TECHNICAL DEPARTMENT-CIVIL (Replace by the Project

Name)
METHOD STATEMENT
Method statement for dewatering

Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages

TEC-312319-MET-DoR-001
02 October 2013
NA
1 of 7

METHOD STATEMENT FOR DEWATERING

PROJECT

: (Replace with the projects name, at location , city name)

CLIENT

: (Replace with the clients name)

MASTER DEVELOPER

: (Replace with the master developers name)

PMC

: (Replace with the PMCs name)

LEAD CONSULTANT

: (Replace with the lead consultants name)

SUB-CONSULTANT

: (Replace with the sub-consultants name)

MAIN CONTRACTOR

: (Replace with the main contractors name)

SUB-CONTRACTOR

: (Replace with the sub-contractors name)

TECHNICAL DEPARTMENT-CIVIL (Replace by the Project


Name)
METHOD STATEMENT
Method statement for dewatering

Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages

TEC-312319-MET-DoR-001
02 October 2013
NA
1 of 7

TABLE OF CONTENTS
1. REVISION RECORD .............................................................................................................................. 2
2. PURPOSE ............................................................................................................................................. 1
3. SCOPE OF WORKS ............................................................................................................................... 1
4. REFERENCES ........................................................................................................................................ 1
4.1.

Contract documents ....................................................................................................................... 1

4.2.

Contractors Submittal..................................................................................................................... 1

5. DEFINITIONS / ABBREVIATIONS ......................................................................................................... 1


5.1.

Definition ........................................................................................................................................ 1

5.2.

Abbreviations .................................................................................................................................. 2

6. PERSONNEL RESPONSIBLE .................................................................................................................. 2


6.1.

Project Manager ............................................................................................................................. 2

6.2.

Site Manager ................................................................................................................................... 2

6.3.

Safety Officer .................................................................................................................................. 3

6.4.

Site Surveyor ................................................................................................................................... 3

6.5.

Site Engineer/ Forman .................................................................................................................... 3

7. PLANT AND EQUIPMENT .................................................................................................................... 3


8. PROCEDURE PODIUM ...................................................................................................................... 3
9. HEALTHY, SAFETY AND ENVIRONMENTAL ......................................................................................... 4
10.

ATTACHMENTS................................................................................................................................ 4

10.1.

Inspection Checklists .................................................................................................................. 4

10.2.

Inspection Test Plan .................................................................................................................... 4

10.3.

Risk Assessment .......................................................................................................................... 4

TECHNICAL DEPARTMENT-CIVIL (Replace by the Project


Name)
METHOD STATEMENT
Method statement for dewatering

Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages

TEC-312319-MET-DoR-001
02 October 2013
NA
2 of 7

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All
previous revisions are hereby superseded and are to be destroyed.
Rev

Date

By

2-Oct-13

Chkd.

Approved Description of Revisions


First issue

Signature field
Revision
Number

Reviewed
By

Approved
By

Revision
Date

Construction Technical
Manager
Manager

Project
Manager

2-Oct-13

QA/QC
Engineer

Prepared by Checked by

HSE Officer

MEP Coordinator

Subcontractor

TECHNICAL DEPARTMENT-CIVIL (Replace by the Project


Name)
METHOD STATEMENT
Method statement for dewatering

Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages

TEC-312319-MET-DoR-001
02 October 2013
NA
1 of 7

2. PURPOSE
This documentation outlines the Procedure Involved in the installation of a dewatering system for Podium.

3. SCOPE OF WORKS
Installation of the dewatering system as designed and detailed by Temporary works designer.

4. REFERENCES
4.1.
1.
2.

Contract documents

Project Specification
Contract Drawings

4.2.

Contractors Submittal

3.
4.

Project Quality Plan


Project Safety Plan

5.

Material approvals

Sr.
No.

:- Division 31, Section 312319


:-

::-

Description

Material Sub. No.

Rev No.

Date

Remarks

Shop Dwg. No.

Rev No.

Date

Remarks

1
2
3
6.

Shop Drawings approvals

Sr.
No.
1

Description
Layout of the dewatering plan

2
7.

Report of the site soil investigation 0303079B.

8.

Bulk excavation Method Statement.

5. DEFINITIONS / ABBREVIATIONS
5.1.
1.
2.
3.
4.
5.
6.
7.

Definition

Project
-(Replace with project name)
Client
-(Replace with clients name)
Developer
-(Replace with developers name)
Consultant
-(Replace with consultants name)
PMC
-(Replace with PMC name)
Contractor
-(Replace with contractors name)
Sub-contractor
-(Replace with sub-contractors name)

TECHNICAL DEPARTMENT-CIVIL (Replace by the Project


Name)
METHOD STATEMENT
Method statement for dewatering

8. Supplier

5.2.

Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages

TEC-312319-MET-DoR-001
02 October 2013
NA
2 of 7

-(Replace with suppliers name)

Abbreviations

1. Engineer
2. ICL
3. IR
4. ITL
5. ITP
6. ITR
7. MAT
8. MEP
9. MET
10. MIR
11. MSDS
12. PPE
13. PQP
14. PTW
15. RA
16. RFIA
17. SPD
18. TBM

- Representative of Name of engineering consultancy


- Inspection Check List
- Inspection Request
-Independent Testing Laboratory
- Inspection and Test Plan
-Inspection & Test Requests
- Material Submittal
- Mechanical Electrical Plumbing
- Method Statement
- Material Inspection Request
- Material Safety Data Sheet
-Personal Protective Equipment
-Project Quality Plan
-Permit To Work ( Working at Height or enclosed spaces)
-Hazard Identification and Risk Assessment
- Request for Inspection and Approval
- Shop Drawing
- Temporary Bench Mark

6. PERSONNEL RESPONSIBLE
6.1.

Project Manager

1. Ensure the design is completed by Temporary Works designer, submitted and approved by project
management and approved.
2. Ensure the works are carried out according to the specification and approved shop drawings.
3. To co-ordinate with the site Manager for the provision of all the necessary information to be
distributed among the construction team.
4. Ensure all the plant and equipment is available to progress the works.
5. Co-ordinate with safety officer to ensure that the works are carried out in a safe working practice.
6. Ensure full compliance of the works with the related quality procedure.

