Beruflich Dokumente
Kultur Dokumente
All rights reserved. No part of the publication may be reproduced or copied in any form without prior written
permission from Langdon & Seah.
The information contained in the handbook should be regarded as indicative and for general guidance only.
Whilst every effort has been made to ensure accuracy, no responsibility can be accepted for errors and
omissions, however caused.
Unless otherwise stated, costs reflected in the handbook are costs as at 4th Quarter 2011.
CONSTRUCTION COSTS FOR SELECTED
ASIAN CITIES
BUILDING TYPE
US$/m
2
HONG KONG
+
SHANGHAI
+
BEIJING
+
GUANGZHOU/
SHENZHEN
+
CHONGQING
+
CHENGDU
+
DOMESTIC
Detached houses and bungalows 3,838 1,096 776 622 760 780
Terraced houses 2,863 822 528 439 480 500
Average standard apartments, high rise 2,217 658 560 525 440 470
Luxury apartments, high rise 2,453 987 993 605 800 1,000
OFFICE/COMMERCIAL
2,251 987 947 760 860 940
2,733 1,316 1,269 1,044 1,100 1,250
Shopping centres 2,545 1,206 1,090 983 900 950
HOTELS
Resort hotels N/A 1,370 N/A N/A N/A N/A
3-star budget hotels, inclusive of F.F. & E. 2,713 1,096 1,116 N/A 1,050 1,100
5-star luxury hotels, inclusive of F.F. & E. 3,436 2,193 1,919 1,517 1,880 2,150
INDUSTRIAL
1,184 N/A N/A N/A N/A N/A
warehouses 1,334 N/A N/A N/A N/A N/A
Single storey conventional factory of
structural steelwork N/A 548 586 520 550 550
Owner operated factories, low rise 1,805 735 765 648 N/A N/A
OTHERS
Basement carparks (< 3 levels) 1,900 830 780 759 700 700
Elevated carparks (< 4 levels) 1,028 398 456 353 390 390
Primary and secondary schools 1,497 598 632 415 480 500
Student hostels 1,663 343 335 266 330 330
Sports clubs inclusive of F.F. & E. 2,852 1,051 970 798 900 990
Exchange Rate Used : US$1 = HK$7.8 RMB6.35 RMB6.35 RMB6.35 RMB6.35 RMB6.35
The above costs are at 4th Quarter 2011 levels, inclusive of preliminaries and contingencies unless otherwise stated.
For latest cost information, please refer to our Quarterly Construction Cost Review.
+ Rates are exclusive of contingencies.
Prestige offices, high rise
Average standard offices, high rise
Light duty flatted factories
Heavy duty flatted factories and
CONSTRUCTION COSTS FOR SELECTED
ASIAN CITIES
BUILDING TYPE
US$/m
2
MACAU
SINGAPORE
KUALA
LUMPUR
BRUNEI INDIA
MANILA
DOMESTIC
Detached houses and bungalows 3,455 2,400 962 751 409 1,210
Terraced houses 3,015 2,040 317 525 300 620
Average standard apartments, high rise 1,545 1,680 463 871 347 845
Luxury apartments, high rise 2,230 2,760 1,070 1,071 439 1,070
OFFICE/COMMERCIAL
2,200 2,080 752 871 406 820
2,520 2,320 1,105 1,192 514 1,080
Shopping centres 2,710 2,240 917 1,097 470 960
HOTELS
Resort hotels N/A 2,480 1,333 1,438 723 1,290
3-star budget hotels, inclusive of F.F. & E. 2,560 2,560 1,537 1,559 817 1,230
5-star luxury hotels, inclusive of F.F. & E. 3,480 3,440 2,241 2,163 1,588 1,600
INDUSTRIAL
1,245 1,120 438 483 263 430
warehouses N/A 1,360 521 N/A 313 475
Single storey conventional factory of
structural steelwork N/A 960 435 441 252 410
Owner operated factories, low rise N/A N/A 530 N/A 317 440
OTHERS
Basement carparks (< 3 levels) 1,230 1,310 505 N/A 254 480
Elevated carparks (< 4 levels) 910 760 286 494 222 465
Primary and secondary schools N/A 1,055 327 693 178 590
Student hostels N/A 1,160 413 793 228 695
Sports clubs inclusive of F.F. & E. N/A 1,770 854 N/A 605 1,260
Exchange Rate Used : US$1 = MOP7.97 S$1.25 RM3.15 B$1.26 INR50 PHP43
Rates based on projects in Bangalore and are nett of VAT and
Service Tax. Mumbai costs are generally 8% higher.
Rates are exclusive of contingencies and include 12% VAT.
The above costs are at 4th Quarter 2011 levels, inclusive of preliminaries and contingencies unless otherwise stated.
For latest cost information, please refer to our Quarterly Construction Cost Review.
Rates are exclusive of contingencies and any management
contract fee.
Rates are nett of GST and exclusive of contingencies.
Prestige offices, high rise
Average standard offices, high rise
Light duty flatted factories
Heavy duty flatted factories and
PROGRESS PAYMENTS
CONTRACT
PERIOD
CUMULATIVE
PROGRESS
CLAIMES
CONTRACT
PERIOD
CUMULATIVE
PROGRESS
CLAIMES
5% 1% 55% 59%
10% 3% 60% 68%
15% 5% 65% 77%
20% 7% 70% 83%
25% 10% 75% 88%
30% 14% 80% 92%
35% 21% 85% 94%
40% 29% 90% 96%
45% 38% 95% 98%
50%
48% 100% 100%
The following graph and table are an indication of the rate of expen-
diture for construction projects.
The rate of expenditure is an average rate and will vary from proj-
ect to project when specific project circumstances are taken into
account.
No account has been made for retention.
CONSTRUCTION COSTS FOR SELECTED
ASIAN CITIES
BUILDING TYPE
US$/m
2
KARACHI BANGKOK
#
JAKARTA ^ HO CHI MINH
#
SEOUL
$
TOKYO
DOMESTIC
Detached houses and bungalows 985 - 1,150 967 475 500 - 600 1,930 2,760
Terraced houses 250 - 350 583 N/A 425 - 485 1,605 N/A
Average standard apartments, high rise 580 - 775 828 595 635 - 760 1,310 2,230
Luxury apartments, high rise 870 - 1,150 1,162 800 815 - 945 1,630 3,100
OFFICE/COMMERCIAL
575 - 725 750 575 760 - 880 1,170 2,680
950 - 1,150 983 860 890 - 1,130 1,330 3,200
Shopping centres 695 - 900 800 495 695 - 815 1,480 2,190
HOTELS
Resort hotels 1,965 - 2,305 2,267 1,200 1,195 - 1,500 1,535 3,510
3-star budget hotels, inclusive of F.F. & E. 1,125 - 1,450 1,367 980 1,495 - 1,750 1,730 3,480
5-star luxury hotels, inclusive of F.F. & E. 1,800 - 2,100 1,933 1,395 1,825 - 2,060 2,300 5,100
INDUSTRIAL
300 - 375 600 N/A 238 - 390 N/A 1,540
warehouses 350 - 450 N/A N/A 395 - 510 N/A 2,040
Single storey conventional factory of
structural steelwork 435 - 450 600 260 385 - 510 690 1,760
Owner operated factories, low rise 325 - 425 N/A N/A 395 - 495 N/A N/A
OTHERS
Basement carparks (< 3 levels) 275 - 325 683 390 640 - 730 965 N/A
Elevated carparks (< 4 levels) 200 - 250 350 260 340 - 455 565 1,690
Primary and secondary schools 550 - 675 N/A N/A 475 - 500 1,820 2,070
Student hostels 410 - 540 N/A N/A 500 - 630 1,080 1,890
Sports clubs inclusive of F.F. & E. 810 - 900 N/A N/A 755 - 840 1,460 2,280
Exchange Rate Used : US$1 = PKR89.42 BAHT30 IDR8,910 VND21,011 KRW1,144 JPY78.14
$ Rates are nett of VAT and exclusive of contingencies.
Rates exclude contingencies, consultant fees and consumption tax.
The above costs are at 4th Quarter 2011 levels, inclusive of preliminaries and contingencies unless otherwise stated.
For latest cost information, please refer to our Quarterly Construction Cost Review.
#
Rates are nett of VAT and contingencies.
^
Rates are nett of VAT.
Prestige offices, high rise
Average standard offices, high rise
Light duty flatted factories
Heavy duty flatted factories and
M&E COSTS FOR SELECTED ASIAN CITIES
BUILDING TYPE
HONG KONG SHANGHAI BEIJING
GUANGZHOU/
SHENZHEN
CHONGQING CHENGDU
HK$/m
2
RMB/m
2
RMB/m
2
RMB/m
2
RMB/m
2
RMB/m
2
MECHANIAL SERVICES
1,600 - 2,350 761 - 966 750 - 990 650 - 880 700 - 900 700 - 1,000
Industrial * 380 - 500 173 - 289 160 - 270 135 - 240 150 - 250 150 - 250
Hotels 1,750 - 2,150 971 - 1,265 910 - 1,110 890 - 1,115 750 - 1,000 750 - 1,200
Shopping Centres 1,950 - 2,400 1,050 - 1,103 790 - 950 660 - 890 600 - 850 600 - 1,000
Apartment 650 - 1,300 310 - 410 130 - 370 105 - 325 100 - 300 100 - 300
ELECTRICAL SERVICES
1,300 - 1,950 593 - 651 460 - 670 450 - 650 450 - 650 450 - 700
Industrial ** 450 - 850 305 - 431 320 - 450 260 - 400 300 - 400 300 - 400
Hotels 1,500 - 2,150 651 - 830 705 - 898 565 - 765 550 - 700 550 - 800
Shopping Centres 1,400 - 1,950 520 - 651 481 - 663 450 - 610 450 - 600 450 - 700
Apartment 850 - 1,300 252 - 368 253 - 386 240 - 380 250 - 350 250 - 350
HYDRAULIC SERVICES
270 - 380 110 - 163 95 - 140 105 - 140 70 - 130 70 - 130
Industrial 220 - 330 89 - 131 95 - 140 75 - 102 70 - 120 70 - 120
Hotels
800 - 1,050
368 - 488
360 - 470
325 - 410
300 - 400
300 - 400
Shopping Centres 270 - 380 137 - 184 140 - 200 105 - 140 70 - 130 70 - 130
Apartment 550 - 850 168 - 226 165 - 225 125 - 220 120 - 200 120 - 200
FIRE SERVICES
430 - 550 226 - 320 180 - 265 190 - 295 180 - 250 180 - 250
Industrial 250 - 300 168 - 278 140 - 215 125 - 240 150 - 250 150 - 250
Hotels 430 - 550 289 - 399 215 - 370 230 - 345 200 - 330 200 - 330
Shopping Centres 430 - 550 268 - 383 215 - 370 230 - 345 220 - 330 220 - 330
Apartment 75 - 120 47 - 116 60 - 125 55 - 105 50 - 100 50 - 100
LIFTS / ESCALATORS
550 - 900 275 - 540 294 - 577 250 - 410 350 - 550 350 - 600
Industrial 450 - 600 130 - 380 145 - 400 135 - 390 150 - 350 150 - 350
Hotels 450 - 650 215 - 485 232 - 520 200 - 390 300 - 450 300 - 500
Shopping Centres 650 - 850 320 - 485 327 - 520 305 - 430 300 - 400 300 - 450
Apartment 330 - 650 160 - 320 175 - 289 105 - 230 140 - 250 140 - 250
The above costs are at 4th Quarter 2011 levels, exclusive of contingencies unless otherwise stated.
*
Generally without A/C.
**
Excludes special power supply.
Offices
Offices
Offices
Offices
Offices
M&E COSTS FOR SELECTED ASIAN CITIES
BUILDING TYPE
MACAU SINGAPORE
KUALA
LUMPUR
BRUNEI INDIA
MANILA
MOP/m
2
S$/m
2
RM/m
2
B$/m
2
INR/m
2
PHP/m
2
MECHANIAL SERVICES
N/A 153 - 228 350 - 455 133 - 166 3,600 - 4,700 3,000 - 4,300
Industrial * N/A 29 - 136 60 - 90 17 - 29 1,600 - 2,800 650 - 1,300
Hotels 1,850 - 2,150 150 - 289 280 - 450 214 - 247 4,500 - 4,850 3,000 - 6,000
Shopping Centres 1,600 - 2,150 158 - 214 280 - 410 152 - 181 3,500 - 4,500 2,500 - 3,700
Apartment 550 - 650 95 - 192 200 - 283 157 - 181 2,000 - 2,500 1,900 - 3,000
ELECTRICAL SERVICES
N/A 203 - 306 220 - 465 171 - 214 2,800 - 4,000 3,300 - 6,000
Industrial ** N/A 58 - 148 140 - 157 143 - 171 1,800 - 3,100 2,000 - 3,500
Hotels 1,900 - 2,300 202 - 340 240 - 590 214 - 280 3,200 - 4,900 4,400 - 8,400
Shopping Centres 1,900 - 2,100 170 - 275 200 - 260 162 - 233 3,000 - 4,000 3,600 - 5,400
Apartment 650 - 850 109 - 252 85 - 210 185 - 233 1,200 - 1,600 3,200 - 4,800
HYDRAULIC SERVICES
N/A 31 - 71 23 - 52 12 - 29 575 - 850 900 - 2,000
Industrial N/A 19 - 39 36 - 45 8 - 14 375 - 650 700 - 1,200
Hotels
850 - 1,050
97 - 136
173 - 235
45 - 62
3,000 - 4,500
1,750 - 3,800
Shopping Centres 300 - 400 49 - 75 23 - 30 9 - 30 825 - 1,500 650 - 1,100
Apartment 550 - 750 75 - 159 18 - 45 28 - 44 1,300 - 1,800 1,300 - 2,600
FIRE SERVICES
N/A 32 - 64
57 - 80
24 - 29 900 - 1,200 600 - 1,200
Industrial N/A 24 - 54 45 - 60 9 - 14 400 - 550 600 - 900
Hotels 500 - 600 49 - 78 65 - 90 19 - 36 1,000 - 1,300 600 - 1,100
Shopping Centres 400 - 500 38 - 63 60 - 80 24 - 48 850 - 950 600 - 900
Apartment 100 - 150 19 - 53 20 - 25 19 - 38 450 - 550 600 - 1,300
LIFTS / ESCALATORS
N/A 62 - 177 88 - 400 7 - 24 650 - 900 1,600 - 2,900
Industrial N/A 46 - 114 54 - 190 3 - 14 400 - 550 N/A
Hotels 500 - 700 76 - 138 85 - 370 9 - 33 800 - 1,000 1,500 - 3,000
Shopping Centres 400 - 600 83 - 200 85 - 110 9 - 27 800 - 1,100 700 - 1,700
Apartment 400 - 500 27 - 123 63 - 105 8 - 19 500 - 700 800 - 1,500
Rates are based on projects in Bangalore and are nett of VAT and Service
Tax. Mumbai costs are generally 8% higher.
Transformer, included in Electrical Services.
*
Generally without A/C.
**
Excludes special power supply.
Rates are nett of GST.
The above costs are at 4th Quarter 2011 levels, exclusive of contingencies unless otherwise stated.
Offices
Offices
Offices
Offices
Offices
M&E COSTS FOR SELECTED ASIAN CITIES
BUILDING TYPE
KARACHI BANGKOK
JAKARTA
#
HO CHI MINH SEOUL
$
TOKYO
PKR/m
2
BHT/m
2
IDR'000/m
2
VND'000/m
2
KRW'000/m
2
JPY/m
2
MECHANIAL SERVICES
3,750 - 8,500 3,900 - 4,800 625 - 735 1,590 - 2,267 200 - 280 21,000
Industrial * 1,085 - 1,890 1,250 - 1,400 195 - 455 N/A 87 - 150 11,200
Hotels 7,600 - 9,950 4,500 - 5,100 625 - 840 N/A 205 - 330 14,800
Shopping Centres 7,600 - 9,950 4,400 - 4,800 570 - 680 N/A 144 - 240 7,100
Apartment 2,600 - 3,500 4,400 - 4,500 570 - 730 1,198 - 1,729 92 - 169 3,000
ELECTRICAL SERVICES
4,425 - 5,413 2,250 - 2,500 510 - 680 1,962 - 2,337 250 - 365 19,600
Industrial ** 2,431 - 3,392 1,650 - 1,700 280 - 450 N/A 115 - 150 10,400
Hotels 5,850 - 9,925 2,750 - 3,200 510 - 730 N/A 350 - 460 18,800
Shopping Centres 4,715 - 7,825 2,150 - 2,400 450 - 570 N/A 200 - 230 7,600
Apartment 2,000 - 3,270 2,390 - 2,950 510 - 680 1,740 - 2,197 130 - 165 12,200
HYDRAULIC SERVICES
765 - 1,205 750 - 890 120 - 190 263 - 502 32 - 55 12,600
Industrial 630 - 835 700 - 780 71 - 130 N/A 20 - 30 5,700
Hotels
3,200 - 4,845
1,350 - 1,490
510 - 740
N/A
57 - 89
16,600
Shopping Centres 465 - 1,240 780 - 950 120 - 190 N/A 27 - 56 5,400
Apartment 1,360 - 1,970 1,150 - 1,350 510 - 730 514 - 1,171 49 - 65 18,300
FIRE SERVICES
Included
in above
1,285 - 1,675 760 - 850 160 - 250 614 - 1,019 40 - 65
Industrial 1,125 - 2,025 720 - 750 70 - 130 N/A 27 - 30
Hotels 1,285 - 2,650 750 - 850 150 - 250 N/A 56 - 87
Shopping Centres 1,125 - 2,025 760 - 790 160 - 210 N/A 42 - 69
Apartment 850 - 1,350 760 - 850 160 - 210 420 - 528 32 - 65
LIFTS / ESCALATORS
1,745 - 3,100 1,000 - 1,050 270 - 740 563 - 1,079 45 - 60 5,600
Industrial 1,745 - 3,100 N/A N/A N/A 16 - 25 2,500
Hotels 3,500 - 8,100 1,000 - 1,100 270 - 680 N/A 110 - 155 5,100
Shopping Centres 1,745 - 3,100 210 - 490 205 - 540 1,161 - 1,642 55 - 78 3,600
Apartment 1,745 - 3,100 450 - 500 260 - 540 633 - 920 27 - 38 2,700
# All rates are nett of VAT. Rates for Electrical Services are excluding genset. Rates
for Hydraulic Services are excluding STP. Rates for Mechanical Services refer to
ACMV Rates only.
