Sie sind auf Seite 1von 4

Risk Management in the

Procurement of Community Based


Construction Projects in Zambia


RESEARCH PROPOSAL BY
By
MUKUKA KOWA
(MSCPM5732014)
LECTURER : PROF J. TEMBO
COURSE CODE : GBS700
DUE DATE : 01/09/2014
I. INTRODUCTION
Construction, like any other business venture, is affected by a number of risks and it is therefore
imperative that risk management techniques are applied in all its activities. Risks have a
significant impact on a construction projects performance in terms of cost, time and quality. As
the size and complexity of the projects have increased, an ability to manage risks throughout
the construction process has become a central element preventing unwanted consequences.
How risks are shared between the project actors is to a large extent governed by the
procurement option and the content of the related contract documents. Therefore, selecting an
appropriate project procurement option is a key issue for project actors. The findings of this
work show a lack of an iterative approach to risk management, which is a weakness in current
procurement practices. This aspect must be addressed if the risk management process is to
serve projects and, thus, their clients. The absence of systematic risk management is especially
noted in the programme phase, where it arguably has the greatest potential impact.

II. BACKGROUND
Most of the projects currently being undertaken by the Government of Zambia are community-
based. For example 75 percent of schools constructed under the Ministry of Education since
1999 to date are executed using the community- based approach (Nthele 2005). There is,
therefore, need to improve on the management of such projects to improve the quality of the
products, minimize costs and improve the efficiency of implementation up to commissioning
stage and beyond. In 2004 alone, the Ministry of Education needed more than K4 billion for the
repair of blown-off roofs on classroom blocks country-wide (MOE-SIS, 2004). Most of the
buildings under repair were constructed in the past ten years using community-based mode of
construction.
III. STATEMENT OF THE PROBLEM
The government of the republic of Zambia with the assistance of co-operating partners has
spent and continues to spend colossal amounts of money on infrastructure development to
improve the socio-economic life of the citizens. Some of the structures developed are of poor
quality that cannot stand the test of time and require rehabilitation at an early stage. For
example, a classroom block at Kalingalinga Primary school in Lusaka district developed serious
structural cracks within ten years of its construction such that it could no longer be used for
teaching and learning. Investigations revealed that the thickness of the foundation footing for the
building was less than 100mm instead of the specified 200mm and was placed at less than
300mm below the ground level contrary to a minimum 600mm requirement in general
engineering practice in Zambia. Most of the donor assistance to the Zambian government and
indeed other developing countries is through loans and failure to use them properly will not only
mean a waste of resources, but a disservice to future generations who will end up paying for
abortive work. In addition, government is spending a lot of scarce resources to rehabilitate and
repair poorly constructed buildings.
IV. AIM OF THE RESEARCH
The aim of the research is to develop a Risk Management Model (RMM) to be used or adopted
by the community and other stakeholders in the procurement of community-based construction
projects in Zambia in order to improve their implementation. Improved implementation can be
construed to be improved delivery time, cost-effectiveness and improved quality.
V. OBJECTIVES
To achieve the above aim, the following are the objectives:
i. find risk management means for the risks that are associated with the project network
structure. And to make improvement suggestions on the use of these risk management
methods.
ii. Identify all possible construction management risks that are associated with community-
based construction projects from initiation to commissioning stage;
iii. Determine the probability and likelihood of occurrence of the identified risks;
iv. rank the risks according to severity on project objectives;
v. Develop responses for mitigating, controlling and monitoring the risks with negative
effects on the project targets so as to minimize costs, improve quality and efficiency of
project delivery.
vi. To develop recommendations, which contribute to more effective risk management in
construction projects.
VI. RESEARCH QUESTIONS
I. How do communities tackle issues of technical specifications, such as quality of
construction materials, and quality control during execution of the works?
II. What measures are put in place to ensure transparency and accountability in the
management of community-based project funds and how does this affect the
implementation schedule of the projects?
III. What are the major problems encountered in the procurement and transportation of
materials and how is their quality assured?
IV. What technical and management problems are encountered during the implementation
of community-based projects?

VII. CONCLUSION
The need for infrastructure development and upgrade in developing countries is increasing and
the main driver is the rise on demand due to: population increase, technology accessibility and
global competition. Zambia mainly rely on international firms and experts to fulfill their
objectives that are at times too ambitious for local companies to handle. The need to optimize
the use of scarce public funds through increases in efficiency and predictability in
implementation is vital; and the stakeholders are requesting more accountability from
government agencies in the effective use of these funds. This research will compile evidence
that proves the above statements, and willgo further to find patterns to the difficulties affecting
infrastructure projects and solutions to overcome these challenges.

VIII. BIBLIOGRAPHY
Baker, S., Ponniah, D. and Smith, S. (1999) Survey of Risk Management in Major U.K.
Companies, Journal of Professional Issues in Engineering Education and Practice, Vol. 125, No.
3, pp 94 104.
Nthele J. F., (2005) Sustainable construction guidelines for government rural schools in Zambia.
Final year thesis, University of South Australia, pp 5.

Das könnte Ihnen auch gefallen