Scheduling/Leveling Report - 18-Sep-14 - PM.

exe
===============================================
Default Project..................................................MIRAGE
Projects:
MIRAGE..........................................................
.ROYAL MIRAGE III - PALM JUMEIRAH
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retaine
d Logic
Calculate start-to-start lag from ...............................Early S
tart
Define critical activities as Total Float less than or equal to .50
Compute Total Float As ..........................................Finish
Float
Calculate float based on finish date of .........................Each pr
oject
Calendar for scheduling Relationship Lag ........................Predece
ssor Activity Calendar
Advanced
--------
Calculate multiple float paths...................................No
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................117
# Not Started....................................................117
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................172
# Activities with Constraint.....................................0
Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: MIRAGE Activity: A1000 Letter of Award
/ Notice to Commence
Activities without successors....................................15
Project: MIRAGE Activity: A1370 Trusses on Roof
incl Roof Tiles
Project: MIRAGE Activity: A1380 Commencement of
Work - MANOR HOUSE
Project: MIRAGE Activity: A1382 Commencement of
Work - PHASE 1 BUILDINGS
Project: MIRAGE Activity: A1384 Commencement of
Work - PHASE 2 BUILDINGS
Project: MIRAGE Activity: A1390 Completion of St
ructural works - MANOR HOUSE
Project: MIRAGE Activity: A1400 Completion of Fi
nishes - MANOR HOUSE
Project: MIRAGE Activity: A1410 Final Completion
/ Handing over - MANOR HOUSE
Project: MIRAGE Activity: A1760 Trusses on Roof
incl Roof Tiles
Project: MIRAGE Activity: A2100 Trusses on Roof
incl Roof Tiles
Project: MIRAGE Activity: A2110 Completion of St
ructural works - PHASE 1 BUILDINGS
Project: MIRAGE Activity: A2120 Completion of Fi
nishes - PHASE 1 BUILDINGS
Project: MIRAGE Activity: A2130 Final Completion
/ Handing over - PHASE 1 BUILDINGS
Project: MIRAGE Activity: A2140 Completion of St
ructural works - PHASE 2 BUILDINGS
Project: MIRAGE Activity: A2150 Completion of Fi
nishes - PHASE 2 BUILDINGS
Project: MIRAGE Activity: A2160 Final Completion
/ Handing over - PHASE 2 BUILDINGS
Out-of-sequence activities.......................................0
Activities with Actual Dates > Data Date.........................0
Milestone Activities with invalid relationships..................16
Project: MIRAGE Activity: A1010 Receipt of Build
ing Permit / NOC to construct.
Project: MIRAGE Activity: A1030 Handing over fro
m Piling / Excavation subcontractor
Project: MIRAGE Activity: A1060 Receipt of FINAL
structural drawings (ALL LEVELS) - "For Construction"
Project: MIRAGE Activity: A1070 Receipt of FINAL
MEP details for structure (ALL LEVELS)
Project: MIRAGE Activity: A1280 Completion of In
ternal Finishes
Project: MIRAGE Activity: A1320 Final Completion
of works
Project: MIRAGE Activity: A1430 Handing over fro
m Piling / Excavation subcontractor
Project: MIRAGE Activity: A1450 Receipt of FINAL
structural drawings (ALL LEVELS) - "For Construction"
Project: MIRAGE Activity: A1460 Receipt of FINAL
MEP details for structure (ALL LEVELS)
Project: MIRAGE Activity: A1670 Completion of In
ternal Finishes
Project: MIRAGE Activity: A1710 Final Completion
of works
Project: MIRAGE Activity: A1790 Handing over fro
m Piling / Excavation subcontractor
Project: MIRAGE Activity: A1810 Receipt of FINAL
structural drawings (ALL LEVELS) - "For Construction"
Project: MIRAGE Activity: A1820 Receipt of FINAL
MEP details for structure (ALL LEVELS)
Project: MIRAGE Activity: A2010 Completion of In
ternal Finishes
Project: MIRAGE Activity: A2050 Final Completion
of works
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................117
