Construction Estimate

File Name: Estimate1_A.est


Qty
1.00

Craft@Hours
--@.0000

Unit
--

Page 1
Material

Labor

Equipment

Total

0.00

0.00

0.00

0.00

0.00

435.94

0.00

866.21

ESTIMATION #1
I. Lots and Ground.
1).The Retaining Wall is signs of movement.
Repair and adjust wood retaining wall and used Jack post.
Retaining Wood wall
8" x 8" (5.71 BF per LF)
38.00

B1@3.344

LF

294.96

140.98

2)The deck has been build below acceptable building standards and not safe.
Repair deck up to an acceptable building standard.
Repair composite lumber decking
2" x 8" recycled composite lumber decking:
42.00

B1@7.140

SF

565.49

300.72

3). Grading.
The grade and landscaping materials are too high and extend above the window well at the Northeast
rear of the home.
The grade reduced of the metal window well soil retainer be replaced with a taller unit to keep the mulch
and soil beds from washing into well.
These costs and productivity are based on utility line trenches and hand job and used compaction
machine. Linear feet (LF), cubic yards (CY), square feet (SF), or square yards (SY) per hour shown are
based on a 2-man crew. Increase costs by 10% to 25% when spoil is loaded in trucks. Hauling,
shoring, dewatering or unusual conditions are not included.
12" wide bucket, for 12" wide trench. Depths 1' to 5'. Equipment is a wheel loader with 1 CY bucket and
integral backhoe. Use $400 as a minimum job charge:
Trench hand excavation with gradall
Loose soil:
2.00

BL@32.00

Mhour

0.00

790.00

II. GARAGE/GROUNDS.
1). Garage Floor - Poured concrete, cracked with minor displacement.

70.00

860.00

Construction Estimate
File Name: Estimate1_A.est
Qty

Craft@Hours

Unit

Page 2
Material

Labor

Equipment

Total

5.94

131.00

8.74

145.68

Repair garage concrete floor.


2.00

BT@3.740

LF

2).The door contact safety switch is out of adjustment and not reverse the door operation when the door.
Radio controlled, electric, single or double door, includes typical electric hookup to existing adjacent
110 volt outlet.
Garage door openers
Adjustment of garage door contact switch
1.00

BC@4.040

Ea

243.78

187.00

0.00

430.78

176.00

0.00

176.00

198.00

0.00

198.00

III. ELECTRICAL.
Dauble taps in general panel at several breakers.
Garage door openers
Correctionns main electtrical panel
1.00

E4@4.040

Ea

0.00

IV. ATTIC.
Repair attic.
1). Repair attic, prevent water penetration.
Repair attic
Built-up roof, 3 ply and gravel
1.00

BL@8.000

SQ

0.00

2). Missing fiberglss batt insulation, additional insulation missing in the 4 SF.
Insulation Roof insulation. Local regulation can affect the cost and availability of urethanes,
isocyanurates, phenolics and polystyrene roof insulation board.
Fiberglass board roof insulation
2" 4' x 8' panels
4.00

R3@4.400

SQ

236.23

283.20

0.00

519.43

Construction Estimate
File Name: Estimate1_A.est
Qty

Craft@Hours

Unit

Page 3
Material

Labor

Equipment

Total

V. CRAWL SPACE.
1). Moisture Penetration .
Install Insulation to the all crawl space.
Coverage wall and ceiling application and coverage allows for framing
Kraft-faced. Install Building Paper and Polyethylene Film
Poly-faced insulation, vapor retarding twisted Miraflex fibers, ASTM C665, Type II, Class C, coverage
allows for framing
Vapor retardind:
980.00

BC@5.880

SF

729.71

274.40

0.00

1,004.11

VI. ROOF.
1). Missing roof fiberglass shingles.
Installed over existing suitable substrate. Add the cost of equipment rental (the kettle) and consumable
supplies (mops, brooms, gloves). Typical cost for equipment and consumable supplies is $15 per 100
square feet applied.
Type 1: 2 ply felt and 1 ply 90-pound cap sheet, including 2 plies of hot mop asphalt
Fiberglass ply IV roll roofing ASTM D-2178 Type IV. 500 square foot roll.
Per 100 square feet
54.00
R1@7.560
SQ
233.54
Add for mopping in 30-pound hot asphalt
54.00

R1@18.90

SQ

339.66

0.00

573.20

272.65

847.80

0.00

1,120.45

0.08

7.50

0.00

7.58

VII. PLUMBING.
1). Basement Water Heater TPRV.
Missing drain tube.
Install coupper drain tube.
1/2" pipe
1.00

P6@.1100

Ea

VIII. BATHROOM.
1). Master Bathroom leaking PVC trap.

Construction Estimate
File Name: Estimate1_A.est
Qty

Craft@Hours

Unit

Page 4
Material

Labor

Equipment

Total

Remove old and install new trap.


Plumbing fixtures and windows. Includes removing construction debris and grime. Add for removing
paint splatter or mastic. Work performed using hand tools and commercial non-toxic cleaning products
or solvent. Use $80.00 as a minimum job charge.
PVC trap
1.00

PM@2.500

Ea

200.00

88.10

0.00

288.10

0.00

52.90

0.00

52.90

IX. KITCHEN.
1). Hot/Cold water operation reversed.
Plumbing:
1.00

PM@1.500

Ea

X. LAUNDRY.
1). Waser hose worn/expanded and ready to burst.
The hose replacement with burst-proof stainless stee braided hoses.
Hot and cold water supply: 16' of 1/2" type M hard copper pipe, (straight lengths) including associated
fittings, solder, flux, and pipe clips. Drains and vents: 21' of 1-1/2" stainless steel braided hoses and
vent pipe with associated fittings, glue and strapping.
Hot and cold water supply
1.00

P1@1.000

Ea

20.50

46.20

0.00

66.70

XI. EXTERIOR SURFACE.


1). Brick veneer - Loose brick at the front door.
Remove and tuckpoint brick back in place.
Masonry work:
1.00

BB@1.000

Hr

0.00

31.80

0.00

31.80

LF

50.85

337.00

0.00

387.85

2). Wood Trim.


Damaged wood trim.
Replace wood trim.
wood trim 12" x 8'
1.00

B1@8.000

3).The wood window boxes have water damage.


Repair all wood damage and privent water penetration.

Construction Estimate
File Name: Estimate1_A.est
Qty

Craft@Hours

Unit

Page 5
Material

Repair exterior surfaice and privent water penetration


1.00
B2@16.00
Hr
100.67

Total Manhours, Material, Labor, and Equipment:


129.2
2,954.40

Labor

Equipment

Total

452.00

80.00

632.67

4,684.26

158.74

7,797.40

Subtotal:
6.00% Overhead:
4.50% Contingency:
10.00% Profit:
Estimate Total:
8.25% Tax on Materials:
Grand Total:

7,797.40
467.84
371.94
863.72
9,500.90
243.74
9,744.64