Services. Smoke spill exhaust system is included in Mechanical Services. Fire
alarm system, emergency PA system are included in Electrical Services.
*
Generally without A/C.
**
Excludes special power supply.
Based upon nett enclosed area and nett of VAT.
$ Rates are nett of VAT.
The above costs are at 4th Quarter 2011 levels,
exclusive of contingencies unless otherwise stated.
Offices
Offices
Offices
Offices
Offices
All costs are average. Sprinkler system, fire hose reel are included in Hydraulic
MAJOR RATES FOR SELECTED ASIAN CITIES
DESCRIPTION UNIT
HONG KONG SHANGHAI BEIJING
/ U O H Z G N A U G
SHENZHEN
CHONGQING CHENGDU
HK$ RMB RMB RMB RMB RMB
1. Excavating basements 2.00m deep m
3
115 30 15 25 16 20
2. Excavating for footings 1.50m deep m
3
110 25 18 30 18 25
3. Remove excavated materials off site m
3
190 * 105 25 68 43 35
4. m
3
650 168 120 155 120 130
5. Mass concrete grade 15 m
3
900 400 500 380 380 380
6. Reinforced concrete grade 30 m
3
1,130 470 560 465 420 420
7. Mild steel rod reinforcement kg 9.8 6 6.3 6.2 6.3 6.3
8. High tensile rod reinforcement kg 9.8 6 6.3 6.2 6.3 6.3
9.
slabs m
2
180
55
65
45
55
55
10. Sawn formwork to columns and walls m
2
180 55 55 45 55 55
11. 112.5mm thick brick walls m
2
190 60
@
90 58 47 50
12.
steel sheeting m
2
600
N/A
N/A
N/A
N/A
N/A
13. Aluminium casement windows, single
glazed m
2
1,700
600
780
**
550
750
**
750
**
14. Structural steelwork - beams, stanchions
and the like kg
25
12
11
14
12
12
15.
the like kg
27
10
11
11
10
10
16. 25mm cement and sand (1:3) paving m
2
80 35 20 21 22 25
17. 20mm cement and sand (1:4) plaster
to walls m
2
95
28
22
18
17
20
18.
(m/s) m
2
270
160
120
115
120
120
19. m
2
430 170 140 157 130 130
20. Two coats of emulsion paint to plastered
surfaces m
2
44
32
30
26
30
30
Average expected preliminaries % 10 - 15 3 - 8 5 - 10 5 - 10 5 - 10 5 - 10
The above costs are at 4th Quarter 2011 levels and are based on lump sum fixed price contract rates exclusive of preliminaries and
contingencies unless otherwise stated.
**
Rates for double glazed window.
*
Rate including waste charges implemented on 1 Dec. 2005.
@
Rates for 120mm thick concrete block walls.
Hardcore bed blinded with dine materials
Sawn formwork to soffits of suspended
Kliplok Colorbond 0.64mm profiled
Steelwork - angles, channels, flats and
Ceramic tiles bedded to floor screed
12mm fibrous plasterboard ceiling lining
MAJOR RATES FOR SELECTED ASIAN CITIES
DESCRIPTION UNIT
MACAU SINGAPORE
KUALA
LUMPUR
BRUNEI INDIA
MANILA
MOP S$ RM B$ INR PHP
1. Excavating basements 2.00m deep m
3
110 16.5 15 - 20 3.5 130 350
2. Excavating for footings 1.50m deep m
3
105 16.5 15 - 20 3 145 250
3. Remove excavated materials off site m
3
60 15 20 - 25 3 100 200
4. m
3
580 50 60 - 70 37 3,060 2,500
5. Mass concrete grade 15 m
3
680 202
230 - 250 117 4,200 3,500
6. Reinforced concrete grade 30 m
3
730 155 - 170 250 - 280 132 5,125 4,800
7. Mild steel rod reinforcement kg 9.5 1.6 - 1.75 3.5 - 3.8 0.98 40 47
8. High tensile rod reinforcement kg 9.5 1.6 - 1.75 3.5 - 3.8 0.98 42 48
9.
slabs m
2
160
30 - 33 30 - 38
14.5
425
850
10. Sawn formwork to columns and walls m
2
160 30 - 33 30 - 38 14 450 800
11. 112.5mm thick brick walls m
2
250 30 - 35 32 - 45 18.5 700 N/A
12.
steel sheeting m
2
N/A
43 55 - 60
56
960
900
13. Aluminium casement windows, single
glazed m
2
2,000
290 350 - 500
166 - 216
3,700
9,000
8,000 55 22 23
7,000 48 20 21
6,000 41 18 19
5,000 35 16 17
4,000 28 12.75 14.5
3,000 21 10 11.5
21
19
17
15
11.75
9
Gravel Size
3
/
4
1
1
/
2
Reinforcement
Bar Diameter
(mm)
6
8
10
12
16
20
25
32
40
Weight/m
(kg/m)
0.222
0.395
0.616
0.888
1.579
2.466
3.854
6.313
9.864
Perimeter
(mm)
Area
(mm
2
)
18.85
25.13
31.42
37.70
50.27
62.83
78.54
100.53
125.66
28.27
50.26
78.54
113.10
201.06
314.16
490.88
804.25
1256.64
Dimensions for standard parking space,
loading/unloading bays and lay-bys
Length Width Headroom
(m) (m) (m)
Private Cars,
Taxis and Light Vans 5 2.5 2.4
Coaches and Buses 12 3.0 3.8
Lorries 11 3.5 4.1
Container Vehicles 16 3.5 4.5
Minimum heandroom means the clearance between the floor and
the lower most projection from the ceiling including any lightings
units, ventilation duct, conduits or similar.
The above ratios are indicative and for reference purpose only.
They do not account for buildings with special shapes,
configurations or particularly small foot prints.
Average Loads Volume
Lorry (24 ton) 10.0 m
3
Concrete truck (24 ton) 5.5 m
3
Structure Design - Concrete Ratios
The following is a range of concrete ratios for building
superstructure design in Manila:
0.4 m
3
/m
2
to 0.55 m
3
/m
2
2.0 m
2
/m
2
to 3.0 m
2
/m
2
Reinforcement 180 kg/m
3
to 280 kg/m
3
Formwork/floor area
Concrete/floor area
Average External Wall/Floor Ratio
Residential Apartments 1.0 m
2
/m
2
0.4 m
2
/m
2
Industrial 0.4 m
2
/m
2
Office, Hotel
Average Internal Wall/Floor Ratio
Residential Apartments 1.0 m
2
/m
2
0.5 m
2
/m
2
Hotel 1.5 m
2
/m
2
Office
CONSTRUCTION MATERIALS WHOLESALE
PRICE INDEX IN THE NATIONAL CAPITAL
REGION (NCR)
2010
ALL ITEMS
A. Sand and gravel
B. Concrete Products
C. Cement
D. Hardware
E. Plywood
F. Lumber
G. G.I. Sheet
H. Reinforcing Steel
I. Structural Steel
J. Tile Works
K. Glass and Glass Products
L. Door, Jambs and Steel
Casement
M. Electrical Works
N. Plumbing Fixtures &
Accessories/Waterworks
O. Painting Works
P. PVC Pipes
Q. Fuel and Lubricants
R. Asphalt
S. Machinery and
Equipment Rental
Dec
171.7
183.8
182.9
194.5
157.3
172.9
202.3
220.1
246.0
159.9
174.6
180.6
171.3
146.9
185.1
165.3
290.3
388.0
114.6
197.0
Jan
171.1
185.1
183.2
195.2
157.9
172.9
203.0
221.1
246.2
160.7
174.6
181.1
171.5
147.3
185.8
166.0
299.3
388.0
114.6
199.4
Feb
171.4
186.6
183.3
195.2
161.1
172.9
204.8
225.1
251.0
162.4
174.6
184.5
174.0
148.8
186.8
166.0
305.7
388.0
114.6
201.8
Mar
174.2
189.7
183.7
197.5
165.1
173.5
210.7
230.7
253.8
162.6
176.0
189.3
177.2
150.0
189.5
166.8
326.5
388.0
114.6
206.6
Base Year (2000 = 100)
114.6 114.6 114.6 114.6 114.6 114.6 114.6 114.6
Apr
178.7
193.8
184.1
201.2
168.8
213.6
173.6
234.4
257.4
163.5
177.7
388.0
190.4
180.6
152.4
190.4
166.8
336.5
210.5
May
181.8
194.0
178.6
203.9
170.9
217.1
173.6
235.8
262.1
164.4
177.7
411.3
190.5
183.9
154.5
193.0
168.8
329.7
210.8
Jun
182.2
194.8
179.2
206.0
171.3
217.1
173.6
238.9
264.7
165.1
177.7
411.3
190.5
184.0
154.5
193.4
168.8
325.8
211.4
Jul
184.5
195.5
177.9
205.9
172.3
217.2
173.6
238.9
266.8
166.3
177.7
431.4
190.5
184.9
154.5
193.6
168.8
326.4
212.0
Aug
185.8
195.5
176.0
205.8
173.3
216.3
173.5
239.0
265.8
167.5
177.7
431.4
190.4
185.3
154.5
195.3
169.5
324.4
211.7
Sep
181.8
195.9
177.9
205.8
172.2
217.2
173.6
238.2
266.0
169.4
177.7
441.4
190.4
187.1
154.5
195.3
169.5
326.4
212.3
Oct
182.2
195.9
177.0
205.8
172.2
217.2
173.6
238.2
266.0
169.4
177.7
441.3
190.4
187.4
154.5
195.5
169.5
324.2
212.2
Nov
190.0
195.9
177.2
206.5
174.5
218.2
173.5
242.6
267.7
169.4
177.7
441.4
191.6
187.4
154.3
196.5
170.2
333.1
213.7
2011
Source : www.census.gov.ph/data/sectordata
MINIMUM WAGE
* ECOLA (Emergency Cost of Living Allowance)
Source : National Wages & Productivity Council,
Department of Labor and Employment
26 May 2011
01 January 1991
16 December 1993
01 April 1994
02 February 1996
01 May 1996
06 Febuary 1997
01 May 1997
06 February 1998
31 October 1999
01 November 2000
05 November 2001*
01 Febuary 2002*
25 June 2004*
16 June 2005
11 July 2006
28 August 2007
14 June 2008
28 August 2008
23 June 2010
NCR 16
NCR 02
NCR 03
NCR 03
NCR 04
NCR 04
NCR 05
NCR 05
NCR 06
NCR 07
NCR 08
NCR 09
NCR 09
NCR 10
NCR 11
NCR 12
NCR 13
NCR 14
NCR 14
NCR 15
22.00
12.00
17.00
10.00
16.00
4.00
15.00
5.00
13.00
25.50
26.50
15.00
15.00
20.00
25.00
25.00
12.00
15.00
5.00
22.00
426.00
118.00
135.00
145.00
161.00
165.00
180.00
185.00
198.00
223.50
250.00
265.00
280.00
300.00
325.00
350.00
362.00
377.00
382.00
404.00
Wage Amnt. of Peso per
Year
Order # Increase Day
0.00
50.00
100.00
150.00
200.00
250.00
300.00
350.00
400.00
450.00
2001 2011
Y E A R
2004 2006 2008 2010
Peso per Day
AVERAGE EARNINGS INDEX FOR
CONSTRUCTION (1987 = 100)
Q1 2,527.7 2,402.6 2,265.4 2,172.9
Q2 2,711.6 2,556.6 2,392.8 2,311.4
Q3 2,290.1 2,242.2 2,169.7
Q4 2,289.6 2,114.8 2,171.2
YEAR 2010 2009 2008
QUARTERLY 2,384.7 2,253.8 2,206.3
2011
January 2,577.3 2,250.1 2,165.1 2,386.3
February 2,366.2 2,211.0 2,121.2 2,300.6
March 2,639.6 2,335.0 2,232.5 2,521.0
April 2,664.3 2,413.6 2,312.7 2,511.4
May 2,834.4 2,447.9 2,365.6 2,601.4
June 2,636.1 2,317.0 2,255.8 2,556.8
July 2,188.0 2,168.7 2,208.4
August 2,234.1 2,146.7 2,236.5
September 2,304.6 2,193.6 2,425.4
October 2,064.8 2,131.2 2,297.5
November 2,135.8 2,163.0 2,366.8
December 2,143.7 2,219.3 2,204.5
ANNUAL 2,253.8 2,206.3 2,384.7
YEAR 2010 2009 2008 2011
CONSTRUCTION COST SPECIFICATION
The costs for the respective categories given on the previous
pages are averages based on fixed price competitive tenders. It
must be understood that the actual cost of a building will depend
upon the design, procurement methods and many other factors
and may vary from the figures shown.
The costs per square metre are based on construction floor areas
measured to the outside face of the external walls/external perim-
eter including lift shafts, stairwells, plant rooms, water tanks and
the like.
All buildings are assumed to have no basements (except other-
wise stated) and are built on flat ground, with normal soil condi-
tions and minimal external works. The costs exclude land cost,
professional fees, finance and legal expenses.
The standards for each category of building vary from country to
country and do not necessarily follow those of Manila.
FF&E refers to loose furniture, fixtures and equipment. FF&E is
excluded from office, residential and retail project costs, but are
included in hotels and country club project costs.
DOMESTIC
Average standard apartments of 6-8 flats per floor, 50m2 - 150 m2
per flat, facade comprising textured paint and punch window,
itnernal finishes comprising wood parquet, plaster and paint and
painted rubbed concrete to residential units and local ceramic tiles
to toilets.
Luxury residential facade comprised of window wall, textured
paint with stone accents, finished with homogeneous tiles, wood
cladding and coved timber ceiling to lobby, combination of wood
planks, plaster and paint and gypsum board to residential units
and homogenous tiles to toilets.
Air conditioning, gensets, automatic sprinkler system, complete
plumbing and disposal system, complete fire alarm and detection
system, CATV system are allowed for luxury apartments and
prestige houses.
Services to standard apartment also include for paging system
and Davit type gondola.Services to luxury residential also include
CCTV cameras on lobby, track mounted type gondola and helipad
provision.
OFFICE/COMMERCIAL
Based on building 30-40 storeys high with floor plans minimum
1,000 m2 per level.
Average standard offices and shopping centres have bare finish
and exclude A/C ducting and light fittings to tenants areas.
Prestige offices have curtain wall elevations, stone finished
lobbies
INDUSTRIAL
Owner operated factories exclude manufacturing equipment, air-
conditioning and special services provisions.
HOTELS
F.F. &E. includes interior decoration and loose furniture, etc. but
excludes hotel operators items (e.g. cutlery, crockery, linen etc.).
Includes 1 level of basement.
OTHERS
Carparks to be multi-storey, above ground.
Schools with standard government provisions.
Student hostels to university standard.Hospitals include fit-out to
nursing rooms, hospital facilities; services i.e., oxygen piping, A/C,
genset, ultrapure water system, fire suppression system and spe-
cial type plumbing fixtures; fit-out to doctors offices is excluded.
RETAIL PRICES OF BASIC CONSTRUCTION
MATERIALS FOR PHILIPPINES
Cement
240
220
200
180
160
140
120
100
Php / bag (40kg)
Year
Aggregates
1,100
1,000
900
800
700
600
500
400
300
2007 2008 2009 2010 2011
Year
Php / m3
Sand Gravel
2007 2008 2009 2010 2011
Ordinary Concrete Hollow Blocks
2007 2008 2009 2010 2011
Year
15
14
13
12
11
10
9
8
7
6
5
Php / piece
Timber
Php/bdft
2007 2008 2009 2010 2011
Year
Softwood
Hardwood
140
120
100
80
60
40
20
0
4" thk 6" thk
Reinforcing Bar
(Intermediate Grade - Grade 40; 275 Mpa)
Php/kg
2007 2008 2009 2010 2011
Year
Reinforcing Bar
(High Yield Grade - Grade 60; 10 Mpa)
Php/kg
Year
16mm
32mm
65
60
55
50
45
40
35
30
25
20
65
60
55
50
45
40
35
30
25
20
16mm
32mm
2007 2008 2009 2010 2011
Structural Steel (Angle Bar; A36)
Php/kg
75
70
65
60
55
50
45
40
35
30
25
2007 2008 2009 2010 2011
Year
60
55
50
45
40
35
30
25
Structural Steel (Wide Flange)
Php/kg
2007 2008 2009 2010 2011
Year
1/4" x 2" x 20'
3/8" x 3" x 20'
14 x 30 lbs
UNIT COSTS FOR ANCILLARY FACILITIES
FOR PHILIPPINES
DESCRIPTION UNIT PESO
SQUASH COURTS
Single court with glass backwall including
associated mechanical and electrical services
but including any public facilities (enclosing
structure not included)
per court 1,300,000
SWIMMING POOLS
Half Olympic (25m x 16m) 6-lanes outdoor
swimming pool built in ground, fully tiled,
complete with 5m wide deck and associated
equipment
Half Olympic (25m x 16m) 6-lanes indoor
swimming pool with suspended structure
(enclosing structure not included) fully tiled
and completed with 5m wide deck, including
mechanical ventilation and associated
equipment.
