Sie sind auf Seite 1von 15

CIV3703 Transport Engineering

Assignment 2
Description Marks out of Weighting(%) Due date
Assignment 2 200 marks 20% 17 October 2014

Rationale:
This assignment is designed to test your achievement of the learning objectives of Modules 1, 4, 5, 6,
and 7.
Special instructions:
Assignment 2 must be submitted by the due date via study desk link as attachment (as word file or
scanned .pdf file).
Information provided is generally adequate. If any assumptions are required, those should be clearly
stated. The answers should be well set out and clearly shown including all required calculations,
estimation of relevant parameters and similar. No excel files will be accepted as a part of your
calculations.
For this assignment, a formal report is NOT required, but clearly presents your answers (hand written
or typed) in a format appropriate to a student presenting answers to examination questions.

Penalty for late submission of assignment:
Please note that the onus is on students to organise their affairs so that they can achieve the
educational objectives of the course and submit assignments for assessment no later than the due date.
Work commitments will not be considered a legitimate reason for late assignments.
If students submit assignments after the due date without legitimate and extenuating circumstances
(e.g. illness substantiated by a medical certificate) then a penalty of 5% of the assigned mark may
apply for each working day late up to a maximum of ten working days at which time a mark of zero
can be recorded for that assignment.
The onus is also on the student to provide, if requested, the time and the date of upload to the study
desk submission link or proof of date of despatch.


Question 1 (50 Marks)

Calculate the design traffic in ESA for the follows cases:
Case A Case B
Road type Urban arterial
Principal road between major
regions
AADT (data year) 12 000 (5 years ago) 5000 (last year)
HV % 10 20
Annual growth rate % 4 8
Design period 20 years 15 years
Directional Factor 60:40 50:50
Lane distribution
Factor
85% of HV using outer lane 95% of HV using outer lane


For Case A:
Using Table 6.2,

)
ESA per HV for Urban Arterial = 1.8




For Case B:
Using Table 6.2,

)
ESA per HV for Principal road between major regions = 3




Question 2 (50 Marks)
A granular pavement with bituminous seal is to be design for a collector road in urban area. The
design lane traffic loading in Equivalent Standard Axles (DESA) is 20 million ESLs.

Testing reveals a subgrade CBR of 3, and could be improved from CBR 3 to CBR 7 with lime
stabilization. Available equipment and construction techniques dictate that the stabilised layer must be
150 mm compacted thicknesses and the cost for stabilisation will be $35.00 per m
3
.

The minimum thickness of any layer is 100mm.

The following materials are available for your use and are as placed.

Material Cost

Crushed rock, CBR 90 $55.00/ m
3

Crushed river gravel, CBR 30 $35.00/ m
3

River gravel, CBR 15 $15.00/ m
3

Selected fill, CBR 7 $10.00/ m
3


Consider possible pavement options and recommend a final pavement configuration for adoption. It is
essential to provide justification as to why you have selected a particular design for construction.
While cost is an important issue, include some discussion on the potential long-term performance of
the selected pavement as compared with other pavements.

Note: The pavement seal has already been designed, and you do not need to design either seal or other
road elements such as slopes, drainage, etc.

STEP 1:
California bearing Ratio (CBR) for subgrade given as 3 (without stabilization)
California bearing Ratio (CBR) for subgrade given as 7 (with lime stabilization)

STEP 2:
Design traffic given as 20,000,000 ESA



STEP 3:
Without Stabilization:
Using Figure 6.4 at ESA =

and
Thickens of granular material = 690 mm
Minimum Thickness of Base material = 180 mm

With Lime Stabilization:
Using Figure 6.4 at ESA =

and
Thickens of granular material = 430 mm
Minimum Thickness of Base material = 180 mm

STEP 4:
Base:
Crushed Rock CBR 90
Sub-Base:
Crushed river gravel CBR 30
River Gravel, CBR 15
Selected fill, CBR 7

STEP 5:
Required cover for sub-base material, using table 6.4
Sub-Base Material Required Cover
Crushed river gravel CBR 30 180 mm
River Gravel, CBR 15 265 mm
Selected fill, CBR 7 430 mm


STEP 6:
Maximum value from Step 3 and Step 5
Sub-Base Material Without Stabilization
(180 mm)
With Lime Stabilization
(180 mm)
Crushed river gravel CBR 30 180 mm 180 mm
River Gravel, CBR 15 265 mm 265 mm
Selected fill, CBR 7 430 mm 430 mm

