Beruflich Dokumente
Kultur Dokumente
SAND
BEAN SIZE
G3.0
8
12
14
16
20
8
12
16
18
20
E6.00
D3.00
PRODUCTION
RATE
BSW
REMARKS
8
12
14
16
20
AMENDMENT 2
AMENDMENT No. 3 TO NDPR-1 (OTARI) COMPLETION PROGRAM
A. BACKGROUND :
Most of the challenging well bore preparation is the 7 casing. It is intended to clean out to the
G3.0 sand with the DWC- 20, taking advantage of its higher hoisting capacity. Be that as it
may, all hands must be on deck to achieve a successful clean out operation.
The greatest challenge is to ensure successful runs with the Rock bit without loosing any cone
in hole.
After inflow testing TOL, D1.0 perforations and suspected casing suspect 9342ft continue as
follows.:
1. MU 6 PDC bit . RIH to TOL Continue drill out cement from 10000ft to top EZSV plugs
at 10777ft. Circ clean and POH.
2. MU 6 rock bit and RIH to 10777ft. Drill out EZSVs and cement until bit dull. Change
bit and drill out cement plus plugs top EZSV at 13290ft.
3. Circulate clean and displace hole to brine, SG. 0.452psi/ft. Observe well for 30mins.
4. POH Bit assy.
5. Make up and run in whole 6 tapered mill and tandem 7 and 9-5/8 scraper to top liner.
7 scraper should be spaced 3630 ft from 9-5/9 scraper(TOL to TD is 3629ft).
NOTE: At TOL, circulate and rotate tapered mill across TOL several times and continue
RIH to TD at 13290ft.
6. Carryout well bore cleaning as per well bore clean up program (Attached). Brine wt is
0.452 psi/ft. Target NTU is 20 and solid content is 10.
7. POH mill and tandem scrapers assy while laying down drill pipes.
8. Carryout routine BOP test
4. RIH and perforate G3.0 at 13256 13266ft and 13274 13284 ft.
Note: Fill up well with brine and check for losses/gain. Report to base if either occurs.
POH gun.
5. PU Mod D packer Size 84-32 with expendable plug installed set packer at 13200ft.
and POH
6. RIH 12ft x 4-1/2 OD gun assembly( HSD, power jet 4512, 12 spf, 135/45deg
phasing, deep penetrating charges) and perforate E6.0. at
10818 10830ft .
Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
POH gun.
7. RIH 6ft x 7 OD gun assembly ( HSD, power jet 4512, 12 spf, 135/45deg phasing,
deep penetrating charges and perforate D3.0 sand at 9476 - 9482ft.
Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
POH gun. POH gun.
Running 3-1/2 Completion Long string (L/S)
1. Prepare rig floor and rig up for running 3-1/2 tubing.
NOTE:
2. RIH tail pipe assy.(2-3/8) + G- locator seal assy crossover to 3-1/2 HCS.
3. MU 3-1/2 tubing and RIH to Blast joint sub assy as per space out program.
4. MU Baker model HS packer and RIH. As per space out program.
5. MU Model GT dual packer assy with S/S tale pipe as per space out.
6. Continue RIH to12900 SCSSV depth.
7. Install safety valve. Flush control line and Connect to Safety valve.
8. RIH to 13100ft(top packer) and strap C/L
9. Lower string in slips. RU slick line.
10. Run 2.992 drift to top x/o at 13159ft.
11. POH and RD W/L.
12. PU string RIH and push out Expendable plug from Mod D packer.
4
1.
2.
3.
4.
5.
6.
F3.0
F1.0
E10.0
E9.0
E8.0
E1.0
D1 & D3.0
E6.0
11. Rig up shooting Nipple and install WL BOPs. Test WL BOPs to 1000psi
MU 20ft (10 + 10 with 8ft spacer) x 4-1/2 OD gun assembly ( HSD, power jet 4512,
12 spf, 135/45deg phasing, deep penetrating charges).
6
12. RIH and perforate G3.0 at 13256 13266ft and 13274 13284 ft.
Note: Fill up well with brine and check for losses/gain. Report to base if either occurs.