6.2.

Site Manager

1. Ensure the works are carried out according to the specification and approved shop drawings.
2. Coordinate with the project manager the agreed sequence of works with respect to the construction
programme.
3. Co-ordinate with the site team for proper distribution of the work force.
4. Coordinate with the Safety officer ensuring safe working practices are implemented.
5. Ensure all necessary plant and equipment is available on site and ready to progress the works.

TECHNICAL DEPARTMENT-CIVIL (Replace by the Project


Name)
METHOD STATEMENT
Method statement for dewatering

6.3.
1.
2.
3.
4.
5.
6.

Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages

TEC-312319-MET-DoR-001
02 October 2013
NA
3 of 7

Safety Officer

Inspection of the access routes to the areas of work.


Ensure the areas of work are sectioned off to prevent unnecessary access.
To Provide / monitor a safe access and egress to the areas of work.
Ensure all operatives wearing full P.P.E.
Ensure all Safety Signs are in place.
Ensure plant operators have a current certificate of competency.

6.4.

Site Surveyor

1. To establish bench marks from agreed reference point.


2. Provide required setting out and level markings.
3. Coordinate with site manager for the sequence of work.

6.5.

Site Engineer/ Forman

1. To coordinate with site manager for the distribution of the work force, plant and equipment on a daily
basis.
2. Co-ordinate with the safety officer ensuring safe working practices is implemented.
3. To coordinate with the site manager if additional plant, equipment and operatives are required.
4. To ensure proper daily records are taken of the progress of works.

7.

PLANT AND EQUIPMENT


1.
2.
3.
4.
5.
6.
7.

Piling rig to auger in casings.


360 Excavator
18 m Tippers
6 inch Pumps, suction hoses and dewatering lay flat hoses.
Drum Roller.
Compacting Plates.
Dewatering Settlement tank.

8. PROCEDURE PODIUM
1. Prior to commencement the site surveyor will establish both vertical and horizontal control points
using setting out stations.
2. Set out and excavate the site from the present level of +2.3m down to +0.5m with the excavated
materials taken off site using 18m3 tippers to be stock piled for future use as agreed / approved by the
client. Access will be clearly maintained across the site for both vehicles and pedestrians such that
other areas of work are not affected.
3. When the +0.5m level is established, each end of the proposed filter drain will be set out and the
correct fall established from one end to the other using profile boards.
4. Excavation for the filter drains will be commenced from the sump i.e. lowest end towards the highest
end. Side slopes shall be battered or stepped at 1V:2H for safety down to the bottom of the trench as
per drawing and one 6 inch pump will discharge the water from the sump into the adjacent creek via a
settlement tank.

TECHNICAL DEPARTMENT-CIVIL (Replace by the Project


Name)
METHOD STATEMENT
Method statement for dewatering

Doc. No.
(Rev No.)
Issue Date
Rev. Date
Pages

TEC-312319-MET-DoR-001
02 October 2013
NA
4 of 7

5. The filter drain at the bottom of the trench will then be constructed 1.5m deep by 1.5m wide and filled
with 2 to 4 natural gravel wrapped in a geotextile terram material. The geotextile will be folded over
at the top of the stone to prevent the filtration of fines and then the trench will be backfilled up to the
existing ground level.
6. Where the permanent sumps cannot be installed, then temporary sumps will be placed at the lowest
point where the excavation is commenced to ensure the water always runs away from the point of
excavation and one 6 inch pump will discharge the water into the creek via a settlement tank.
7. If required, additional temporary sumps may have been installed at locations to help draw down the
ground water.
8. The filter drains will be installed as shown on in the following sequence to match the excavation
sequence from:
9. The permanent dewatering pumps will be located at sumps 1 and 2 and each shall contain one 6 inch
pump with suction hose into the sump and flexible lay flat hose discharging back into the creek via a
settlement tank. Sumps will be constructed as per.
10. Checks shall be carried out each week by visually inspecting the settlement tanks to monitor how
much fines are being removed from the drain.
11. On completion of the works tidy the areas and compact ready for the main construction works.

9. HEALTHY, SAFETY AND ENVIRONMENTAL


1. During the excavation, ensure the area of work is protected by a demarcation barrier therefore
isolating from all un-authorized personnel.
2. Side slopes must be checked to be cut to 1V:2H due to the nature of the soil.
3. All plant and equipment will be inspected by the site Safety Officer, Ensuring all the test certificates
are provided and valid.
4. Ensure drip trays are placed under all static plant e.g. generators and pumps.
5. Ensure that the 6 inch pump discharges into a settlement tank and that the fines within the settlement
tank are monitored and removed when necessary.
6. Ensure all operatives and Site management have full P.P.E.

10. ATTACHMENTS
10.1.

Inspection Checklists

10.2.

Inspection Test Plan

10.3.

Risk Assessment