excavation 10 Cu.ft 14.00 140.00
Back filling 10 Cu.ft 15.00 150.00
mass concrete 3.3 Cu.ft 285.00 940.50
1,230.50
123.05
13.07 shower mixer spray
Material
shower mixer spray
1 Nos 6,000.00 6,000.00
Flexible hose
2 Nos 325.00 650.00
wall mounted tap
1 Nos 750.00 750.00
Transport 2%
148.00
Labour
Fixing charges
1 Item 1,200.00 1,200.00
Total basic cost 8,748.00
Add O/H 18%
1,574.64
10,322.64
13.08 towel rail
32 dia 600mtr towel rail
1 no 2,000.00 2,000.00
Nuts
4 no 25.00 100.00
Transport 2%
42.00
Labour
Fixing charges
1 Item 300.00 300.00
Total basic cost 2,442.00
Add O/H 18%
439.56
2,881.56
13.09 sigle bowl stainless steel sink
Material
sigle bowl stainless steel sink
1 Nos 8,500.00 8,500.00
Flexible hose
2 Nos 325.00 650.00
Bottel trap
1 Nos 2,750.00 2,750.00
Angle valve
1 Nos 750.00 750.00
Swell type piller tap
1 Nos 2,500.00 2,500.00
Mixer tap
1 Nos 3,000.00 3,000.00
Transport 2%
363.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 21,263.00
Add O/H 18%
3,827.34
25,090.34
13.1 Double bowl stainless steel sink
Material
Double bowl stainless steel sink
1 Nos 15,000.00 15,000.00
Flexible hose
2 Nos 325.00 650.00
Bottel trap
1 Nos 2,750.00 2,750.00
Angle valve
1 Nos 750.00 750.00
Swell type piller tap
1 Nos 2,500.00 2,500.00
Mixer tap
1 Nos 3,000.00 3,000.00
Transport 2%
493.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 27,893.00
Add O/H 18%
5,020.74
32,913.74
13.12 Soap tray
Soap tray
1 No 1,500.00 1,500.00
Screws
2 No 25.00 50.00
Transport 2%
31.00
Labour
Fixing charges
1 Item 200.00 200.00
Total basic cost 1,781.00
Add O/H 18%
320.58
2,101.58
13.13 1/2" Garden tap
1/2" Garden tap 1 No 750.00 750.00
Transport 2%
15.00
Labour
Fixing charges
1 Item 250.00 250.00
Total basic cost 1,015.00
Add O/H 18%
182.70
1,197.70
Water pump
1 15,720.00 15,720.00
Gate valve
3 1,650.00 4,950.00
Non retern valve
1 2,000.00 2,000.00
Transport 2%
453.40
Labour
Fixing charges
1 Item 2,000.00 2,000.00
Total basic cost 25,123.40
Add O/H 18%
4,522.21
29,645.61
Water pump
1 44,000.00 44,000.00
Gate valve
3 1,650.00 4,950.00
Non retern valve
1 2,000.00 2,000.00
Transport 2%
1,019.00
Labour
Fixing charges
1 Item 2,000.00 2,000.00
Total basic cost 53,969.00
Add O/H 18%
9,714.42
63,683.42
Water pump
1 32,500.00 32,500.00
Gate valve
3 1,650.00 4,950.00
Non retern valve
1 2,000.00 2,000.00
Transport 2%
789.00
Labour
Fixing charges
1 Item 2,000.00 2,000.00
Total basic cost 42,239.00
Add O/H 18%
7,603.02
49,842.02
Q16 Supply & install centrifugal electric
water pump
Materials
Electric water pump (Delivery
2000gl/hr@ 12Mtr
1 No 28,543.00 28,543.00
Gate valve
2 No 1,650.00 3,300.00
Non-Return valve
1 No 2,000.00 2,000.00
Balancing valve
1 No 2,000.00 2,000.00
Stainer
1 No 2,000.00 2,000.00
Float switch panel
1 No 650.00 650.00
Control panel
1 No 75,000.00 75,000.00
Tarter
1 No 10,300.00 10,300.00
solvent cement
75.00 grms 2.28 171.00
Other
Item 1,000.00 1,000.00
GI Pipe
1 No -
Transport 2%
2,499.28
Labour
Fixing charges
1 Item 2,000.00 2,000.00
129,463.28
Q17 Supply & install Pressure boosting
package near the over head tank
Materials
65 Ltr per per minits at 30psi. Pressure
tank
1 No ##### 125,000.00
solvent cement
100.00 grms 2.28 228.00
Tarter
1 No 10,300.00 10,300.00
Transport 2%
2,710.56
Labour
Fixing charges
1 Item 2,000.00 2,000.00
140,238.56
Q18 Supply & install 1000 Ltr plastic water
tank
Materials
1000Ltr water tank
1 No 12,000.00 12,000.00
Gate valve
2 No 1,650.00 3,300.00
Non-Return valve
1 No 2,000.00 2,000.00
solvent cement
75.00 grms 2.28 171.00
Other
Item 1,000.00 1,000.00
Transport 2%
369.42
Labour
Fixing charges
1 Item 2,000.00 2,000.00
20,840.42
Q20 32mm dia. Pumping main to over head
tank from sump
Assume 50 L.ft
Materials
32mm pipe
50.00 l.ft 49.23 2,461.54
clipe & nails
160.00
solvent cement
75.00 grms 2.28 171.00
Others
1,280.00
4,072.54
Labour
skilled labourer
0.75 day 950.00 712.50
U/sk labour
0.75 day 650.00 487.50
1,200.00
3% for tool
36.00
5% for Scaffolding
60.00
5,368.54
107.37
Q21 Supply & fix 1" dia gate valve
Materials
1" dia gate valve
1 No 1,650.00 1,650.00
solvent cement
10.00 grms 2.28 22.80
Transport 2%
33.46
Labour
Fixing charges
1 Item 500.00 500.00
2,206.26
Q22 Laying of 25mm supply main from the
road & to the sump as shown in
drawing
Assume 50 L.ft
Materials
25mm pipe
50.00 l.ft 33.00 1,650.00
clipe & nails
160.00
solvent cement
75.00 grms 2.28 171.00
Others
880.00
2,861.00
Labour
excavation
0.75 day 950.00 712.50
skilled labourer
0.75 day 950.00 712.50
U/sk labour
0.75 day 650.00 487.50
1,912.50
3% Tools
57.38
5% Scaffolding
95.63
4,926.50
98.53
Q31 20mm polypropylene pipe or equivalent
hot water
Materials 287
20mm hot water pipe
100.00 l.ft 87.50 8,750.00
20mm ' T ' joint
5.00 No 145.00 725.00
20mm Elbow
3.00 No 100.00 300.00
20mm Lugged Elbow
8.00 No 240.00 1,920.00
20mm Clip
67.00 No 19.14 1,282.38
Concrete nail with roll plug
133.00 No 5.00 665.00
13,642.38
Transport 2%
272.85
Wastage 5%
682.12
Labour
Plumber
10.50 day 950.00 9,975.00
U/sk labour
10.50 day 650.00 6,825.00
16,800.00
3% of Tools
504.00
5% of Scaffolding
840.00
32,741.35
327.41
Q32 15mm polypropylene pipe or equivalent
hot water 100 L.ft
Materials
15mm hot water pipe
100.00 l.ft 70.12 7,012.20
15mm ' T ' joint
5.00 No 65.00 325.00
15mm Elbow
3.00 No 60.00 180.00
15mm Lugged Elbow
8.00 No 195.00 1,560.00
15mm Clip
67.00 No 19.14 1,282.38
Concrete nail with roll plug
133.00 No 5.00 665.00
11,024.58
Transport 2%
220.49
Wastage 5%
551.23
Labour
Plumber
10.50 day 950.00 9,975.00
U/sk labour
10.50 day 650.00 6,825.00
16,800.00
3% of Tools
504.00
5% of Scaffolding
840.00
29,940.30
299.40
Q33 10mm polypropylene pipe or equivalent
hot water
Materials
10mm hot water pipe
100.00 l.ft 60.98 6,097.56
10mm ' T ' joint
8.00 No 65.00 520.00
10mm Elbow
7.00 No 60.00 420.00
10mm Lugged Elbow
11.00 No 195.00 2,145.00
10mm Clip
100.00 No 19.14 1,914.00
Concrete nail with roll plug
### No 5.00 1,000.00
12,096.56
Transport 2%
241.93
Wastage 5%
604.83
Labour
Plumber
10.50 day 950.00 9,975.00
U/sk labour
10.50 day 650.00 6,825.00
16,800.00
3% of Tools
504.00
5% of Scaffolding
840.00
31,087.32
310.87
Q34 Supply & fix solar hot water panel 300
Ltr
Materials
solar hot water panel 300 Ltr
1 No ##### 198,000.00
Others
2,000.00 2,000.00
200,000.00
Q36 1 1/2" dia gate valve
Materials
1 1/2" dia gate valve
1 No 4,800.00 4,800.00
solvent cement
5.00 grms 2.28 11.40
Transport 2%
96.23
Labour
Fixing charges
1 Item 200.00 200.00
5,107.63
Q37 1 1/4" dia gate valve
Materials
1 1/4" dia gate valve
1 No 3,600.00 3,600.00
solvent cement
5.00 grms 2.28 11.40
Transport 2%
72.23
Labour
Fixing charges
1 Item 200.00 200.00
3,883.63
Q38 1" dia gate valve
Materials
1" dia gate valve
1 No 2,450.00 2,450.00
solvent cement
5.00 grms 2.28 11.40
Transport 2%
49.23
Labour
Fixing charges
1 Item 200.00 200.00
2,710.63
Q39 3/4" dia gate valve
Materials
3/4" dia gate valve
1 No 1,950.00 1,950.00
solvent cement
5.00 grms 2.28 11.40
Transport 2%
39.23
Labour
Fixing charges
1 Item 200.00 200.00
2,200.63
Q40 1/2" dia gate valve
Materials
1/2" dia gate valve
1 No 1,475.00 1,475.00
solvent cement
5.00 grms 2.28 11.40
Transport 2%
29.73
Labour
Fixing charges
1 Item 200.00 200.00
1,716.13
Sanitary fittings
Q42 Fixing of pedestal type of water closet
Material
Flexible hose
1 Nos 325.00 325.00
"S" or "P" trap
1 Nos 500.00 500.00
Angle valve
1 Nos 750.00 750.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 4,325.00
Q43 Fixing of Vanity wash basin
Material
Flexible hose
2 Nos 325.00 650.00
Bottel trap
1 Nos 1,350.00 1,350.00
Angle valve
2 Nos 750.00 1,500.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 6,250.00
Q44 Fixing of Stainless steel sink double
bowl sigle drain (Mixer tap)
Flexible hose
2 Nos 325.00 650.00
Bottel trap
1 Nos 1,350.00 1,350.00
Angle valve
1 Nos 750.00 750.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 5,500.00
Q45 Fixing of Stainless steel sink double
bowl sigle drain (single tap)
Material
Flexible hose
2 Nos 325.00 650.00
Bottel trap
1 Nos 1,350.00 1,350.00
Angle valve
2 Nos 750.00 1,500.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 6,250.00
Q46 Fixing of Mirror (pencil edge Size 2'-6"
x 2'-0"
Pencil
9 L.ft 45.00 405.00
holl making
4 Nos 50.00 200.00
Nuts
4 Nos 25.00 100.00
Labour
Fixing charges
1 Item 500.00 500.00
Total basic cost 1,205.00
Q47 Supply & fix chromium plated telephon
head shower spray with concealed type
shower (Mixer tap)
Material
chromium plated telephon head shower
1 Nos -
Flexible hose
2 Nos 325.00 650.00
Angle valve
1 Nos 750.00 750.00
Mixer tap
1 Nos -
Transport 2%
28.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 4,178.00
Q48 Fix chromium plated telephon head
shower spray with control type shower
(Mixer tap)
Material
Flexible hose
2 Nos 325.00 650.00
Angle valve
1 Nos 750.00 750.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 4,150.00
Q49 Fixing of approved quality hand spray
bidet comprising
Material
Flexible hose
1 Nos 325.00 325.00
Angle valve
1 Nos 750.00 750.00
Labour
Fixing charges
1 Item 2,750.00 2,750.00
Total basic cost 3,825.00
Q50 Fixing of stainless steel towel rail 32
dia.
Labour
Fixing charges
1 Item 250.00 250.00
Total basic cost 250.00
Q51 Fixing of stainless steel brass pegs
with double hanging hooks fixed to
doors
Labour
Fixing charges
1 Item 250.00 250.00
Total basic cost 250.00
Q52 Fixing of stainless steel soap tray
Labour
Fixing charges
1 Item 250.00 250.00
Total basic cost 250.00
Q50 Supply & fix 1/2" dia. C.P Garden tap
1/2" dia. C.P Garden tap
1 Nos 365.00 365.00
solvent cement
5.00 grms 2.28 11.40
Labour
Fixing charges
1 Item 200.00 200.00
576.40
W17 Supply & fix 110 dia. uPVC (Type400)
Consider 50 L.ft
Materials
110mm pipe
50.00 L.ft 195.60 9,780.00
Solvent cement
150.00 Grms 2.28 342.00
Other
15,000.00
25,122.00
Labour
Excavation
0.75 Day 650.00 487.50
Skilled labourer
0.75 Day 950.00 712.50
U/sk labour
0.75 Day 650.00 487.50
1,687.50
Add: 3% Tools
3% 50.63
Add: 5% Scaffolding
5% 84.38
26,944.50
538.89
C Supply and Fix water pump including
valve
Materia
Supplu of motar pump
1 Nos 15,000.00 15,000.00
cement
0.25 Cement 740.00 185.00
Sand
0.01 Cube 7,500.00 75.00
Allum for pipe
1 Item 500.00 500.00
15,760.00
Transport 10% 1,576.00
Labour
Mason
0.50 day 950.00 475.00
Un skilled
0.50 day 650.00 325.00
Plumber
0.50 day 950.00 475.00 475.00
Tools 3%
14.25
17,825.25
O/H & Profit 25% 4,456.31
Total Cost 22,281.56
Water Geyser
Material
30L Water geyser 1.00 Nos 16,500.00 16,500.00
Angle valve 2.00 Nos 750.00 1,500.00
Flexible hoses
2.00 Nos 325.00 650.00 18,650.00
Labour
Skilled 1.00 Day 950.00 950.00
Un skilled
1.00 Day 650.00 650.00 1,600.00
Tools 3%
48.00
Cost for 1 Nos 20,298.00
Supply & Fix Squatting fan
Material
Squatting pan
1 No 549.00 549.00
Cement bedding
200.00
Labour
Fixing charges
1 Item 750.00 750.00
Total basic cost 1,499.00
Supply & Fix Shower
Material
Shower head
1 Nos 150.00 150.00
Solvent cement
50.00
Labour
Fixing charges
1 Item 200.00 200.00
Total basic cost 400.00
TIMBER WORKS
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
15%
1 Timber deck with 2" x4 ", 2"x 2" fram
and 3/4" thick kubuk plank 785.57
Consider 10' 0"x10' 0" area
Material ( balaw)
2"x 4" timber 60.00 L ft 135.50 8,130.00
2"x 2" timber 60.00 L ft 55.00 3,300.00
3/4" thick timber plank (Kmbuk) 100.00 Sq ft 450.00 45,000.00
Nails 5 kg 160.00 800.00
57,230.00
Wastage 5% 0.05 2,861.50
Timber plaking
Labour
Carpenter 2 days 950.00 1,900.00
Un skilled 1 day 650.00 650.00
2,550.00
Add for tools 3% of labour 0.03 76.50
Add for scaffolding 5% of labour 0.05 127.50
62,845.50
Main Index
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Add O/H & profit 0.25 15,711.38
Cost for 1 Sqr 78,556.88
1" thick, 6" width yellow Balue timber plank
fixed on RCC beams with 1/2" gap finished
with two coats of water based lacqer
Assume 1'-4" wide 75 L.ft long 6.25 1 sqr
Materials
1" thick, 6" width yellow Balue 91.44 Sq.ft 292.00 26,699.75
Nut & bolts 550.00 No 10.00 5,500.00
sand paper 5.00 no 40.00 200.00
brush 0.10 no 595.00 59.50
32,459.25
Transport 7% 2,272.15
Labour
skilled labourer 1.00 day 950.00 950.00
un /skilled labourer 1.00 day 650.00 650.00
1,600.00
3% of labour cost 48.00
Paint
Timber Planking 91.44 Sq.ft 10.00 914.38
wood preservative 7.32 Cu.ft 263.00 1,923.85
wood Treatment 91.44 sq.ft 20.00 1,828.75
Water base lacqer 182.88 sq.ft 88.00 16,093.00
20,759.97
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
57,139.37
3 6" high kubuk skirting Mansoor
Consider 10 L.ft
Material
Kumbuk Plank 10.00 L ft 175.00 1,750.00
Wastage 10% 10% 175.00
Nails 20.00 8.35 167.00
Wood presevative 250.00
2,342.00
Labour
Skilled 1 day 950.00 950.00
Un skilled 1 day 650.00 650.00
1,600.00
Add 3% for tools 3% 48.00
3,990.00
Add O/H & profit 25% 25% 997.50
4,987.50
Cost for one L ft 498.75
4 Staircase hand rail including copper
posr. Mansoor
Consider 12 L.ft
Material
2"x4" teak hand rail 12.00 L.ft 625.00 7,500.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
S/S Cable 48.00 L.ft 250.00 12,000.00
Copper post (1"x2 1/4"x2'9") 4.00 Nos 3,000.00 12,000.00
31,500.00
Labour
Skilled 7.00 day 900.00 6,300.00
Un skilled 4.00 day 650.00 2,600.00
8,900.00
Add 3% for tools 3% 267.00
40,667.00
Add O/H & profit 25% 25% 10,166.75
50,833.75
Cost for 1 L.ft 4,236.15
3" x 2" teak timber member fixed to 2"
thick flat iron wiyh welded to 5/8" dia mild
steel round bar spaces fixed to wall all
complete as per detail drawing
Assume 10 L.ft
Materials
3" x 2" Teak 10.00 L.ft 700.00 7,000.00
2" Flat iron 10.00 L.ft 68.42 684.20
5/8" mild steel round bar 72.00 L.ft 22.03 1,585.96
Bolt & Nuts 15.00 No 10.00 150.00
Welding rod 5.00 No 10.00 50.00
sand paper 5.00 No 35.00 175.00
Anchor bolt etc 360.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
10,005.16
Transport 7% 700.36
Welding plant 1.00 hour 312.50 312.50
Labour
Skilled Labour 3.00 day 950.00 2,850.00
Un / skilled Labour 2.00 day 650.00 1,300.00
4,150.00
Paint
Tmber planking 10.00 L.ft 10.00 100.00
Tmber painting (spry) 11.60 Sq.ft 115.00 1,334.00
Iron paint
Anti corosive 1.50 Ltr 586.00 879.00
Steel primer 1.00 Ltr 973.00 973.00
Black eggshell paint 1.50 Ltr 542.00 813.00
Tinner 2.00 Ltr 338.00 676.00
Brush 1/2" 1.00 no 100.00 20.00
4,795.00
19,963.03
1,996.30 299.45 2,295.75
prilimineries 10% 0.10 1,996.30
21,959.33
Cost per L.ft 2,195.93 329.39 2,525.32
5 Timber staircas support with "U" Iron
Material
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
1' 0" width "U" Iron
22.33 L.ft 2,600.00 58,058.00
"L" Iron
84.00 L.ft 125.00 10,500.00
25mm Tor steel rod
7.06 kg 260.00 1,834.90
1 1/2" thick Kumbuk timber
90.00 Sq.ft 450.00 40,500.00
1:2:4 Concrete
0.20 Cube 38,400.00 7,587.84
3/4" Screws
100.00 Nos 5.58 558.00
Glue
4.00 Ltr 175.00 700.00
119,738.74
Add 10% for wastage
10% 11,973.87
Add 5% for transport
5% 5,986.94
Labour
Skilled Labour
5.00 day 950.00 4,750.00
Un Skilled Labour
5.00 day 650.00 3,250.00
8,000.00
Add 3% for tools
3% 240.00
Add 5% for scaffolding
5% 400.00
146,339.55
Add O/H & profit 25%
25% 36,584.89
Cost for Staircase 182,924.44
6 TIMBER LATTIS 676.82 Kiri
Consider 3.41 Sqr (48.75' x 7')
Material
2" x 2" battens 500.00 L.ft 45.00 22,500.00
2" x 1" reepers 3,920.00 L.ft 27.00 105,840.00
128,340.00
Wastage 10% 10% 12,834.00
Transport 7% 7% 8,983.80
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Nails & screws 14.00 160.00 2,240.00
2,240.00
Labour
Planing charges 3,920.00 L.ft 7.00 27,440.00
Skilled 3.00 Day 950.00 2,850.00
Un skilled 3.00 Day 650.00 1,950.00
4,800.00
Basic cost 184,637.80
Add O/H & profit 25% 25% 46,159.45
Cost per 3.41 Sqr 230,797.25
Cost per Sqr (without polish) 67,682.48
Pressure impregnated,mature coconut,
sealed 8"x8" square ends finished smooth
Material
8" dia app 9' 6" high columns
1.00 Nos 6,000.00 6,000.00
Transport 5%
300.00 6,300.00
labour
Planking charges
Post making & Fixing charges
650.00 650.00
Tools 3%
19.50
Cost for one Post 6,969.50
Galvanized iron angle iron
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
For 1 pair
Material
100x 75x 8mm angle iron 1.33 L.ft 750.00 1,000.00
12mm bolts
2.00 nos 300.00 600.00 1,600.00
Labour
Un skilled
0.25 Day 650.00 162.50 162.50
Cost for one pair 1,762.50
Concrete encasing to anchor bolts
For 1 No
2' 0"x8"x6"
Material
Concrete (grade 20)
0.66 Cu.ft 297.00 196.02
Wastage 5%
9.80 205.82
Labour
Skilled
0.1 Day 950.00 95.00
Un skilled
0.1 Day 650.00 65.00 160.00
Tools 3%
4.80
Cost for 1 nos 370.62
Prepair and apply two coats water based
sanding sealer, stain and two finishing coats
on Coconut.
