Beruflich Dokumente
Kultur Dokumente
H
V
I
R
T
e
s
t
D
e
g
r
e
e
o
f
P
r
o
t
e
c
t
i
o
n
R
o
u
t
i
n
e
t
e
s
t
a
s
p
e
r
N
T
P
C
s
p
e
c
A
l
l
R
o
u
t
i
n
e
t
e
s
t
s
a
s
p
e
r
N
T
P
C
s
p
e
c
.
&
I
S
Sheet Steel (IS : 513) Y Y Y Y Y
Aluminum Bus bar Material
(IS : 5082)
Y Y Y Y Y Y
Copper Bus bar Material
(IS : 613)
Y Y Y Y Y Y
Support Insulator (IS :
9431, IS : 10912, IEC :
660)
Y Y Y Y Y
Air Circuit Breaker (IS:
13947)
Y Y Y Y Y Y Y
Energy Meters (IS : 722)
Y Y Y Y Y Y
Power & Aux. Contactors
(IS : 13947)
Y Y Y Y Y Y
Protection & Aux. Relays
(IS : 3231)
Y Y Y Y Y Y
Control & Selector
Switches (IS : 6875)
Y Y Y Y Y Y
CTs & PTs (IS 2705 /
3156)
Y Y Y Y
MCCB (IS : 13947) Y Y Y Y Y
Indicating Meters (IS :
1248)
Y Y Y Y Y Y
Indicating Lamps (IS :
13947)
Y Y Y Y Y Y
Air Break Switches
(IS : 13947)
Y Y Y Y Y
Control Terminal Blocks Y Y Y Y
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-03
LT SWITCHGEAR AND
BUS DUCT
PAGE 2 OF 3
LT SWITCHGEAR
(MCC, PCC, ACDB, DCDB, FUSE BOARDS, LOCAL PUSH BUTTON STATION, LOCAL
MOTOR STARTERS)
ATTRIBUTES /
CHARACTERIS-
TICS
ITEMS/
COMPONENTS/
SUB SYSTEM
ASSEMBLIY
M
a
k
e
,
M
o
d
e
l
,
T
y
p
e
,
R
a
t
i
n
g
&
T
C
D
i
m
e
n
s
i
o
n
s
&
F
i
n
i
s
h
E
l
e
c
t
r
i
c
a
l
p
r
o
p
e
r
t
i
e
s
M
e
c
h
a
n
i
c
a
l
P
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
p
r
o
p
e
r
t
i
e
s
F
u
n
c
t
i
o
n
a
l
&
O
p
e
r
a
t
i
o
n
a
l
F
e
a
t
u
r
e
s
a
s
p
e
r
N
T
P
C
S
p
e
c
.
I
t
e
m
t
o
c
o
n
f
o
r
m
t
o
r
e
l
e
v
a
n
t
S
t
a
n
d
a
r
d
s
P
r
e
t
r
e
a
t
m
e
n
t
a
s
p
e
r
I
S
6
0
0
5
P
a
i
n
t
S
h
a
d
e
,
A
d
h
e
s
i
o
n
,
T
h
i
c
k
n
e
s
s
&
F
i
n
i
s
h
F
u
n
c
t
i
o
n
a
l
C
h
e
c
k
s
M
i
l
l
i
-
v
o
l
t
d
r
o
p
T
e
s
t
I
R
H
V
I
R
T
e
s
t
D
e
g
r
e
e
o
f
P
r
o
t
e
c
t
i
o
n
R
o
u
t
i
n
e
t
e
s
t
a
s
p
e
r
N
T
P
C
s
p
e
c
A
l
l
R
o
u
t
i
n
e
t
e
s
t
s
a
s
p
e
r
N
T
P
C
s
p
e
c
.
&
I
S
Fuse (IS 13703) Y Y Y Y
Control
Transformer
(IS : 12021)
Y Y Y Y Y Y
Push Buttons (IS :
4794)
Y Y Y Y Y Y
Transducer (IEC :
60688)
Y Y Y Y Y Y
MCB (IS : 8828) Y Y Y Y Y Y
Breaker Handling
Trolley
Y Y Y Y Y Y
Synthetic Rubber
Gasket
(IS : 11149)
Y Y Y Y Y
LT SWITCHGEAR
(IS : 8623)
Y Y Y Y Y Y Y Y Y Y Y
Notes:
1. This is an indicative list of tests / checks. The manufacturer is to furnish a detailed
Quality Plan indicating the practice and procedure along with relevant supporting
documents.
2. Makes of all major Bought Out Items will be subject to NTPC approval.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-03
LT SWITCHGEAR AND
BUS DUCT
PAGE 3 OF 3
LT BUSDUCT
ATTRIBUTES ,
CHARACTERISTICS
ITEM,
COMPONENTS,
SUB SYSTEM
ASSEMBLY
D
i
m
e
n
s
i
o
n
&
S
u
r
f
a
c
e
F
i
n
i
s
h
M
a
k
e
,
T
y
p
e
,
R
a
t
i
n
g
&
T
C
E
l
e
c
t
r
i
c
a
l
P
r
o
p
e
r
t
i
e
s
M
e
c
h
a
n
i
c
a
l
P
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
P
r
o
p
e
r
t
i
e
s
I
t
e
m
t
o
c
o
n
f
o
r
m
t
o
r
e
l
e
v
a
n
t
I
S
W
P
S
A
p
p
r
o
v
a
l
,
W
e
l
d
e
r
Q
u
a
l
i
f
i
c
a
t
i
o
n
W
e
l
d
Q
u
a
l
i
t
y
C
h
e
c
k
(
D
P
t
e
s
t
&
x
-
r
a
y
T
e
s
t
)
P
a
i
n
t
S
h
a
d
e
,
T
h
i
c
k
n
e
s
s
,
A
d
h
e
s
i
o
n
&
F
i
n
i
s
h
T
i
g
h
t
n
e
s
s
b
y
T
o
r
q
u
e
m
e
a
s
u
r
e
m
e
n
t
E
l
e
c
t
r
i
c
a
l
C
l
e
a
r
a
n
c
e
s
G
a
l
v
a
n
i
z
i
n
g
T
e
s
t
a
s
p
e
r
I
S
2
6
2
9
/
2
6
3
3
/
I
R
H
V
I
R
T
e
s
t
P
h
a
s
e
S
e
q
u
e
n
c
e
C
h
e
c
k
D
e
g
r
e
e
o
f
P
r
o
t
e
c
t
i
o
n
r
o
u
t
i
n
e
t
e
s
t
a
s
p
e
r
N
T
P
C
s
p
e
c
.
Aluminum Sheets /
Plates / Strips /
Flexibles / tubes
(IS : 5082 / 737)
Y Y Y Y Y Y Y
CRCA Flats / ISMC
(IS 2062)
Y Y Y Y Y
Neoprene / Synthetic
Rubber Gaskets (IS
11149 / 3400)
Y Y Y Y
Rubber Bellows (IS :
3400)
Y Y Y Y
Support Insulator
(BS : 2782,
IEC : 660, IS:10912)
Y Y Y Y
Galvanized Structure
& GI Earthing Flat
(IS : 2629 / 2633 /
4749 )
Y Y Y Y
Space Heater &
Thermostat
Y Y Y
LT Busduct (IS :
8623 PART 2)
Y Y Y Y Y Y Y Y Y Y Y
Notes:
1. This is an indicative list of tests / checks. The manufacturer is to furnish a detailed
Quality Plan indicating the practice and procedure along with relevant supporting
documents.
2. Makes of all major Bought Out Items will be subject to NTPC approval.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-04
LT POWER CABLE
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-04
LT POWER CABLES
PAGE 1 OF 3
QUALITY ASSURANCE & INSPECTION
L.T POWER CABLES
(1.1 KV PVC & XLPE CABLES)
Attributes /
Characteristics
Item / Components /
Sub System Assembly
M
a
k
e
,
R
a
t
i
n
g
,
T
y
p
e
&
T
C
D
i
m
e
n
s
i
o
n
/
s
u
r
f
a
c
e
f
i
n
i
s
h
M
e
c
h
a
n
i
c
a
l
P
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
C
o
m
p
o
s
i
t
i
o
n
E
l
e
c
t
r
i
c
a
l
P
r
o
p
e
r
t
i
e
s
S
p
a
r
k
T
e
s
t
H
o
t
s
e
t
t
e
s
t
(
X
L
P
E
)
L
a
y
l
e
n
g
t
h
/
S
e
q
u
e
n
c
e
A
r
m
o
u
r
c
o
v
e
r
a
g
e
,
C
r
o
s
s
o
v
e
r
,
l
o
o
s
e
n
e
s
s
,
G
a
p
b
e
t
w
e
e
n
t
w
o
a
r
m
o
u
r
w
i
r
e
/
s
t
r
i
p
S
e
q
u
e
n
t
i
a
l
m
a
r
k
i
n
g
/
s
u
r
f
a
c
e
f
i
n
i
s
h
/
c
a
b
l
e
l
e
n
g
t
h
T
e
n
s
i
l
e
s
t
r
e
n
g
t
h
,
e
l
o
n
g
a
t
i
o
n
b
e
f
o
r
e
&
a
f
t
e
r
a
g
e
i
n
g
o
f
i
n
s
u
l
a
t
i
o
n
&
o
u
t
e
r
s
h
e
a
t
h
T
h
e
r
m
a
l
S
t
a
b
i
l
i
t
y
o
f
i
n
s
u
l
a
t
i
o
n
a
n
d
o
u
t
e
r
s
h
e
a
t
h
*
A
n
t
i
t
e
r
n
i
t
e
t
r
e
a
t
m
e
n
t
o
n
w
o
o
d
e
n
d
r
u
m
s
C
o
n
s
t
r
u
c
t
i
o
n
a
l
/
r
e
q
u
i
r
e
m
e
n
t
a
s
p
e
r
N
T
P
C
S
p
e
c
.
R
o
u
t
i
n
e
a
n
d
a
c
c
e
p
t
a
n
c
e
t
e
s
t
a
s
p
e
r
R
e
l
e
v
a
n
t
S
t
a
n
d
a
r
d
a
n
d
N
T
P
C
s
p
e
c
i
f
i
c
a
t
i
o
n
F
R
L
S
T
e
s
t
Aluminum (IS-8130) Y Y Y Y Y
PVC Compound (IS-5831) Y Y Y Y
XLPE Compound(IS-7098 Part-I) Y Y Y Y Y
FRLS PVC Compound(IS-5831 )
ASTM-D-2843/ ASTM-D-2863
IEC-754 Part-I
Y Y Y
Armour wire/strip (IS-3975) Y Y Y
Insulated Core Y Y Y Y
Laid up core Y Y
PVC Inner sheath Y
Armouring Y Y
Outer sheath Y Y Y Y Y
Finish cable (IS-1554 & 7098
Part-1)
ASTM-D-2843/ IS 10810 (Part- - 58 )
IEC-754 Part-I
Swedish Chimney SS 4241475 for
(F3 category)
Flammability test IEC-332 Part 3
Cat-B
Y Y Y Y Y Y Y
Y Y
Wooden drum (IS-10418) / Steel
drum
Y Y
Note: This is an indicative list of test/checks. The manufacturer is to furnish a detailed quality plan indicating the practice
and procedure along with relevant supporting documents.
2. Not applicable for XLPE insulation
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-04
LT POWER CABLES
PAGE 2 OF 3
ROUTINE TESTS
Routine tests shall be carried out on each drum of finished cables for all
types & sizes.
Following shall constitute routine tests:
1) Conductor Resistance test
2) High voltage test at room temperature
ACCEPTANCE TESTS
Following Acceptance tests shall be carried out for each type and size
of the cables on the cable drums selected at random as per sampling
plan mentioned in IS: 1554 Part 1 & IS 7098 Part-I
A) For Conductor
1) Annealing test For copper conductor only
2) Tensile test For aluminium conductor only
3) Wrapping test For aluminium conductor only
4) Resistance test
B) For Armour Wires / Formed Wires ( If applicable )
1) Measurement of Dimensions
2) Tensile Tests
3) Elongation Test
4) Torsion Test For Round wires only
5) Wrapping Test
6) Resistance Test
7) Mass of Zinc coating test For G S wires / Formed wires only
8) Uniformity of Zinc coating For G S wires / Formed wires only
9) Adhesion test For G S wires / Formed wires only
10) Freedom from defects
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-04
LT POWER CABLES
PAGE 3 OF 3
C) For PVC / XLPE insulation & PVC Sheath
1) Test for thickness
2) Hot set test For XLPE insulation only
3) Tensile strength & Elongation before ageing
D) For completed cables
1) Insulation resistance test (Volume resistivity method)
2) High voltage test at room temperature
E) Following tests shall be carried out and only one sample shall be taken
from each offered lot of all sizes for these tests:-
1) Tensile strength & elongation after ageing on PVC / XLPE insulation and
PVC outer sheath
2) Thermal stability test on PVC insulation and outer sheath
3) Oxygen index test on outer sheath
4) Smoke density rating test on outer sheath as per ASTM D 2843
5) Acid gas generation test on outer sheath as per IEC 754 (Part 1)
6) Flammability test as per IEC-332 - Part- 3 (Category- B) on completed
cable
7) Fire resistance test as per SS 4241475 (F3 Category ) on completed cable
F) Following tests shall be carried on one length of each size of offered
lot:
1) Surface finish, length measurement, sequence of cores, armour coverage,
Gap between two consecutive armour wires / formed wires
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-05
LT CONTROL CABLES
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-05
LT CONTROL CABLES
PAGE 1 OF 3
QUALITY ASSURANCE & INSPECTION
L.T CONTROL CABLES
(1.1 KV PVC CABLES)
Attributes /
Characteristics
Item / Components /
Sub System Assembly
M
a
k
e
,
T
y
p
e
,
R
a
t
i
n
g
,
T
.
C
D
i
m
e
n
s
i
o
n
/
s
u
r
f
a
c
e
f
i
n
i
s
h
M
e
c
h
a
n
i
c
a
l
P
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
C
o
m
p
o
s
i
t
i
o
n
E
l
e
c
t
r
i
c
a
l
P
r
o
p
e
r
t
i
e
s
S
p
a
r
k
T
e
s
t
L
a
y
l
e
n
g
t
h
/
S
e
q
u
e
n
c
e
A
r
m
o
u
r
c
o
v
e
r
a
g
e
,
c
r
o
s
s
o
v
e
r
,
l
o
o
s
e
n
e
s
s
,
g
a
p
b
e
t
w
e
e
n
t
w
o
a
r
m
o
u
r
w
i
r
e
S
e
q
u
e
n
t
i
a
l
m
a
r
k
i
n
g
/
s
u
r
f
a
c
e
f
i
n
i
s
h
/
c
a
b
l
e
l
e
n
g
t
h
T
e
n
s
i
l
e
s
t
r
e
n
g
t
h
,
e
l
o
n
g
a
t
i
o
n
b
e
f
o
r
e
&
a
f
t
e
r
a
g
e
i
n
g
o
f
i
n
s
u
l
a
t
i
o
n
&
o
u
t
e
r
s
h
e
a
t
h
s
h
e
a
t
h
T
h
e
r
m
a
l
s
t
a
b
i
l
i
t
y
o
f
i
n
s
u
l
a
t
i
o
n
a
n
d
o
u
t
e
r
s
h
e
a
t
h
A
n
t
i
t
e
r
m
i
t
e
t
r
e
a
t
m
e
n
t
o
n
w
o
o
d
e
n
d
r
u
m
s
C
o
n
s
t
r
u
c
t
i
o
n
a
l
f
e
a
t
u
r
e
a
s
p
e
r
N
T
P
C
S
p
e
c
.
R
o
u
t
i
n
e
&
A
c
c
e
p
t
a
n
c
e
t
e
s
t
a
s
p
e
r
r
e
l
e
v
a
n
t
s
t
a
n
d
a
r
d
&
p
a
g
e
2
&
3
o
f
t
h
i
s
t
a
b
l
e
F
R
L
S
T
e
s
t
Copper Conductor
(IS-8130)
Y Y Y Y Y
PVC Compound (IS-5831) Y Y Y Y
FRLS PVC Compound
IS-5831
ASTM-D-2843/ IS 10810
(Part-58 ) IEC-754 Part-1
Y Y Y Y
Armour wire/strip (IS-3975) Y Y Y
Insulated Core Y Y Y Y
Laid up core Y Y
PVC Inner sheath Y
Armouring Y Y
Outer sheath Y Y Y Y Y
Finish cable (IS-1554- 1)
ASTM-D-2843/ IS 10810
(Part-58 )
IEC-754 Part-1
Swedish Chimney: SEN
SS 424-1475( F3 category)
Flammability test IEC-332
Part-3 Cat-B
Y Y Y Y Y Y Y Y Y
Wooden drum (IS : 10418)
/ Steel drum
Y Y
1.Note : This is an indicative list of test/checks. The manufacturer is to furnish a detailed
quality plan indicating the Practice and procedure along with relevant supporting documents.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-05
LT CONTROL CABLES
PAGE 2 OF 3
CONTROL CABLE
ROUTINE TESTS
Routine tests shall be carried out on each drum of finished cables for all
types & sizes.
Following shall constitute routine tests:
1) Conductor Resistance test
2) High voltage test at room temperature
ACCEPTANCE TESTS
Following Acceptance tests shall be carried out for each type and size
of the cables on the cable drums selected at random as per sampling
plan mentioned in IS: 1554 Part 1
A) For Conductor
1) Annealing test For copper conductor only
2) Resistance test
B) For Armour Wires / Formed Wires (If applicable)
1) Measurement of Dimensions
2) Tensile Tests
3) Elongation Test
4) Torsion Test For Round wires only
5) Wrapping Test
6) Resistance Test
7) Mass of Zinc coating test For G S wires / Formed wires only
8) Uniformity of Zinc coating For G S wires / Formed wires only
9) Adhesion test For G S wires / Formed wires only
10) Freedom from defects
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-05
LT CONTROL CABLES
PAGE 3 OF 3
C) For PVC insulation & PVC Sheath
1) Test for thickness
2) Tensile strength & Elongation before ageing
D) For completed cables
1) Insulation resistance test (Volume resistivity method)
2) High voltage test at room temperature
E) Following tests shall be carried out and only one sample shall be taken
from each offered lot of all sizes for these tests:-
1) Tensile strength & elongation after ageing on PVC insulation and PVC
outer sheath
2) Thermal stability test on PVC insulation and outer sheath
3) Oxygen index test on outer sheath
4) Smoke density rating test on outer sheath as per ASTM D 2843
5) Acid gas generation test on outer sheath as per IEC 754 (Part 1)
6) Flammability test as per IEC-332 - Part- 3 (Category- B) on completed
cable
7) Fire resistance test as per SS 4241475 (F3 Category) on completed cable
F) Following tests shall be carried on one length of each size of offered
lot:
1) Surface finish, length measurement, sequence of cores, armour coverage,
Gap between two consecutive armour wires / formed wires
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-06
INSTRUMENTATION CABLES
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-06
INSTRUMENTATION
CABLES
PAGE 1 OF 1
INSTRUMENTATION CABLE
TESTS
ITEMS
C
o
n
d
u
c
t
o
r
R
e
s
i
s
t
a
n
c
e
&
(
A
)
H
i
g
h
V
o
l
t
a
g
e
&
(
A
)
I
n
s
u
l
a
t
i
o
n
R
e
s
i
s
t
a
n
c
e
&
(
A
)
C
o
n
s
t
r
u
c
t
i
o
n
a
l
d
e
t
a
i
l
,
d
i
m
e
n
s
i
o
n
s
(
A
)
O
u
t
e
r
-
S
h
e
a
t
h
e
/
c
o
r
e
m
a
r
k
i
n
g
,
e
n
d
s
e
a
l
i
n
g
(
A
)
T
h
e
r
m
a
l
S
t
a
b
i
l
i
t
y
(
A
)
+
V
i
s
u
a
l
,
S
u
r
f
a
c
e
f
i
n
i
s
h
(
A
)
+
E
l
e
c
t
r
i
c
a
l
P
a
r
a
m
e
t
e
r
s
*
*
(
A
)
+
P
e
r
s
u
l
p
h
a
t
e
T
e
s
t
(
A
)
+
O
v
e
r
a
l
l
/
C
o
v
e
r
a
g
e
/
C
o
n
t
i
n
u
i
t
y
(
A
)
S
w
i
d
e
s
h
c
h
i
m
n
e
y
T
e
s
t
(
S
S
-
4
2
4
1
4
7
5
)
(
A
)
+
+
F
R
L
S
T
e
s
t
*
(
A
)
+
+
T
e
n
s
i
l
e
&
E
l
o
n
g
a
t
i
o
n
b
e
f
o
r
e
&
a
f
t
e
r
a
g
i
n
g
(
A
)
+
+
V
o
l
.
