Beruflich Dokumente
Kultur Dokumente
1.
Introduction
2.
3.
Project Viability
4.
5.
Security Arrangements
6.
Legal Structure
7.
Sources of Funds
8.
9.
Case Study
CHAPTER 1: INTRODUCTION
PROJECT FINANCING
Page 1 of 32
In the case of India, the government has taken great strides in improving the
infrastructure stock of the nation since independence. However, when
PROJECT FINANCING
Page 2 of 32
compared to developed countries we still have a long way to go. For instance,
per capita power consumption in India is a meagre 282 KWH compared to
18,117 KWH for Canada. The situation has worsened in the 90s with
frequent revisions being made to the eighth plan document owing to the
governments inability to bear the cost of infrastructure anymore.
The simple truth is that public money is no longer sufficient to meet the
burgeoning needs of the nation in line with its economic aspirations.
Reluctantly, therefore the government has to throw open the doors to private
participation in infrastructure.
PROJECT FINANCING
Page 3 of 32
In addition to
Belief that the problems with supply and technology require highly
active intervention by the government.
Faith that the government could succeed where markets appear to fail
Operational deficiencies
Inadequate maintenance
PROJECT FINANCING
Page 4 of 32
circumstances have varied across countries and sectors, the shift towards
greater private involvement has been driven by the need to provide better
services to more people at a lower cost.
The main reason for a shift towar4ds private infrastructure is the growing
dissatisfaction with the public ownership monopoly and provision of
infrastructure facilities. Under-investment by many state utilities has resulted
in a back-log of unmet demand for infrastructure services: in many countries
this is the principal constraint to growth. Power shortages have led to a
shortfall in production, higher costs and a decline in investment. Similarly
limited availability and the poor quality of telecommunications have made it
difficult for business in many developing countries to participate in the new
international information based economy, Fiscal constraints faced by the
governments and technological developments are other factors which have
favoured increased private participation
Contract based relationships (eg. Build-Operate-transfer, Build-ownOperate, Concessions) have allowed private entry even within the
existing regulatory network but with minor modifications.
Also, the private sector entry often sets up a pressure for further regulatory
changes and sometimes competition may mitigate the need for close
regulation.
PROJECT FINANCING
Page 5 of 32
PROJECT FINANCING
Page 6 of 32
In project financing the project, its assets, contracts, inherent economic and
cash flows are separated from their promoters or sponsors in order to permit
credit appraisal and loan to the project, independent of the sponsors. The
assets of the specific project serve as a collateral for the loan, and all loan
repayments are made out of the cash of the project. In this sense, the loan is
said to be of non-resource to the sponsor. Thus, project financing may be
defined as the scheme of financing of a particular economic unit in which l
lender is satisfied in looking at the cash flows and the earnings of that
economic unit as a source of funds, from which a loan can be repaid, and to
the assets of the economic unit as a collateral forte the loan*2. In the past,
project financing was mostly used in oil exploration and other mineral
extraction through joint ventures with foreign firms. The most recent use of
project financing can be found in infrastructure projects, particularly in power
a telecommunication projects.
*2Nevitt, P.K., Project Financing, Euro money Publications, 1983.
Project financing is made possible by combining undertakings and various
kinds of guarantees by parties who are interested in a project. It is built in
such a way that no one party alone has to assume the full credit responsibility
of the project.
PROJECT FINANCING
Page 7 of 32
the lender looks at the cast flows and assets of the whole company in order to
service the debt and provide security. Figure 30.3 shows the basic differences
between balance sheet financing and project financing.
Balance sheet financing
Project Financing
Lender
Lender
Project Sponsor
Project Sponsor
Equity
Equity
Loan
Special Project
Entry
Owns
Project Assets
Owns
Project Assets
Thus,
The project funding and all its other cash flows are separated from the
parent companys balance sheet.
PROJECT FINANCING
Page 8 of 32
PROJECT FINANCING
Page 9 of 32
PROJECT FINANCING
Page 10 of 32
Lenders
Contractor
Loan
Debt Service
Fuel
Transport
Equity
Investors
Owner
Return on
Equity
Operation &
Maintenance
Ownership
Payment
Land Lease
Payment
Power Plant
Electricity
Supply Company
KW Hrs
BOOT/BOO structure of power plant
This may take place in spite of legal agreements, which includes inspection
plans and other such measures. In any case, there does not seem to be any
rationale for such a transfer if the very basis of the projects was to run it
outside the public sector. One alternative to transfer that has been suggested
is for the foreign shareholders to divest themselves of their equity either
entirely or up to some negotiated percentage at the end of the stipulated time
period. Such an arrangement is generally referred to as the build-operate-own
(BOO) arrangement.