0.33
19.71
For 8" dia 9' 6" high column
Material
Water based Sandind sealer 0.83 Ltr 820.00 680.60
Wood stain 0.83 Ltr 656.25 544.69
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Wood finishing
1.25 Ltr 805.00 1,006.25
Sand paper
10.00 Nos 40.00 400.00
Canvas
10.00 l.ft 65.00 650.00
Brush
0.25 Nos 595.00 148.75 3,430.29
Wastage 5%
171.51
Labour
Skilled 1.00 Day 950.00 950.00
Unskilled
2.00 Day 650.00 1,300.00 2,250.00
Add 3% for tools
67.50
Cost for 1 Sqr
5,919.30
Cost for 1 Sq.ft
59.19
Cost for 8" dia 9' 6" high column (19.71
Sq.ft)
1,166.69
Skirting moulded top edge
4" x 1/2" high straight timber
Consider 10 L.ft
Material
4" x 1/2" high straight timber 10.00 L ft 200.00 2,000.00
Wastage 10% 10% 200.00
Transport 10% 200.00
Nails 20.00 8.35 167.00
Wood presevative
2,567.00
Labour
Skilled 0.5 day 950.00 475.00
Un skilled 0.5 day 650.00 325.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
800.00
Add 3% for tools 3% 24.00
Cost for 10 L ft 3,391.00
Cost for 1 L ft 339.10
B Teak panneled door
D 4 (1200x3000)
Material
Door sash
38.74 Sq ft 650.00 25,178.40
Wastage 10%
25,178.40
2,517.84
Labour
38.74 Sq ft 350.00 13,557.60
Tools 3%
406.73
Cost for Door sash 41,660.57
F Antique Door
(1200x2100)
Material
Door sash
27.12 Sq ft 450.00 12,201.84 12,201.84
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Cost for Door sash 12,201.84
Ex 03 2" x 1" Lattis area For 3.41 Sqr
48'- 9" x 7'- 0"
Material
2" x 2" reepers 92.00 L.ft 45.00 4,140.00
2" x 1" reepers 2,341.43 L.ft 27.00 63,218.57
67,358.57
Wastage 15% 10,103.79
Transport 10% 6,735.86
Wood Preservative 5,500.00
Nails & screws 14.00 160.00 2,240.00
Labour
Planing charges 2,433.43 L.ft 7.00 17,034.00
Skilled 3.00 Day 950.00 2,850.00
Un skilled 3.00 Day 650.00 1,950.00 4,800.00
Basic cost 113,772.21
Add O/H & profit 25% 28,443.05
142,215.27
Cost per Sqr (without polish) 41,705.36
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
SUPPLY & FIX KUMBUK PLANK TO
VENITY TOP Mansoor
Consider 32 Sq.ft
Material
1" thick kubuk plank
32.00 Sq ft 450.00 14,400.00
Wastage 10%
10% 1,440.00
Wood preservative
150.00
15,990.00
Labour
Skilled
0.50 days 950.00 475.00
Un skilled
0.50 days 650.00 325.00
800.00
Tools 3%
3% 24.00
Planning charges
340.00
340.00
17,154.00
Add O/H & profit 25%
25% 4,288.50
Cost for 1 Sqr 21,442.50
Cost for 1 Sq.ft 670.08
Pantry Cupboard
Complete mahogany pantry cupboard (
Bottom and upper )
L.ft 15,000.00
Complete Teak pantry cupboard ( Bottom
and upper )
L.ft 20,000.00
Item Description Qty Unit Rate Amount Amount O/H & Profit
Amount with
profit
Mahogany cacase and surface teak pantry
cupboard ( Bottom and upper )
L.ft 18,500.00
Complete MDF pantry cupboard ( Bottom
and upper )
L.ft 9,200.00
Remarks
Remarks
Remarks
Remarks
Remarks
Buller's
Remarks
Remarks
134
Remarks
3.142857143
Remarks
Remarks
Remarks
Remarks
Remarks
STEEL WORKS
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount with
profit
15%
1 STEEL DOOR
Supply and fixing of steel door
9' 2" x 6' 10" (0.6 sqr)
Material
50 x 50 x 6 mm box iron 3.00 Nos 1,346.09 4,038.27
25 x 25 x 3 mm box iron 10.00 Nos - -
Door lock 1.00 Nos 6,900.00 6,900.00
Hinges 4.00 Nos 1,100.00 4,400.00
Welding rods 5.00 kg -
Cutting disks 6.00 Nos -
Oil primer 4.00 Liters -
Enamal paint 4.00 Liters 553.00 2,212.00
17,550.27
Labour
For fabricating and fixing
Skilled lobour 3.00 days - -
Un skilled 4.00 days 123.50 494.00
Main Index
For painting
Skilled lobour 1.00 days - -
494.00
ADD 3% for tools 3% 14.82
18,059.09
30,098.48 4,514.77 34,613.26
prilimineries 10% 0.1 1,805.91
Cost for 0.6 sqr 19,865.00
Cost for 1 sqr 33,108.33 4,966.25 38,074.58
2 HAND RAIL
Fixing of wall hand rail (10 L.ft)
Material
50mm dia G.I pipe 10.00 L.ft 1,900.00 19,000.00
12mm M.S rods 40.00 L.ft -
6mm M.S plates 4.00 nos -
16mm dia ancher bolts 16.00 nos -
Welding rods 2.00 kg -
Primer 0.50 lts -
Auto colour paint 0.50 lts -
Additional promote 0.50 lts -
19,000.00
Labour
For fabricating and fixing
Skilled lobour 2.00 days - -
Un skilled 3.00 days 123.50 370.50
370.50
ADD 3% for tools 0.03 11.12
Cost for 1 sqr without prilimineries 19,381.62
1,938.16 290.72 2,228.89
prilimineries 10% 0.10 1,938.16
Cost for10 L.ft 21,319.78
Cost for 1 L.ft 2,131.98 319.80 2,451.77
3 SUPPLY & FIX " H" BEAM
Material
" H" beam 350x175x41.5kg 1 Nos 47,300.00 47,300.00
Bolt 8 Nos 150.00 1,200.00
10mm plate 2 sq.ft 1,100.00 2,200.00
50,700.00
Transport 3,500.00
Labour
Sk 1 Days 950.00 950.00
Un/sk 1 Days 650.00 650.00
1,600.00
Small tools 3% 3% 48.00
Scafolding 5% 5% 80.00
55,928.00 8,389.20 64,317.20
prilimineries 10% 0.10 5,592.80
Cost for above Item 61,520.80 9,228.12 70,748.92
3 G.I LADDER
Assume
35 L.ft
Material
4/3" G.I. pipe 70.00 L.ft 64.21 4,494.74
1/2" G.I. pipe solied 35.00 L.ft 62.11 2,173.68
10% wastage 666.84
Welding rods Item 600.00
Welding plant 1.00 Day 2,500.00 2,500.00
Grinding Item 900.00
11,335.26
Transport 10% 1,133.53
Labour
Skillded 4.00 Day 950.00 3,800.00
Un/skilled 4.00 Day 650.00 2,600.00
6,400.00
Tools 3% 192.00
Scafallding 5% 320.00
19,380.79
553.74 83.06 636.80
prilimineries 10% 0.10 1,938.08
21,318.87
Cost per 1 L.ft 609.11 91.37 700.48
Roller Shutter
Over size 20'-0" x 10'-0" (type
RD1 200Sq.ft)
Morter 1.00 No 35,000.00 35,000.00
Roller Shutter
200.00 Sq.ft 700.00 140,000.00
175,000.00 26,250.00 201,250.00
875.00 131.25 1,006.25
prilimineries 10% 0.10 17,500.00
192,500.00 28,875.00 221,375.00
Cost per Sq.ft 962.50 144.38 1,106.88
Balcony Terrace Railling
2" Diameter galvanized iron
(Horizontzl) with 1" dia m/s rood
(Vertical @ 8" centers) fixed to
horizontzl galvanized bar & fixed to
wall
Assume 10 L.ft
Materials
2" Diameter galvanized iron 10.00 L.ft 222.11 2,221.10
1" dia m/s 4.00 L.ft 52.63 210.52
Achobolt 1.00 Item 100.00 100.00
Welding rod 5.00 No 10.00 50.00
sand paper 3.00 No 35.00 105.00
2,686.62
Transport 7% 188.06
Welding plant 1.00 hour 312.50 312.50
Labour
Skilled Labour 2.00 day 950.00 1,900.00
Un / skilled Labour 2.00 day 650.00 1,300.00
3,200.00
Iron paint
Anti corosive 0.75 Ltr 586.00 439.50
Steel primer 1.00 Ltr 973.00 973.00
Black eggshell paint 0.50 Ltr 542.00 271.00
Tinner 1.00 Ltr 338.00 338.00
Brush 1/2" 1.00 no 100.00 20.00
2,041.50
8,428.68
842.87 126.43 969.30
prilimineries 10% 0.10 842.87
9,271.55
Cost per L.ft 927.16 139.07 1,066.23
Weld mesh Galvanized iron
Assume 1 Sqr
Weld mesh Galvanized iron (3.15mm) 100.00 Sq.ft 45.00 4,500.00
Wastage 5% 225.00
Wastage 5% 225.00
Allow for galvanizing 1,000.00
Labour
Skill 0.20 Day 950.00 190.00
Un Skill 0.20 Day 650.00 130.00
Per Sqr 6,270.00
62.70
Railing
1 1/2" primer & painted G I hand rail
with fixing bracket 12mm G I painted
rods with timber railing @ 2' 0" c/c as
detail
Consider 10 L.ft
Material
1 1/2" G I hand rail 10.00 L.ft 100.00 1,000.00
12mm GI rods @ 2' 0" c/c 6.00 l.ft 32.00 192.00
fixing brackets 600.00
Allow sum for galvanized 500.00 2,292.00
Wastage 10% 229.20
Labour
Skilled 1.00 day 950.00 950.00
Un skilled 2.00 day 650.00 1,300.00 2,250.00
Add 3% for tools 67.50
Cost for 10 L ft 4,838.70
Cost for 1 L ft
483.87
1,750.00
Ex.40 Supply And fix Cast Iron lids for manhols and gullys.
Material
12" x 12" Rainwater Gully cover 12.00 Nos 4,980.00 59,760.00
18" x 18" Gully cover 5.00 Nos 10,800.00 54,000.00
30" x 20" Gully cover 2.00 Nos 14,900.00 29,800.00
26" x 24" Gully cover 2.00 Nos 11,696.00 23,392.00
24" x 24" Gully cover 1.00 Nos 11,696.00 11,696.00
12" x 12" Dranage cover 1.00 Nos 3,950.00 3,950.00
20" x 25" Gully cover 1.00 Nos 11,696.00 11,696.00
14" x 14" Gully cover 1.00 Nos 6,780.00 6,780.00
21" x 21" Gully cover 1.00 Nos 11,696.00 11,696.00
Cement 1.00 bag 780.00 780.00
Sand 0.09 cube 7,500.00 675.00
Water 12.00 gal 0.50 6.00
Transport 10% 214,231.00
21,423.10
Labour
Skilled 6.00 Day 950.00 5,700.00
Un skilled 6.00 650.00 3,900.00 9,600.00
Tools 3% 288.00
-
O/H & Profit 25% 0
Total Cost -
Remarks
Buller's
Nishani
Queens
Queens
TYPE OF BOUNDARY WALL
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
15%
1 BOUNDRY WALL
Consider 10' 0" long
Consider 10' 0" long, 7'-0" high
Excavation 10.00 1.18 1.25 14.75 Cu ft 13.39 197.50
Rubble 10.00 1.18 1.25 14.75 Cu ft 1.54 22.68
10.00 0.75 0.50 3.75 Cu ft 1.54 5.77
4" block work 10.00 7.00 70.00 Sq ft 1.20 84.00
concrete in 4"x4" columns 2 2.00 2.00 0.50 4.00 Cu ft 328.94 1,315.74
2 0.34 0.34 8.00 1.85 Cu ft 328.94 608.40
Formwork in 4"x4" columns 2 1.68 8.00 26.88 Sq ft 14.78 397.16
Reinforcement in 4"x4" columns 4 9.00 6.78 kg - -
4" block wall
1' 0"
Main Index
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
32 0.50 1.08 kg - -
Rough plaster 2.00 10.00 7.00 140.00 Sq ft - -
Painting 2.00 10.00 7.00 140.00 Sq ft 0.60 84.00
Copping 10.00 10.00 Lft 80.00 800.00
3,515.25
351.52 52.73 404.25
Preliminaries 0.10 351.52
Cost for 10 l ft 3,866.77
Cost for 1 l ft 386.68 58.00 444.68
Chain Link Fencing
PVC coated 2"x2" square,guage 10
chainlink fence,with 9' 0" high
reinforced concrete posts equilent
to as manufactured by SEC, buried
in 18"x18"x24" deep concrete at 8'
0" c/c as detail,with 3 stands
staining wire the bottom encased in
13"x6" concrete. 18.75 Concrete volume
Assume 50 L.ft
Material
Cement 2.5 Bag 740.00 1,850.00
Sand -rough 0.08 Cube 7,000.00 560.00
Metail 0.14 Cube 4,800.00 672.00
Concrete precast fence post 7'-7"
high 6 Nr 1,211.28 7,267.68
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
PVC coated 2"x2" square chainlink
fence -Fence hight 8'-0" 50.00 L.ft 385.71 19,285.71
Tensin wire 150.00 l.ft 10.00 1,500.00
31,135.39
Transport 5% 5% 1,556.77
Wastage 10% 10% 3,113.54
Labour
Skilled 2.00 day 950.00 1,900.00
Un skilled 4.00 day 650.00 2,600.00 4,500.00
3% of labour Cost for tools 135.00
Cost for 50 L.ft 40,440.70
Cost for 1 L.ft
808.81
MISSALLANIOUS
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
15%
Concrete Arch Demolish A11
Machine & equipment hiried
Time for demolosh work - 15 Days
Jacks 100 Nos 750.00 75,000.00
Jack hire for 1 day 50/= 15 days @ 75/=
Concrete braker 15 Days 5,000.00 75,000.00
Oxigen cutter 1 Days 6,000.00 6,000.00
156,000.00
Labour
Skilled -braker opretor 15 Days 1,200.00 18,000.00
For demolish
Un/sk 75 Days 675.00 50,625.00
( 15 days 5 un/sk )
75
Remove to tactor
Un/sk 25 Days 675.00 16,875.00
( 15 days 5 un/sk )
Main Index
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
85,500.00
Tractor loard remove from site 5 load 1,500.00 7,500.00
7,500.00
Small tools 3% 2,565.00
Scafolding 5% 4,275.00
Basik cost 255,840.00
O/H and profit 25% 63,960.00
Cost for above 319,800.00
Demolish Concrete Slab & Beam Buller's
Machine & equipment hiried
Jacks ( 5 days) 40 Nos 250.00 10,000.00
Jack hire for 1 day 50/= 5 days @ 50/=
Concrete braker 5 Days 5,000.00 25,000.00
Oxigen cutter 0.5 Days 6,000.00 3,000.00
38,000.00
Labour
Skilled -braker opretor 5 Days 1,200.00 6,000.00
Un Skille laber for demolish 15 Days 675.00 10,125.00
( 5 days 3 un/sk )
Un Skille laber for remove 4 Days 675.00 2,700.00
( 2 days 2 un/sk ) 18,825.00
Small tools 3% 3% 564.75
Scafolding 5% 5% 941.25
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
Tractor loard remove from site 2 load 1,500.00 3,000.00
3,000.00
61,331.00
O/H and profit 25% 25% 15,332.75
Cost for above 76,663.75
3' 0"x3' 0"x3' 0" PVC coated GI gabion
basckets filleed with 6"x 9" random
rubble and buried 3' 0" deep and 3' 0"
above ground level.
For one box
Material
3' 0"x3' 0"x3' 0" PVC coated GI gabion
basckets 1 Nos 4,560.00 4,560.00
6"x 9" random rubble 0.27 Cube 2,300.00 621.00 5,181.00
Transport 7% 362.67
Labour
For excavation Unskilled 0.5 day 650.00 325.00
skilled 0.5 day 950.00 475.00
Un skilled 0.75 day 650.00 487.50 1,287.50
Tools 3% 38.63
Cost for one Box (.27 Cube) 6,869.80
Cost for one Cube
25,443.69
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
Fixing Concret stain posts in fence.
For one post
Material
Concrete post 1 Nos 475.00 475.00
Transport 5% 23.75 498.75
Labour
Skilled 0.25 Day 950.00 237.50
Un skilled 0.50 Day 650.00 325.00 562.50
Tools 3% 16.88
Cost for one Post
1,078.13
F Remove roof Galle
For 1 Sqr
Labour
Skilled 1.00 day 950.00 950.00
Unskilled 2.00 day 750.00 1,500.00 2,450.00
Tools 3% 73.50
2,523.50
O/H & profit 25% 630.88
Total 3,154.38
For 28.19 Sqr 88,921.83
Ex.49 Garden tap with Brick wall sink 4'-0" x 2'-0" 0'-5"
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
Material
4" Thick concrete 3.25 Cu.ft 412.00 1,338.53
6" brick work
12.48 Sq.ft 125.00 1,559.65
Water proofing
16.99 Sq.ft 110.00 1,869.14
Tilling
16.99 Sq.ft 140.00 2,378.91 7,146.23
Labour
Skilled Labour 4.00 Day 1,000.00 4,000.00
Un skilled Labour 3.00 day 750.00 2,250.00 6,250.00
Tools 3% 187.50
Total Cost 13,583.73
3 Built up Temperary huts for workers
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
Consider 12'-0" x 10'-0"
Floor & wall
Excavation top soil 168.00 Sq.ft 8.37 1,405.95
2" thick screed 120.00 Sq.ft 48.53 5,823.41
Cement rendering 120.00 Sq.ft 28.36 3,402.60
Covering GI sheets 72.00
60.00
132.00 Sq.ft 12.75 1,683.00
2" x2" Timber frame 45.00
48.00
40.00
133.00 L.ft 28.00 3,724.00
Nails 1.00 Kg 160.00 160.00
Usk labour 0.50 day 650.00 325.00
Roof
GI sheets 120.00 Sq.ft 12.75 1,530.00
Frame 36.00
20.00
56.00 Sq.ft 28.00 1,568.00
Nails 1.00 Kg 160.00 160.00
Usk labour
0.50 day 650.00 325.00
20,106.96
Cost per 1 Sqr 16,755.80
4
Built up Temperary toilet for workers
including temperary pit
Consider 5'-0" x 4'-0"
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
Excavation top soil 30.00 Sq.ft 8.37 251.06
2" thick screed 20.00 Sq.ft 48.53 970.57
Cement rendering 20.00 Sq.ft 28.36 567.10
Covering GI sheets 70.00
56.00
126.00 Sq.ft 12.75 1,606.50
2" x2" Timber frame 35.00
20.00
16.00
71.00 L.ft 28.00 1,988.00
Hinges 2.00 no 49.00 98.00
Nails 1.00 Kg 160.00 160.00
Usk labour 0.50 day 650.00 325.00
Roof
GI sheets 20.00 Sq.ft 12.75 255.00
Frame 10.00
8.00
18.00 Sq.ft 28.00 504.00
Nails 1.00 Kg 160.00 160.00
Usk labour 0.50 day 650.00 325.00
Supply & Fix Squatting fan 1.00 No 1,499.00 1,499.00
Supply & Fix Angle Valve 2.00 No 576.40 1,152.80
Supply & Fix Shower 1.00 No 400.00 400.00
63mm pipe 3.00 L.ft 253.53 760.60
32mm pipe 5.00 L.ft 107.37 536.85
25mm pipe 3.00 L.ft 83.14 249.42
Supply & Fix Pit 1.00 No 5,000.00 5,000.00
Item Description Qty Unit Rate Amount Amount
O/H &
Profit
Amount
with profit
Remarks
Excavation for pit 48.00 C.ft 13.39 642.72
PAINTING
Item Description Qty Unit Rate
5 APPLY TWO COAT OF TOTAL COAT
Consider 8.45 Sqr
Material
Total coat 28kg bucket 3.50 Bucket 2,800.00
Sand paper 10 Nos 42.50
Bruss 0.1 Nos 595.00
Add: 5% transport 5%
Labour
Painter 4 Days 950.00
Add: 3% tools 3%
Add: 5% Scafolding 5%
Preliminaries
10%
Cost for 8.45 Sqr
Two coat of Total coat & cut the surface using
sand paper (No 120,No 100,No 80,No 60) &
apply one coat of acralic filler and two coats of
interior emulsion paint of approved colour
Internaly
INTERNAL PAINT APPLICATION
Main Index
Consider 8.45 Sqr
Material
Total coat 3.50 Bucket 2,800.00
One coat of acralic filler 7.00 Ltr 337.00
Two coats of emulsion 11.27 Ltr 550.00
Sand paper 40.00 Nos 42.50
Roller Bruss 3.00 Nos 400.00
Add: 5% transport 0.05
Labour
Painter for Totalcoat apply 4.00 Days 950.00
Painter 15.00 Days 950.00
Add: 3% tools 0.03
Add: 5% Scafolding 0.05
Cost per Sqr
Preliminaries
10%
Cost for 1 Sqr
Painting & alkail Resistant Primer -CIC
Wall putty -Asian Paint
Emulsion 02 coats to internal walls including primer
Materials
Emulsion paint
2.00 Ltr 550.00
Wall putty @ Rs. 2100 per 28kg bag
7.50 Kg 75.00
sand paper
2.00 no 42.50
roller brush
0.08 no 595.00
Transpor 5%
Labour
skilled labourer
1.75 day 950.00
3% of labour cost for tools
0.03
3% of labourer cost scaffolding
0.03
Prepare and apply one coat of interior emulsion
white paint to internal soffit slab.
Slab & Soffit Painting(Ceiling)
Consider 8.45 Sqr
Material
One coat of acralic filler 8.45 Ltr 337.00
Two coats of interior emulsion 12.68 Ltr 550.00
Sand paper 40.00 Nos 42.50
Bruss 6.00 Nos 400.00
Add: 5% transport 0.05
Labour
Sk labour 8.45 Days 950.00
unSk labour 8.45 Days 650.00
Add: 3% tools 0.03
Add: 5% Scafolding 0.05
Cost per Sqr
Preliminaries
10%
Cost for 1 Sqr
Weathershield 02 coats to external walls including primer
Materials
Weathershield paint
1.50 Ltr 750.00
Alkali resistance plaster primer
1.00 Kg 805.00
brush
0.08 no 555.00
EXTERNAL PAINT APPLICATION
Transpor 5%
Labour
skilled labourer
1.50 day 950.00
3% of labour cost for tools
0.03
3% of labourer cost scaffolding
0.03
2 SPRAY PAINT
Consider Door size 3' 0" x 7' 0" 75.00 Sq.ft
Material
First coat
Die 1.25 Ltr 1,810.00
Second coat
Base coat 1.25 Ltr 1,916.67
Third coat
Laquare 1.25 Ltr 1,916.67
Wastage 10% 10%
Labour
For cutting Unskilled 2.00 day 650.00
For spraying Skilled 1.50 day 950.00
Add 3% for tools 3%
For 75 Sq ft
For 1 Sqr
TIMBER SURFACE FINISHING APPLICATION
Prepair and apply two coats of sanding sealer, stain
and two coats colourless matt lacqer on Timber.
For 1 Sqr
Material
Sandind sealer 0.83 Ltr 820.00
Wood stain 0.83 Ltr 656.25
Matt lacqer 1.25 Ltr 805.00
Thinner 7.00 Ltr 599.00
Sand paper 10.00 Nos 40.00
Canvas 10.00 l.ft 65.00
Brush 0.25 Nos 595.00
Wastage 5%
Labour
Skilled 1.00 Day 950.00
Unskilled 2.00 Day 650.00
Add 3% for tools
Cost for 1 Sqr
Cost for 1 L.ft (4" thick)
Prepair and apply sanding sealer system on timber
frame and enamel paint system on ms rods.
