METHOD STATEMENT FOR INSTALLATION OF CHILLED WATER PUMPS

1.0 SCOPE OF WORK


The Method Statement is applicable to installation of CHW pumps at First Floor.
2.0 RESPONSIBILITY
Before commencement of any installation activity, the followin procedures are re!uired to be carried out.
".# $ll materials used must have an approved material submittal.
"." Chec% that pumps are in compliance with approved submittal
".& Chec% for any physical damaes upon receipt of the same at site.
".' Chec% Floatin Floors ( plinths for dimensions ) locations with respect to approved shop drawins.
".* Chec% +nertia Bases and $nti ,ibration mounts are in place as per approved submittal
".- .etain the shippin crates and protection covers until the unit is at its final location.
3.0 DESCRIPTION OF WORK
Installat!n P"!#$%&"$
3.1 T'$ (an #!nt"a#t!"s S#!)$ !* +!",.
&.#.# CHW /umps should be lifted and /ositioned to the Second Floor.
&.#." /umps shall be off0loaded with tower)mobile crane and movin to the re!uired location.
&.#.& Floatin Floor should be constructed and should be ready for the M1/ wor% installation as per approved
2r.
3.2 BBAE s#!)$s !* +!",s.
# /rovide supervision and labor to assist in the riin operation.
" Maneuver the e!uipment from loadin points into the plant rooms in a reasonably timely manner.
& $ssist in lowerin the e!uipments onto +nertia Bases with Sprins +solators.
' +nstallation to be as per approved shop drawin.
* Before installation of pump ensures the foundation 3base4, bloc% wall and plaster is completed and allows
sufficient space to move the unit inside the plant room.
- Select the correct si5e ) model pumps and install the unit in the location as confiured in the shop drawin.
6 Connect suction and dischare pipin with fle7ible connectors as per shop drawin ) e!uipment
connection details and ensures that no weiht is put onto pump connections.
8 Complete electrical connection to the unit recommended by the manufacturer.
9 1nsure that oil reservoir is filled to the correct level and with lubricant as per pump supplier:s installation
instructions.
#; $fter completin pipe installation chec% for free movement of motor and impeller by turnin them by
hand.
## Contact supplier:s technician to chec% pump alinment prior to commissionin.
-.0 LABOUR. PLANT / MATERIAL RE0UIREMENTS
'.# The material shall be of approved Manufacturer as per the material submittal.
'." S%illed technicians, in sufficient numbers, shall carry out the installation.
'.& The wor%manship shall be maintained at all times.
1.0 SUPER2ISION ARRAN3EMENTS
*.# $ constant supervision by the foreman and supervisor shall be carried out in order to control the wor% and
the wor%manship.
*." 17perienced supervisors shall be appointed to carry out the wor% smoothly and to have the full control of
the labour.
4.0 R$*$"$n#$ D!#&($nts
-.# 2rawins
-." Specification< #**';
5.0 E6&)($nt R$6&"$%
6.# $ll necessary riin e!uipment i.e. slins, chains, deshac%les, spreader bars etc.
6." Chain bloc%s, e7tra chains)slins, rollers etc for maneuverin within plant rooms.
7.0 EN2IRONMENTAL RE0UIREMENTS
8.# $ Safety officer shall ensure that the labor has a ood wor%in environment, a ha5ard free environment.
8.0 TEMPORARY WORKS TO BE DESI3NATED AND INSTALLED
=)$
10.0 HEALTH / SAFETY RE0UIREMENTS
#;.# 1nsure wor% area is clean and tidy.
#;." 1nsure the wor% $rea is well ventilated.
#;.& $ll employees shall adopt safe wor%in practices.
#;.' Safety e!uipment 3e7ample Hard Hats, Safety Shoes, Coveralls, >loves, >oles when necessary etc.4 to
be worn at all times.