13. POH gun
14. PU Mod D packer Size 84-32 install set packer at 13200ft. and POOH
15. RD Schlimberger.
16. MU on DP Model FBGP Packer plus tail assembly
17. RIH and stab into Model D packer at 13, 200 ft. Pull up 1ft.
18. Check stabbing 500psi through annulus, if okay set Model FBGP 12,850 ft
19. Set packer according to Baker Engineers instruction.
20. Release setting tool and pick up combo tool 5ft above port collar. Slack off and open
port collar. Close Annular preventer and test pkr setting 500psi and report result
immediately to base( Ilesanmi )
21. Pick up +- 20ft and close port collar. Release dogs.
22. Pull out further to Top packer at 12850ft. Circ hole to Brine 0.45psi/ft. Observe well for
30mins. If no flow proceed to item 16. If there is flow, report to base immediately
( Ilesanmi ).
Note: Brine wt increase may be advised.
23. POOH setting tool assembly and L/D drill pipe.
10818 10830ft .
Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
POH gun.
4. RIH 6ft x 7 OD gun assembly ( HSD, power jet 4512, 12 spf, 135/45deg phasing,
deep penetrating charges and perforate D3.0 sand at 9476 - 9482ft.
Note: Fill up well bore with brine and check for losses/gain. Report to base if either occurs
5.POH gun.
NOTE : Prepare rig floor & R/U 3-1/2Completion running gear for tail pipe assy. Ensure that
appropriate crossover subs from 3-1/2 tubing to Kelly cock are available on the rig floor and
properly made up. Hold pre job/tool box meeting prior to commencing RIH.
Assy No. 2
Assy No. 3
Long string
Assy No.10
string
3 Perforated production tube
(Modified)
RIH completions string slowly to top of Liner, before entering the liner record
UP/DOWN weights. Slowly pass the tail pipe and HS packer into the liner.
Note:
Maintain safe speed to avoid packer setting prematurely.
RIH to +/-10ft above FBGP-1 packer at +/- 12,850 ftah. Record up & down weight and
reverse circulate twice string content with a maximum surface pressure of 500 psi.
Note;
Do not exceed MSP of 500 psi to avoid setting the packer pre-maturely.
RIH slowly and stab 80-40 seals into FBGP-1 packer at 12850ft. Set down 10kips.
Pick up the string to its neutral weight. Close annular BOP and test stabbing with
500psi. If ok Pull up 2ft and recheck stabbing with 500psi. If OK. Pull up the long string
10ft above FBG-1 pkr.
RU the Flow head/Flow TEE, Slick line BOP, and lubricator and test to 3000psi.
RIH with a 2.75 Gauge Cutter (GC) to drift the tubing to XN-Nipple at +-12,860 ft,
and lay down. Rig down slick line equipment.
POH in stands as per space out plan up to the TRSCSSSV position and set slips.
Note:
1. Ensure clean return is observed.
2. When spacing out, the TRSCSSV should be positioned at approximately 120 ft below
the THS. The length of the control line reel should also be considered when spacing
out so as to ensure that the control line would get to the rig floor after final string
landing.
Make up the dummy tubing hanger (without seals) and landing joint on the long string,
and slowly land the hanger in the THS. Remove the landing joint. Clean, grease and
install 3 NRV in the hanger.
Note:
The tubing length pulled out, the GT Dual Grip packer depth, and the
correct length of space out pups required.
Ensure that the tubing hanger seals are removed during this first run to
avoid being damaged.
10
1.2
Make up Snap Latch with 80-37 seal assembly and run in hole with the short string to
+/- 200ft above the MOD GT packer.
Install the tubing hanger and hang off the short string. Clean, grease and install 3
NRV in the hanger.
Note:
Ensure x/over is available to properly land tubing hanger.
Ensure that the short string tubing hanger seals are removed during this first
run to avoid being damaged.
Ensure also the 3 IF box x 3 HCS pin to the Kelly cock.
1.3 LANDING LONG STRING
Pick up and MU TRSCSSSV sub-assembly to the string as per space out plan.
Flush the control line and connect to the TRSCSSV. Test the control line against the
TRSCSSV valve to 5,000 psi for 15 mins. Bleed down pressure to 3000psi.
Strap the control line at three places on each tubing joint, with bandit clamps and
buckle (one each close to the tubing collar and one at the middle of the tubing.