Material
Enamal paint 1.25 Ltr 857.00
Thinner 7.00 Ltr 599.00
Sand paper 10.00 Nos 40.00
Brush 0.25 Nos 595.00
Wastage 5%
Labour
Skilled 1.00 Day 950.00
Unskilled 2.00 Day 650.00
Add 3% for tools
Cost for 1 Sqr
Cost for 1 Sq.ft
Amount Amount
O/H &
Profit
Amount with
profit
Remarks
15%
Mansoor
1 Sqr
9,800.00
425.00
59.50
10,284.50
514.23
3,800.00
3,800.00
114.00
190.00
14,902.73
1,763.64 264.55 2,028.18
1,490.27
16,393.00
1,940.00 291.00 2,231.00
INTERNAL PAINT APPLICATION
9,800.00
2,359.00
6,198.50
1,700.00
1,200.00
21,257.50
1,062.88
3,800.00
14,250.00
18,050.00
541.50
902.50
4,948.45 742.27 5,690.71
494.84
5,443.29 816.49 6,259.79
1,100.00
562.50
85.00
47.60
1,795.10
89.76
1,884.86
1,662.50
1,662.50
49.88
49.88
3,647.11 547.07 4,194.17
2,847.65
6,971.25
1,700.00
2,400.00
13,918.90
695.95
8,027.50
5,492.50
13,520.00
405.60
676.00
3,457.57 518.64 3,976.20
345.76
3,803.32 570.50 4,373.82
1,125.00
805.00
44.40
EXTERNAL PAINT APPLICATION
1,974.40
98.72
2,073.12
1,425.00
1,425.00
42.75
42.75
3,583.62 537.54 4,121.16
140.88 Mansoor
2,262.50
2,395.84
2,395.84
7,054.18
705.42
1,300.00
1,425.00
2,725.00
81.75
10,566.34
10,566.34
14,088.46 2,113.27 16,201.73
TIMBER SURFACE FINISHING APPLICATION
680.60
544.69
1,006.25
4,193.00
400.00
650.00
148.75 7,623.29
381.16
950.00
1,300.00 2,250.00
67.50
10,321.95
34.41
1,071.25
4,193.00
400.00
148.75 5,813.00
290.65
950.00
1,300.00 2,250.00
67.50
8,421.15
84.21
1 Steel
2 Masonry
3 Roofing Materials
4 Electrical
5 Doors & Windows -glass, hingers etc.
6 Painting
7 Waterproofing
8 Floor / Wall / Ceiling Finishes
9 Plumbing / Sanitary fittings
10 Ready Mix Concrete
11 Timber
12 Tools & Equipment
13 Miscellaneous Materials
14 Labour / Hire Charges
15 Orange Electrical price list
16 Habour
17 Micro Partition
18 Labour Rate
MATERIAL PRICES
Main Index
Code Category Description Remarks Unit
S Steel Tor steel 10,12,16,20,25 Mton
S Steel M.S rounds 10,12 Mton
S Steel M.S rounds 16,21 Mton
B Bunding wire G18 Kg
A Angle iron Size 1"x1"1/8" 6mts
A Angle iron Size 2"x2"x3mm 6mts
A Angle iron Size 2"x2"x5mm 6mts
A Angle iron Size 3"x3"x 6mm 6mts
A Angle iron Size 4"x4"x6mm 6mts
A Angle iron Size 11/2"x11/2"x3mm 6mts
Angle iron Size 50x50x6mm 5.8mts
A Aluminium flat Size 1"x3mm 12L.ft
A Aluminium box Size 2"x1" 12L.ft
A Aluminium box Size 2"x2"x3mm 6mts
A Aluminium box 4" Flat iron -6mm 6mts
A Aluminium box 3"x3" 6mts
A Channel 100x50 "C" Chanel
A Channel 150x75 "C" Chanel
A Channel 200x100 "C" Chanel 6mts
A Channel 150x65x20mm 2.3mm thick Lm
A Channel 100x50x20mm 2.0mm thick Lm
G G.I pipe 1/2" dia meadium duty 6mtr
G G.I pipe 1/2" pipe 6mtr
G G.I pipe 3/4" pipe Pakistan 6mtr
G G.I pipe 1" dia meadium duty 6mtr
G G.I pipe 1.5" dia meadium duty 6mtr
G G.I pipe 1 1/2" pipe 6mtr
G G.I pipe 1 1/4" pipe heavy 6mtr
G G.I pipe 2" dia meadium duty 6mtr
G G.I pipe 2" dia Pakistan 6mtr
G G.I pipe 3" dia meadium duty 6mtr
G G.I pipe 4" dia meadium duty 6mtr
G G.I pipe 4" dia 6mtr
Steel Material
Index
G G.I plain sheet G 18 8'x4' Sheet
G G.I plain sheet G 22 8'x3' Sheet
G G.I plain sheet G 30 8'x3' Sheet
G G.I welding mesh G10 2"x2" (12'x7') Sheet
B Box iron 1/2"x 1/2" x 6 mm box iron
B Box iron 1" x 1" x 6 mm box iron
B Box iron 25 x 25 x 3 mm box iron
F Flat iron Size 3/4"x1/4" 6mtr
F Flat iron Size 1/2"x1/4" 6mtr
F Flat iron Size 1"x1/4" 6mtr
F Flat iron Size 1 1/2"x1/4" 6mtr
F Flat iron Size 2"x1/4" 6mtr
F Flat iron Size 4"x1/4" 6mtr
M M.S sheet Size 8'x4'x1/16" Sheet
M M.S sheet Size 8'x4'x1/8" Sheet
M M.S sheet Size 8'x4'x1/4" Sheet
M M.S sheet Size 8'x4'x 10mm Sheet
M M.S sheet Size 8'x4'x 1/2" Sheet
M M.S sheet Size 8'x4'x 15mm Sheet
M M.S sheet Size 8'x4'x 9mm Sheet
S Steel plate
MS plate 8'-x4' 3mm
Nos
S Steel plate
MS plate 8'-x4' 6mm
Nos
S Steel plate
MS plate 8'-x4' 8mm
Nos
S Steel plate
MS plate 8'-x4' 10mm
Nos
S Stainless steel plate
8'-0" x4'-0" 1.5mm thick type 304
Nos
N Nail wire nail 5-to 8G Nos
N Nail wire nail 10G Nos
N Nail wire nail 12G Nos
N Nail wire nail 14G Nos
W
Wire nail
5 to 8G Kg
W
Wire nail
10G Kg
W
Wire nail
12G Kg
W
Wire nail
14G Kg
B Bolts
16mm bolt
Nos
B
S Steel "H" beam 8"x4"x7mm thick (22 kg per mtr ) 6m
S Steel "H" beam 8"x8"x11mm thick (50 kg per mtr ) 6m
S Steel "H" beam 10"x5"x8mm thick (26 kg per mtr ) 6m
S Steel "H" beam 14"x7"x6mm thick (41.5 kg per mtr ) 6m
S
BRC mesh B.R.C fabrick 12'x7" sheets 6mm
8"x8'
Sheet
S
BRC mesh B.R.C fabrick 12'x7" sheets 5mm
8"x8'
Sheet
S
BRC mesh B.R.C fabrick 12'x7" sheets 6mm
6"x6"
Sheet
S
BRC mesh B.R.C fabrick 12'x7" sheets 5mm
6"x6"
Sheet
S
BRC mesh B.R.C fabrick 12'x7" sheets 6mm
8"x8'
Sheet
S
BRC mesh B.R.C fabrick 12'x7" sheets 3.15mm
2"x2"
Sheet
S
BRC mesh B.R.C fabrick 12'x7" sheets 6mm
4"x4''
Sheet
S wire rod wire rods 6mm Mton
S
Barbed wire Barbed wire 25Kg
25kg
C Chicken mesh Sq.ft
C Chequred plate 6mm thick, 8' x 4' sheet Nos
C Sheet pil 450mm width, 6m long Nos
Currencet price Date Other Remark Telephone Price Date Price
106,400.00 14/8/2009 With VAT 113,000.00 3/3/2009 165,000.00
106,400.00 14/8/2009 With VAT 113,000.00 3/3/2009 65,700.00
59,000.00
100.00
325.00
810.00 11/4/2009
2,400.00 11/4/2009 875.00
1,600.00
3,000.00
775.00
2,400.00 27/5/2009
230.00
898.00 24/09/2008 480.00
2,400.00
3,000.00
4,394.00 10/10/2008
5,200.00
9,500.00
21,000.00
1,000.00 30/01/2009
740.00 30/01/2009
750.00 575.00
1,180.00 24/09/2008
1,220.00 11/4/2009 1,475.00
4,400.00 11/7/2008 950.00
1,900.00 1,400.00
3,150.00 24/09/2008
2,050.00 11/4/2009
8,850.00 11/7/2008 1,900.00
4,220.00 11/4/2009
3,300.00
4,300.00
1,050.00 24/09/2007
Steel Material
2,250.00
1,375.00
475.00
3,800.00 9/2/2009 1,375.00
2,200.00
850.00 11/4/2009
700.00 11/4/2009
650.00 27/4/2009 300.00
390.00 27/4/2009
495.00 27/4/2009 350.00
800.00 27/4/2009
575.00
1,300.00
1,800.00
2,700.00
5,300.00
35,000.00 6/5/2008 8,500.00
10,500.00
14,000.00
31,500.00 6/5/2008
6,900.00
14,000.00
18,500.00
34,000.00 12/8/2008
17,000.00 3/3/2009 Nawaloka 0115-323023
82.80
82.80
86.30
88.50
160.00 5/8/2008
170.00 5/8/2008
170.00 5/8/2008
170.00 5/8/2008
50.00

22,500.00 6/5/2008
52,000.00 6/5/2008
26,500.00 6/5/2008
47,300.00 12/8/2008
2,555.00 1,212.17
888.30
3,130.00 1,586.96
1,212.17
1,212.17
3,800.00 12/4/2009 1,332.17
4,500.00 2,380.00
4,818.00 12/8/2008
40.00
15,500.00 27/5/2009
70,000.00 28/09/2010
Date
11/5/2004
11/5/2004
11/5/2004
24/09/2008
11/5/2004
11/5/2004
11/5/2004
11/5/2004
11/5/2004
11/5/2004
11/5/2004
Code Category Description Remarks Unit Currencet price
C Cement Holcim 50kg bag 700.00
C Cement Sevana 50kg bag
C Cement 50kg bag 740.00
R Rubble Rubble 6"x 9" Cube 4,200.00
R Rubble Rubble 6"x 4" Cube 3,400.00
B Brick 9"x41/2"x 3" Nos 7.00
S Sand
Smooth sand
Cube 7,500.00
S Sand
Rough sand
Cube 7,000.00
S Sand
Sea sand
Cube 4,900.00
M Metal " metal Cube 4,800.00
M Metal 1" metal
M Metal " metal
M Chip metal Cube 3,750.00
L Lime Kg 14.50
B Hollow blocks 390x100x190mm (4") SMA holdings Nos 42.55
B Hollow blocks 390x150x190mm (6") Nos 62.67
B Hollow blocks 390x200x190mm (8") Nos 83.05
B Solid blocks 390x100x190m (4") Nos 59.86
B Solid blocks 390x150x190mm (6") Nos 82.82
B Solid blocks 390x200x190mm (8") Nos 115.83
R Regiform sheet 2" thick Nos 330.00
P Pergolas 2" x6" L.ft 90.00
P Pergolas
P Pergolas
Masonary meterial
Index
F Fence post 5'-9" Middle post No 784.00
F Fence post 7'-7" bend type No 1,211.28
F Fence post 8' No
F Fence post 9' No
F Fence post 10' No
F Fence post 8 height 1'6" bent type No
Path edge 50x150x600mm No 153.00
Curbe 125x255x915 Nr 580.00
Half curbe 125x255x450mm Nr 297.25
C Chemefix Kg 880.00
E
Earth with transport
imported 1 cube 2,200.00
Fwk Formwork Formwork Sanken M2 1,129.00
Fwk Formwork Maga M2
Fwk Formwork DG5 M2 1,150.00
Fwk Formwork Mould oill Ltr 20.00
Fwk Formwork Base plate No 175.00
Fwk Formwork Grease Kg 460.00
W Water bars 6" high l.ft 300.00
W Water bars 8" high l.ft 400.00
W Water bars 9" high l.ft 400.00
Q Quarry dust 1 cube 4,500.00
Date Other Remark Telephone Price Date
14/8/2009 785.00 12/4/2009
12/4/2009 630.00
785.00 12/4/2009
1/6/2009
23/05/2008
12/4/2009
12/4/2009
8/3/2009
12/4/2009
12/4/2009
11/10/2007
15/02/2010 With out VAT
15/02/2010
15/02/2010
15/02/2010 36.50 16/11/07
15/02/2010 57.50 16/11/07
15/02/2010 73.56
08.07.2008 With out VAT price
Masonary meterial
15/02/2010 Including VAT. SEC 2236279 303.00
15/02/2010 Including VAT 366.00
510.00
693.00
960.00
1,140.00
15/02/2010
15/02/2010
15/02/2010
17.04.2009 80.00
21/3/2009 1,750.00
12/8/2008
12/9/2009
12/8/2008
12/8/2008
12/8/2008
10/10/2008
Code Category Description Remarks Unit
C
R Roofing sheet Zn/Al sheet .47 m
R Roofing sheet Zn/Al sheet 4.7 2'-6" x 1'-0"=265/= Sq ft
Acrylic Sheet Sq ft
A Asbestos roofing sheet 12 ft (3500 x 1090mm) 4' Nos
A Asbestos roofing sheet 10 ft (3000 x 1090mm) 4' Nos
A Asbestos roofing sheet 8 ft (2500 x 1090mm) 4' Nos
A Asbestos roofing sheet 6 ft (1750 x 1090mm) 4' Nos
G GI roofing sheet 10 ft (3000 x 1090mm) 4' Nos
H Half round tile ( Sinhala Ulu) 420 per sqr Nos
R Calicut tile Flat tile 125 per sqr Nos
R Asbestos covering tile covering tile 450 per sqr Nos
R DSI Tile covering tile 138 per sqr Nos
T Ridge tile Ridge tile Nos
T Ridge tile Zn/Al G18 L.ft
T Ridge tile Asbastos ajestable Pair
R Roofing screws Nos
R
T Tar sheet Tar sheet Sq ft
J J bolt J bolt Nos
S Screws 1 1/4" Nos
J
P Polycorbanete sheet 4mm thick 6'-11" x 19'-0" Nos
P 6mm thick 6'-11" x 19'-0" Nos
Polycorbanete sheet Roller 4'-0" width 4mm thcik L.ft
4'-0" width 1mm thcik L.ft
7'-0" width 2mm thcik L.ft
P
R Insulation Mcfoil sheet Sq.m
R Insulation 50mm ,double side Sq ft
Roofing material
Index
R Insulation mesh Sq ft
R
R Macfoil 5mm double side m2
R 10mm double side m2
R
R
Sisilation domestic
100 Sq ft
R
Currencet price Date Other Remark Telephone
970.31 7/7/2008 With VAT
106.00 25/03/2009
150.00
1,685.00 15/2/2010 440 per sq. m Mascons -2325561
1,375.00 15/2/2010
1,165.00 15/2/2010
825.00 15/2/2010
510.00 2/6/2009
20.00 25/03/2009 3600 of one lorry load Randatha Ulu 060-2150285
28.00 25/03/2009
18.00 25/03/2009
150.00 25/03/2009
45.00 11/3/2005
135.00 25/03/2009
45.00
15.00
10.00
5.00 5/8/2008 195/= per 1 kg ( 38 Nos per kg)
8.35
9,000.00 31/2/2010
13,100.00 31/2/2010
560.00 31/2/2010
3,000.00 31/2/2010
1,600.00 31/2/2010
90.00 8/3/2009 077-7772857 /50 /56
26.50 8/3/2009 Roofmart 037-5260269
Roofing material
6.70 8/3/2009 Bor-0112519804
191.00 22/04/2009
338.00 22/04/2009
12.88
Price Date Price Date
1,680.00 5/8/2008 975.00 5/2/2005
1,370.00 5/8/2008 825.00 5/3/2005
1,160.00 5/8/2008 690.00 5/4/2005
820.00 5/8/2008 485.00 5/5/2005
Roofing material
Code Category Description Remarks
E Switches ( White series ) One gang one way
E Switches ( White series ) One gang two way
E Switches ( White series ) Two gang one way
E Switches ( White series ) Three gang one way
E Switches ( White series ) Four gang one way
E Switches ( White series ) Five gang one way
E Switches ( White series ) Six gang one way
E Switches ( White series ) 20A double pole W/ neon
S Socket outlet 5A switched Socket outlet
S Socket outlet 15A switched Socket with neon
S Socket outlet 15A switched Socket outlet
S Socket outlet 15A switched Socket with neon
S Socket outlet 13A switched Socket outlet
S Socket outlet 13A switched Socket with neon
S Socket outlet TV socket
S Socket outlet Twin TV socket
S Socket outlet Telephone socket outlet 4 line
S Socket outlet Telephone socket outlet 4 line
S Socket outlet Twin Telephone socket outlet 4 line
S Socket outlet Twin Telephone socket with shutter
S Socket outlet Telephone socket shutter ( fast rapid
connection)
S Socket outlet TwinTelephone socket shutter ( fast rapid
connection)
S Socket outlet Combine TV & Tel socket
S Socket outlet Data socket with shutter
S Socket outlet Tiwn Data socket with shutter
S Socket outlet 110V shaver socket
C Controllers Hum free fan controller
C Controllers Fan controller with swith 1 gang
C Controllers Light dimmer with swith 1 gang
C Controllers Bell press
C Controllers Bell push
Electrical Items
Index
C Controllers Bell push whether prrof W/indicator
C Controllers Weather proof cover transparent
C Controllers Weather proof cover mat
C Controllers Two way mechanisim dolly only
C Controllers Key switch
C Controllers 45A/ 13A cooker switch
C Controllers Fan controller with 21 gang
C Controllers Light dimmer with 2 gang
C Controllers Tumbler box
C Controllers Sun box
C Controllers Junction box
M MCB 6A ,10A , 16A, 20A, 25A, 32A Single pole 4.5A
M MCB 40A
M MCB 63A
M MCB 6A ,10A , 16A, 20A, 25A, 32A ,40ATwo pole
M MCB 63A
M MCB 6A ,10A , 16A, 20A, 25A, 32A ,40ATheree pole
M MCB 63A
M MCB 100A
M MCB 6A ,10A , 16A, 20A, 25A, 32A ,40A Four pole
M MCB 63A
M MCB 100A
I Isolater 2P/40A
I Isolater 2P/63A
I Isolater 4P/40A
I Isolater 4P/63A
I Isolater 4P/100A
C Changing over Switches 2P/40A
C Changing over Switches 4P/40A
B Cables- CU/PVC/PVC 2 Core 1.5mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 1.5mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 1.5mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 2.5mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 2.5mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 2.5mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 4mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 4mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 4mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 6mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 6mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 6mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 10mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 10mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 10mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 2 Core 16mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 3 Core 16mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 16mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 25mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 35mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 50mm2 Cu/PVC/PVC
B Cables- CU/PVC/PVC 4 Core 70mm2 Cu/PVC/PVC
B Cables- Cu/XLPE/PVC 2Core 4mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 4mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 6mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 6mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 10mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 10mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 16mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 16mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 25mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 3Core 25mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 25mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 2Core 35mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 3Core 35mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 35mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 50mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 70mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 95mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 120mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 150mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 185mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 240mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 300mm2 Cu/XLPE/PVC
B Cables- Cu/XLPE/PVC 4Core 400mm2 Cu/XLPE/PVC
B Cables- CU/PVC/PVC 1 Core x 1 mm Cu/PVC / PVC
earth
B Cables- CU/PVC/PVC 1 Core x 1.5 mm Cu/PVC /PVC
earth
B Cables- CU/PVC/PVC 1 Core x 2.5 mm Cu/PVC / PVC
earth
B Cables- CU/PVC/PVC 1 Core x 4 mm Cu/PVC /PVC
earth
B Cables- CU/PVC/PVC 1 Core x 6 mm Cu/PVC /PVC
earth
B Cables- CU/PVC/PVC 1 Core x 10 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 16 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 25 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 35 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 50 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 70 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 95 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 120 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 150 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 185 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 240 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC 1 Core x 300 mm Cu/PVC/PVC
earth
B Cables- CU/PVC/PVC
earth
B Cables- CU/PVC/PVC
earth
B Cables- XLPE/SWA/PVC 2 Core x 1 mm Cu/ XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 1 mm Cu/ XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 1 mm Cu/ XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 2 Core x 2.5 mm Cu/ XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 2.5 mm Cu/ XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 2.5 mm Cu/ XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 2 Core x 4 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 4 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 4 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 2 Core x 6 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 6 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 6 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 2 Core x 10 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 10 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 10 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 2 Core x 16 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 16 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 16 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 2 Core x 25 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 25 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 25 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 2 Core x 35 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 3 Core x 35 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 35 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 50 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 70 mmCu/ XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 95 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 120 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 150 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 185 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 240 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 300 mm Cu/XLPE/SWA/PVC armoured
B Cables- XLPE/SWA/PVC 4 Core x 400 mm Cu/XLPE/SWA/PVC armoured
Cables single core - Cu/PVC/PVC
Cables single core - Cu/PVC/PVC
Cables single core - Cu/PVC/PVC 1/1.13 mm Cu/PVC/PVC
1mm2
Cables single core - Cu/PVC/PVC 1/1.38 mm Cu/PVC/PVC
1.5mm2
Cables single core - Cu/PVC/PVC 7/0.53 mm Cu/PVC/PVC - S
1.5mm2
Cables single core - Cu/PVC/PVC 7/0.53 mm Cu/PVC/PVC - T
1.5mm2
Cables single core - Cu/PVC/PVC 7/0.67 mm Cu/PVC/PVC - S
2.5mm2
Cables single core - Cu/PVC/PVC 7/0.67 mm Cu/PVC/PVC - T
2.5mm3
Cables single core - Cu/PVC/PVC 7/0.85 mm Cu/PVC/PVC - S
4mm2
Cables single core - Cu/PVC/PVC 7/0.85 mm Cu/PVC/PVC - T
4mm2
Cables single core - Cu/PVC/PVC 7/1.04 mm Cu/PVC/PVC - S
6mm2
Cables single core - Cu/PVC/PVC 7/1.04 mm Cu/PVC/PVC - T
6mm2
Cables single core - Cu/PVC/PVC 7/1.35 mm Cu/PVC/PVC - S
10mm2
Cables single core - Cu/PVC/PVC 7/1.35 mm Cu/PVC/PVC - T
10mm2
Cables single core - Cu/PVC/PVC 7/1.70 mm Cu/PVC/PVC - S
16mm2
Cables single core - Cu/PVC/PVC 7/1.70 mm Cu/PVC/PVC - T
16mm2
Cables single core - Cu/PVC/PVC 7/2.14 mm Cu/PVC/PVC
25mm2
Cables single core - Cu/PVC/PVC 19/1.35 mm Cu/PVC/PVC - S
25mm2
Cables single core - Cu/PVC/PVC 19/1.53 mm Cu/PVC/PVC - S
35mm2
Cables single core - Cu/XLPC/PVC
Cables single core - Cu/XLPC/PVC 19/1.78 mm Cu/XLPC/PVC - S
50mm2
Cables single core - Cu/XLPC/PVC 19/2.14 mm Cu/XLPC/PVC - S
70mm2
Cables single core - Cu/XLPC/PVC 19/2.52 mm Cu/XLPC/PVC - S
95mm2
Cables single core - Cu/XLPC/PVC 37/1.78 mm Cu/XLPC/PVC - S
95mm2
Cables single core - Cu/XLPC/PVC 37/2.03 mm Cu/XLPC/PVC - S
120mm2
Cables single core - Cu/XLPC/PVC 37/2.25 mm Cu/XLPC/PVC - S
150mm2
Cables single core - Cu/XLPC/PVC 37/2.52 mm Cu/XLPC/PVC - S
185mm2
Cables single core - Cu/XLPC/PVC 61/2.25 mm Cu/XLPC/PVC - S
240mm2
Cables single core - Cu/XLPC/PVC 61/2.52 mm Cu/XLPC/PVC - S
300mm2
Cables single core - Cu/XLPC/PVC 61/2.85 mm Cu/XLPC/PVC - S
400mm2
Cables single core - Cu/XLPC/PVC 61/3.20 mm Cu/XLPC/PVC - S
500mm2
Cables single core - Cu/XLPC/PVC 91/3.00 mm Cu/XLPC/PVC - S
630mm2
D
C
Ceiling Rose
H
Holders
R
Round block
B
Brass screws 1"
B
Brass screws 1 1/2"
W
Flexible wire
W
Steel condute pipe 50mm dia , Length - 12' 6"
Ceiling mounted sprit AC unit
18000 Btu/hr
24000 Btu/hr
48000 Btu/hr
Unit Currencet price Date Other Remark Telephone Price
Nos 108.00 8/3/2009 84.00
Nos 172.00 8/3/2009 131.00
Nos 184.00 8/3/2009 144.00
Nos 265.00 8/3/2009 218.00
Nos 355.00 8/3/2009 291.00
Nos 442.00 8/3/2009 364.00
Nos 470.00 8/3/2009 440.00
8/3/2009
Nos 758.00 8/3/2009 617.00
8/3/2009
Nos 307.00 8/3/2009 249.00
Nos 354.00 8/3/2009 271.00
Nos 378.00 8/3/2009 304.00
Nos 451.00 8/3/2009 331.00
Nos 325.00 8/3/2009 257.00
Nos 8/3/2009
Nos 507.00 8/3/2009 400.00
Nos 642.00 8/3/2009 Kevilton 600.00
Nos 507.00 8/3/2009 400.00
Nos 470.00 8/3/2009 440.00
Nos 642.00 8/3/2009 600.00
Nos 631.00 8/3/2009 590.00
Nos 406.00 8/3/2009 380.00
Nos 610.00 8/3/2009 570.00
Nos 589.00 8/3/2009 550.00
Nos 1,077.00 8/3/2009 915.00
Nos 1,252.00 8/3/2009 1,170.00
Nos 3,210.00 8/3/2009 3,000.00
8/3/2009
Nos 819.00 8/3/2009 700.00
Nos 760.00 8/3/2009 587.00
Nos 760.00 8/3/2009 587.00
Nos 260.00 8/3/2009 195.00
Nos 260.00 8/3/2009 195.00
Electrical Items
Nos 500.00 8/3/2009 400.00
Nos 230.00 8/3/2009 185.00
Nos 230.00 8/3/2009 185.00
Nos 78.00 8/3/2009 73.00
Nos 3,010.00 8/3/2009 2,800.00
Nos 1,290.00 8/3/2009 1,200.00
Nos 667.00 8/3/2009 60.00
Nos 667.00 8/3/2009 620.00
Nos 102.00 8/3/2009 70.00
Nos 32.00 8/3/2009 30.00
Nos 29.00 8/3/2009 27.00
Nos 529.00 9/8/2008 With VAT -Kalani cable 0112-2574511-5
Nos 1,035.00 9/8/2008
Nos 1,610.00 9/8/2008
Nos 1,955.00 9/8/2008
Nos 4,025.00 9/8/2008
Nos 2,875.00 9/8/2008
Nos 5,750.00 9/8/2008
Nos 19,550.00 9/8/2008
Nos 7,130.00 9/8/2008
Nos 9,775.00 9/8/2008
Nos 21,850.00 9/8/2008
Nos 1,322.50 9/8/2008
Nos 1,955.00 9/8/2008