R
e
s
i
s
t
i
v
i
t
y
.
a
t
r
o
o
m
&
E
l
e
v
a
t
e
d
T
e
m
p
.
(
A
)
+
+
S
p
a
r
k
t
e
s
t
r
e
p
o
r
t
r
e
v
i
e
w
1. Instrument cable
twisted and shielded
Conductor (IS-8130) Y Y Y
Insulation (VDE-207) Y Y Y Y Y Y
Pairing/Twisting Y Y Y
Shielding Y Y Y
Drain wire Y Y Y Y Y
Inner Sheath Y Y Y Y Y Y
Outer Sheath Y Y Y Y Y Y
Over all cable Y Y Y Y Y Y Y Y Y
Cable Drums
(IS-10418)
Y Y
Note : High Temp. cables shall be subjected to tests as per VDE-207(Part-6)
Compensating cables shall be checked for Thermal EMF/Endurance test as per IS
8784.
Note : This is an indicative list of tests/checks. The manufacture is to furnish a
detailed Quality Plan indicating his practice & Procedure along with relevant
supporting documents during QP finalization for all item.
Note : - Routine Test A - Acceptance Test Y - Test Applicable
Note : Sampling Plan for Acceptance test shall be as per IS 8784 (As applicable)
* FRLS Tests: Oxygen / Temp Index (ASTM D-2863), Smoke Density Rating
(ASTM D 2843), HCL Emission (IEC-754-1)
** Characteristic Impedance, Attenuation, Mutual Capacitance, Cross Talk
(As applicable)
+ Sample size will be One No. of each size/type per lot.
++ Sample size will be One No. sample for complete lot offered irrespective of
size/type.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-07
STATION LIGHTING
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-07
STATION LIGHTING
PAGE 1 OF 1
STATION LIGHTING
Item Components
Sub System
Assembly
Attributes
Characteristics
M
a
k
e
,
T
y
p
e
,
R
a
t
i
n
g
/
T
C
D
i
m
e
n
s
i
o
n
P
r
e
-
T
r
e
a
t
m
e
n
t
o
f
s
h
e
e
t
P
a
i
n
t
S
h
a
d
e
T
h
i
c
k
n
e
s
s
A
d
h
e
s
i
o
n
&
F
i
n
i
s
h
G
a
l
v
a
n
i
s
e
T
e
s
t
I
P
T
e
s
t
B
o
u
g
h
t
O
u
t
I
t
e
m
s
/
B
i
l
l
o
f
M
a
t
e
r
i
a
l
H
V
&
I
R
F
u
n
c
t
i
o
n
a
l
C
h
e
c
k
a
s
p
e
r
s
p
e
c
.
C
o
n
s
t
r
u
c
t
i
o
n
a
l
F
e
a
t
u
r
e
a
s
p
e
r
N
T
P
C
s
p
e
c
.
R
o
u
t
i
n
e
T
e
s
t
a
s
p
e
r
r
e
l
e
v
a
n
t
s
t
d
a
n
d
s
p
e
c
A
c
c
e
p
t
a
n
c
e
T
e
s
t
a
s
p
e
r
r
e
l
e
v
a
n
t
s
t
d
a
n
d
s
p
e
c
I
t
e
m
t
o
c
o
n
f
o
r
m
t
o
r
e
l
e
v
a
n
t
s
t
a
n
d
a
r
d
Luminaries (IS-10322
Part-5 Sec.1)
Y Y Y Y
Y
Electronic Ballast Y
Y
Y Y
Lighting Wire (IS-694) Y
Y
Fans (IS-374) Y
Y
Pole (IS-2713) Y Y Y
Y
Y
Lamps (IS-9800, IS-
9974)
Y Y Y
Lighting Mast Y Y Y Y
Y
Y
Wall Mounted Lighting
Panel (IS-513, IS-5)
Y Y Y Y Y Y Y Y Y Y Y Y
Switch Box/ Junction
Box/Receptacles/ Local
Push Button Station,
Lighting Panel (IS-513,
2629, 2633, 4759,
6745)
Y Y Y Y Y Y Y Y Y Y Y Y
Cable Gland (BS-6121) Y Y Y
Cable Lug (IS-8309) Y Y Y
Flexible Conduit Y
Y
Lighting Transformer
(IS-1117)
Y Y Y
Epoxy & Galvanised
Conduit (IS-9537, 2629,
2633, 4759, 6745)
Y Y
Y
Y
Notes:
1. This is an indicative list of tests / checks. The manufacturer is to furnish a detailed Quality Plan
indicating the practice and procedure along with relevant supporting documents.
2. Make of all major Bought Out Items will be subject to NTPC approval.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-08
CABLING, EARTHING & LIGHTNING
PROTECTION
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-08
CABLING, EARTHING
& LIGHTING
PROTECTION
PAGE 1 OF 1
CABLING, EARTHING, LIGHTNING PROTECTION
ATTRIBUTES /
CHARACTERISTICS
ITEMS/COMPONENTS /
SUB SYSTEMS
D
i
m
e
n
s
i
o
n
P
a
i
n
t
s
h
a
d
e
,
p
a
i
n
t
t
h
i
c
k
n
e
s
s
,
a
d
h
e
s
i
o
n
P
r
e
-
t
r
e
a
t
m
e
n
t
o
f
s
h
e
e
t
I
P
p
r
o
t
e
c
t
i
o
n
P
r
o
o
f
l
o
a
d
*
S
u
r
f
a
c
e
f
i
n
i
s
h
D
e
f
l
e
c
t
i
o
n
t
e
s
t
*
H
V
&
I
R
G
a
l
v
a
n
i
s
e
T
e
s
t
(
I
f
A
p
p
l
i
c
a
b
l
e
)
F
u
n
c
t
i
o
n
a
l
B
o
u
g
h
t
o
u
t
i
t
e
m
s
/
B
i
l
l
o
f
m
a
t
e
r
i
a
l
R
o
u
t
i
n
e
t
e
s
t
s
a
s
p
e
r
r
e
l
e
v
a
n
t
s
t
a
n
d
a
r
d
&
s
p
e
c
i
f
i
c
a
t
i
o
n
A
c
c
e
p
t
a
n
c
e
t
e
s
t
s
a
s
p
e
r
r
e
l
e
v
a
n
t
s
t
a
n
d
a
r
d
&
s
p
e
c
i
f
i
c
a
t
i
o
n
C
o
n
s
t
r
u
c
t
i
o
n
a
l
f
e
a
t
u
r
e
a
s
p
e
r
N
T
P
C
Wall Mounted-Lighting Panel
(IS-513, IS:5, IS:2629, 2633,
6745)
Y Y Y Y Y Y Y Y Y Y Y Y
Switch box/junction box/
Receptacles Panel (IS-513,
IS:5, IS:2629, 2633, 6745)
Y Y Y Y Y Y Y Y Y Y Y Y
Cable glands(BS-6121) Y Y
Cable lug(IS-8309) Y Y
Lighting wire(IS-694) Y Y
Flexible conduits Y Y Y
Conduits (Galvanise & Epoxy)
IS-9537 & IS-2629, 2633, 6745
Y Y Y Y Y
RCC Hume Pipe (IS-458) Y
Cable termination & straight
through joint (VDE-0278)
Y Y Y
Cable Trays, Flexible supports
system & accessories IS-513,
2629, 2633, 6745
Y Y Y Y Y Y Y Y Y Y
Trefoil clamp Y Y
GI flats for earthing & lighting
protection (IS 2062, 2629,
6745, 2633)
Y Y Y Y Y
GI wire (IS-280) Y Y
Fire Sealing System ( BS 476) Y Y Y
Note: 1. This is an indicative list of tests /checks. The manufacturer is to furnish a detailed Quality Plan
indicating the practice and procedure along with relevant supporting documents.
2. * Deflection Test on cable trays and Proof Load test on cable trays support system will be as per
details given in the NTPC technical specification & approved MQP. The above acceptance tests
shall be done only on one sample from each size of offered lot.
3. Make of all items will be subject to NTPC approval.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-09
CONTROL PANELS
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-09
CONTROL PANEL
PAGE 1 OF 1
CONTROL PANEL
Attributes
Characteristics
Item Components
Sub System Assembly
E
l
e
c
t
r
i
c
a
l
P
r
o
p
e
r
t
i
e
s
M
e
c
h
a
n
i
c
a
l
P
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
P
r
o
p
e
r
t
i
e
s
D
i
m
e
n
s
i
o
n
s
/
F
i
n
i
s
h
T
y
p
e
/
R
a
t
i
n
g
/
F
u
n
c
t
i
o
n
a
l
c
h
e
c
k
H
V
/
I
R
R
o
u
t
i
n
e
t
e
s
t
a
s
p
e
r
r
e
l
e
v
a
n
t
s
t
d
.
C
o
n
s
t
r
u
c
t
i
o
n
a
l
F
e
a
t
u
r
e
s
I
S
:
6
0
0
5
,
S
e
v
e
n
t
a
n
k
p
r
o
c
e
s
s
P
a
i
n
t
f
i
n
i
s
h
/
s
h
a
d
e
/
t
h
i
c
k
n
e
s
s
a
d
h
e
s
i
o
n
M
o
u
n
t
i
n
g
s
/
B
O
M
/
M
a
k
e
,
C
o
m
p
l
e
t
e
n
e
s
s
/
W
i
r
i
n
g
I
n
t
e
r
l
o
c
k
F
u
n
c
t
i
o
n
a
l
&
O
p
e
r
a
t
i
o
n
T
e
s
t
i
n
g
/
S
i
m
u
l
a
t
i
o
n
c
h
e
c
k
D
e
g
r
e
e
o
f
P
r
o
t
e
c
t
i
o
n
T
e
s
t
S
p
e
c
i
f
i
c
a
t
i
o
n
r
e
q
u
i
r
e
m
e
n
t
Sheet Steel (IS-513) Y Y Y
Aluminum / Copper Bus-bar
(IS-5082/IS-613/IS-1987)
Y Y Y Y
Support Insulator
(BS-2782/IEC-660/IS-10912)
Y Y Y Y
Control / Selector Switch
(IS-6875)
Y Y Y
Contractor/ MCB (IS-13947) Y Y Y
O/L Protection relays (IS-3231) Y Y
C.T /V.T/ Indicating Meter
(IS-2705/3156/1248)
Y Y Y
Fuse/ Fuse carrier
(IS-13703)
Y Y Y
Terminals/lugs/PVC wires
(IS-13947//IS-694)
Y Y Y Y Y
Timers(IS-3231) Y Y Y
LVS, Mosaics Y
Push Button/ Lamp/ (IS-6875) Y Y Y
Control Transformer
(IS-12021)
Y Y Y
Mimic, Annunciater Y Y
Gasket (IS-11149) Y Y Y Y Y
Fabrication Y
Pretreatment & Painting Y Y
Control panel Y Y Y Y Y
NOTE:
1. This is an indicative list of Test/ Checks. The manufacturer to furnish a detailed Quality Plan
indicating the practice and procedure along with relevant supporting documents.
2. All major Bought out Items will be subject to NTPC approval.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-10
CONTROL DESK WITH
PROGRAMMABLE LOGIC CONTROLLER
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-10
CONTROL DESK WITH PLC
PAGE 1 OF 1
PROGRAMMABLE LOGIC CONTROLLER
TESTS
ITEMS
V
i
s
u
a
l
G
A
,
B
O
M
,
L
a
y
O
u
t
o
f
c
o
m
p
o
n
e
n
t
s
D
i
m
e
n
s
i
o
n
s
P
a
i
n
t
S
h
a
d
e
/
T
h
i
c
k
n
e
s
s
/
A
d
h
e
s
i
o
n
A
l
i
g
n
m
e
n
t
o
f
S
e
c
t
i
o
n
C
o
m
p
o
n
e
n
t
R
a
t
i
n
g
/
M
a
k
e
/
T
y
p
e
W
i
r
i
n
g
I
R
&
H
V
R
e
v
i
e
w
o
f
T
C
f
o
r
i
n
s
t
r
u
m
e
n
t
s
/
D
e
v
i
c
e
s
/
R
e
c
o
r
d
e
r
s
,
I
n
d
i
c
a
t
o
r
s
/
M
o
s
a
i
c
I
t
e
m
s
/
T
r
a
n
s
d
u
c
e
r
s
A
c
c
e
s
s
i
b
i
l
i
t
y
o
f
T
B
S
/
D
e
v
i
c
e
s
I
l
l
u
m
i
n
a
t
i
o
n
F
u
n
c
t
i
o
n
a
l
C
h
e
c
k
f
o
r
C
o
n
t
r
o
l
E
l
e
m
e
n
t
,
A
n
n
u
n
c
i
a
t
i
o
n
M
i
m
i
c
T
e
s
t
a
s
p
e
r
I
E
C
1
1
3
1
*
T
e
s
t
a
s
p
e
r
S
t
d
&
(
A
)
1. PLC Panel Y Y Y Y Y Y Y Y Y Y Y Y
2. Control Desk With PLC Y Y Y Y Y Y Y Y Y Y Y Y Y
Note: 1) Detailed procedure of Environmental Stress Screening test shall be as per Quality Assurance
Programme in General Technical Conditions
2) This is an indicative list of test/ checks. The manufacturer is to furnish a detailed quality plan
indicating the Practice and Procedure alongwith relevant supporting documents.
*Applicable for PLC Y - Test Applicable , - Routine Test (A) - Acceptance Test
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-11
BATTERY CHARGER & BATTERIES
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-11
BATTERY CHARGER
PAGE 1 OF 4
BATTERY CHARGER
Attributes / Characteristics
Items / Components /
Sub- assembly
M
a
k
e
,
M
o
d
e
l
,
T
y
p
e
,
R
a
t
i
n
g
D
i
m
e
n
s
i
o
n
a
l
c
h
e
c
k
a
n
d
P
a
i
n
t
s
h
a
d
e
,
t
h
i
c
k
n
e
s
s
,
a
d
h
e
s
i
o
n
&
F
i
n
i
s
h
c
h
e
c
k
s
C
o
m
p
l
e
t
e
p
h
y
s
i
c
a
l
e
x
a
m
i
n
a
t
i
o
n
f
o
r
c
o
n
s
t
r
u
c
t
i
o
n
a
l
f
e
a
t
u
r
e
s
a
s
p
e
r
a
p
p
r
o
v
e
d
d
r
g
s
R
i
p
p
l
e
C
o
n
t
e
n
t
T
e
s
t
,
L
o
a
d
L
i
m
i
t
e
r
o
p
e
r
a
t
i
o
n
&
A
V
R
O
p
e
r
a
t
i
o
n
T
e
s
t
O
p
e
r
a
t
i
o
n
a
l
&
F
u
n
c
t
i
o
n
a
l
C
h
e
c
k
s
o
f
a
u
x
.
D
e
v
i
c
e
s
l
i
k
e
a
n
n
u
n
c
i
a
t
o
r
,
s
w
i
t
c
h
e
s
,
i
n
d
i
a
c
t
o
r
s
e
t
c
.
H
V
&
I
R
T
e
s
t
E
n
v
i
r
o
n
m
e
n
t
a
l
S
t
r
e
s
s
S
c
r
e
e
n
i
n
g
Battery Charger Y Y Y Y Y Y Y
Note 1 : This check list is applicable for Battery Charger of capacity upto 24 V / 48 V , 150
A DC.
2 : Separate approval of QP is not envisaged. Main Contractor / nominated inspection
agency will carry out the inspection as per above check-list and submit inspection
report to NTPC for their review / acceptance of the same.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-11
BATTERY CHARGER
PAGE 2 OF 4
DC SYSTEM SQE_19
LEAD ACID BATTERY
ATTRIBUTES /
CHARACTERISTICS
ITEMS,
COMPONENTS, SUB
SYSTEM ASSEMBLY D
i
m
e
n
s
i
o
n
s
&
F
i
n
i
s
h
C
o
n
f
o
r
m
a
n
c
e
t
o
r
e
l
e
v
a
n
t
p
a
r
t
d
r
g
.
&
M
a
n
u
f
a
c
t
u
r
e
r
s
s
t
a
n
d
a
r
d
s
C
h
e
m
i
c
a
l
c
o
m
p
o
s
i
t
i
o
n
L
e
a
d
C
o
a
t
i
n
g
T
h
i
c
k
n
e
s
s
(
m
i
n
.
2
5
m
i
c
r
o
n
s
,
I
S
:
6
8
4
8
A
p
p
.
