Sie sind auf Seite 1von 28

Doc. No.

HM - LE - PRWIDE M0101 - DOC - MA -PMC -

Project: Hyderabad Metro Rail

Date: 29-11-2012

00 - 002
Revision. 3
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 1 of 28

Table of Contents
1

Introduction..........................................................................................................
1.1
1.2

Overview.............................................................................................................. 7
Objective..............................................................................................................8
Resource Management........................................................................................

2.1
2.2
3

Organisation and Roles & Responsibilities...........................................................8


Resource Requirement......................................................................................10
Interface Requirements......................................................................................

3.1
3.2
3.3
4

Allocation of Interface requirements...................................................................11


Interface description between contractors..........................................................11
Areas of concern................................................................................................13
Process Management........................................................................................

4.1
4.2
4.3
4.4
5

Change of interfacing requirement.....................................................................15


Verification and Validation of Interfacing Requirements......................................15
Testing and Commissioning on Interfaces..........................................................15
Quality Procedures.............................................................................................15
Document Management.....................................................................................

5.1
5.2
5.3
6

Reference Documents.......................................................................................16
Structure of Reference Documents....................................................................17
Version Control of Interface Documents.............................................................17
Communication..................................................................................................

6.1
Terms of Reference of Interface Meetings..........................................................19
6.2
Exchange of Information between Contractors..................................................20
6.3
Submission
to Employers Representative.........................................................20
18-05-2012
0
New
6.4
Request
for
Employer/ Employers
Representative Attention.............................20
DATE
REV. NO. Preparation
DESCRIPTION
Designed Checked Approved
7

REVISIONS
Interface Hazard Management...........................................................................

Programme........................................................................................................
LARSEN & TOUBRO LIMITED

8.1
8.2
CLIENT :
8.3

Key Activities......................................................................................................22
Key Dates.......................................................................................................... 24
CONSULTANT :
Critical Items / Critical Path................................................................................24
M/S LOUIS BERGER CONSULTING PVT.

RAIL (HYDERABAD) LIMITED


9L&T METRO Records.............................................................................................................
LTD
PROJECT :

HYDERABAD METRO RAIL PROJECT

List of Figures

SUPPLIER / CONTRACTOR:

LIMITED, Construction Viaduct


Figure
1LARSEN & TOUBRO
:
Interface
JOB No. LE 100514
Organisation.
10
TOTAL NO. OF PAGES
TITLE : :
Figure
2
Project
Life
Cycle
NAME
SIGN
DATE
.
INTERFACE MANAGEMENT PLAN FOR
DSGN
13 DS
Figure
3
:
Flow
chart
for
Interface
Management
Plan
CHKD
Process..
16
APPD
DOC. No.

RELEASED FOR

CODE

REV.

HM - LE - PRWIDE M0401 - DOC - MA -PMC - 00 - 002

PRELIMINARY

CONSTRUCTION

TENDER

INFORMATION

APPROVAL

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Project: Hyderabad Metro Rail

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 2 of 28

List of Appendices
Appendix A.........................................................................................................................
Appendix B: Interface Specification Form.....................................................................
Appendix C: Interface Change Request Form (ICRF)..................................................

Acronyms & Definitions


The following definitions apply throughout this procedure and will be used in
interpreting the meaning of terms used in this document
Term
Definition
AFC

Automatic Fair Collection

ASS

Auxiliary sub-station

COM

Communication

CSD

Combined Services Drawings.

CW
DBS
DCIV
DME
DMP
ER
GS
HVAC
IM
IMP
IMPG
MIM
MSS
OETS
PSS

Civil Works
Depot building services
Depot civil
Depot Maintenance equipment
Design Management plan
Employers Representative
General Specification
Heating ventilation air conditioning
Interface Manager
Interface Management Plan
Interface Management Programme
Master interface matrix
Manual of Specification and Standards
Overhead Electrical traction system
Power supply and Supervisory Control And Data Acquisition
system
Quality Management plan
Rolling stock
Receiving sub-station
Signal and train control
Station building services
Station civil
Track work
Technical Specification
Viaduct

QMP
RSK
RSS
S&T C
SBS
SCIV
TRW
TS
VIA

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 3 of 28

Introduction

The Hyderabad Metro is a proposed rapid transit system for the city of
Hyderabad, Andhra Pradesh, India. The present scope of project includes three
corridors along high-density traffic corridors, spanning approximately 71kms.
Corridor-1 will run from north to south and will be 28.87 km long, connecting 27
stations from Miyapur to L. B. Nagar. Corridor-2 will be 14.78 km long, connecting
14 stations from Parade Grounds to Falaknuma. The Corridor-3 will run from north
to south and will be 27.51 km long, connecting 23 stations from Nagole to
Shilparamam.
The Hyderabad Metro will be an elevated system with a 9m-wide viaduct
structure. The viaduct will run from the central median of the road and will have
two tracks. The tracks will be 1435 mm standard gauge. The system's electrical
traction will be AC and power will be supplied through the overhead electric
system.