Nos 5,750.00 9/8/2008
Nos 6,325.00 9/8/2008
Nos 8,050.00 9/8/2008
Nos 3,680.00 9/8/2008
Nos 4,600.00 9/8/2008
1m 280.00 ACL CABLE
1m 340.00
1m 410.00
1m 380.00
1m 500.00
1m 560.00
1m 760.00
1m 820.00
1m 840.00
1m 950.00
1m 1080.00
1m 1140.00
1m 1190.00
1m 1590.00
1m 1830.00
1m 1700.00
1m 2060.00
1m 2400.00
1m
1m
1m
1m
1m 2280.00
1m 2750.00
1m 3160.00
1m 3050.00
1m 3390.00
1m 3840.00
1m 5240.00
1m 7020.00
1m 9660.00
1m 11370.00
1m 14200.00
1m 19040.00
1m 22230.00
1m 28740.00
1m 38220.00
100m 1,810.00 3/3/2009 1750.00
100m 3760.00
100m 5540.00
100m 8650.00
100m 12570.00
100m 20710.00
100m 31590.00
100m 54500.00
100m 70410.00
100m 86700.00
100m 143010.00
100m 179510.00
100m 248650.00
100m 282570.00
100m 353100.00
100m 522580.00
100m 668040.00
1m 290.00
1m 350.00
1m 430.00
1m 390.00
1m 520.00
1m 580.00
1m 800.00
1m 860.00
1m 880.00
1m 1000.00
1m 1130.00
1m 1190.00
1m 1250.00
1m 1670.00
1m 1920.00
1m 1780.00
1m 2160.00
1m 2520.00
1m 2400.00
1m 2890.00
1m 3320.00
1m 3210.00
1m 3560.00
1m 4040.00
1m 5510.00
1m 7380.00
1m 10160.00
1m 11960.00
1m 14940.00
1m 20040.00
1m 23400.00
1m 30250.00
1m 40230.00
100m 1850.00
100m 3830.00
100m 4160.00
100m 7920.00
100m 6150.00
100m 11540.00
100m 9610.00
100m 18170.00
100m 13960.00
100m 24930.00
100m 23010.00
100m 41340.00
100m 35090.00
100m 62420.00
100m 56940.00
100m 60550.00
100m 78230.00
100m 96330.00
100m 158890.00
100m 199450.00
100m 205450.00
100m 276270.00
100m 313960.00
100m 392330.00
100m 580640.00
100m 742260.00
100m 908330.00
100m 1173420.00
100m 1468140.00
Nos 35.00
Nos 65.00
Nos 20.00
Nos 10.00
Nos 5.00
Nos 25.00
3,500.00
99,900.00 LG brand
127,900.00
429,000.00
Date
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
9/8/2008
Code Category Description
E Iron mongery
B Brass screws 1"
B Brass screws 3/4"
B Brass screws 1/2"
B Barrel bolt Brass 4"
B Barrel bolt 6"
B Barrel bolt Brass 8"
B Barrel bolt 12"
B Barrel bolt 1' 6"
Barrel bolt Brass 24"
B
B Barrel bolt stinless steel 4"
B Barrel bolt stinless steel 6"
B Barrel bolt stinless steel 8"
B Barrel bolt stinless steel 10"
B Barrel bolt stinless steel 12"
B Barrel bolt stinless steel 18"
B Barrel bolt stinless steel 2"
T Tower Bolts Metal 2 1/2"
T Tower Bolts Metal 3"
T Tower Bolts Metal 4"
T Tower Bolts Metal 5"
T Tower Bolts Metal 6"
T Tower Bolts Metal 12"
T Tower Bolts Metal 14"
T Tower Bolts Metal 16"
B Butt hinges 6"x 4"
B Butt hinges 6"x 6"
B Butt hinges 3"x 4"
B Butt hinges 2 1/2"x 4"
B Butt hinges Brass 3"x 4"
Doors windows materila
Index
H Heavy Butt Hinges Metal 2" x 2"
H Heavy Butt Hinges Metal 3" x 2"
H Heavy Butt Hinges Metal 3" x 3"
H Heavy Butt Hinges Metal 4" x 2"
H Heavy Butt Hinges Metal 4" x 2 1/2"
H Heavy Butt Hinges Metal 4" x 3"
H Heavy Butt Hinges Metal 4" x 4"
H Heavy Butt Hinges Metal 5" x 3"
H Heavy Butt Hinges Metal 5" x 4"
H Heavy Butt Hinges Metal 5" x 5"
H Heavy Butt Hinges Metal 6" x 4"
H Heavy Butt Hinges Metal 6" x 6"
H Heavy Tee Hinges Metal 4"
H Heavy Tee Hinges Metal 5"
H Heavy Tee Hinges Metal 6"
H Heavy Tee Hinges Metal 8"
H Heavy Tee Hinges Metal 10"
H Heavy Tee Hinges Metal 12"
H Heavy Tee Hinges Metal 14"
H Heavy Tee Hinges Metal 16"
B Brass barrel nipple 1/2" diameter
B Brass barrel nipple
B Brass barrel nipple
C Casement fastner
C Casement fastner
C Casement fastner
C Casement stays Metal 10"
C Casement stay
C Casement stay
C Casement stay
M Mortice lock
M Mortice lock
M Mortice lock
U Union lock
H Hasps & Staples Metal 2 1/2"
H Hasps & Staples Metal 3"
H Hasps & Staples Metal 4"
H Hasps & Staples Metal 5"
H Hasps & Staples Metal 6"
W Window Fasterners Metal Left
W Window Fasterners Metal Right
W Window Rings Metal
S Sliding gear
S Sliding gear
S Sliding gear
G Glass Tempeted glass 12'-0" x 8'-0'
G Glass 5mm thick clear glass
Glass 6mm thick clear glass
G Glass 6.3mm thick laminated clear glass
G Glass Sand blast glass 6mm thick one side
G Glass Pencil edgge
P Plywood doors Ordinary/MR 2'-3"
P Plywood doors Ordinary/BR 2'-3'
P Plywood doors Teak one side MR 2'-3"
P Plywood doors Teak one side BR 2'-3"
P Plywood doors Teak two side MR 2'-3"
P Plywood doors Teak two side BR 2'-3'
P Plywood doors
P Plywood doors Ordinary/MR 2'-6"
P Plywood doors Ordinary/BR 2'-6'
P Plywood doors Teak one side MR 2'-6"
P Plywood doors Teak one side BR 2'-6"
P Plywood doors Teak two side MR 2'-6"
P Plywood doors Teak two side BR 2'-6'
P Plywood doors
P Plywood doors Ordinary/MR 2'-9"
P Plywood doors Ordinary/BR 2'-9'
P Plywood doors Teak one side MR 2'-9"
P Plywood doors Teak one side BR 2'-9"
P Plywood doors Teak two side MR 2'-9"
P Plywood doors Teak two side BR 2'-9'
P Plywood doors
P Plywood doors Ordinary/MR 3'-0"
P Plywood doors Ordinary/BR 3'-0'
P Plywood doors Teak one side MR 3'-0"
P Plywood doors Teak one side BR 3'-0"
P Plywood doors Teak two side MR 3'-0"
P Plywood doors Teak two side BR 3'-0'
P Plywood doors
P Plywood doors Ordinary/MR 3'-6"
P Plywood doors Ordinary/BR 3'-6'
P Plywood doors Teak one side MR 3'-6"
P Plywood doors Teak one side BR 3'-6"
P Plywood doors Teak two side MR 3'-6"
P Plywood doors Teak two side BR 3'-6'
F Fibre Window
D Finish dooor 3'-6" x 7'-0" Jack
D Finish dooor 3'-6" x 7'-0" Mahogani
D
D Roller door Zn/Al
D Roller door
D Roller door Moter
D
Remarks Unit Currencet price Date Other Remark
No 8.35
No 5.58
No
No 250.00 29/12/2008
No 490.00 13/10/2008
No 435.00 29/12/2008
No 550.00
No 2,600.00 13/10/2008
No 1,800.00 29/12/2008
No 185.00 4/3/2009
No 195.00 4/3/2009
No 305.00 4/3/2009
No 415.00 4/3/2009
No 520.00 4/3/2009
No 550.00 4/3/2009
No 52.00 4/3/2009
Powder coated finish-Metco Gold 1 No 104.00 8/3/2009
1 No 138.25 8/3/2009
1 No 152.75 8/3/2009
1 No 168.75 8/3/2009
1 No 180.25 8/3/2009
1 No 325.50 8/3/2009
1 No 364.00 8/3/2009
1 No 410.00 8/3/2009
pair 1,100.00
pair
pair 360.00
pair 275.00
Indian No 180.00 29/12/2008
Doors windows materila
Powder coated finish-Metco Gold 1 No 49.00 8/3/2009
1 No 65.00 8/3/2009
1 No 77.75 8/3/2009
1 No 93.25 8/3/2009
1 No 101.00 8/3/2009
1 No 126.75 8/3/2009
1 No 181.75 8/3/2009
1 No 190.75 8/3/2009
1 No 227.75 8/3/2009
1 No 271.25 8/3/2009
1 No 286.75 8/3/2009
1 No 358.50 8/3/2009
Powder coated finish-Metco Gold 1 No 109.50 8/3/2009
1 No 126.50 8/3/2009
1 No 165.25 8/3/2009
1 No 248.00 8/3/2009
1 No 274.50 8/3/2009
1 No 309.00 8/3/2009
1 No 523.75 8/3/2009
1 No 571.50 8/3/2009
No
Powder coated finish-Metco Gold 1 No 190.75 8/3/2009
1 No 2,910.00
2,900.00
Powder coated finish-Metco Gold 1 No 50.75 8/3/2009
1 No 58.50 8/3/2009
1 No 109.00 8/3/2009
1 No 119.00 8/3/2009
1 No 216.00 8/3/2009
Powder coated finish-Metco Gold 1 No 102.00 8/3/2009
1 No 102.00 8/3/2009
Powder coated finish-Metco Gold 1 No 69.00 8/3/2009
11 3,360.00 15/10/2008
11 2,670.00 15/10/2008
8 2,170.00 15/10/2008
Sq.ft 450.00 4842
without VAT Sq.ft 75.00 3/3/2009 Asoka glass
with VAT Sq.ft 100.00 27/4/2009
without VAT Sq.ft 280.00 3/3/2009 Asoka glass
Sq.ft 215.00 11/12/2008
L.ft 70.00 11/12/2008
Nos 3,950.00 8/3/2009
Nos 4,100.00 8/3/2009
Nos 4,100.00 15/02/2007
Nos 4,250.00 15/02/2007
Nos 5,100.00 15/02/2007
Nos 5,250.00 15/02/2007
Nos 4,000.00 8/3/2009
Nos 4,150.00 8/3/2009
Nos 4,250.00 15/02/2007
Nos 4,400.00 15/02/2007
Nos 5,200.00 15/02/2007
Nos 5,350.00 15/02/2007
Nos 4,125.00 8/3/2009
Nos 4,275.00 8/3/2009
Nos 4,350.00 15/02/2007
Nos 4,500.00 15/02/2007
Nos 5,250.00 15/02/2007
Nos 5,400.00 15/02/2007
Nos 4,725.00 8/3/2009
Nos 4,875.00 8/3/2009
Nos 4,700.00 15/02/2007
Nos 4,850.00 15/02/2007
Nos 5,650.00 15/02/2007
Nos 5,800.00 15/02/2007
Nos 4,850.00 8/3/2009
Nos 5,000.00 8/3/2009
Nos 4,800.00 15/02/2007
Nos 4,950.00 15/02/2007
Nos 5,750.00 15/02/2007
Nos 5,900.00 15/02/2007
1 Sq.ft 1200.00-3000.00 8/3/2009
Nos 20,000.00 8/3/2009
Nos 14,500.00 8/3/2009
Sq.ft 700.00 21/04/2009
16' 0" x 8' 0" Nos 30,000.00 21/04/2009
Nos 35,000.00 21/04/2009
Telephone Price Date
190.00 13/10/2008
Doors windows materila
20.00
0112-314820-2
90.00 3/3/2009
0112-314820-2
2,800.00 15/02/2007
2,950.00 15/02/2007
2,900.00 15/02/2007
3,050.00 15/02/2007
3,100.00 15/02/2007
3,250.00 15/02/2007
3,600.00 15/02/2007
3,750.00 15/02/2007
3,850.00 15/02/2007
4,050.00 15/02/2007
Code Category Description
Pentalite Emulsion Paints
P Painting Items Emulsion paint
P Painting Items Emulsion paint
P Painting Items Emulsion paint -CIC
P Painting Items Emulsion paint
P Painting Items Emulsion paint
P Painting Items Emulsion paint
P Painting Items Eanemal paint
P Painting Items wood paint
P Painting Items Aluminium paint
P Painting Items Roof paint
P Painting Items Aluminium sealer
P Painting Items Alkali Resistant plaster primer
P Painting Items G.I. Adhession promoter
P Painting Items Q/D Zinc phosphate red primer
P Painting Items Q/D MIO paint silver Grey
P Painting Items Q/D Metal primer Zinc phospate yellow / block
P Painting Items crack bridging wall primer
P Painting Items Colour enhancing wall primer
Painting Items Q/D P/U floor paint
Painting Items Epoxy paint white
Painting Items Blackboard paint
Painting Items Epoxy floor paint
Painting Items Bathroom paint
Painting Items Heat resistance paint
Painting Items Masonary sealer
Painting Items Weathersshield texture base
Painting Items Interior texture base
Painting Items Acrylic wall filler
Painting Items Acrylic wall putty
Painting Items Flexible filler
Painting Items Masonary water repellant
Painting Items Super grip filler
Painting Items
Index
Painting Items Master palette emulsion ( dark colours)
Painting Items Master palette emulsion ( light colours)
Painting Items Master palette weathershield ( dark colours)
Painting Items Master palette weathershield ( light colours)
Painting Items Master palette gloss ( dark colours)
Painting Items Master palette gloss ( light colours)
Painting Items Anicorrsive paint
Painting Items Anicorrsive paint
Painting Items Polyurethane varnish -Gloss
Painting Items Polyurethane varnish -Matt
Painting Items Coach finish varnish - gloss
Painting Items Coach finish varnish - matt
Painting Items Exterior varnish - gloss
Painting Items Exterior varnish - matt
Painting Items Parquet varnish
Painting Items Teak oil
Painting Items Woodfinish gloss lacquer
Painting Items Woodfinish stain
Painting Items Sanding sealer concentrate
Painting Items Sanding sealer rosewood
Painting Items woodfiller ( clear)
Painting Items Wood sheen ( Mshogany , Teak , Walnut, Ebony, Pine)
Painting Items Woodstain ( Mshogany , Teak , Walnut, Jackwood )
Painting Items Thinner 850-8
Painting Items Epoxy thinner 850-761
Painting Items Mineral turpentine
Painting Items Parquet varnish thinner
Painting Items Enamel paint
Painting Items sand paper
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Brush
Painting Items Roller Brush
Painting Items Oil primer
Painting Items Oil primer
Painting Items Oil primer
Painting Items Oil primer
Painting Items Filler
Painting Items Filler
Painting Items Filler
Painting Items Filler
Painting Items Enamal paint
Painting Items Enamal paint
Painting Items Enamal paint
Painting Items Enamal paint
Painting Items Thinner (Autocare N/C Super)
Painting Items Thinner (Autocare N/C GP)
Painting Items Thinner (Autocare GP)
Painting Items Thinner (Asian Paint Epoxy)
Painting Items Thinner (Asian Paint Mineral Turpentine)
Painting Items Thinner (Metacare Stoving Thinner 050)
Painting Items Thinner (Metacare Stoving Thinner CCS)
Painting Items Thinner (Autocare Acrylic Thinner)
Painting Items Wood preservitive
Painting Items Wood preservitive
Painting Items Wood primer
Painting Items Wood primer
Painting Items Wood primer
Painting Items Wall primer
Painting Items Wall primer
Painting Items Wood stain
Painting Items Wood stain
Painting Items Wood stain
Painting Items Wood finish stain
Painting Items Wood finish stain
Painting Items Wood finish stain
Painting Items Wood finish stain
Painting Items
Steel primer
Painting Items Totalcoat
Painting Water base
Painting Spray paint
Wall putty 28Kg bag
Remarks Unit Currencet price Date Other Remark
11/8/2008 CIC price list -11th Aug 2008
White & all colours Ltr 550.00 16/02/2010
Brilllian white Ltr 700.00
weathershield all colour Ltr 750.00 16/02/2010
Dulux gloss finish Ltr
White & all colours Ltr 768.00
Brilllian white Ltr 780.00
Dulux egshell finish ( Black & white) Ltr 857.00
Stain wood Ltr 1,029.00
bright aluminium Ltr 844.00
Roofshied (water base ) all colour Ltr 879.00
Aluminium paint Ltr 723.00
Ltr 805.00
Ltr 494.00
Ltr 928.00
Ltr 1,074.00
Ltr
Ltr 955.00
Ltr 851.00
Ltr 884.00
Ltr
Ltr
Ltr 1,085.00
Ltr 892.00
Ltr 1,619.00
Ltr 560.00
Ltr 339.00
Ltr 328.25
Ltr 416.00
Ltr 631.00
Ltr 758.00
Ltr 564.50
400 gram 182.00
Painting Items
Ltr 705.00
Ltr 648.00
Ltr 1,077.00
Ltr 1,017.00
Ltr 916.00
Ltr 818.00
Black, red, Oxide, Brown Ltr 586.00
Grey , Green Ltr 601.00
Ltr 797.00
Ltr 879.00
Ltr 697.00
Ltr 767.00
Ltr 895.00
Ltr 1,191.00
Ltr 867.00
Ltr 472.75
Ltr 980.00
Ltr 980.00
Ltr 1,069.00
Ltr 1,156.00
Ltr
Ltr 781.00
Ltr 845.00
Ltr
Ltr 260.00
Ltr 432.75
Ltr 262.75
Ltr 351.00
Enamel paint Ltr 622.00
Nos 42.50
1/2" 100.00 8/3/2009
3/4" 115.00 8/3/2009
1" 145.00 8/3/2009
1 1/2" 185.00 8/3/2009
2" 280.00 8/3/2009
2 1/2" 325.00 8/3/2009
3" 400.00 8/3/2009
6" 595.00 8/3/2009
9" 595.00 8/4/2009
10 Ltr Bucut 2,844.00
4 Ltr Bucut 1,138.00
1 Ltr Ltr 337.00
Ltr 525.00
Permoglaze Enamel
Eggshell Finish 4 Ltr 2,168.00
Matt Finish 4 Ltr 2,071.00
1 Ltr 553.00
4 Ltr 2,184.00 8/3/2009
4 Ltr 1,511.00 8/3/2009
4 Ltr 1,280.80 8/3/2009
4 Ltr 2,499.00 8/3/2009
4 Ltr 1,607.00 8/3/2009
4 Ltr 1,468.00 8/3/2009
Normal
4 Ltr 1,352.00 8/3/2009
4 Ltr 2,268.00 8/3/2009
1 Ltr 242.50 5/8/2008
Asian paints Aluminium wood primer 4 Ltr 2,077.00
1 Ltr 555.00
0.5 Ltr 301.00
1 312.75
4 Ltr 2,300.00 575
300 ml 230.00
4 Ltr 2,906.00
1 Ltr 795.00
500 ml 432.00
1 Ltr 973.00 8/3/2009
Bucut 28 kg 2,800.00 8/3/2009
Sq.ft 88.00 8/3/2009
Sq.ft 88.00 8/3/2009
bag 2,100.00
Telephone Price Date
Painting Items
450.00
167.50 9/2/2005
Code Category Description Remarks Unit Currencet price
Waterproofing material Febmix iLtr
Waterproofing material M.C. 31 1Ltr
Waterproofing material DPC tar bitumen gal 530.00
Waterproofing material shell fintkote type 3 Ltr 231.00
Waterproofing material shell fintkote type 5 Ltr 242.00
W Water Proofing 1 m
2
875.00
W Water Proofing Barralastic Without Screed 1Sq.ft 96.00
Waterproofing material
Index
Date Other Remark Telephone Price Date
101.25
27.25
26/04/2009
Waterproofing material
Code Category Description Remarks
Colour cement Red super dark
Colour cement Dark brown
Colour cement Black special
Colour cement Briliant blue extra
Colour cement Green tennis court
Colour cement White cement
Colour cement White cement
T Tile
6" x 6"
T Tile
8" x 8"
T Tile
12" x 12"
T wall tile
6" x 6"
T wall tile
8" x12"
T wall tile
8" x 8"
T wall tile
12" x 12"
T
T wall tile
200mm wide Boder tile
T
T
T Tile
Slate tile 1'-0' 1'-0"
T
T Concrete paving slab
12" x12"
T Concrete paving slab
6" x 6"
T Concrete paving slab
16" x16"
T Concrete paving slab
300x300x50mm Natural
Colour
Natural ( with R/F )
T Tile
Mosaic tile
T
T Tile
Terracota tile 8" x 8"
T Tile
Terracota tile 1'-0" x 1'-0"
T
Floor / wall / Ceiling finishing material
Index
T Tile
Cement Tile 1'-0" x 1'-0"
Tile
16"x16"
Tile
12" x12" Staircase
Tile
16" x16"
Tile
12" x12" bathroom floor
T Tile
12" x12" Bathroom wall
Tile
G Granite Blue fal
G Granite Shiva Gold
G Granite Green Galaxy
G Granite Natural stone 4" x8"
G Granite Natural stone 12" x6"
G
Rough granite "Mirisgal" 1'-0" x1'-0"
Rough granite
Coble stone 9" x 5"
Rough granite Rubble stone (1'0"x1'0" )
Rough granite
Pebbles (50 Kg)
T Tile grout
Terrazzo chips
Titanium
C Construction grout
P External Paving tile Including labour cost
Adhesive glue
Interlocking Paving With Quary Dust
C Ceiling sheet 3.2mm superflex sheet 4'-0" x 4'-0"
C Ceiling sheet 6mm superflex sheet 8'-0" x 4'-0"
C
C Ceiling sheet 9mm Gypsum sheet 4'-0" x 4'-0"
C Ceiling sheet 12mm Gypsum sheet 4'-0" x 4'-0"
C Ceiling sheet Asbestos sheet 4'-0" x4'-0"
C
C Ceiling sheet 1 1/2"x1 1/2" cove moulding
C Ceiling sheet 1/2"x1/2" beading
C
T
Lumumidella plank
6" thick width ( with planing )
Ceiling finishes Concealed ceiling with bulk head
system using " Euro frame" suspended
fames work
Ceiling finishes Mineral fiber ceiling system with
600x600mm frame work
15mm thick
Ceiling finishes Cement finber board / Moisture
resistant 600x600x4.5mm thick
4.5mm thick
Unit Currencet price Date Other Remark Telephone Price Date
kg 456.00 9/8/2008 Mascons Ltd 2325561-3
kg 589.25 9/8/2008 Mascons Ltd
kg 493.25 9/8/2008 Mascons Ltd
kg 640.50 9/8/2008 Mascons Ltd
kg 547.25 9/8/2008 Mascons Ltd
kg 33.80 9/8/2008 Mascons Ltd
bag 1,300.00
80.00 1/6/2009
150.00 1/6/2009 138/= to 173/=
Nos 210.00
Nos 78.75 9/8/2008 Mascons Ltd with VAT
Nos 37.00
Nos 250.00 12/12/2008
Nr 88.00 15/102/2010 SMA holdings
Nr 123.00 15/102/2010
Nr 147.00 15/102/2010
Sq.ft 750.00
nos 28.00 25/03/2009
nos 60.00 25/03/2009
Floor / wall / Ceiling finishing material
nos 180.00 1/6/2009
Sq.ft 160.00 40,277.00
Sq.ft 145.00 40,277.00
Sq.ft 132.00 40,277.00
Sq.ft 140.00 40,277.00
Sq.ft 104.00
Sq.ft 2,650.00 12/8/2008
Sq.ft 975.00 12/8/2008
Sq.ft 1,700.00 12/8/2008
Nos 83.00 12/8/2008
Nos 274.00 12/8/2008
Nos 350.00 20/03/2009
Nos 200.00
Sq.ft 3,000.00
50 kg 7,500.00
kg 155.00
Cwt 950.00
kg 525.00 12/4/2009
25Kg sack 1,147.50
Sq.ft 185.00 8/3/2009
Sq.ft 100.00 8/4/2009
Sq.ft 165.00 9/11/2009 011-2796003
Pavex(Pvt)Ltd
Sheet 400.00 24/10/2008
Sheet 1,840.00 12/4/2009
Sheet 1,175.00 26/4/2009
Sheet 1,350.00 26/4/2009
Nos 380.00 15/2/2010 255.55
Sq.ft 56.00 5/8/2008 NAM timber Tel 2818800
m2 3,775.00 3/11/2008 Access ( Rate without VAT)
m2 2,000.00 3/11/2008 Access ( Rate without VAT)
m2 2,167.00 3/11/2008 Access ( Rate without VAT)
Code Category Description Remarks
P PVC pipe 20mm -1/2" Type 1000
P PVC pipe 25mm - 3/4" Type 1000
P PVC pipe 32mm - 1" Type 1000
P PVC pipe 40mm - 11/4" Type 1000
P PVC pipe 50mm - 11/2" Type 1000
P PVC pipe 63mm - 2" Type 1000
P PVC pipe 75mm - 2 1/2" Type 1000
P PVC pipe 90mm - 3" Type1000
P PVC pipe 110mm - 4" Type1000
P PVC pipe 140mm - 5" Type1000
P PVC pipe 160mm - 6" Type1000
P PVC pipe 225mm - 8" Type1000
P PVC pipe 280mm - 10" Type 1000
P PVC pipe 315mm - 12" Type 1000
P PVC pipe 32mm - 1" Type 600
P PVC pipe 40mm - 11/4" Type 600
P PVC pipe 50mm - 11/2" Type 600
P PVC pipe 63mm - 2" Type 600
P PVC pipe 75mm - 2 1/2" Type 600
P PVC pipe 90mm - 3" Type 600
P PVC pipe 110mm - 4" Type 600
P PVC pipe 140mm - 5" Type 600
P PVC pipe 160mm - 6" Type 600
P PVC pipe 225mm - 8" Type 600
P PVC pipe 280mm - 10" Type 600
P PVC pipe 315mm - 12" Type 600
P PVC pipe 50mm - 11/2" Type 400
P PVC pipe 63mm - 2" Type 400
P PVC pipe 75mm - 2 1/2" Type 400
P PVC pipe 90mm - 3" Type 400
P PVC pipe 160mm - 6" Type 400
P PVC pipe 225mm - 8" Type 400
P PVC pipe 280mm - 10" Type 400
Plumbing material
Index
P PVC pipe 315mm - 12" Type 400
P PVC fittings - clip 20mm -1/2"
P PVC fittings - clip 25mm - 3/4"
P PVC fittings - clip 32mm - 1"
P PVC fittings - clip 40mm - 11/4"
P PVC fittings - clip 50mm - 11/2"
P PVC fittings - clip 63mm - 2"
P PVC fittings - clip 75mm - 2 1/2"
P PVC fittings - clip 90mm - 3"
P PVC fittings - clip 110mm - 4"
P PVC fittings - cap 20mm -1/2"
P PVC fittings - cap 25mm - 3/4"
P PVC fittings - cap 32mm - 1"
P PVC fittings - cap 40mm - 11/4"
P PVC fittings - cap 50mm - 11/2"
P PVC fittings - cap 63mm - 2"
P PVC fittings - cap 75mm - 2 1/2"
P PVC fittings - cap 90mm - 3"
P PVC fittings - cap 110mm - 4"
P PVC fittings - elbow 20mm -1/2"
P PVC fittings - elbow 25mm - 3/4"
P PVC fittings - elbow 32mm - 1"
P PVC fittings - elbow 40mm - 11/4"
P PVC fittings - elbow 50mm - 11/2"
P PVC fittings - elbow 63mm - 2"
P PVC fittings - elbow 75mm - 2 1/2"
P PVC fittings - elbow 90mm - 3"
P PVC fittings - elbow 110mm - 4"
P PVC fittings - equal tee 20mm -1/2"
P PVC fittings - equal tee 25mm - 3/4"
P PVC fittings - equal tee 32mm - 1"
P PVC fittings - equal tee 40mm - 11/4"
P PVC fittings - equal tee 50mm - 11/2"
P PVC fittings - equal tee 63mm - 2"
P PVC fittings - equal tee 75mm - 2 1/2"
P PVC fittings - equal tee 90mm - 3"
P PVC fittings - equal tee 110mm - 4"
P PVC fittings - faucet socket 20mm -1/2"
P PVC fittings - faucet socket 25mm - 3/4"
P PVC fittings - faucet socket 32mm - 1"
P PVC fittings - faucet socket 40mm - 11/4"
P PVC fittings - faucet socket 50mm - 11/2"
P PVC fittings - faucet socket 63mm - 2"
P PVC fittings - faucet socket 75mm - 2 1/2"
P PVC fittings - faucet socket 90mm - 3"
P PVC fittings - faucet socket 110mm - 4"
P PVC fittings - bend 20mm -1/2"
P PVC fittings - bend 25mm - 3/4"
P PVC fittings - bend 32mm - 1"
P PVC fittings - bend 40mm - 11/4"
P PVC fittings - bend 50mm - 11/2"
P PVC fittings - bend 63mm - 2"
P PVC fittings - bend 75mm - 2 1/2"
P PVC fittings - bend 90mm - 3"
P PVC fittings - bend 110mm - 4"
P PVC fittings - socket 20mm -1/2"
P PVC fittings - socket 25mm - 3/4"
P PVC fittings - socket 32mm - 1"
P PVC fittings - socket 40mm - 11/4"
P PVC fittings - socket 50mm - 11/2"
P PVC fittings - socket 63mm - 2"
P PVC fittings - socket 75mm - 2 1/2"
P PVC fittings - socket 90mm - 3"
P PVC fittings - socket 110mm - 4"
P PVC fittings - valve socket 20mm -1/2"
P PVC fittings - valve socket 25mm - 3/4"
P PVC fittings - valve socket 32mm - 1"
P PVC fittings - valve socket 40mm - 11/4"
P PVC fittings - valve socket 50mm - 11/2"
P PVC fittings - valve socket 63mm - 2"
P PVC fittings - valve socket 75mm - 2 1/2"
P PVC fittings - valve socket 90mm - 3"
P PVC fittings - valve socket 110mm - 4"
P PVC conduit pipe 18mm 5/8"
P PVC conduit pipe 20mm 3/4"
P PVC conduit pipe 25mm 1"
P PVC conduit pipe 30mm 1 1/4"
P PVC conduit pipe 40mm 11/2"
P PVC conduit pipe 50mm 2"
P PVC conduit pipe 90mm T 1000
P PVC conduit pipe 110mm T 1000
PVC conduit fittings - bend 18 mm
PVC conduit fittings - bend 20 mm
PVC conduit fittings - bend 25 mm
PVC conduit fittings - bend 30 mm
PVC conduit fittings - bend 40 mm
PVC conduit fittings - bend 50 mm
PVC conduit fittings - socket 18 mm
PVC conduit fittings - socket 20 mm
PVC conduit fittings - socket 25 mm
PVC conduit fittings - socket 30 mm
PVC conduit fittings - socket 40 mm
PVC conduit fittings - socket 50 mm
PVC conduit fittings - saddle 18 mm