F
)
&
A
d
h
e
s
i
o
n
C
o
n
f
o
r
m
a
n
c
e
t
o
C
P
W
D
S
p
e
c
.
f
o
r
T
e
a
k
P
a
i
n
t
P
r
o
c
e
s
s
c
h
e
c
k
s
,
P
a
i
n
t
S
h
a
d
e
,
T
h
i
c
k
n
e
s
s
,
A
d
h
e
s
i
o
n
&
F
i
n
i
s
h
C
o
n
s
t
r
u
c
t
i
o
n
a
l
r
e
q
u
i
r
e
m
e
n
t
s
a
s
p
e
r
N
T
P
C
S
I
n
s
u
l
a
t
i
o
n
R
e
s
i
s
t
a
n
c
e
M
a
r
k
i
n
g
(
R
o
u
t
i
n
e
&
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
C
h
e
c
k
i
n
g
o
f
P
o
l
a
r
i
t
y
&
a
b
s
e
n
c
e
o
f
s
h
o
r
t
c
i
r
c
u
i
t
(
R
o
u
t
i
n
e
&
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
T
e
s
t
f
o
r
C
a
p
a
c
i
t
i
e
s
f
o
r
1
0
h
r
s
.
d
i
s
c
h
a
r
g
e
r
a
t
e
a
l
o
n
g
w
i
t
h
t
h
e
t
e
s
t
f
o
r
v
o
l
t
a
g
e
d
u
r
i
n
g
d
i
s
c
h
a
r
g
e
(
A
c
c
e
p
t
a
n
c
e
Container & Lids (IS :
1146)
Y Y
Vent Plugs Y Y
Sealing Compound
(IS : 3116)
Y Y
Positive & Negative
Plates
Y Y
Separators (IS : 6071) Y Y
Electrolyte
(Water / Sulphuric Acid)
(IS : 1069 / 266)
Y Y
Inter-cell Connectors &
Fasteners
Y Y Y
Battery Stand Y Y Y Y
Cell Insulators Y Y Y
Stack Assembly Y Y
Lead Acid Battery
(IS : 1652)
Y Y Y Y Y
Note: This is an indicative list of tests / checks. The manufacturer is to furnish a
detailed Quality Plan indicating the practice and procedure along with relevant
supporting documents.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-11
BATTERY CHARGER
PAGE 3 OF 4
Ni- Cd BATTERY
ATTRIBUTES /
CHARACTERISTICS
ITEMS, COMPONENTS, SUB
SYSTEM ASSEMBLY
D
i
m
e
n
s
i
o
n
s
&
F
i
n
i
s
h
I
m
p
a
c
t
S
t
r
e
n
g
t
h
C
o
n
f
o
r
m
a
n
c
e
t
o
r
e
l
e
v
a
n
t
p
a
r
t
d
r
g
.
&
M
a
n
u
f
a
c
t
u
r
e
r
s
s
t
a
n
d
a
r
d
s
R
e
s
i
s
t
a
n
c
e
t
o
A
l
k
a
l
i
C
h
e
m
i
c
a
l
c
o
m
p
o
s
i
t
i
o
n
N
i
c
k
e
l
P
l
a
t
i
n
g
t
h
i
c
k
n
e
s
s
P
a
i
n
t
S
h
a
d
e
,
T
h
i
c
k
n
e
s
s
,
A
d
h
e
s
i
o
n
&
F
i
n
i
s
h
A
i
r
P
r
e
s
s
u
r
e
T
e
s
t
a
f
t
e
r
h
e
a
t
s
e
a
l
i
n
g
M
a
r
k
i
n
g
&
M
a
s
s
(
R
o
u
t
i
n
e
&
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
A
i
r
P
r
e
s
s
u
r
e
T
e
s
t
(
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
R
e
t
e
n
t
i
o
n
o
f
C
h
a
r
g
e
T
e
s
t
(
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
A
H
T
e
s
t
(
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
I
n
s
u
l
a
t
i
o
n
R
e
s
i
s
t
a
n
c
e
(
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
P
o
l
a
r
i
t
y
&
a
b
s
e
n
c
e
o
f
s
h
o
r
t
c
i
r
c
u
i
t
(
R
o
u
t
i
n
e
&
A
c
c
e
p
t
a
n
c
e
T
e
s
t
)
Container & Lids Y Y Y Y
Vent Plugs Y Y Y
Perforated Steel Strips Y Y Y Y
Active Material for Positive &
Negative Plates
Y Y
Separators Y Y Y
Electrolyte Y Y
Inter-cell Connectors &
Fasteners
Y Y Y Y
Battery Stand Y Y Y
Cell Insulators Y Y Y
Stack Assembly Y Y Y Y Y Y
Ni-Cd Battery
( IS : 10918)
Y Y Y Y Y Y Y
Notes:
1. This is an indicative list of tests / checks. The manufacturer is to furnish a detailed Quality
Plan indicating the practice and procedure along with relevant supporting documents.
2. Makes of all major Bought Out Items will be subject to NTPC approval.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-11
BATTERY CHARGER
PAGE 4 OF 4
BATTERY CHARGER
Attributes / Characteristics
Items / Components /
Sub- assembly
M
a
k
e
,
M
o
d
e
l
,
T
y
p
e
,
R
a
t
i
n
g
&
F
i
n
i
s
h
V
e
r
i
f
i
c
a
t
i
o
n
o
f
R
o
u
t
i
n
e
t
e
s
t
r
e
p
o
r
t
s
a
s
p
e
r
r
e
l
e
v
a
n
t
I
S
S
h
e
e
t
S
t
e
e
l
P
r
e
t
r
e
a
t
m
e
n
t
&
P
a
i
n
t
i
n
g
p
r
o
c
e
s
s
c
h
e
c
k
s
C
o
n
f
o
r
m
t
o
r
e
l
e
v
a
n
t
S
t
a
n
d
a
r
d
&
N
T
P
C
s
p
e
c
D
i
m
e
n
s
i
o
n
a
l
c
h
e
c
k
a
n
d
P
a
i
n
t
s
h
a
d
e
,
t
h
i
c
k
n
e
s
s
,
a
d
h
e
s
i
o
n
&
F
i
n
i
s
h
c
h
e
c
k
s
C
o
m
p
l
e
t
e
p
h
y
s
i
c
a
l
e
x
a
m
i
n
a
t
i
o
n
f
o
r
c
o
n
s
t
r
u
c
t
i
o
n
a
l
f
e
a
t
u
r
e
s
a
s
p
e
r
N
T
P
C
a
p
p
r
o
v
e
d
d
r
g
s
&
s
p
e
c
i
f
i
c
a
t
i
o
n
T
e
m
p
e
r
a
t
u
r
e
R
i
s
e
T
e
s
t
o
n
o
n
e
u
n
i
t
o
f
e
a
c
h
r
a
t
i
n
g
i
f
T
y
p
e
t
e
s
t
i
n
g
i
s
w
a
i
v
e
d
o
f
f
R
i
p
p
l
e
C
o
n
t
e
n
t
T
e
s
t
,
L
o
a
d
L
i
m
i
t
e
r
&
A
V
R
O
p
e
r
a
t
i
o
n
T
e
s
t
D
y
n
a
m
i
c
R
e
s
p
o
n
s
e
T
e
s
t
O
p
e
r
a
t
i
o
n
a
l
&
F
u
n
c
t
i
o
n
a
l
C
h
e
c
k
s
H
V
&
I
R
T
e
s
t
B
u
r
n
-
I
n
T
e
s
t
a
t
5
0
^
C
f
o
r
4
8
h
r
s
i
n
e
n
e
r
g
i
s
e
d
c
o
n
d
i
t
i
o
n
A
l
t
e
r
n
a
t
i
n
g
c
u
r
r
e
n
t
m
e
a
s
u
r
e
m
e
n
t
t
e
s
t
D
e
g
r
e
e
o
f
P
r
o
t
e
c
t
i
o
n
T
e
s
t
a
s
p
e
r
N
T
C
P
S
p
e
c
.
Rectifier Transformer and
Reactors IS : 4540, 2026)
Y Y Y Y Y
Electronic Components
including Potentiometer
(Vernier Type)
Y Y Y
Electronic Cards Y Y Y
PCB & racks for electronic
cards
Y Y
Control & Selector
Switches (IS : 6875)
Y Y Y
Indicating Meters (IS :
1248 )
Y Y Y
Indicating Lamps (IS:
13947)
Y Y Y
Air Break Switches / Fuses
( IS : 13947 / 13703 )
Y Y Y
Control Terminal Blocks
(IS : 13947)
Y Y
Control Transformer
(IS : 12021)
Y Y Y
Push Buttons (IS : 4794) Y Y Y
MCB (IS : 8828) Y Y Y
PVC insulated Copper
control wires (IS : 694)
Y Y
Sheet Steel (IS : 513) Y Y Y
Synthetic Rubber Gaskets Y Y
Annunciator Y Y Y
Battery Charger Y Y Y Y Y Y Y Y Y Y Y
Notes:
1. This is an indicative list of tests / checks. The manufacturer is to furnish a detailed Quality Plan
indicating the practice and procedure along with relevant supporting documents.
2. Makes of all major Bought out Items will be subject to NTPC approval.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-12
L.T. INDOOR TRANSFORMER (DRY TYPE)
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-12
LT INDOOR
TRANSFORMER
(DRY TYPE)
PAGE 1 OF 1
L.T. INDOOR TRANSFORMER (DRY TYPE)
Attributes /
Characteristics
Items/Components
Sub Systems
V
i
s
u
a
l
&
D
i
m
e
n
s
i
o
n
a
l
c
h
e
c
k
M
e
c
h
a
n
i
c
a
l
p
r
o
p
e
r
t
i
e
s
E
l
e
c
t
r
i
c
a
l
s
t
r
e
n
g
t
h
T
h
e
r
m
a
l
P
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
P
r
o
p
e
r
t
i
e
s
N
D
T
/
D
P
/
M
P
I
V
o
l
t
a
g
e
R
a
t
i
o
,
V
e
c
t
o
r
G
r
o
u
p
&
P
o
l
a
r
i
t
y
M
a
k
e
/
T
y
p
e
/
R
a
t
i
n
g
/
M
o
d
e
l
/
T
C
/
G
e
n
e
r
a
l
P
h
y
s
i
c
a
l
I
n
s
p
e
c
t
i
o
n
W
P
S
&
P
Q
R
R
o
u
t
i
n
e
T
e
s
t
a
s
p
e
r
r
e
l
e
v
a
n
t
s
t
a
n
d
a
r
d
M
e
a
s
u
r
e
m
e
n
t
o
f
c
a
p
a
c
i
t
a
n
c
e
&
t
a
n
d
e
l
t
a
b
e
t
w
e
e
n
w
i
n
d
i
n
g
R
o
u
t
i
n
e
T
e
s
t
Enclosure door, H.V. &
L.V. Cable Box / Flange
Throat
Y Y Y
Copper Conductor Y Y Y Y
Insulating Material Y Y Y
CRGO Lamination & Built
Core
Y
Bushing / Insulator
(IS:2544 / 5621 / 2099)
Y Y Y
Gasket Y Y Y
Off-Circuit Tap Changer Y Y
Core Coil Assembly Y Y
Marshalling Box Y Y
WTI, Thermister, Terminal
Connector
Y Y
Welding Y
Complete Transformer
(IS:11171)
Y Y Y
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-13
ELECTRICAL ACTUATOR WITH
INTEGRAL STARTER
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC. NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-13
ELECTRICAL
ACTUATORS
PAGE 1 OF 2
ELECTRICAL ACTUATOR WITH INTEGRAL STARTER
Test/Attributes
Characteristics
ITEM/
COPONENT/
SUB SYSTEM
ASSEMBLY/
TESTING
R
P
M
N
o
L
o
a
d
C
u
r
r
e
n
t
I
R
&
H
V
T
e
s
t
M
o
u
n
t
i
n
g
D
i
m
e
n
s
i
o
n
A
l
l
r
o
u
t
i
n
e
T
e
s
t
a
s
p
e
r
S
t
a
n
d
a
r
d
&
S
p
e
c
i
f
i
c
a
t
i
o
n
C
o
r
r
e
c
t
P
h
a
s
e
S
e
q
u
e
n
c
e
O
p
e
r
a
t
i
o
n
&
S
e
t
t
i
n
g
o
f
l
i
m
i
t
S
w
i
t
c
h
/
T
o
r
q
u
e
S
w
i
t
c
h
S
t
a
l
l
T
o
r
q
u
e
/
C
u
r
r
e
n
t
(
A
)
H
a
n
d
W
h
e
e
l
o
p
e
r
a
t
i
o
n
/
A
u
t
o
d
e
c
l
u
t
c
h
f
u
n
c
t
i
o
n
(
A
)
F
u
n
c
t
i
o
n
o
f
A
u
x
.
l
i
k
e
P
o
t
e
n
t
i
o
m
e
t
e
r
,
s
p
a
c
e
h
e
a
t
e
r
,
p
o
s
i
t
i
o
n
i
n
d
i
c
a
t
o
r
E
P
T
o
u
t
p
u
t
G
r
e
a
s
e
l
e
a
k
a
g
e
L
o
c
a
l
/
R
e
m
o
t
e
(
O
p
e
n
-
S
t
o
p
-
C
l
o
s
e
)
O
p
e
r
a
t
i
o
n
S
a
f
e
t
y
c
h
e
c
k
(
S
i
n
g
l
e
p
h
a
s
i
n
g
,
P
h
a
s
e
c
o
r
r
e
c
t
i
o
n
,
T
r
i
p
p
i
n
g
e
t
c
.
)
(
A
)
ELECTRICAL
ACTUATOR WITH
INTEGRAL
STARTER(IS_9334)
Motor Y Y Y Y Y
Final Testing Y Y Y Y Y Y Y Y Y Y Y Y Y
Note: 1) Detailed procedure of Environmental Stress Screening test shall be as per
Quality Assurance Programme in General Technical Conditions
2) This is an indicative list of tests/checks. The manufacturer is to furnish a
detailed quality plan indicating the practices and procedure adopted along
with relevant supporting documents.
- Routine Test (A) - Acceptance Test Y - Test applicable
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-13
ELECTRICAL ACTUATORS
PAGE 2 OF 2
PROCESS CONTROL & PIPING
TESTS
ITEMS
V
i
s
u
a
l
G
A
,
B
O
M
,
L
a
y
o
u
t
o
f
c
o
m
p
o
n
e
n
t
&
c
o
n
s
t
r
u
c
t
i
o
n
f
e
a
t
u
r
e
D
i
m
e
n
s
i
o
n
P
a
i
n
t
S
h
a
d
e
/
t
h
i
c
k
n
e
s
s
F
l
a
t
t
e
n
i
n
g
,
f
l
a
r
i
n
g
,
h
y
d
r
o
t
e
s
t
,
h
a
r
d
n
e
s
s
c
h
e
c
k
a
s
p
e
r
A
S
T
M
s
t
a
n
d
a
r
d
(
A
)
C
o
m
p
o
n
e
n
t
R
a
t
i
n
g
s
W
i
r
i
n
g
M
a
k
e
,
M
o
d
e
l
,
T
y
p
e
,
R
a
t
i
n
g
I
R
&
H
V
R
e
v
i
e
w
o
f
T
C
f
o
r
i
n
s
t
r
u
m
e
n
t
/
d
e
v
i
c
e
s
(
R
)
A
c
c
e
s
s
a
b
i
l
i
t
y
o
f
T
B
s
/
D
e
v
i
c
e
s
I
l
l
u
m
i
n
a
t
i
o
n
,
g
r
o
u
n
d
i
n
g
T
u
b
i
n
g
L
e
a
k
/
H
y
d
r
o
t
e
s
t
(
A
)
C
h
e
m
i
c
a
l
/
p
h
y
s
i
c
a
l
p
r
o
p
e
r
t
i
e
s
o
f
m
a
t
e
r
i
a
l
(
A
)
P
r
o
o
f
p
r
e
s
s
u
r
e
t
e
s
t
,
D
i
s
m
a
n
t
l
i
n
g
&
r
e
a
s
s
e
m
b
l
y
t
e
s
t
,
H
y
d
r
u
l
i
c
i
m
p
u
l
s
e
a
n
d
v
i
b
r
a
t
i
o
n
t
e
s
t
(
R
)
T
e
s
t
s
a
s
p
e
r
s
t
a
n
d
a
r
d
s
&
s
p
e
c
i
f
i
c
a
t
i
o
n
Local Instrument enclosure Y Y Y Y Y Y Y Y Y Y Y Y Y
Local instruments racks Y Y Y Y Y Y Y Y Y Y Y Y Y
Junction Box Y Y Y Y* Y Y Y
Gauge Board Y Y Y Y Y Y Y Y Y
Impulse pipes and tubes Y Y Y Y Y
Socket weld fittings ANSI B-
16.11
Y Y Y Y Y
Compression fittings Y Y Y Y Y Y
Instrument valves & Valve
manifolds
Y Y Y Y Y
Copper tubings ASTM B75 Y Y Y
*-applicable for painted junction boxes.
Note: R-Routine Test A- Acceptance Test Y Test applicable
Note: This is an indicative list of tests/checks. The manufacturer is to furnish a detailed quality plan indicating the
Practices and Procedure adopted alongwith relevant supporting documents.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-14
AUXILIARY TRANSFORMER
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-14
AUXILIARY
TRANSFORMERS
PAGE 1 OF 2
AUX. TRANSFORMER
Attributes /
Characteristics
Items/
Components
Sub Systems
V
i
s
u
a
l
&
D
i
m
e
n
s
i
o
n
a
l
C
h
k
M
e
c
h
a
n
i
c
a
l
p
r
o
p
e
r
t
i
e
s
E
l
e
c
t
r
i
c
a
l
s
t
r
e
n
g
t
h
T
h
e
r
m
a
l
p
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
C
o
m
p
o
s
i
t
i
o
n
C
o
m
p
a
t
i
b
i
l
i
t
y
w
i
t
h
o
i
l
C
o
r
e
L
o
s
s
*
,
H
o
t
S
p
o
t
N
D
T
/
D
P
T
/
M
P
I
/
U
T
A
g
e
i
n
g
T
e
s
t
.
V
o
l
t
a
g
e
R
a
t
i
o
,
V
e
c
t
o
r
G
r
o
u
p
&
P
o
l
a
r
i
t
y
,
M
a
g
n
e
t
i
c
B
a
l
a
n
c
e
T
e
s
t
M
a
k
e
/
T
y
p
e
/
R
a
t
i
n
g
/
M
o
d
e
l
/
T
C
/
G
e
n
e
r
a
l
P
h
y
s
i
c
a
l
I
n
s
p
e
c
t
i
o
n
.
W
P
S
&
P
Q
R
R
o
u
t
i
n
e
T
e
s
t
a
s
p
e
r
r
e
l
e
v
a
n
t
t
e
s
t
R
o
u
t
i
n
e
T
e
s
t
Tank, H.V. & L.V.
Cable Box / Flange
throat
Y Y Y
Conservator /
Radiator / Cooler /
Pipes
Y Y Y
Copper Conductor
(IS:191)
Y Y Y Y
Insulating Material Y Y Y Y Y Y
CRGO Lamination &
Built Core
Y Y Y Y Y Y
Bushing / Insulator
(IS:2544 / 5621)
Y Y Y Y
Gasket Y Y Y Y Y
Transformer Oil
(IS:335)
Y
Off-Circuit Tap
Changer
Y Y
Core Coil Assembly
& Pre-tanking
Y Y
Marshalling Box Y Y Y Y
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-14
AUXILIARY
TRANSFORMERS
PAGE 2 OF 2
TRANSFORMER
Attributes /
Characteristics
Items/Compone
nts
Sub Systems
V
i
s
u
a
l
&
D
i
m
e
n
s
i
o
n
a
l
C
h
e
c
k
s
M
e
c
h
a
n
i
c
a
l
p
r
o
p
e
r
t
i
e
s
E
l
e
c
t
r
i
c
a
l
s
t
r
e
n
g
t
h
T
h
e
r
m
a
l
p
r
o
p
e
r
t
i
e
s
C
h
e
m
i
c
a
l
C
o
m
p
o
s
i
t
i
o
n
C
o
m
p
a
t
i
b
i
l
i
t
y
w
i
t
h
o
i
l
C
o
r
e
L
o
s
s
*
,
H
o
t
S
p
o
t
N
D
T
/
D
P
T
/
M
P
I
/
U
T
A
g
e
i
n
g
T
e
s
t
.