To achieve Overall pavement thickness, thickness of sub-base required:

Sub-Base Material Without Stabilization
(690 mm)
With Lime Stabilization
(430 mm)
Crushed river gravel CBR 30 510 mm 250 mm
River Gravel, CBR 15 425 mm 165 mm
Selected fill, CBR 7 260 mm 0 mm


STEP 7:
Cost comparison of different material (assuming 1 m
2
of pavement area)

Without Stabilization:
Pavement Options
Sub-Base
Base
Total
Cost
($/m
2
)
Crushed Rock
Thickness
(mm)
Cost
($/m
2
)
Thickness
Cost
($)
Option 1 (Crushed River Gravel) 510 17.9 180 9.9 27.8
Option 2 (River Gravel) 425 6.4 265 14.6 21
Option 3 (Selected Fill) 260 2.6 430 23.7 26.3


With Lime Stabilization:
Pavement Options
Sub-Base
Base Stabilizing
cost (150
mm @
$35 m
3
Total
Cost
($/m
2
)
Crushed Rock
Thickness
(mm)
Cost
($/m
2
)
Thickness
Cost
($)
Option 1 (Crushed River Gravel) 250 8.8 180 9.9 5.25 23.95
Option 2 (River Gravel) 165 2.5 265 14.6 5.25 22.35
Option 3 (Selected Fill) 0 0 430 23.7 5.25 28.95


Based is the cost analysis, it can be seen that Option 2 under Without stabilization is the most
economical assuming that 690 mm of granular pavement is acceptable.

Hence the final pavement design is
-----------------------------------------------------------------------------------
Crushed Rock CBR 90 Base 265 mm
-----------------------------------------------------------------------------------
River Gravel CBR 15 Sub-base 425 mm
-----------------------------------------------------------------------------------
Sub grade







Question 3 (30 Marks)

a) List the functions of a primer in the application of a bituminous seal over a crushed rock or
natural gravel base, and outline the materials which are typically used for primes.
The functions of primer includes
Enhance bond between the pavement and subsequent bituminous surfacing
Provide water proof membrane in the pavement
Assist in stabilizing moisture conditions in pavement

Typical materials used for primes is Cutback bitumen


b) Explain the basis of mechanistic pavement thickness design methods (i.e. what theories and
assumptions are these methods based on).
Mechanistic pavement thickness design method
mechanistically calculate pavement response such as stress, strains and deflections due
to traffic loading and environmental conditions (response model)
Empirically relate damage over time to pavement distresses such as cracking, rutting,
faulting due to repeated loads (performance model)
Calibrate predictions to observed field performance

Elastic layer model is the commonly used response model to model the pavement as a series of layers
of infinite horizontal extent. Pavement is represented as a grid of finite elements under finite element
model for response model.

Assumptions:
Pavement material are considered homogenous, linease, elastic and isotropic
No slip between adjacent layer



c) List the parameters used in the current Austroads methods for flexible pavement design, and
outline how these parameters are determined.

Design Traffic
Subgrade modulus
Modulus of different materials








Question 4 (20 Marks)
An asphalt stiffness modulus of 4800 MPa was obtained in the laboratory.
In the field, the following are observed:
In-service Air Voids = 8%
WMAPT = 27C
Average traffic speed = 80 kph.

a. Find the Austroads correction factors for the asphalt and obtain the design asphalt modulus.

Correction factor for In-service air voids: 0.82
Correction factor for in-service Temperature: 0.85
Correction factor for traffic speed: 0.95

Design asphalt modulus =


b. Using the calculated design asphalt modulus, design 3 alternative flexible pavements (granular,
deep strength and full depth) using Austroads charts for a design traffic loading of 7.5x10
7
ESA.

Traffic =


Asphalt (3200 MPa)

Assuming available Materials:
Unbound granular (CBR 80)
Cemented material (deep strength) (Modulus 5000 MPa)
Subgrade, CBR=5 (modulus 50 MPa)

Design 1 Asphalt over unbound granular material:
Assuming thickness of unbound granular material of 200 mm

Using charts, Thickness of asphalt required = 315 mm

-----------------------------
Asphalt (315 mm)
-----------------------------
Granular (200 mm)
-----------------------------
CBR5


Design 2 Deep strength (Asphalt over cemented material):
Assuming thickness of cemented material of 200 mm