PVC conduit fittings - saddle 20 mm
PVC conduit fittings - saddle 25 mm
PVC conduit fittings - saddle 30 mm
PVC conduit fittings - saddle 40 mm
PVC conduit fittings - saddle 50 mm
Roof plumbing - gutter Square Gutter
Roof plumbing - gutter Half Round Gutter
Roof plumbing - gutter fittings Running Head
Roof plumbing - gutter fittings Gutter Joiner
Roof plumbing - gutter fittings Mitre Joiner
Roof plumbing - gutter fittings End Cap
Roof plumbing - gutter fittings Gutter Box
Roof plumbing - gutter fittings Gutter Bracket-A
Roof plumbing - gutter fittings Gutter Bracket-B
Roof plumbing - down pipe Down Pipe
Roof plumbing - down pipe fittings Down Spout Elbow
Roof plumbing - down pipe fittings Down Spout Joiner
Roof plumbing - down pipe fittings Down Spout Clip
New Rain Water Gutter System
Roof plumbing - gutter Square Gutter (Brown)
Roof plumbing - gutter Half Round Gutter (Brown)
Gutter & Down Spout Fittings
Roof plumbing - gutter fittings Running Head
Roof plumbing - gutter fittings Gutter Joiner
Roof plumbing - gutter fittings Mitre Joiner (Outer)
Roof plumbing - gutter fittings Mitre Joiner (Inner)
Roof plumbing - gutter fittings End Cap
Roof plumbing - gutter fittings Gutter Box (200x200x200mm)
Roof plumbing - gutter fittings Gutter Bracket (Inner)
Roof plumbing - gutter fittings Gutter Bracket (Outer)
Roof plumbing - gutter fittings DP Elbow
Roof plumbing - gutter fittings DP Angle Elbow
Roof plumbing - gutter fittings DP Joiner
Roof plumbing - gutter fittings DP Clip
Roof plumbing - gutter fittings DP Conveyor
Roof plumbing - gutter fittings DP "Y"
Roof plumbing - gutter fittings DP Tee
Roof plumbing - gutter fittings Gutter Box Connector
Reducing fittings - reducing socket 25x20mm
Reducing fittings - reducing socket 32x20mm
Reducing fittings - reducing socket 32x25mm
Reducing fittings - reducing socket 40x20mm
Reducing fittings - reducing socket 40x25mm
Reducing fittings - reducing socket 40x32mm
Reducing fittings - reducing socket 50x20mm
Reducing fittings - reducing socket 50x25mm
Reducing fittings - reducing socket 50x32mm
Reducing fittings - reducing socket 50x40mm
Reducing fittings - reducing socket 63x20mm
Reducing fittings - reducing socket 63x25mm
Reducing fittings - reducing socket 63x32mm
Reducing fittings - reducing socket 63x40mm
Reducing fittings - reducing socket 63x50mm
Reducing fittings - reducing tee 25x20mm
Reducing fittings - reducing tee 32x20mm
Reducing fittings - reducing tee 32x25mm
Reducing fittings - reducing tee 40x20mm
Reducing fittings - reducing tee 40x25mm
Reducing fittings - reducing tee 40x32mm
Reducing fittings - reducing tee 50x20mm
Reducing fittings - reducing tee 50x25mm
Reducing fittings - reducing tee 50x32mm
Reducing fittings - reducing tee 50x40mm
Reducing fittings - reducing tee 63x20mm
Reducing fittings - reducing tee 63x25mm
Reducing fittings - reducing tee 63x32mm
Reducing fittings - reducing tee 63x40mm
Reducing fittings - reducing tee 63x50mm
H Hot water pipes CPVC Pipe 1/4" ( 10mm)
H Hot water pipes CPVC Pipe 1/2" ( 15mm)
H Hot water pipes CPVC Pipe 3/4" ( 20mm)
Fittings
Hot water - fittings CPVC Coupling 1/2" (15mm)
Hot water - fittings CPVC Coupling 3/4" (20mm)
Hot water - fittings CPVC Threded Male Adaptor 1/2" (15mm)
Hot water - fittings CPVC Threded Male Adaptor 3/4" (20mm)
Hot water - fittings CPVC Threded Female Adaptor 1/2" (15mm)
Hot water - fittings CPVC Threded Female Adaptor 3/4" (20mm)
Hot water - fittings Brass Threded Male Adaptor 1/2" (15mm)
Hot water - fittings Brass Threded Male Adaptor 3/4" (20mm)
Hot water - fittings Brass Threded Female Adaptor 1/2" (15mm)
Hot water - fittings Brass Threded Female Adaptor 3/4" (20mm)
Hot water - fittings Brass EPT Elbow 1/2" (15mm)
Hot water - fittings Brass EPT Elbow 3/4" (20mm)
Hot water - fittings Brass EPT Tee 3/4"x1/2" (20x15mm)
Hot water - fittings Brass Coupling 3/4"x1/2" (20x15mm)
Hot water - fittings CPVC Reducer Coupling 3/4"x1/2" (20x15mm)
Hot water - fittings CPVC Union 1/2" (15mm)
Hot water - fittings CPVC Union 3/4" (20mm)
Hot water - fittings CPVC Elbow 1/2" 45D (15mm)
Hot water - fittings CPVC Elbow 3/4" 45D (20mm)
Hot water - fittings CPVC Cap 1/2" (15mm)
Hot water - fittings CPVC Cap 3/4" (20mm)
Hot water - fittings CPVC Elbow 1/2" (15mm)
Hot water - fittings CPVC Elbow 3/4" (20mm)
Hot water - fittings CPVC Tee 1/2" (15mm)
Hot water - fittings CPVC Tee 3/4" (20mm)
Hot water - fittings CPVC Reducer Bush 3/4"x1/2" (20x15mm)
Hot water - fittings CPVC Reducer Tee 3/4"x1/2" (20x15mm)
Adhesive Solution Adhesive Solution - 50ml
Adhesive Solution Adhesive Solution - 118ml
P Compact Ball Valve
20 mm diameter
P Compact Ball Valve
25 mm diameter
P Compact Ball Valve
32 mm diameter
P Compact Ball Valve
40 mm diameter
P Compact Ball Valve
50 mm diameter
P Compact Ball Valve
63 mm diameter
National PVC water tank
P Water tank 350Ltr
P Water tank 500Ltr
P Water tank 1000Ltr
P Water tank 2000Ltr
P S-Lon Water Tank (vertical)
P Water tank 300Ltr Watermaate
P Water tank 500Ltr Watermaate
P Water tank 1000Ltr Watermaate
P Water tank 2000Ltr Watermaate
P Water tank 350Ltr PE Plus
P Water tank 500Ltr PE Plus
P Water tank 750Ltr PE Plus
P Water tank 1000Ltr PE Plus
P Water tank 1500Ltr PE Plus
P Water tank 2000Ltr PE Plus
P Water tank 5000Ltr PE Plus
P Water tank 500Ltr White Layer
P Water tank 750Ltr White Layer
P Water tank 1000Ltr White Layer
P Water tank 1500Ltr White Layer
P Water tank 2000Ltr White Layer
P Water tank 10000Ltr Solco
P ANTON Water Tank (Vertical)
P Water tank 300Ltr
P Water tank 500Ltr
P Water tank 1000Ltr
P Water tank 1500Ltr
P Water tank 2000Ltr
Stainless steel water tank
P Water tank - Stainless steel 500Ltr
P Water tank - Stainless steel 850Ltr
P Water tank - Stainless steel 1250Ltr
S Water tank - Stainless steel
75L
S Water tank - Stainless steel
100L
S Water tank - Stainless steel
150L
S Water tank - Stainless steel
200L
S Water tank - Stainless steel
300L
S Water tank - Stainless steel
450L
Solar panel
75L
100L
150L
200L
300L
450L
H Hume pipe 3" dia 8' long
H Hume pipe 3" dia 8' long
H Hume pipe 4" dia 6' long
H Hume pipe 4" dia 8' long
H Hume pipe 9" dia 8' long
H Hume pipe 9" dia 4' long
H Hume pipe 12'' dia 8' long
H Hume pipe 12" dia 4' long
H Hume pipe 15" dia 8' long
H Hume pipe 15" dia 4' long
H Hume pipe 18' dia 8' long
H Hume pipe 18" dia 4' long
H Hume pipe 24" dia 8' long
H Hume pipe 24" dia 4' long
H Hume pipe 30" dia 8' long
H Hume pipe 30" dia 4' long
H Hume pipe 36" dia 8' long
H Hume pipe 36" dia 4' long
H Hume pipe 48" dia 8' long
H Hume pipe 48" dia 4' long
H Hume pipe 60" dia 8' long
S Septic tanks 10 Person 24'
S Septic tanks 15 Person 30"
S Septic tanks 25 person 36'
S Septic tanks 35 person 42"
S Septic tanks 50 person 48"
S Septic tanks 60 person 54'
S Septic tanks 75 person 60"
S Septic tanks 125 person 72'
S 10 Person 4'-0" x 8'-0"
S
S Septic tanks 4' 6" dia 8' 0" long
S
S
S Soakage pit 24" x4'
S Soakage pit 30" x4'
S Soakage pit 30" x4'
S Soakage pit 42" x4'
S Soakage pit 48" x4'
S Soakage pit 54" x4'
S Soakage pit 60" x4'
S Soakage pit 72" x4'
B Brass item 0.5" Brass Gate Valve -English
B Brass item 0.5" Brass stops -English
B Brass item 0.5" C/P Stop -Cobra
B Brass item 1/2" Brass bib tap English
S
S
B Ball Cock 1"spain
B
S Solvent cement
25 Grams
S Solvent cement
50 Grams
S Solvent cement
75 Grams
S Solvent cement
90 Grams
S Solvent cement
250 Grams
S Solvent cement
500 Grams
S Solvent cement
1000 Grams
S
S Stainless steel Bottle trap
S
S
S Stainless steel Gully cover
S
S Stainless steel shower Good Quality
S
S
H Hand bidet spray
H
T Towel Rail Cromium Plated 2' 0"
T
T Toilet accessories Cromium Plated
T
M Mirrors Mirror
M Pencil Edge
M Hole making
M Screws
M
F Flexible hose 16"
F
A Angle Valve
A
B Ball valve Pegler
Ball valve 1/2" S -Lon
Ball valve 3/4"
Ball valve 1"
Ball valve 11/4"
Ball valve 11/2"
Ball valve 2"
Ball valve 3"
Ball valve
Ball valve
Cupper gutters
Sanitary fittings
S Sanitary fittings
water closet
S Sanitary fittings
vanity basin
S Sanitary fittings
under counter basin
S Sanitary fittings
S Sanitary fittings
Urinals U.K
S Sanitary fittings
U.K
S Sanitary fittings
wash basin-Pedestal Malaysia
S Sanitary fittings
Squatin pan
S Sanitary fittings
Squatin pan
S Sanitary fittings
Squatin pan
S
T Taps
Dual handle Lavatory mixer tap
T Taps
Single lever Lavatory mixer tap
T Taps
Single lever Lavatory mixer tap
T Taps
Dual handle kitchen mixer tap
T Taps
Sigle handle kitchen mixer tap
T Taps
Sigle handle kitchen mixer tap
T Taps
Sigle handle kitchen mixer tap
T Taps
Garden tap
T
T
T Tap
mixture tap
T
S Shower
Wall mounted single hadle bath
mixer
S Shower
S Shower
S New Eurosmart basin mixer Grohe
S New Eurosmart concealed bath mixer Grohe
S Concealed body bath Grohe
S Relaxa head shower buo Grohe
S Lineare basin mixer Grohe
S Lineare bidet mixer Grohe
S Silver metalic bidet spray Grohe
S Coasta sink mixer Grohe
S New Eurostyle sink mixer Grohe
S mintaa sink mixer Grohe
S Angle valve Grohe
S Angle valve Grohe
Unit Currencet price Date Other Remark Telephone Price
4m (13ft) 156.00 1.12.2008 39.00 194.00
4m (13ft) 429.00 1.12.2008 107.25 429.00
4m (13ft) 640.00 1.12.2008 160.00 640.00
4m (13ft) 948.00 1.12.2008 237.00 948.00
4m (13ft) 1,366.00 1.12.2008 341.50 1,366.00
4m (13ft) 2,305.00 1.12.2008 576.25 2,305.00
4m (13ft) 4,720.00 1.12.2008 1180.00 4,720.00
6m (20ft) 8,556.00 1.12.2008 1426.00 8,556.00
6m (20ft) 12,792.00 1.12.2008 12,792.00
6m (20ft) 21,192.00 1.12.2008 21,192.00
6m (20ft) 26,628.00 1.12.2008 26,628.00
6m (20ft) 51,957.00 1.12.2008 51,957.00
6m (20ft) 80,199.00 1.12.2008 80,199.00
6m (20ft) 101,853.00 1.12.2008 101,853.00
4m (13ft) 272.00 1.12.2008 68.00 272.00
4m (13ft) 663.00 1.12.2008 165.75 663.00
4m (13ft) 886.00 1.12.2008 221.50 886.00
4m (13ft) 1,468.00 1.12.2008 367.00 1,468.00
4m (13ft) 2,898.00 1.12.2008 724.50 2,898.00
6m (20ft) 5,493.00 1.12.2008 915.50 5,493.00
6m (20ft) 8,046.00 1.12.2008 8,046.00
6m (20ft) 12,891.00 1.12.2008 12,891.00
6m (20ft) 16,788.00 1.12.2008 16,788.00
6m (20ft) 32,913.00 1.12.2008 32,913.00
6m (20ft) 50,619.00 1.12.2008 50,619.00
6m (20ft) 64,524.00 1.12.2008 64,524.00
4m (13ft) 628.00 1.12.2008 157.00 628.00
4m (13ft) 1,141.00 1.12.2008 285.25 1,141.00
4m (13ft) 1,836.00 1.12.2008 459.00 1,836.00
6m (20ft) 3,735.00 1.12.2008 622.50 3,735.00
6m (20ft) 11,640.00 1.12.2008 11,640.00
6m (20ft) 23,145.00 1.12.2008 23,145.00
6m (20ft) 34,896.00 1.12.2008 34,896.00
Plumbing material
6m (20ft) 44,466.00 1.12.2008 44,466.00
Nos 16.00 1.12.2008 16.00
Nos 17.00 1.12.2008 17.00
Nos 16.00 1.12.2008 18.00
Nos 21.00 1.12.2008 21.00
Nos 26.00 1.12.2008 26.00
Nos 27.00 1.12.2008 27.00
Nos 66.00 1.12.2008 66.00
Nos 81.00 1.12.2008 81.00
Nos 139.00 1.12.2008 139.00
Nos 19.00 1.12.2008 19.00
Nos 23.00 1.12.2008 23.00
Nos 31.00 1.12.2008 31.00
Nos 43.00 1.12.2008 43.00
Nos 63.00 1.12.2008 63.00
Nos 90.00 1.12.2008 90.00
Nos 255.00 1.12.2008 255.00
Nos 359.00 1.12.2008 359.00
Nos 422.00 1.12.2008 422.00
Nos 15.00 1.12.2008 15.00
Nos 27.00 1.12.2008 27.00
Nos 40.00 1.12.2008 40.00
Nos 66.00 1.12.2008 66.00
Nos 111.00 1.12.2008 111.00
Nos 187.00 1.12.2008 187.00
Nos 404.00 1.12.2008 404.00
Nos 683.00 1.12.2008 683.00
Nos 756.00 1.12.2008 756.00
Nos 20.00 1.12.2008 20.00
Nos 36.00 1.12.2008 36.00
Nos 55.00 1.12.2008 55.00
Nos 90.00 1.12.2008 90.00
Nos 156.00 1.12.2008 156.00
Nos 238.00 1.12.2008 238.00
Nos 395.00 1.12.2008 395.00
Nos 903.00 1.12.2008 903.00
Nos 1,394.00 1.12.2008 1,394.00
Nos 20.00 1.12.2008 20.00
Nos 28.00 1.12.2008 28.00
Nos 36.00 1.12.2008 36.00
Nos 67.00 1.12.2008 67.00
Nos 92.00 1.12.2008 92.00
Nos 143.00 1.12.2008 143.00
Nos 284.00 1.12.2008 264.00
Nos 404.00 1.12.2008 404.00
Nos 906.00 1.12.2008 906.00
Nos 26.00 1.12.2008 26.00
Nos 36.00 1.12.2008 36.00
Nos 51.00 1.12.2008 51.00
Nos 111.00 1.12.2008 111.00
Nos 178.00 1.12.2008 178.00
Nos 288.00 1.12.2008 288.00
Nos 824.00 1.12.2008 824.00
Nos 1,378.00 1.12.2008 1,378.00
Nos 1,746.00 1.12.2008 1,746.00
Nos 16.00 1.12.2008 16.00
Nos 23.00 1.12.2008 23.00
Nos 34.00 1.12.2008 34.00
Nos 51.00 1.12.2008 51.00
Nos 78.00 1.12.2008 78.00
Nos 125.00 1.12.2008 125.00
Nos 308.00 1.12.2008 308.00
Nos 453.00 1.12.2008 453.00
Nos 727.00 1.12.2008 727.00
Nos 20.00 1.12.2008 20.00
Nos 28.00 1.12.2008 28.00
Nos 32.00 1.12.2008 32.00
Nos 60.00 1.12.2008 60.00
Nos 83.00 1.12.2008 83.00
Nos 138.00 1.12.2008 138.00
Nos 373.00 1.12.2008 373.00
Nos 578.00 1.12.2008 578.00
Nos 906.00 1.12.2008 906.00
4m (13ft) 81.00 1.12.2008 94.00
4m (13ft) 121.00 1.12.2008 134.00
4m (13ft) 167.00 1.12.2008 184.00
4m (13ft) 483.00 1.12.2008 483.00
4m (13ft) 686.00 1.12.2008 686.00
4m (13ft) 786.00 1.12.2008 786.00
6m (20ft)
6m (20ft)
Nos 16.00 1.12.2008 16.00
Nos 20.00 1.12.2008 20.00
Nos 24.00 1.12.2008 24.00
Nos 41.00 1.12.2008 41.00
Nos 60.00 1.12.2008 60.00
Nos 85.00 1.12.2008 85.00
Nos 6.00 1.12.2008 6.00
Nos 7.00 1.12.2008 7.00
Nos 7.00 1.12.2008 7.00
Nos 20.00 1.12.2008 20.00
Nos 24.00 1.12.2008 24.00
Nos 38.00 1.12.2008 38.00
Nos 11.00 1.12.2008 11.00
Nos 11.00 1.12.2008 11.00
Nos 11.00 1.12.2008 11.00
Nos 12.00 1.12.2008 12.00
Nos 13.00 1.12.2008 13.00
Nos 17.00 1.12.2008 17.00
3.65m (12ft) 809.00 1.12.2008 934.00
Nos 233.00 1.12.2008 233.00
Nos 101.00 1.12.2008 101.00
Nos 328.00 1.12.2008 328.00
Nos 84.00 1.12.2008 84.00
Nos 554.00 1.12.2008 554.00
Nos 44.00 1.12.2008 44.00
Nos 20.00 1.12.2008 20.00
3.65m (12ft) 788.00 1.12.2008 788.00
Nos 142.00 1.12.2008 142.00
Nos 105.00 1.12.2008 105.00
Nos 22.00 1.12.2008 22.00
1,467.00 11.08.2008
972.00 11.08.2008
Nos 233.00 1.12.2008 264.00
Nos 101.00 1.12.2008 114.00
Nos 328.00 1.12.2008 384.00
Nos 328.00 1.12.2008 384.00
Nos 84.00 1.12.2008 98.00
Nos 554.00 1.12.2008 708.00
Nos 44.00 1.12.2008 48.00
Nos 20.00 1.12.2008 60.00
Nos 168.00 11.08.2008 168.00
Nos 168.00 11.08.2008 168.00
Nos 118.00 11.08.2008 118.00
Nos 28.00 11.08.2008 28.00
Nos 64.00 11.08.2008 64.00
Nos 330.00 11.08.2008 330.00
Nos 240.00 11.08.2008 240.00
Nos 72.00 11.08.2008 72.00
Nos 22.00 1.12.2008 22.00
Nos 27.00 1.12.2008 27.00
Nos 34.00 1.12.2008 34.00
Nos 44.00 1.12.2008 44.00
Nos 50.00 1.12.2008 50.00
Nos 57.00 1.12.2008 58.00
Nos 59.00 1.12.2008 59.00
Nos 68.00 1.12.2008 68.00
Nos 81.00 1.12.2008 81.00
Nos 84.00 1.12.2008 84.00
Nos 99.00 1.12.2008 99.00
Nos 103.00 1.12.2008 103.00
Nos 107.00 1.12.2008 107.00
Nos 110.00 1.12.2008 110.00
Nos 115.00 1.12.2008 115.00
Nos 38.00 1.12.2008 38.00
Nos 50.00 1.12.2008 50.00
Nos 56.00 1.12.2008 56.00
Nos 66.00 1.12.2008 66.00
Nos 86.00 1.12.2008 86.00
Nos 90.00 1.12.2008 90.00
Nos 102.00 1.12.2008 102.00
Nos 119.00 1.12.2008 119.00
Nos 128.00 1.12.2008 128.00
Nos 146.00 1.12.2008 146.00
Nos 228.00 1.12.2008 228.00
Nos 235.00 1.12.2008 235.00
Nos 236.00 1.12.2008 236.00
Nos 238.00 1.12.2008 238.00
Nos 246.00 1.12.2008 246.00
3 m 840.00 27.04.2009
3 m 870.00 27.04.2009 690.00
3 m 861.00 11.08.2008
Nos 35.00 11.08.2008
Nos 65.00 11.08.2008
Nos 45.00 11.08.2008
Nos 80.00 11.08.2008
Nos 65.00 11.08.2008
Nos 105.00 11.08.2008
Nos 450.00 11.08.2008
Nos 580.00 11.08.2008
Nos 450.00 11.08.2008
Nos 590.00 11.08.2008
Nos 195.00 11.08.2008
Nos 240.00 11.08.2008
Nos 275.00 11.08.2008
Nos 260.00 11.08.2008
Nos 70.00 11.08.2008
Nos 540.00 11.08.2008
Nos 795.00 11.08.2008
Nos 60.00 11.08.2008
Nos 100.00 11.08.2008
Nos 30.00 11.08.2008
Nos 50.00 11.08.2008
Nos 50.00 11.08.2008
Nos 100.00 11.08.2008
Nos 65.00 11.08.2008
Nos 145.00 11.08.2008
Nos 35.00 11.08.2008
Nos 125.00 11.08.2008
kg 640.00 11.08.2008
kg 920.00 11.08.2008
Nos 122.00 1.12.2008 122.00
Nos 221.75 1.12.2008 221.00
Nos 237.00 1.12.2008 237.00
Nos 371.75 1.12.2008 371.00
Nos 494.75 1.12.2008 494.00
Nos 789.50 1.12.2008 789.00
Nos 5,065.00
Nos 7,000.00
Nos 11,300.00
Nos 20,665.00
Nos 4,775.00 11.08.2008
Nos 5,775.00 11.08.2008
Nos 10,300.00 11.08.2008
Nos 18,700.00 11.08.2008
Nos 5,125.00 11.08.2008
Nos 6,580.00 11.08.2008
Nos 9,800.00 11.08.2008
Nos 12,000.00 11.08.2008
Nos 17,000.00 11.08.2008
Nos 21,450.00 11.08.2008
Nos 50,500.00 11.08.2008
Nos 8,460.00 11.08.2008
Nos 10,900.00 11.08.2008
Nos 13,400.00 11.08.2008
Nos 19,400.00 11.08.2008
Nos 24,700.00 11.08.2008
Nos 84,000.00 11.08.2008
Nos 5,170.00 11.08.2008
Nos 6,940.00 11.08.2008
Nos 12,835.00 11.08.2008
Nos 17,975.00 11.08.2008
Nos 26,200.00 11.08.2008
Nos 19,600.00 11.08.2009
Nos 24,900.00 11.08.2009
Nos 32,900.00 11.08.2009
Nos 55,000.00 11.08.2009
Nos 69,000.00 11.08.2009
Nos 93,000.00 11.08.2009
Nos 115,000.00 11.08.2009
Nos 150,000.00 11.08.2009
Nos 225,000.00 11.08.2009
Nos 68,000.00 15/02/20210
Nos 85,000.00 15/02/20210
Nos 106,250.00 15/02/20210
Nos 127,500.00 15/02/20210
Nos 168,300.00 15/02/20210
Nos 242,250.00 15/02/20210
6lft 420.00
8lft 636.00
6lft 510.00
8lft 663.00
8lft 3,200.00 5/7/2007 978.00
4lft 1,800.00 5/7/2007
8lft 3,800.00 5/7/2007 1,275.00
4lft 1,900.00 5/7/2007
8lft 5,000.00 5/7/2007 1,275.00
4lft 2,500.00 5/7/2007
8lft 5,800.00 5/7/2007 1,950.00
4lft 2,900.00 5/7/2007
8lft 7,200.00 5/7/2007 1,950.00
4lft 3,225.00 9/1/2009 Dias concrete -2930763
8lft 8,800.00 5/7/2007 1,950.00
4lft 4,400.00 5/7/2007
8lft 10,800.00 5/7/2007 1,951.00
4lft 6,000.00 9/1/2009 Dias concrete -2930763
8lft 16,900.00 5/7/2007 9,330.00
4lft 8,450.00 5/7/2007
8lft 14,100.00
No 5,100.00
No 69,000.00
No 8,700.00
No 10,500.00
No 25,000.00 13/07/06 13,700.00
No 16,800.00
No 21,930.00
No 29,400.00
No 30,300.00 3/12/2008 Dias concrete -2930763
No 40,975.00 21/04/2009
No 2,130.00
No 2,940.00
No 3,750.00
No 4,830.00
No 6,000.00
No 7,260.00
No 8,700.00
No 13,200.00
No 350.00
No 350.00
No 750.00
No 350.00
Nos
25 Grams
57.00 1.12.2008 57.00
50 Grams
108.00 1.12.2008 108.00
75 Grams
142.00 1.12.2008 142.00
250 Grams
451.00 1.12.2008 451.00
500 Grams
874.00 1.12.2008 874.00
1000 Grams
1,720.00 1.12.2008 1,720.00
Nos
2,750.00 21/04/2009
1,350.00 20/03/2009
Nos
1,250.00 21/04/2009
Nos
8,000.00 21/04/2009
Nos
4,000.00 21/04/2009
Nos
2,700.00 21/04/2009
Nos
2,000.00 21/04/2009
Set 7,200.00 21/04/2009
Sq.ft 350.00 21/04/2009
L.ft 45.00 21/04/2009
Nos 50.00 21/04/2009
Nos 25.00 21/04/2009
Nos 325.00 20/03/2009
Nos 750.00 20/03/2009
Nos 1,475.00 20/03/2009
Nos 122.00 15/02/20010
Nos 221.00 15/02/20010
Nos 237.00 15/02/20010
Nos 371.00 15/02/20010
Nos 494.00 15/02/20010
Nos 789.00 15/02/20010
Nos 2,070.00 15/02/20010
L.ft 4,500.00
Nos 15,200.00
Nos 5,638.13
Nos 5,006.66
Nos 2,265.00 9/8/2008 Mascons Ltd 2325561-3
Nos 1,380.00
Nos 5,899.50
Nos 862.00
Nos 816.00
Nos 549.00
Nos 2,363.25 9/8/2008 Mascons Ltd
Nos 1,495.00
Nos 1,989.50
Nos 2,386.25
Nos 519.00
Nos 701.50
Nos 1,058.00
Nos 365.00
Nos 1,442.00
Nos 2,202.25 9/8/2008 Mascons Ltd
Nr 14,960.00 6/2/2010
Nr 12,950.00 6/2/2010
Nr 12,320.00 6/2/2010
Nr 22,810.00 6/2/2010
Nr 34,510.00 6/2/2010
Nr 34,510.00 6/2/2010
Nr 9,130.00 6/2/2010
Nr 10,570.00 6/2/2010
Nr 21,340.00 6/2/2010
Nr 58,400.00 6/2/2010
Nr 1,850.00 6/2/2010
Nr 1,650.00 6/2/2010
Date Price Date
11.08.2008 168.00
11.08.2008 329.00
11.08.2008 491.00
11.08.2008 726.00
11.08.2008 1,046.50
11.08.2008 1,766.50
11.08.2008 3,652.00
11.08.2008 6,955.00
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008 308.00
11.08.2008 524.00
11.08.2008 718.00
11.08.2008 1,157.00
11.08.2008 2,278.00
11.08.2008 4,464.00
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
Plumbing material
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008 13.00
11.08.2008 21.00
11.08.2008 34.00
11.08.2008 53.00
11.08.2008 95.00
11.08.2008 150.00
11.08.2008 326.00
11.08.2008 552.00
11.08.2008 610.00
11.08.2008 17.00
11.08.2008 29.00
11.08.2008 47.00
11.08.2008 72.00
11.08.2008 125.00
11.08.2008 192.00
11.08.2008 318.00
11.08.2008 729.00
11.08.2008 1,125.00
11.08.2008 17.00
11.08.2008 22.00
11.08.2008 31.00
11.08.2008 54.00
11.08.2008 74.00
11.08.2008 115.00
11.08.2008 213.00
11.08.2008 326.00
11.08.2008 731.00
11.08.2008 22.00
11.08.2008 29.00
11.08.2008 44.00
11.08.2008 89.00
11.08.2008 143.00
11.08.2008 232.00
11.08.2008 664.50
11.08.2008 1,112.50
11.08.2008 1,409.50
11.08.2008 14.00
11.08.2008 19.00
11.08.2008 29.00
11.08.2008 41.00
11.08.2008 62.00
11.08.2008 101.00
11.08.2008 248.50
11.08.2008 365.50
11.08.2008 585.50
11.08.2008 17.00
11.08.2008 22.00
11.08.2008 30.00
11.08.2008 48.00
11.08.2008 67.00
11.08.2008 111.00
11.08.2008 300.50
11.08.2008 466.00
11.08.2008 731.00
11.08.2008 49.00 8/4/2004
11.08.2008 74.80 8/4/2004
11.08.2008 106.00 8/4/2004
11.08.2008 269.00 8/4/2004
11.08.2008 384.00 8/4/2004
11.08.2008 440.00 8/4/2004
10,395.00
11.08.2008 13.25
11.08.2008 15.75
11.08.2008 19.50
11.08.2008 33.25
11.08.2008 48.75
11.08.2008 69.00
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
11.08.2008
420.00
636.00
510.00
663.00
978.00
1,275.00
1,275.00
1,950.00
1,950.00
1,950.00
1,951.00
9,330.00
14,100.00
5,100.00
69,000.00
8,700.00
10,500.00
13,700.00
16,800.00
21,930.00
29,400.00
2,130.00
2,940.00
3,750.00
4,830.00
6,000.00
7,260.00
8,700.00
13,200.00
350.00
350.00
750.00
350.00
170.00
11.08.2008 45.50
11.08.2008 87.00
11.08.2008 136.00
11.08.2008 362.50
11.08.2008 703.50
11.08.2008 1,384.75
Code Category Description Remarks Unit
Q Ready Mix Concrete G40 excl. VAT M
Q Ready Mix Concrete G35 excl. VAT M
Q Ready Mix Concrete G30
excl. VAT & Pumping
M
Q Ready Mix Concrete G25
excl. VAT & Pumping
M
Q Ready Mix Concrete G20
excl. VAT & Pumping
M
Q Ready Mix Concrete G15
excl. VAT & Pumping
M
Q Ready Mix Concrete G30
excl. VAT & Pumping
M
G25 M
G20 M
G15
excl. VAT & Pumping
Q Ready Mix Concrete G35
excl. VAT & Pumping
M
excl. VAT & Pumping
Q Ready Mix Concrete G30
excl. VAT & Pumping
M
Q Ready Mix Concrete G25
excl. VAT & Pumping
M
excl. VAT & Pumping
Q Ready Mix Concrete G30
excl. VAT & Pumping
M
G25
excl. VAT & Pumping
G20
excl. VAT & Pumping
G15
excl. VAT & Pumping
Q Ready Mix Concrete G15 excl. VAT M
Q Ready Mix Concrete G40 excl. VAT M
Q Ready mix concrete Ready mix concrete grade 25 with VAT 1m3
Q Pump car carging 30m3
Q Ready mix concrete Ready mix concrete grade 20 with VAT 1m3
Q Ready mix concrete Ready mix concrete grade 25 with VAT 1m3
Q Ready mix concrete Ready mix concrete grade 30 with VAT 1m3
Ready Mix Concrete
Index
Currencet price Date Other Remark Telephone Price
11,175.00 25.09.08 excl. pumping, max 15km transport 2368494 Thudawe Bros.