Extra for heating equipment
Extra for salt chlorine generator
per pool 7,500,000
per pool 11,500,000
per pool 1,500,000
per pool 500,000
BASKETBALL COURTS
Exposed court, approximately 975 m
2
including
player benches and excluding equipment
Covered court approximately 975m
2
,
including metal viewing seats, built-in
furniture, provision for T&B, etc*
per court 3,500,000
per court 18,000,000
TENNIS COURTS
Single court on grade with acrylic surfacing
completed with chain link fence
Extra for lighting
per court 1,960,000
per court 2,400,000
per court 500,000
Single court on grade with artificial turf
surfacing including chain link fence
* includes provision for forward/rear fold ceiling mounted
basketball goal.
DESCRIPTION UNIT PESO
PLAYGROUND EQUIPMENT
Outdoor playground equipment
comprising various activities and
safety mat
500,000
to
1,500,000
per set
SAUNAS
Sauna room for 4-6 people complete
with all accessories (enclosing
structure not included)
500,000
per
room
STEAM BATHS
Steam bath for 4-6 people complete
with all accessories (enclosing
structure not included)
600,000
per
room
GOLF COURSES
(Based on Average Cost Model of an
18 hole golf course in Asia)
excluding fairway construction and
rough hydroseeding
Including fairway construction and
rough hydroseeding
23,000,000
27,000,000
per hole
per hole
GOLF SIMULATOR
Complete golf simulation system
complete with projector, high impact
projection screen, artificial grass
putting turf, putting green cup and
control computer with software
overall size 4m x7m x 3m high
(enclosing structure not included)
3,000,000
to
4,500,000
per set
M & E MAJOR PLANT COSTS FOR THE
PHILIPPINES
DESCRIPTION
1. Water cooled electric chiller
2. Air-cooled electric chillers
3. Cooling Towers; induced draft
4. Air Handling Units (AHU)
5. Packaged water-cooled units
(PWCU)
6. Fire Pumps; electric motor driven
7. Fire Pumps; diesel engine driven
8. Standby generator sets
COST
(Php)
16,000 25,000
25,000 35,000
1,500 2,000
11,000 18,000
16,000 21,000
17,000 21,000
22,000 25,000
5,500 9,000
UNIT
per TR
per TR
per GPM
per TR
per TR
per HP
per HP
per KW
NOTE:
1. Rates are based on direct supply of imported quipment and
materials by the developer.
2. Rates include all government imposed taxes, import duties
brokerage fees and allowances for local materials and
installation cost.
3. Rates exclude preliminaries and contingencies.
4. Rates are based on fixed price tenders received in 4th
Quarter 2011.
9. Power transformers, with built-in
primary protections; padmount
10. Power transformers, with primary
protection; silicon oil filled
11. Power transformers, with primary
protection cast resin
12. Sewage Treatment Plant,
Sequencing Batch Reactor (SBR);
including civil works
1,600 6,000
1,300 4,400
2,000 5,000
20,000 30,000
per KVA
per KVA
per KVA
per
m
3
/day
FIT- OUT COSTS FOR PHILIPPINES
HOTELS
Public Areas (Front of House) :
3-star Hotel 18,000 - 22,000
4-star Hotel 24,000 - 28,000
5-star Hotel 30,000 up
Guest rooms :
3-star Hotel 16,000 - 18,000
4-star Hotel 20,000 - 25,000
5-star Hotel 25,000 - 35,000
Notes :
1. Includes furniture, floor, wall and ceiling
finishes, drapery, sanitary fittings and
light fittings.
2. Excludes partitioning, M & E works,
building shell, chandelier, operational items
and equipment (e.g. bed, cutlery, crokery,
linen, television, refrigerator, etc.), opening
expenses, stage equipment and computer
systems.
COMMERCIAL
Shopping centers 18,000 - 22,000
Notes :
1. Mall/Public areas only; tenant area to be
bare finish
2. See notes 1,2,& 3 below
DESCRIPTION PESO/m
2
OFFICES
18,000 - 26,000
35,000 - 50,000
Banking lobby *** 55,000 - 65,000
* Medium quality systems furniture
** High quality furnitures and finishes
*** Imported stone finishes; double volume
spaces
Note :
See notes 1, 2 & 3 below
Executive offices **
Standard offices *
NOTE:
1. Costs are at December 2011 Levels.
2. Costs include wall, floor, ceiling finishes, doors, FF&E,
M&E Works service reticulation, preliminaries
Forex US$1:43
3. Costs exclude operational equipment and supplies,
structure, external enclosure, major M&E plant, financing
and developers costs, professional and marketing fees.
DESCRIPTION PESO/m
2
RESTAURANT
General dining restaurant 15,000 - 30,000
Fine dining restaurant 30,000 up
Note :
Includes furniture, floor, wall and ceiling
finishes, minor alteration to air-conditioning
and fire services installation to suit layout,
exhaust for kitchen but excludes exhaust
flue, operational items (e.g. cutlery, crockery,
linen, utensils, etc.).
55,000 - 70,000
30,000 - 45,000
50,000 - 65,000
45,000 - 70,000
40,000 - 45,000
THEATRES / CINEMAS
Theatres *
Cinemas **
* Includes stage rigging and equipment,
draperies, AV equipment projectors,
screens, acoustics and seatings
** Includes screens, projection equipment,
seats, finishes, ticketing booth
AUDITORIUMS
BUSINESS CLUBS
BAR / BILLIARDS *
* Excluding kitchen equipment
KITCHEN EQUIPMENT COSTS
FOR PHILIPPINES
DESCRIPTION COST (Php)
BUSINESS CLUB
15M - 20M
500 - 900 m
2
floor area
EXECUTIVE DINING
15M - 25M
200 - 400 m
2
floor area
4 STAR HOTEL
20M - 30M
50 - 150 rooms
5 STAR HOTEL
200 - 500 rooms
30M - 40M
OFFICE CANTEEN
10M - 20M
200 - 300 m
2
floor area
TRENDS IN CONSTRUCTION COSTS
FOR PHILIPPINES
Year Hotels Residential Retail
US$
to Php
2001 56,160 30,680 36,140 20,800 52.00
2011 68,800 46,400 46,010 41,280 43.00
2002 57,240 31,270 36,835 21,200 53.00
2003 57,750 31,625 37,125 20,625 55.00
2004 58,800 32,200 36,680 18,840 56.00
2005 58,850 32,175 36,850 19,800 55.00
2006 60,000 34,000 37,000 21,760 50.00
2007 60,200 36,980 37,410 26,500 43.00
2008 66,960 45,120 44,160 29,500 48.00
2009 67,000 45,120 44,180 29,800 47.00
2010 69,080 46,860 45,760 32,340 44.00
Building Construction Cost (Php/m
2
)
Office
Php / m2 (Thousands)
0
10
20
30
40
50
60
70
80
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
Year
Office Bldgs. - Grade A
Residential - Luxury Apts.
Retail Stores
Hotels - 5-star
PROPERTY COMMENTARY
by Jones Lang LaSalle Leechiu
In General
The robust performance of the general property market in 2010,
particularly in Metro Manila, had sparked optimism in the market
in 2011. This has led property developers to introduce new proj-
ects and has encouraged increases in real estate prices. As a
result, positive growth in all property sectors (commercial office,
residential, hotel, retail and industrial) has been observed.
The upward trend in rentals that started in 2010 continued in 2011
as commercial office spaces in Makati, Ortigas and Bonifacio
Global City enjoyed healthy demand primarily from the offshoring
and outsourcing (O&O) sector. As a result, property developers
were encouraged to roll out more new office projects in various
areas in Metro Manila. Consequently, the volume of future supply
in the next few years has thoroughly increased as compared to
the previous year. In 2012, prices are still projected to rise
although tightening competition brought on by the large incoming
supply may limit their growth.
The residential condominium sector has sustained its positive per-
formance in 2011, supported by the remittances from overseas
Filipinos and relatively low interest rates. In the coming years, the
future stock of residential condominiums is expected to further
increase, reaching twice the current stock by 2015. The large
incoming supply may lead to an imbalance between demand and
supply, which may limit growth in rentals and capital values in the
mid-term.
The retail sub-sector has also recorded improvements in 2011 as
mall developers reported growth in their rental income. Despite
the lower domestic economic growth and the fragile state of the
global economy, remittance inflows from overseas Filipinos have
helped buoy retail spending in the country. Over the next year, the
forecast modest economic growth may likely support moderate
growth in the retail sector as well.
In the coming years, the hotel sub-sector is expected to experi-
ence a boom in room supply as new hotels across Metro Manila
are completed. Majority of these new hotels will likely be concen-
trated in Bonifacio Global City and Entertainment City where
most of the upcoming hotels are casino-related. Aside from Metro
Manila, many developers are venturing to more leisure resort
developments outside Metro Manila. These activities may poten-
tially attract more investments in the hotel sub-sector.
The industrial market remained resilient despite experiencing a
challenging year as economic externalities affected the perfor-
mance of the countrys exports. The sub-sector may likely post
minimal growth in the near term. However, recovery in the
countrys trade and manufacturing industry can propel growth in
the industrial sub-sector.
In general, the outlook on the property market for 2012 remains
positive, albeit growth may be modest as compared to the rela-
tively high growth experienced in the last couple of years. Amidst
the positive sentiments for the market for the year, property play-
ers are advised to exercise caution as the global economy contin-
ues to be volatile. The slow recovery of the US economy from the
last recession in 2009 and the lingering Eurozone debt crisis, are
market externalities that threaten to dampen the growth prospects
of the property market.
Commercial Sector
Jones Lang LaSalle Leechiu Research, Consulting & Valuation
(JLLL Research, Consulting & Valuation) notes that the consoli-
dated office stock for all grades in the established business
districts of Makati, Ortigas and Bonifacio Global City stood at
approximately 5.46 million sqm in 2011. This represents around
80% of the total stock of office space in Metro Manila (includes the
emerging urban districts of Eastwood City, Bay City, Newport City,
Alabang and other districts in Quezon City among others). Aver-
age vacancy of office developments in Makati CBD and Bonifacio
Global City declined from last years level to an estimated 4%. In
the next four years, approximately 1.06 million sqm are expected
to be added to the total office stock in Makati CBD, Ortigas CBD
and Bonifacio Global City.
In 2012, more than 300,000 sqm of new office space are being
constructed. Most of this future supply will come from completions
in Bonifacio Global City.
After the downturn in the property market experienced in 2009,
the office sector recovered in 2010 as rentals began rising again.
In 2011, rentals of office developments have continued this
upward trend. Average rental rates of prime and Grade A offices
in Makati and Bonifacio Global City have grown to reach around
Php9,100 per sqm per annum from approximately Php7,980 per
sqm per annum in the previous year. However, the upcoming
supply in 2012, which is more than twice the completions in 2011,
may affect the growth in rentals.
JLLL Research, Consulting & Valuation estimates that the aver-
age achievable gross rental levels for Grade A facilities in Makati
CBD (which continue to enjoy a premium to the overall market) is
approximately at Php750 to Php850 per sqm per month over
2012. Average rentals in prime office developments in Makati
CBD are projected to hover around Php900 to Php1,000 per sqm
per month. Meanwhile, rentals in office developments in Ortigas
CBD are projected to reach around Php500 to Php650 per sqm
per month. For office developments located in Bonifacio Global
City, rentals are estimated within the range of Php650 to Php850
per sqm per month. In terms of capital values, Grade A offices in
Makati CBD are estimated to achieve resale prices at around
Php75,000 to Php90,000 per sqm. In Ortigas CBD, average capi-
tal values of office spaces are projected within the range of
Php45,000 to Php55,000 per sqm.
Residential Condominium Sector
From the economic slowdown in 2009, the residential property
sector picked up in 2010 and continued to perform well in 2011.
Demand continued to be fueled by the sustained inflow of remit-
tances from overseas Filipinos coupled with the low interest rates
and flexible financing schemes. In terms of supply, the residential
condominium market continued to exhibit strong growth as total
stock in Makati CBD, Ortigas CBD, and Bonifacio Global City is
estimated at around 45,300 units in 2011.
Supply side factors in the residential sector remain a concern as
the number of residential condominium buildings further
increases. The large magnitude of supply expected in the coming
years may negatively affect the growth of rentals and capital
values. From 2012 to 2015, around 54,000 residential units are
expected to be added to the total supply in Makati CBD, Ortigas
CBD and Bonifacio Global City. On average, around 13,000 units
are expected per year for the next four years.
Rental rates of condominiums located in Makati CBD, Ortigas
CBD and Bonifacio Global City averages between Php375 and
Php700 per sqm per month. Meanwhile, average resale capital
values in these districts range from around Php60,000 to
Php115,000 per sqm, depending on the quality and location of the
condominium.
Hotels and Service Apartments Sector
The total number of hotel rooms has reached 15,765 rooms (as of
April 2011). Majority of the supply still stems from the deluxe and
standard hotel classification. These types of hotels also pose the
highest occupancy rates from January to August 2011. Occu-
pancy rates of deluxe hotels picked up as it rose to 72% while
average occupancy of standard hotels remained at 66%. How-
ever, overall occupancy of hotels across the various classifica-
tions remained at roughly the same level.
After the slight decline in occupancy rates in 2009, which may be
attributed to the global economic slowdown, performance of
hotels picked up in 2010. With the help of the growing number of
tourists coming into the country hand in hand with the economic
recovery in many countries, many hotels experienced a boost in
their occupancy rates, especially with deluxe hotels. This trend
continued through 2011, as occupancy rates continued to rise for
deluxe hotels.
Total Number of Residential Condominium Units
Makati CBD, Ortigas CBD and Bonifacio Global City:
By Type of Units (2001 - 2015E)
-
20,000
40,000
60,000
80,000
100,000
120,000
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012E 2013E 2014E 2015E
Makati CBD Bonifacio Global City Ortigas
Average Occupancy Rates of Hotels in Metro Manila By
Hotel Classification: 1996 to 2011
0%
10%
20%
30%
40%
50%
60%
70%
80%
Deluxe (5-star) First Class (4-star) Standard (3-star) Economy (2 and 1-star)
Deluxe (5-star) 75.00 73.00 60.00 63.81 65.27 58.39 62.72 61.23 71.03 74.03 73.63 73.84 70.11 64.43 70.45 72.17
First Class (4-star) 66.00 70.00 55.00 60.44 50.80 54.24 59.90 59.94 65.80 70.22 72.32 75.89 68.97 60.61 62.43 60.17
Standard (3-star) 65.00 62.00 53.00 51.53 53.14 52.51 55.88 58.97 64.28 67.88 70.29 71.81 70.77 67.77 65.72 66.05
Economy (2 and 1-star) 49.00 57.00 51.00 53.24 37.97 41.13 51.34 54.07 54.12 65.90 58.42 61.76 62.32 64.63 59.04 63.18
96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11
In the next four years, more than 9,000 hotel rooms are expected to open in Metro Manila. In 2012
alone, around 2,000 hotel rooms would be added to the Metro Manila market. Upcoming hotel
developments are expected in Quezon City, the Bay Area, Bonifa-
cio Global City and Alabang are expected to boost tourist arrivals
in the next few years.
Retail Sector
In 2011, the retail property sector sustained its positive perfor-
mance as shopping mall rentals witnessed growth and new retail
stock was added during the year. The retail market continues to
benefit from the countrys large consumer market, which is sup-
ported by the remittances from overseas Filipinos. Despite the
various ongoing problems affecting the global economy, such as
the debt crisis in the Eurozone and the slow recovery of the US
economy, remittances still grew by around 7% from January to
September 2011.
Despite the various ongoing problems affecting the global
economy, such as the debt crisis in the Eurozone and the slow
recovery of the US economy, remittances still grew by around 7%
from January to September 2011. Total remittances in 2011 is
estimated at around USD20 billion, while remittances for 2012 is
forecast to grow by 5%.
As a result of a stable inflow of remittances from overseas Filipi-
nos and the generally healthy spending of consumers in the coun-
try, demand in the retail property market witnessed positive
growth in the last couple of years with the entry and expansion of
new international retailers. Most of these retailers have either food
or clothing businesses. In 2012, many of these new retailers are
expected to expand within Metro Manila, and may venture out to
other urban centers in the Philippines.