# Relationships with other projects..............................0
Data Date........................................................01-Dec-
08
Earliest Early Start Date........................................01-Dec-
08
Latest Early Finish Date.........................................31-May-
10
Exceptions:
-----------
Critical Activities..............................................54
Project: MIRAGE Activity: A1000 Letter of Award
/ Notice to Commence
Project: MIRAGE Activity: A1020 Excavation for F
ootings / Pile Caps
Project: MIRAGE Activity: A1030 Handing over fro
m Piling / Excavation subcontractor
Project: MIRAGE Activity: A1040 Mobilisation at
site
Project: MIRAGE Activity: A1050 Joint Surveys &
Setting out
Project: MIRAGE Activity: A1060 Receipt of FINAL
structural drawings (ALL LEVELS) - "For Construction"
Project: MIRAGE Activity: A1070 Receipt of FINAL
MEP details for structure (ALL LEVELS)
Project: MIRAGE Activity: A1080 Internal Enginee
ring for Shop Drawings - GA + BBS
Project: MIRAGE Activity: A1090 Verticals for Le
vel +5.50 --- + 9.00
Project: MIRAGE Activity: A1100 Slabs at Level +
9.00
Project: MIRAGE Activity: A1110 Verticals for Le
vel + 9.00 --- + 12.50
Project: MIRAGE Activity: A1120 Slabs at Level +
12.50
Project: MIRAGE Activity: A1130 Verticals for Le
vel +12.50 --- +16.00
Project: MIRAGE Activity: A1140 Slabs at Level -
Lower Roof
Project: MIRAGE Activity: A1150 Blockworks
Project: MIRAGE Activity: A1160 Internal Plaster
Project: MIRAGE Activity: A1170 External Plaster
Project: MIRAGE Activity: A1190 GRC cornices / C
ladding works
Project: MIRAGE Activity: A1210 MEP 2nd Fixes
Project: MIRAGE Activity: A1220 MEP Final Fixes
Project: MIRAGE Activity: A1250 External Texture
painting
Project: MIRAGE Activity: A1260 Suspended ceilin
gs
Project: MIRAGE Activity: A1270 Internal Final c
oat painting
Project: MIRAGE Activity: A1280 Completion of In
ternal Finishes
Project: MIRAGE Activity: A1300 Installation of
Furniture, Fittings, Furnishings, etc
Project: MIRAGE Activity: A1310 Civil Defense in
spection & approval
Project: MIRAGE Activity: A1320 Final Completion
of works
Project: MIRAGE Activity: A1330 MEP Testing & Co
mmissioning
Project: MIRAGE Activity: A1410 Final Completion
/ Handing over - MANOR HOUSE
Project: MIRAGE Activity: A1420 Excavation for F
ootings / Pile Caps
Project: MIRAGE Activity: A1480 Verticals for Le
vel GF - 1F
Project: MIRAGE Activity: A1490 Slabs at First F
loor
Project: MIRAGE Activity: A1520 Verticals for 1F
- Roof
Project: MIRAGE Activity: A1530 Slabs at Roof Le
vel
Project: MIRAGE Activity: A1780 Excavation for F
ootings / Pile Caps
Project: MIRAGE Activity: A1840 Verticals for Le
vel GF - 1F
Project: MIRAGE Activity: A1850 Slabs at First F
loor
Project: MIRAGE Activity: A1860 Verticals for 1F
- Roof
Project: MIRAGE Activity: A1870 Slabs at Roof Le
vel
Project: MIRAGE Activity: A1880 Blockworks
Project: MIRAGE Activity: A1890 Internal Plaster
Project: MIRAGE Activity: A1900 External Plaster
Project: MIRAGE Activity: A1920 GRC cornices / C
ladding works
Project: MIRAGE Activity: A1940 MEP 2nd Fixes
Project: MIRAGE Activity: A1950 MEP Final Fixes
Project: MIRAGE Activity: A1980 External Texture
painting
Project: MIRAGE Activity: A1990 Suspended ceilin
gs
Project: MIRAGE Activity: A2010 Completion of In
ternal Finishes
Project: MIRAGE Activity: A2020 Snagging works
Project: MIRAGE Activity: A2030 Installation of
Furniture, Fittings, Furnishings, etc
Project: MIRAGE Activity: A2040 Civil Defense in
spection & approval
Project: MIRAGE Activity: A2050 Final Completion
of works
Project: MIRAGE Activity: A2060 MEP Testing & Co
mmissioning
Project: MIRAGE Activity: A2160 Final Completion
/ Handing over - PHASE 2 BUILDINGS
Activities with unsatisfied constraints..........................0
Activities with unsatisfied relationships........................0
Activities with external dates...................................0