V
o
l
t
a
g
e
R
a
t
i
o
,
V
e
c
t
o
r
G
r
o
u
p
&
P
o
l
a
r
i
t
y
,
M
a
g
n
e
t
i
c
B
a
l
a
n
c
e
M
a
k
e
/
T
y
p
e
/
R
a
t
i
n
g
/
M
o
d
e
l
/
T
C
/
G
e
n
e
r
a
l
P
h
y
s
i
c
a
l
I
t
i
W
P
S
&
P
Q
R
R
o
u
t
i
n
e
T
e
s
t
a
s
p
e
r
r
e
l
e
v
a
n
t
t
e
s
t
V
a
c
u
u
m
&
P
r
e
s
s
u
r
e
T
e
s
t
R
o
u
t
i
n
e
T
e
s
t
WTI, OTI, MOG,
PRD, Breather,
Terminal
Connector,
Bucholz Relay,
Globe & Gate
Valve,
Y Y
Welding (ASME
Sect-IX)
Y Y
Complete
Transformer
(IS:2026)
Y Y
* Core Loss on first Job
Note:
1) This is an indicative list of tests / checks. The manufacturer is to furnish a detailed
Quality Plan indicating the practice and procedure along with relevant supporting
documents.
2) All major Bought Out Items will be subject to NTPC approval.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-15
MEASURING INSTRUMENTS
(PRIMARY AND SECONDARY)
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-15
MEASURING
INSTRUMENTS
PAGE 1 OF 2
MEASURING INSTRUMENTS (PRIMARY AND SECONDARY)
TESTS
ITEMS
D
i
m
e
n
s
i
o
n
s
(
R
)
M
a
k
e
,
M
o
d
e
l
,
T
y
p
e
,
R
a
t
i
n
g
(
R
)
P
r
o
c
e
s
s
/
E
l
e
c
t
r
i
c
a
l
c
o
n
n
e
c
t
i
o
n
(
R
)
C
a
l
i
b
r
a
t
i
o
n
(
R
)
T
e
s
t
a
s
p
e
r
s
t
a
n
d
a
r
d
(
R
)
I
n
s
u
l
a
t
i
o
n
R
e
s
i
s
t
a
n
c
e
(
R
)
I
B
R
C
e
r
t
i
f
i
c
a
t
i
o
n
(
i
f
a
p
p
l
i
c
a
b
l
e
)
(
R
)
H
y
d
r
o
T
e
s
t
(
R
)
M
a
t
e
r
i
a
l
T
e
s
t
c
e
r
t
i
f
i
c
a
t
e
1. PR Gauge (IS-3624) Y Y Y Y Y
2. Temp. Gauge (BS-5235) Y Y Y Y Y
3. Pr./D.P.Switch(BS-6134) Y Y Y Y Y Y
4. Electronic Transmitter(BS-6447 / IEC-
60770)
Y Y Y Y Y Y
5. Temp. Switch Y Y Y Y Y Y
6. Recorder(IS-9319/ANSI C-39.4) Y Y Y Y Y Y
7. Vertical indicators Y Y Y Y Y
8. Digital Indicators Y Y Y Y Y
9. Integrators Y Y Y Y
10. Electrical Metering Instrument (IS-
1248)
Y Y Y Y Y Y
11. Transducer (IEC-688) Y Y Y Y Y Y
12. Thermocouples (ANSI-MC-96.1) Y Y Y Y Y Y
13. RTD(IEC-751) Y Y Y Y Y Y
14. Thermowell Y Y Y Y Y
R-Routine Test A- Acceptance Test Y Test applicable
Note: 1) Detailed procedure of Environmental Stress Screening Test shall be as per
Quality Assurance Programme in General Technical Conditions
2) This is an indicative list of tests/checks. The manufacturer is to furnish a
detailed quality plan indicating the Practices and Procedure adopted
alongwith relevant supporting documents.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-15
MEASURING
INSTRUMENTS
PAGE 2 OF 2
TESTS
ITEMS
D
i
m
e
n
s
i
o
n
s
(
R
)
M
a
k
e
,
M
o
d
e
l
,
T
y
p
e
,
R
a
t
i
n
g
(
R
)
P
r
o
c
e
s
s
/
E
l
e
c
t
r
i
c
a
l
c
o
n
n
e
c
t
i
o
n
(
R
)
C
a
l
i
b
r
a
t
i
o
n
(
R
)
R
e
q
u
i
r
e
m
e
n
t
a
s
p
e
r
s
t
a
n
d
a
r
d
(
R
)
W
P
S
a
p
p
r
o
v
a
l
(
A
)
N
o
n
-
d
e
s
t
r
u
c
t
i
v
e
t
e
s
t
i
n
g
(
R
)
C
a
l
c
u
l
a
t
i
o
n
f
o
r
a
c
c
u
r
a
c
y
(
R
)
I
n
s
u
l
a
t
i
o
n
R
e
s
i
s
t
a
n
c
e
(
R
)
I
B
R
C
e
r
t
i
f
i
c
a
t
i
o
n
a
s
a
p
p
l
i
c
a
b
l
e
(
R
)
H
y
d
r
o
t
e
s
t
(
R
)
M
a
t
e
r
i
a
l
t
e
s
t
c
e
r
t
i
f
i
c
a
t
e
(
A
)
15. Cold junction
compensation box
Y Y Y Y Y
16. Orifice plate(BS-1042) Y Y Y Y
*
Y Y
**
Y
**
Y Y
**
Y
17. Flow nozzle(BS-1042) Y Y Y Y
*
Y Y Y Y Y Y
18. Impact head type element Y Y Y Y Y
19. Level transmitter/float type
switch
Y Y Y Y Y Y Y Y
20. Flue Gas analyser Y Y Y Y
21. Dust emission monitors Y Y Y Y
*Calibration to be carried out
on one flow element of each
type and size if calibration
carried out as type test same
shall not be repeated.
** If applicable
R-Routine Test A- Acceptance Test Y Test applicable
Note: 1) Detailed procedure of Environmental Stress Screening test shall be as
per Quality Assurance Programme in General Technical Conditions
2) This is an indicative list of tests/checks. The manufacturer is to furnish a
detailed quality plan indicating the Practices and Procedure adopted
alongwith relevant supporting documents.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-16
SAMPLING TESTING & QUALITY
ASSURANCE FOR CIVIL WORKS
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 1 OF 36
SAMPLING, TESTING AND QUALITY ASSURANCE FOR CIVIL WORKS
1.00.00 INTRODUCTION
1.01.00 This part of the specification covers the sampling, testing and quality assurance
requirement (including construction tolerances and acceptance criteria) for all civil
and structural works covered in this specification including excavation and filling,
cast in situ concrete and allied works, fabrication and erection of structural steel
works, masonry / sheeting and allied works, finishing items etc.
1.02.00 This part of the technical specification shall be read in conjunction with other Parts of
the technical specifications, general technical requirements & erection conditions of
the contract. Wherever IS code or standards have been referred they shall be the
latest revisions.
1.03.00 All tests required for all materials (bought by Contractor) and workmanship shall be
done / got done by the contractor at his own cost. The rate for respective items of
work or price shall include the cost for all works, activities, equipment, instrument,
personnel, material etc. whatsoever associated to comply with sampling, testing and
quality assurance requirement including construction tolerances and acceptance
criteria and as specified in subsequent clauses of this part.
2.00.00 QUALITY ASSURANCE PROGRAMME (QAP)
2.01.00 The Contractor shall adopt suitable Quality Assurance Programme (QAP) to ensure
that the equipments and services under the scope of contract whether manufactured
or performed within Contractors works or at his sub-Contractors premises or at the
Owners site or at any other place of work are in accordance with the specifications.
Such QAP shall be outlined by the Contractor and shall be finally accepted by the
Owner or his authorized representative after discussions before the start of work.
The QAP shall be generally in line with IS/ISO Systems. The QAP of the Contractor
shall generally indicate the following:
His organization structure for the management and implementation of the
proposed quality assurance programme
Quality System Manual
Design Control System
Documentation and Data Control System
Qualification data / details for Contractors key personnel.
The procedure for purchase of materials, parts, components and selection of
sub-contractors services including vendor analysis, source inspection,
incoming raw-material inspection, verification of materials purchased etc.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 2 OF 36
System for shop manufacturing and site erection controls including process,
fabrication and assembly.
Control of non-conforming items and system for corrective actions and
resolution of deviations.
Inspection and test procedure both for manufacture and field activities.
Control of calibration and testing of measuring testing equipment.
System for Quality Audits.
System for identification and appraisal of inspection status.
System for authorizing release of manufactured product to the Owner.
System for handling, storage and delivery.
System for maintenance of records, and
Quality plans for manufacturing and field activities detailing out the specific
quality control procedure adopted for controlling the quality characteristics
relevant to each item of work/ equipment/component.
3.00.00 SAMPLING, LABORATORY AND FIELD TESTING
3.01.00 The Contractor shall provide the facilities whatsoever required and also bear the cost
for all sampling, testing and quality assurance in the field and in the laboratory. The
Contractor shall carry out all sampling and testing in accordance with the relevant
Indian standards and / or international standards and this technical specification.
Where no specific testing procedure is mentioned, the tests shall be carried out as
per the best prevalent engineering practices and to the directions of the Engineer. All
sampling shall be done in the presence of the Engineer or his authorized
representative. The Contractor shall establish the QA&QC laboratory at site and all
field tests shall be done in the presence of the Engineer and / or his authorized
representative. The tests which cannot be carried out in the field laboratory shall be
done at a laboratory of repute such as CSMRS, NCBM, IITs, National Test House,
Kolkata etc. as agreed by the Engineer. The test samples for such test shall be jointly
selected and sealed by the engineer and thereafter these shall be sent to the
concerned laboratory through the covering letter signed by FQA representative of the
engineer. The cost of transportation and other associative cost including the test
charges shall be borne by the contractor. These cost shall deemed to be included in
the respective item of work in the contract. If the Engineer desires to witness such
tests at laboratory, Contractor shall arrange to conduct the test in his presence. At
least one set of mix design shall be carried out by contractor at NCB,Ballabgarh/
CSMRS, Delhi.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 3 OF 36
Before execution of any civil work the Contractor shall conduct full-scale suitability
tests on various construction and building material such as fine and coarse
aggregates, Cement, Reinforcement, construction chemicals, supplementary
cementitious Materials and Construction water to check their suitability for use from
reputed institutes such as NCB-Ballabhgarh, CSMRS-Delhi, IITs.
3.02.00 The recommendations and suitability of material for concreting and other building
materials like brick, cement, aggregates etc., shall be ascertained by contractor prior
to start of work.
Preliminary evaluation of aggregate and its evaluation for potential alkali-aggregate
reactivity as per following scope of work shall be done:-
A. Evaluation of Aggregates:
I. To carry out different tests on coarse aggregate sample i.e. specific
gravity, water absorption, sieve analysis, deleterious material;
soundness, crushing value, impact value, abrasion value, elongation
index and flakiness index, as per IS: 2386.
II. To carry out different tests on fine aggregate sample i.e. specific
gravity, water absorption, sieve analysis soundness, deleterious
material, silt content, clay content and organic impurities as per IS:
2386.
III. To prepare evaluation report based on test results of I) and II) above
and to advise regarding suitability of fine and coarse aggregates.
B. Evaluation of Aggregates for Potential Alkali-Aggregate Reactivity:
Evaluation for Potential Alkali-Aggregate reactivity as per following scope of
work:
I. To carry out petrographic analysis and accelerated Mortar bar Test on
aggregate samples (1N NaOH at 80 deg. Centigrade for 14 days as
per ASTM 1260, or the method established/ developed by CSMRS for
22days test).
II. To prepare a report based on test results of I) above and to advise
regarding suitability of aggregates and further testing required if any.
The contractor shall initiate the action with regard to the above mentioned evaluation
of aggregates and other building material, so as to ensure timely completion of these
tests thereby not affecting any project work. All records shall be submitted, unless
specified otherwise, as per the format developed by the Contractor and approved by
the Engineer.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 4 OF 36
3.03.00 The FQA laboratory set-up shall be constructed by the Contractor at his own cost at
site in line with the indicative field QA&QC laboratory set-up enclosed at Annexure-I.
The Laboratory building shall be constructed and installed with the adequate facilities
to meet the requirement of envisaged test setup. Temperature and humidity controls
shall be available wherever necessary during testing of samples. The Quality Plan
shall identify the testing equipments/ instrument, which the Contractor shall deploy
and equip the Field quality Laboratory for meeting the Field Quality Plan
requirements. The Contractor shall furnish a comprehensive list of testing
equipments/ instrument required to meet the planned/scheduled tests for the
execution of works for Owner acceptance/ approval. The contractor shall mobilize the
requisite laboratory equipment and QA&QC manpower at least 15 days prior to the
planned test activity as per the schedule of tests.
If any facility for testing or the trained personnel for conducting any special test is not
available with the Contractor then the Contractor may get the test done from reputed/
approved laboratory or out source the personnel as approved by Owner.
All equipments and instruments shall be calibrated before the commencement of
tests and then at regular intervals, as per the manufacturers recommendation and as
directed by the Owner. Contractor shall arrange for having the instruments/
equipments tested for their calibration at an NABL/NPL accredited agency and the
test report shall be submitted to the Owner.
Based on the schedule of work agreed with the Engineer-in-charge and the approved
FQP, the Contractor shall prepare a schedule of tests and submit them to the
Engineer-in-charge and organize to carry out the tests as scheduled/ agreed.
4.00.00 QA & QC MANPOWER
4.01.00 The Contractor shall appoint a dedicated, experienced and competent QA&QC in-
charge at site, preferably directly reporting to the Project Manager, supported as
necessary by experienced personnel, to ensure the effective implementation of the
approved QAP. An indicative structure of Contractors QA&QC manpower required to
be deployed at site is enclosed at Annexure-II. Based on the finalized L-2 network
and the approved Field Quality plan the Contractor shall finalize and submit a
deployment schedule of QA&QC personnel along with their details to Owner for
approval/ acceptance and further shall ensure their availability well before the start of
the concern activity.
The QA&QC in-charge shall have the organizational freedom and authority to
implement the requirements of these quality assurance arrangements, free from
commercial and programme restraints. The QA&QC setup of the Contractor shall
consist of qualified and experienced Civil, Electrical, Mechanical Engineers and
Laboratory assistants with their supporting staff both at their works and site.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 5 OF 36
4.02.00 The deployment of man power for QA & QC set up shall be affected on the basis of
agreed manpower deployment schedule, which shall be prepared by the contractor
based on the L-2 network and the same shall be submitted to the Engineer-in-charge
for acceptance.
5.00.00 FIELD QUALITY PLAN (FQP) AND MANUFACTURING QUALITY PLAN (MQP)
5.01.00 Well before the start of the work, the Contractor shall prepare the Field Quality Plans
(FQP) and obtain approval of Owner, which shall detail out for all the works,
equipments, services, quality practices and procedures etc in line with the
requirement of the technical specifications to be followed by the Contractor at site.
This FQP shall cover for all the items / activities covered in the contract/schedule of
items and required right from material procurement to completion of the work. The
Field Quality Plan (FQP) submission shall be furnished on the format No. QS-01-QAI-
P-09/F2-R1 for Owner approval. An Indicative Field Quality Plan for civil works is
enclosed at Annexure IV.
5.02.00 All materials / components and equipment covered under the scope of work, shall be
procured by the Contractor for the purpose of the contract, after obtaining the written
approval of the Owner, which are to be manufactured at shop/ factory of the
vendor/sub vendor shall be covered under a comprehensive quality assurance
programme. The Contractors purchase specifications and inquiries shall call for
Manufacturing Quality Plans (MQP) to be submitted by the sub-contractor/ sub-
supplier/ sub-vendor. The MQPs called for from the sub-contractor shall detail out for
all the components and equipment-various tests/inspection, to be carried out as per
the requirements of this specification and standards mentioned therein, quality
practices and procedures followed by contractors/ sub-contractors/ sub-suppliers
Quality Control Organization, the relevant reference documents and standards,
acceptance norms, inspection documents raised etc., during all stages of materials
procurement, manufacture, assembly and final testing/performance testing. Such
quality plans of the vendors shall be submitted to the Owner for approval in the
prescribed format No. QS-01-QAI-P-09/F1-R1 for Manufacturing Quality Plan and
such approved Quality Plans shall form a part of the purchase order/contract between
the Contractor and sub-contractor. The Quality Plans shall be submitted on electronic
form e.g. CD or E-mail in addition to hard copy, for review and approval of Owner.
After approval the same shall be submitted in compiled form on CD in addition to
hard copy.
5.03.00 The Contractor shall furnish copies of the reference documents/plant standards
/acceptance norms/tests and inspection procedure etc., as referred in Quality Plans.
These Quality Plans and reference documents/standards etc. will be subject to
Owner approval without which manufacturer shall not proceed. These approved
documents shall form a part of the contract. In these approved Quality Plans, Owner
shall identify customer hold points (CHP), i.e. test/checks which shall be carried out in
presence of the Owner Engineer or his authorized representative and beyond which
the work shall not proceed without consent of Owner in writing. All deviations to this
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 6 OF 36
specification, approved quality plans and applicable standards must be documented
and referred to Owner along with technical justification for approval and
dispositioning.
5.04.00 With in three weeks of the release of the purchase orders /contracts for such bought
out items /components, a copy of the same without price details but together with the
detailed purchase specifications, quality plans and delivery conditions shall be
furnished to the Owner for reference/record by the Contractor along with a report of
the Purchase Orders placed so far for the contract.
5.05.00 Monthly progress reports on MQP/FQP submission/approval shall be furnished by the
Contractor on the format No. QS-01-QAI-P-02/F1-R0. List of items requiring Quality
Plans and Sub-supplier approval shall be finalized with the Contractor on the format
No. QS-01-QAI-P-01/F3-R1 during the post bid discussions.
6.00.00 BOUGHT OUT ITEMS (BOIs) AND SUB-VENDORS/ SUB-MANUFACTURERS /
SUB-SUPPLIERS
6.01.00 The Contractor shall enclose a comprehensive list of bought out items (BOIs)
envisaged in the contract for carrying out fabrication/ manufacturing/ erection/
construction/ commissioning activities etc and shall indicate the names of reputed
manufacturers for each of them in their bid proposal. The items envisaged by the
Contractor to be procured from these manufacturers shall meet the specification
requirement. Some of these major bought out items list (not exhaustive) is enclosed
at Annexure- III for which the Contractor shall submit the requisite details / lists of
manufacturers in their bid proposal.
