STANDARDS OF CONSTRUCTION
Refer to Clause 1.1.1 of section 1- preliminaries, which applies to this section. All materials and
workmanship shall comply with design requirements
10.2
10.3
10.3.1
10.3.2
10.3.3
a.
b.
Sample room
Amongst other samples, a representative section of the complete roof covering (minimum area
2000 X 2000 mm) shall be installed as prototype of materials and method of application for
approval of the Engineer before the actual works can proceed on site. This shall involve showing
all details including all laps, skirtings, dressings to outlets, etc as will be required for the whole
metal roofing. The Engineer will nominate one room at the project that shall be used to establish
the prototypes. The Contractor shall notify Engineer to attend the work done in the sample room,
and a joint inspection of the work will be made. Engineers acceptance of the samples at the
sample room will be the standard on which subsequent installation is based.
10.3.4
Hand-over documents
Refer to clause 1.1.3 of section 1- preliminaries, which applies to this section. Submit documents
required by The Relevant Authorities in Vietnamese language, and documents required by
Engineer in English language.
10.4
MATERIALS
10.4.1
Whenever a material, item, article or product is specified by trade name, manufacturers name or
catalogue reference, the Contractor may use its equivalent in the Works, if approved by the
Engineer.
10.4.2
SA10-METAL ROOF
sheets shall be in continuous lengths fixed to steel purlins in strict accordance with the approved
roofing sheet manufacturers instructions. The colour shall be for one side and shall be selected
by the Engineer.
Metal roofing sheets shall comply with the following specifications:Material
Tolerances
0.47mm
Fixing straps
(b)
(c)
Fascia cladding
washers
No 8 - 18 x 12mm per head screws. At least 3
fasteners shall be used per sheet at each support
at the valley of the double rib
SA10-METAL ROOF
10.5
10.6
b.
c.
d.