NIGER DELTA PETROLEUM RESOURCES LIMITED

44 East West Road, Rumuodara, Port Harcourt


END OF WELL REPORT
OGBELLE-1 INITIAL COMPLETION

1.0 Executive summary:


Ogbelle-1 is located in OML-54. Drilled in 1980 as an exploration well to a depth of 13600ft,
was temporarily abandoned with three strings of casing, 13-3/8, 9-5/8 and 7 casing cemented
in place. The G, E, D sands discovered in the well, were subjected to DST tests after
perforating casing. Thereafter, the well was abandoned with several 6 EZSV plugs and
squeezed off with 4 cement plugs totaling 800ft in the 7 casing while the 9-5/8 casing was
abandoned with 2 EZSV plugs and squeezed off with 3 cement plugs totaling 600ft.
The re-entry objective was to attain a two string dual (TSD) completion with the Long string on
the E6.0 and the short string on the D3.0 reservoirs.
DWC-10 a 525HP rig started operation on the well February 4, 2005. After initial wellhead rig
up, the rig commenced drilling out cement and plug from the 9-5/8 casing. While breaking a bit
connection during a bit change, the derrick shook violently, twisted and fell. This rendered the
rig not operable. Therefore, operation was therefore suspended on the February 16, 2005 to
enable the rig Debris be cleared and another rig sourced to continue with the operation.
DWC rig 20 a 1200HP was mobilized and accepted to commence operations June 14, 2005.
The original objectives of the reentry were then changed to include the deeper G3.0 reservoir
due to availability of the higher capacity DWC 20 rig. The well was then to be completed as a
Two String Multiple (TSM) with long sting, selective on the G3.0 and E6.0 reservoirs and the
short string on the D3.0 reservoir.
The 9-5/8 casing was then cleared of plugs and cement to top of liner at 10093ft. The integrity
of the sealing on the top liner was ascertained by performing inflow test on it. Thereafter the
cement and plugs in the 7 casing was drilled out to 13290ft.
Note that after drilling out the plug above the G1.0 at 12920ft, the reservoir pressure caused
the well to flow. This was brought under control with a mud weight of 0.5psi/ft.
Logs were taken and the G3.00, E6.00 and D3.00 sands were perforated. After perforating the
G3.0 Mod D packer was set above the G3.0 perforations after which a straddle packer
assembly was set above the G1.0 to isolate it from the well bore.
Tubing size 3-1/2 was ran as long string, 2-3/8 as short string and the well completed as a
TSM Two string Multiple with long string selective on G3.00 and E6.00 and D3.00.as short
string.
The strings were cleaned up and produced to clean reservoir fluids. Established rates are as
follows :

SAND

BEAN SIZE

G3.0

8
12
14
16
20
8
12
16
18
20

E6.00

D3.00

PRODUCTION
RATE

BSW

REMARKS

8
12
14
16
20

2.0. WELL PROGRAM AND AMENDMENTS


Original well program is attached as Appendix I
Amendment 1 to NDPR-1 (Otari) well initial completion program.
Background.
a. Prior to the incident of February 16, 2005, the DWC rig 10 had cleaned Ogbelle 1 well
bore in the 95/8 casing from surface to 9340ft. After the incident, the DWC rig 20 a
higher capacity rig was being mobilized to continue the well operation. Consequently,
the original clean up program and completion design is being amended.
b. Similarly, all efforts to set the test plug in the DCB for the purpose of testing the BOPS,
prior to 16th Feb were unsuccessful. In other to prevent difficulties landing the
completion strings in the DCB at the completion phase, it is planned to inspect the
DCB immediately after the rig acceptance audit as follows:
a. Check wellhead pressures and report to base immediately, if any pressure is
recorded. Further instructions will follow; otherwise continue with item2.
b. Open blind rams. MU 30ft x 31/2 DP below a retrievable packer + safety joint.
RIH ondps to 3000ft. Install Kelly cock inside BOPS. MU landing JT. Set
packer at cica 3000ft. Back off landing joint and suspend string 10ft below
wellhead.
c. Lift BOPS and inspect DCB. If okay, run plug tester to check bore. If okay, sit
hangers in DCB, if okay NU BOPS and test. If not okay replace DCB.
d. MU landing jt. Unset pkr, POH and LD.
e. Continue with item 7 on the main program.

AMENDMENT 2
AMENDMENT No. 3 TO NDPR-1 (OTARI) COMPLETION PROGRAM
A. BACKGROUND :
Most of the challenging well bore preparation is the 7 casing. It is intended to clean out to the
G3.0 sand with the DWC- 20, taking advantage of its higher hoisting capacity. Be that as it
may, all hands must be on deck to achieve a successful clean out operation.
The greatest challenge is to ensure successful runs with the Rock bit without loosing any cone
in hole.
After inflow testing TOL, D1.0 perforations and suspected casing suspect 9342ft continue as
follows.:
1. MU 6 PDC bit . RIH to TOL Continue drill out cement from 10000ft to top EZSV plugs
at 10777ft. Circ clean and POH.
2. MU 6 rock bit and RIH to 10777ft. Drill out EZSVs and cement until bit dull. Change
bit and drill out cement plus plugs top EZSV at 13290ft.
3. Circulate clean and displace hole to brine, SG. 0.452psi/ft. Observe well for 30mins.
4. POH Bit assy.
5. Make up and run in whole 6 tapered mill and tandem 7 and 9-5/8 scraper to top liner.
7 scraper should be spaced 3630 ft from 9-5/9 scraper(TOL to TD is 3629ft).
NOTE: At TOL, circulate and rotate tapered mill across TOL several times and continue
RIH to TD at 13290ft.
6. Carryout well bore cleaning as per well bore clean up program (Attached). Brine wt is
0.452 psi/ft. Target NTU is 20 and solid content is 10.
7. POH mill and tandem scrapers assy while laying down drill pipes.
8. Carryout routine BOP test

Wire line operations.