6.02.00 The contractor shall identify the bought out items as per owners specification and
shall finalize the list of manufacturers/ vendors for each bought out items envisaged
in the contract during the post bid discussions stage. The BOIs shall conform to the
relevant IS/technical referred specifications for the highest quality/ grade of material
unless otherwise specified. All bought out items shall be procured from the
manufacturers approved by Owner and tested as per relevant IS Codes/Owner
Specification. To facilitate advance planning (well before the start of activity as per L-
2 network) of material testing/ approval of bought out items, representative samples
shall be procured by the Contractor (from approved vendors) and submitted to the
Engineer for his approval before bulk procurement at least two months prior to start of
works. In case of manufacturers test certificate is submitted for acceptance, it shall be
clearly traceable and correlated with the consignment received at site. Approval of
material / sample by the Engineer shall not relieve the Contractor of his responsibility,
for their conformance to the specification, as well as the requisite quality and
performance of material.
6.03.00 The list of manufacturers / sub-vendors of each of the BOIs identified / indicated by
the Contractor shall be discussed / reviewed by the Owner during post bid
discussions and the list of proposed manufacturers / sub-vendors for each of the BOI
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 7 OF 36
shall be agreed/ approved. The list of manufacturers for all the BOIs envisaged in
contract shall be included in the bid proposal and the same shall be discussed for
finalization during the post bid discussions before placement of award. Where the
manufacturers are placed in DR (Details required) category, the details of the
manufacturers / sub-vendors placed in the DR category shall be submitted to the
Owner for approval within the period agreed at the time of post bid discussions. The
Contractors proposal shall include vendors site facilities, expertise, facilities
established at the respective works, the process capability, process stabilization, QC
systems followed, experience list, etc. along with his own technical evaluation for
identified sub-Contractors proposed. The formats for furnishing above details shall be
given to the Contractor at post bid discussion stage. Monthly progress reports on
sub-Contractor detail submission / approval shall be furnished on format no. QS-01-
QAI-P-02/F1. The Owner shall furnish other relevant formats for information/
clarification for manufacturers / sub-vendors approval to the Contractor at the time of
post bid discussions (Main suppliers evaluation report Format No: QA-01-QAI-P-
04/F1-R0 and Sub supplier questionnaire Format no: QA-01-QAI-P-04/F2-R0). Such
manufacturers / sub-vendors approval shall not relieve the Contractor from any
obligation, duty or responsibility under the contract.
6.04.00 Structural Steel for site procurement shall be procured from main steel producers like
SAIL, TISCO, IISCO, RINL, Jindal Steels etc. In case some of the sections are not
available with main Producers and are proposed to be supplied from the re-rollers of
main steel producers, the name of such re-rollers will have to be cleared by corporate
quality assurance of NTPC for which details such as BIS approval, Main steel
producers approval, Past experience for production of sections of specified material,
details of machines plants testing facilities etc., confirmation that the process control
and manufacturing of steel sections by re-rollers shall be same as that of main steel
producers, that billets for re-rolling will be sourced from main steel producers only
shall be furnished with regards to re-roller.
Even after clearance of re-rollers, induction of billets with identified and correlated Mill
test certificates (TCs) in the process of re-rolling, sampling of steel, quality checks
thereof and stamping of final product for further identification and correlation with
TCs prior to dispatch will be in presence of authorised representative of main
Contractor.
Reinforcement steel shall be procured from main steel producers like SAIL, TISCO,
IISCO, RINL, Jindal Steels etc. and mill test certificates (TC) is to be obtained and
submitted to NTPC for co-relation. In case any size /diameter specified is not
available and are proposed to be supplied from the conversion agent of the main
Steel producer the name of such conversion agent / re roller shall have to be
approved by NTPC for which details such as BIS approval, Main steel producers
approval, Past experience for production of sections of specified material, details of
machines, plants testing facilities etc., and confirmation that the process control and
manufacturing of steel sections by re-rollers is the same as that of main steel
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 8 OF 36
producers, that billets for re-rolling are sourced from main steel producers only shall
be furnished with regards to re-roller.
7.00.00 STRUCTURAL STEEL WELDING REQUIREMENTS
7.01.00 The Contractor shall submit to the Owner Field Welding Schedule for field welding
activities in the format No.: QS-01-CQA-W11/F1, this format shall be furnished to the
Contractor at pre-award stage. The field-welding schedule shall be submitted to the
Owner along with all supporting documents, like welding procedures, heat treatment
procedures, NDT procedures etc. at least ninety days before schedule start of
erection work at site. The Contractor shall submit Welding Procedure Specification
(WPS) in the format No: QS-01-QAI-W-06/F1 for Owner approval/ acceptance, this
format shall be furnished to the Contractor during post bid discussion stage.
All welding and brazing shall be carried out as per procedure drawn and qualified in
accordance with requirements of ASME Section IX/BS-4870 or other International
equivalent standard acceptable to the Owner.
All welding/brazing procedures shall be submitted to the Owner or its authorized
representative for approval prior to carrying out the welding/brazing.
All brazers, welders and welding operators employed on any part of the contract
either in the Contractors/ sub-Contractors works or at site or elsewhere shall be
qualified as per AWSD1.1/ASME Section-IX or BS-4871 or other equivalent
International Standards acceptable to the Owner.
Welding procedure qualification and Welder qualification test results shall be
furnished to the Owner for approval. However, where required by the Owner, tests
shall be conducted in presence of Owner/authorized representative.
No welding shall be carried out on cast iron components for repair.
All the heat treatment results shall be recorded on time temperature charts and
verified with recommended regimes.
All Non-destructive examination shall be performed in accordance with written
procedures as per International Standards and as mentioned elsewhere in the
technical specification; The NDT operator shall be qualified as per SNT-TC-IA (of the
American Society of non-destructive examination). NDT shall be recorded in a
report, which includes details of methods and equipment used, result/evaluation, job
data and identification of personnel employed and details of co-relation of the test
report with the job. The records of RT (Films) and UT (inspection records or printed
reports if possible) shall be documented and produced to Owner.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 9 OF 36
8.00.00 QUALITY AUDIT
8.01.00 Owner reserves the right to carry out quality audit and quality surveillance of the
systems and procedures of the Contractors or their sub-Contractors quality
management and control activities.
The Contractor shall provide all necessary assistance to enable the Owner carry out
such audit and surveillance. The Contractor shall carry out an inspection and testing
Programme during manufacture in his work and that of his sub-Contractors and at
site to ensure the mechanical accuracy of components, compliance with drawings,
conformance to functional and performance requirements, identity and acceptability
of all materials parts and equipment. The Contractor shall carry out all
tests/inspection required to establish that the items/equipment conform to
requirements of the specification and the relevant codes/standards specified in the
specification, in addition to carrying out tests as per the approved quality plan.
8.02.00 Quality audit/surveillance/approval of the results of the tests and inspection will not,
however, prejudice the right of the Owner to reject the equipment/ facilities if it does
not comply with the specification when erected or does not give complete satisfaction
in service and the above shall in no way limit the liabilities and responsibilities of the
Contractor in ensuring complete conformance of the materials/equipment supplied to
relevant specification, standard, data sheets, drawings, etc.
9.00.00 GENERAL QA REQUIREMENTS
9.1.0 QA REQUIREMENTS FOR PROPERTIES, STORAGE AND HANDLING OF
COMMON BUILDING MATERIALS
1. All the materials like Bricks, Stones, Concrete Blocks, Lime, Cement, Water,
Aggregates, Sand, Reinforcement Steel, Structural Steel shall conform to the
relevant IS Codes/NTPC Technical Specification requirements.
2. All materials shall be stacked and stored by the Contractor as per IS-4082
and as per the requirements specified in NTPC Technical Specification.
3. All material shall be stacked separately.
4. Lime and cement shall be stored on a raised platform in Weather Proof, Dry &
Leak Proof Conditions stores.
5. Different consignment of different types of cement shall be stored separately
with clear identification mark.
6. Cement stored for more than 60 days in contractors godown shall be retested
to check their suitability for use.
7. Cement shall be consumed on first in first out basis.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 10 OF 36
8. Steel shall be stacked and stored consignment wise, on raised wooden
battens size wise and grade wise with identification mark.
9. For properties, storage and handling of all materials used shall comply to the
requirements of NTPC Technical Specification
10. The sheets/ packets(Profiled sheets for decking, roofing and cladding) shall
be stacked neatly clear off the ground at an angle to the ground, over a base
pallet to provide drainage.
11. The sheets/ packets(Profiled sheets for decking, roofing and cladding) must
be covered with water proof covering to protect from moisture rain and foreign
particles.
12. Water / moisture should not be allowed to stagnate on surface, or in between
layers of sheets/ packets(Profiled sheets for decking, roofing and cladding).
This can damage the coating , and cause corrosion.
9.2.0 QA REQUIREMENTS FOR SHEETING WORKS.
1. Colour coated sheet
i) Chemical & physical properties of raw material sheet as per relevant
codes.
ii) Bare Metal Thickness
iii) Thickness of coatings
iv) Type of coating/paint
v) Hardness of painted surface (2H pencil Hardness) (ASTM-D-3363)
vi) Flexibility Test (Bend test) as per IS-14246 ASTMD-328 at 180 degree
bends (twice the thickness of sheet). There should not be any crack.
vii) Dimensional check after profiling of sheets
viii) Salt spray test as per ASTM B-117/ IS:9844 for minimum 1000 hrs.
One sample per batch at random. (For true representative sampling,
three samples shall be taken from each batch out of which one sample
shall be sent for salt spray test .The batches shall be chosen at the
beginning of supply, another at the middle of supply and the third
towards the end of the supply)
ix) Cross hatch adhesion test as per IS: 14246
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 11 OF 36
2. Bonded Mineral Wool Insulation
a) Thickness
b) Density
c) Thermal Conductivity
d) All other tests as per IS-8183.
3. Sheeting Installation
a) Workmanship including alignment
b) Level, Slope
c) Side and End Laps
d) Proper Installation of Flashing
e) Fixing including opening,(No gas cut opening shall be allowed at the
site , whenever opening is specified these shall be properly cut in the
factory and shall be filled with lipping/flashing for true shape/
dimension etc.)
f) Location, Installation of Lining & Installation.
4. All bought out items shall be procured from the manufacturers approved by
Engineer-in - charge and tested as per relevant IS Codes/ Specification.
5. The sheets/ packets shall be stacked neatly clear off the ground at an angle to
the ground, over a base pallet to provide drainage.
6. The packets/ sheets must be covered with water proof covering to protect
from moisture rain and foreign particles.
7. Water / moisture should not be allowed to stagnate on surface, or in between
layers. This can damage the coating, and cause corrosion.
9.3.0 QA REQUIREMENTS FOR ACID/ALKALI RESISTANT LINING
1. Acid Resistant Bricks/Tiles shall be tested for Water Absorption, Compressive
Strength, Resistance to Acid, Flexural Strength, Dimensions and all other
tests as per IS-4860 and IS-4457.
2. Acid and Alkali Resistant Bitumastic ready mixed paint shall be tested for all
tests as per IS-158.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 12 OF 36
3. Bitumastic shall be tested as per IS-9510.
4. Potassium Silicate, Resin type and Sulphur type Mortars shall be tested as
per IS-4832, Part I, II and III.
5. Surface preparation shall be checked as per IS-2395.
6. Application of Primer, laying of Acid Proof Bitumastic layer, Acid/Alkali
Resistant Tiles/Bricks, Chemical Resistant Epoxy Lining and Epoxy Paint shall
be as per NTPC Technical Specification.
7. Thickness of Acid and Alkali Lining shall be checked.
8. Epoxy painting shall be carried for required coating thickness and dry film
thickness.
9.4.0 QA REQUIREMENTS FOR RCC PILES - BORED CAST-IN-SITU PILES
1. Standard Penetration Test (SPT) as per IS-2131 and NTPC Technical
Specification to determine the founding level of piles.
2. Founding level of the piles shall be decided based on the criteria given in
NTPC Technical Specification.
3. Check for control of position and alignment of piles as per IS-2911 Part I/Sec-
2
4. Boring & Drilling : Drilling mud shall be tested for the following
Liquid limit of drilling mud (Bentonite Slurry) as per IS-2720 Part V.
Sand content of Bentonite powder (shall not be greater than 7%).
Density of freshly prepared Bentonite suspension shall be checked in
each pile bore before concreting and it should be between 1.034 and
1.10 gm/ml depending upon the pile dimension and type of the soil in
which the pile is to be installed. However, the density of bentonite
suspension after getting mixed with deleterious material in the pile
bore may be up to 1.25 gm/ml.
Marsh viscosity (when tested by marsh cone shall be between 30 to 60
seconds).
Differential free swell index.
pH value of Bentonite suspension (shall be between 9 and 11.5).
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 13 OF 36
Properties of drilling mud shall be checked prior to commencement of the
piling work and thereafter, minimum once per week or as found necessary by
the engineer. One sample consisting of 3 specimens shall be tested for the
above.
5. Check cleaning of pile bore
6. Concreting: All the checks/tests on concrete and concrete materials shall be
carried out as per FQP and IS-2911 Part I/Sec.2
a) Before starting concreting the contaminated drilled mud at the (slurry
collected in sampler tube) bottom of pile bore shall be tested for
density and sand content. Density should not be more than
1.25T/CuM.
b) For Working Piles: Minimum one sample consisting of 6 test cubes
shall be made for first ten piles. Out of these 3 shall be tested for 7
days cube strength and 3 for 28 days cube strength. Minimum one
sample of 6 test cubes for every 25 nos. of piles shall be tested , out of
these 3 shall be tested for 7 days cube strength and 3 for 28 days
cube strength
7. Reinforcement bars used for concreting of piles shall be of tested quality and
conform to the requirements of relevant IS codes.
a) Check distances between two adjacent main reinforcement bars and it
should be as specified in Technical Specification.
b) Check proper cover and central placement of reinforcement cage in
the pile bore by suitable concrete spacers/rollers. Check minimum
clear cover to reinforcement should be as specified in technical
specification.
8. Check cut off level of piles as per drawing.
9. Check recording of all data during installation of piles in prescribed pile data
sheet.
10. Slumps of concrete shall be tested at every one-hour interval.
11. Checking position and Alignment: Each pile shall be checked for its position
w.r.t. Specified location. Each pile shall be checked for its alignment.
Permissible limits for deviation shall be as specified elsewhere in the
Technical Specification.
12. Check for Pile Bore: On completion of boring and cleaning, the bottom of each
pile bore shall be checked from the samples collected from near the bottom of
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 14 OF 36
pile bore or any other method approved by the Engineer, to ensure that it is
free from pile bore spoil/debris and any other loose material before
concreting.
13. Low strain pile integrity test on all job piles and test piles shall be conducted
as specified in the Technical Specification. This test shall be suitably used to
identify the piles for routine tests.
14. High Strain dynamic test shall be done as per the technical specification. The
frequency of the test shall be as per the BOQ /technical specification.
9.5.0 QA REQUIREMENTS FOR RCC PILES LOAD TEST ON RCC PILES
1. Pile load testing shall conform to IS-2911 (Part IV) and the Technical
Specification.
2. Check all the equipment and instrument used are properly calibrated.
3. Initial load test shall be conducted to assess the safe load carrying capacity of
pile before start of work.
a) Cyclic vertical (compression) load test to assess safe vertical load
capacity.
b) Lateral load test to assess safe horizontal load capacity.
c) Pull out (Tension) load test to assess safe pull out load capacity.
4. Routine Load Test shall be conducted on Working Piles, to verify their load
carrying capacity.
a) Direct Vertical (Compression) load test for vertical load capacity.
b) Lateral load test for horizontal load capacity
5. All other tests on piles shall be carried out as specified in Technical
Specification.
6. Pile load-testing procedure and the test setup/scheme to be submitted for
approval from NTPC. The contractor shall use the test setup having
arrangement for reaction piles for both vertical compression and uplift
(tension) Load test (initial) on piles. The cost of reaction system/ piles shall
deem to be included in the cost of test piles.
7. All the gauges(pressure etc.) and the instruments shall be calibrated before
the start of the tests on test piles and working piles and the calibration record
shall be verified before start of execution of the test.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 15 OF 36
9.6.0 QA REQUIREMENTS FOR PRE CAST CONCRETE WORKS
1. All the materials used in Pre cast Concrete work shall be tested and conform
to the requirements of IS codes and NTPC Tech. Specification. If the material
of the cast-in-situ concrete is already tested and part of the same is used for
precast concrete, further testing is not required, otherwise testing is required
for every 50 Cum. Of Concrete.
2. Concrete mix for Pre cast members shall conform to IS-456-2000 i.e. the
provisions of IS:456 shall apply.
3. All relevant QA requirements pertaining to cast in situ concrete shall be
applicable.
4. Load test on Pre cast members shall be carried out for the type of members
as decided by NTPC Engineer as per IS-456-2000.
5. Pre Cast Concrete member shall be checked for dimensions (length, cross
sectional dimensions, straightness, squareness, and flatness) and tolerances
shall be as per NTPC Technical Specification.
9.7.0 QA REQUIREMENTS FOR PLASTERING & ALLIED WORKS
1. Materials like sand, lime for preparation of putty, coarse aggregate, gypsum
etc. shall confirm to the relevant IS codes specified in NTPC Technical
Specification.
2. Check proper mixing of mortar
3. Plaster surface shall be checked for following defects and the remedial
measures for the same shall be adopted as per IS-1661.
a) Blistering
b) Bond filer or loss of adhesion.
c) Cracking and crazing
d) Efflorescence
e) Grinning
f) Irregularity of Surface Texture
g) Popping or blowing
h) Recurrent surface dampers
i) Softness or chalkiness
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 16 OF 36
4. Trueness of Plastering System:
Finished plaster surface shall not show any deviation more than 4mm when
checked with straight edge of 2 Mt. length.
5. Check thickness of plaster.
9.8.0 QA REQUIREMENTS FOR CONCRETING
All records of concreting, reinforcement, testing of materials, as-built dimensions, the
details of the rectification, etc, shall be maintained as given below. Copies of such
record shall be submitted to owner for their record and future reference.
a) Testing data / report of aggregates
b) Mix design details.
c) Testing records of admixture including dosage, workability and setting time.
d) Approved scheme for concreting.
f) Hourly records of concreting including pour card.
g) Protocol indicating the dimensional tolerance and details of inserts.
h) Bar bending schedule.
i) Location and details of mechanical anchoring used for reinforcement.
j) Protocol giving the details of checking of reinforcements before concreting
and conformance to the reinforcement details as shown in the construction
drawings.
k) Report on petrographic examination & potential reactivity of aggregate
l) All tests/checks shall be carried out as per FQP.