Using charts, Thickness of asphalt required = 220 mm

-----------------------------
Asphalt (220 mm)
-----------------------------
Cemented (200 mm)
-----------------------------
CBR5



Design 3 Full depth asphalt:
Using charts, Thickness of asphalt required = 320 mm

-----------------------------
Asphalt (320 mm)
-----------------------------
CBR5




c. Explain the disadvantages and advantages of each pavement option considering issues such as
subgrade strength, long term settlement, reflective cracking, durability, construction

Note:
Refer to: Australian Standard-Methods of sampling and testing asphalt.pdf file uploaded on study
desk.
Design 1 Asphalt over unbound granular material:
Dominant stress mode is fatigue of asphalt
Granular base is assumed stable but failure through rutting is possible due to inferior material
and compaction
Moisture adversely affect granular base, hence dry back after compaction is required
Relatively cheap due to inexpensive granular material

Design 2 Deep strength (Asphalt over cemented material):
As cemented material has significant tensile strength, fatigue is likely to occur
Cracking is common
Block crack appear on asphalt layer
Greater pavement life

Design 3 Full depth asphalt:
Dominant stress mode is fatigue of asphalt
Expensive due the presence of large quantity of asphalt
Easy to construct and can be open to traffic almost immediately after construction
Assist construction to be done in stages




Question 5 (50 Marks)

You were involved in a dispute concerning the supply of asphalt for a full depth pavement
construction. During the first summer after road opening, it was observed that the asphalt experienced
extensive rutting. In addition, some bleeding occurred at a few locations. The available laboratory
record indicated that the asphalt aggregate as supplied could be classified as well graded.

The following data is obtained from a cored asphalt specimen taken from the site:

Mass of asphalt specimen in air = 1200 g
Mass of asphalt specimen in water = 680 g
Bulk density of coarse aggregate = 2.68 t/m
3

Bulk density of fine aggregate = 2.74 t/m
3

Bulk density of filler = 3.10 t/m
3

Density of binder = 1 .02 t/m
3

% coarse aggregate of total mass = 60 %
% filler of total mass = 10%
Binder content by mass in asphalt mix = 6.4 %
Maximum density of asphalt mix (AS 2891.7.1) = 2.51 t/m
3


The asphalt laboratory suggested the effective binder content (% by volume) of typical asphalt mixes
are as follows:
Coated stone 7-9
Continuously graded asphalt mix 10-12
Gap graded asphalt mix 13-15
Gap graded wearing course 16-18
Mastic asphalt 24-28

a) Analyse the results of the laboratory test, do some calculations and draw a conclusion as to why
the pavement experienced the above problems. Also suggest how to rectify the situation. Hints:
Find the % Air Voids and % Effective Binder Content.

% Aggregate in total asphalt mass = P = 100% - % Binder by mass
P = 100 6.4 = 93.6%

% mass coarse aggregate in aggregate mix = Q = 60/P * 100%
Q = 60/93.6 * 100 = 64.1%

% fine aggregate of total mass = 100 60 10 6.4 = 23.6%
% mass fine aggregate (R) in aggregate mix = 23.6/93.6 * 100 = 25.21%

% mass filler (S) in aggregate mix = 10/93.6 * 100 = 10.68%

Q + R + S = 64.1 + 25.21 + 10.68 = 99.99

Bulk Density of Aggregate Mix



Percentage Binder absorbed

)
(

)



Effective binder



Volume of specimen:



Mass of specimen = 1200g = 1.2kg

Bulk Density of specimen



Percentage of Air Voids




% Volume of (effective binder + aggregate) = X = 100 AV = 100 7.97 = 92.03%

Volumetric proportion of effective binder = Y = % aggregate by mass / density of binder



Volumetric proportion of aggregate = Z = % aggregate by mass / bulk density of aggregate mix



% Volume of effective binder




Its a gap graded asphalt mix

b) Calculate (show calculation details and explain the meaning / significance of each item below):
1. Maximum theoretical density (t/m
3
)
2. Voids in mineral aggregate (%)
3. Voids filled with binder (%)


Maximum theoretical density




Voids in mineral aggregate





Voids filled with binder







c) Further tests revealed that the stiffness modulus of the recovered binder = 50 MPa. Estimate the
laboratory stiffness modulus of the asphalt using the Shell nomograph.

Stiff ness Modulus




Note:
Refer to: Australian Standard-Methods of sampling and testing asphalt.pdf file uploaded on study
desk.

Das könnte Ihnen auch gefallen