Note:
1. Ensure that the clamps are tight so as to avoid control line slack.
2. Ensure that the control line pressure is monitored through a gauge while strapping and
RIH.
MU Tubing Hanger assembly to the string. Install seals. MU landing joint unto the
hanger.
Assy No. 12
11
Bleed off pressure from control line. Connect 1/4" NPT x 1/4 swage lock with control
line extension on the top side of the hanger and flush the hanger control line ports, top
to bottom.
Connect the control line to the 1/4" NPT port underside of the hanger. Pressure up to
5000psi for 15mins from the top of the hanger to test the connection for leaks.
Note:
1. Record UP and DOWN weight.
2. Position slips carefully to avoid crushing control line
Slowly lower the string and land split hanger in THS. Continue to monitor the
Control line pressure while landing the hanger in the THS.
1.4
Remove 3 NRV from SS hanger. Engage short string with landing joint and pull
Tubing hanger to rig floor. Remove tubing hanger.
RIH Anchor Latch seal assy and Stab into GT packer at +/-9,400ft with 11kips, (mark
pipe at rotary table for space out). Pull 5kips to confirm anchorage. Slack off to
neutral wt .
Rotate string ( +/-4 at 9800ft) right hand turn at neutral point. Pick up slowly to
retrieve seal assy from GT packer.
Note: Extreme care needs to be taken to avoid backing off the string.
Pull up to TRSCSSV installation position (+/- 90 below rotary table). Install TRSCSSV
assembly
Flush control line and connect to SCSSSV. Test control line to 5000 psi against valve.
Bleed down pressure to 3000 psi. Strap control line with bandit clamps in three places
on the tubing, close to each end and one in the middle. (Maintain 3000 psi on control
at all times) Run the tubing in the hole slowly.
Note:
Continue monitoring C/L pressure on L/S.
Make up SS tubing hanger and bleed off pressure on the control line. Flush control
line port on hanger. Connect nipple with control line extension on top of hanger.
Connect control line at the bottom of hanger. Pressure up control line to 5000 psi and
check for leaks, if ok, bleed off pressure to 3000 psi and maintain this pressure on
control line.
Make up landing joint on the hanger. Lower the string slowly and land short string in
the THS.
12
Note:
The BOP and Riser stack should be drained before landing hanger
The Tie-down bolts should be fully retracted after draining the BOP stack, and the bore
of the THS should be flushed with water to get rid of any debris that may be lodged
around the THS bore.
Remove the master bushing to allow passage of the Tubing Hanger through the Rotary
Table.
Ensure that the landing joint make-up torque is half the recommended torque for the
tubing (easy back-off).
1.5
RU Flow head/Flow TEE and Slick line BOP and lubricator on the S/S, and pressure
test the assembly to 3000 psi. .
Note:
Pump open the TRSCSSV and keep in open position on the hand pump through out the
duration of the slick line operation.
RIH on the S/S with a 1.85 GC to the 2-3/8 XN-Nipple position at +/-9460ft, POH
GC.
Install 1.85 QTT in XN nipple @ +/-9,022ft and slack off wire. Fill string and
lubricator and pressure up tubing in stages of 500 psi. to 3000 psi for 15 minutes.
Check annulus for returns, if OK, take some tension on the wire and bleed off
pressure slowly to zero. Retrieve QTT to surface.
Note:
1.6
Ensure C/line is monitored during the test at the hand pump(which should
be locked close).
Before pressurizing, fill up annulus.
Ensure the THS outlet valves are open before pressure testing.
RU the Flow head/Flow-TEE, Slick line BOP, and lubricator and test to 3000psi.
Pump open the TRSCSSV.
13
Note:
Pump open the TRSCSSV and keep in open position on the hand pump through out the
duration of the slick line operation.
Note:
Ensure the build up/bleed down are done gradually and recorded.
Ensure C/line is monitored during the test at the hand pump(which should
be locked close).
Before pressurizing, fill up annulus.
Ensure the THS outlet valves are open before pressure testing.
RIH shifting tool and open XA sleeve at +/-9459ft.
POH shifting tool and RD Slickline.
Back off landing joint and install 3 NRV in the L/S tubing hanger.
2.0
Nipple up the Xmas Tree on the THS. Pressure test Xmas Tree gasket sealing through
the test port to 5,000psi for 15 mins. Bleed off.