10,725.00 25.09.08 excl. pumping, max 15km transport 2368494 Thudawe Bros.
9,700.00 20/04/2010
30m3 plumping charge 12.000.00
after 30m3 400/= per 1m3
2368494 Thudawe Bros.
9,000.00 20/04/2010 2368494 Thudawe Bros.
8,700.00 20/04/2010 2368494 Thudawe Bros.
8,600.00 25.09.08 2368494 Thudawe Bros.
8,950.00 20/04/2010
25m3 plumping charge 10.000.00
after 25m3 300/= per 1m3
2522939 Sanken
8,600.00 20/04/2010
8,100.00 20/04/2010
2808835 Maga
2423085 orumix
2807808 LHP
9,650.00 20/04/2010
20m3 plumping charge 5.000.00
4400404 ICC
9,200.00 20/04/2010
8,900.00 20/04/2010
8,000.00 20/04/2010
2375500 Sunbee
2945865 Supermix
8,970.00 22/102007
14,375.00 22/10/2007
9,545.00 3/6/2008
10,005.00 3/6/2008
10,580.00 3/6/2008
Ready Mix Concrete
Ready Mix Concrete
Code Category Description Remarks Unit
T Timber Teak 2"x1" timber L.ft
T Timber Teak
2" x 2" timber
L.ft
T Timber Teak
2" x 3" timber
L.ft
T Timber Teak
3" x 5" timber
L.ft
T Timber Teak
5" x 5" timber
L.ft
T Timber Teak
7" x 7" timber
L.ft
T Timber Balaw 2"x1" timber L.ft
T Timber Balaw
2" x 2" timber
L.ft
T Timber Balaw
2" x 4" timber
L.ft
T Timber Balaw
2" x 5" timber
L.ft
T Timber Balaw
2" x 6" timber
L.ft
T Timber Balaw
2" x 7" timber
L.ft
T Timber Balaw
2" x 8" timber
L.ft
T Timber Balaw
3" x 4" timber
L.ft
T Timber Balaw
3" x 5" timber
L.ft
T Timber Balaw
3" x 6" timber
L.ft
T Timber Balaw
4" x 6" timber
L.ft
T Timber Balaw
4" x 8" timber
L.ft
T Timber Balaw
1" x 8" timber
L.ft
T Timber Balaw
1" x 9" timber
L.ft
T Timber Balaw
1" x 10" timber
L.ft
T Timber Balaw
1" x 12" timber
L.ft
T Timber Balaw
11/4" x 9" timber
L.ft
T Timber Balaw
11/4" x 10" timber
L.ft
T Timber Balaw
3/4" timber
L.ft
T
T Timber Yellow Balaw
1 1/4" thick
Sq.ft
T Timber Yellow Balaw
1" thick
Sq.ft
T
T Tholang 2"x1" timber L.ft
T Tholang
2" x 2" timber
L.ft
T Tholang
2" x 4" timber
L.ft
T Tholang
2" x 5" timber
L.ft
Timber
Index
T Tholang
2" x 6" timber
L.ft
T Tholang
2" x 7" timber
L.ft
T Tholang
2" x 8" timber
L.ft
T Tholang
3" x 4" timber
L.ft
T Tholang
3" x 5" timber
L.ft
T Tholang
3" x 6" timber
L.ft
T Tholang
4" x 6" timber
L.ft
T Tholang
4" x 8" timber
L.ft
T Tholang
1" x 8" timber
L.ft
T Tholang
1" x 9" timber
L.ft
T Tholang
1" x 10" timber
L.ft
T Tholang
1" x 12" timber
L.ft
T Tholang
11/4" x 9" timber
L.ft
T Tholang
11/4" x 10" timber
L.ft
T Kempus
2" x 2" timber
L.ft
T Kempus
2" x 3" timber
L.ft
T Kempus
2" x 4" timber
L.ft
T Kempus
3" x 4" timber
L.ft
T Kempus
2" x 6" timber
L.ft
T Kempus
3" x 6" timber
L.ft
T Altoniya
2" x 2" timber
L.ft
T
T Rubber plank
3/4" x7"
L.ft
T
T Tuna timber
6' x 3/4"
Sq.ft
T
T
1" thick kubuk plank
Sq.ft
T
T
11/4" thick teak timber
Local teak Sq.ft
T
11/2" thick Mahogani timber
plank
Sq.ft
T
T
Balau Balau
Cu.ft
T
T Timber Cu.ft
T
T
T Showring Plank
1' 6'' thick planks
s.ft
T Showring Plank
2'' x 6'' joist
l ft
T Showring Plank
12' 0'' long joist
no
T Showring Plank
2'' x 4'' joist
l ft
T Showring Plank 4' 0'' long props (2''x4'') no
T
P Plywood sheet 6mm 4'x8' Nos
P Plywood sheet 9mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 12mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 15mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 18mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 21mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 25mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 29mm (Moisture Resistant) 4'x8' Nos
P Plywood sheet 9mm (W.B.P) 4'x8' Nos
P Plywood sheet 12mm (W.B.P) 4'x8' Nos
P Plywood sheet 15mm (W.B.P) 4'x8' Nos
P Plywood sheet 18mm (W.B.P) 4'x8' Nos
P Plywood sheet 21mm (W.B.P) 4'x8' Nos
P Plywood sheet 25mm (W.B.P) 4'x8' Nos
P Plywood sheet 29mm (W.B.P) 4'x8' Nos
V Valance board timber 1" x9" 1 L.ft
F Finish Timber Stairscse Hand Rail 1 L.ft
F Finish Timber with metal Stairscse Hand Rail 1 L.ft
W Wood treatment 2" x 1" L.ft
W Wood treatment 4" x 1" L.ft
W Wood treatment 5" x 1" L.ft
W Wood treatment 6" x 1" L.ft
W Wood treatment 7" x 1" L.ft
W Wood treatment 8" x 1" L.ft
W Wood treatment 9" x 1" L.ft
W Wood treatment 10" x 1" L.ft
W Wood treatment 11" x 1" L.ft
W Wood treatment 12" x 1" L.ft
W Wood treatment 12" x 1 1/4" L.ft
W Wood treatment 10" x 1 1/4" L.ft
W Wood treatment 9" x 1 1/4" L.ft
W Wood treatment 8" x 1 1/4" L.ft
W Wood treatment 2" x 2" L.ft
W Wood treatment 2" x 3" L.ft
W Wood treatment 2" x 4" L.ft
W Wood treatment 2" x 5" L.ft
W Wood treatment 2" x 6" L.ft
W Wood treatment 2" x 7" L.ft
W Wood treatment 2" x 8" L.ft
W Wood treatment 2" x 10" L.ft
W Wood treatment 3" x 4" L.ft
W Wood treatment 3" x 5" L.ft
W Wood treatment 3" x 6" L.ft
W Wood treatment 3" x 7" L.ft
W Wood treatment 4" x 4" L.ft
W Wood treatment 4" x 5" L.ft
W Wood treatment 4" x 6" L.ft
W Wood treatment 4" x 8" L.ft
W
W Wood Seasion 1'-0" x 1'-0" x 1'-0" Cu.ft
P Planking charges L.ft
P Planking charges Sq.ft
Currencet price Date Other Remark Telephone Price
375.00
750.00
1,125.00
2,000.00
33.00 5/8/2008 NAM timber Tel 2818800 23.00
55.00 5/8/2008 NAM timber 45.00
135.50 5/8/2008 NAM timber 135.00
171.50 24/01/2008 100.00
214.00 24/01/2008
350.00 24/01/2008
214.00 24/01/2008 106.00
290.00 25/09/2008 NAM timber Tel 2818800 150.00
285.00
458.00 24/01/2008
665.00 24/01/2008
380.00 27/04/2009
292.00 27/04/2009
49.00 26/05/2008
123.50 24/01/2008
163.50 24/01/2008 100.00
Timber
198.00 24/01/2008
215.00
290.00 24/01/2008
183.00 26/05/2008 106.00
245.00 26/05/2008 150.00
260.00
410.00 24/01/2008
595.00 26/05/2008
150.00
168.75
187.50
225.00
195.00
217.00
28.00 28/02/2008
65.00 28/02/2009 Nadeeka
135.00 28/02/2009
195.00 28/02/2009
195.00 28/02/2009
325.00 28/02/2009
18.00 15/01/08
11.00 30/10/2004 10,646.76 per M3
95.00
450.00 12/8/2008
95.00 20/03/2009
420.00 25/02/2009
3,240.00 5/8/2008
1,980.00
100.00 125.00
165.00
780.00
165.00
160.00
725.00 12.08.2008 243.78125
2,675.00 1/1/2009 MACKPLY
3,050.00 1/1/2009 1025.5625 0114400136-137 2,055.00
3,200.00 1/1/2009 1076 mackply @sltnet.lk 2,625.00
3,550.00 1/1/2009 1193.6875 2,010.00
4,000.00 1/1/2009 1345
5,800.00 1/1/2009 1950.25
7,550.00 1/1/2009 2538.6875
2,825.00 1/1/2009
3,250.00 1/1/2009 1092.8125
3,450.00 1/1/2009 1160.0625
3,750.00 1/1/2009 1260.9375
4,125.00 1/1/2009 1387.03125
6,175.00 1/1/2009 2076.34375
8,175.00 1/1/2009 2748.84375
200.00 28/02/2009
1,950.00 8/3/2009
2,200.00 8/3/2009
3.54 8/3/2009
7.09 8/3/2009
8.86 8/3/2009
10.63 8/3/2009
12.40 8/3/2009
14.17 8/3/2009
15.94 8/3/2009
17.72 8/3/2009
19.49 8/3/2009
21.26 8/3/2009
26.57 8/3/2009
22.14 8/3/2009
19.92 8/3/2009
17.72 8/3/2009
7.09 8/3/2009
10.63 8/3/2009
14.17 8/3/2009
17.72 8/3/2009
21.26 8/3/2009
24.80 8/3/2009
28.34 8/3/2009
35.43 8/3/2009
21.26 8/3/2009
26.57 8/3/2009
31.89 8/3/2009
37.20 8/3/2009
28.34 8/3/2009
35.43 8/3/2009
42.52 8/3/2009
56.68 8/3/2009
263.00 8/3/2009
10.00 8/3/2009
10.00 8/3/2009
Date
23.00
45.00
135.00
100.00
30/01/2009
Code Category Description Remarks Unit
Z
D Diamond cutting wheel 7" Nos
D 4" Nos
Z Day
Z
Z
Z
Tools & Equipment
Index
Currencet price Date Other Remark Telephone
Tools & Equipment
Price Date
3,500.00
1,350.00
Tools & Equipment
Code Category Description Remarks Unit
A Arpifoam 3'x6'x1/4" Sheet
A Arpifoam 3'x6'x1/2" Sheet
A Asphalt Hot application 1ltr
A Angle valve C/P 1/2" German type No
A A/C unit 9000BTU/hr Nos
A A/C unit 12000BTU/hr Nos
A A/C unit 18000BTU/hr Nos
A A/C unit 24000BTU/hr Nos
Staircase Nosing aluminium - natural with VAT- 12' lengths m
Staircase Nosing pvc with VAT - 2.44m lengths m
Water gal
Glass box
1'-0"x 1'-0" glass
blocks Nos
A
Anti termite tretment
1 Sqr
A
Anti termite tretment
1 Sq.ft
Tube Wells For Gardens 30' 0" Nos
For drinking water 100' 0" Nos
Miscellaneous
Index
Currencet price Date Other RemarkTelephone Price Date
103.00
838.00
20.00
225.00
42,930.00 15/02/2007
48,800.00 15/02/2007
62,200.00 15/02/2007
82,300.00 15/02/2007
323.35 28/10/2008
350.41 28/10/2008
0.50
1,700.00
1,975.00
13.00 8/3/2009 Terminators
40000.00-35000.00 21/04/2009
130,000.00 21/04/2009
Miscellaneous
Miscellaneous
Code Category Description Remarks Unit
Labour Mason
Labour Carpenter
Labour Blaksmith
Labour Painter
Labour Plumber
Labour
Sk labour
Labour
Un/sk labour
Labour Electricion
Labour
Mixer operator
Hire Concrete mixture Day
Hire Vibrator Day
Hire Tractor 1 load
Hire Terrazo cut Machine
Hire Welding plant Day
Hire JCB Hour
Hire Bracker Day
Labour / Hire Charges
Index
Currencet price Date Other Remark Telephone Price Date
950.00
950.00
950.00
950.00
950.00
950.00
650.00
950.00
950.00
2,300.00 12/10/2007
1,850.00 12/10/2007
850.00 22/10/2007
3,200.00
2,500.00 1/12/2008
2,000.00 30/04/2009
4,500.00 20/07/2009
Labour / Hire Charges
Labour / Hire Charges
NET VAT
Rs. 12%
X05-0110 ONE GANG ONE WAY SWITCH 97.40 11.69
X05-0120 TWO GANG ONE WAY SWITCH 164.35 19.72
X05-0130 THREE GANG ONE WAY SWITCH 235.66 28.28
X05-0140 FOUR GANG ONE WAY SWITCH 312.18 37.46
X05-0150 FIVE GANG ONE WAY SWITCH 446.09 53.53
X05-0210 ONE GANG TWO WAY SWITCH 153.99 18.48
X05-0220 TWO GANG TWO WAY SWITCH 270.44 32.45
X05-0230 THREE GANG TWO WAY SWITCH 405.22 48.63
X05-0240 FOUR GANG TWO WAY SWITCH 540.87 64.90
X05-0250 FIVE GANG TWO WAY SWITCH 607.83 72.94
X05-0260 TUMBLER SWITCH 92.18 11.06
X05-0200 BLANK PLATE W/REMOVERBLE PLUG 82.61 9.91
X05-0270 LIGHT DIMMER 665.22 79.83
X05-0280 FAN SPEED CONTROLLER 665.22 79.83
XF5-1100 X SERIES 4 STEP FAN CONTROLLER 716.52 85.98
X05-1050 5A SWITCHED SOCKET OUTLET 271.31 32.56
X05-1060 5A S/SOCKET OUTLET W/NEON 312.18 37.46
X05-1130 13A SWITCH SOCKET OUTLET 286.96 34.44
X05-1140 13A S/SOCKET OUTLET W/NEON 338.27 40.59
X05-1170 13A TWIN SOCKET OUTLET 588.70 70.64
X05-1150 15A SWITCH SOCKET OUTLET 333.05 39.97
X05-1160 15A S/SOCKET OUTLET W/NEON 399.05 47.89
XAC-2050 5A PLUG TOP 116.52 13.98
XAC-2130 13A PLUG TOP 178.26 21.39
XAC-410L LAMP HOLDER 102.61 12.31
X05-1190 75 OHM TELEVISION OUTLET 445.22 53.43
X05-1180 ONE GANG 4 WIRE TELPHON OUTLET 445.22 53.43
X05-1200 8 CON 8WAY TEL SOCKET W/PLATE 1,249.57 149.95
XAC-310S MOUNTING BOX (SINGLE) 35.65 4.28
X05-0180 X30 1G 2WAY B/PRESS SWITCH 230.44 27.65
X05-0320 20A DOUBLE POLE SWITCH W/NEON 665.22 79.83
X07-1180 COOKER CONTROL UNIT 2,250.43 270.05
X05-1183 4G TRAILING SOCKET OUTLET 1,534.79 184.17
X-SERIES WIRING ACCESSORIES PRICE LIST
ITEM CODE DESCRIPTION
1
Orange
OREL SOLUTIONS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792100/1/100 Fax :0114792253

TV / TELEPHONE OUTLETS
MOUNTING BOX
SPECIAL PURPOSE FLUSH SWITCHES
Index
With White or Colour Surround
NET VAT
Rs. 12%
X07-0110 ONE GANG ONE WAY SWITCH WITH SURROUND 86.91 10.43
X07-0120 TWO GANG ONE WAY SWITCH WITH SURROUND 145.22 17.43
X07-0130 THREE GANG ONE WAY SWITCH WITH SURROUND 213.04 25.56
X07-0140 FOUR GANG ONE WAY SWITCH WITH SURROUND 282.61 33.91
X07-0150 FIVE GANG ONE WAY SWITCH WITH SURROUND 349.57 41.95
X07-0210 ONE GANG TWO WAY SWITCH WITH SURROUND 134.78 16.17
X07-0220 TWO GANG TWO WAY SWITCH WITH SURROUND 245.22 29.43
X07-0230 THREE GANG TWO WAY SWITCH WITH SURROUND 368.70 44.24
X07-0240 FOUR GANG TWO WAY SWITCH WITH SURROUND 491.30 58.96
X07-0200 BLANK PLATE WITH SURROUND 73.91 8.87
X07-0270 LIGHT DIMMER WITH SURROUND 595.65 71.48
X07-0280 FAN SPEED CONTROLLER WITH SURROUND 595.65 71.48
X07-0300 FAN SPEED CONTROLLER 4 STEP WITH SURROUND 650.43 78.05
X07-1050 5A SWITCHED SOCKET OUTLET 245.22 29.43
X07-1130 13A SWITCHED SOCKET OUTLET 260.87 31.30
X07-1150 15A SWITCHED SOCKET OUTLET 300.87 36.10
X07-1190 TV SOCKET WITH SURROUND 405.22 48.63
X07-1184 TELEPHONE SOCKET WIYH SURROUND 405.22 48.63
X07-1200 8CON 8WAY TELEPHONE SOCKET OUTLET WITH SURROUND -
X07-0180 BELL PRESS 204.35 24.52
X07-0190 10A INTERMEDIATE SWITCH 2,455.65 294.68
X07-1170 SHAVER SOCKET 3,426.96 411.24
X07-1180 COOKER CONTROL UNIT 2,250.43 270.05
X07-0915 45A DP APPLIANCE SWITCH WITH NEON 1,575.65 189.08
X07-0910 KEY TAG SWITCH 1,841.74 221.01
X07-0320 20A DOUBLE POLE SWITCH WITH NEON 595.65 71.48
OS PROJECTS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
More Details Please Contact Riskhan : 0114792241 or 0773576803. Fax 0114792253
X-2000 WIRING ACCESSORIES PRICE LIST
ITEM CODE DESCRIPTION
SINGLE POLE FLUSH SWITCHES
LIGHT DIMMERS & FAN SPEED CONTROLLERS
SWITCHED SOCKET OUTLETS
TV / TELEPHONE OUTLETS
SPECIAL PURPOSE FLUSH SWITCHES
NET VAT
Rs. 12%
X06-3110 1GANG 1WAY -FERROUS SILVER HL 683.04 81.96
X06-3120 2GANG 1WAY -FERROUS SILVER HL 787.50 94.50
X06-3030 3GANG 1WAY -FERROUS SILVER HL 787.50 94.50
X06-3140 4GANG 1WAY -FERROUS SILVER HL 866.07 103.93
X06-3150 5GANG 1WAY -FERROUS SILVER HL 945.54 113.46
X06-3210 1GANG 2WAY -FERROUS SILVER HL 735.71 88.29
X06-3220 2 GANG 2WAY -FERROUS SILVER HL 840.18 100.82
X06-3270 LIGHT DIMMER-FERROUS SILVER HL 1,334.82 160.18
X06-3280 FAN CONTROL-FERROUS SILVER HL 1,334.82 160.18
X06-3050 5A S/SOCKET -FERROUS SILVER HL 645.54 77.46
X06-3130 13A S/SOCKET -FERROUS SILVER HL 787.50 94.50
X06-3190 TV SOCKET - FERROUS SILVER HL 1,371.43 164.57
X06-3080 X6 Telepho Skt-FERROUS SILVER HL 740.18 88.82
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
TV / TELEPHONE OUTLETS
SPECIAL PURPOSE FLUSH SWITCHES
ITEM COAD DISCRIPTION
SWITCHED SOCKET OUTLETS
X06 WIRING ACCESSORIES PRICE LIST-GOALD HL
LIGHT DIMMERS & FAN SPEED CONTROLLERS
SINGLE POLE FLUSH SWITCHES
X06-3180 BELL PRESS - FERROUS SILVER HL 566.96 68.04
X06-3320 DOUBLE POLE-FERROUS SILVER HL 840.18 100.82
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
XMA-106C 6A 1POLE MCB Type C 179.14 21.50
XMA-110C 10A 1POLE MCB Type C 179.14 21.50
XMA-116C 16A 1POLE MCB Type C 179.14 21.50
XMA-120C 20A 1POLE MCB Type C 179.14 21.50
XMA-132C 32A 1POLE MCB Type C 179.14 21.50
XRA-240Y 40A 30mA 2POLE RCD 1,611.31 193.36
XIS-240A 40A 2POLE ISOLATOR 399.14 47.90
XMS-106C 6A 1 POLE MCB TYPE C - SIGMA (With 5Years Warraty) 302.61 36.31
XMS-110C 10A 1 POLE MCB TYPE C- SIGMA ( do) 302.61 36.31
XMS-116C 16A 1 POLE MCB TYPE C - SIGMA (do) 302.61 36.31
XMS-120C 20A 1 POLE MCB TYPE C - SIGMA (do) 302.61 36.31