In addition to the above the following may also be ensured
i. Check temperature control of fresh concrete during hot weather.
ii. Plasticizer cum Retarder type mixture to be added in the concrete shall be
tested as per IS-9103/ ASTM C 494.
iii. REINFORCEMENT :
a) Check conformity of material to relevant IS codes.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 17 OF 36
b) Check lapping/spacing of Reinforcement staggered as under no
circumstances more than 50% of bars at cross section shall be lapped.
iv. Sample test for mechanical bars grips shall be carried out upto the yield
strength of reinforcement of bars. The no. of tests to be carried out shall be
3% of the no. of bar grips used subject to a minimum of three.
v. Batching Plant shall be calibrated regularly at least once in a 3 months and
computerized output shall be taken for each batch of production of concrete.
The calibration if the batching plant shall be done by NABL accredited
laboratories/weights of NPL traceability.
vi. All precautions and control as specified in NTPC Technical Specification shall
be taken care of during concreting. IS 456-2000 shall be applicable for
acceptance of execution of concrete works & test results.
STAGING AND FORM WORK
Automatic climb form scaffolding systems shall be used. Slipform with
proven record for similar towers may be used subject to IS specific approval of
the owner. The design and detailed construction of the form work and the
scaffolding system shall be as described elsewhere in the technical
specification and shall be submitted to NTPC for approval.
Concrete shall have sufficient strength to with stand the anchoring loads of
scaffolding system. The concrete strength shall be continuously checked and
documented during the climbing process of the scaffolding.
Design and execution of the form work , staging, shuttering and scaffolding
shall conform to National Safety Council and all relevant IS Code provisions,
i.e. IS 2750, IS:4014, IS:4923, IS:800 etc. In case the IS Codes do not cover
the specific type of shuttering system, then any international Code of Practice,
as approved by the engineer, may be followed.
Deployment of vertical laser ray equipment for measuring the dimensions and
controlling the shape of the tower at all elevations and plan angles shall be
carried out.
9.9.0 QA REQUIREMENTS FOR STRUCTURAL STEEL WORK
9.9.1 Site Fabricated:
1. Physical and chemical properties of material as per relevant codes. Review
of correlated Mill Test Certificates or check testing in absence of MTC.
2. Ultrasonic test on plates above 40mm as per ASTM A435.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 18 OF 36
3. Welding Procedure & Welders Qualification Test as per ASME Section
IX/AWS D1.1
4. Fillet Welds:
a) Check for size and visual examination.
b) Microetch examination on production test coupons for main fillet welds
with minimum one joint per built up beams, columns and crane girder
etc.
c) 25% weld length of tension member of crane girder shall be subjected
to Dye Penetration Test.
d) On all other fillet welds, DPT on 5% of weld length with minimum
300mm at each location shall be carried out.
5. Butt Welds:
a) DPT on all butt welds after back gouging
b) Mechanical testing of production test coupons with minimum one joint
per built up beam, column and crane girder.
c) 100% radiography test on butt welds of tension flange (bottom flange)
of crane girder. All other butt welds shall be subjected to Radiography
test on 10% weld length of each welder. Wherever RT is not feasible,
UT shall be carried out.
d) Full penetration welds (other than butt welds) shall be subjected to
Ultrasonic Testing in following quantum :
i) 100% UT on web to flange joint of crane girder.
ii) 10% UT on other full penetration joints.
6. Every 1
st
and further every 10
th
set of identical structure shall be checked for
control assembly in shop before erection.
7. All structure components/members shall be checked for dimensional
tolerances during fabrication and erection as per IS-7215 and IS-12843
respectively.
8. Check for Surface Preparation and Paint thickness.
9. In case of failure of any welds in SPOT RT/UT, the %age for retesting shall
be doubled at that particular location. Acceptance criteria of NDT on welds
shall be as per AWS D1.1.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 19 OF 36
10. Low hydrogen electrode (AWS E-7018) for welding of High/Medium tensile
steel, for M.S (IS 2062 Gr. A/Gr. B, IS 8500) sections thickness above 20mm
shall be used. Preheating and Post weld heat treatment requirements shall be
complied as specified in the technical specs. /approved WPS.
9.9.2 Shop Fabricated:
In addition to requirement of Clause 9.9.01 above following provisions shall also
apply:
1. Sub-Vendor approval having requisite manufacturing facilities shall be
required from NTPC.
2. Manufacturing Quality Plan indicating stage inspection/CHP shall be
submitted for NTPC review and approval.
3. Pre-dispatch inspection shall be carried out inline with the approval MQP and
the dispatch shall be effected through MDCC.
4. Raw Material including plates and structural shall be procured from the
manufacturers as identified in the contract with MTC and co-relable
traceability.
9.10.0 ARCHITECTURAL & MISC. WORKS
1. Material used for floor finishes and allied work shall conform and tested as per
the requirements of relevant IS Codes specified in NTPC Technical
Specification.
2. Finishes shall be checked for the following:
Level, Slope, Plumb
Pattern & Symmetry
Alignment of joints, dividing strips etc.
Colour, Texture
Surface Finish
Thickness of Paint
Details of edges, junction etc.
Performance
Precautions specified for durability.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 20 OF 36
3. For fabricated item like metal doors, windows, ventilators, louvers, rolling
shutters and grills etc. The following checks shall be carried out.
Overall Dimensions
Mullions Transoms
Doors & Windows shall operate without jamming
Doors, windows & frames etc. shall be on a true plane, free from wrap
or buckle.
All welds shall be dressed flush on exposed and contact surfaces.
Correctness of locations and smoothness of operation of all shop
installed hardware and fixtures.
Provision of hardware & fixtures to be installed at site.
Glazing beads shall be cut with mitered corners.
Glazing clips, fixing devices etc. shall be supplied in adequate nos.
Shop coats shall be properly applied.
Exposed aluminium surface shall be free from scratches, stains and
discoloration.
9.11.0 ROLLING SHUTTERS/GRILLS
After installing the shutters, the contractor shall test the performance of the shutter in
the presence of the engineer. The shutter shall be smoothly operable under all
ambient conditions. All controls and locking devices shall give fault free performance.
9.12.0 FIRE PROOF DOORS
1. Fire Proof doors shall be tested for the requirements mentioned in IS-3614
Part-I&II and The Technical Specification. The type test of the doors shall be
carried out at CBRI Roorkee for minimum 2 hours fire rating and its
Fabrication drawing shall also be approved by CBRI, Roorkee.
2. DFT of paint of Fire Proof Doors and its fittings and fixtures as per BOQ shall
be checked. The doors shall be finished with suitable fire retardant painting
system.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 21 OF 36
9.13.0 GLASS AND GLAZING
1. Materials used in glass and glazing shall conform to the requirements of the
Technical Specification and IS Codes specified in the Technical Specification.
2. All installation shall be free from cracked, broken or damaged glass, edges of
large panes of thicker glass and heat insulating glass be inspected carefully
for chipped, cracked or underground edges.
3. Glazing shall be carefully done to avoid direct contact with metal frames.
4. All glasses shall be embedded in mastic for steel works and fixed by
neoprene gasket for aluminium works to give a leak proof installation.
5. On completion, the panes shall be free from dirt, stains, excess putty etc. to
the complete satisfaction of the engineer.
9.14.0 ROOF WATER PROOFING & ALLIED WORKS
1. Material used shall be tested and conforms to the requirements of IS
Codes/International Codes specified in NTPC Technical Specification.
2. All elastomeric membrane is fully dried to perform testing with water ponds
created on minimum 5% of area of nominal size 6m x 6m for height of 25mm
to 30mm at critical locations for a period of 48 Hrs. No dampness shall be
visible on the underneath side of roof (i.e. ceiling, parapet and wall junction
etc.). The above testing shall be carried out prior to application of wearing
course.
9.15.0 PAINTING & ALLIED WORKS.
1. Various materials used shall conform and tested for the requirements of
Indian/International Codes specified in the Technical Specification.
2. Surface to receive paint shall be prepared as per the requirement of technical
specification.
3. Painting shall be checked for thickness of different coats as specified in
schedule of items and the Technical Specification/Drawing.
10.00.00 CONSTRUCTION TOLERANCE AND ACCEPTANCE CRITERIA
10.1.0 Excavation and Filling
Tolerance
Finished surface level shall be within 20mm of the level shown in the drawing.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 22 OF 36
Acceptance Criteria
Following acceptance criteria shall be followed.
a) When only one set of sample is tested, then all individual samples collected
and tested should pass without any deviation
b) For retest of any sample two additional samples shall be collected and tested,
and both should pass without any deviation.
c) Where a large number of samples are tested for a particular test then 9
samples out of every 10 consecutive samples tested shall meet the
specification requirement.
d) Tolerance on finished levels for important filling areas at approved interval
shall be + 20mm. However, for an unimportant area, tolerance upto +75mm
shall be acceptable at the discretion of the Engineer. However, these
tolerances shall be applicable for localised areas only.
10.2.0 Cast-in-situ concrete and Allied works
10.2.01 Tolerances
a) Cast-in-situ concrete
Unless otherwise specified, the tolerance in construction shall be as follows:
The dimensions of concrete as cast when compared with those on the
drawings shall be within the tolerance given below:
-----------------------------------------------------------------------------------------------------------------
Description of Item/ Structural Element Max Min
(mm) (mm)
-----------------------------------------------------------------------------------------------------------------
Faces of concrete in foundations
and structural members against which
back fill is placed +25 -10
Eccentricity of footing 2% of footing width in
the direction of placement
but limited to 50mm
Top surfaces of slabs and of concrete
to receive base plates to be grouted +5 -5
Alignment of beams, lintels, columns,
walls, slabs and similar structural
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 23 OF 36
elements +5 -5
Cross sectional dimensions of walls,
slabs and similar structural elements +5 -5
Deviation from specified dimensions
of cross-section of columns and beams +12 -6
Alignment of holding down bolts without
sleeves +1.5 -1.5
Alignment of holding down bolts with
sleeves +5 -5
Level of holding down bolt assemblies +10 -10
Embedded Parts ( in any direction). +5 -5
Level of embedment for equipment
support +1.5 0
Level of embedment for other
embedded parts +5 -5
Centers of pockets or holes
with greatest lateral dimension not
exceeding 150mm +10 -10
Variation in steps
Riser +1.5 +3.0
Tread -1.5 -3.0
(b) Reinforcement
Tolerance on placing of reinforcement and for cover shall be as per clause
12.3 of IS: 456.
Reinforcement shall be placed within the following tolerances:
a) For effective depth 200 mm or less 10mm
b) For effective depth more than 200 mm 15mm
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 24 OF 36
Tolerance for cover
Actual concrete cover should not deviate from the required nominal cover by +
10 mm
(c) Pre cast concrete
Tolerance on dimensions of pre-cast units shall be as follows:
1. Length: +/- 0.1 percent subject to minimum of +/- 5 mm and maximum
of + 10 mm.
2. Cross-sectional dimensions: +/- 3 mm or +/- 0.1 percent whichever is
greater.
3. Straightness or Bow: 1/750 of the length subject to minimum of +/- 5
mm and maximum of +/- 10 mm.
4. Squareness: When considering the squareness of the corner the
length of the two adjacent sides being checked shall be taken as the
base line. The shorter side shall not vary in length from the
perpendicular by more than 5 mm.
5. Flatness: The maximum deviation from a 1.5m straight edge placed in
any position on a nominal plant surface shall not exceed 5 mm.
(d) Formwork and staging
(i) Staging shall be checked for its soundness as a whole and for
adequacy of the joints and its foundations. Formwork joints shall be
inspected for soundness of connections. All joints shall be either
vertical or horizontal and shall be such as to avoid loss of liquid
through the formwork.
(ii) Dimensional tolerance for formwork shall be as per Clause 9.6 of IS :
14687 and 11.1 of IS : 456, which is reproduced as given below:
Deviation from specified dimensions of :
cross section of columns and beams : +12mm - 6mm
Deviation from dimensions of footings :
1) Dimensions in plan: + 50mm - 12 mm
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 25 OF 36
2) Eccentricity: 0.02 times the width of the
footing in the direction of
deviation but not more than
50 mm
3) Thickness 0.05 times the specified
thickness
The above tolerances apply to concrete dimensions only, and not to
positioning of vertical reinforcing steel or dowels.
(iii) Checklist for formwork shall be as per Clause 9.9 of IS : 14687.
Format as per Annexure-C of IS : 14687 shall necessarily be made for
all important structures including all machine foundations.
11.2.2 Acceptance Criteria
(a) The acceptance criteria of concrete shall be in accordance with clause no.16
of IS : 456. However in exceptional circumstances, and that too in non-critical
areas, the Engineer may accept concrete work which is marginally
unacceptable as per the criteria laid down in IS : 456. For such accepted
work, payment shall be made at a reduced rate pro rate to the concrete cube
strength obtained, against that stipulated.
(b) Unacceptable concrete work shall be dismantled by the Contractor and
replaced by fresh work, meeting the specification requirements. In the course
of dismantling, if any damage is done to the embedded items or adjacent
structures, the same shall be made good, by the Contractor, to the
satisfaction of the Engineer, at no extra cost to the Owner.
(c) Test shall be conducted for the water tightness of the liquid retaining
structures as per IS : 3370 and IS : 6494.
10.3.0 Fabrication and Erection of Structural Steel Work
10.3.1 Tolerances
I. Fabrication tolerances
(a) maximum permissible gap in built up members
(b) maximum permissible deviation in depth and/or width of girder at the
joints
(c) maximum permissible out-of-square of flanges in built-up girders
(d) tolerances on length of beams and girders and their components
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 26 OF 36
(e) permissible deviation in column heights
All tolerances for above shall be as per drg / IS : 7215
II. Erection tolerances
(a) permissible tolerances in erected steel columns
(b) permissible tolerances in erected steel trusses
(c) permissible tolerances in crane girder and rails
All tolerances for above shall be as per approved drg / IS : 12843
III. Requirement of pre-heating
Thickness of thickest
part at the area of
welding / heat affected
zone
Welding using other
than low hydrogen
welding electrodes IS
: 2062
Welding using low
hydrogen welding
electrodes or submerged
arc welding IS:2062
Upto 20 mm (including) None None
Over 20 mm to 40 mm
(including)
Not allowed 20
0
C
Over 40 mm to 63 mm
(including)
Not allowed 66
0
C
Over 63 mm Not allowed 110
0
C
11.3.2 Acceptance Criteria
(a) The acceptance criteria of Non Destructive Testing (NDTs) on welds shall be
as per AWS D1.1 (Dynamically Loaded Structures - tension welds). In case of
failure of any of the tests, the Contractor at his own cost shall also carry out
rectification of such defective welds. Retesting of the rectified joint, shall also
be carried out by the Contractor at his own cost.
(b) Every 1
st
and further every 10
th
set of identical structure shall be checked for
control assembly in shop before erection.
Embedded part
The tolerances for embedded parts shall be as specified under concrete works.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 27 OF 36
10.4.0 Masonry & Allied works
11.4.1 Tolerances
(a) All masonry shall be built true and plumb within the tolerances prescribed as
below. Care shall be taken to keep the perpends properly aligned. Unless
specified otherwise the tolerances in construction of masonry works shall be as
below:
i) Deviation in verticality in total height of any wall of a building more than
one storey in height shall not exceed 12.5mm.
ii) Deviation from vertical within a storey shall not exceed 6mm per 3m
height.
iii) Deviation from the position shown on the plan of any brickwork more
than one storey in height shall not exceed 12.5mm.
iv) Relative displacement between load bearing walls in adjacent storeys
intended to be in vertical alignment shall not exceed 6mm.
v) Deviation of bed joint from horizontal in any length upto 12m shall not
exceed 6mm, and in any length over 12m it shall not exceed 12.5mm
total.
vi) Deviation from the specified thickness of bed-joints, cross-joints or
perpends shall not exceed 3mm.
b) The plastered surface shall be checked for
i) Blistering, bond failure or loss of adhesion, cracking, crazing,
efflorescence, grinning, irregularity of surface texture, popping or
blowing, recurrent surface dampness, softness or chalkiness defects
and the remedial measures for the same shall be adopted as per IS:
1661.
ii) The finished plastered surface shall not show any deviation more than
4 mm when checked with a straight edge of 2 metre length placed
against the surface.
iii) The thickness of the plaster shall be measured exclusive of the
thickness of key i.e., grooves or open joints in brickwork. The average
thickness of plaster shall not be less than the specified thickness. The
minimum thickness over any portion of the surface shall not be less
than the specified thickness by more than 3 mm for plaster thickness
above 12mm and 1 mm for ceiling plaster. Extra thickness required in
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 28 OF 36
dubbing behind rounding of the corners at junctions of wall or in
plastering of masonry cornices etc. shall be ignored.
11.4.2 Acceptance Criteria
Following acceptance criteria shall be followed:
General workmanship is being good and as recommended by the manufacturer
and approved by the Engineer.
Tolerances are within the specified limit.
Material test certificate is in compliance with the applicable codes/standards.
Bought out material is from the approved manufacturer / vendor.
Bought out material is matching with the approved sample.
10.5.0 Finishing & Allied works
11.5.1 Tolerances
a) The floor finish shall be checked specially for the following :
i.) Level, slope, plumb as the case may be
ii.) Pattern and symmetry
iii.) Alignment of joints, dividing strips etc.
iv.) Colour, texture
v.) Surface finish
vi.) Thickness of joints
vii.) Details of edges, junction etc.
viii.) Performance
ix.) Precautions specified for durability
Local depressions on account of faulty workmanship shall not be acceptable.
Tiles / natural stones with cracked or broken/chipped edges shall not be
acceptable.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 29 OF 36
b) The door, window, ventilator, partition during and after fitting and fixing etc
shall be checked for the following:-
i) Installation shall be at correct locations, elevations and in general on a
true vertical plane.
ii) Fixing details shall be strictly as shown on drawings.
iii) Assembly of composite units shall be strictly as per drawing, with
mastic caulking at transoms and mullions, gaskets, weather strips etc.
complete.
iv) All frames on external wall shall be mastic caulked to prevent leakage
through joint between frames and masonry.
v) All openable sections shall operate smoothly without jamming. Lock,
fasteners, etc, shall engage positively. Keys shall be non-
interchangeable.
vi) Cutting to concrete or masonry shall be made good and all abrasions
to shop paint shall be touched up with paint or same quality as shop
paint.
vii) Aluminium doors, windows, ventilators, partitions etc., shall be free
from scratches, stains or discolouration.
viii) Door and window shutters shall operate without jamming. The
clearance at head and jamb for door shutters shall not exceed 1.5 mm.
For double leaf doors, the gap at the meeting stiles shall not be more
than 2.5 mm.
10.6.0 For False ceiling system the following shall be checked for :-
i) As installed shall be true to shape, level.
ii) Correctness for the opening for the fixtures, colour and shade.
iii) All joints shall be in the same line and cross joints shall be securely fixed to
walls.
iv) There shall not be any sagging and/ or unevenness in the surface
11.6.1 Acceptance criteria
Ceiling panels shall be best quality material in thickness and properties called for in
the specification /schedule of items. Material Test Certificate to be submitted before
bulk supply.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 30 OF 36
Finished ceiling shall be at the correct plane and prevent an aesthetically pleasing
and uniform appearance, free from sags and warps. Joints and exposed grids shall
be in true lines and symmetrically placed in manner as shown in drawings. Cut outs
for light fixtures, diffusers and other relevant services shall be of exact dimensions
and in exact locations.
