1.1 OBJECTIVE.
A key objective of ADC Procedures is to set up a step by step way of handling the
job. It is also an analysis of associated hazards pertaining to the jobs and measures to
minimize the risks.
This procedure has developed to be applied and discussed before each job listed in
the contents.
1.2 SCOPE.
This procedure applies to Rig AD-32
1.3 RESPONSIBILITY.
It is the responsibility of the Tool-pusher and Rig Manager to insure all listed
operations are executed in a safe and efficient manner. It is their responsibility to
conduct a Pre-job Safety Meeting and discuss and review the related JSA, prior to
starting each operation.
Tool-pusher is responsible to ensure that each work permit has its dedicated JSA
attached to.
JSA to be reviewed and updated at least annually or
When equipment is modified
When processes are changed
When material are changed
When changing people/contractors
When there is an accident or near miss.
The Rig Sup. is accountable for keeping this document up-to date.
The JSA date and the crew should be same as Work Permit date and crew.
Author:
Arabian Drilling
Company
Rig Specific
Procedure
AD - 32
Checked By
Approved By:
Table of Contents
TASK ANALYSIS
Is Procedure relevant for the operation?
What can interfere with the operation (Simops)?
Who is going to be in charge, position?
Who is giving instructions/signals, who replace him?
How many people are required to do the job?
-
Position
Position
Position
Position
Position
Position
REF: 2
Page
Issued:
Version
April 2008
Author:
Checked By
Approved By:
Subject: Rig Specific
Procedures
Additional Comments:
Arabian Drilling
Company
Rig Specific
Procedure
AD - 32
Reset pressure relief
valve
REF: 2
Page
Issued:
April 2008
Version
Preparation
Hold a pre-job safety meeting prior to commencement job with all personnel
involved.
Review JSA/HARC.
Full body harness
Review JSA number 2 related.
Tools
Pressure relief valves are installed on mud pumps in order to prevent an overpressure
which could result in a serious damage of the pump and serious or fatal injury to
personnel.
The discharge pressure is routed to the closer mud tank, via a 2 line minimum clamped all
the way along. Mud is flowing into the mud tank until 0 pressure in the line.
Read carefully manufacturer instructions regarding setting, handling, refurbishing of such
equipment.
In any cases if you dont know/ understand how to do it dont do it, ask your supervisor.
1) Pressure relief valves are set usually to 90% of the maximum working pressure of
the liners in use. Read carefully manufacturer chart for pressure setting versus size
of liners.
2) The most commonly used pressure relief valve is RETSCO, 500 and 750, which
stands for mud pumps maximum working pressure 5000psi and mud pumps
7500psi.
3) Prior to installing a pressure relief valve it needs to be tested on a bench.
Author:
Arabian Drilling
Company
Rig Specific
Procedure
AD - 32
Checked By
Approved By:
Subject: Rig Specific
Procedures With a
REF: 2
Page
Issued:
April 2008
When the pressure test has been successful, put a tag on the pressure relief valve, where
it is mentioned:
-The date of the test.
-The pressure of the test.
-If the pressure relief valve was reconditioned.
Store it properly away from dust and adverse weather.
Author:
Arabian Drilling
Company
Rig Specific
Procedure
AD - 32
Checked By
Approved By:
Subject: Rig Specific
Procedures
5)
REF: 2
Page
Issued:
April 2008
6) Proceed to remove the upper part of the pressure relief valve with the
Allen key.