0 Bewertungen0% fanden dieses Dokument nützlich (0 Abstimmungen)
395 Ansichten4 Seiten
The document provides a method statement for screed concrete work on an aerator, floccurator, and treated water tank. It outlines that 36 cubic meters of grade 20 concrete will be poured between 3-7 PM from a batch plant 14 km away. Excavation to foundation level will occur followed by soil compaction and concrete formwork installation. Concrete will be poured in 2 meter wide strips using a shooter and finished smooth and level with curing over 7 days. Safety equipment and an 8 person workforce with engineers and supervisors will oversee the work.
Originalbeschreibung:
Originaltitel
method statement for screed concreting aerator TWT.docx
The document provides a method statement for screed concrete work on an aerator, floccurator, and treated water tank. It outlines that 36 cubic meters of grade 20 concrete will be poured between 3-7 PM from a batch plant 14 km away. Excavation to foundation level will occur followed by soil compaction and concrete formwork installation. Concrete will be poured in 2 meter wide strips using a shooter and finished smooth and level with curing over 7 days. Safety equipment and an 8 person workforce with engineers and supervisors will oversee the work.
The document provides a method statement for screed concrete work on an aerator, floccurator, and treated water tank. It outlines that 36 cubic meters of grade 20 concrete will be poured between 3-7 PM from a batch plant 14 km away. Excavation to foundation level will occur followed by soil compaction and concrete formwork installation. Concrete will be poured in 2 meter wide strips using a shooter and finished smooth and level with curing over 7 days. Safety equipment and an 8 person workforce with engineers and supervisors will oversee the work.
METHOD STATEMENT FOR SCREED CONCRETE WORK OF AERATOR ,
FLOCCURATOR &TREATED WATER TANK
1. General We planned to place Grade 20 concrete for the screed concrete of the Areator, flocculator and treated water tank structures Quantity of concrete 36 cum Concrete work will be commenced at 15.00hr and it is scheduled to finish at19.00hrsame day. Concrete will be obtained from Bathalayaya Ready mix plant. Distance from the Batching plant to the site is 14km
2.Method of construction Setting out for the AFS structure Dumping of top soil in a suitable place Excavation up to foundation level by considering hydraulic profile of Treatment Plant. Storing of excavated soil suitable for compaction, separately Dumping of soil unsuitable for back filling outside the TP area Compaction of the areas where the soil is loose due to the removal of roots etc. using a compactor to obtain 98% compaction , Compaction of foundation area by using 2 Ton vibration roller or 1Ton vibration rollerto achieve 98% compaction
3.Levels Top levels of Screed concrete is established on the perimeter of structure by 02M intervals
4.Formwork Along the perimeter of base 75mm Height plywood strips are fixed to keep concrete edges straight.
5.Placing of concrete A shooter is used to avoid segregation of concrete and it is carried from place to place to get concrete easily.
6.Methord of concreting Before starting of concrete placing ,a high gauge polythene is laid on prepared base floor and fixed 2 M wide concrete strips are lead and compacted by using a timber tamper and two skilled labors care will be taken to keep top surface of concrete smooth and leveled .this procedure is repeated to finish the concrete .the joint of the concrete shall be refreshing within 45 min. care will be taken to cure the new concrete continuously.
11. Safety All the concrete workers using Helmets ,Gumboots, Hand gloves, A vehicle stand by at the site Fist aid available at the site Site is fully covered with adequate safety arrangement up to the finish of work. Safety officer will be deployed for fulltime of construction work.
12.Curing of concrete After the concrete we cover with gunny bags and watering of 7 days
Prepared by;
AUGMENTATION OF MAHIYANGANAYA WATER SUPPLY PROJECT
CONSTRUCTION OF WATER TREATMENT PLANT EXCAVATION WORK OF AERATOR, FLOCCRATOR & SEDIMENTATION TANK