Sie sind auf Seite 1von 3

Key Doc No OPSD-CDM-G-006 Prepared CDM

Cells Coloured Yellow Rev C Checked AST


Date 11/7/2005 Approved MJO
Cells Coloured Blue
Cells Coloured Red
Project
Rigging Summary
Specification
Drawing Title
Is load more than 70%of crane
SWL? 1
Nominated competent lift supervisor?
(*1 min)
Approved Procedure and / or
MOC complete? Project Engineer
Client Length (m) Drawing No
Is there a seabed connection,
before, during or after the lift. 2
Nominated competent lift team? (*2
min) Primary
Risk Assessment actions
Closed Out? Lift Supervisor
Vessel / Site Width (m) Rev
Is there seabed penetration
loading? 3
JHA completed for a personnel
transfer? Secondary
Lift Plan Safety Masures
Considered and Mitigation
Actions in Place?
Offshore
Construction
Manager
Location Height (m)
Lift Planning
Summary Drawing
Title
Is a crane technician required
offshore for the Lift? 4
JHA completed for a dangerous goods /
chemical lift? Tertiary
Suitable weather criteria &
window available?
Lift Plan Unique No 0 Static weight in air Drawing No What is the lift analysis report no 5
Dedicated certified lift points for lift
rigging?
Lifting Protocol
Agreed
Warranty surveyor certificate
issued? (as required)
Brief Description of
Lift
Static weight in
water Rev
Has a trial lift been completed
successfully? (Detail results) 6
Lifting accessories and equipment fit
for purpose?
Personnel and
Crane Escape
Routes Verified
Pre-lift meeting complete
with all relevant parties?
Date Created
Max calculated
Dynamic hook load,
including rigging
(Te)
Lifting
arrangement
description
Is pre ballasting of the vessel
required? 7
Lifting accessories and equipment
certificates checked?
Lift Plan complete and
signed off?
Date of Lift Position of C.O.G
Static rigging
weight (Te) Is the heeling system required? 8
Has the lift equipment had a pre-use
check?
Routine/Non Routine
Lift
Can the load free
flood?
Certification
available &
checked Is there topside clearance? 9 Weight verified?
Procedure Title
Other Relevant
Information
Is this a spreader
bar lift Seafastening disconnected? 10
Normal size & shape / free from sharp
edges?
Procedure No
What is the
minimum
clearance to the
spreader bar Are there any exclusion zones? 11 Is the lift point directly above load?
Procedure Rev
Can the spreader
bar be connected/
disconnected
safely Any risk to subsea architecture? 12 Is the load secure of loose objects?
Risk Assessment
(Onshore) Title Path of load considered? 13
Does crane driver have continuous
visibility of lift?
RA No Landing of load considered? 14
Lift clear of any plant / equipment /
assets / people?
RA Rev
Disconnection of load
considered? 15
Pick up & lay down within operation
radius of crane?
Job Risk
Assessment
(Offshore) (As
Required) Title
Can the Lift Rigging be recovered
safely? 16
Assets, deck equipment protected from
load?
JRA No
Any other Lifting Preparations
Required? (Specify) 17
Loads clearly visible during night /
subsea working?
JRA Rev 18
Load landing area clear, deck strong
enough and properly prepared?
19 Are tag lines required?
20
Vessel stability - pre ballasting
completed?
21
Correct PPE worn? (Banksman clearly
identifiable)
22
Sufficient head room / lift height
clearance
23
Lifting equipment movement controlled
i.e spreader bar
24 Route & laydown area clear
25
Is the lift free from parallel conflicting
operations?
26
Is there only one crane in operation,
which is not in conflict with other
cranes?
27
Does the mode of utilisation permit the
full SWL of the crane?
28
Is the Lifting Operation Free of
Exclusion Zones or Subsea
Architecture?
29 Is hook isolation a non-requirement?
30
Will the lift be continually supervised by
the crane driver whilst the load is
connected to the crane?
31 Any other concerns? - specify
Name 1. Administration 2. Crane /Lifting Appliance Details
Crane #2 designation
Crane #1
0 0
6. Lifting Preparations Date