In BOO arrangement, projects are funded without any direct sovereign
guarantee. Thus, it implies limited recourse financing. Unlike in BOOT
arrangements, in BOO structure, the project is not transferred to the host
government, rather the owner will divest his stake and seek investment =s
from investors in the capital markets. This facilitates the availability of
PROJECT FINANCING
Page 11 of 32
finances. BOOT and BOO arrangements are essentially similar except thT IN
boo arrangement the sponsor preserves the ownership.
Build-Lease-Transfer arrangement
In the build lease transfer arrangement, the control of the project is
transferred from the project owners to a lease. The shareholders retain the full
ownership of the project, but, for operation purposes, they lease it to a lessee.
The host government agrees with the lessee to buy the output or service of the
project. The lessor receives the lease rental guaranteed by the host
government.
Investors are concerned about all the risks a project involves, who will bear
each of them, and whether their returns will be adequate to compensate them
for the risks they are being asked to bear. Both the sponsors and their adviser
must be thoroughly familiar with the technical aspects of the project and the
risks involved, and they must independently evaluate a projects economics
and its ability to service project related borrowings.
Technical Feasibility:
Prior to the start of construction, the project sponsors must undertake
extensive engineering work to verify the technological processes and design
of the proposed facility. If the project requires new or unproven technology,
test facilities or a pilot plant will normally have to be constructed to test the
feasibility of the process involved and to optimise the design of full scale
facilities. A well-executed design will accommodate future expansion of the
project; often, expansion beyond the initial operating capacity is planned at
PROJECT FINANCING
Page 12 of 32
the outset. Rhe related capital cost and the impact of project expansion on
operating efficiency are then reflected in the original design specifications
and financial projections.
Project Construction Cost
The detailed engineering and design work provides the basis for estimating
the construction costs for the project. Construction costs should in clued the
cost of all facilities necessary for the projects operation as a freestanding
entity. Construction costs should include contingency factor adequate to
cover possible design errors or unforeseen costs. Project sponsors or their
advisers generally prepare a time schedule detailing the activities that must be
accomplished before and during the construction period. A quarterly
breakdown of capital expenditures normally accompanies the time schedule.
The time schedule specifies (1) time expected to be required to obtain
regulatory or environmental approvals and permits for construction. (2) The
procurement lead time anticipated for major pieces of equipment and (3) the
time expected to be required fro pre-construction activities- performing
detailed design work, ordering the equipment and building materials,
preparing the site and hiring the necessary manpower. The project sponsor
examines the critical path of the construction schedule to determine where the
risk of delay is greatest and then assesses the potential financial impact of any
projected delay.
Economic Viability
The critical issue concerning economic viability is whether the projects
expected net present value is positive. It will be positive only if the expected
present value of the future free cash flows exceeds the expected present value
of the projects construction costs. All the factors that can affect project cash
flows are important in making this determination.
Assuming that the project is completed on schedule and within budget, its
economic viability will depend primarily on the marketability of the projects
output (price and volume). To evaluate marketability, the sponsors arrange
PROJECT FINANCING
Page 13 of 32
for a study of projected supply and demand conditions over the expected life
of the project. The marketing study is designed to confirm that, under a
reasonable set of economic assumptions, demand will be sufficient to absorb
the planned output of the project at a price that will cover the full cost of
production, enable the project to service its debt, and provide an acceptable
rate of return to equity investors. The marketing study generally includes 1) a
review of competitive products and their relative cost of production; 2) an
analysis of the expected life cycle for project output, expected sales volume,
and projected prices; and 3) an analysis of the potential impact of
technological obsolescence.
PROJECT FINANCING
Page 14 of 32
Creditworthiness:
A project has no operating history at the time of its initial debt financing.
Consequently, the amount of debt the project can raise is a function of the
projects expected capacity to service debt from project cash flow- or more
simply, its credit strength. A projects credit strength derives from (1) the
inherent value of the assets included in the project, (2) the expected
profitability of the project, (3) the amount of equity project sponsors have at
risk and indirectly, (4) the pledges of creditworthy third parties or sponsors
involved in the project.
Expected profitability of the project:
The expected profitability of a project represents the principal source of funds
to service project debt and provide an adequate rate of return to the projects
equity investors. Lenders generally look for two sources of repayment for
their loans: (1) the credit strength of the entity to which they are loaning
funds and (2) the collateral value of any assets the borrower pledges to secure
the loans. Also, there is a third source, the credit support derived indirectly
from pledges of third parties.
Amount of equity project sponsors have at risk:
Debt ranks senior to equity. In the event a business fails, debt holders have a
prior claim on the assets of the business. Given the value of project assets, the
PROJECT FINANCING
Page 15 of 32
greater the amount of equity, the lower the ratio of debt to equity. Therefore,
the lower the degree of risk lenders face.
Credit support derived indirectly from pledges by third paries.