Retrieve both NRVs from the strings and install TWCVs in both string hangers.
Pressure test the Tree and flow line valves against the TWCV and 11" x 5K flanged
connection to 5,000psi for 10 mins. Bleed off pressure to zero and retrieve the TWCV
from both strings.
3.0
Rig up W/L. on L/S. RIH shifting tool and close SSD at +/-9459ft.
Apply 500 psi on SS and check sleeve closed. If OK, RD W/L
Record Well head pressures
14
15
OGBELLE
30 Stove Pipe to 24
20 Conductor to 505
/8
1200
- 9330
D1
Sa
nd
Perfd
}
}
oil,; 3030
EZSV @ 9700
- 10200
- 80; Buttress
6
Sa
nd
E
Perfd
10822
Test #4 2685
mscf /d
1
Sa
nd
G
Perfd
12955
Perfd
12963
Test #3 451
bopd (46.8
o ),
13400
}
WELL
mscf /d
DATA
40'
Kelly Bushing
41'
Ground Level
21.7'
Datum
- Top CHH
Datum
- Top Tree
Spud Date
6/4/80
Date Suspended
6/8/80
Recompletion
10
Casing Data
Perfd
3
Sa
nd
G
Perfd
13258
13270
Test #2 403
bopd (47.3
o ),
13300
- 13220
mscf /d
Date
EZSV @ 13290
Perfd
13307
N80 9
N80 7"
Total)
5/
#47
#29
11
12
No of Joints SS
13
Fluid in Hole
10250
13650
7 shoe @ 13650
16
Operation
Planned
Hrs
Mobilization
Accept Rig from DWC
Cleanout 9.5/8" Casing
NU 13.5/8" BOP. Test same
Mix Gel/Water mud
M/U 8-1/2" bit and BHA.
Fishing Operations for lost Shackle
RIH and drill out cement plug at 1000ft
Casing Test and BOP Test
RIH and wash down to 9200ft
Pressure test casing to 2000 psi
Casing Test Fails
Tag cement plug at 9280 ft and drill out to 9330ft
Drill out EZSV.
Drill and wash down to 9700 ft, tag and drill out EZSV
Unable to drill EZSV
Drill out junk and cement to 10093ft (TOL)
Circulate clean and POOH
RIH Reverse Circ JB and 9.5/8" scraper to TOL
POOH
M/U RTTS and RIH to 9250 ft.
Displace DP to diesel
Set Pkr. Inflow test below pkr
Inflow Test fails
POOH
Cleanout 7" Liner
Make up 6" bit & BHA and RIH to TOL.
Drill out cement and run into liner
Tag cement at 10600ft and drill out
Drill EZSV at 10777ft
Clean out and push junk to 11,850 ft
Cleanout 7" Liner to 13290 ft
Circulate clean and POOH
Evaluate and prepare hole
Rig up electric wireline and run RST log
Make up 7" and 9.5/8" scraper assembly and RIH
Circulate and work scrapers.
Pump clean up sweeps and displace to filtered inhibited brine
Circulate until NTU<20
POOH laying down DP
12.00
4.00
2.00
0.00
8.00
0.00
16.00
1.00
1.00
4.00
6.00
36.00
6.00
10.00
10.00
8.00
9.00
2.00
4.00
8.00
15.00
2.00
4.00
6.00
3.00
13.00
24.00
11.00
2.00
6.00
6.00
20.00
17
Perforate
M/U TCP guns to perforate D3 zone 9480 - 9490
RIH on 3-1/2" HCS tubing
Correlate with wireline
Set pkr and fire guns
Reverse out and kill well. Circulate well in balance
POOH and lay down spent guns
M/U TCP guns to perforate E6 zone 10820 - 10843
RIH on 3-1/2" HCS tubing
Correlate with wireline
Set pkr and fire guns
Reverse out and kill well. Circulate well in balance
POOH and lay down spent guns
R/U wireline and RIH DAB pkr and set at 10788
POOH
Complete
Rig up to run completion
Make up LS tailpipe, dual packer and SS tailpipe
RIH LS tubing to top of DAB packer
Tag pkr, mark for space out and POOH to SSSV depth
PU L/S and install TRSSSV, control line, space out and land
RIH L/S and stab into pkr. Test ann to 500 psi
Pressure up on tubing to set pakr. Test tbg and trip Hydrotrip
Install NRV in hanger of LS.