(any answer NO needs mitigated) (all answers must be YES to proceed
Crane #1 designation Overall dimensions Water depth (m) Communications available & checked
7. Safety Measures to be Considered
8. Communications / Lift protocol
9. Final Offshore Check
No of Falls
Whipline
No of Falls
Whipline
Hydrodynamic loads?
Working Wire Length (m)
Working Wire Length (m)
Potential for Lightening
Strike
Mobile Crane Use -
Outriggers Foundations
Satisfactory?
Mobile Crane Use - Free
from Overhead Services
/ Traffic?
Winch SWL (Te)
Is this a winch Crosshaul /
Pull-in operation?
Crane #2 modes required
during lift
Winch #1
No of Tuggers
Crane tuggers required?
Winch Mode
Is Crane Protection
Required i.e. crane master
No of Falls
Working Wire Length (m)
Please type in your input
If you have any comments regarding the use of this
spreadsheet, please direct your E-mail queries to
liftingoperations@technip.com where they will be addressed
Max Design Lift conditions
Slack wire possibility?
Design load trim?
Wind (knots)
Drop Down Menu
Do not Touch
3. Load Details 4. Lift Rigging Details 5. Lifting Environment Details
Type of lift
Main Block
Significant Wave Height
(m)
Free Flooding Surface?
Seabed Conditions?
Crane #1 modes required
during lift
Crane #2
Main Block
Suction Loads?
Splash Zone Effect?
\\vboxsrv\conversion_tmp\scratch_4\247116635.xls.ms_office
Doc No Prepared CDM
Rev Checked AST
Date Approved MJO
0
0
0 0 0 0
0
0
0 Type of Lift
Main Block
0 Crane #1 Modes Required During Lift
Crane #2 0 Crane #2 Modes Required During Lift
Winch SWL (Te) Crane Tuggers Required 0
Winch #1 0
In Air (Te) 0
In Water (Te) 0
Rev
0
Rev
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
15. Pick up & lay down within operation radius of crane?
16. Asset/deck/equipment protected from load?
17. Loads clearly visible during night/subsea working?
28. Is the Lifting Operation free of exclusion zones or subsea architecture?
29. Is hook isolation a non-requirement?
9. Weight verified?
10. Normal size & shape/free from sharp edges?
11. Is the lift point directly above load?
12. Is the load secure of loose objects?
13. Does crane driver have continuous visibility of lift?
14. Lift clear of any plant/equipment/assets/people?
0
0
Any risk to subsea architecture?
Are there any exclusion zones?
0
0
0
Path of Load considered?
Is pre ballasting of the vessel required?
Is the heeling system required?
PROJECT LIFTING ANALYSIS REPORT NO
(Issued to Ships Services for Approval) 0
0
0
0
5. LIFTING ENVIRONMENT DETAILS
Position of COG?
Max Calculated Dynamic Hook & Load, inc rigging (Te)
0 0 0
No of Tuggers
0
0
0 0 0
0 0
3. LOAD DETAILS
No of Falls
0
Client
Vessel/Site
Procedure
Procedure No
Risk Assessment (Onshore) 0
0
0
0
Winch Mode Working Wire Length (m)
Is this a Winch Crosshaul / Pull-in Operation?
OPSD-CDM-G-006
C
11/7/2005
Help? - liftingoperations@technip.com
1. ADMINISTRATION
Project
Brief Description of Lift
0
No of Falls
0 0
Is Crane Protection required? i.e. Crane Master
0 Crane Designation #2
Whipline Working Wire Length (m)
Design Load Trim?
STATIC WEIGHT
0 Length (m)
4. LIFT RIGGING DETAILS
RIGGING SUMMARY SPECIFICATION DRAWING
Static Rigging Weight (Te)
LIFT PLANNING SUMMARY DRAWING
Width (m)
Other Relevant Information
0
Lifting Arrangement Description
Water Depth
Certification Available & checked
0
0
Can the spreader bar be connected/disconnected safely?
Title
0
Drawing No
Lift Plan No
Date Created
Routine/Non Routine Lift
00/01/1900
0
0





















Is there a Seabed Connection Before, During or After the Lift?
2. Nominated competent lift team (x2 min)


COMPLETE MITIGATION ACTIONS IF "NO" ANSWERED

Slack Wire Possibility?
0
0

7. SAFETY MEASURES TO BE CONSIDERED
Has a Trial Lift been completed successfully? (Detail Results)
IF THE ANSWER TO ANY OF THE ABOVE QUESTIONS IS 'YES'
PERMISSION FROM SHIPS SERVICES REQUIRED, REFERENCE FMS-SF-622, Rev 2
Seafastening Disconnected?