NOTE: The D3.000 sand has not been perforated before. Therefore the exact reservoir
pressure is not known. Similarly the G3.00 and E6.00 that were perforated were produced for
only two hours each, the reservoir pressures might also still be a little speculative.
It is recommended that special attention be paid to the well immediately after perforating each
interval and monitored through the perforation operations
1. RU Schlumberger
2. GR / CCL. From 13290 - 9000ft
3. Rig up shooting Nipple and install WL BOPs. Test WL BOPs to 1000psi
MU 20ft (10 + 10 with 8ft spacer) x 4-1/2 OD gun assembly ( HSD, power jet 4512,
12 spf, 135/45deg phasing, deep penetrating charges).
3

4. RIH and perforate G3.0 at 13256 13266ft and 13274 13284 ft.
Note: Fill up well with brine and check for losses/gain. Report to base if either occurs.
POH gun.
5. PU Mod D packer Size 84-32 with expendable plug installed set packer at 13200ft.
and POH
6. RIH 12ft x 4-1/2 OD gun assembly( HSD, power jet 4512, 12 spf, 135/45deg
phasing, deep penetrating charges) and perforate E6.0. at

10818 10830ft .

Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
POH gun.
7. RIH 6ft x 7 OD gun assembly ( HSD, power jet 4512, 12 spf, 135/45deg phasing,
deep penetrating charges and perforate D3.0 sand at 9476 - 9482ft.
Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
POH gun. POH gun.
Running 3-1/2 Completion Long string (L/S)
1. Prepare rig floor and rig up for running 3-1/2 tubing.
NOTE:

1. Tail pipe is 2-3/8 tubing.


2. Optimum MU Torque for 3-1/2 HCS is 3000ft-lb

2. RIH tail pipe assy.(2-3/8) + G- locator seal assy crossover to 3-1/2 HCS.
3. MU 3-1/2 tubing and RIH to Blast joint sub assy as per space out program.
4. MU Baker model HS packer and RIH. As per space out program.
5. MU Model GT dual packer assy with S/S tale pipe as per space out.
6. Continue RIH to12900 SCSSV depth.
7. Install safety valve. Flush control line and Connect to Safety valve.
8. RIH to 13100ft(top packer) and strap C/L
9. Lower string in slips. RU slick line.
10. Run 2.992 drift to top x/o at 13159ft.
11. POH and RD W/L.
12. PU string RIH and push out Expendable plug from Mod D packer.
4

13. Stab into Mod D with 15kips. Test annulus 500psi.


14. PU 1 ft and retest 500psi Annulus.

15. Space out string and install hanger.


16. Flush hanger and Install C/L to hanger.
17. MU landing Jt and Land string in DCB.
18. Remove landing Jt. Install NRV in hanger.
Running 2-3/8 Completion Short string (S/S).
NOTE: 1. Optimum MU Torque for 2-3/8 EUE Tubing is 1800ft-lb
Change pipe rams to 2-3/8 offcet.
PU tail pipe seal assy- shot string.
RIH to top GT Dual packer at 9399ft.
Circulate bottoms up.
Stab into GT dual packer with 10kips. Pull on string to snap out of packer.
Space out and install SCSSSV in string. Install Hanger. MU landing Jt . RIH and land
string in DCB.
7. RU W/L. RIH 1.875 drift to XN at 9417ft
8. RD W/L. Install NRV from hanger

1.
2.
3.
4.
5.
6.

Packer setting sequence.


1. RU landing Jt on L/S and install Circulating head. Drop 1-3/4 steel ball in long string.
Chase ball to bottom.
2. Pressure up string to set Mod HS packer in stages of 500 psi to 1500psi. Pressure up
further to 2500spi to test string. Observe pressure for 10mins. Pressure up further to
3000psi to shear out hydro trip sub.
3. Install NRV in hanger.
4. Retrieve NRV from S/S hanger. RU landing jt. Drop 1-3/4 steel bal in S/S and chase
ball to ball seat in Hydro trip sub at 9420ft.
5. Pressure up string to set Mod HS packer in stages of 500 psi to 1500psi. Pressure up
further to 2500spi to test string. Observe pressure for 10mins. Pressure up further to
3000psi to shear out hydro trip sub.
Well head operation.
1. Report to base if either occurs RD landing jt. Install TWCV in S/S. Retrieve NRV from
L/S and install TWCV.
2. Screw in all lock nuts on hanger. Energise hanger seals and test 500psi. through
annulus.
3. Flange down BOPS. Install X-mass tree. Test X-mass tree and valves to 5000psi.
4. Retrieve TWCV in hangers.
5. RU slick line. Open XA sleeve in L/S at 9459ft.

