Vertical Drainage Consolidation Analysis with MCC Model
Soft Ground Soft Ground
Soft Ground Tutorial
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
00
Vertical Drainage Consolidation Analysis with MCC Model
Overview
Banked consolidation analysis
applying drain material of both
sides drainage condition will be
performed using Modified Cam
Clay(MCC)Model.
Model the vertical drainage using
Embankment
g g
draining boundary condition
Simulate the Initial, Embankment
and Leave stages.
Clay 1
Clay 2
The ground settlements and
excess pore pressure due to
embankment will be checked.
Clay 3
Weathered Rock
Vertical Drainage
Vertical Drainage Consolidation Analysis with MCC Model 1
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
01
Material Property
ID 1 2~4 5
Ground Material Properties
Name Embankment Clay 1~3 Weathered Rock
Constitutive Model MC MCC MC
Modulus of Elasticity
[tonf/m
2
]
3,000 300 15,000
P i R ti ( ) 0 30 0 38 0 30 Poissons Ratio () 0.30 0.38 0.30
Unit Weight (Y) [tonf/m
3
] 1.80 1.96 2.10
Saturated Unit Weight
(Ysat) [tonf/m
3
]
1.85 2.00 2.10
Cohesion (c) [tonf/m
2
] 1.5 - 3.0 ( ) [ ]
Internal Friction Angle () 25 - 35
P bilit (k) [ /d ] 1 0 0001 1
Vertical Drainage Consolidation Analysis with MCC Model 2
Permeability (k) [m/day] 1 0.0001 1
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
01
Material Property
Ground Material Properties (MCC Properties)
ID 2 3 4
Name Clay 1 Clay 2 Clay 3
Over Consolidation Ratio (OCR) 1 1 1
Slope of Normal Consolidation Line () 0.217 0.217 0.217
Slope of Over Consolidation Line () 0.043 0.043 0.043
Critical State Specific Volume () 3.579 3.817 4.928
Slope of Critical State Line (M) 0.772 0.772 0.772
Although MCC Model properties determined by triaxial compression test, which also can be estimated through
using general properties calculated by the formulations shown below in roundabout way.
C C
|
'
i 6
303 . 2
c
C
=
303 . 2
s
C
= k
z
p
sub c
=
'
e + = 1
0
v
|
|
|
|
'
'
=
0
ln
p
c
c
k v v
c c
p N
'
+ = ln v
2 ln ) ( k = I N
|
|
'
'
= M
sin 3
sin 6
Vertical Drainage Consolidation Analysis with MCC Model
2
p
sub c
0 |
.
\
'
0
0
p
c
c c
p
2 ln ) ( k I N
3
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
02
Import > CAD file(*.dwg/*.dxf)
Procedure
Select the SoilWorks excution
icon from the Desktop.
2
1
Project Manager > click Soft
Ground
Initial Parameters > click User
Defined
2
1
4
Defined
Select [ton], [m] and [day]
Main Icon > Import > select CAD
file
3
3
4
file.
Select the Vertical Drainage
Consolidation Analysis with MCC
Model.dwg, and click [Open]
5
Unit of Force and Length are
converted automatically, but unit of
Time is not converted
automatically Therefore specify
5
automatically. Therefore, specify
the unit of Time when performing
the consolidation analysis.
User can copy and paste the
Vertical Drainage Consolidation Analysis with MCC Model 4
objects in CAD program directly
into SoilWorks.
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
03
Model > Ground Material Property
Procedure
From Main Menu, select Model >
Ground Material Property
(command : gm)
1
2
11
(command : gm)
Refer to Step 01. to enter the
ground material properties and
click Add.
22
Click [Close]
33
SoilWorks permits ground material
properties used in projects to be
compiled in a database. The
3
p
database is created by editing the
*.gdb file in SoilWorks/Dbase in the
Install folder.