In terms of supply, there were a few new shopping malls and
expansions of existing malls completed in 2011. With these new
additions, total retail stock of major malls in Metro Manila reached
4.0 million sqm. In the next few years, Metro Manila will likely
witness several new mid-scale shopping malls, more expansions
of existing shopping centers as well as retail malls within mixed-
use developments. In 2012, more than 200,000 sqm of retail
space is expected to be added to the total retail stock in Metro
Manila. Despite the additional retail space, JLLL Research, Con-
sulting & Valuation estimates vacancy rates in major malls to
remain in the vicinity of 4%-5%. In addition, mall developers are
also entering other underserved provinces where shopping cen-
ters are few and rare. Overall, retail supply in the Philippines is
expected to follow an upward pattern in the short- to medium-
term.
Industrial Sector
The industrial property sector recovered in the early part of 2011
as evidenced in the positive figures recorded over the said period.
Industrial land values picked up as developers faced renewed
interest from firms riding on the positive growth of the economy.
Average estimated land values in Cavite and Laguna were
observed to be between Php 3,000 and Php 3,700 per sqm.
Meanwhile, asset performance likewise improved as average
rentals in the aforementioned areas reached Php 110 to Php184
per sqm per month.
The sector remained relatively stable despite the set of crises in
Japan and more recently, the double digit dip in the countrys
exports in September. Total foreign direct investments in the
country surged in 3Q11, posting a 32% growth to Php 25 billion.
Approximately Php 9.6 billion of investment pledges were cor-
nered by the manufacturing sector alone. This growth in invest-
ments may represent the increased interest of foreign firms to
enter the Asian market as Western economies are poised to post
slow growth in the medium term. This increased interest may also
be reflected in the sustained take up of industrial products coupled
with the higher number of on-going constructions in select eco-
zones of the country.
The industrial market may exhibit subdued growth in 2012 as
externalities continue to exert pressure over the global economy.
In particular, the growing US debt and Eurozone crisis may impact
on the export-dependent Asian economies. Despite these exter-
nalities, industrial growth may be supported in the medium term
by regional trade with the countrys resilient Asian trading part-
ners. In the local scene, the open access to electricity is expected
to be implemented by September 2012 and is projected to assist
firms in securing cost-effective power rates which may improve
the marketability of the industrial sector.
Disclaimer: This document is prepared by Jones Lang LaSalle Leechiu, for information only. Whilst
reasonable care has been exercised in preparing this document, it is subject to change, and Jones
Lang LaSalle Leechiu makes no representations as to its truth, accuracy or completeness, and accord-
ingly cannot be held responsible for any liability whatsoever for any loss howsoever arising from or in
reliance upon the whole or any part of the contents of this document.
Provided by : Jones Lang Lasalle Leechiu
Accumulated Total Supply of Gross Leasable Space (in sq. m.)
Major Metro Manila Retail Malls 1995-2012E
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
1
9
9
5
1
9
9
6
1
9
9
7
1
9
9
8
1
9
9
9
2
0
0
0
2
0
0
1
2
0
0
2
2
0
0
3
2
0
0
4
2
0
0
5
2
0
0
6
2
0
0
7
2
0
0
8
2
0
0
9
2
0
1
0
2
0
1
1
2
0
1
2
E
G
L
A
(
i
n
'0
0
0
s
q
m
)
Jones Lang LaSalle Leechiu is the leading provider of profes-
sional services in real estate in the Philippines. Globally, the firm
offers integrated services delivered by expert teams worldwide to
clients seeking increased value by owning, occupying or investing
in real estate. With 2010 global revenue of more than USD 2.9
billion, Jones Lang LaSalle serves clients in 60 countries from
more than 1,000 locations worldwide, including 185 corporate
offices. The firm is an industry leader in property and corporate
facility management services, with a portfolio of approximately 1.8
billion square feet worldwide.
Jones Lang LaSalle has over 50 years of experience in Asia
Pacific, with over 19,400 employees operating in 78 offices in 13
countries across the region.
Jones Lang LaSalle Leechiu is currently the number one agency
in the Philippines, bringing together strong local presence and
talent and a global platform and infrastructure.
Jones Lang LaSalle Leechiu
5/F Equitable Bank Tower
8751 Paseo de Roxas
1226 Makati City
Philippines
Telephone : +63 (2) 902 0888
Fax : +63 (2) 729 5159
Website : www.joneslanglasalleleechiu.com.ph
: ap.joneslanglasalle.com/researchhub
For more information, please contact :
David T. Leechiu
Country Head
Telephone : +63 (2) 902 0880
Mobile : +63 (918) 910 5158
Email : david.leechiu@ap.jll.com
Claro dG. Cordero, Jr.
Head, Research, Consulting & Valuation
Telephone : +63 (2) 902 0887
Mobile : +63 (918) 914 3309
Email : claro.cordero@ap.jll.com
PHILIPPINES KEY DATA
* Population of Philippines key cities only
# Forecast / Projected
POPULATION
Population (August 2007) 88.57M
Population # (2012) 97.69M
Urban Population * 30.14%
Population under 15 31.97%
Population over 65 3.31%
Ave. annual growth rate (2000 - 2007) 2.04%
GEOGRAPHY
Land Area 300,000 km
2
Agricultural Area (2010) 42.98%
Capital City Manila
(population metropolitan Manila) 11.55M
(population Manila) 1.66M
ECONOMY 2011
Monetary Unit
Average Headline Inflation rate (Jan - Nov)
Peso
(2006 = 100) 4.83%
Gross Domestic Product (GDP)
(1Q to 3Q) Php 7,005.072bn
GDP per capita Php 79,090.80
CONSTRUCTION (1Q to 3Q) in 2011
Gross value of const. output Php 538.736bn
Net value of const. output Php 393.553bn
Net value of const. output as a
proportion of the GDP
2.07%
ECONOMIC HIGHLIGHTS
3rd Quarter 2011
Philippine Economy grows by 3.2 percent in Q3 2011
The domestic economy has decelerated for the third consecutive
quarter from the 7.3 percent honey moon growth last year to 3.2
percent this year. The so called death spiral of debt that hounds
our trading partners, the uninvigorating, albeit already expanded
government spending, and the decline in fishing due to unfavor-
able weather and the high cost of fuel contributed to this relatively
lethargic growth. As almost always, the Services sector saved the
domestic economy from posting an even lower growth. With the
downwardly revised second quarter GDP estimate, this puts the
growth for the first nine months of 2011 at 3.6 percent, quite a
distance even from the lower end of the whole year target of 4.5
percent.
On the demand side, consumer spending bolstered growth but
Construction continued to suffer from the much delayed imple-
mentation of the Public-Private Partnership program while Export
of Goods really got hit by the global crisis, posting a double digit
decline for the first time since the second quarter of 2009.
Industry declines
The Industry Sector contracted by 0.2 percent, its second con-
secutive quarter of decline after posting robust growths in the pre-
ceding five quarters. Manufacturing and Mining and Quarrying
contributed positively to Industry with [2.06 percentage point] and
[0.03 percentage point]; respectively.
Construction was the star under performer again, pulling down the
growth of Industry [with negative 2.15 percentage point]. Electric-
ity, Gas and Water Supply, likewise made a negative contribution
of [0.12 percentage point].
Construction slumps
For the second consecutive quarter, Construction declined by
12.2 percent from a growth of 15.6 percent recorded last year with
the decline of Private Construction and the contraction, albeit
lower, of Public Construction.
Source : The National Accounts of the Philippines
National Statistical Coordination Board
(www.nscb.gov.ph)
CONSUMER PRICE INDEX
Note : Base date 2006 = 100
2011*
2006
2007
2008
2009
2010
Year
126.0
100.0
102.9
111.4
116.0
120.4
Index
4.84%
2.95%
8.15%
4.22%
3.80%
% Change
* January - November 2011 CPI Average
0
1
2
3
4
5
6
7
8
9
2007 2008 2009 2010 2011
Year
% Change in CPI Index
EXCHANGE RATES
Approximate rates prevailing as at 02 January 2012
Notes:
* Convertible currencies with BSP
+ Non Convertible currencies with BSP
BSP Bangko Sentral ng Pilipinas
Source: Business Worls - BSP Reference Rate
COUNTRY
Australia*
Bahrain*
Brunei*
Canada*
China*
Denmark+
European
Currency Unit*
Hong Kong*
India+
Indonesia*
Japan*
Malaysia+
New Zealand+
Norway
Currency
dollar
dinar
dollar
dollar
yuan
kroner
euro
dollar
rupee
rupiah
yen
ringgit
dollar
kroner
44.88
116.50
33.74
43.09
6.95
7.65
56.84
5.65
0.83
0.00
0.57
13.86
34.12
7.34
Foreign
Currency
in PHP
0.0222
0.0085
0.0296
0.0232
0.1434
0.1438
0.0175
0.1768
1.2070
208.3333
1.7519
0.0721
0.0293
0.1361
PHP in
Foreign
Currency
0.98
0.38
1.30
1.02
6.32
6.32
0.77
7.77
53.01
9,090.00
76.94
3.17
1.29
5.97
US$ in
Foreign
Currency
COUNTRY
Pakistan+
Saudi Arabia*
Singapore*
South African+
South Korea*
Sweden+
Switzerland*
Taiwan+
Thailand*
United Arad
Emirates (UAE)*
United Kingdon*
United States of
America*
Currency
rupee
rial
dollar
rand
won
kroner
franc
NT dollar
baht
dirham
pound
dollar
0.49
11.71
33.87
6.49
0.38
6.37
46.842
1.45
1.40
11.96
68.25
43.92
Foreign
Currency
in PHP
2.0441
0.0853
0.0295
0.1542
26.3852
0.1568
0.0213
0.6892
0.7179
0.0836
0.0146
0.0227
PHP in
Foreign
Currency
89.78
3.75
1.29
6.79
1,158.75
6.88
0.94
30.27
31.53
3.67
0.64
1.00
US$ in
Foreign
Currency
CURRENCY CHARTS
Note: Monthly Average Rate
US Dollar
Japanese Yen
Php per 100 Japanese Yen
60
50
40
30
20
10
0
2006 2007 2008 2009 2010 2011
Year
Php per US$
60
50
40
30
20
10
0
2006 2007 2008 2009 2010 2011
Year
Singapore Dollar
Php per Singaporean Dollar
2006 2007 2009 2010 2011
Year
Sterling Pound
Php per GBP
2006 2007 2008 2009 2010 2011
Year
40
30
20
10
0
120
100
80
60
40
20
0
2008
Dirham
Php per Dirham
16
14
12
10
8
6
4
2
0
2006 2007 2008 2009 2010 2011
Year
Hong Kong Dollar
Php per Hong Kong Dollar
10
8
6
4
2
0
2006 2007
Year
2008 2009 2010 2011
Euro
80
70
60
50
40
30
20
10
0
Php per Euro
2006 2007 2008 2009 2010 2011
Year
Australian Dollar
Php per Australian Dollar
2006 2007 2008 2009 2010 2011
Year
50
40
30
20
10
0
MANILA REFERENCE RATE
0
2
4
6
8
10
2006 2007 2008 2009 2010 2011
Year
Note: Based on all maturities.
DATE %
Mar 2011 4.71
Jun 2011 4.71
Sep 2011 4.83
Dec 2011 4.81
Mar 2006 6.81
Jun 2006 7.13
Sep 2006 6.63
Dec 2006 6.63
Mar 2007 6.31
Jun 2007 6.56
Sep 2007 5.75
Dec 2007 6.06
Mar 2008 5.63
Jun 2008 5.63
Sep 2008 5.06
Dec 2008 5.38
Mar 2009 5.50
Jun 2009 5.40
Sep 2009 5.02
Dec 2009 4.88
Mar 2010 4.79
Jun 2010 4.81
Sep 2010 4.88
Dec 2010 4.86
PHILIPPINE CENTRAL BANK
MANILA REFERENCE RATE
Manila Reference Rate (%)
PHILIPPINE MAP
ENVIRONMENTAL SUSTAINABILITY
Overview of Leadership in Energy & Environmental Design
(LEED)
The U.S. based Leadership in Energy & Environmental Design
(LEED) Green Building System is a voluntary third-party rating
system in which credits are earned for satisfying specified green
building criteria. Projects are evaluated within six environmental
categories.
Sustainable Sites
Water Efficiency
Energy & Atmosphere
Materials & Resources
Indoor Environmental Quality
Innovation & Design
Certified, Silver, Gold and Platinum levels of green building certifi-
cation are awarded based on the total points earned.
Professional Services
Pre Design
Integrated sustainable design consulting ensures available opportu-
nities are recognized and explored
Assist in team selection
Evaluate project-specific opportunities and challenges based on
LEED goals
Create project-specific green guidelines
Design
Team members works closely and effectively towards a green solu-
tion.
Create sustainable design checklist including schedule and design
implications
Thoroughly evaluate design at key stages and provide detailed
instructions to the design team
Monitor design team responsibilities
Coordinate cost analysis with sustainable design goals
Develop on energy model
Liaise with USGBC
Assist and compile LEED documentation for Green Building Certi-
fication Institute (GBCI) review
Construction
Provide pre-bid conferences and contractor training
Assist during construction, including submittals and progress
reports
Monitor the implementation of green guidelines or green site con-
ditions
Liaise with USGBC
Assist and compile LEED documentation for certification
Operations
Perform post-occupancy project audits - lessons
Being part of LEED
Global Linkage
Davis Langdon & Seah (Phils) Inc. is a member of US Green Build-
ing Council (USGBC) and the Philippine Green Building Council
(PGBC).
Our environmental sustainability services employed highly skilled
Leadership in Energy & Environmental Design - Accredited Profes-
sionals (LEED-AP), certified Building for Ecologically Responsive
Design Excellence (BERDE) Professionals and highly qualified
Energy Modeller.
Green Building Facts
An Up-front investmentof 5-7% in green building design, on aver-
age, results in life cycle savings of 20% of the total construction
cost.
Source: The Costs and Financial Benefits of Green
Buildings: A report to Californias sustainable Building Task
Force, October 2003
Operating cost decrease 8-9%
Building value increase 7.5%
Return on investment improved 6.6%
Occupancy ratio increase 3.5%
Rent ratio increases 3%
Source: McGraw Hill Construction, Greening of Corporate
America SmartMarket Report, 2007.
Green buildings consume less energy and fewer resources
Green buildings consume 15-20% average less energy than con-
ventional buildings
Green buildings save, on average, 40% of drinkable / potable
water
Corporate perception of whether green fosters innovation: 57%
agree; 28% neutral and 15% disagree.
Source: McGraw Hill Construction, Greening of Corporate
America SmartMarket Report, 2007.
INTRODUCTION
Davis Langdon & Seah International has been involved in the
publication of construction costs handbooks for countries such
as Hong Kong, India, Malaysia, Philippines and Vietnam and
is also the editor of the Spons Price Book Series which com-
prise
Spons Asia Pacific Construction Costs Handbook
Spons European Construction Costs Handbook
Spons Architects' and Builders Price Book
Spons Civil Engineering and Highway Works Price Book
Spons Mechanical and Electrical Services Price Book
Spons Landscape and External Works Price Book (co-edited
by Derek Lovejoy Partnership)
As in the previous editions, the DLS Handbook -Singapore
2012 focuses on the construction cost profile of Singapore and
those of the major cities in Asia.
The handbook is structured to serve as a general reference
guide on construction cost indicators in Asia.
The information contained in this handbook has been com-
piled by Davis Langdon & Seah Singapore Pte Ltd. Any further
information and/or if advice relating toparticular projects is
required, please contact any of the regional offices listed
under the Directory of Davis Langdon & Seah International
Offices at the end of this handbook.