0
0
6. LIFTING PREPARATIONS
0
Is the load more than 70% of crane SWL? 0
Potential for Lightening Strike?
Landing of Load considered?
Disconnection of Load considered?
Can the Lift Rigging be recovered safely?
0
0
0
Seabed Conditions?
MAX DESIGN LIFT CONDITIONS
Wind (knots)
Significant Wave Height (m)
Hydrodynamic Loads?
Free Flooding Surface
Splash Zone Effect?
0
0
0
0
0
Mobile Crane Use - Outriggers Foundations Satisfactory?
What is the minimum clearance to the spreader bar?
Can the Load Free Flood?
0
0
Job Risk Assessment (Offshore)
(As required)
0
0
OVERALL DIMENSIONS
0
Height (m)
Crane Designation #1
Report No
Report No
Location
0
0
24. Route & laydown area clear?
18. Load landing area clear, deck strong enough and properly prepared?
19. Tag lines (as required)?
1. Nominated competent lift supervisor (x1 min)
5. Dedicated certified lift points for lift rigging?
0
0
Is there Seabed Penetration loading?
0
27. Does the mode of utilisation permit the full SWL of the crane?
26. Is there only one crane in operation which is not in conflict with other cranes?
20. Vessel stability - pre ballasting completed?
21. Correct PPE worn? (Banksman clearly identifiable)
22. Sufficient head room/lift height clearance?
23. Lifting equipment movement controlled i.e. spreader bar
Suction Loads?
0
Is this a spreader bar lift?
0
Rev 0
Rev
0
00/01/1900
Rev
Date of Lift
2. CRANE DETAILS / LIFTING APPLIANCE DETAILS
Crane #1


0
25. Is the lift free from parallel conflicting operations
Is there topside clearance?
31. Any other concerns? (Please specify)
3. JRA completed for a personnel transfer?
4. JRA completed for a dangerous goods/chemical lift?
Any other Lifting Preparations required? (specify)
6. Lifting accessories and equipment fit for purpose?
30. Will the lift be continually supervised by the crane driver whilst the load is connected to
the crane?
Mobile Crane Use - Free from Overhead Services/Traffic?
Is a Crane Technician Required Offshore for the Lift?
7. Lifting accessories & equipment certificates checked?
8. Has the lift equipment had a pre-use check?
LIFT PLAN
0 0
Title Drawing No
0
0
0
\\vboxsrv\conversion_tmp\scratch_4\247116635.xls.ms_office
0
0
0
0
Lift Supervisor
0
1/0/1900
Approved Procedure and/or MOC completed?
Risk Assessment Actions Closed Out?
Suitable Weather Criteria and Window Available?
0 Warranty Surveyor Certificate Issued? (As required)
Have personnel and crane escape routes been verified? 0
Help? - liftingoperations@technip.com
COMPLETE OFFSHORE ONLY
10. SIGNED AND DATED
COMPLETE OFFSHORE ONLY
9. FINAL OFFSHORE CHECKS (All answers must be YES to Proceed with Lift)
POSITION
0
Tertiary (as required)
0
SIGN
DATE
Project Engineer
0
1/0/1900
Lift Plan Complete and signed off?
0
1/0/1900
Offshore Construction Manager
NAME
0
8. COMMUNICATIONS/LIFT PROTOCOL
Primary Lifting Protocol Agreed?
Secondary
0
Lift Plan Safety Measures Considered and Mitigation Actions in Place?
0
COMMUNICATIONS AVAILABLE
0 Pre-Lift Meeting Completed with all Relevant Parties
\\vboxsrv\conversion_tmp\scratch_4\247116635.xls.ms_office

Das könnte Ihnen auch gefallen