11.7.0 Water proofing
Water proofing shall be tested for water tightness by creating a pond of water
minimum 25 mm height on area of 6 m x 6 m, for the period of 48 hrs on fully dried
elastomeric membrane surfaces. Minimum 5% area of the roof shall be subjected to
water tightness test. Such test necessarily be conducted on vulnerable areas like
drain channel/ drain head. No dampness shall be visible on the underneath side of
roof (i.e. ceiling), parapet and wall junctions etc. which have been subjected for
testing. The above testing shall be carried out prior to application of wearing course.
11.8.0 Water Supply, Drainage & Sanitation
11.8.1 Tolerances
a) All soil pipes, waste pipes, ventilating pipes and all other pipes, when above
ground, shall be gas tight. All sewers and drain laid below ground shall be
watertight.
b) Obstruction / Straightness Test
The obstructions shall be checked by inserting a smooth ball, of diameter 13
mm less than the pipe bore at the high end of the sewer or drain. If absence
of any obstructions, such as yarn or mortar projecting through the joints, ball
shall roll down the invert of the pipe and emerge at the lower end. The
straightness shall be checked by means of a mirror at one end of the line and
lamp at the other. If the pipeline is straight, the full circle of the light may be
observed. The mirror will also indicate obstruction in the barrel, if the pipeline
is not straight.
c) Service pipes testing with water
The service pipes shall be slowly and carefully charged with water, allowing
all air to escape avoiding all shock or water hammer. The service pipe shall
then be inspected under working condition of pressure and flow, when all
draw off taps are closed. The service pipes shall be checked for satisfactorily
support and protection from damage corrosion and frost.
d) Fixtures etc.
All fixtures and fittings shall be connected by watertight joints. No dripping of
water shall be acceptable.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 31 OF 36
11.8.2 Acceptance Criteria
Following acceptance criteria shall be followed:
General workmanship is being good and is recommend by the manufacturer and
approved by the engineer.
Tolerances are within the specified limit.
Material test certificate is in compliance with the applicable IS Codes.
Bought out material is from the approved manufacturer / vendor.
Bought out material is matching with the approved sample.
12.00.00 QA REQUIREMENTS FOR ROAD WORK
Quality Assurance and testing requirements for roadwork shall be as per relevant
IRC Codes for Road .
13.00.00 SPECIAL ITEMS
1. Vibration Isolation System(V.I.S)
Stiffness values shall be checked. The permissible deviation shall be
as per DIN 2096.
For accepting values , following acceptance criteria shall be followed:
1. General workmanship is being good and as recommended by
the manufacturer and approved by the Engineer.
2. Tolerances are within the specified limit.
3. Material tests certificate (M.T.C.) is in compliance with the
applicable codes standards.
4. Bought out material is from the approved manufacturer /
vendor.
5. Bought out material is matching with the approved sample.
14.00.00 ASSOCIATED DOCUMENT FOR QUALITY ASSURANCE PROGRAMME:
14.01.00 Indicative list of Field Quality Laboratory and Survey equipment list (Annexure-I)
14.02.00 Indicative QA&QC Manpower requirements (Annexure-II)
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 32 OF 36
14.03.00 Indicative list of Bought Out Items for Civil Works (Annexure III)
14.04.00 Indicative Field Quality Plan for Civil and structural steel works (Annexure-IV) Note:
The field quality plans attached is indicative and minimum required. However any
addition or deletion in the scope of work, during detailed engineering shall be
accordingly added/ deducted from the indicative Field Quality Plan)
14.05.00 Field Quality Plan Format No.: QS-01-QAI-P-09/F2-R1
14.06.00 Manufacturing Quality Plan Format No.: QS-01-QAI-P-09/F1-R1
14.07.00 Status of items requiring Quality Plan and sub supplier approval. Format No.: QS-01-
QAI-P-02/F1-R0
14.08.00 List of items requiring quality plan and sub supplier approval. Format No.: QS-01-
QAI-P-01/F3-R0
14.09.00 Field Welding Schedule Format No.: QS-01-CQA-W-11/F1-R0
14.10.00 Welding Procedure Specification (WPS) Format No.: QS-01-QAI-W-06/F1-R0
14.11.00 Main suppliers evaluation report Format No: QA-01-QAI-P-04/F1-R0
14.12.00 Sub supplier questionnaire Format no: QA-01-QAI-P-04/F2-R0
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 33 OF 36
TYPICAL QA/QC LAB EQUIPMENT ANNEXURE - I
INDICATIVE FIELD QA&QC LABORATORY SET-UP
S. No Equipment Nos
1. Standard sieve analysis setup along with the sieve G.I.
frame , Motorized sieve shaker, Pans and Covers etc.
1 Set
2. Slump Testing Equipment - Slump test mould, temping
rod etc.
2 Set
3. Compression test for concrete cubes and bricks Cube
moulds, compression testing machine, cylinders,
temping rods, laboratory concrete mixer etc.
1 Set
4. Le-chatelier apparatus, Viacat apparatus, balance,
standard weights, gauging trowel
1 Set each
5. Rebound Hammer for NDT testing of concrete 1 Set
6. Thermostatically controlled laboratory Electric ovens
and Portable ovens.
1 Set each
7. Physical balances and Electronic balances. 1 Set each
8. Micro Meter, Vernier Calipers 1 Set each
9. Mhos scale for hardness test 1 Set
10. Electrical moisture meter (IS 287) for timber test 1 Set
11. Digital Elco-meter for paint thickness 1 Set
12. Standard Proctor test set-up and Core cutters for in-
situ density test set-up
1 Set each
13. NDT tests on welding DPT set-up, UT and RT (with
BARC approved source) set-up
1 Set each
14. Computerized Seismographs for blast vibration
monitoring, if required
1 Set each
15. Glass Jar, sedimentation pipette, Measuring Cylinders,
Containers, Evaporating dish, steam bath, desiccators,
muffle furnace, chemicals etc.
As required
16. Thermometer, Steel rules, Measuring wedge for bricks
etc.
As required
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 34 OF 36
NOTE:
1. The equipments listed above are indicative and required to be mobilised as
minimum requirement. Additional equipment if any, required for successful
completion of work shall be provided /arranged by the contractor.
2. All test reports/ inspection reports have to be computerized and maintained on
LAN with an access to the owner
3. Computers - 2 Nos shall be deployed with Windows operating system and
connected to the NTPC server
4. Based on the schedule (L2/L3 Network), Quality control & Quality Assurance
work plan shall be finalized by the contractor and the same shall be submitted
to the engineer-in-charge for acceptance/approval. The Finalized work plan
shall be maintained on the computer to be accessed by the owner for
database and day to day monitoring.
5. The CC may indicate the tests proposed to be outsourced, if any, to be
conducted at NTPC approved third party laboratories such as NCB, CSMRS,
IITs etc.
6. All laboratory / measurement / survey equipments to be used at site shall be
calibrated by NABL/NPL accredited laboratory / agency.
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 35 OF 36
Annexure II
INDICATIVE FIELD QA & QC MANPOWER STRUCTURE
NOTE:
1. The above organization setup is minimum, however their deployment shall be as per the agreed
deployment schedule. The contractor shall prepare a manpower deployment schedule in line
with the finalized L2 network the same shall be submitted to the engineer-in charge for
acceptance/ approval.
2. The contractor shall mobilize the QA& QC manpower in line with the finalized manpower
deployment schedule and shall ensure their availability well in advance (15 days approx.) of the
beginning of the concerned activity/ work.
3. The contractor shall further mobilize required number of skilled & supporting staff and additional
resources, if any to meet the work schedule.
4. All the areas / activities shown above shall headed by experienced and qualified engineers
supported by sufficient numbers of supervisors and supporting staff. The bidder shall indicate
the number of engineers and supervisors in their bid, which shall be discussed and finalized
before award of package.
PROJECT MANAGER
QA & QC MANAGER
QC ENGINEER-IN-CHARGE
QA&QC
LABORATORY
IN-CHARGE
CONCRETE & BUILDING MATERIALS
EVALUATION/ TESTING, CONCRETE
MIX DESIGN, PRODUCTION, AND
PLACING AND OTHER MISC WORKS-
CIVIL ENGINEERS
NDT ENGINEERS FOR STRUCTURAL
STEEL WORK R.T. LEVEL- II, UT
LEVEL-II NDT ENGINEERS
QUALITY ASSURANCE
DOCUMENTATIO
N- QAP, FQP,
MQP, MONTHLY/
QUARTERLY
REPORTS ETC.
CO-ORDINATION
AND
INTERACTION
WITH NTPC AND
SUB-
CONTRACTORS
TEST ON
BOUGHT OUT
ITEMS
THIRD PARTY
LABORATORY
SUPPROTING FIELD
AND LAB.STAFFF
SUPPROTING STAFF
EXCAVATION, FILLLING,
FOUNDATIONS, PILING -
GEOTECHNICAL ENGINEERS
CLAUSE NO.
QUALITY ASSURANCE
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
TECHNICAL SPECIFICATIONS
SECTION VI, PART-B
BID DOC NO.:CS-0260-156-2(R)
SUB-SECTION-IIIE-16
SAMPLING TESTING
FOR CIVIL WORKS
PAGE 36 OF 36
Annexure III
Indicative List of Bought Out Items for Civil Works
Sr.
No.
Bought Out Item Proposed Make Proposed list of
Manufacturers
1. Structural steel and
reinforcement steel
2. Cement
3. Doors including fire proof
doors, windows, ventilators,
partitions, louvers, rolling
shutters, etc
4. Finish paints etc
5. Concrete Admixtures,
chemical injection grouting,
waterproofing chemicals etc.
6. Permanently Colour Coated
Sheets
7. PVC Water stops
Note:
The bidder shall furnish the list of manufacturers of each bought out items in their bid,
which shall be reviewed and finalized during the post bid discussions with the
successful bidder.
NTPC TAMIL NADU ENERGY CO LTD.
POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BIDDING DOCUMENT NO.: CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART-B
PART - B
SUB-SECTI ON-I I I E-17
INDICATIVE FIELD QUALITY PLAN
Page 1 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
1 GENERAL REQUIREMENTS
A Setting up of Field QA&QC laboratory
As agreed / required
A Physical Once prior to start of work SR Functioning of laboratory equipment in proper
working condition to be verified on monthly basis
B Avialablility of requisite laboratory set
up and equipment in good working
condition well before
commencement of concerned activity
As agreed / required
A Physical Once prior to start of
work and thereof monthly
SR
C Submission of QA & QC manpower
deployment schedule based on
agreed L-2 network .
- A Physical Once prior to start of
work
D Availability of QA& QC manpower
based on deployment schedule .
- A Physical Once prior to start of
work and thereof monthly
SR
E Sampling for testing of buliding
materials, concrete mix design etc. As agreed / required
A Physical Once per each source SR/TR Test report along with the recommendations from
specialist agency to be submitted to NTPC.
F Submission of schedule of tests to be
done monthly / quaterly and
maintenace of the same on a
computer connected to LAN of NTPC
for monitoring
- A Physical Once prior to start of
work and thereof monthly
SR
2
2.1 Nature, type of soil/rock before and during
excavations
As agreed / required
B Visual Random in eah shift SR
2.2 Initial ground level before start of
excavations
As agreed / required
B Measurement 100% SR
2.3 Final shape and Dimensions of
excavations.
As agreed / required
B Measurement 100% SR
2.4 Final excavation lelvels As agreed / required B Measuement 100% SR
2.5 Side slope of final excavation As agreed / required B Measurement Random in eah shift SR
2.6 Excavation in Hard Rock- If required
i Receipt, Storage, accountability of
Explosive
As agreed / required
B Physical Random in each week SR
ii Execution of Blasting Operation As agreed / required B Physical Random in eah shift SR
iii Submission of Blasting report to EIC As agreed / required C Physical Each blast
2.7 Excavation in Hard Rock (Blasting
Prohibited)
As agreed / required
B Physical 100% SR
2.8 A
Suitability
As agreed / required
B Visual Randon in each shift
2.8 B
i Grain size analysis Set of Seives,
Hydrometer etc.
B Physical One in every 2000 cum
for each type and source
of fill materials subject to
a min. of 2 samples
SR/TR
The parameters should not be worse than the
parameter of the existing soil in plant area
ii Liquid & plastic limit Mechanical liquid limit
device, grooving tools,
Evaporating
Disc,Spatula, Palette
knives, Balance oven
containers, etc.
B Physical One in every 2000 cum
for each type and source
of fill materials subject to
a min. of 2 samples
SR/TR
The parameters should not be worse than the
parameter of the existing soil in plant area
Excavations-
Fill/ Backfill -
Suitability of borrow fill material- Applicable in case the earth is brought from an area, out of the NTPC aquired land area
Suitability of borrow fill material - If earth is brought from area within the NTPC acquired area
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
EXCAVATION AND FILLING IN FOUNDATION WORKS
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Indian Explosive Act 1940/all statutory
norms, Tech Specs and Const. Drawings
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
IS:4081, Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
As per approved drawing/ scheme, Tech
Specs and Const. Drawings
As per technical specifications
IS:2720 (Pt.IV), Tech Specs and Const.
Drawings
IS:2720 (Pt.IV) , Tech Specs and Const.
Drawings
NTPC approved specialist blasting agency such as
CMRI, NIRM shall be deployed at site for trial
blasts, design blasts, blast vibration monitoring etc.
Seismographs shall be deployed at site for
monitoring of blast operation vibrations.
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
NTPC TAMIL NADU ENERGY CO LTD. POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BID DOC. NO.:CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART - B
SUB-SECTION-IIIE-17
INDICATIVE FIELD QUALITY PLAN 1 of 21
Page 2 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
iii Shrinkage limit -do- B Physical One in every 5000 cum
for each type and source
of fill materials subject to
a min. of 2 samples
SR/TR
The parameters should not be worse than the
parameter of the existing soil in plant area
iv Free Swell Index Measuring cylinders,
etc.
B Physical One in every 5000 cum
for each type and source
of fill materials
SR/TR
The parameters should not be worse than the
parameter of the existing soil in plant area
v Chemical Analysis
a Organic Matter Oven chemical
balance, volumetric
flasks, burettes,
pipettes, conical flasks,
set of seives, measuring
cylinders etc.
B Physical One in every 5000 cum
for each type and source
of fill materials
SR/TR
b Calcium carbonate Reagents and
indicators,Burette,flasks
,funnels etc.
B Physical One in every 5000 cum
for each type and source
of fill materials
SR/TR
c pH value
As agreed / required
B Physical One in every 5000 cum
for each type and source
of fill materials
SR/TR
d Total soluble sulphate
As agreed / required
B Physical One in every 5000 cum
for each type and source
of fill materials
SR/TR
2.9 Standard proctor Test Optimum moisture content and max. dry
density before fill
As per IS: 2720, Proctor
needle apparatus,etc.
A Physical One in every 2000 cum
for each type and source
of fill materials
SR/TR
2.10 Moisture content Moisture content of fill before compaction As per IS: 2720,
balance, oven etc.
A Physical One in every 2000 cum
for each type and source
of fill materials
SR/TR
2.9
i) For foundation fill/
backfill one for every 10
foundations for each
compacted layer.
SR/TR
ii) For area filling, one
every 1000 SQM area for
each compacted layer.
SR/TR
ii Relative density (Density Index) As per IS: 2720,
balance oven etc.
A Physical ----do----- (i) & (ii) above SR/TR
iii Dry Density by proctor needle penetration As per IS-2720, proctor
nedle apparatus etc.
B Physical Random checks to be
carried out for each
compacted layer
SR/TR
3.0 CAST-IN-SITU CONCRETE
MATERIALS
3.1 CEMENT
i Storage in weather tight covered area on
raised platform.
as per IS: 4082 B Visual 100% covered storage SR/LB
ii Retesting for compressive Strength &
setting time if stored for more than 60
days in site shed
Vicat Apparatus,
standard sand
compression testing
machine etc.
A Physical At Random Test
Report
3.2 Coarse Aggregate
Degree Of Compaction Of Fill if borrowed from outside plant area / Backfill
IS 2720 (Pt. XXIX), Tech Specs and Const.
Drawings
i Dry density by core cutter method
---- OR----
Dry density in place by sand displacement
method
As per IS:
2720/compaction test
(core cutter), balance
etc.
A Physical
Each consignment of cement shall be duly
correlated with Manufacturers TC.
In case the cement is supplied by the contractor
random sample from each lot of delivery shall be
tested for Setting time and Compressive strength.
Acceptance norms shall be as per relevant IS
Tech Specs and Const. Drawings
Part XXIII of IS-2720, Tech Specs and
Const. Drawings
IS:2720 (Pt.IV), Tech Specs and Const.
Drawings
IS:2720 (Pt.XI), Tech Specs and Const.
Drawings
IS:2720 Pt.XXII, Tech Specs and Const.
Drawings
Tech Specs and Const. Drawings
IS 2720 (Pt. XXVIII), Tech Specs and
Const. Drawings
Tech Specs and Const. Drawings
IS 2720 (Pt. XIV), Tech Specs and Const.
Drawings
IS 2720 (Pt.II), Tech Specs and Const.
Drawings
IS 2720 (Pt.VII), Tech Specs and Const.
Drawings
Part XXVI of IS-2720, Tech Specs and
Const. Drawings
Part XXVII of IS-2720, Tech Specs and
Const. Drawings
NTPC TAMIL NADU ENERGY CO LTD. POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BID DOC. NO.:CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART - B
SUB-SECTION-IIIE-17
INDICATIVE FIELD QUALITY PLAN 2 of 21
Page 3 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
i Moisture content . B Physical Once for each stack of
100 Cum. or part there of
Except during monsoon
when this has to be done
every day before start of
concreting
SR/LB Accordingly water content of the concrete will be
adjusted
ii Specific gravity, bulk density, voids, water
absorption,
Balance, seives
(conforming to IS:460-
1962) etc.
B Physical Once for each source &
for every change of
source
SR/LB/
Test
Report
These tests will be carried out white establishing
design mix and the results to be intimated to
NTPC.
iii Particle, size & Shape-(Sieve analysis,
determination of material finer than 75
micron, flakiness index, elongation index,
angularity number)
Seives, balance oven ,
thickness guage ,length
gauge metal scoop etc.
B Physical One per 100 cum., or
part thereof/change of
source whichever is
earlier
SR/LB -do-
iv Deleterious materials & organic impurities
(determination of clay lumps, fine silt, fine
dust , light weight pieces , soft particle &
estimation of organic impurities.)
Balance, seives
(conforming to IS:460-
1962) etc.