Although lenders look principally to the revenues generated from the
operations of a project to determine its viability and credit worthiness,
supplemental credit support for a project may have to be provided by the
sponsors or other creditworthy parties benefiting from the project. The
contractual agreements among the operator / borrower, the sponsors, other
third parties, and the lenders, which are designed to ensure debt repayment
and servicing, as well as the credit standing of these guarantors, are necessary
to provide adequate security to support the projects financing arrangements.
Conclusion:
To arrange financing for a stand-alone project, prospective lenders must be
convinced that the project is technically feasible and economically viable and
that the project will be sufficiently creditworthy if financed. Establishing
technical feasibility requires demonstrating that the construction can be
completed on schedule and within budget and that the project will be able to
operate at its design capacity following completion. Establishing economic
viability requires demonstrating hat the project will be able to generate
sufficient cash flow so as to cover its overall cost of capital. Creditworthiness
will be established by demonstrating that even under reasonably pessimistic
circumstances, the project will be able to generate sufficient revenue to cover
all operating costs and to service project debt in a timely manner. The loan
terms have an impact on how much debt the project can incur and still remain
creditworthy.
PROJECT FINANCING
Page 16 of 32
From the perspective of potential investors, the main risks relate to project
completion, market, foreign currency, and supply of inputs. The objective is
to allocate these risks to those parties who are in the best position to control
particular risk factors. This reduces the moral hazard problem and
minimises the costs of bearing risks.
PROJECT FINANCING
Page 17 of 32
PROJECT FINANCING
Page 18 of 32
Supply of inputs:
This is important for power projects, which require a reliable supply of
quality fuel. The risk is covered through a contract with a fuel supply
agency. The price risk is usually covered through a provision to pass on
increases in fuel prices through higher tariffs. Such an arrangement i.e.
transferring the ris of increases in fuel prices from the project to the
power purchaser, may have an adverse impact on the incentives of the
project sponsor to control price increases. A corollary, it increases the
responsibility of the power purchaser to monitor the increase in input
prices.
Hedging with forwards and futures:
A forward contract obligates the contract seller to deliver to the contract
buyer (1) a specified quantity (2) of a particular commodity, currency, or
some other item (3) on a specified future date to a stated price that is
agreed to at the tie the two parties enter into the contract. A futures
contract is similar to a forward contract except that a futures contract is
traded on an organized exchange whereas forwards are traded over the
counter and a futures contract is standardized whereas forwards is
customized.
Interest rate Cap Contract:
An interest rate cap contract obligates the writer of the contract to pay the
purchaser of the contract the difference between the market interest rate
and the specified cap rate whenever the market interest rate exceeds the
cap rate.
PROJECT FINANCING
Page 19 of 32
Sector Risk:
PROJECT FINANCING
Page 20 of 32
Sector risk refers to the risk in certain sectors because of the role of
government agencies in those sectors. For example, in the power sector, the
buyer is usually a government utility agency that transmits and distributes
power. The solvency of the utility is critical for the take or pay power
purchase agreement to have any value. For selected power projects, the
Indian government has agreed in principle to give counter guarantees to back
up state guarantees for the State Electricity Boards (SEBs), payment
obligations to private generating companies, on a specific request to the state
government concerned and subject to the state government agreeing to certain
terms and conditions.
For toll roads, government support may be necessary to enforce toll
collections. Similarly, in the case of municipal services such as water supply
and solid-state disposal, the support of municipal authorities is important. In
each case, the government may guarantee contract compliance of the
respective agencies.
Commercial risk:
Commercial risk refers to the risk to profitability arising from market demand
and price; availability of inputs and prices; and variations in operating
efficiency. These risks, except to the extent they are induced by country risk
and sector policy risk, should ideally be borne by the investors. However, as
noted in the World Developmental Report, 1994, in such projects, the market
risk or the risk arising from fluctuation in demand is effectively transferred to
the government through the take or pay formula. This becomes necessary
because the market risk is intermingled with the danger that financially
troubled power purchasers or water users may not honour their commitments.
Overall sector reform is required to eliminate policy-induced risk and thus
reveal the market risks.
CHAPTER 5: SECURITY ARRANGEMENTS
PROJECT FINANCING
Page 21 of 32
PROJECT FINANCING
Page 22 of 32
After the project commences operations, contracts for the purchase and sale
of the projects output or utilization of the projects services normally
constitute the principal security arrangements for project debt. Such contracts
are intended ensure that the project will receive revenues that are sufficient to
cover operating costs fully and meet debt service obligations in a timely
manner.
PROJECT FINANCING
Page 23 of 32
Step-up provisions:
The strength of these various agreements can be enhanced in situations where
there are multiple purchasers of the output. A step-up provision is often
included in the purchase and sale contracts. It obligates all the other
purchasers to increase their respective participation in case one of the
purchasers goes into default.
