Cable Installation on Existing SAP Survey Report

INDEX
NOTES
W35111-ML1
W35111-ML2
W35112-ML1
W35112-ML2
W35130
W35171-ML
W35191-ML
W35311-ML
W35313-ML
W35339-ML1
W35339-ML2
W35351-ML
W35414-ML1
W35414-ML2
W35414-ML3
W35414-ML4
W35416
W35418
W35430-PS
W35502-ML1
W35502-ML2
W35504-ML1
W35504-ML2
W35625-ML
W35626-ML
W35637-ML
W35638-ML
W35714-T
W35721-EH
W35722-EH
W35723-EH
W35724-EH
W35741-ML
W35742-ML
W35754-T
W35761-EH
W35762-EH
W35763-EH
W35764-EH
Appendix 1: AEI Cable Dimensions
Appendix 2: Hawke Cable Gland Details

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet No.
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
45

Sheet2of45

Cable Installation on Existing SAP Survey Report


NOTES
1)

Visualinspectionshallpayparticularattentiontotheconditionofcablesheathandinsulation,
whereaccessible.
NoevidenceofdegradationduetochemicalorUVexposureshallbeobserved.
Nomecahnicaldamageshallbeobserved.
Bendingradiishallbecompliantwithmanufacturer'sadvice.

2)

Allcableglandshroudsshallberemovedcarefully,soastoavoiddamagingthecablesheath.

3)

Insulationresistanceandcontinuitychecksshallbecarriedoutwiththecabledisconnected
fromtheloadandfromtheswitchgear.

4)

ConductorcontinuityshallbecheckedusingaproprietaryinstrumentapprovedbyBGT.

5)

Insulationresistanceshallbemeasuredusinga1000VMegger,orsimilarinstrumentas
approvedbyBGT.

6)

Reportsheetsaresetupforthreecorecables.Whereafourthcoreispresentthatshallbe
includedintheinsulationresistancetestsuchthattheresistancebetweeneachpairofcores
[L1/L2;L2/L3;L3/L4;L4/L1;L2/L4],andbetweeneachcoreandground,isgreaterthan2M.
Relevantvaluesshallberecordedinthe"Notes"sectionatthebottomoftherelevantsheet.
Wherethefourthcoreisagroundconnectionthecableshallbetreatedashavingthreecores.

7)

Cablereinstallationconsiderationsshallinclude:
i.
accessibilityforcablepulling
ii.
minimumbendingradiiconstraints
iii.
requirementforscaffolding
iv.
glandingspaceatswitchgearandloadterminalboxes
v.
cableentrysizeprovided
vi.
terminalsizeinrelationtorequiredconductorsize
vii. necessityforatransitionjunctionboxtoaccommodateincreasedconductorsize
viii. installedcircuitprotection(fuse/mccbrating)
ix.
spaceavailabilityinrelevantcabletransits
x.
impactonExcertification,whereapplicable
xi.
conductor/glandearthingatsupplyandloadlocations.

8)

GENESIScablediametersandglandsizesareshownforreferenceonly.Theyaredeirvedfrom
typicalmanufacturrer'sdata:AEIforcables;Hawkeforglands.Datasheetsareprovidedfor
information.

HOLDS

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet3of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35111-ML1

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3511A
Scheduled Length:

28

Installed csa:

120

Measured length installed:

Dilution Air Blower

m
mm2 csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

120
39.00

mm

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm refer Note 8

M40 / C2

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At switchgear: YES / NO

At terminal box: YES / NO


Certification maintained? YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet4of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35111-ML2

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3511A
Scheduled Length:
Installed csa:

28

120

Measured length installed:

Dilution Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

120
39.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M40 / C2

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet5of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35112-ML1

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3511B
Scheduled Length:
Installed csa:

32

120

Measured length installed:

Dilution Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

120
39.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M40 / C2

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet6of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35112-ML2

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3511B
Scheduled Length:
Installed csa:

32

120

Measured length installed:

Dilution Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

120
39.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M40 / C2

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet7of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35130

Installed type:

FROM: MCC1

400V MCC

TO: P-3513
Scheduled Length:

83

Installed csa:

1.5

Measured length installed:

Condensate Pump
m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet8of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35171-ML

Installed type:

FROM: MCC3

400V MCC

TO: C-3517

Combustion Air Blower

Scheduled Length:

60

Installed csa:

70

2
mm csa calculated as undersized for load

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

95
36.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M40 / C2

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet9of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35191-ML

Installed type:

FROM: MCC1

400V MCC

TO: C-3522
Scheduled Length:

75

Installed csa:

1.5

Measured length installed:

Scavenging Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet10of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35311-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3531A

Hot Oil Pump

Scheduled Length:

50

Installed csa:

50

2
mm csa calculated as undersized for load

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

70
31.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M32 / C

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet11of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35313-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3531B

Hot Oil Pump

Scheduled Length:

50

Installed csa:

50

2
mm csa calculated as undersized for load

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

70
31.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M32 / C

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet12of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35339-ML1

Installed type:

FROM: MCC2

400V MCC

TO: E-3539/1
Scheduled Length:

50

Installed csa:

Measured length installed:

Hot Oil Cooling Blower


m
2
mm csa calculated as undersized for load

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

10
17.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20 / A

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet13of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35339-ML2

Installed type:

FROM: MCC1

400V MCC

TO: E-3539/2
Scheduled Length:

50

Installed csa:

Measured length installed:

Hot Oil Cooling Blower


m
2
mm csa calculated as undersized for load

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

10
19.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20 / A

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet14of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35351-ML

Installed type:

FROM: MCC2

400V MCC

TO: P-3535
Scheduled Length:

40

Installed csa:

2.5

Measured length installed:

Hot Oil Start-Up Pump


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet15of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35414-ML1

Installed type:

FROM: MCC2

400V MCC

TO: E-3540/1

Cooling Water HE Blower

Scheduled Length:

100

Installed csa:

1.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYCY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet16of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35414-ML2

Installed type:

FROM: MCC1

400V MCC

TO: E-3540/2
Scheduled Length:

97

Installed csa:

1.5

Measured length installed:

Cooling Water HE Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20 / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet17of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35414-ML3

Installed type:

FROM: MCC1

400V MCC

TO: E-3540/3
Scheduled Length:

96

Installed csa:

1.5

Measured length installed:

Cooling Water HE Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20 / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet18of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35414-ML4

Installed type:

FROM: MCC1

400V MCC

TO: E-3540/4
Scheduled Length:

95

Installed csa:

1.5

Measured length installed:

Cooling Water HE Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20 / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet19of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35416

Installed type:

FROM: MCC1

400V MCC

TO: P-3542A

Cooling Water Pump

Scheduled Length:

100

Installed csa:

1.5

2
mm csa inadequate for starting volt-drop

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20 / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet20of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35418

Installed type:

FROM: MCC1

400V MCC

TO: P-3542B

Cooling Water Pump

Scheduled Length:

100

Installed csa:

1.5

2
mm csa inadequate for starting volt-drop

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20 / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet21of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35430-PS

Installed type:

FROM: EL-3503

400V Switchboard

TO: E-3543
Scheduled Length:
Installed csa:

90

120

Measured length installed:

Refrigeration Unit
m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
45.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M50 / D

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet22of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35502-ML1

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3552A
Scheduled Length:
Installed csa:

58

150

Measured length installed:

Cooling Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

150
44.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M50 / D

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet23of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35502-ML2

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3552A
Scheduled Length:
Installed csa:

58

150

Measured length installed:

Cooling Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

150
44.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M50 / D

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet24of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35504-ML1

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3552B
Scheduled Length:
Installed csa:

55

150

Measured length installed:

Cooling Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

150
44.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M50 / D

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet25of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35504-ML2

Installed type:

FROM: EL-3503

400V Switchboard

TO: C-3552B
Scheduled Length:
Installed csa:

55

150

Measured length installed:

Cooling Air Blower


m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

150
44.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M50 / D

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet26of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35625-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3563A
Scheduled Length:

90

Installed csa:

1.5

Measured length installed:

Acid Pump 'A'


m
2
mm csa calculated inadequate for volt-drop

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet27of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35626-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3563B
Scheduled Length:

97

Installed csa:

1.5

Measured length installed:

Acid Pump 'B'


m
2
mm csa calculated inadequate for volt-drop

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet28of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35637-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3566A
Scheduled Length:

98

Installed csa:

1.5

Measured length installed:

Acid Loading Pump 'A'


m
2
mm csa calculated undersized for load

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet29of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35638-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3566B
Scheduled Length:

98

Installed csa:

1.5

Measured length installed:

Acid Loading Pump 'B'


m
2
mm csa calculated undersized for load

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet30of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35714-T

Installed type:

FROM: EL-3503

400V Switchboard

TO: F-3570
Scheduled Length:

101

Installed csa:

70

Measured length installed:

E/S Separator
m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

70
36.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M40 / C2

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet31of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35721-EH

Installed type:

FROM: CU

400V Distribution

TO: EH-35721

Heater Junction Box

Scheduled Length:

107

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet32of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35722-EH

Installed type:

FROM: CU

400V Distribution

TO: EH-35722

Heater Junction Box

Scheduled Length:

118

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet33of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35723-EH

Installed type:

FROM: CU

400V Distribution

TO: EH-35723

Heater Junction Box

Scheduled Length:

119

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet34of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35724-EH

Installed type:

FROM: CU

400V Distribution

TO: EH-35724

Heater Junction Box

Scheduled Length:

108

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet35of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35741-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3574A
Scheduled Length:

98

Installed csa:

1.5

Measured length installed:

Dilute Acid Pump 'A'


m
2
mm csa inadequate for starting volt-drop

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet36of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35742-ML

Installed type:

FROM: MCC1

400V MCC

TO: P-3574B
Scheduled Length:

98

Installed csa:

1.5

Measured length installed:

Dilute Acid Pump 'B'


m
2
mm csa inadequate for starting volt-drop

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
15.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet37of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35754-T

Installed type:

FROM: EL-3503

400V Switchboard

TO: F-3575
Scheduled Length:

100

Installed csa:

70

Measured length installed:

E/S Separator
m
2
mm csa calculated as adequate

Existing Cable Entry Size

Physical condition:
Continuity:

NYCWY

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

70
36.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M40 / C2

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet38of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35761-EH

Installed type:

FROM: CU

400VDistribution

TO: EH-35761

Heater

Scheduled Length:

114

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet39of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35762-EH

Installed type:

FROM: CU

400VDistribution

TO: EH-35762

Heater

Scheduled Length:

116

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet40of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35763-EH

Installed type:

FROM: CU

400VDistribution

TO: EH-35763

Heater

Scheduled Length:

118

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet41of45

Cable Installation on Existing SAP Survey Report


CABLE No.

W35764-EH

Installed type:

FROM: CU

400VDistribution

TO: EH-35764

Heater

Scheduled Length:

117

Installed csa:

2.5

2
mm csa calculated as adequate

Measured length installed:

Existing Cable Entry Size

Physical condition:
Continuity:

NYY-J

Visual

PASS / FAIL

at Switchboard:

mm

at Load:

mm

Insulation Resistance L1 / L2:

[to be > 2M]

Insulation Resistance L1 / Gnd:

[to be > 2M]

Insulation Resistance L2 / L3:

[to be > 2M]

Insulation Resistance L2 / Gnd:

[to be > 2M]

Insulation Resistance L1 / L3:

[to be > 2M]

Type:

Insulation Resistance L3 / Gnd:

[to be > 2M]

Rating:

Cable Gland Earthing


at Load:

to be < 0.5

Installed Circuit Protection

GENESIS REQUIREMENT
Type:
csa:
Nominal o/d:
Nominal Gland Size:

XLPE/SWA/PVC

4
13.00

[refer Electrical Design Philosophy


BG-TUN-PROJ-AGM-08-KD-00013]

mm2
mm refer Note 8

M20S / O

refer Note 8

Check sufficient space to accommodate this cable size ...


Ladder rack / cable tray: YES / NO

Cable transit(s): YES / NO

Terminals / terminal boxes: YES / NO

Transition box required? YES / NO

Check sufficient space to accommodate this gland size ...


At terminal box: YES / NO
Certification maintained? YES / NO

At switchgear: YES / NO

N/A

NOTES:

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet42of45

Cable Installation on Existing SAP Survey Report


Appendix 1: AEI Cable Dimensions

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet43of45

Cable Installation on Existing SAP Survey Report

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet44of45

Cable Installation on Existing SAP Survey Report


Appendix 2: Hawke Cable Gland Details

BGTUNPROJAGM08TCH00029RevBCableInstallationonExistingSAPSurveyReport

Sheet45of45