Sie sind auf Seite 1von 3

1

Operation instructions for 180 overturning machine


. Structure principle
The 180 overturning machine including two sets every group is mainly used to
overturning H-section steel finish welding one face, it through 2 hydraulic cylinder
drive 2 L type rack turning synchronization, overturning the H-section steel after
assembling and then conveying to rollers, rollers transfer them to next process or
other working. On the rack installed speed reducer and moving wheel to make the
rack have moving function.
This overturning machine is composed of main body, hydraulic system and electrical
control system. Main body is composed of double 90 rocking arm, base frame,
moving wheel group, moving motor speed reducer and track (see drawing A).






. Main technical parameter
Suitable weight of workpiece: 15T
Moving speed reducer power: 1.5KW
Moving speed: 6m/min
Diameter of overturning oil cylinder: 140mm
Max pressure of hydraulic system: 20Mpa









2
. Working principle and operating procedure
1. check the input voltage should be 3 P 380V (allowed fluctuate range 105).
2. Push power on button, the indicate lamp light. Push: oil pump start button, the
indicate lamp of oil pump working light, Adjust the oil pump working pressure to
6-10Mpa.
3. Through heavy-load conveying roller, transfer H-section steel above 180
overturning machine.
4. Push working/adjust button, then push move left or move right button,
adjust one of hydraulic overturning rack; push working/adjust button again,

3
button loose, begin working, at this time, the two hydraulic overturning racks
working synchronously. Push move left or move right button, adjust to
needed position.
5. Switch the rotating direction to forward position, push NO1 arm 90, then
push total 90 button, when turning arm to 45 , after transfer the section steel to
suitable position, push total 90 button, to make section steel overturning 90,
then push NO2 arm 90 to reset.
6. Switch the rotating direction to reverse position, push NO2 arm 90, then
push total 90 button, when turning arm to 45 , after transfer the section steel to
suitable position, push total 90 button, to make section steel overturning 90,
then push NO1 arm 90 to reset.

. Maintenance and fault remove
1. The moving part should turn flexible, no block, chain wheel should have
lubrication oil; piston rod should clean frequently to keep lubrication.
2. Check hydraulic oil pipe, oil cylinder and hydraulic system in a certain period, if
find anything abnormal, should inspect oil pipe.
3. Check the track of overturning rack, clean sundries block moving.
4. After finish working, the piston rod should back to oil cylinder to avoid pollution
of dust and scalethe overturning rack should stop at the outside of conveying
roller.