This Presentation Will Cover:
Main drivers for testing PBRCs in Sri Lanka
Capacity building of domestic contractors.
Main benefits obtained after the first pilot(s).
Role of the ADB and recommendations in the
future.
Dos / donts and lessons learnt

2
Main Drivers for Testing PBRCs in
Sri Lanka





3
Significant and on-going investment into the Sri
Lanka road transportation sector is occurring, but..
Supporting administration systems and resource
needs are lagging behind
There is the need for more efficient and effective
road management processes that can:
Improve the asset knowledge
Better demonstrate value for money outcomes
Increase focus on customers (communities / road users) needs
and satisfaction
Transfer responsibility and some risks to the contractor, to
stimulate innovation and cost-effective delivery of output.
Main Drivers for Testing PBRCs in
Sri Lanka





4


Incentives are required to address historical problems:
Less than optimum pavement asset lifecycles
Traditional design/construction approaches often fail to
adequately consider long term maintenance issues
Variability in service and investment levels within/between
road classifications.
Budget overruns through measure and value contract
variations
Variable annual funding not aligned with maintenance needs


Capacity Building of Domestic
Contractors.
Industry surveys and discussions on PBRCs in Sri
Lanka have identified:
There is adequate capacity and interest in the market
place for private industry to undertake PBRCs.
However.
There is limited understanding of performance based
concepts
Concern over the potential transfer of risks associated
with these long term contacts e.g. emergency works or
overloading of pavements.

5
Capacity Building of Domestic
Contractors.




6


Several Pilot PBRCs have been undertaken to
increase awareness and build capacity e.g.
Northern Road Connectivity Project.



7


Northern Road Connectivity Project:



8


Northern Road Connectivity Project:

NRCP Phase 1

NRCP Phase 2

No of Km 175 128
Loan Amount
(US$m)
130 98
PBM 3yrs 5yrs
Condition of
Contract
MDB 2006 MDB 2010
Capacity Building of Domestic
Contractors.




9


Introductory discussions held with local
contracting industry to introduce the concepts
Workshop on PBRCs organized for RDA
personnel in March 2014 (ADB Support)
Further contractor workshops planned prior to
next round of PBRC contract bids.

Main Benefits Obtained After the
First Pilot(s).







10
Northern Road Connectivity Project identified several
benefits:
Term of contracts has increased as confidence has grown
(from 3 years to 5 years now being implemented)
Improved understanding of pricing by contracting industry
under PBRCs (especially maintenance inputs)
Better understanding of contract management
requirements (both contract relationship and service level
compliance).



Role of ADB and Recommendations
in the Future

11
ADB support during implementation.
Support and advice to the RDA for future contract
development.
Development and implementation of latest generation
of PBRCs is underway.
Three Performance based contracts spanning several provinces
totalling 230 km of National Roads under preparation
A further 160 km in further packages likely to follow.
12
Dos / Donts



Dos
Do raise awareness and align contract requirements
with industry capability to manage
Do encourage and support employer asset, data
management processes, and system development
Do engage and retain experienced management
personnel (Employer and Contractor)
Do incorporate experience and learning over time
(contract evolution).
13
Dos / Donts



Donts
Do not transfer too much risk to the contractor
Do not implement on networks likely to undergo
significant change during the contract, where the
change cannot be easily quantified or priced in the
lump sum
Do not interfere unnecessarily with the contractors
activities, (but do carefully monitor and manage).


Thank You