XMS-132C 32A 1 POLE MCB TYPE C - SIGMA (do) 302.61 36.31
XMS-140C 40A 1 POLE MCB TYPE C - SIGMA (do) 343.48 41.22
XMS-206C 6A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39
XMS-210C 10A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39
XMS-216C 16A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39
XMS-220C 20A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39
XMS-232C 32A 2 POLE MCB TYPE C - SIGMA (do) 578.27 69.39
XMS-240C 40A 2 POLE MCB TYPE C - SIGMA (do) 660.00 79.20
XMS-263C 63A 2 POLE MCB TYPE C - SIGMA (do) 660.00 79.20
XMS-306C 6A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73
XMS-310C 10A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73
XMS-316C 16A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73
XMS-320C 20A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73
XMS-332C 32A 3 POLE MCB TYPE C - SIGMA (do) 906.09 108.73
XMS-340C 40A 3 POLE MCB TYPE C - SIGMA (do) 941.74 113.01
OS PROJECTS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792131/100 Fax :0114792128
ORANGE ALPHA & SIGMA PRICE LIST
ORANGE ALPHA
ORANGE SIGMA
XMS-363C 63A 3 POLE MCB TYPE C - SIGMA (do) 1,002.61 120.31
XMS-406C 6A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16
XMS-410C 10A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16
XMS-416C 16A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16
XMS-420C 20A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16
XMS-432C 32A 4 POLE MCB TYPE C - SIGMA (do) 1,151.31 138.16
XMS-440C 40A 4 POLE MCB TYPE C - SIGMA (do) 1,213.05 145.57
XMS-463C 63A 4 POLE MCB TYPE C - SIGMA (do) 1,330.44 159.65
XRS-240Y 40A 30mA 2 POLE RCD - SIGMA ( with 5 Years warranty) 2,148.70 257.84
XRS-240Z 40A 100mA 2 POLE RCD - SIGMA ( do) 2,327.83 279.34
XRS-240Y 63A 30mA 2 POLE RCD - SIGMA ( do) 2,302.61 276.31
XRS-240Z 63A 100mA 2 POLE RCD - SIGMA ( do) 2,358.27 282.99
XRS-240Y 40A 30mA 4 POLE RCD - SIGMA ( do) 3,100.00 372.00
XRS-240Z 40A 100mA 4 POLE RCD - SIGMA ( do) 3,222.61 386.71
XRS-240Y 63A 30mA 4 POLE RCD - SIGMA ( do) 3,401.74 408.21
XIS-240A 40A 2 POLE ISOLATOR - SIGMA ( With 5 Years Warranty) 640.00 76.80
XIS-263A 63A 2POLE ISOLATER -SIGMA (do) 757.40 90.89
XIS-340A 40A 3POLE ISOLATER -SIGMA (do) 1,064.35 127.72
XIS-363A 63A 3POLE ISOLATER -SIGMA (do) 1,151.31 138.16
XIS-440A 40A 4POLE ISOLATER -SIGMA (do) 1,213.05 145.57
XIS-463A 63A 4POLE ISOLATER -SIGMA (do) 1,330.44 159.65
ZT000310 ORANGE CFL 5W (Day Light / Pin Type) 265.22 31.83
XCU-P07D ORANGE CFL 7W (Day Light / Pin Type) 265.22 31.83
XCU-P09D ORANGE CFL 9W (Day Light / Pin Type) 265.22 31.83
XCU-P11D ORANGE CFL 11W (Day Light / Pin Type) 265.22 31.83
XCU-P15D ORANGE CFL 15W (Day Light / Pin Type) 265.22 31.83
XCU-P20D ORANGE CFL 20W (Day Light / Pin Type) 321.74 38.61
XCU-P05W ORANGE CFL 5W (Warm White / Pin Type) 265.22 31.83
XCU-P09W ORANGE CFL 9W (Warm White / Pin Type) 265.22 31.83
XCU-P11W ORANGE CFL 11W (Warm White / Pin Type) 265.22 31.83
XCU-P15W ORANGE CFL 15W (Warm White / Pin Type) 265.22 31.83
XCU-P20W ORANGE CFL 20W (Warm White / Pin Type) 321.74 38.61
ZT000311 ORANGE CFL 5W (Day Light / Srew Type) 265.22 31.83
XCU-S09D ORANGE CFL 9W (Day Light / Srew Type) 265.22 31.83
Prices are subjected to change without prior notice
5 Years Warranty For Sigma Products & 1 Year Warranty For Alpha RCD
RCD SIGMA
More Details Please Contact Lakshitha Morawaka: 0114792133 or 0773688392. Fax 0114792253
OS PROJECTS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
ORANGE COMPACT FLUORESCENT LAMPS (CFL.s)
XCU-S11D ORANGE CFL 11W (Day Light / Srew Type) 265.22 31.83
XCU-S15D ORANGE CFL 15W (Day Light / Srew Type) 265.22 31.83
XCU-S20D ORANGE CFL 20W (Day Light / Srew Type) 321.74 38.61
XCU-S05D ORANGE CFL 9W (Warm White / Srew Type) 265.22 31.83
XCU-S09W ORANGE CFL 9W (Warm White / Srew Type) 265.22 31.83
XCU-S11W ORANGE CFL 11W (Warm White / Srew Type) 265.22 31.83
XCU-S15W ORANGE CFL 15W (Warm White / Srew Type) 265.22 31.83
XCU-S20W ORANGE CFL 20W (Warm White / Srew Type) 321.74 38.61
(Warranty : 18 Month)
ORANGE SPIRAL CFL
XCS-P07D ORANGE SPIRAL CFL 7W (Day Light / Pin Type) 308.70 37.04
XCS-P11D ORANGE SPIRAL CFL 11W (Day Light / Pin Type) 308.70 37.04
XCS-P15D ORANGE SPIRAL CFL 15W (Day Light / Pin Type) 308.70 37.04
XCS-P20D ORANGE SPIRAL CFL 20W (Day Light / Pin Type) 391.70 47.00
XCS-P25D ORANGE SPIRAL CFL 25W (Day Light / Pin Type) 413.04 49.56
XCS-S07D ORANGE SPIRAL CFL 7W (Day Light / Srew Type) 308.70 37.04
XCS-S11D ORANGE SPIRAL CFL11W (Day Light / Srew Type) 308.70 37.04
XCS-S15D ORANGE SPIRAL CFL15W (Day Light /SrewType) 308.70 37.04
XCS-S20D ORANGE SPIRAL CFL 20W (Day Light / Srew Type) 391.30 46.96
XCS-S25D ORANGE SPIRAL CFL 25W (Day Light / Srew Type) 413.04 49.56
XCS-P07W ORANGE SPIRAL CFL 7W (Warm White / Pin Type) 308.70 37.04
XCS-P11W ORANGE SPIRAL CFL 11W ( Warm White/ Pin Type) 308.70 37.04
XCS-P15W ORANGE SPIRAL CFL 15W ( Warm White/ Pin Type) 308.70 37.04
XCS-P20W ORANGE SPIRAL CFL 20W ( Warm White/ Pin Type) 391.30 46.96
XCS-S07W ORANGE SPIRAL CFL 7W (Warm White / Screw Type) 308.70 37.04
XCS-S11W ORANGE SPIRAL CFL 11W (Warm White / Screw Type) 308.70 37.04
XCS-S15W ORANGE SPIRAL CFL 15W (Warm White / Screw Type) 308.70 37.04
XCS-S11W ORANGE SPIRAL CFL 20W (Warm White / Screw Type) 391.30 46.96
Warranty : 12 Month
ORANGE FLOURESCENT TUBES
XTL-018D FLUORESCENT TUBE 2FEET - DAYLIGHT 73.91 8.87
XTL-036D FLUORESCENT TUBE 4FEET - DAYLIGHT 73.91 8.87
ORANGE GLS
XG1-025C 25W GLS BULBS (Clear /Pin Type) 55.36 6.64
XG1-040C 40W GLS BULBS (Clear /Pin Type) 55.36 6.64
XG1-060C 60W GLS BULBS (Clear /Pin Type) 55.36 6.64
XG1-075C 75W GLS BULBS (Clear /Pin Type) 55.36 6.64
XG1-100C 100W GLS BULBS (Clear /Pin Type) 55.36 6.64
XG2-025C 25W GLS BULBS (Clear /Screw Type) 55.36 6.64
XG2-040C 40W GLS BULBS (Clear /ScrewType) 55.36 6.64
XG2-060C 60W GLS BULBS (Clear /Screw Type) 55.36 6.64
XG2-075C 75W GLS BULBS (Clear /Screw Type) 55.36 6.64
XG2-100C 100W GLS BULBS (Clear /Pin Type) 55.36 6.64
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
Item Description Imp Size mm Size
PVC Cable
XT-01113-B-RD-4 1/1.13mm S/C 100m Red 1/0.044 1
XT-01113-B-RD-2 1/1.13mmS/C 50m Red 1/0.044 1
XT-01113-B-BK-4 1/1.13mm S/C 100m Black 1/0.044 1
XT-01113-B-BK-21/1.13mmS/C 50m Red 1/0.044 1
XT-07053-B-RD-4 7/0.50mm S/C100m Red 3/0.036 1.5
XT-07053-B-BK-4 7/0.50mm S/C100m Black 3/0.036 1.5
XT-07053-C-MC-4 7/0.50mm T/ Flat 100m 3/0.036 1.5
XT-07067-B-RD-4 7/0.67mm S/C100m Red 7/0.029 2.5
XT-07067-B-BK-4 7/0.67mm S/C100m Black 7/0.029 2.5
XT-07067-C-MC-4 7/0.67mm T/ F 100m 7/0.029 2.5
XT-07067-P-MC-4 7/0.67 mm Green 100m 7/0.029 2.5
XT-07067-P-MC-2 7/0.67 mm Green 50m 7/0.029 2.5
XT-07085-B-RD-4 7/0.85 mm S/C100m Red 7/0.036 4
XT-07085-B-BK-4 7/0.85 mm S/C100m Black 7/0.036 4
XT-07085-C-MC-4 7/0.85 mm T/ F 100m 7/0.036 4
XT-07104-B-RD-4 7/1.04mm S/C 100m Red 7/0.044 6
XT-07104-B-BK-4 7/1.04mm S/C 100m Black 7/0.044 6
XT-07104-C-MC-4 7/1.04mm T/ F 100m 7/0.044 6
XT-07104-C-MC-2 7/1.04mm T/ F 50m 7/0.044 6
XT-07135-B-RD-4 7/1.35mm S/C 100m Red 7/0.052 10
XT-07135-B-BK-4 7/1.35mm S/C 100m Black 7/0.052 10
XT-07135-C-MC-4 7/1.35mm T/ F 100m 7/0.052 10
XT-07170-B-RD-4 7/1.70mmS/C 100m Red 7/0.064 16
XT-07170-B-BK-4 7/1.70mmS/C 100m Black 7/0.064 16
XT-07170-C-MC-4 7/1.70mm T/ F 100m 7/0.064 16
XLPE INSULATED CABLES (Cu/XLPE/PVC)
XT-07214-B-BK-47/2.14mm S/C 100m Red 19/0.044 25
CABLE PRICE LIST
OREL SOLUTIONS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133 Fax :0114792253
XT-07214-B-RD-4 7/2.14mm S/C 100m Red 19/0.044 25
XT-19135-B-BK-4 19/1.35mm S/C 100m Black 19/0.052 25
XT-19135-B-RD-4 19/1.35mm S/C 100m Red 19/0.052 25
XT-19153-B-RD-4 19/1.53mm S/C 100m Red 19/0.064 35
XT-19153-B-BK-419/1.53mm S/C 100m Black 19/0.064 35
XT-19178-B-RD-4 19/1.78mm S/C 100m Red 19/0.073 50
XT-19178-B-BK-419/1.78mm S/C 100m Black 19/0.073 50
XT-19214-B-RD-4 19/2.14mm S/C 100m Red 19/0.083 70
XT-19214-B-BK-419/2.14mm S/C 100m Black 19/0.083 70
XT-19252-B-RD-4 19/2.52mm S/C 100m Red 37/0.072 95
XT-19252-B-BK-419/2.52mm S/C 100m Black 37/0.072 95
XT-37178-B-RD-4 37/1.78mm S/C 100m Red 37/0.072 95
XT-37178-B-BK-4 37/1.78mm S/C 100m Black 37/0.072 95
XT-37203-B-RD-4 37/2.03mm S/C 100m Red 37/0.083 120
XT-37203-B-BK-4 37/2.03mm S/C 100m Black 37/0.083 120
XT-37225-B-RD-4 37/2.25mm S/C 100m Red 37/0.093 150
XT-37225-B-BK-4 37/2.25mm S/C 100m Black 37/0.093 150
XT-37252-B-RD-4 37/2.52mm S/C 100m Red 37/0.103 185
XT-37252-B-BK-437/2.52mm S/C 100m Black 37/0.103 185
XT-61225-B-RD-4 61/2.25mm S/C 100m Red 61/0.093 240
XT-61225-B-BK-461/2.25mm S/C 100m Black 61/0.093 240
XT-61252-B-RD-4 61/2.52mm S/C 100m Red 61/0.103 300
XT-61252-B-BK-4 61/2.52mm S/C 100m Black 61/0.103 300
XT-61285-B-RD-4 61/2.85mm S/C 100m Red 400
XT-61285-B-BK-4 61/2.85mm S/C 100m Black 400
XT-61320-B-RD-4 61/3.20mm S/C 100m Red 91/0.103 500
XT-61320-B-BK-4 61/3.20mm S/C 100m Black 91/0.103 500
GROSS
Rs.
109.09
184.07
263.94
349.64
499.62
172.47
302.89
453.85
605.77
680.77
103.24
92.52
745.05
745.05
802.50
303.87
349.64
321.40
378.86
659.34
373.02
446.94
130.50
199.65
114.92
498.65
498.65
1,399.52
39.93
258.09
745.05
2,520.48
1,718.96
X-SERIES WIRING ACCESSORIES PRICE LIST
1
Orange
OREL SOLUTIONS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792100/1/100 Fax :0114792253

TV / TELEPHONE OUTLETS
MOUNTING BOX
SPECIAL PURPOSE FLUSH SWITCHES
GROSS
Rs.
97.34
162.65
238.60
316.52
391.52
150.95
274.65
412.94
550.26
82.78
667.13
667.13
728.48
274.65
292.17
336.97
453.85
453.85
-
228.87
2,750.33
3,838.20
2,520.48
1,764.73
2,062.75
667.13
OS PROJECTS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
More Details Please Contact Riskhan : 0114792241 or 0773576803. Fax 0114792253
X-2000 WIRING ACCESSORIES PRICE LIST
SINGLE POLE FLUSH SWITCHES
LIGHT DIMMERS & FAN SPEED CONTROLLERS
SWITCHED SOCKET OUTLETS
TV / TELEPHONE OUTLETS
SPECIAL PURPOSE FLUSH SWITCHES
GROSS
Rs.
765.00
882.00
882.00
970.00
1,059.00
824.00
941.00
1,495.00
1,495.00
723.00
882.00
1,536.00
829.00
More Details Please Contact Lakshitha: 0114792133 or 0773688392. Fax 0114792253
TV / TELEPHONE OUTLETS
SPECIAL PURPOSE FLUSH SWITCHES
SWITCHED SOCKET OUTLETS
X06 WIRING ACCESSORIES PRICE LIST-GOALD HL
LIGHT DIMMERS & FAN SPEED CONTROLLERS
SINGLE POLE FLUSH SWITCHES
635.00
941.00
200.64
200.64
200.64
200.64
200.64
1,804.67
447.04
338.92
338.92
338.92
338.92
338.92
384.70
647.66
647.66
647.66
647.66
647.66
739.20
739.20
1,014.82
1,014.82
1,014.82
1,014.82
1,014.82
725.00
OS PROJECTS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792131/100 Fax :0114792128
ORANGE ALPHA & SIGMA PRICE LIST
ORANGE ALPHA
ORANGE SIGMA
800.00
925.00
925.00
925.00
925.00
925.00
975.00
1,000.00
2,406.54
2,607.17
2,578.92
2,641.26
3,472.00
3,609.32
3,809.95
716.80
848.29
1,192.07
1,289.47
1,358.62
1,490.09
297.05
297.05
297.05
297.05
297.05
360.35
297.05
297.05
297.05
297.05
360.35
297.05
297.05
Prices are subjected to change without prior notice
5 Years Warranty For Sigma Products & 1 Year Warranty For Alpha RCD
RCD SIGMA
More Details Please Contact Lakshitha Morawaka: 0114792133 or 0773688392. Fax 0114792253
OS PROJECTS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133/108/100 Fax :0114792253
ORANGE COMPACT FLUORESCENT LAMPS (CFL.s)
297.05
297.05
360.35
297.05
297.05
297.05
297.05
360.35
345.74
345.74
345.74
438.70
462.60
345.74
345.74
345.74
438.26
462.60
345.74
345.74
345.74
438.26
345.74
345.74
345.74
438.26
82.78
82.78
62.00
62.00
62.00
62.00
62.00
62.00
62.00
62.00
62.00
62.00
Amp Net Vat Gross Price
12 1,286.96 154.44 1441.40
12 643.48 77.22 720.70
12 1,286.96 154.44 1441.40
12 643.48 77.22 720.70
14 2,803.48 336.42 3139.90
14 2,803.48 336.42 3139.90
14 5,337.39 640.49 5977.88
17 4144.57 497.35 4641.92
17 4144.57 497.35 4641.92
17 7776.96 933.24 8710.20
17 3733.48 448.02 4181.50
17 1866.74 224.01 2090.75
29 6476.30 777.16 7253.46
29 6476.30 777.16 7253.46
29 12245.00 1469.40 13714.40
37 9407.83 1128.94 10536.77
37 9407.83 1128.94 10536.77
37 16800.65 2016.08 18816.73
37 8400.33 1008.04 9408.37
51 15506.74 1860.81 17367.55
51 15506.74 1860.81 17367.55
51 27859.57 3343.15 31202.72
66 23647.61 2837.71 26485.32
66 23647.61 2837.71 26485.32
66 42065.65 5047.88 47113.53
87 38372.61 5755.89 44128.50
CABLE PRICE LIST
OREL SOLUTIONS (PVT) LTD
No 49, Sri Jinaratana Road, Colombo 02.
Tel 0114792133 Fax :0114792253
87 38372.61 5755.89 44128.50
87 40805.43 6120.81 46926.24
87 40805.43 6120.81 46926.24
106 52720.22 7908.03 60628.25
106 52720.22 7908.03 60628.25
125 64918.04 9737.71 74655.75
125 64918.04 9737.71 74655.75
160 107078.04 16061.71 123139.75
160 107078.04 16061.71 123139.75
195 134411.96 20161.79 154573.75
195 134411.96 20161.79 154573.75
195 139567.39 20935.11 160502.50
195 139567.39 20935.11 160502.50
220 186181.96 27927.29 214109.25
220 186181.96 27927.29 214109.25
260 211581.74 31737.26 243319.00
260 211581.74 31737.26 243319.00
295 264396.30 39659.45 304055.75
295 264396.30 39659.45 304055.75
360 391300.87 58695.13 449996.00
360 391300.87 58695.13 449996.00
410 500218.70 75032.81 575251.51
410 500218.70 75032.81 575251.51
457 612135.43 91820.31 703955.74
457 612135.43 91820.31 703955.74
520 790783.04 118617.46 909400.50
520 790783.04 118617.46 909400.50
Fenders & Bollards
#
Description Unit Qty Rate Amount
1 Mild steel chain links with
16mm wire (available in 3m
lengths) m 3 1,500.00 4,500.00
2 Mild steel D-shackle 12mm nr 1 175.00 175.00
3 Rubber Fender (1800mm
length - IRHD 65) m 1.8 16,666.67 30,000.00
Habour
Index
Habour
Contact Mr. Chaminda Williams
0773 667665
# Description Rate Unit
Notes:
Micro partitining system
siutable for both internal & external walls
can build with the rigiform+mesh panels to any span
supply & installation done by micro
1 Per unit floor area to complete including all foundation
work, structure, finishing as with normal brick wall. 3200 sq.ft.
2 Per unit wall area including plaster and painted finish as
with normal brick wall 450 sq.ft.