6. Displace L/S and S/S to diesel.


7. Close XA sleeve at 9459ft. Check sleeve closed by pumping 500psi into L/S. Observe
corresponding pressure in shot string gauge. Bleed off displacing pressures on both
strings. Record final pressures.
8. RD slick line. Install NRV in both strings.
SUSPEND WELL FOR RIG MOVE.
ADDENDUM 2 TO AMENDMENT No. 3 TO NDPR-1 (OTARI) COMPLETION
PROGRAM
A. BACKGROUND:
As a result of inadequate cement squeeze job on the perforations of the G1.0 sands which
gave rise to an inflow of gas from the reservoir, and subsequent well control wit 0.5 psi/ft mud
weight, it is imperative that we isolate the mobile G1.0 gas reservoir Thus still in current mud
mode operation will continue until the G1.0 reservoir has been isolated as follows:
1. Continue drilling out EZSVs and cement until bit dull. Change bit and drill out cement
plus plugs to top of EZSV at 13290ft.
2. Circulate clean with mud in hole of SG. 0.5psi/ft in and out with viscous spill. Observe
well for 30mins.
3. POOH Bit assy.
4. Make up and RIH 6 tapered mill and scraper from 10,093ft to 13,290ft
5. Circulate Hole clean and POOH

Wire line operations.


NOTE :
1. It is recommended that special attention be paid to the well at all times and especially
after perforating each interval.
2. Ensure that 50bbls LCM Pill is available at all times.
8. RU Schlumberger
9. RIH Junk basket - GR / CCL Gauge ring size 6.184 Log up between 13,290ft 9,000ft
10. Log RST at the following intervals
a.
b.
c.
d.
e.
f.
g.
h.

F3.0
F1.0
E10.0
E9.0
E8.0
E1.0
D1 & D3.0
E6.0

12,300 12,360 ftAHD


12,018 12,133 ftAHD
11,856 11,924 ft AHD
11,695 11,818 ftAHD
11,568 11,652 ftAHD
10,340 10,450 ftAHD
9,300 9,500 ftAHD
10,818 10,858ftAHD

11. Rig up shooting Nipple and install WL BOPs. Test WL BOPs to 1000psi
MU 20ft (10 + 10 with 8ft spacer) x 4-1/2 OD gun assembly ( HSD, power jet 4512,
12 spf, 135/45deg phasing, deep penetrating charges).
6

12. RIH and perforate G3.0 at 13256 13266ft and 13274 13284 ft.
Note: Fill up well with brine and check for losses/gain. Report to base if either occurs.
13. POH gun
14. PU Mod D packer Size 84-32 install set packer at 13200ft. and POOH
15. RD Schlimberger.
16. MU on DP Model FBGP Packer plus tail assembly
17. RIH and stab into Model D packer at 13, 200 ft. Pull up 1ft.
18. Check stabbing 500psi through annulus, if okay set Model FBGP 12,850 ft
19. Set packer according to Baker Engineers instruction.
20. Release setting tool and pick up combo tool 5ft above port collar. Slack off and open
port collar. Close Annular preventer and test pkr setting 500psi and report result
immediately to base( Ilesanmi )
21. Pick up +- 20ft and close port collar. Release dogs.
22. Pull out further to Top packer at 12850ft. Circ hole to Brine 0.45psi/ft. Observe well for
30mins. If no flow proceed to item 16. If there is flow, report to base immediately
( Ilesanmi ).
Note: Brine wt increase may be advised.
23. POOH setting tool assembly and L/D drill pipe.

Wire line operations.


1. RU Schlumberger
2. Rig up shooting Nipple and install WL BOPs. Test WL BOPs to 1000psi
3. RIH 12ft x 4-1/2 OD gun assembly( HSD, power jet 4512, 12 spf, 135/45deg
phasing, deep penetrating charges) and perforate E6.0. at

10818 10830ft .

Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
POH gun.
4. RIH 6ft x 7 OD gun assembly ( HSD, power jet 4512, 12 spf, 135/45deg phasing,
deep penetrating charges and perforate D3.0 sand at 9476 - 9482ft.
Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
5.POH gun.

CONTINUE WITH RUNNING completion long string till end of program as in


amendment 3
ADDENDUM No. 3 AMENDMENT 3 TO OGBELLE 1 COMPLETION PROGRAM
1.0 BACKGROUND:
It is desired to investigate the anomaly observed on the recently concluded D3.0 reservoir RST
log, before completing Ogbelle-1 as a TSM. The most technically and commercially viable
method has been considered to be a quick production test on the reservoir.
2.0 Well bore condition:
1. The well bore is stable, brine wt of 0.48 psi/ft.
2. G3.0 sand perforated and exposed.
3. G1.0 has been straddled behind blank pipe.
3.0 Program
After pulling out of hole the Baker and TAM setting tools, if Schlm. is already at well site,
proceed with item 1 otherwise report to base for further instructions:
1.
2.
3.
4.
5.
6.
7.
8.
9.

RU schlm. and shooting Nipple.