M/U SS latch and sub assemblies
RIH picking up 2-3/8" tubing
PU S/S. Reverse out debris and stab into pkr. Pull back and install
TRSSSV sub assbly and c/l. Space out and land
P test S/S and trip hydrotrip sub
Install Hgr and NRV
ND BOP
NU and test tree
RU slickline and open sleeve at 9460 ft on LS
Displace both strings to diesel
Close sliding sleeve
Rig Down
4.00
21.00
4.00
2.00
6.00
10.00
4.00
12.00
4.00
2.00
8.00
9.00
6.00
3.00
4.00
6.00
12.00
2.00
4.00
2.00
1.00
1.00
2.00
19.00
4.00
1.00
1.00
4.00
8.00
8.00
6.00
4.00
4.00
18.63
Baseline Operational Times
Assume 8% NPT for the rig
20.12
18
WELL:
CASING
SIZE
30
13 3/8
9-5/8
7
STOVE
X-55
N80 BTC
N80 SLX
DEPTH (ft)
CEMENT G
PIPE
55
47
29
24
5529
10250
13650
DRIVEN
CEMENTED
CEMENTED
CEMENTED
TUBING
WT GRADE
STRING SIZE
L/S
3-1/2 9.3
+ 2-3/8 4.7
S/S
2-3/8
4.7
N-80
ITEM
HCS/EUE
SAND PERFORATIONS
SIZE (INS)
COOPER
DSB
N/A
DCB
DCB
N/A
3 x 3
11x 3-1/8x 3-1/8
11x 3-1/2HCS x3-1/2
WP (PSI)
5000
5000
5000 W/CLP
TUBING SPOOL
11x 13-5/8
5000 x 3000
RISER
T CONNECTION
BACK PR. VALVE
CSG. H. HOUSING
WF
13-3/8 x 13-5/8
3000 X 5000
CSG. H. SPOOL
SEAL BUSHING
X
11 X 13-5/8
HOLE
OPEN HOLE PLUGS ACTIVITY MAX.SG RESERVOIR DATE
ALL
06/04/80
DRILLED
IC
June05
Zero deg
HCS
HCS
DFE
ORDF-TCHH
ORDF-TOP XMT
TYPE
GATE VALVE
XMAS TREE
ADAPTER FLANGE
TUBING HANGER
DEVIATION
TYPE
N80
N-80
NDPR - 01
WELLHEAD
WT.
GRADE
40.00 FT
XXXFT
XXX FT
STATUS
90
120
30STOVE PIPE
S/L
S
S
L
ID
2.99
1.99
1.87
2.81
DESCRIPTION
OD
3.99 X-OVER 3-1/2HCS (P x P)
3.99 X-OVER, 3 HCSb X 2 3/8 HCSp
2.75 2 3/8 EUE 8rd bxp TE-5 TRSCSSSV w/X Profile
5.25 3 HCS bxp TE-5 TRSCSSSV
@ 24 ft
20 CONDUCTOR
@ 505 ft
13 3/8 CASING
@ 5529ft
D3.0
9476 9482 FT
(6 FT PERF.)
9392
9400
9414
1.99
9424
9427
9459
S
S
L
9469-9489
2.37
XN NIPPLE 2 3/8HCS
10300
10790
E6.0
10818 10830 FT
(12 FT PERF.)
G1.0
SEQUEZEED OFF
G3.0
13256 13266 FT
&
13274 13284 FT
LOGS
10804-10844
12853
12853
12857
12856
12864
12870
12875
12876
12916
12921
13216
13219
13217
13237
13242
13280
TD = 13920 FT
4.25
L
L
L
L
L
L
L
L
PREPARED BY:
ALAKE, O.A
DATE:03 / 08 / 05
19
Planned
time
4.38 days
Clean out
95/8 casing
Cleanout 7 1.79 days
liner
Evaluate
2.88 days
and Prepare
hole
Perforations 3.96 days
Actual time
Remarks
33.88days
12.46 days
5.48 days
7.81 days
Completions
NB: Details of NPT are attached in Appendix 3
20
21