Davis Langdon & Seah Singapore Pte Ltd
MATERIAL PRICE INDICES
94 135.00 100.0 - 585.04 100.0 - 233.00 100.0 - 17.97 100.0 - 101.35 100.0 -
95 134.00 99.3 -0.7% 542.51 92.7 -7.3% 244.00 104.7 4.7% 18.11 100.8 0.8% 103.01 101.6 1.6%
96 135.00 100.0 0.7% 526.97 90.1 -2.8% 240.00 103.0 -1.6% 20.68 115.1 14.2% 111.04 109.6 7.9%
97 131.00 97.0 -3.0% 521.03 89.1 -1.1% 227.00 97.4 -5.4% 22.12 123.1 7.0% 106.96 105.5 -3.7%
98 107.00 79.3 -18.2% 522.86 89.4 0.3% 185.00 79.4 -18.5% 14.45 80.4 -34.7% 83.35 82.2 -22.1%
99 74.00 54.8 -30.9% 474.50 81.1 -9.3% 135.00 57.9 -27.1% 11.38 63.3 -21.3% 70.36 69.4 -15.6%
00 71.00 52.6 -4.0% 458.65 78.4 -3.3% 141.00 60.5 4.5% 12.55 69.8 10.3% 71.32 70.4 1.4%
01 70.00 51.9 -1.3% 432.81 74.0 -5.6% 147.00 63.1 4.3% 12.69 70.6 1.1% 61.40 60.6 -13.9%
02 67.00 49.6 -4.4% 442.92 75.7 2.3% 149.00 63.9 1.3% 12.65 70.4 -0.3% 55.41 54.7 -9.7%
03 71.00 52.6 6.0% 579.62 99.1 30.9% 163.00 70.0 9.5% 12.25 68.2 -3.1% 56.75 56.0 2.4%
04 76.76 56.9 8.2% 863.40 147.6 48.9% 185.77 79.7 13.9% 12.57 69.9 2.5% 62.50 61.7 10.2%
05 85.21 63.1 10.9% 738.44 126.2 -14.5% 267.86 115.0 44.3% 16.29 90.7 29.8% 72.13 71.2 15.4%
06 88.02 65.2 3.3% 729.52 124.7 -1.2% - - - 16.58 92.3 1.8% 73.88 72.9 2.4%
07* 115.40 85.5 31.1% 1,054.60 180.3 44.6% - - - 24.10 134.1 45.3% 127.00
2
125.3
2
71.9%
08 120.40 89.2 4.3% 913.00 156.1 -13.4% - - - 23.90 133.0 -0.8% 121.90
2
120.3
2
-4.0%
09 93.40 69.2 -22.4% 722.50^^ 123.5^^ -20.9% - - - 17.10 95.2 -28.4% 93.30
3
92.1
3
-23.4%
10 89.00 65.9 -4.8% 867.50 148.3 20.1% - - - 23.40 130.2 36.8% 106.70
4
105.3
4
14.3%
11p** 94.60 70.1 6.4% 936.00 160.00 7.9% - - - 20.20 112.4 -13.7% 109.20
4
107.7
4
2.3%
YEAR INDEX
(BASE
1994)
$/TONNE INFLATION INDEX
(BASE
1994)
$/'000
BRICKS
$/TONNE INFLATION INDEX
(BASE
1994)
$/TONNE INFLATION INDEX
(BASE
1994)
INFLATION INDEX
(BASE
1994)
INFLATION $/m
3
CEMENT IN BULK STEEL BARS BRICKS^ GRANITE READY MIXED CONCRETE
1
Source: Building and Construction Authority as at 8 November 2011
Note:
^From 1st Quarter 2006, statistics on bricks have been discontinued.
*Market prices from 2007 to 2010 are based on prices as at the month of December.
**Market prices for 2011 are preliminary ('p' denotes preliminary) and are based on prices as at the month of October.
^^The market prices of rebar from 2009 onwards are based on fixed supply contracts with contract period 6 months or less.
1
Prior to 2007, the market prices of ready mixed concrete (RMC) were for Grade 30.
2
The market prices of RMC were for Grade 35.
3
The market prices of RMC were based on non-fixed price contract for Grade 35 Pump.
4
The market prices of RMC are based on contracts with non-fixed price, fixed price and market retail price for Grade 40 Pump.
40
80
120
160
200
94 95 96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11p
Cement In Bulk Steel Bars Bricks Granite Ready Mixed Concrete
TENDER PRICE, MATERIAL, LABOUR AND CONSUMER PRICE INDICES
*The Singapore Department of Statistics has rebased the Consumer Price Index (CPI) Base Year to Year 2009. **Indices for 2011 are based on 3
rd
Quarter 2011.
Source: Building and Construction Authority and Singapore Department of Statistics
100.7 - 118.2 97.5 - 105.3 102.5 - 82.3 91.0 - 94
104.8 4.1% 119.9 98.9 1.4% 109.3 106.4 3.8% 83.7 92.6 1.7% 95
107.6 2.7% 120.8 99.7 0.8% 112.2 109.3 2.7% 84.9 93.9 1.4% 96
107.3 -0.3% 119.4 98.5 -1.2% 111.2 108.3 -0.9% 86.6 95.8 2.0% 97
100.2 -6.6% 115.9 95.6 -2.9% 112.0 109.1 0.7% 86.4 95.5 -0.3% 98
88.9 -11.3% 111.9 92.3 -3.5% 98.7 96.1 -11.9% 86.4 95.5 0.0% 99
87.9 -1.1% 112.4 92.7 0.4% 103.1 100.4 4.5% 87.6 96.8 1.3% 00
88.1 0.2% 112.5 92.8 0.1% 102.3 99.6 -0.8% 88.4 97.8 1.0% 01
89.9 2.0% 112.5 92.8 0.0% 104.7 101.9 2.3% 88.1 97.4 -0.4% 02
95.6 6.3% 113.6 93.7 1.0% 104.9 102.1 0.2% 88.5 97.9 0.5% 03
98.9 3.5% 117.9 97.3 3.8% 104.6 101.9 -0.2% 90.0 99.5 1.7% 04
100.0 1.1% 121.2 100.0 2.8% 102.7 100.0 -1.9% 90.4 100.0 0.5% 05
103.2 3.2% - - - - - - 91.3 101.0 1.0% 06
122.5 18.7% - - - - - - 93.2 103.1 2.1% 07
137.3 12.1% - - - - - - 99.4 109.9 6.6% 08
115.9 -15.6% - - - - - - 100.0 110.6 0.6% 09
114.4 -1.3% - - - - - - 102.8 113.7 2.8% 10
114.5 0.1% - - - - - - 109.2 120.7 6.2% 11**
BCA TPI
INDEX
(BASE 2005) (BASE 2005) (BASE 2005) (BASE 2005)
INFLATION INDEX INDEX INFLATION INDEX INDEX INFLATION INDEX INDEX INFLATION YEAR
BCA BMPI BCA LCI CPI*
85
105
95
115
135
125
145
94 95 96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11
BCA TPI BCA BMPI BCA LCI CPI
STANDARD FORMS (PRIVATE SECTOR) -
MAIN FEATURES
SIA Articles and Conditions of Building Contract
(1) Contractors rates include all other works necessary to complete
the Works, whether or not specifically mentioned in the Contract
Documents [Article 5]
(2) Architects orders must be expressed as directions or instruc-
tions [Clause 1(2)]
(3) Contractor is responsible for own design and of his sub-contractors
or suppliers [Clause 3(1)]
(4) Contractor must supply a make-up of his prices [Clause 5]
(5) Provision is made for staged possession of the site and phased
completion of the Works [Clauses 10 and 25]
(6) No provision for Employer to take out insurances [Clauses 19
and 20]
(7) Contractors notification within 28 days of any event, direction or
instruction entitling the Contractor to an extension of time with
condition precedent to an extension of time [Clause 23(2)]
(8) Following failure of Contractor to remedy any defects within 3
months from the date of issue of Schedule of Defects (or such
other time as stated in the Appendix), Architect must direct the
Contractor, within 14 days from the expiry of 3 months from the
issue of the Schedule of Defects, that a defect need not be rem-
edied. In lieu thereof, the Employer may deduct from any monies
due to or recover from the Contractor based on the estimated cost
incurred by the Employer to employ other Contractors to remedy
the defects [Clause 27.4]
(9) After the expiry of the Maintenance Period and all defects are
either remedied, or dealt with under Clause 27.4, Architect to
issue Maintenance Certificate [Clause 27.5]
(10) Contractor is responsible for Designated/Nominated Sub-
Contractors in respect of design, delays, etc [Clause 28(2)]
(11) Contractor entitled to serve payment claim (which is defined as
having the same meaning ascribed in the Building and Construc-
tion Industry Security of Payment Act) on Employer on the last day
of each month following the month in which the contract is made
(or otherwise by such time or on such day specified in Appendix)
where interim payment is based on periodic valuation, or on certi-
fied completion of the relevant stage where interim payment is
by stage instalments [Clause 31(2)]
(12) Architect issues Interim Certificates within 14 days after receipt of
payment claim [Clause 31(3)]
(13) Second release of Retention monies shall be paid under the Final
Certificate issued by the Architect at the expiry of the Mainte-
nance Period or the issuance of Maintenance Certificate, which-
ever is the later [Clause 31(10)]
(14) Architect has no power to certify compensation to Contractor for
breaches of contract by Employer [Clause 31(14)]
(15) Employer responds to payment claim by providing, or causing to
be provided, a payment response within 21 days after service of
payment claim by Contractor [Clause 31(15)]
(16)Contractor entitled to serve Notice of Termination following failure
of payment of adjudicated amount by Employer [Clause 33(3)]
(17)Contractor entitled to suspend work pursuant to provisions of
Building and Construction Industry Security of Payment Act
[Clause 33(6)]
(18) Parties may refer dispute to mediation; provision for mediation
does not affect or prejudice right to refer dispute to arbitration
[Clause 38]
(19) Parties may refer technical disputes to expert determination; pro-
vision for expert determination does not affect or prejudice right to
refer dispute to mediation or arbitration [Clause 38A](
20)Optional clauses permit fluctuations on specified materials
[Clause 39] and insurance excesses [Clause 40]
SIA Conditions of Sub-Contract
(1) Contractor issues directions and instructions to the Sub-
Contractor [Clause 5.1]
(2) Contractor orders variations on sub-contract works [Clause 7.1]
(3) Application for extension of time is made to the Contractor, not the
Architect [Clause 11.2]
(4) Time period for notification of any event, direction or instruction
entitling the Sub-Contractor to an extension of time is 21 days
[Clause 11.2]
(5) Extension of time is assessed and granted by the Contractor
[Clause 11.2]
(6) The following certificates are issued by the Contractor:
- Sub-Contract Completion Certificate [Clause 11.3]
- Sub-Contract Maintenance Certificate [Clause 12.2]
- Sub-Contract Termination Certificate [Clause 13.1]
(7) Provision for recovery of general damages only - amount is set off
and deducted from monies due to the Sub-Contractor after condi-
tion precedents are satisfied [Clause 11.4]
(8) Contractor can terminate sub-contract without the need for the
Architect to issue notices [Clause 13.1]
(9) Sub-Contractor is entitled to serve Notice of Termination following
failure of payment of adjudicated amount by Contractor [Clause
13.6]
(10) Sub-Contractor entitled to serve payment claim (which is
defined as having the same meaning ascribed in the Building and
Construction Industry Security of Payment Act) on Contractor on
the last day of each month following the month in which the sub-
contract is made where interim payment is based on periodic valu-
ation, or on certified completion of the relevant stage where
interim payment is by stage instalments [Clause 14.4]
(11) Contractor responds to payment claim by providing, or causing
to be provided, a payment response within 21 days after service
of payment claim by Sub-Contractor [Clause 14.5]
(12) Where sub-contract is a supply contract, Contractor o respond to
payment claim by paying Sub-Contractor claimed amount or such
amount as Contractor agrees to pay [Clause 14.6]
(13) Contractor has no power to revise or correct any certificates
issued by him save for clerical, computational or typographical
errors, or errors of a similar nature [Clause 14.10]
(14) Parties may refer dispute to mediation; provision for mediation
does not affect or prejudice right to refer dispute to arbitration
[Clause 16]
(15) Parties may refer technical disputes to expert determination;
provision for expert determination does not affect or prejudice
right to refer dispute to mediation or arbitration [Clause 16A]
REDAS Design and Build Conditions of Contract
(1) No order of priority for Contract Documents; in the event of any
discrepancies between the documents, Employer's Requirements
shall prevail [Clause 1.7]
(2) Provision for Named Sub-Contractors; Contractor is entitled to
rights of objection [Clause 2.4 and 2.5]
(3) Contractor's Works and design shall be fit for their intended pur-
pose in accordance with the Employer's Requirements; Contrac-
tor also responsible for the sufficiency and correctness of the
Employer's designs, specifications and calculations in the Em-
ployer's Requirements [Clause 4.1]
(4) Administration of the Contract is carried out by the Employer's
Representative appointed by the Employer; Employer's Repre-
sentative's duties can be delegated to assistants with Employer's
consent [Clause 5]
(5) Provision is made for completion of the Works in whole or in
phases/sections [Clause 10]
(6) Contractor must satisfy extensive criteria before handing over
[Clause 11]
(7) Employer may occupy any parts of the Works upon issuance of
the Handing Over Certificate of Occupied Part by the Employer's
Representative [Clause 12]
(8) Contractors application for extension of time within 28 days of
occurance of cause of delay is condition precedent to an exten-
sion of time [Clause 16.2]
(9) Contractor entitled to serve payment claim (which is defined as
having the same meaning ascribed in the Building and Construc-
tion Industry Security of Payment Act 2004) (the SOP Act) on the
Employer on the last day of each month following the month in
which the Contract is made (or otherwise by such time or on such
day as stated in Appendix 1) [Clause 22.1]
(10) Employers Representative issues Interim Payment Certificate
within 14 days of receipt of payment claim [Clause 22.2]
(11) Interim payment certificate or final payment certificate issued by
the Employers Representative shall be deemed the payment
response from the Employer under the SOP Act if the Employer
does not provide any response within 21 days of service of pay-
ment claim. Where the Employer provides a payment response
within 21 days of service of payment claim, such response shall
take precedence over the interim payment certificate or final pay-
ment certificate [Clause 22.4]
(12) Application for final payment claim by Contractor to issuance of
final payment certificate by the Employers Representative is
regulated by a procedure [Clause 24]
(13) Claims for additional payment are regulated by a claims proce-
dure [Clause 29]
(14) Employer may at his convenience at any time to terminate the
Contract without cause [Clause 30.1]
(15) Contractor entitled to suspend work pursuant to provisions of
SOP Act [Clause 31.1]
(16) Contractor entitled to serve Notice of Termination following
failure of payment of adjudicated amount by Employer [Clause
31.2]
(17) Upon issuance of a Notice of Taking Over, Employer may take
over design and construction of a part of the Works where termi-
nation for default is not practical as a default may relate to a spe-
cific part only [Clause 32]
(18) Parties may refer dispute to mediation; provision for mediation
does not affect or prejudice right to refer dispute to arbitration
[Clause 33]
(19) Additional optional clause permit fluctuations on specified mate-
rials used for permanent works only [Clause 34]
(20) Option Module (with Employers Architectural Design) where the
Employer retains his own design consultants to provide the archi-
tectural design works and make the statutory submissions
FIDIC Conditions of Contract for Construction for Building and
Engineering Works designed by the Employer
(1) Documents forming the Contract are accorded a sequence of
priority for purposes of interpretation [Clause 1.5]
(2) Administration of the Contract and supervision of the execution
of the Works are carried out by the Engineer appointed by the Em-
ployer [Clause 3.1]
(3) Provision is made for the Contractor to design the Works to the
extent specified in the Contract [Clause 4.1]
(4) Contractor is obliged to submit detailed time programme within
28 days from receipt of notice of the Commencement Date
[Clause 8.3]
(5) Employer may take over any part of the Works upon issue of a
Taking-Over Certificate by the Employer [Clause 10.2]
(6) Employer is entitled to an extension of the Defects Notification
Period (by not more than two years) if the Works or a Section
thereof cannot be used by reason of a defect or damage [Clause
11.3]
(7) Contractor may submit to the Engineer value engineering pro-
posals to accelerate completion, reduce cost of construction,
maintenance and operation, or improve efficiency or value to the
Employer [Clause 13.2]
(8) Quantities in the Bill of Quantities are estimated quantities
[Clause 14.1]
(9) Provision for advance payment to the Contractor upon submis-
sion of an Advance PaymentGuarantee, if Employer agrees
[Clause 14.2]
(10) Amount certified in Interim Payment Certificate is paid by the
Employer within 56 days from receiptof the Contractor's State-
ment and supporting documents [Clause14.7]
(11) Employer is entitled to terminate the Contract without cause at
any time for his convenience subject to certain provisions [Clause
15.5]
(12) Insuring party is the Contractor unless otherwise stated in the
Particular Conditions that the Employer wishes to effect insur-
ances [Clause 18.2]
(13) Provision is made for disputes to be adjudicated by a Dispute
Adjudication Board [Clause 20]
(14) Claims for additional payment and extension of time are regu-
lated by a claims procedure which inter alia, requires the Engineer
or Employer to respond within a given time period [Clause 20]
STANDARD FORMS (PUBLIC SECTOR) -
MAIN FEATURES
Public Sector Standard Conditions of Contract for Construction
Works (PSSCOC)
(1) Superintending Officer, Superintending Officers Representative
and assistants to Superintending Officer and Superintending
Officers Representative are appointed for design, cost control
and contract administration [Clause 2]
(2) Failure to comply with the Superintending Officers instructions
entitles the Employer to recover any cost, loss, expense and
damage incurred inemploying another contractor and any other
loss or damage as a result of the Contractors default [Clause 2]
(3) Contractor must provide a security deposit (either as cash deposit
or guarantee from a bank or Monetary Authority of Singapore
approved insurer) within 14 days from letter of acceptance or such
other longer period as stated in Appendix [Clause 4.5]
(4) Employer may provide geotechnical information but it does not
relieve the Contractor from carrying his own investigation or
search for existing and other additional relevant information
[Clause 5.1]
(5) If Contractor encounters adverse physical conditions (which
include unforeseen sub-surface and ground conditions and under-
ground services), he may be granted extension of time and loss
and expense provided such conditions could not have been rea-
sonably foreseen by an experienced contractor [Clause 5.2]
(6) Superintending Officer has express power to suspend the Works,
and if suspension is more than 90 days, Contractor may regard it
as omission of the affected part (which is suspended) or a termi-
nation (where the suspension affected the whole Works) [Clause
13]
(7) If progress or completion of the Works will be delayed, Contractor
has to notify the Superintending Officer within 60 days of occur-
rence of the delaying event [Clause 14.3]
(8) Superintending Officer may require the Contractor to submit quota-
tion for any proposed variation before issuing an instruction
[Clause 19.3]
(9) Superintending Officer has 60 days from the date of certified sub-
stantial completion of the variation works to value the amount due
and notify the Contractor [Clause 20.2(2)]
(10) Provision is made for Contractor to recover loss and expense as
a result of regular progress and/or completion of the Works having
been disrupted, prolonged or materially affected by variation
instructions, failure to give site possession, suspension, late
supply of information, Superintending Officers instructions (which
Employer is liable to pay loss and expense),unforeseeable
adverse physical conditions, acts or omissions of other contrac-
tors and Employers act of prevention or breach of contract
[Clause 22]
(11) Superintending Officer has power to certify amounts payable to
the Contractor for all work executed until termination (where such
termination is without default of the Contractor) and any loss and
expense suffered by the Contractor [Clause 31.4]
(12) Superintending Officer has to issue a Payment Certificate to the
Contractor within 14 days of receipt of a Payment Claim (which is
defined as having the same meaning ascribed in the Building and
Construction Industry Security of Payment Act) [Clause 32.2(1)]
(13) Payment Certificate issued by Superintending Officer shall be
deemed the Payment Response from the Employer under the
Building and Construction Industry Security of Payment Act if the
Employer does not provide any response within 14 days from the
Payment Claim [Clause 32.2(2)]
(14) Where the Employer provides a Payment Response within 14
days from the Payment Claim, such response takes precedence
over the Superintending Officers Payment Certificate [Clause
32.2(2)]
(15) Contractor has 90 days from the Date of Substantial Completion
to submit Final Payment Claim which shall constitute a Payment
Claim under the Building and Construction Industry Security of
Payment Act [Clause 32.4]
(16) Superintending Officer has 21 days from receipt of Final Payment
Claim to provide Contractor with an Interim Final Account and at
the same time issue a Payment Certificate [Clause 32.5(1)]
(17) Where Contractor fails to submit a Final Payment Claim, Superin-
tending Officer has 150 days from the Date of Substantial
Completion to issue Interim Final Account, and a further 30 days
thereafter to issue a payment certificate. Interim Final Account
and payment certificate under such circumstances are not subject
to the Building and Construction Industry Security of Payment Act
[Clause 32.5(2)]
(18) Mechanism for fluctuation of materials prices applicable to speci-
fied materials in Appendix [Clause 33]
(19) Any dispute or difference which involves a Payment Claim or Pay-
ment Response to which the Building and Construction Industry
Security of Payment Act applies, entitles the Contractor to make
an adjudication application [Clause 35.5(1)]
(20) Employer can only recover from the Contractor any sum due or
to become due under this contract (and not from any other con-
tract between the Employer and the Contractor) [Clause 36.1]
Public Sector Standard Conditions of Contract for Design and
Build (PSSCOC D&B) (only main features which differ from the
Build form are highlighted below)
(1) Contractor is responsible for choice of plant, materials, goods,
workmanship and coordinating all design work [Clause 4.1]
(2) Contractor to engage and include all fees, costs, etc in the Con-
tract Sum for suitable qualified personnel viz, Registered Inspec-
tor, Resident Engineer and any others as required by statute;
such persons cannot be replaced without prior consent of the
Superintending Officer [Clause 4.2]
(3) Contractor must indemnify the Employer against all claims and
proceedings for infringements of any patent rights, design, trade-
mark name or copyright [Clause 4.6]
(4) Contractor warrants that the Contractors Proposals meet the
Employers Requirements and are fit for the purpose [Clause 6.1]
(5) Contractor indemnifies the Employer for any breach of design
responsibility in contract and under common law [Clause 6.1]
(6) When the Works are substantially completed and the Temporary
Occupation Permit obtained, Contractor gives notice plus an
undertaking to complete any outstanding work during the defects
liability period; Superintending Officer has 21 days from the notice
to either issue certificate or instructions on works still to be com-
pleted [Clause 17]
(7) No provision for Named Sub-Contractors
CONTRACTUAL ARRANGEMENTS
Contractual arrangements are concerned with the typeof agree-
ment to be entered into and the obligations,responsibilities, rights
and liabilities assumed by the parties under a contract. It deals
with the situation that exists from the time when a contract is
formed until the time when all the obligations created by it have
been discharged.