Vertical Drainage Consolidation Analysis with MCC Model
5
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
04
Geometry > Smart Surface
Procedure
For generating the surfaces to
assign the material properties
2
4
3
1
From the Main Menu, select
Geometric Shape > Auto-
generate Surfaces (command: ss)
For checking the assignment status
1
For checking the assignment status
From the Main Menu, select
Window > Display Settings ( )
Select General > Screen Object
2
3
5
Select General > Screen Object
Select Change Background
Color > Attribute Color
Click [OK]
3
4
5
Click [OK]
Property not entered currently will
be set basically as gray and
changed as property color defined
when property data entered, which
is useful to check property defined
Vertical Drainage Consolidation Analysis with MCC Model
is useful to check property defined
for composite model.
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
05
Assign Material Property
Procedure
Assign the ground material property.
Refer to Page 1 to select the
1
surface of Embankment, and
select Embankment under
Ground Material Property from
th W k T d D & the Works Tree and Drag &
Drop.
1
8
1 1 2 3 4
Vertical Drainage Consolidation Analysis with MCC Model
to Works Tree > Mesh > bottom of
mesh set with assigned name.
8
(O) (X) (O)
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
07
Define Boundary Conditions
Procedure
Define the ground supports.
From the Main Menu, select
1
1
4
Loads | Boundaries > Smart
Support (command : as)
Enter the name of Boundary Set
2
Click [OK]
Define the boundary condition for
the drainage
2
3
3
From the Main Menu, select
Loads | Boundaries >
Draining Condition
4
Enter the name of Boundary Set
Select the Curve from Type
Select the line(vertical drain
5
6
7
5
material, both sides drain) relevant
to drain condition
Click [OK]
8
8
5
6
7
Vertical Drainage Consolidation Analysis with MCC Model 9
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
07
Define Boundary Conditions
Procedure
Define the Non-consolidation
Boundary Condition
1
6
From the Main Menu, select
Loads | Boudnaries >Non-
Consolidation Boundary
Element
1
2
3
4
3
Element
Enter the name of Boundary Set
Select the Mesh from the Type
2
3
5
Select the mesh relevant to
embankment material.
Click [OK]
4
5
Define the water level
From the Main Menu, select
Loads | Boundaries >Water
6
Level
Select line placed by the water
level.
7
7
8
Vertical Drainage Consolidation Analysis with MCC Model
Click [OK]
10
8
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
08
Define Construction Stages
Procedure
Define the construction stages
From the Main Menu, select
1
1
Analysis | Design > Construction
Stage
Click the Add Construction Stage
2
2
3
4
Enter 3
Click [OK]
Select the Construction Stage 1
3
4
5
Enter Initial
Click the [Time Steps]
Create the time and number of
6
5
7
8
8
steps (Period: 1, No. of Steps: 1)
Click [OK]
Check on Water Level, and select
9
10
10
7
6
the Water Level function
Check on Initialize Displacement
Click [Modify]
11
10
11
12
9
12
Vertical Drainage Consolidation Analysis with MCC Model
.
11
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
08
Define Construction Stages
Procedure
Define the time steps for each stage
Select the Construction Stage 2, and
1
1
2
3
4
5
enter Embankment
Click the [Time Steps]
Enter Period > 45, No. of Steps > 10
2
3
5
Check on Save Result
Click [Create Steps]
Click [OK]
4
5
6 6
7
Click [Modify] 7
The number of step is an item
defining the force increment size
Although defining more number of
g g
step to generate the unequribrium
force can get excellent astringency,
the analysis time will be longer at the
same time Using the same way
Vertical Drainage Consolidation Analysis with MCC Model
same time . Using the same way,
input 300 to period, 20 to number of
step in stage of Leave.
12
MIDAS IT Co., Ltd. MIDAS IT Co., Ltd.
Step
08
Define Construction Stages
Procedure
Define the mesh set, boundary and
load set for each stage
1
From the Main Menu, select
Analysis|Design > Stage
Models
2 4
1
Select the Initial stage
Drag&Drop the Clay Layer,
Ground Support, Drainage
Conditions relevant to primary
2
3
Conditions relevant to primary
stage as data for adding to current
stage.
Click [Apply]
4
3
Apply the mesh and boundary set Apply the mesh and boundary set
of construction stage in same way.
Checking the Simulate Each
Stage, the element added/removed
b h k d il