Perforate E6.0 sand at 10818 10830ft .
Perforate D3.0 at 9476 9482ft. RD Schlm.
RIH 7 Retrievable packer assy + Storm Choke and 1500ft of 3-1/2 drill pipe tail.
Set packer at 10,200ft to isolate bottoms perforations.
POH Storm choke setting tool.
MU 9-5/8 Retrievable packer + 30 x 3-1/2 ft tail to tail at 9450ft.
Displace string to Diesel and create 682-psi draw down.
Open up well to choke manifold. Record well pressures immediately to Base. Observe
well for flow.
NOTE : 1. Report well rate every hour to base.
2. Production test may be terminated immediately.
Further instructions will depend on production test.
ADDENDUM 4 TO AMENDMENT No. 3 TO NDPR-1 (OTARI) COMPLETION PROGRAM
1.0 RUNING COMPLETION STRINGS
1.1 RUNNING OF 3-1/2 LONG STRING COMPLETION
NOTE:
Ensure that tubing Rubber protector is used.
Ensure that the trip tank is used at all times
Ensure that all safety precautions are taken and adhered to while RIH and strapping
Control Line.
Ensure that all completion tubular are drifted/washed on the rack before PU and RIH.
They should be further drifted while PU as well.

NOTE : Prepare rig floor & R/U 3-1/2Completion running gear for tail pipe assy. Ensure that
appropriate crossover subs from 3-1/2 tubing to Kelly cock are available on the rig floor and
properly made up. Hold pre job/tool box meeting prior to commencing RIH.

M/U and RIH completion sub assemblies as follows:


Assy No. 1

3 Half Mule Shoe sub assy


3 HCS Pup Joint
Otis XN Nipple, 3 1/2 HCS
3 1/2 HCS Pup Joint

Assy No. 2

3 1/2 HCS Pup Joint


Baker G-Locator sub + E- Seals, Size 80-40 with 3 1/2 HCS
3 1/2 HCS Pup Joint
Appropriate length of 3-1/2 HCS Tubing

Assy No. 3

3 HCS Pup Joint


Blast joint x 40 ft.

Appropriate length of 3-1/2 HCS Tubing


Assy No. 4

3 1/2 HCS Pup Joint


3 1/2 Otis XA Sliding Sleeve
3 1/2 HCS Pup Joint

Appropriate length of 3-1/2 HCS Tubing


Assy No. 5

3 1/2 HCS Pup Joint


3 1/2 Otis 7 Baker HS Packer
3 1/2 HCS Pup Joint

Appropriate length of 3-1/2 HCS Tubing


Assy No. 6

3 HCS Pup Joint


Blast joint x 20 ft.

Appropriate length of 3 HCS Tubing


Assy No. 7

3 1/2 HCS Pup Joint


3 1/2 Otis XA Sliding Sleeve
3 1/2 HCS Pup Joint

Appropriate length of 3-1/2 HCS Tubing


Assy No. 8

3 1/2 HCS Pup Joint


GT Double Grip packer 9 5/8

Long string

3 1/2 HCS pup joint


Assy No. 9

3 1/2 HCS tubing x 30 ft long


3 1/2 Otis XA Sliding Sleeve
3 1/2 HCS Pup Joints

Assy No.10

XN Nipple 3 1/2 HCS


3 HCS Pup joint x 10 ft

made up below the short

string
3 Perforated production tube
(Modified)

RIH completions string slowly to top of Liner, before entering the liner record
UP/DOWN weights. Slowly pass the tail pipe and HS packer into the liner.

Note:
Maintain safe speed to avoid packer setting prematurely.

RIH to +/-10ft above FBGP-1 packer at +/- 12,850 ftah. Record up & down weight and
reverse circulate twice string content with a maximum surface pressure of 500 psi.

Note;
Do not exceed MSP of 500 psi to avoid setting the packer pre-maturely.

RIH slowly and stab 80-40 seals into FBGP-1 packer at 12850ft. Set down 10kips.
Pick up the string to its neutral weight. Close annular BOP and test stabbing with
500psi. If ok Pull up 2ft and recheck stabbing with 500psi. If OK. Pull up the long string
10ft above FBG-1 pkr.
RU the Flow head/Flow TEE, Slick line BOP, and lubricator and test to 3000psi.
RIH with a 2.75 Gauge Cutter (GC) to drift the tubing to XN-Nipple at +-12,860 ft,
and lay down. Rig down slick line equipment.
POH in stands as per space out plan up to the TRSCSSSV position and set slips.
Note:
1. Ensure clean return is observed.
2. When spacing out, the TRSCSSV should be positioned at approximately 120 ft below
the THS. The length of the control line reel should also be considered when spacing
out so as to ensure that the control line would get to the rig floor after final string
landing.

Make up the dummy tubing hanger (without seals) and landing joint on the long string,
and slowly land the hanger in the THS. Remove the landing joint. Clean, grease and
install 3 NRV in the hanger.
Note:

The tubing length pulled out, the GT Dual Grip packer depth, and the
correct length of space out pups required.

Ensure that the tubing hanger seals are removed during this first run to
avoid being damaged.
10

1.2

RUNNING OF 2 3/8 SHORT STRING COMPLETION

Make up Snap Latch with 80-37 seal assembly and run in hole with the short string to
+/- 200ft above the MOD GT packer.