Contractual arrangements may comprise the following:
Conventional Contracts
The commonest form of contract is one based upon the SIA Con-
ditions of Contract. The design is prepared bya Consultant and
the price of the works determined before award, usually by com-
petition but occasionallyby negotiation. Small projects tend to be
based upon specification and drawings whilst large projects are
usually based upon bills of quantities.
Design and Build Contracts
A design and build contract is a contractual arrangementwhere
the Employer employs a Contractor to design and build the proj-
ect.
The Contract Sum is inclusive of design work,management and
construction costs.
Develop and Construct Contracts
A develop and construct contract is a contractual arrangement
where the Employer engages consultants to design the project to
a certain stage; the Contractor then develops and completes the
design and constructs the building.
Term Contracts
Under term contracts, the Contractor signs a contract to carry out
an indefinite amount of work within a certain framework over a
time period or term. While exactly what is to be done may be
uncertain, the generalcharacter of the work will usually be fairly
easy to define.
Orders for work are issued progressively from timeto time
throughout the contract period. The work is measured, valued and
the Contractor is paid accordingly subject to the tendered adjust-
ment on the Schedule of Rates.
Guaranteed Maximum Price (GMP) Contracts
A GMP, effectively a guaranteed lump sum price for a project, is a
set of conditions that can be introduced and used in conjunction
with any standard form of contract, e.g. SIA Standard Form (for
traditional procurement),JCT Standard Form with Contractor's
Design or REDAS Design and Build Standard Form (for design-
build procurement) and JCT Management Contract Standard
Form (for management contracting). It is not a standard form of
contract.
The guaranteed price is not subject to upward adjustment except
for fundamental and material changes in the client scope of work
or as a result of legislation or statutory requirements.
The benefits of GMP include greater price certainty, early start as
design and construction can overlap, contractor's input and contri-
bution on buildability, best practice construction methods and mu-
tually beneficial partnering-style relationship.
Management Contracts
A management contract is one in which the Management Con-
tractor is appointed to manage the planning and construction of a
project and in which the construction work is executed by Sub-
Contractors working under him, selected and appointed as the job
proceeds.
The Management Contractor prepares the programme, decides
on the contents of each work package to be sub-contracted, orga-
nises and manages the construction of all works which are under-
taken by Sub-Contractors, each selected in competition.
Construction Management Contracts
Construction management contracts entail an interactive procure-
ment concept involving combined efforts of the Employer, Con-
struction Manager, design consultants and multitude of work
package contractors.
Under construction management contracts, theConstruction Man-
ager is appointed to manage the entire delivery process from
inception to completion while construction work is executed by a
myriad of work package contractors engaged by the Employer,
selected and appointed as the job proceeds.
Public-Private Partnership (PPP)
Public-Private Partnership (PPP) is a generic term whichde-
scribes the various structures possible whereby the public and
private sectors work together in the delivery of services and the
provision and operation of assets. Typical forms of project struc-
tures under PPP include PFI (Private Finance Initiative), DBFO
(Design, Build, Finance, Operate), DCMF (Design, Construct,
Manage, Finance), BOO (Build, Own, Operate), BOT (Build,
Operate, Transfer) and BOOT (Build, Own, Operate, Transfer).
Broadly, a typical PPP model involves the procuring authority (or
public agency) contracting with the Special Purpose Vehicle
(SPV) under a long-term service purchase agreement for the
design, construction,maintenance and operation of the facility.
The SPV enters into a range of subcontracts for the building
works, and operations and maintenance of the new asset.
PREAMBLES
The construction costs for the respective categories given on the
following pages are average costing at 4th Quarter 2011. They
are based on interpolation of competitive tenders received.
The construction cost serves as a guide for preliminary cost
appraisals and budgeting. It must be understood that the actual
cost of a building will depend upon the design and many other
factors such as major infrastructure of the buildings/structures,
etc. and may vary from the figures shown. The costs per square
metre are basedon construction floor areas measured to the out-
side face of the external walls/external perimeter including
liftshafts, stairwells, plant rooms, water tanks and the like.
As a guide, it might be worth to note that construction costs gener-
ally may vary accordingly depending on the following specific
requirements:
a. Complexity of the project
b. Site encumbrances
c. The need of special structural such as heavy transfer structures
over MRT/RTS structures/tracks/boxes, etc. or due to close prox-
imity to nearby infrastructure such as canals, bridges, etc.
d. The types of structural system (i.e. reinforced concrete or
structural steel system, precast/prefabrication, etc.)
e. The types of temporary works required (i.e. diaphragm walls,
sheet piling, etc.)
f. The method of construction e.g. conventional or top down
g. Basement works which are carried out in phases may require
additional temporary works and different types of construction
sequence
h. Deep basement (i.e. levels of basement)
i. Selection of Contractor (i.e. local or foreign)
j. Shape of the existing site as longish sites would generally attract
higher cost due to higher wall to floor ratio
k. The level of Green Mark rating
All buildings are assumed to have no basements (except other-
wise stated) and are built on flat ground, with normalsoil condi-
tions and minimal external works. The costs exclude the following:
Professional fees
Authorities plan processing charges
Land cost
Financing charges
Site inspectorate
CURRENT CONSTRUCTION REGULATIONS
BCA Contractors Registry System (CRS)
The Contractors Registry was established in 1984 to register
contractors who provide construction-related goods and ser-
vices to the public sector. Contractors who wish to be registered
with the Registry must show that they have the relevant experi-
ence, financial, technical and management capability.
The table below summaries the registration requirements for gen-
eral building (CW01) and civil engineering works (CW02):
Source: Building and Construction Authority as at August 2011
GRADE
(PLEASE
REFER TO
NOTE: 1)
CW01 CW02
FINANCIAL
(MIN PAID-UP
CAPITAL &
MIN NET
WORTH)
MANAGEMENT
&
DEVELOPMENT
TRACK RECORD
(PAST 3 YEARS)** ADDITIONAL
REQUIREMENTS
A1 $15.0m 24RP/P/T incl
min 8RP
ISO9001:2008
(SAC)
ISO14000
OHSAS18000/
SS506 Part 1
$150.0m
of which
$75.0m PS
$112.5m MC
$37.5m SP
$150.0m
of which
$75.0m PS
$75.0m MC
$37.5m SP
A2 $6.5m 12RP/P/T incl
min 4RP
ISO9001:2008
(SAC)
ISO14000
OHSAS18000/
SS506 Part 1
$65.0m
of which
$32.5m PS
$48.75m MC
$16.25m SP
$65.0m
of which
$32.5m PS
$32.5m MC
$16.25m SP
i) Annual
submission
of financial
accounts and
certified VAP
calculation
ii) Annual
submission
of CET
declaration
iii) General
Builder
Licence -
Class 1 (GB1)
B1 $3.0m 6RP/P/T incl
min 2RP
ISO9001:2008
(SAC)
OHSAS18000/
SS506 Part 1
ISO14000
(by 1 Jul 13)
$30.0m
of which
$22.5m MC
$7.5m SP
$30.0m
of which
$15.0m MC
$7.5m SP
B2 $1.0m 3RP/P/T incl
min 1RP
ISO9001:2008
(SAC)
OHSAS18000/
SS506 Part 1
ISO14000
(by 1 Jul 13)
$10.0m
of which
$7.5m MC
$2.5m SP
$10.0m
of which
$5.0m MC
$2.5m SP
C1 $300,000 1P + 1T
SMC
$3.0m $3.0m
C2 $100,000 1P or 2T
SMC
$1.0m $1.0m
C3 $25,000 1T $100,000
(Please refer
to Note: 14)
$100,000
(Please refer
to Note: 14)
i) Annual
submission
of financial
accounts and
certified VAP
calculation
ii) General
Builder
Licence -
Class 1 (GB1)
General
Builder
Licence -
Class 2 (GB2)
Note:
1) Please refer to Page 131 for the tendering limits
2) m stands for million
3) Both minimum (min) paid-up capital and minimumnet worth must
be met. C3 firms are required to submit the latest management
accounts (not more than 12 months old)
4) PS projects executed in Singapore
5) MC main contracts (nominated sub-contracts may be included)
6) SP minimum size single project
7) Percentage of sub-contract value taken into consideration shall
be 50% for CW01 and 75% for CW02
8) RP Professional with relevant qualifications from universities
recognised by PEB, BOA or BCA P/T Professional and Tech-
nical personnel with relevant qualifications
9) PEB Professional Engineers Board of Singapore
10) BOA Board of Architects of Singapore
11) ISO 9001:2008 must be SAC accredited i.e. the certificate to
bear the SAC logo
12) SMC (Safety Management Certificate awarded by BCA) or
OHSAS 18000 required for C1 and C2
13) CET The continuing education and training (CET) requirement
has been implemented since 1 November 2010. In order to
retain their respective grades (i.e. A1 and A2), each registered
personnel is required to complete 14 hours of structured CET
courses annually over a 12-month period from 1 November to 31
October (of the next calendar year).
14) With effect from 1 February 2012, entry grade C3 will require
completed or on-going track recordof $100,000 for new, renewal
and upgrading applications. For companies with insufficient track
record, an interview with the technical personnel (conducted at
BCA office) will be required.
**For renewal cases of grades A1 to C2, projects completed satis-
factorily in the past 5 years including on-going projects and
recently awarded projects will be considered as track record. For
CW02-A1 registration, projects completed satisfactorily in the past
5 years can be considered as track record. For evaluation of over-
seas projects and financial accounts, BCA may send its officers to
the respective countries for further verification. All flight and
accommodation expenses shall be fully borne by the applicant.
In June 2006, BCA adopted a credit rating system to indicate the
financial standing of larger construction firmsin its Contractors
Registry. The adopted credit ratingsystem is similar to one devel-
oped by credit and business information bureau DP Information
Group to assess thefinancial health of companies.
However, the BCA system applies only to the larger construction
companies (i.e. those in the top categories of A1, A2 and B1).
Government agencies will use the DP credit rating as an addi-
tional reference on the financial standing of the firms when evalu-
ating public tenders.
CURRENT CONSTRUCTION REGULATIONS
CONSTRUCTION WORKHEADS
A1 A2 B1 B2 C1 C2 C3
(CW01 & 02)
Tendering limit ($million)
Unlimited 85.0 40.0 13.0 4.0 1.3 0.65
1 Jul 10 to 30 Jun 11
Tendering limit ($million)
Unlimited 85.0 40.0 13.0 4.0 1.3 0.65
1 Jun 11 to 30 Jun 12
SPECIALIST WORKHEADS
L6 L5 L4 L3 L2 L1
(CR, ME, MW & SY)
Tendering limit ($million)
Unlimited 13.0 6.5 4.0 1.3 0.65
1 Jul 10 to 30 Jun 11
Tendering limit ($million)
Unlimited 13.0 6.5 4.0 1.3 0.65
1 Jul 11 to 30 Jun 12
Source: Building and Construction Authority as at 23 May 2011
New Tendering Limits for BCA Registered Contractors
In 2002, BCA launched a Tender Limit VariableComponent
(TLVC) to the tender limits of all registration grades in the Con-
tractors Registry System (CRS). TLVC is determined using the
Tender Price Index (TPI) to reflect the impact of tender price
movements on project value. Over the years, the TPI has moved
up significantly, hence resulting a need to adjust the tender limits
of the various CRS registration grades to better reflect the fluctua-
tions in the construction costs in the market.
In November 2007, BCA announced that the tendering limits will
be adjusted once a year on the first of July. The current new ten-
dering limits shown below are based on the latest TLVC updated
on 23 May 2011.
CURRENT CONSTRUCTION REGULATIONS
Man-Year Entitlement (MYE)
The Man-Year Entitlement (MYE) system is a work permit alloca-
tion system implemented by the Ministry of Manpower (MOM) in
April 1998. Under this system, main contractors are given entitle-
ments to employ foreign workers from Non-Traditional Sources
and the Peoples Republic of China either directly or indirectly
from their sub-contractors based on the nature and value of their
projects.
To reduce the construction industrys heavy reliance on foreign
workers and to raise the productivity levels, MOM has been tight-
ening the MYE formula so as to meet the Construction 21 (C21)
targets for MYE to be further reduced to 70% of 1999-level by
2005 and eventually to 50% of 1999-level by 2010, or earlier.