Raw material supply agreements:
A raw material supply agreement represents a contract to fulfil the projects
raw material requirements. The contract specifies certain remedies when
deliveries are not made. Often both purchase and supply contracts are made
to prove=ide credit support for a project.
A supply-or-pay contract obligates the raw material supplier to furnish the
requisite amounts of the raw material specified in the contract or else make
payments to the project entity that are sufficient to civer the projects debt
service.
Supplemental credit support:
Depending on the structure of a projects completion agreement and the
purchase and sale contracts, it may be necessary to provide supplemental
credit support through additional security arrangements. These arrangements
will operate in the event the completion undertaking or the purchase and sale
contracts fail to provide the cash to enable the project entity to meet its debt
service obligations.
Financial support agreement:
A financial support agreement can take the form of a letter of credit or similar
guarantee provided by the project sponsors. Payments made under the letter
of credit or similar guarantee are treated as subordinated loans to the project
company. In some cases it is advantageous to purchase the guarantee of a
financially able party to provide credit support for the obligations of a project
company/
PROJECT FINANCING
Page 24 of 32
One of the most critical questions project sponsors need to address is whether
a legally distinct project financing entity should be employed and how it
should be organized. The appropriate legal structure for a project depends on
a variety of business, legal, accounting, tax, regulatory factors.
Undivided Joint interest:
Projects are often owned directly by the participants as tenants in common.
Under the undivided joint interest ownership, each participant owns an
PROJECT FINANCING
Page 25 of 32
undivided interest in the real and personal property constituting the project
and shares in the benefits and risks of the project in direct proportion to the
ownership percentage. The ownership interests relate to the entire assets of
the project; no participant is entitled to any particular portion of the property.
When the project is organized, the participants choose someone in their ranks
to serve as the project operator. This arrangement is particularly suitable
when one of the owners already has operations in the same industry that are
of a similar nature, or otherwise has qualified employees available. The duties
of the operator and obligations of all other parties are specified in an
operating statement. The joint venture will require each participant to assume
responsibility for raising its share of the projects external financing
requirements. Each sponsor will be free to do so by whatever means are most
appropriate to its circumstances. Thus for example, if a sponsor owns 25
percent of the project, it will be required to provide, from its resources, 25
percent of the funds necessary to construct the project.
The undivided joint interest has particular appeal when firms of widely
differing credit strength are sponsoring the project. By financing
independently, the higher-rated credits can borrow at a cost that is lower than
the cost at which the project entity can borrow based on its composite credit.
Depending on the sponsors ability to take immediate advantage of the tax
benefits of ownership arising out of the project, direct co-ownership may also
provide the project sponsors with immediate cash flow to fund their equity
investments.
Corporation:
The form of organization most frequently chosen for a project is the
corporation. A new corporation is formed to construct, own, and operate the
project. This corporation, which is typically owned by the project sponsors,
raises funds through the sponsors equity contributions and through the sale
of senior debt securities issued by the corporation. The senior debt securities
typically take the form of either first mortgage bonds or debentures
containing a negative pledge covenant that protects their senior status. The
negative pledge prohibits the project corporation from granting a lien on
PROJECT FINANCING
Page 26 of 32
project assets in favour of other lenders unless the debentures are secured
rateable. The corporate form permits creation of other types of securities,
such as junior debt (second mortgage, unsecured, or subordinated debt),
preferred stock, or convertible securities.
The corporate form of organization offers the advantages of limited liability
and an issuing vehicle. Nevertheless, the corporate form has disadvantages
that must be considered. The sponsors usually do not receive immediate tax
benefits from any investment tax credit (ITC) the project entity can claim or
from construction period losses of the project (see Tax Considerations
below). Also, the ability of a sponsor to invest in the project corporation may
be limited by provisions contained in the sponsors bond indentures or loan
agreements. In particular, the provisions restricting investments either by
amount or by type may impose such limitations.
Partnership:
The partnership of organization is frequently used in structuring joint venture
projects.
PROJECT FINANCING
Page 27 of 32
However, there must be at least one general partner who does have such
exposure.
Financing options
(a) Equity finance
Government policy allow a debt equity ratio of 8:2, however lending
institutions advocate a gearing ratio up to 7:3 as a prudent measure of
lending. Specialised infrastructure and mutual funds have come up to
bridge the equity gap in mega projects such as Global Power investment
of GE Caps, the AIG Asian Infrastructure Fund, and the Asian
Infrastructure Fund of Peregrine Capital Ltd. And ICICI.
(b) Debt Financing
PROJECT FINANCING
Page 28 of 32
PROJECT FINANCING
Page 29 of 32
PROJECT FINANCING
Page 30 of 32
PROJECT FINANCING
Page 31 of 32
PROJECT FINANCING
Page 32 of 32