Circulate bottoms up.

Install the tubing hanger and hang off the short string. Clean, grease and install 3
NRV in the hanger.

Note:
Ensure x/over is available to properly land tubing hanger.
Ensure that the short string tubing hanger seals are removed during this first
run to avoid being damaged.
Ensure also the 3 IF box x 3 HCS pin to the Kelly cock.
1.3 LANDING LONG STRING

Retrieve the 3 NRV from the LS.


Install landing joint on the LS hanger, and pull the hanger 2 ft above the rig floor, and
Set slips.
Remove the tubing hanger from the LS.

Pull back the string up to the TRSCSSV installation position.

Pick up and MU TRSCSSSV sub-assembly to the string as per space out plan.

Assy No. 11 Pup joint


Baker TE-5 TRSCSSSV, 3 1/2 x 2.81 ID
Pup joint
Note:

Flush the control line and connect to the TRSCSSV. Test the control line against the
TRSCSSV valve to 5,000 psi for 15 mins. Bleed down pressure to 3000psi.

Strap the control line at three places on each tubing joint, with bandit clamps and
buckle (one each close to the tubing collar and one at the middle of the tubing.

Note:
1. Ensure that the clamps are tight so as to avoid control line slack.
2. Ensure that the control line pressure is monitored through a gauge while strapping and
RIH.

MU Tubing Hanger assembly to the string. Install seals. MU landing joint unto the
hanger.
Assy No. 12

3 HCS Pin x Pin


11 x 3 Split Hanger

11

Bleed off pressure from control line. Connect 1/4" NPT x 1/4 swage lock with control
line extension on the top side of the hanger and flush the hanger control line ports, top
to bottom.

Connect the control line to the 1/4" NPT port underside of the hanger. Pressure up to
5000psi for 15mins from the top of the hanger to test the connection for leaks.

Note:
1. Record UP and DOWN weight.
2. Position slips carefully to avoid crushing control line

Slowly lower the string and land split hanger in THS. Continue to monitor the
Control line pressure while landing the hanger in the THS.

1.4

SPACING OUT SHORT STRING

Remove 3 NRV from SS hanger. Engage short string with landing joint and pull
Tubing hanger to rig floor. Remove tubing hanger.

RIH Anchor Latch seal assy and Stab into GT packer at +/-9,400ft with 11kips, (mark
pipe at rotary table for space out). Pull 5kips to confirm anchorage. Slack off to
neutral wt .
Rotate string ( +/-4 at 9800ft) right hand turn at neutral point. Pick up slowly to
retrieve seal assy from GT packer.

Note: Extreme care needs to be taken to avoid backing off the string.

Pull up to TRSCSSV installation position (+/- 90 below rotary table). Install TRSCSSV
assembly

Flush control line and connect to SCSSSV. Test control line to 5000 psi against valve.
Bleed down pressure to 3000 psi. Strap control line with bandit clamps in three places
on the tubing, close to each end and one in the middle. (Maintain 3000 psi on control
at all times) Run the tubing in the hole slowly.
Note:
Continue monitoring C/L pressure on L/S.

Make up SS tubing hanger and bleed off pressure on the control line. Flush control
line port on hanger. Connect nipple with control line extension on top of hanger.
Connect control line at the bottom of hanger. Pressure up control line to 5000 psi and
check for leaks, if ok, bleed off pressure to 3000 psi and maintain this pressure on
control line.

Make up landing joint on the hanger. Lower the string slowly and land short string in
the THS.

12

Note:
The BOP and Riser stack should be drained before landing hanger
The Tie-down bolts should be fully retracted after draining the BOP stack, and the bore
of the THS should be flushed with water to get rid of any debris that may be lodged
around the THS bore.
Remove the master bushing to allow passage of the Tubing Hanger through the Rotary
Table.
Ensure that the landing joint make-up torque is half the recommended torque for the
tubing (easy back-off).
1.5

SHORT STRING TEST:

RU Flow head/Flow TEE and Slick line BOP and lubricator on the S/S, and pressure
test the assembly to 3000 psi. .

Note:
Pump open the TRSCSSV and keep in open position on the hand pump through out the
duration of the slick line operation.

RIH on the S/S with a 1.85 GC to the 2-3/8 XN-Nipple position at +/-9460ft, POH
GC.
Install 1.85 QTT in XN nipple @ +/-9,022ft and slack off wire. Fill string and
lubricator and pressure up tubing in stages of 500 psi. to 3000 psi for 15 minutes.
Check annulus for returns, if OK, take some tension on the wire and bleed off
pressure slowly to zero. Retrieve QTT to surface.
Note:

1.6

Ensure C/line is monitored during the test at the hand pump(which should
be locked close).
Before pressurizing, fill up annulus.
Ensure the THS outlet valves are open before pressure testing.

Rig down slick line equipment.


Back off landing joint and install 3 NRV in S/S tubing hanger.
Tighten the Hanger Tie-down bolts evenly, and ensure bolts are fully located into the
tubing hanger groove.
Inject plastic sticks to energise the hanger seal as required.
Test the Hanger Seals from below, by pressuring the annulus through the THS outlet
line to 500 psi for 15 mins. Bleed-off pressure to zero and then re-tighten the Tie-down
bolts.
SLICK LINE OPERATIONS TO SET PACKERS & TEST LONG STRING

RU the Flow head/Flow-TEE, Slick line BOP, and lubricator and test to 3000psi.
Pump open the TRSCSSV.