In line with the C21 blueprint, MOM has since implemented MYE
cuts/adjustments as follows:
June 2002
70% of 1998 MYE level for all upgrading projects
80% of 1998 MYE level for all civil engineering projects
65% of 1998 MYE level for all building projects below S$10
million
60% of 1998 MYE level for all building projects at or above
S$10 million
December 2004
Based on the feedback given by the industry, MYE allocation
was increased by 10% of 2002 MYE level for all new and on-
going construction projects
January 2007
5% reduction from 2004 MYE level for all projects except for
projects above $100 million
April 2007
5% restoration of January 2007 MYE level for all new and on-
going projects except for projects above $100 million
In March 2010, the Singapore Government made an announce-
ment that, with effect from 1 July 2010, there will be progressive
reduction in the MYE in phases, leading to a cumulative 25% cut
in MYE allocation by July 2012, details as follows:
Reduce MYE by 25% over 3 phases
- 1 July 2010 = 5%
- 1 July 2011 = 10%
- 1 July 2012 = 10%
The tabulation below illustrates the MYE allocation for different
project values applied during the respective periods:
Source: Ministry of Manpower as at 1 July 2011
PROJECT
VALUE
BETWEEN
1 JUL 10 AND
30 JUN 11
AFTER
1 JUL 11
BETWEEN
1 JUL 10 AND
30 JUN 11
AFTER
1 JUL 11
BETWEEN
1 JUL 10 AND
30 JUN 11
AFTER
1 JUL 11
$140,000,000 772 695 1,081 973 237 at least* 214 at least*
$35,000,000 296 266 430 387 129 116
$25,500,000 237 213 345 310 105 95
$15,000,000 158 142 229 206 70 63
$7,000,000 94 84 126 113 38 35
$600,000 12 11 18 16 5 5
$400,000 0 0 0 0 0 0
BUILDING
PROJECTS
UPGRADING
PROJECTS
CIVIL ENGINEERING
PROJECTS
*For CE Projects with contract value above $100 million, the MYE are to be
decided on a case-by-case basis.
The Government have made an announcement on 21 February
2011 that there will be a further 15% cut in the MYE quota for new
projects in July 2013.
CURRENT CONSTRUCTION REGULATIONS
Residential
(landed)
Residential
(non-landed)
Commercial
Industrial
School
Institutional and
Others
MINIMUM BUILDABLE DESIGN SCORE CATEGORY OF
BUILDING WORK /
DEVELOPMENT
57 (for A&A work within existing building)
60
2,000m
2
GFA <
5,000m
2
5,000m
2
GFA <
25,000m
2
65 68
60 (for A&A work within existing building)
67 72 75
62 (for A&A work within existing building)
69 74 77
62 (for A&A work within existing building)
69 74 77
60 (for A&A work within existing building)
64 69 72
60 (for A&A work within existing building)
60 66 69
GFA 25,000m
2
Source: Building and Construction Authority
Minimum Buildable Design Score
The legislation on buildability came into effect on 1 January 2001.
Projects submitted for planning after 1 January 2001 will be
affected by the legislation and are required to comply with a mini-
mum buildable design score as stipulated in the Code of Practice
on Buildability.
Over the years, the minimum buildability scores have been pro-
gressively raised.
In September 2005, all new building projects with gross floor area
equal or greater than 2,000m
2
are required to comply with the
minimum buildability score.
The minimum buildability score requirement shall also apply to
A&A work to an existing building if the building works involve the
construction of new floor and/or reconstruction of existing floor for
which their total gross floor area is 2,000m
2
or more.
The Code of Practice on Buildability (April 2011) has stipulated
the minimum buildable design score for building works with appli-
cations for planning permission made on or after 15 July 2011 for
different building types:
CURRENT CONSTRUCTION REGULATIONS
Source: Building and Construction Authority
Residential (landed)
Residential (non-landed)
Commercial
Industrial
School
Institutional and Others
MINIMUM CONSTRUCTABILITY SCORE CATEGORY OF
BUILDING WORK /
DEVELOPMENT 5,000m
2
GFA < 25,000m
2
GFA 25,000m
2
40
(Minimum 25 points from
Structural System)
50
(Minimum 35 points from
Structural System)
Constructability Score
To steer the construction industry towards higher level of productiv-
ity, the Building and Construction Authority (BCA) would be tighten-
ing the existing BuildabilityFramework and mandating a new com-
ponent called Constructability Score. In this connection, contractors
would be expected to adopt more labour-efficient construction
methods or technologies.
The constructability requirement would apply to all planning permis-
sions submitted on and after 15 July 2011. This extends to all new
building works and projects involving repairs and Addition & Altera-
tion Works to existing buildings with GFA of 5,000m2 or more. The
Constructability Score of a project is made up of 3 parts
: Part A Maximum of 60 points for Structural System. Points are
awarded for various methods and technologies adopted during
the construction of structural works
Part B Maximum of 50 points for Architectural, Mechanical,
Electrical and Plumbing (AMEP) Systems. Points are awarded for
various methods and technologies adopted during the construc-
tion of AMEP works
Part C Maximum of 10 points for Good Industry Practices. Points
are awarded for good industry practices adopted on site to
improve productivity
Under the BCAs Code of Buildability (April 2011), the minimum
Constructability Score requirements and minimum score under the
Structural System component are allocated as follows:
CURRENT CONSTRUCTION REGULATIONS
Earth Control Measures
Public Utilities Board (PUB) has amended its Code of Practices on
Surface Water Drainage* to provide comprehensive guidelines on
how the industry can apply more effective erosion and sedimenta-
tion control measures, this came into force in October 2006.
The Code of Practice on Surface Water Drainage contains infor-
mation pertaining to the basic planning, design and procedural
requirements for surface water drainage, and specifies the mini-
mum engineering requirements for the provision of functional
facilities for surface water drainage. This Code of Practice is
issued under Section 32 of the Sewerage and Drainage Act
(Chapter 294).
As part of our commitment of excellent service to our clients, DLS
has responded to the amendments with changes in our contrac-
tual clauses and front-end documents.
*Code of Practice on Surface Water Drainage (Fifth Edition with
amendments under Addendum No. 4 September 2006)
CURRENT CONSTRUCTION REGULATIONS
Building Control Act (Chapter 29)
The salient features incorporating the Building Control
(Amendment) Act 2007 are highlighted below:
Require Site Supervision Teams to ensure adequate Supervi-
sion of Structural Works
Under this new requirement, both the Qualified Person (QP) and
the Builder are required to provide their own supervision team. The
actual number and compositions of the supervision team will
depend on the project costas prescribed in the Regulations.
Appointment ofsupervision teams will be required for projects
where the first application for a permit is made on or after the effec-
tive date of the Act.
While this supervision team does not apply to projects which had
already obtained a permit earlier, QPs are nonetheless encouraged
to adopt the supervision team where necessary.
Strict Regulation on Major Geotechnical Works
The Act imposes more stringent regulation of major underground
building works that have significant safety impact, in particular on
the design of Earth Retaining or Stabilising Structures (ERSS) in
excavations. The Act stipulates that the design of such ERSS be
carried out by a Registered Professional Engineer (PE) and
reviewed by a Registered Accredited Checker (AC). A PE is also
required to supervise the construction of ERSS.
In addition, the geotechnical aspects of major under-ground build-
ing works including ERSS in excavations more than 6m deep, will
also require the inputs from PEs and ACs who are specialists in
geotechnical engineering.
Appointment of Instrumentation Specialist Builder (ISB)
The Developer of the building works shall appoint a Specialist
Builder to monitor instruments measuring pore pressures for satu-
rated and unsaturated levels, ground water levels and ground
movements or building movements where the building works com-
prise wholly or partly of any underground building works.
Underground building works generally mean thefollowing:
A tunnel with a diameter or height of more than 2 metres
Excavation with a depth of more than 6 metres
Foundation works for buildings of 30 or more storeys high
Any of the above case would require the appointment of an ISB and
the Act stipulates that the appointment shall be made by the Devel-
oper.
Licensing of Builders
This is a licensing scheme to set minimum standards of profession-
alism for general builders and six selective specialist builders
whose works have significant safety impact.
To be licensed, builders must be financially sound, have good
safety records and appoint key personnel with suitable qualifica-
tions and experience to manage the firm and supervise the con-
struction works.
The licensing of builders came into effect on 16 December 2008.
There was a grace period of six months (till 16 June 2009) for build-
ers to apply for the licence. There are two types of licence the
General Builder licence and the Specialist Builder licence. After 16
June 2009, all builders who had been granted or to be granted a
permit to carry out general building works, as well as builders carry-
ing out work in the six selective specialists work areas must pos-
sess a licence issued by the Commissioner of Building Control.
With effect from 15 April 2011, BCA has increased the number of
key construction trades under CoreTrade from seven (7) to seven-
teen (17) to enable the building up of a larger pool of higher skilled
and experienced workers.
In addition, the following shall apply to construction projects for
which the permits to commence structural works are submitted to
BCA from 15 October 2011
: There will be 4 project categories (instead of 3) under Core-
Trade, in recognition of the distinct manpower needs of conven-
tional Civil Engineering (CE) works and CE works involving MRT
stations:
- New Building Works
- Addition & Alteration (A&A) Works
- Civil Engineering Works (General)
- Civil Engineering Works (MRT Station)
Increasing the CoreTrade Man-Year deployment requirements
General Builders Specialist Builders
Commence 16 Dec 08 Transition Phase till 16 Jun 09 Implementation Phase
Class 1: Unlimited
Paid up capital:
Not less than $300,000
Class 2: $6mil limit
Paid up capital:
Not less than $25,000
Approved Person Technical Controller
Criteria
1. Sole Proprietor
2. Partner
3. Director
Six Categories
1. Piling Works
2. Ground Works
3. Site Investigation Works
4. Structural Steelworks
5. Pre-cast Concrete Works
6. In-situ Post-tensioning
Works
LICENSING OF BUILDERS
Tradesmen
1. Construction Plant Operation
Works
2. Electrical Works
3. Plumbing & Piping Works
4. Tiling, Stone Laying & Floor
Finishing Works
5. Reinfored Concrete Works
6. Structural Steelworks
7. Waterproofing Works
8. Cladding & Curtain Wall
Installation
9. Glazing Works
10. Drywall Installation
11. Suspended Ceiling Installation
12. Doors & Windows Installation
13. Joinery Works
14. Air-con Ducting Installation
15. Fire Protection Works
16. Gas Pipefitting Works
17. Lift Installation
Trade Foremen
Notes:-
1. Class 1 Builders with project
contract value of more than
$20mil have to submit to the
Commissioner of Building
Control a manpower program
showing the deployment of
CoreTrade personnel for the
duration of the project.
2. Deployment requirements for
3 classes of projects:-
a. New Building Works
b. A&A Works
c. Civil Engineering Works
(General)
d. Civil Engineering Works
(MRT Station)
CORETRADE
1. Electrical Works
2. Plumbing & Piping Works
3. Tiling, Stone Laying & Floor
Finishing Works
4. Waterproofing Works
5. Reinfored Concrete Works
6. Structural Steelworks
7. Waterproofing Works
8. Cladding & Curtain Wall
Installation
9. Glazing Works
10. Drywall Installation
11. Suspended Ceiling Installation
12. Doors & Windows Installation
13. Joinery Works
14. Air-con Ducting Installation
15. Fire Protection Works
16. Gas Pipefitting Works
17. Lift Installation
Administrative expenses
Legal costs and disbursements
Demolition of existing building/s
Furniture, fittings and equipment (F.F. & E.) (unless otherwise
stated)
Operating equipment
Cost escalation
Goods and Services Tax
The codes and standards for each category of building vary from
country to country and do not necessarily follow those of Singa-
pore.
Registration of CoreTrade Personnel
With effect from 16 June 2009, all Class 1 General Builders*
undertaking a project of value which is $20 million or more will be
required to deploy a prescribed minimum number of construction
personnel who are registered under the CoreTrade Scheme.
The objective of this new requirement is to build up a core group
of locals and experienced foreign workers in key construction
trades to anchor and lead the workforce.
*Class 1 General Builder licence allows the holder to carry on the
business of a general builder for any project.
Enhance Independence of Parties in Construction Projects
To avoid any situations of conflicts on interest, the Act imposes
restrictions to insulate the QP and Contractor supervising the
structural works from the influence of the developer or builder by
requiring that the QP responsible for supervision should not be
associated with the developer or builder.
Standards on Environmental Sustainability
Please refer to Page 147 for details
.Maintenance of Barrier-Free Provisions
Please refer to Page 162 for details.
Stiffer Penalties for Non-Compliance
The penalties provided in the new Act are set at a higher level
than those found in the previous Act in order to align them with the
relevant provisions of the Workplace Safety and Health Act
(WSHA).
Statutory Duty on Developers to Report AnyContravention of
the Building Control Act and Regulations to the Commis-
sioner of Building Control(CBC)
Under the Act, the developer, who is one of the key parties in the
project, has a duty to report to the CBCof any contravention of the
Building Control Act/Regulations relating to the project that he
knows or ought reasonably to know.
Mandatory Higher Green Mark Standard forGovernment Land
Sales (GLS) Sites in Selected Strategic Areas
It was announced in BCAs 2nd Green Building Master-plan in
2009 that projects developed on GLS sites in the selected strate-
gic growth areas will be subject to higher Green Mark standards.
This requirement aims to maximize the potential for cost-effective
energy savings in our built environment.
Any new development located on land sold on or after 5 May 2010
under the GLS Programme in the following strategic areas will be
required to be designed to meet the prescribed Green Mark certifi-
cation:
SELECTED STRATEGIC AREAS
Exact Location to refer to the Building
Control (Environmental Sustainability)
Regulations 2008
REQUIREMENTS FOR BUILDING WHOLLY
OR PARTLY WITHIN AREA THAT IS ON
LAND SOLD UNDER THE GLS
PROGRAMME
Marina Bay
Jurong Lake District
Kallang Riverside
Paya Lebar Central
Downtown Core including areas within
the CBD located next to Marina Bay
Green Mark Platinum
Green Mark Gold
PLUS
Source: Building and Construction Authority as at 10 December 2010
For building works that are subject to this requirement, the QPs
need not submit their declaration of the Green Mark scores along
with the building plan submission. Instead, the QPs should ensure
that, prior to the building plan submission, an application is made
to BCA for the project to obtain the Green Mark Certification in
accordance with the BCA Green Mark Certification Standard for
New Buildings. Upon completion of the building works, the QPs
should submit the Green Mark Certification rating achieved for the
project along withhis application for Temporary Occupation
Permit(TOP) or Certificate of Statutory Completion (CSC).The
prescribed Green Mark Certification rating for the building has to
be obtained before a TOP/CSC can be granted.
The certification standard has been revised from 1 December
2010 in tandem with the changes in the Green Mark Criteria. The
compliance with the respective certification standards will be
based on the tender award letter issued by the Urban Redevelop-
ment Authority (URA) to the successful developer under the GLS
Programmes for the selected strategic areas and as stated in the
table below:
Green Mark Version 4.0 for New Buildings
On 31 August 2010, BCA announced that the Green Mark (GM)
Criteria will be revised to raise the standards of environmentally
friendly buildings in Singapore. This is a step forward in achieving
the target of greening 80% of the existing buildings stock by
2030.
The revised BCA GM Criteria for new buildings (Version 4.0) will
be implemented with effect from 1 December 2010. Some of the
key changes include enhance pre-requisites for higher GM
rating, increase in focuson passive designs, sustainable con-
struction practices, introduction of carbon footprint and a mini-
mum 10% energy improvement as compared to Version 3.0.
DATE OF TENDER CLOSED UNDER
THE GLS PROGRAMMES
COMPLIANCE STANDARD
From 5 May 2010 to 30 November 2010
From 1 December 2010 and onwards
BCA Green Mark Certification Standards
for New Building, GM Version 3.0, May
2010 issue
BCA Green Mark Certification Standards
for New Building, GM Version 4.0, August
2010 issue
Source: Building and Construction Authority as at 10 December 2010
An extract on the implementation timelines of BCA GM Criteria
Version 4.0 in other green building initiatives are outlined in the
table below:
More information on the Revised BCA Green Mark Criteria for
New Buildings (Version 4.0) can be found in BCAs website.
(http://210.23.8.172/einfo/Uploads/Circular/CBCA100902.pdf)
GREEN BUILDING INITIATIVES IMPLEMENTATION TIMELINE
Government Land Sales (GLS)
Programmes
Any new development located on land sold
under the GLS are required to attain Green
Mark Gold
PLUS
or Platinum Rating.
. e t a d e s o l c r e d n e t S L G e h t n o d e s a B
Projects with tender closing date on or after
1 December 2010 will be assessed and
certified using the Revised BCA Green Mark
Criteria for new buildings (GM Version 4.0).
Public Sector Taking the Lead
New public sector buildings with more than
5,000m
2
air-conditioned floor area are
required to attain the Green Mark Platinum
Rating.
Based on the date of tender notices for the
consultancy or design and build contract.
The revised BCA Green Mark Criteria for
new buildings (GM Version 4.0) will be
applicable to public sector projects with
tenders for design that are called on or after
1 December 2010.
Green Mark Gross Floor Area (GM-GFA)
Incentive Scheme
Incentives in the form of additional GFA can
be granted by URA if development attains
Green Mark Gold
PLUS
or Platinum Rating.
Based on the submission date of BCA-
GM-GFA application.
Projects with applications submitted on or
after 1 December 2010 will be assessed
and certified using the Revised BCA Green
Mark Criteria for new buildings (GM Version
4.0).
Source: Building and Construction Authoritys Circular dated 31
August 2010
CURRENT CONSTRUCTION REGULATIONS
Source: Building and Construction Authority as at 11 July 2011
ENERGY SAVINGS
GREEN
MARK
RATING
Gold
PLUS
0.65 30% 35% 30% $500,000
Certified
0.70
20% 25%
20% $150,000
Gold 15% 20%
Platinum 0.60 35% 40% 35% $1,500,000
AIRCON
SYSTEM
EFFICIENCY
(KW/RT)
CO-FUNDING
RATE
(BASED ON
EQUIPMENT
COST)
CAP
BASED ON
TOTAL
BUILDING
CONSUMPTION
BASED ON
TOTAL
LANDLORDS
CONSUMPTION
Green Mark Incentive Scheme for Existing Building (GMIS-
EB)
GMIS-EB was introduced by BCA in April 2009. The Scheme aims
to encourage private building owners to undertake improvements
and/or retrofits to their existing buildings to achieve substantial
improvement in energy efficiency. It provides a cash incentive
that co-funds up to 35% (capped at $1.5 million) of the costs of
energy efficient equipment installed for energy efficiency improve-
ment in their existing buildings. In addition, it will also co-funds up
to 50% of the cost for conducting a energy audit (Health Check
scheme) on the efficiency of the air-conditioning plants.