B Physical Once per source/ on
every change of source
SR/LB/
Test
Report
Experts opinion regarding suitability of the
aggregates shall be obtained from the specialist
agency such as NCB BallbhGarh etc. finalised
during preaward. Results will be reported nearest
to 0.1% of clay lumps.
v Soundness reagents (sodium
sulphate or magnesium
sulphate )etc
B Physical Once per source/ on
every change of source
SR/LB/
Test
Report
Experts opinion regarding suitability of the
aggregates shall be obtained from the specialist
agency such as NCB BallbhGarh etc. finalised
during preaward.
vi Alkali aggregate reactivity scales, weight, sieves,
glass graduates, mixing
bowl, trovel, container,
length comparetor, etc
B Physical Once per source/ on
every change of source
SR/LB/
Test
Report
the quantity of dissolved silica , and reduction in
alkalinity to be reported and hence the aggregate
type (deleterious/innocuous) result should be
supported by petrographic examination
vii Petrographic examination screens , hand lens,
microscope etc
B Physical Once per source/ on
every change of source
SR/LB/
Test
Report
Reporting of petrographic examination shall be
done as illustrated in IS 2386 ( part-VIII)-1963.
petrographic report shall be supported by the
analysis and recommendation by a specialist
instute.
viii Crushing value abrasion value and impact
value
standard apparatus for
these tests shall be
used
B Physical Once per source/ on
every change of source
SR/LB/
Test
Report
-do-
ix Repeated Temp, Cycle Test of Aggregate
As agreed / required
B Physical Once per source/ on
every change of source
Test
Report
Applicable for Aggregate used in TG, BFP. Fan &
Mills Foundations. To be carried out at NIRM and
their expert opinion to be sought.
3.3 Fine Aggregate
i Bulkage/ moisture content balance , oven etc B Physical To be done every day
before start of work
SR/LB/
TR
Volume of sand and weight of water shall be
adjusted as per bulkage & moisture content.
ii Silt, Clay content and organic impurities
As agreed / required
B Physical Once per source& for on
every change of source
SR/LB/
TR
Acceptance limit as per relevant IS code
iII All other tests similar to coarse
aggregates as mentioned above.
As agreed / required
B As above Refer S.No. 2.01.02 SR/LB/
TR
IS: 2386 Part-V, IS:383 , Tech Specs and
Const. Drawings
No residual expansion, , Tech Specs and
Const. Drawings
IS: 2386 Part-III IS:383 , Tech
Specs and Const. Drawings
IS: 2386 Part-VIII, IS:383 , Tech Specs and
Const. Drawings
IS:383, IS-2386 Part IV/, Tech Specs and
Const. Drawings
IS:2386 Part-III, IS : 456, IS : 383/Tech
Spec, Tech Specs and Const. Drawings
IS-2386, IS-383, Tech Specs and Const.
Drawings
IS: 2386 Part-II, IS:383 , Tech Specs and
Const. Drawings
IS:2386 Part-I, IS : 456, IS : 383/Tech
Spec, Tech Specs and Const. Drawings
IS:2386 Part-II, IS : 456, IS : 383/Tech
Spec, Tech Specs and Const. Drawings
IS: 2386 (Part-VII), IS:383 , Tech Specs
and Const. Drawings
IS:2386 Part-III, IS : 456, IS : 383/Tech
Spec, Tech Specs and Const. Drawings
NTPC TAMIL NADU ENERGY CO LTD. POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BID DOC. NO.:CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART - B
SUB-SECTION-IIIE-17
INDICATIVE FIELD QUALITY PLAN 3 of 21
Page 4 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
3.4 Water
i Test for sulphates and chlorides Buret, conical flask,
pipette etc
B Testing Once per each source
thereof quarterly.
SR/LB/
TR
ii Tests for ascertaining limit of solids
As agreed / required
B Physical Once per each source
thereof quarterly.
SR/LB/
TR
iii Tests for pH Value pH meter B Testing Once per each source
thereof quarterly.
SR/LB/
TR
iv Initial set time for used water and distilled
water
Vicat appratus A Physical See Remarks See
Remarks
In case of doubt regarding development of
strength,. Initial set time with used water and
the distiled watershould meet the requirements of
clause 5.4.1.3 of IS 456
v Compressive strength of concrete with
used water and distilled water
Standard sand and
compression testing
machine
A Physical See Remarks See
Remarks
In case of doubt regarding development of
strength,. Compressive strength with used
water and the distiled water should meet the
requirements of clause 5.4.1.2 of IS 456
3.5 CONCRETE
i Proportions of materials for nominal mix
concrete As agreed / required
B Physical Random in each shift SR/LB/
Test
Report
ii Trial mix (Cubes compressive strength) as
per Mix Design
As agreed / required
A Physical Min. 4 Trial Mixes with
admixtures and Without
admixtures With fly ash.
SR/LB/
Test
Report
For trial mix min. of 6 cubes for each mix, 3
specimen shall be tested at 7 days remaining 3
shall be for 28 days comp. Strength. Mix design
shall carried out at agency finalised during pre
award )
iii Crushing strength (works Tests cubes)
As agreed / required
A Physical One set of 6 cubes per
50 M3 or part thereof for
each grade of concrete
per shift whichever is
earlier.
SR/LB/
Test
Report
Min. of 6 cubes for each mix, 3 specimen shall be
tested at 7 days remaining 3 shall be for 28 days
comp. Strength.
iv Workability - slump test Standard appratus for
different method used
for measuring
workability
B Physical One sample every 2 hrs.
from every mixing plant
SR/LB/T
R
Slump test for medium and high workability,
Compaction factor test for medium and low
workability, V.B. test for low to Very low workability
v Cement content
As agreed / required
B Physical At random at the time of
batching.
SR/LB
vi Admixtures for Concrete from approved
sources
As agreed / required
A Review of MTC Random in each shift Test
Report
Admixture of appd. Brand and tested quality shall
be used.
vii Water Tightness Test for Water Retaining
Structures As agreed / required
A Physical Each Structure Inspectio
n Report
viii Dimensions and visual exa-mination of
finished structure
As agreed / required
B Physical/ visual 100% SR
3.6 CONCRETE CONVEYING, PLACING& COMPACTION
i Mixing of concrete mixing of concrete shall be done in a
approved mixer such as to produce a
homogenous mix
To be calibrated at the
time of starting and
subsequently once in
three months, and shall
confirm to IS:4925
time of mixing will be as given in IS 457
ii Calibration of Batching Plant batcher should comply
with reqirement of IS
457
A Physical To be calibrated at the
time of starting and
subsequently once in
three months, and shall
confirm to IS:4925
TR
iv
3.8 REINFORCEMENT STEEL
i Physical and Chemical Properties for
each lot as per relevant IS codes
As required/ agreed A Review of MTC Each batch of delivery MTC
ii
Acceptance of installation of Aluminium
Composite Panel Cladding
As agreed / required
B Physical Each installation SR
Installation shall be done by specialist agency
18.5
Acid/ Alkali Resistance Treatment
i
Check for acid/ alkali resistance materials
- Bricks, vitreous tiles, mortar, sealing,
paints, coatings, sheets, fillers etc
As agreed / required
A Physical and MTC
Review
Each batch of delivery SR/MTC
ii Check for surface preparation As agreed / required B Physical Random in each shift
iii Acceptance of each type of installation As agreed / required B Physical Each installation SR DFT shall be checked for paints, coats
Tech Specs and Const. Drawings, IS
12436, IS 13204, IS 8183
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Free from defect , Tech Specs and Const.
Drawings Tech Specs and Const. Drawings,
Relevant IS 3043
Tech Specs and Const. Drawings, IS 4860,
IS 4457, IS 4832
Tech Specs and Const. Drawings, IS 2395
Tech Specs and Const. Drawings
As per relevant IS and Tech. Specs /
Manufacturer's TC, IS 3043
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings, IS 73, IS
383
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
No gas cutting of sheets acceptable . Profile
sheets will be kept covered in weather proof
storage &stored at accurate height to avoid any
exposure of actual water. Principle of first in and
first out shall be apply for erecting the sheets.
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
Tech Specs and Const. Drawings
NTPC TAMIL NADU ENERGY CO LTD. POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BID DOC. NO.:CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART - B
SUB-SECTION-IIIE-17
INDICATIVE FIELD QUALITY PLAN 12 of 21
Page 13 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
19.00 ROAD WORKS
19.1 Construction of Sub-Grade and
earthen/hard soulders
i Standard proctor Test to determine
optimum moisture content and max. dry
density
As per IS: 2720, Proctor
needle apparatus,etc.
A Physical One in every 2000 cum
for each type and source
of fill materials
SR/TR
In cutting or existing levelled ground - quantum of
check shall be one per 1000 SQM
ii Moisture content of fill before compaction
As per IS: 2720,
balance, oven etc.
B Physical One in every 2000 cum
for each type and source
of fill materials
SR/TR
In cutting or existing levelled ground - quantum of
check shall be one per 1000 SQM
iii Dry density by core cutter method
---- OR----
Dry density in place by sand displacement
method
As per IS:
2720/compaction test
(core cutter), balance
etc.
A Physical One in every 500 SQM
area for each compacted
layer.
SR/TR
Both for embankment and cut formation quantum
of check - One in every 1000 SQM area for each
compacted layer.
19.2 Water Bound Macadam (Non-
Bituminous) for base course and
sub-base course
i Aggregate Impact value Agrregate Impact value
Test Apparatus
A Physical One test per 200 cum of
Test aggregate
SR
ii Grading
Set of IS Sieves
B Physical One test per 100 cum of
aggregate
SR
iii Flakiness index and elongation index
Flakiness test gauge
B Physical One test per 200cun of
agregate
SR
iv Atterberg Limits of binding material Atterberg limits
determination
A Physical One test per 25 cum of
binding material
SR
v Atterberg Limits of portion of agreggate
passing 425 micron sieve
Atterberg limits
determination
A Physical One test per 100cum of
aggregate
SR
vi Standard proctor Test to determine
optimum moisture content and max. dry
density
As per IS: 2720, Proctor
needle apparatus,etc.
A Physical One in every 2000 cum
for each type and source
of fill materials
SR
vii Moisture content of fill before compaction
As per IS: 2720,
balance, oven etc.
B Physical One in every 2000 cum
for each type and source
of fill materials
SR
viii Dry density by core cutter method
---- OR----
Dry density in place by sand displacement
method
As per IS:
2720/compaction test
(core cutter), balance
etc.
A Physical For area filling, one every
1000 SQM area for each
compacted layer.
SR
19.3 Bituminous Macadam for base and
binder course
i Quality of binder
Penetrometre with St.
needle
A Physical No. of samples per Lot &
tests as per IS:73, IS:217,
IS:8887 as applicable
SR
ii Aggregate Impact Value / Los angeles
abrasion value
Aggregate Impact
ValueTest apparatus
A Physical One test per 50 cum of
aggregate
SR
iii Flakiness Index and elongation index of
aggregates Flakiness test gauge
B Physical One test per 50 cum of
aggregate
SR
iv Stripping value of aggregate (Immersion
tray test)
As required / agreed
B Physical Initialy one set of 3
representative specimen
per source, and on every
change of source.
SR
v Water sensitivity of mix
As required / agreed
A Physical Initialy one set of 3
representative specimen
per source, and on every
change of source.
SR
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification, IS
2720 (Pt. XXIX)/ IS 2720 (Pt. XXVIII),
As perTech Specs and Const. Drawings,
Section 900 of MORTH specification,
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification, IS 73
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
IS 2720 (Pt.VII), Tech Specs and Const.
Drawings,Section 900 of MORTH
specification
IS 2720 (Pt.II), Tech Specs and Const.
Drawings, Section 900 of MORTH
specification
IS 2720 (Pt. XXIX)/ IS 2720 (Pt.
XXVIII),Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As perTech Specs and Const. Drawings,
Section 900 of MORTH specification,
As perTech Specs and Const. Drawings,
Section 900 of MORTH specification,
As perTech Specs and Const. Drawings,
Section 900 of MORTH specification,
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const.
Drawings,Section 900 of MORTH
specification, IS 2720 (Pt.VII)
As perTech Specs and Const. Drawings,
Section 900 of MORTH specification,
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification, IS
2720 (Pt.II)
NTPC TAMIL NADU ENERGY CO LTD. POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BID DOC. NO.:CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART - B
SUB-SECTION-IIIE-17
INDICATIVE FIELD QUALITY PLAN 13 of 21
Page 14 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
vi Grading of aggregates
Set of Sieves
B Physical Two test per day per
plant both on individual
constituents and mixed
aggregate from drier
SR
vii Water absorption of aggregate
As required / agreed
Initially one set of 3
representative specimen
per source, and on every
change of source.
SR
viii Soundness ( Magnesium and Sodium
Sulphate) As required as per
IS:2386
A Physical Once per source by each
method and on every
change of source
SR
ix Percentage of fractured faces
As required / agreed
B Physical When gravel is used one
test per 50cum of
aggregates
SR
x Binder content and aggregate grading
Bitumen extractor
A Physical Periodic, subject to a min
of two tests per day per
plant
SR
xi Control of Temperature of binder and
aggregate for mixing and of the mix at the
time of laying and rolling
Thermometer
B Physical At regular close intervals SR
xii Rate of spread of mixed materials
As required / agreed
B Physical Regular control through
checks of layer thickness
SR
xiii Density of compacted Layer
As required / agreed
A Physical One test per 250 sqm of
area
SR
19.4 Bituminous Surfacing - Open
graded premix carpet and Seal
coat
i Quality of binder
Penetrometre with St.
needle
A Physical No. of samples per Lot &
tests as per IS:73, IS:217,
IS:8887 as applicable
SR
ii Aggregate Impact Value / Los angeles
abrasion value
Aggregate Impact
ValueTest apparatus
A Physical One test per 50 cum of
aggregate
SR
iii Flakiness Index and elongation indexof
aggregates
Flakiness test gauge
B Physical One test per 50 cum of
aggregate
SR
iv Stripping value of aggregate (Immersion
tray test)
As required / agreed
B Physical Initialy one set of 3
representative specimen
per source, and on every
change of source.
SR
v Water absorption test A Physical Initialy one set of 3
representative specimen
per source, and on every
change of source.
SR
vi Water sensitivity of mix
As required / agreed
A Physical Initialy one set of 3
representative specimen
per source, and on every
change of source.
SR
vii Grading of aggregates
Set of Sieves
B Physical One test per 25 cum of
aggregates
SR
viii Soundness ( Magnesium and Sodium
Sulphate) As required as per
IS:2386
A Physical Once per source by each
method and on every
change of source
SR
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
IS 73,Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
NTPC TAMIL NADU ENERGY CO LTD. POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BID DOC. NO.:CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART - B
SUB-SECTION-IIIE-17
INDICATIVE FIELD QUALITY PLAN 14 of 21
Page 15 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
ix Polished stone value As required as per
BS:812(Part 114)
B Physical As required SR
x Temperature of binder at application
Thermometer
B Physical At regular close intervals SR
xi Binder content
Bitumen extractor
A Physical One test per 500 cum&
not less than two tests
per day
SR
xii Rate of spread of materials
As required / agreed
B Physical One test per 500 cum
and not less than 2 tests
per day
SR
xiii Percentage of fractured faces
Bitumen extractor
A Physical When gravel is used one
test per 50cum of
aggregates
SR
19.5 Tack Coat/ Prime coat/ fog coat
i Quality of binder
Penetrometre with
Standard needle
A Physical No. of samples per Lot &
tests as per IS:73, IS:217,
IS:8887 as applicable
SR
ii Temperature of binder at application
Thermometer
B Physical At regular close intervals SR
iii Rate of spread of binder
As required / agreed
B Physical One test per 500 cum
and not less than 2 tests
per day
SR
19.6 RCC Pavements Concrete - Material, Mix design, Trial
Mixes, Production, Transportation,
Placement, Compaction, Curing, Test on
green concrete, Test on hardened
concrete etc.
As required / agreed
- - Refer FQP for concrete
Works
- FQP for Concrete Works shall be application for
all concrete works
19.7 Alignment, Level, Surface
regularity and rectification
i Horizontal alignment, Surface levels and
Surface regularity
As required / agreed
B Physical As per section 900 of
MORTH specification
SR
ii Rectification
As required / agreed
B Physical Each rectification SR
20.00
20.1 Deployment of approved Geotechnical
Investigation Agency - Check for
Equipments, Manpower etc
As required / agreed
A Physical Once before
commencement of work
SR
20.2 Execution of Geotechnical Investigation -
Check for locations, type etc as per
scheme
As required / agreed
B Physical Each Location SR
20.3 Collection of disturbed and undisturbed
samples , their packing and storage As required / agreed
B Physical each sampling SR
20.4 Conducting filed tests as per investigation
scheme- such as,
SPT/ERT/SCPT/PLT/PMT etc
As required / agreed
B Physical each field test SR
20.5 Submittion of Field Borelogs in approved
format
As required / agreed
B Review Within 24 hours after
completion of each BH
SR
20.6 Submittion of laboratory test schedule and
selection of samples for laboratory testing
As required / agreed
A Review and
acceptance
as per consultation with
engineer during dispatch
of samples to approved
laboratory
SR
20.7 Submission of Final Geotechnical
investigation report along with
recommendations
As required / agreed
B Physical After completion of
investigation work and
review of draft reports
-
As per technical specifications and relevant
IS Codes
As per technical specifications and relevant
IS Codes
As per technical specifications and relevant
IS Codes
As per technical specifications and relevant
IS Codes
As per technical specifications and relevant
IS Codes
As per technical specifications and relevant
IS Codes
As per technical specifications and relevant
IS Codes
GEOTECHNICAL INVESTIGATION WORK( IF APPLICABLE)
Refer FQP for concrete Works, , Tech
Specs and Const. Drawings, IRC & MOST
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
IS 73,Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
As per Tech Specs and Const. Drawings,
Section 900 of MORTH specification
NTPC TAMIL NADU ENERGY CO LTD. POWER PROJECT (3X500 MW)
IN PLANT COAL HANDLING SYSTEM
BID DOC. NO.:CS-0260-156-2(R)
TECHNICAL SPECIFICATION
SECTION-VI
PART - B
SUB-SECTION-IIIE-17
INDICATIVE FIELD QUALITY PLAN 15 of 21
Page 16 of 16 1 PROJECT:
0 PACKAGE:
CONTRACT NO.
MAIN CONTRACTOR
1 2 4 5 6 7 8 9 D* 10
Format of
Record
Remarks Acceptance
Norms
Type of Check Quantum Of check Reference Document
3
Sl. No Characteristics / instruments Class# of
check
Activity and operation
SUPPLIERS NAME AND ADDRESS:
LOGO
QP NO. :
REV. NO .:
DATE :
PAGE :
INDICATIVE FIELD QUALITY PLAN
ITEM : CIVIL WORK
SUB-SYSTEM : GEOTECH INVI, FOUNDATIONS, EXCAVATION
& FILL, SITE LEVELLING, CONCRETE, ROAD, BUILDING ETC.
ANNEXURE- V
21.00 ANTI WEED TREATMENT
21.1
Check for the Anti-weed treatment
materials
As agreed / required
A Physical and MTC
Review
Each batch of delivery SR