13

Note:
Pump open the TRSCSSV and keep in open position on the hand pump through out the
duration of the slick line operation.

RIH 2.75 QTT and set in XN at +/-12860 ft.


Fill up the string and lubricator and pressure up gradually in stages of 500 psi to
1500psi to set HS packer and GT packers. Pressure up further to 3000 psi for 15
minutes to test string.
If ok, bleed off pressure to 0psi as the W/L picks up the QTT. POH QTT.
Check GT packer setting 500psi annulus. If OK.

Note:
Ensure the build up/bleed down are done gradually and recorded.
Ensure C/line is monitored during the test at the hand pump(which should
be locked close).
Before pressurizing, fill up annulus.
Ensure the THS outlet valves are open before pressure testing.
RIH shifting tool and open XA sleeve at +/-9459ft.
POH shifting tool and RD Slickline.
Back off landing joint and install 3 NRV in the L/S tubing hanger.
2.0

WELLHEAD MAKE-UP AND TESTING


Note:
Ensure that no debris enters the control line or test port on the Xmas Tree by flushing
and plugging them off before PU and NU Xmas Tree.
Mark the control line and the test port before PU and MU the Xmas Tree.
Nipple down BOP
Clean the top of the Tubing Hanger, and the THS flange guard and ring gasket. Install
the ring gasket on the THS gasket groove. Install the seal sub & seal pad on the
Tubing Hanger neck. Flush the test port and the control line port on the Xmas tree.

Nipple up the Xmas Tree on the THS. Pressure test Xmas Tree gasket sealing through
the test port to 5,000psi for 15 mins. Bleed off.

Retrieve both NRVs from the strings and install TWCVs in both string hangers.
Pressure test the Tree and flow line valves against the TWCV and 11" x 5K flanged
connection to 5,000psi for 10 mins. Bleed off pressure to zero and retrieve the TWCV
from both strings.

3.0

DISPLACING STRINGS TO DIESEL


Displace both strings to Diesel oil Long string in S/S out.

Rig up W/L. on L/S. RIH shifting tool and close SSD at +/-9459ft.
Apply 500 psi on SS and check sleeve closed. If OK, RD W/L
Record Well head pressures

14

4.0 SECURING AND WELL HANDOVER


. Install NRV in hangers
Close all wellhead valves and remove hand wheels. Install name plate indicating L/S
and S/S strings (API) Standard.
SUSPEND WELL FOR RIG MOVE.

15

INITIAL STATUS DIAGRAM/COST

OGBELLE

- 1 WELL STATUS DIAGRAM as at 1/1/2003

30 Stove Pipe to 24

20 cemented with 800 sacks

20 Conductor to 505

Cement Plug 1000


13 5

/8

No returns; tailed with 1000 sacks

1200

cemented with 3000 sacks; tailed with 500 sacks

13 3 / Casing 54# X.55 Buttress to 5529


8

Cement Plug 9280


EZSV @ 9330
Perfd

- 9330

9428 with 17.5 bbl cement

9330 37;1/2 holes; 4 SPF;

Not Tested; squeezed with 75 bbl cement


Perfd

D1
Sa
nd

9382 88 ;1/2 holes; 4 SPF;

Test #6 ; no flow to surface


Perfd

9405 - 11;1/2 holes; 4 SPF;

Perfd

9422 - 28;1/2 holes; 4 SPF;

Test #5 2000bw/d w/traces 55.2

}
}

oil,; 3030

mscf /d gas; squeezed with 18 bbl cement

EZSV @ 9700

Cement Plug 10000

- 10200

9 5 / cement not clear

- Tagged cement @ 5294 & .

Top Liner 10093


8

9 5 / Casing to 10250; 47# N


8

- 80; Buttress

CBL shows poor bond

- squeezed shoe with 18 bbl cement

Cement Plug 10600


EZSV @ 10777 squeezed 12.5 bbl cement into formation

6
Sa
nd
E

Perfd

- 38;1/2 holes; 4 SPF;

10822

bopd (43.6 o), 4020

Test #4 2685

mscf /d

Cement Plug 12475


EZSV @ 12700
Cement Plug
EZSV @12920; squeezed with 58 sacks cement

1
Sa
nd
G

Perfd

12955

- 58;1/2 holes; 4 SPF;

Perfd

12963

- 69;1/2 holes; 4 SPF;

Test #3 451

bopd (46.8

o ),

13400

}
WELL

mscf /d

DATA

Derrick Floor Elevation

40'

Kelly Bushing

41'

Ground Level

21.7'

Datum

- Top CHH

Datum

- Top Tree

Spud Date

6/4/80

Date Suspended

6/8/80

Initial Completion Date

Recompletion

10

Casing Data

7 Liner cemented with 1650 sacks


Class G + additives

Loose EZSV @ 13170


Cement Plug 13170
EZSV @ 13220

Perfd

3
Sa
nd
G

Perfd

13258

13270

Test #2 403

- 66;1/2 holes; 4 SPF;

- 76;1/2 holes; 4 SPF;

bopd (47.3

o ),

13300

- 13220

mscf /d
Date

EZSV @ 13290
Perfd

13307

- 20;1/2 holes; 4 SPF;

N80 9

Test #1 small blow; no flow to surface (3 tests

N80 7"

Total)

Plug Depth 13609

5/

#47

#29

11

No. of Joints L/S

12

No of Joints SS

13

Fluid in Hole

10250
13650

7 shoe @ 13650

16

PLAN ACTIVITY TIME CHART FOR TSD COMPLETION.