All building owners of private existing non-residential buildings
with gross floor area of 2,000m2 and above with central chilled
water air-conditioning plants or which will be graded to have cen-
tral chilled water air-conditioning plants are eligible for application
of the incentive. However, the eligible buildings must first achieve
at least BCA Green Mark Certified rating and air-conditioning
system efficiency of 0.7 kW/RT or better, with 15% energy savings
or higher. The amount of co-funding for building owners will vary
depending on the Green Mark rating, air-conditioning system
efficiency and energy savings that are achieved. The amount of
co-funding rate and cap amount are summarised as follow:
The cash incentives will be disbursed in two stages. The first
disbursement, set at 50% of the approved co-funding, will be
given out upon completion of the energy improvement retrofits.
The final disbursement of the approved co-funding will be given
out upon Green Mark certification and verification of air-
conditioning plant system efficiency and the energy savings
achieved.
The scheme is applicable with effect from 29 April 2009 and will
expire 5 years later on the 28 April 2014 or when the GMIS-EB
fund is fully disbursed, whichever earlier. Participation in the
scheme will be on a first-come-first served basis, subject to avail-
ability of funds.
For more information on the Scheme, please refer to BCAs web-
site for more details.
Green Mark Gross Floor Area (GM GFA) Incentive Scheme
The Green Mark Gross Floor Area (GM GFA) Incentive Scheme
came into effect on 29 April 2009 for a periodof 5 years with a
mid-term review after 2 years ofimplementation. The Scheme was
introduced toencourage building owners/developers to accelera-
tethe adoption of environmental-friendly green building technolo-
gies and building design practices that will contribute to the sus-
tainable development of Singapore.
Building owners/developers can enjoy additional GFA allowed
over and above the Master Plan (MP) Gross Plot Ratio (GPR)
should their buildings achieve GM ratings of Gold
PLUS
and above.
The quantum of GM GFA allowed under the Scheme is up to 1%
for Green Mark Gold
PLUS
and up to 2% for Green Mark Platinum,
subject to a cap of 2,500m
2
for Gold
PLUS
and 5,000m
2
for Plati-
num.
Development that are eligible for the GM GFA Incentive Scheme
includes:
Residential non-landed, mixed commercial and residential
development and others (approved on a case-by-case basis)
Non-Residential commercial, office, retail, business parks,
industrial, institutional, community building, hotel, hospital, white
site development and others (approved on a case-by-case basis)
New private developments, redevelopments and reconstruction
developments which includes major additions and alterations to
existing buildings and major retrofitting to existing buildings as
deemed suitable for the GM GFA incentive scheme at BCAs sole
discretion
Government Land Sales (GLS) sites, except for sites in which
GM Platinum or Gold
PLUS
standards are mandated as part of the
sales condition. For sites where the Gold
PLUS
standard is man-
dated, the developer will still enjoy an incremental GFA incentive
if the developer attained the higher GM Platinum standard
Applicants who take up the GM GFA Incentive Scheme will not
be eligible for the GMISThe method of determining the GM GFA is
based on the following:
Proposed GFA (sqm) Prescribed Green
Equivalent
X
=
(subject to MP allowable intensity) Premium ($/sqm)
Bonus GFA
Land Value ($/sqm) (determined by proxy using DC rates)
Note: The additional GFA is subject to payment of
differential premium or development charge,
whichever is applicable.
For more information on the Scheme, please refer
to BCAs website for more details.
CURRENT CONSTRUCTION REGULATIONS
Legislation on Environmental Sustainability for Buildings
Since the launch of BCA Green Mark Scheme in 2005, BCA has
enhanced the Building Control Act to include a minimum environ-
mental sustainability standard that is equivalent to the Green Mark
Certified Level for new buildings and existing ones that undergo
major retrofitting.
The Building Control (Environmental Sustainability) Regulations
2008 stipulates a minimum Green Mark score of 50 for affected
building works. It applies to:
All new building works with Gross Floor Area of 2,000m
2
or more
Additions or extensions to existing buildings which involve
increasing Gross Floor Area of the existing buildings by 2,000m
2
or more
Building works which involve major retrofitting to existing build-
ings with existing Gross Floor Area of 2,000m
2
or more
Alterations to existing buildings which does not involve major retro-
fitting works is not subject to the new requirements.
The effective date of implementation will be based on the first sub-
mission date for URA Planning Permission on or after 15 April
2008.
With effect from 1 December 2010, the minimumenvironmental
sustainability standard has been revised. The compliance with the
respective environmental sustainability standards will be based on
the firstsubmission date for URA planning permission as stated in
the table below:
The requirements on environmental sustainability of buildings will
be integrated with the Building Plan process. The Qualified Person
(QP) who submits the Building Plan and the other appropriate prac-
titioners will be responsible for assessing and scoring the building
works under their charge using the criteria and scoring methodol-
ogy spelled out in the Code for Environmental Sustainability of
Buildings.
Under the Legislation, Green Mark assessments are no longer
required to be conducted as an independent third party certification.
Compliance to the regulations will be based on QPs declaration
and random audit and site checks prior or during Temporary Occu-
pation Permit (TOP).
1
ST
SUBMISSION DATE FOR
URA PLANNING PERMISSION
COMPLIANCE STANDARD
From 15 April 2008 to
30 November 2010
Code for Environmental
Sustainability for Buildings,
1
st
Edition, April 2008 issue
From 1 December 2010
onwards
Code for Environmental
Sustainability for Buildings,
2
nd
Edition, August 2010 issue
However, third party assessment by BCA will be conducted to
award projects with Green Mark Gold rating and above.
The BCA Green Mark has assessment criteria for three main
categories:
New Buildings
Existing Buildings and
Beyond Buildings
New buildings refer to new developments,redevelopments, addi-
tions and alterations to existing buildings and major retrofitting to
existing buildings. Existing buildings refer to buildings under opera-
tions with no significant retrofitting works. Lastly, beyond buildings
refer to new parks design and development, existing parks, office
interiors, infrastructure with no significant retrofitting works and
district development.
In line with the above new regulations, the BCA Green Mark
Assessment Criteria for New Buildings has been revised and will
take effect from 1 December 2010 onwards. All Green Mark appli-
cations for new buildings that are submitted on or after this date will
be assessed and certified based on this new version.
Append hereunder are the various Green Mark categories:
BCA Green Mark for Non-Residential New Buildings (Version
NRB/4.0) Applicable for new buildings such as offices, commer-
cial, industrial and institutional buildings with or without air-
conditioning systems.
BCA Green Mark for Residential New Buildings (Version RB/4.0)
Applicable for new private and public residential developments.
BCA Green Mark for Non-Residential Existing Buildings (Version
NREB/2.1) Applicable to existing commercial, industrial and insti-
tutional buildings under operation.
BCA Green Mark for Existing Residential Buildings (Version
ERB/1.0) Applicable for existing private and public residential
developments.
BCA Green Mark for Existing Schools (Version ES/1.0) Appli-
cable to Ministry of Education main stream schools (excluding
International schools, Universities and Institute of Higher Learn-
ing: Polytechnics and Institute of Technical Education.)
BCA Green Mark for Office Interior (Version 1.0) Applicable for
tenant renovation and maintenance practices.
BCA Green Mark for Landed Houses (Version LH/1.0) Applicable
for landed housing projects.
BCA Green Mark for Infrastructure (Version 1.0) Applicable for
infrastructure projects (e.g. barrages, roads, bridges, etc.)
BCA Green Mark for District (Version 1.0) Applicable for district
projects.
BCA Green Mark for Restaurants (Version 1.0) Applicable for res-
taurants.
The Green Mark rates the environmental friendliness of a building
based on a point scoring approach. Depending on the score, the
rating is categorized in four levels Platinum, Gold
PLUS
, Gold and
Certified
GREEN MARK RATING GREEN MARK POINTS GREEN MARK POINTS
WITH EFFECT FROM WITH EFFECT FROM
1 DECEMBER 2010 1 DECEMBER 2009
VERSION 4.0 VERSION 2.1
NON-RESIDENTIAL & NON-RESIDENTIAL
RESIDENTIAL BUILDINGS EXISTING BUILDINGS
Green Mark Platinum 90 and above 90 and above
Green Mark Gold
PLUS
85 to <90 85 to <90
Green Mark Gold 75 to <85 75 to <85
Green Mark Certified 50 to <75 50 to <75
GREEN MARK RATING GREEN MARK POINTS GREEN MARK POINTS
WITH EFFECT FROM WITH EFFECT FROM
19 MAY 2011 4 AUGUST 2011
VERSION 1.0 VERSION 1.0
EXISTING RESIDENTIAL EXISTING SCHOOLS
BUILDINGS
Green Mark Platinum 90 and above 90 and above
Green Mark Gold
PLUS
85 to <90 85 to <90
Green Mark Gold 75 to <85 75 to <85
Green Mark Certified 50 to <75 50 to <75
GREEN MARK RATING GREEN MARK POINTS GREEN MARK POINTS
WITH EFFECT FROM WITH EFFECT FROM
27 MAY 2009 27 MAY 2009
VERSION 1.0 VERSION 1.0
OFFICE INTERIOR & INFRASTRUCTURE
LANDED HOUSES
Green Mark Platinum 95 and above 90 and above
Green Mark Gold
PLUS
85 to <95 80 to <90
Green Mark Gold 75 to <85 70 to <80
Green Mark Certified 50 to <75 50 to <70
GREEN MARK RATING GREEN MARK POINTS PRE-REQUISITES
WITH EFFECT FROM
29 OCTOBER 2009
VERSION 1.0
T C I R T S I D
Green Mark Platinum 90 and above At least one building (GFA
> 5,000m
2
) at Phase I to
achieve Green Mark
Platinum
Green Mark Gold
PLUS
80 to <90 At least one building (GFA
> 5,000m
2
) at Phase I to
achieve Green Mark
Gold
PLUS
Green Mark Gold 65 to <80 At least one building (GFA
> 5,000m
2
) at Phase I to
achieve Green Mark Gold
Green Mark Certified 50 to <65 Nil
GREEN MARK RATING GREEN MARK POINTS
WITH EFFECT FROM
12 SEPTEMBER 2011
VERSION 1.0
S T N A R U A T S E R
Green Mark Platinum 95 and above
Green Mark Gold
PLUS
85 to <95
Green Mark Gold 75 to <85
Green Mark Certified 50 to <75
More information on the BCA Green Mark Scheme can be found
in BCAs website. (http://www.bca.gov.sg/GreenMark/green_
mark_buildings.html)
CURRENT CONSTRUCTION REGULATIONS
TOTAL NO. OF
BCA GREEN MARK BCA GREEN MARK
BUILDINGS RATED CHAMPION PLATINUM CHAMPION
Green Mark Gold and above At least 10 At least 50
Green Mark Gold
PLUS
At least 3 At least 15
Green Mark Platinum At least 3 At least 15
Source: Building and Construction Authority
BCA Green Mark Champion
The Green Mark Champion Award established in May 2008 was
an extension to the BCA Green Mark Award introduced in 2005.
This new award was created to recognize developers/building
owners with strong commitment towards corporate social respon-
sibility and outstanding achievements in environmental sustain-
ability. It is given to developers/building owners who achieve a
substantial number of Green Mark buildings at Gold level and
higher.
There are 2 categories for the award:
BCA Green Mark Champion
BCA Green Mark Platinum Champion
In addition to demonstrating strong commitment towards corpo-
rate social responsibility and environmentalsustainability,
developers/building owners must also meet the minimum criteria
set out below to qualify for the award:
CURRENT CONSTRUCTION REGULATIONS
Solar Capability Scheme (SCS)
In May 2008, the Clean Energy Programme Office (CEPO) (now
known as Energy Innovation Programme Office (EIPO)) of the Sin-
gapore Economic Development Board (EDB) announced the estab-
lishment of the SolarCapability Scheme (SCS). The primary purpose
of this scheme is to encourage the use of solar energy systems in
new developments, and also to build capacity within the local con-
struction industry for the implementation of such systems.
Under the scheme, building owners and developers may enjoy a
grant of 30% - 40% of the capital cost (capped at $1 million per proj-
ect) of installing solar energy systems in their new developments. It
is estimated that savings from the electricity generated by these sys-
tems will allow the owner to recover a further 50% of the capital cost
incurred. The initial budget for the scheme is $20 million, and the
quantum of grant is expected to be reviewed on a regular basis to
factor in changes in the prices of solar systems and energy prices.
Eligibility for the SCS is restricted to new buildings that have attained
a minimum Green Mark Gold standard (administered by the Building
and ConstructionAuthority), while buildings undergoing extensive
retrofit will be considered on a case-by-case basis. To qualify, a mini-
mum system size of 10kWp is required.
The following evaluation criteria determine the actual amount of the
grant:
a) Innovation
- Innovative application of solar technologies
- New products, technologies or solutions developed
b) Design
- Aesthetics of building and solar system design and integration
- Integration of solar technologies in the building's sub-system
c) Effectiveness
- Cost effectiveness of solar solutions
- Percentage of conventional electricity replaced
d) Skill Development
- Number of man-months of Singapore based staff involved in
solar related activities in the project
- Number of man-months of formal training
Disbursement of the grant is conducted in 2 phases as follows:
i. Capital Component:
70% of the grant to be disbursed from the start of the project
on a reimbursement basis
ii. Performance Component:
30% of the grant to be disbursed 2 years after the system
becomes operational, subject to the project meeting submitted
plans, including stipulated electricity output
CONSTRUCTION COSTS FOR SINGAPORE
The above costs are at 4th Quarter 2011 levels.
.
TYPES
LOW HIGH
S$/m
2
S$/m
2
RESIDENTIAL
Terraced Houses 2,400 2,650
Semi-Detached Houses 2,550 3,000
Detached Houses 3,000 4,000
Average Standard Condominium 1,850 2,100
Mid Range Condominum 2,100 2,800
Luxury Condominium 2,800 4,200
OFFICE
Average Standard Offices 2,400 2,600
Prestige Offices 2,600 2,900
COMMERCIAL
Shopping Centres, Average Quality 2,600 2,800
Shopping Centres, High Quality 2,800 3,100
Theatres / Cinemas 1,950 2,200
CAR PARKS
Multi-Storey Car Parks 900 1,300
Basement Car Parks 1,300 1,750
OVERALL COST
INDUSTRIAL
Flatted Light Industrial Buildings 1,250 1,400
Flatted Heavy Industrial Buildings 1,400 1,850
Single Storey Industrial Buildings 1,150 1,300
Flatted Warehouses 1,150 1,300
Single Storey Warehouses 1,000 1,300
HOTEL (Including F.F. & E.)
Resort Hotels 2,850 3,100
3-Star Hotels 2,950 3,200
4-Star Hotels 3,100 3,700
5-Star Hotels 3,750 4,300
Serviced Apartments 2,200 2,850
HEALTH
Private Hospitals 3,750 3,950
Polyclinics 1,550 1,750
Nursing Homes 1,550 1,850
Medical Centres 2,900 3,100
With effect from 1 March 2010, the eligibility for the SCS has been
revised as follows:
a) SCS will offset up to 30% of the total capital cost instead of 30%
- 40% of the capital cost
b) New buildings have to attained minimum Green Mark Gold
PLUS
standard instead of Green Mark Gold standard
c) Minimum system size of 50kWp is required instead of 10kWp
CURRENT CONSTRUCTION REGULATIONS
Revised Strata Landed Housing Guidelines Allowable
Number of Units per Development
With effect from 3 February 2009, the maximum number of allow-
able units in strata landed housing developments will be capped
based on a minimum plot size per unit for the respective conven-
tional landed housing form.
Under the new guidelines, the maximum number ofunits allowed
for strata landed housing developmentscomprising only 1 type of
housing form will be determined by the following formula:
The maximum number of units allowed for mixed strata landed
housing developments comprising more than 1 type of landed
housing form will be determined by the following formula:
(B x Y
B
) + (SD x Y
S
) + (T x Y
T
) Total Site Area of
Development
Where,
B = proposed number of strata bungalow units
SD = proposed number of strata semi-detached house
units
T = proposed number of strata terraced house units
Y
B
,Y
S
,Y
T
= plot size control for the relevant landed
housing form
2
Note:
Development applications (excluding Outline applications) sub-
mitted prior to 3 February 2009 which results in a Provisional Per-
mission will continue to be evaluated under the old guidelines
1
Where the formula does not result in a round number, the number of allowable
units will be rounded down to cater for each unit having the minimum plot size for
the proposed housing form
2
Y
B
= 400 sqm for Bungalow; Y
S
= 200 sqm for Semi-detached house; Y
T
= 150
sqm for Terraced house
Where Y = plot size control for the relevant landed
housing form
2
Number of Allowable