Sie sind auf Seite 1von 7

The Resume of:

Carl Nelson France


Pipeline Inspector -
http://carlnelsonfrance.com
Project Management Highlights
!
Employer: Willbros Construction US LLC
!
Date: 2012-2013
!
Location: Colorado/Houston Texas
!
Project Description: Estimator/Project Manager, Duties included Estimate large Mainline and mid
size Pipeline Projects throughout the United States. Went to pre bid meetings and bid walks,
completed Material Take Offs, evaluated RFQs from sub contractors, completed project review
packages for approval, detailed Risk Analysis, Daily Production Estimates, sub contractor pricing and
award justication, equipment and Man Hour review including Crew Loading, Peak, Duration, Man
Hours per Foot, Cash Flow, Schedule, Key Personnel, Risk Contingency and nal Prot Margins.
Completed nal negotiations and oversaw Project Execution Plans.
Project Management Highlights
!
Employer: DT Limited
!
Date: 2009-2011
!
Location: Hong Kong
!
Project Description: Estimating Consultant, Duties include completing Budgetary
Estimates,FeasibilityStudies and Risk Analysis for potential mainline routs throughout Asia and
Europe. Travel extensively throughout Europe and Asia.
Project Management Highlights
!
Company: IXP, Inc.
!
Date: 2004-2008
!
Location: Pinedale Wyoming, Grand Junction Colorado
!
Project Description: President, Duties included Estimating, organizing and overseeing all aspects of
pipeline
Project Management Highlights
!
Company: Duke Energy/ Jonah Gas Gathering
!
Date: 2003-2004
!
Location: Pinedale, Wyoming
!
Project Description: Pipeline Project Manager, for the Jonah and Mesa gathering systems near
Pinedale, Wyoming. Duties included Cost Estimating and tracking of projects, coordination with
producers and drilling schedules, arranging ROW and permits, purchase of pipe and tting, hiring,
managing and processing invoices for inspection and x-ray.pipeline contractors.
Project Management Highlights
!
Company: Duke Energy / Cleveland Inspection
!
Date: 2002-2003
!
Location: Pinedale and Opal Wyoming, Farmington New Mexico
!
Project Description: CWI Chief Welding Inspector, for 85 miles of 24" and 20" mainline and 35 miles
of 16" and 12" mainline. Duties included qualify welding procedures, welder testing and certication,
welding inspection of mainline and fabrication, order, coordinate and sign invoices for x-ray.
Project Management Highlights

!
Company: UWI Pipeline
!
Date: 1997-2001
!
Location: Pinedale, Wyoming
!
Project Description: Project Superintendent, over pipeline and lateral construction for the Jonah and
Mesa Gathering systems. Duties included estimating, overseeing and coordination of construction
crews installing pipelines and laterals. Coordination of schedules, material, manpower and
equipment with Alberta Energy representative.

Das könnte Ihnen auch gefallen