Operation

Planned
Hrs

Mobilization
Accept Rig from DWC
Cleanout 9.5/8" Casing
NU 13.5/8" BOP. Test same
Mix Gel/Water mud
M/U 8-1/2" bit and BHA.
Fishing Operations for lost Shackle
RIH and drill out cement plug at 1000ft
Casing Test and BOP Test
RIH and wash down to 9200ft
Pressure test casing to 2000 psi
Casing Test Fails
Tag cement plug at 9280 ft and drill out to 9330ft
Drill out EZSV.
Drill and wash down to 9700 ft, tag and drill out EZSV
Unable to drill EZSV
Drill out junk and cement to 10093ft (TOL)
Circulate clean and POOH
RIH Reverse Circ JB and 9.5/8" scraper to TOL
POOH
M/U RTTS and RIH to 9250 ft.
Displace DP to diesel
Set Pkr. Inflow test below pkr
Inflow Test fails
POOH
Cleanout 7" Liner
Make up 6" bit & BHA and RIH to TOL.
Drill out cement and run into liner
Tag cement at 10600ft and drill out
Drill EZSV at 10777ft
Clean out and push junk to 11,850 ft
Cleanout 7" Liner to 13290 ft
Circulate clean and POOH
Evaluate and prepare hole
Rig up electric wireline and run RST log
Make up 7" and 9.5/8" scraper assembly and RIH
Circulate and work scrapers.
Pump clean up sweeps and displace to filtered inhibited brine
Circulate until NTU<20
POOH laying down DP

12.00
4.00
2.00
0.00
8.00
0.00
16.00
1.00
1.00
4.00
6.00
36.00
6.00
10.00
10.00
8.00
9.00
2.00
4.00
8.00
15.00
2.00
4.00
6.00
3.00
13.00
24.00
11.00
2.00
6.00
6.00
20.00

17

Perforate
M/U TCP guns to perforate D3 zone 9480 - 9490
RIH on 3-1/2" HCS tubing
Correlate with wireline
Set pkr and fire guns
Reverse out and kill well. Circulate well in balance
POOH and lay down spent guns
M/U TCP guns to perforate E6 zone 10820 - 10843
RIH on 3-1/2" HCS tubing
Correlate with wireline
Set pkr and fire guns
Reverse out and kill well. Circulate well in balance
POOH and lay down spent guns
R/U wireline and RIH DAB pkr and set at 10788
POOH
Complete
Rig up to run completion
Make up LS tailpipe, dual packer and SS tailpipe
RIH LS tubing to top of DAB packer
Tag pkr, mark for space out and POOH to SSSV depth
PU L/S and install TRSSSV, control line, space out and land
RIH L/S and stab into pkr. Test ann to 500 psi
Pressure up on tubing to set pakr. Test tbg and trip Hydrotrip
Install NRV in hanger of LS.
M/U SS latch and sub assemblies
RIH picking up 2-3/8" tubing
PU S/S. Reverse out debris and stab into pkr. Pull back and install
TRSSSV sub assbly and c/l. Space out and land
P test S/S and trip hydrotrip sub
Install Hgr and NRV
ND BOP
NU and test tree
RU slickline and open sleeve at 9460 ft on LS
Displace both strings to diesel
Close sliding sleeve
Rig Down

4.00
21.00
4.00
2.00
6.00
10.00
4.00
12.00
4.00
2.00
8.00
9.00
6.00
3.00
4.00
6.00
12.00
2.00
4.00
2.00
1.00
1.00
2.00
19.00
4.00
1.00
1.00
4.00
8.00
8.00
6.00
4.00
4.00

18.63
Baseline Operational Times
Assume 8% NPT for the rig

20.12

18

3.0. DETAIL EXECUTION REPORT


ACTUAL STATUS DIAGRAM/COST
STATUS :- PROPOSED INITIAL COMPLETION DIAGRAM

WELL:

CASING
SIZE

30
13 3/8
9-5/8
7

STOVE
X-55
N80 BTC
N80 SLX

DEPTH (ft)

CEMENT G

PIPE
55
47
29

24
5529
10250
13650

DRIVEN
CEMENTED
CEMENTED
CEMENTED

TUBING
WT GRADE

STRING SIZE

L/S

3-1/2 9.3
+ 2-3/8 4.7

S/S

2-3/8

4.7

N-80

ITEM

HCS/EUE

SAND PERFORATIONS

SIZE (INS)

COOPER

DSB
N/A
DCB
DCB
N/A

3 x 3
11x 3-1/8x 3-1/8
11x 3-1/2HCS x3-1/2

WP (PSI)

5000
5000
5000 W/CLP

TUBING SPOOL
11x 13-5/8
5000 x 3000
RISER
T CONNECTION
BACK PR. VALVE
CSG. H. HOUSING
WF
13-3/8 x 13-5/8
3000 X 5000
CSG. H. SPOOL
SEAL BUSHING
X
11 X 13-5/8
HOLE
OPEN HOLE PLUGS ACTIVITY MAX.SG RESERVOIR DATE
ALL
06/04/80
DRILLED
IC
June05

Zero deg

HCS
HCS
DFE
ORDF-TCHH
ORDF-TOP XMT

TYPE

GATE VALVE
XMAS TREE
ADAPTER FLANGE
TUBING HANGER

DEVIATION
TYPE

N80
N-80

NDPR - 01

WELLHEAD

WT.