Habour
Index
Habour
LABOUR RATES
Code Category Description Remarks Unit Currencet price
1 Labour Rate Foundation excavation Cube 2,000.00
2 Labour Rate Earth filling around foundation Cube 800.00
3 Labour Rate 2" thick lean concrete Sq.ft 25.00
4 Labour Rate 3" thick lean concrete Sq.ft 30.00
5 Labour Rate 4" thick lean concrete Sq.ft 35.00
6 Labour Rate Column base 3'-0" 3'-0" Nos 2,400.00
7 Labour Rate Column base 6" thick Sq.ft 65.00
8 Labour Rate Column base 9" thick Sq.ft 70.00
9 Labour Rate Column base 12" thick Sq.ft 75.00
10 Labour Rate Rubble foundation Cu.ft 42.00
11 Labour Rate DPC 1'-0" with (Two coat tar) L.ft 20.00
12 Labour Rate 9" thick brick wall Sq.ft 45.00
13 Labour Rate 41/2" thick brick wall Sq.ft 30.00
14 Labour Rate 8" thick block wall Sq.ft 32.00
15 Labour Rate 6" thick block wall Sq.ft 28.00
16 Labour Rate 4" thick block wall Sq.ft 25.00
17 Labour Rate Column 9" x 9" L.ft 95.00
18 Labour Rate Column 12" x 12" L.ft 110.00
19 Labour Rate Lintol 41/2" X 6" L.ft 55.00
20 Labour Rate Lintol 4" X 6" L.ft 50.00
21 Labour Rate Lintol 9" X 6" L.ft 55.00
22 Labour Rate Beam 9" x 9" L.ft 100.00
23 Labour Rate Beam 9" x 12" L.ft 110.00
24 Labour Rate Beam 9" x 15" L.ft 120.00
25 Labour Rate Beam 9" x 18" L.ft 125.00
26 Labour Rate 41/2" thick slab -Conc., R/F & formwork Sq.ft 70.00
27 Labour Rate Stair case Sq.ft 160.00
28 Labour Rate Smooth plaster Sq.ft 20.00
29 Labour Rate Rough plaster Sq.ft 18.00
30 Labour Rate Soffit plaster Sq.ft 27.00
31 Labour Rate Smooth plaster in sides of column & beam Sq.ft 45.00
32 Labour Rate Rough plaster in sides of column & beam Sq.ft 40.00
33 Labour Rate Floor concrete 3" Sqr 2,500.00
34 Labour Rate Cement rendering- smooth Sq.ft 30.00
Labour Rate
Index
35 Labour Rate Cement rendering- rough Sq.ft 20.00
36 Labour Rate Skirting - cement L.ft 30.00
37 Labour Rate Floor tile 1' 6" x 1' 6" Sq.ft 35.00
38 Labour Rate Wall tile Sq.ft 45.00
39 Labour Rate Skirting - tile L.ft 40.00
40 Labour Rate Plinth plaster Sq.ft 30.00
41 Labour Rate Internal painting Sqr 1,200.00
42 Labour Rate External painting Sqr 1,000.00
43 Labour Rate Putty & paint Sqr 2,000.00
44 Labour Rate Door frame fix Nos 600.00
45 Labour Rate Window - large Nos 850.00
46 Labour Rate Window Nos 600.00
47 Labour Rate Polishing Sqr 3,500.00
48 Labour Rate weather gard L.ft 60.00
49 Labour Rate Ridge tile L.ft 55.00
50 Labour Rate Concrete drain with plastering Sq.ft 70.00
51 Labour Rate Manhole (2' x 2' x 2') Nos 3,000.00
52 Labour Rate Terazzo Sq.ft 270.00
53 Labour Rate Titanium - normal Sq.ft 220.00
54 Labour Rate Titanium - colour Sq.ft 250.00
55 Labour Rate Fixing marble with adhensive Sq.ft 125.00
56 Labour Rate Fixing tile 1'-0" x 1'-0" Sq.ft 35.00
57 Labour Rate Assorted dressed stone Sq.ft 40.00
58 Labour Rate Glass mosaic Tile Sq.ft 50.00
Labour Rate Mason 1,250.00
Labour Rate Labour 850.00
Date Other Remark Telephone Price Date Price Date Price
23/11/2009 1,500.00 12/1/2009
23/11/2009 1,000.00 12/1/2009
23/11/2009
23/11/2009 25.00 12/1/2009
10/11/2009
12/1/2009
23/11/2009
23/11/2009
23/11/2009
23/11/2009 30.00 12/1/2009
23/11/2009 15.00 12/1/2009
23/11/2009 42.00 10/11/2009 38.00 8/3/2009 28.00
23/11/2009 35.00 10/11/2009 25.00 8/3/2009 24.00
23/11/2009 35.00 10/11/2009
23/11/2009 30.00 10/11/2009
23/11/2009 25.00 10/11/2009
23/11/2009 85.00 12/1/2009
12/1/2009
12/1/2009
23/11/2009
23/11/2009 65.00 12/1/2009
23/11/2009 80.00 12/1/2009
23/11/2009 95.00 12/1/2009
23/11/2009
23/11/2009
23/11/2009 85.00 12/1/2009
23/11/2009
23/11/2009 20.00 8/3/2009 20.00 12/1/2009
23/11/2009 18.00 8/3/2009 18.00 12/1/2009
23/11/2009 28.00 8/3/2009 28.00 12/1/2009
23/11/2009
23/11/2009
12/1/2009
23/11/2009 21.00 12/1/2009
Labour Rate
23/11/2009
23/11/2009 28.00 12/1/2009
23/11/2009 37.50 8/3/2009 30.00 12/1/2009
23/11/2009 40.00 8/3/2009 45.00 12/1/2009
23/11/2009
23/11/2009
8/3/2009
8/3/2009
8/3/2009
23/11/2009 500.00 8/3/2009
23/11/2009
8/3/2009
8/3/2009
23/11/2009
23/11/2009
23/11/2009
23/11/2009
1/6/2009
1/6/2009
1/6/2009
1/6/2009
1/6/2009
1/6/2009
1/6/2009
8/3/2009 950.00
8/3/2009 650.00
Date
12/1/2009
12/1/2009
HOSPITAL EQUEPMENT
Code Category Description Remarks Unit Currencet price
Paitient Beds Nr 25,000.00
Delivery beds Nr 300,000.00
Examination beds Nr 25,000.00
Paitient Trolley Nr 25,000.00
Drug Trolley Nr 30,000.00
Dressing Trolley Nr 30,000.00
Wheel chair Nr
Ward screen Nr 25,000.00
Saline stand Nr 12,500.00
Bed side cupboard Nr 15,000.00
Oxygen cylinder stand 15,000.00
Index
Date Other Remark Telephone Price Date Price
26/05/2010 Biomed International (Pvt) Ltd 2576104 /2577226
26/05/2010
26/05/2010
26/05/2010
26/05/2010
26/05/2010
26/05/2010
26/05/2010
26/05/2010
26/05/2010
26/05/2010
Date Price Date
Discription Nos Length Width Height Qty
3.1.21
Casting and fixing in position 6"x 2 1/2" R.C pergolas
reinforced with 02 nos.Y 10 bars and R6 links at 6"
centres all complete Rate shall include for prepare and
apply two coats weather shield emulsion paint of
approved quality and colour .
Assume 10 L,ft
Material
Concrete for pergolas
Wastage 10%
Reinforcement Y 10
Painting
two coats weather shield emulsion paint
Labour
Cost for 10 L.ft
O/H % Profit 18%
Cost for 1 L.ft
Cost for 1 m
Supply and lay 6mm double sided 'Macfoil ' aluminium
foil as directed.
assume 10 m2
Material
6mm double sided 'Macfoil '
screws and nails
wastage 5%
Transport 7%
Labour
unskilled
Tools 3%
Total cost
O/H % Profit 18%
Cost for 10m2
Cost for 1m2
6.10
Supply and lay two layers of half round tiles as coping
over walls/boundary walls complete as per drawing .
Assume 10 L.ft
Material
Half round tile
Cement
Sand
Transport 10%
Labour
Skilled
Un skilled
Tools 3%
Cost for 10 L.ft
O/H % Profit 18%
Cost for 1 L.ft
Cost for 1 m
14.02
Single sash white powder coated aluminium louvred
door complete as per type D6 , Size 750x2400mm
14.03
White powder coated aluminium window with glazed
and louvred panels complete as per type W2 ,Size
600x1500mm
14.03
Mild steel grille door complete as per type G1 Size
1500x2400mm
Material
36mm dia GI frame
18mm GI horizontal members
GI Hinges 3" x 5"
Locking divice
Labour
Tools 3%
Total cost
Add O/H & Profit 18%
Cost for I Door
Cost for I m2
14.04
Mild steel grille door complete as per type G2 Size
900x2400mm
14.05
Mild steel grille door complete as per type G3 Size
1237x1800mm
14.06
Mild steel grille door complete as per type G4 Size
4000 x 2875mm
14.07
Mild steel grille door complete as per type G5 Size
4200 x 2875mm
14.08
Mild steel grille door complete as per type G6 Size 600
x 750 mm
14.09
Mild steel grille door complete as per type G7 Size
1500 x 1500 mm
15.01
Built in R.C.C. concrete storage unit with shelves 75mm
thick 5000x600 mm and 5000x300 mm with 16mm
thick plywood doors with a painted finish and self
closing hinges and lock in store room complete as per
drawing .
Material
100mm thick brick wall 4 0.60 2.10 5.04
75mm thick RCC shelves 9 0.92 0.60 4.97
Formwork 18 0.92 0.60 9.94
BRC mesh 9 0.92 0.60 4.97
50 x 50mm timber frame 10 2.10 21.00
5 0.92 4.60
Plywood doors 5 5.00
Brick wall & shelves plastering 8 0.60 2.10 10.08
18 0.92 0.60 9.94
Brick wall & shelves painting 8 0.60 2.10 10.08
18 0.92 0.60 9.94
Plywood doors painting 10 0.92 2.10 19.32
Self closing hinges 10 10.00
Total cost
O/H % Profit 18%
15.02
Built in R.C.C. concrete storage unit with shelves 75mm
thick 5000x600 mm and 5000x300 mm with 16mm
thick plywood doors with a painted finish and self
closing hinges and lock in study room complete as per
drawing .
Material
100mm thick brick wall 2 0.30 2.40 1.44
3 0.30 1.05 0.95
75mm thick RCC shelves 22 0.30 0.70 4.62
1 3.50 0.60 2.10
Formwork 44 0.30 0.70 9.24
2 3.50 0.60 4.20
BRC mesh 22 0.30 0.70 4.62
1 3.50 0.60 2.10
50 x 50mm timber frame 8 0.75 6.00
Plywood doors 2 0.75 0.75 1.13
Brick wall & shelves plastering 4 0.30 2.40 2.88
6 0.30 1.05 1.89
44 0.30 0.70 9.24
Brick wall & shelves painting 4 0.30 2.40 2.88
6 0.30 1.05 1.89
44 0.30 0.70 9.24
Plywood doors painting 2 0.75 0.75 1.13
Cut & polish concrete 1 3.50 0.60 2.10
Self closing hinges 4 4.00
Total cost
O/H % Profit 18%
15.04
Built in R.C.C Work Tops,shelves and granite slab over
work top /shelves , internal shelf of timber,drawers and
cupboards doors in pantry all complete as per drawing
.

Material
75mm thick RCC shelves 1 5.00 0.60 3.00
8 0.60 0.90 4.32
6 2.40 0.60 8.64
1 5.00 0.60 3.00
1 2.70 0.60 1.62
1 5.00 1.14 5.70
Formwork 2 5.00 0.60 6.00
16 0.60 0.90 8.64
12 2.40 0.60 17.28
2 5.00 0.60 6.00
2 2.70 0.60 3.23
2 5.00 1.14 11.40
BRC mesh 1 5.00 0.60 3.00
8 0.60 0.90 4.32
6 2.40 0.60 8.64
1 5.00 0.60 3.00
1 2.70 0.60 1.62
1 5.00 1.14 5.70
Plywood doors 5.00 0.75 3.75
5.00 2.40 12.00
10 0.90 0.60 5.40
10 0.30 0.90 2.70
10 0.30 0.60 1.80
Brick wall & shelves plastering 2 5.00 0.60 6.00
16 0.60 0.90 8.64
12 2.40 0.60 17.28
2 5.00 0.60 6.00
2 2.70 0.60 3.23
2 5.00 1.14 11.40
Brick wall & shelves painting 2 5.00 0.60 6.00
16 0.60 0.90 8.64
12 2.40 0.60 17.28
2 5.00 0.60 6.00
2 2.70 0.60 3.23
2 5.00 1.14 11.40
Plywood doors painting 2 5.00 0.75 7.50
2 5.00 2.40 24.00
20 0.90 0.60 10.80
20 0.30 0.90 5.40
20 0.30 0.60 3.60
Granite 5.00 0.60 3.00
5.00 1.14 5.70
0.98 0.90 0.88
Self closing hinges 4 4.00
Total cost
O/H % Profit 18%
15.05
Built in seat / table with cut & polished cement finish in
living room complete as per drawing .
Material
Concrete 4.90 0.95 0.30 1.40
2.40 0.25 0.70 0.42
Formwork 1 4.90 0.30 1.47
2 0.95 0.30 0.57
2 2.40 0.70 3.36
2 0.70 0.25 0.35
BRC mesh 4.90 0.95 4.66
2.40 0.25 0.60
Cut & Polish 2 2.40 0.70 3.36
2 0.80 1.25 2.00
100mm deep cushion 2 2.40 0.70 3.36
Rough granite 2 0.30 1.25 0.75
Total cost
O/H % Profit 18%
15.06
Built in R.C.C Work Tops , shelves and cut and
polished cement finished over work tops / shelves
,internal shelf of timber,drawers and cupboards doors
in kitchen all complete as per drawing .
75mm thick RCC shelves 5 2.58 0.60 7.73
1 0.52 0.60 0.31
13 0.90 0.60 7.02
3 0.96 0.60 1.72
2 1.13 0.60 1.36
3 2.16 0.60 3.89
5 0.90 0.60 2.70
Formwork 10 2.58 0.60 15.45
2 0.52 0.60 0.62
26 0.90 0.60 14.04
6 0.96 0.60 3.44
4 1.13 0.60 2.72
6 2.16 0.60 7.79
10 0.90 0.60 5.40
BRC mesh 5 2.58 0.60 7.73
1 0.52 0.60 0.31
13 0.90 0.60 7.02
3 0.96 0.60 1.72
2 1.13 0.60 1.36
3 2.16 0.60 3.89
5 0.90 0.60 2.70
Cut & Polish 5 2.58 0.60 7.73
1 0.52 0.60 0.31
13 0.90 0.60 7.02
3 0.96 0.60 1.72
2 1.13 0.60 1.36
3 2.16 0.60 3.89
5 0.90 0.60 2.70
Plywood doors and drawers 3 0.96 0.60 1.72
6 0.96 0.15 0.86
6 0.60 0.15 0.54
Plywood doors and drawers painting 6 0.96 0.60 3.44
12 0.96 0.15 1.72
12 0.60 0.15 1.08
Total cost
O/H % Profit 18%
15.07
Built in R.C.C. concrete bed 1875x1800 mm in bed
room 01 complete as per drawing . 1.88 1.80
Mass Concrete 1.88 1.80 0.23 0.76
1.80 0.80 0.15 0.22
Formwork 2 1.88 0.23 0.86
2 1.80 0.23 0.83
1 1.80 0.80 1.44
2 0.80 0.15 0.24
1 1.80 0.15 0.27
BRC mesh 1.80 0.15 0.27
0.15 0.80 0.12
Total cost
O/H % Profit 18%
15.08
Built in R.C.C.concrete ledge 600x675 mm in bed room
01 complete as per drawing .
Concrete ledge 1 0.68 0.60 0.41
Formwork 1 0.68 0.60 0.41
2 0.68 0.08 0.10
2 0.60 0.08 0.09
BRC Mesh 0.68 0.60 0.00
Cut & polish 1 0.68 0.60 0.41
2 0.68 0.08 0.10
2 0.60 0.08 0.09
Total cost
O/H % Profit 18%
15.09
Built in R.C.C.concrete dressing table/storage
2700x600 mm with cement rendered with cupboard
doors in bed room 01 complete as per drawing .
75mm thick RCC shelves 1 1.38 0.60 0.83
4 1.20 0.60 2.88
2 0.60 0.60 0.72
3 2.40 0.60 4.32
Formwork 2 1.38 0.60 1.65
8 1.20 0.60 5.76
4 0.60 0.60 1.44
6 2.40 0.60 8.64
BRC Mesh 1 1.38 0.60 0.83
4 1.20 0.60 2.88
2 0.60 0.60 0.72
3 2.40 0.60 4.32
Cut & polish 2 1.38 0.60 1.65
8 1.20 0.60 5.76
4 0.60 0.60 1.44
6 2.40 0.60 8.64
Plywood door 2.40 1.20 2.88
Plywood door painting 2 2.40 1.20 5.76
Total cost
O/H % Profit 18%
15.10
Built in R.C.C. concrete bed 1950x1800 mm in bed
room 01 complete as per drawing . 1.95 1.80
Mass Concrete 1.95 1.80 0.23 0.79
1.80 0.80 0.15 0.22
Formwork 2 1.95 0.23 0.90
2 1.80 0.23 0.83
1 1.80 0.80 1.44
2 0.80 0.15 0.24
1 1.80 0.15 0.27
BRC Mesh 1.80 0.15 0.27
0.15 0.80 0.12
Total cost
O/H % Profit 18%
15.13
Built in R.C.C.concrete dressing table 2713x675 mm
with cement rendered in master bed room complete as
per drawing .
75mm thick RCC shelves 8 0.68 0.68 3.68
3 1.05 0.60 1.89
4 2.40 0.60 5.76
Formwork 16 0.68 0.68 7.37
6 1.05 0.60 3.78
8 2.40 0.60 11.52
BRC mesh 8 0.68 0.68 3.68
3 1.05 0.60 1.89
4 2.40 0.60 5.76
Cut & polish 16 0.68 0.68 7.37
6 1.05 0.60 3.78
8 2.40 0.60 11.52
Ply wood doors 2 1.60 0.68 2.18
Ply wood doors painting 4 1.60 0.68 4.36
Total cost
O/H % Profit 18%
15.14
Built in R.C.C.concrete cupboard and open shelfs
3000x2400mm high in master bed room complete as
per drawing .

75mm thick RCC shelves 10 0.60 0.60 3.60
4 2.40 0.60 5.76
2 1.44 0.60 1.73
Formwork 20 0.60 0.60 7.20
8 2.40 0.60 11.52
4 1.44 0.60 3.46
BRC Mesh 10 0.60 0.60 3.60
4 2.40 0.60 5.76
2 1.44 0.60 1.73
Cut & polish 20 0.60 0.60 7.20
8 2.40 0.60 11.52
4 1.44 0.60 3.46
Ply wood doors 2 2.40 0.68 3.27
Ply wood doors painting 4 2.40 0.68 6.55
Total cost
O/H % Profit 18%
15.15
Built in R.C.C.concrete cupboard 1695x600 mm with
cement rendered in master bed room complete as per
drawing .
75mm thick RCC shelves 5 1.70 0.60 5.09
3 2.40 0.60 4.32
Formwork 10 1.70 0.60 10.17
6 2.40 0.60 8.64
BRC Mesh 5 1.70 0.60 5.09
3 2.40 0.60 4.32
Cut & polish 10 1.70 0.60 10.17
6 2.40 0.60 8.64
Ply wood doors 2 2.40 0.81 3.89
Ply wood doors painting 4 2.40 0.81 7.78
Total cost
O/H % Profit 18%
15.22
Built in R.C.C.concrete table 3000x600mm in bed
room 02 complete as per drawing .
75mm thick RCC shelves 1 3.00 0.60 1.80
3 0.75 0.60 1.35
Formwork 2 3.00 0.60 3.60
6 0.75 0.60 2.70
BRC Mesh 1 3.00 0.60 1.80
3 0.75 0.60 1.35
Cut & polish 2 3.00 0.60 3.60
6 0.75 0.60 2.70
Ply wood doors 2 0.75 0.80 1.20
Ply wood doors painting 4 0.75 0.80 2.40
Total cost
O/H % Profit 18%
15.23
Built in R.C.C.concrete cupboard with 1163x2400mm
including timber doors & drawers in bed room 02
complete as per drawing .
75mm thick RCC shelves 5 1.16 0.60 3.49
2 2.40 0.60 2.88
Formwork 10 1.16 0.60 6.98
4 2.40 0.60 5.76
BRC Mesh 5 1.16 0.60 3.49
2 2.40 0.60 2.88
Cut & polish 10 1.16 0.60 6.98
4 2.40 0.60 5.76
Ply wood door and drawers 1 2.40 1.16 2.78
4 1.16 0.60 2.78
8 1.16 0.15 1.39
8 0.60 0.15 0.72
Ply wood doors painting 2 2.40 1.16 5.57
8 1.16 0.60 5.57
16 1.16 0.15 2.78
16 0.60 0.15 1.44
Total cost
O/H % Profit 18%
15.25
Built in R.C.C. concrete bed 1913x600 mm in staff
room complete as per drawing .
Brick base 2 1.91 0.28 1.05
75mm thick RCC concrete 1.91 0.90 1.72
Formwork 1 1.91 0.90 1.72
2 1.91 0.08 0.29
2 0.90 0.08 0.14
BRC Mesh 1.91 0.90 1.72
Cut & polish 1.91 0.90 1.72
Total cost
O/H % Profit 18%
15.26
Built in R.C.C. concrete work top & open shelves 75mm
thick 2712x600x900mm high , granite top and plywood
doors with high gloss finish PU paint of approved colour
complete as per drawing .
75mm thick RCC concrete 2 2.71 0.60 3.25
1 1.36 0.60 0.81
5 0.90 0.60 2.70
Formwork 4 2.71 0.60 6.51
2 1.36 0.60 1.63
10 0.90 0.60 5.40
BRC Mesh 2 2.71 0.60 3.25
1 1.36 0.60 0.81
5 0.90 0.60 2.70
Cut & polish 4 2.71 0.60 6.51
2 1.36 0.60 1.63
10 0.90 0.60 5.40
Ply wood doors 2 0.90 0.68 1.22
Ply wood doors painting 4 0.90 0.68 2.44
Granite Tile 1 2.71 0.60 1.63
Total cost
O/H % Profit 18%
Supply and fix cement grill 1m2
Material
1'-0" x1'-0" cement gril
Cement
Sand
Transpoort
Labour
Mason
Un/ Sk
Tools
O/H % Profit 18%
Total Qty Unit Rate
1.10 Cu.ft 200.00 220.00
3.76 Kg 112.00 421.56
1.02 Kg 112.00 113.82
12.50 sq.ft 50.00 625.00
280.00
1,660.38
298.87
1,959.25
195.92
642.63
10.00 m2 191.00 1,910.00
150.00
103.00
144.20
0.10 day 650.00 65.00
1.95
2,374.15
427.35
2,801.50
280.15
44.00 Nos 18.00 792.00
0.01 bag 785.00 7.85
0.02 Cube 7,000.00 140.00 939.85
93.99
0.10 Day 950.00 95.00
0.10 Day 650.00 65.00 160.00
4.80
1,198.64
215.75
1,414.39
141.44
463.92
1.00 10,760.00
1.80 19,368.00
1.00 10,760.00
0.90 9,684.00
1.50 2.40 3.60
18.90 L.ft 165.79 3,133.42
37.50 L.ft 77.63 2,911.18
4.00 Nos 510.00 2,040.00
1.00 Nos 1,500.00 1,500.00 9,584.61
2,000.00
60.00 2,060.00
11,644.61
2,096.03
13,740.63
3,816.84
0.90 2.40 2.16
8,244.38
1.24 1.80 2.23
8,498.58
4.00 2.88 11.50
43,893.69
4.20 2.88 12.08
46,088.38
0.60 0.75 0.45
1,717.58
1.50 1.50 2.25
8,587.90
5.04 m2 1,200.00 6,048.00
4.97 m2 1,100.00 5,464.80
9.94 m2 715.00 7,104.24
4.97 m2 450.00 2,235.60
25.60 m 180.00 4,608.00
5.00 Nos 4,725.00 23,625.00
20.02 m2 580.00 11,609.28
20.02 m2 340.00 6,805.44
19.32 m2 800.00 15,456.00
10.00 Nos 250.00 2,500.00
85,456.36
15,382.14
100,838.50
2.39 m2 1,200.00 2,862.00
6.72 m2 1,100.00 7,392.00
13.44 m2 715.00 9,609.60
6.72 m2 450.00 3,024.00
6.00 m 180.00 1,080.00
1.13 m2 2,500.00 2,812.50
14.01 m2 580.00 8,125.80
14.01 m2 340.00 4,763.40
1.13 m2 800.00 900.00
2.10 m2 1,350.00 2,835.00
4.00 Nos 250.00 1,000.00
44,404.30
7,992.77
52,397.07
26.28 m2 1,100.00 28,904.70
52.55 m2 715.00 37,576.11
26.28 m2 450.00 11,824.65
25.65 m2 2,500.00 64,125.00
52.55 m2 580.00 30,481.32
52.55 m2 340.00 17,868.36
51.30 m2 800.00 41,040.00
9.58 m2 8,000.00 76,620.00
4.00 Nos 250.00 1,000.00
309,440.14
55,699.23
365,139.37
1.82 m3 12,245.00 22,243.04
5.75 m2 715.00 4,111.25
5.26 m2 450.00 2,364.75
5.36 m2 1,350.00 7,236.00
3.36 m2
0.75 m2 8,000.00 6,000.00
41,955.04
7,551.91
49,506.95
24.73 m2 1,100.00 27,198.60
49.45 m2 715.00 35,358.18
24.73 m2 450.00 11,126.70
24.73 m2 1,350.00 33,380.10
3.12 m2 2,500.00 7,796.25
6.24 m2 800.00 4,989.60
119,849.43
21,572.90
141,422.33
0.98 m3 12,245.00 11,943.47
3.64 m2 715.00 2,602.96
0.39 m2 450.00 175.50
14,721.92
2,649.95
17,371.87
0.41 m2 1,100.00 445.50
0.60 m2 715.00 429.00
1.01 m2 450.00 452.25
0.60 m2 1,350.00 810.00
2,136.75
384.62
2,521.37
8.75 m2 1,100.00 9,621.48
17.49 m2 715.00 12,507.92
8.75 m2 450.00 3,936.06
17.49 m2 1,350.00 23,616.36
2.88 m2 2,500.00 7,200.00
5.76 m2 800.00 4,608.00
61,489.82
11,068.17
72,557.99
1.01 m3 12,245.00 12,315.41
3.68 m2 715.00 2,627.63
0.39 m2 450.00 175.50
15,118.53
2,721.34
17,839.87
11.33 m2 1,100.00 12,466.08
22.67 m2 715.00 16,205.90
11.33 m2 450.00 5,099.76
22.67 m2 1,350.00 30,598.56
2.18 m2 2,500.00 5,456.00
4.36 m2 800.00 3,491.84
73,318.14
13,197.27
86,515.41
11.09 m2 1,100.00 12,196.80
22.18 m2 715.00 15,855.84
11.09 m2 450.00 4,989.60
22.18 m2 1,350.00 29,937.60
3.27 m2 2,500.00 8,184.00
6.55 m2 800.00 5,237.76
76,401.60
13,752.29
90,153.89
9.41 m2 1,100.00 10,345.50
18.81 m2 715.00 13,449.15
9.41 m2 450.00 4,232.25
18.81 m2 1,350.00 25,393.50
3.89 m2 2,500.00 9,720.00
7.78 m2 800.00 6,220.80
69,361.20
12,485.02
81,846.22
3.15 m2 1,100.00 3,465.00
6.30 m2 715.00 4,504.50
3.15 m2 450.00 1,417.50
6.30 m2 1,350.00 8,505.00
1.20 m2 2,500.00 3,000.00
2.40 m2 800.00 1,920.00
22,812.00
4,106.16
26,918.16
6.37 m2 1,100.00 7,005.90
12.74 m2 715.00 9,107.67
6.37 m2 450.00 2,866.05
12.74 m2 1,350.00 17,196.30
7.68 m2 2,500.00 19,200.00
15.36 m2 800.00 12,288.00
67,663.92
12,179.51
79,843.43
1.05 m2 1,800.00 1,893.87
1.72 m2 1,100.00 1,890.90
2.14 m2 715.00 1,530.46
1.72 m2 450.00 773.55
1.72 m2 1,350.00 2,320.65
8,409.43
1,513.70
9,923.12
6.77 m2 1,100.00 7,444.80
13.54 m2 715.00 9,678.24
6.77 m2 450.00 3,045.60
13.54 m2 1,350.00 18,273.60
1.22 m2 2,500.00 3,051.00
2.44 m2 800.00 1,952.64
1.63 m2 8,000.00 13,017.60
56,463.48
10,163.43
66,626.91
11.00 Nos 75.00 825.00
0.50 Bag 785.00 392.50
0.05 Cube 7,000.00 350.00
78.38
1.00 Day 950.00 950.00
0.50 Day 650.00 325.00 1,275.00
38.25
1,391.63
250.49
1,642.12

Das könnte Ihnen auch gefallen