GRADE

40.00 FT
XXXFT
XXX FT

STATUS

DEPTH (FT) STR

90
120

30STOVE PIPE

S/L
S
S
L

ID
2.99
1.99
1.87
2.81

DESCRIPTION
OD
3.99 X-OVER 3-1/2HCS (P x P)
3.99 X-OVER, 3 HCSb X 2 3/8 HCSp
2.75 2 3/8 EUE 8rd bxp TE-5 TRSCSSSV w/X Profile
5.25 3 HCS bxp TE-5 TRSCSSSV

@ 24 ft

20 CONDUCTOR
@ 505 ft

13 3/8 CASING
@ 5529ft

D3.0

9476 9482 FT
(6 FT PERF.)

3.75 2.99 J LOCK ANCHOR LATCH SEAL NIPPLE 3 1/2NV p


8.63 2.99 9 5/8 GT DOUBLE GRIP PACKER

9392
9400

9414

1.99

9424
9427
9459

S
S
L

1.99 2.37 PERFORATED PUP JT. 2 3/8HCS


1.99 3.10 MULE SHOE, HCS BOX Up
4.25 2.81 MOD. L SLIDING SLEEVE DOOR 3 1/2 HCS

9469-9489

2.92 3.99 BLAST JOINT 20 FT LONG 3 1/2 HCS

2.37

XN NIPPLE 2 3/8HCS

TOP LINER 10093FT


9-5/8 CASING SHOE
@ 10250 FT-AH

10300
10790

E6.0

10818 10830 FT
(12 FT PERF.)

G1.0

SEQUEZEED OFF

G3.0

13256 13266 FT
&
13274 13284 FT

LOGS

7 LINER SHOE @ 13650ftah

10804-10844

12853
12853
12857
12856
12864
12870
12875
12876
12916
12921
13216
13219
13217
13237
13242
13280

TD = 13920 FT

5.91 2.92 BAKER MOD 7 HS PACKER SIZE 591-292

4.25

L
L
L
L

L
L
L
L

2.81 MOD. L SLIDING SLEEVE DOOR 3 1/2 HCS

2.92 3.99 BLAST JOINT 40 FT LONG 3 1/2 HCS

2.92 4.00 G-LOCATOR, 3 1/2 HCS b X p


4.00 5.875 BAKER MOD FBGP PKR, SIZE 85-40 W/ 5 STC b
2.92 4.00 BAKER 80-40 SEAL ASSY
4.77 5.50 MILLOUT EXTENSION 5 STC(P x P)
2.92 3.99 OTIS XN NIPPLE 3 1/2 HCS
2.92 3.99 MULE SHOE, 3 HCS
3.875 5.80 X-OVER SUBS: 5 LTC(B) x 4 BTC(P)
4.00 5.00 BLANK PIPE W/ 4 11.6# BTC b X p
3.93 5.13 PORTED COLLAR W/ 4 BTC b X b
4.00 5.00 BLANK PIPE W/ 4 11.6# BTC b X p
2.44 4.70 G-LOCATOR SIZE 80-32, 2 7/8 EUE b X p
3.25 5.875 MODEL D PACKER, SIZE 84-32
2.44 3.25 80-32 SEAL ASSY. W/8 SEAL UNITS
1.81 2.75 OTIS XN NIPPLE 2-7/8HCS
1.99 3.10 2 3/8 RATCHETING MULE SHOE
TOP OF PLUG

AUTHOR: CONSULTANT ENGR

PREPARED BY:
ALAKE, O.A

DATE:03 / 08 / 05

PLANNED/ACTUAL TIME CHART


Attached as appendix 2

19

PLANNED /ACTUAL SUMMARY SHEET


Activity

Planned
time
4.38 days

Clean out
95/8 casing
Cleanout 7 1.79 days
liner
Evaluate
2.88 days
and Prepare
hole
Perforations 3.96 days

Actual time

Remarks

33.88days

NPT 12.25 days (Unplanned events; Inspect DCB)

12.46 days

NPT 2.02days (Unplanned events; changed TD


from 11850ft to 13290ft, well control situation
NPT 2.75 days (Unplanned RST runs, Testing BOP
unplanned)

5.48 days
7.81 days

NPT 1.375 days (unplanned Isolation of G1 sand,


production testing of the D3 sand )

Completions
NB: Details of NPT are attached in Appendix 3

20

5.0. ANALYSIS OF DIFFERENTIAL TIME.


6.0. BUDGET
- PLANNED/VALUE OF WORK DONE.
7.0. CONCLUSION
8.0. RECOMMENDATION

21