1.1

Purpose of Document

This plan is wholly based on requirements captured in General Specification for


each interface, wherein the Contractor shall develop, an IMP which is mutually
acceptable to other interfacing Contractor/s. The purpose of this plan shall
identify the system and the sub-systems as well as the civil works and facilities
with interfacing requirements. It shall define the authority and responsibility of
the Contractor's and Other Contractors' staff involved in interface management
and development.
This Plan describes the methodology for managing interfaces to achieve a
comprehensive design covering all foreseen aspects specific to the VIA system. It
shall identify the information to be exchanged, precise division of responsibility
between the Contractors and integrated tests to be performed at each stage of
the Contractor's works. It addresses the works programme of the Contract to
meet the key dates of each Contractor and highlight programme risks if any to
Employer Representative. It shall also indicate dates for the commencement and
completion of each principal activity and the key dates for exchanging system
data and interface design information by the Contractor and the Interfacing
Other Contractor.
This Interface Management Plan (IMP) outlines the activities to demonstrate how
the Contractor proposes to achieve a coordinated VIA System, compatible with
design and construction carried out by other interfacing contractors. The plan
describes the methods and strategies for managing interfaces. It also provides
control of associated interfaces as the project grows through engineering,
construction, installation and closeout.

1.2

Overview

The plan outlines the process for effective exchange of information for a safe &
effective execution of the Hyderabad Metro project especially with large number
of interfaces that increase the task complexity. The Interface Management Plan
allows identification of critical interfaces through a structured approach leading
to early identification of potential issues and resolution thereon.

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 4 of 28

The interfaces covered in this document is specifically for VIA system, but with
its association with other contractors, which are different in their nature, the
document is therefore organized considering how these interface activities would
be managed as a whole. This interface management plan shall be applicable
from Design, Execution and handing over the VIA system
The Interface management process would involve various stages from design,
manufacturing, construction, installation, testing & commissioning including final
acceptance of the Employer.

1.2.1 Objective
The objective of the Interface management plan is to facilitate agreements with
other stakeholders regarding roles & responsibilities, providing interface
information and identification of critical interfaces. It also ensures that all
interfaces between the VIA & other Contractors as required for the completion of
scope of works of the Contract are identified and controlled. This shall ensure
integrity between the different elements associated with the project.

Management

2.1

Organisation and Roles & Responsibilities

The following organogram shows the roles and responsibilities identified to


coordinate all interface activities under the Contract with that of the Interfacing
Parties.
Team level VIA Interface Organisation

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 5 of 28

Figure 1 : VIA Interface Organisation

Responsibility and authorities of the identified Interface members are as follows:

2.1.1 Project Manager


The Project Manager for VIA shall be responsible for all contractual, cost and
project delay issues for all interface activities. This may include resolution of
interface conflicts on scope of supply and responsibilities, and specific arbitration
that may be required among the interfacing parties.
Project Manager shall extend his support to the Interface Manager for achieving
interface settlement according to the time schedule.
Shall also be responsible for ensuring that interface agreement does not conflict
with any other Contractor interfaces and scope of responsibilities

2.1.2 Chief Interface Manager


The roles of Chief Interface Manager shall be to support the coordination of the
Interface Manager (VIA ) with other nominated Interface Managers of L&TC. .The
Chief Interface Manager shall ensure the overall Interface Management plan is
followed throughout the Project Delivery phase.
The Chief Interface Managers responsibilities are:

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 6 of 28

1) Facilitate consultations with nominated Interface Managers within L&T C on


regular basis to achieve agreements on interfaces;
2) Facilitate consultations between Interface Managers of L&T C and that of
Client Contractors, as required
3) Develop and manage the Interface Action Log for all interface issues that
provided status of interfaces, closed out issues;
4) Resolution of the interface issues and conflicts arising between Interface
Managers;
5) Facilitate specific meeting on request of any interfacing parties;
6) Monitor and validate the exchange of Interface data between the various
package Contractors;
7) Extend the information to the Client L&T Hyderabad Metro Rail Limited.

2.1.3 Interface Manager


Interface Manager (IM) of VIA is primary contact person for internal and external
personnel and will establish direct lines of communication between the interface
partners of the distinct interfaces. IM shall be the single point of contact for
interface meetings, actions, planning, scheduling and coordination. The IM shall
manage all interface/issues between design and execution teams. The IM shall
ensure that all interface issues are captured, managed and brought to the
Interface Meeting for a timely resolution.
The IM ensures that the process identified in this plan is adhered to and followed.
The IM will coordinate the interfaces activities performed under the responsibility
of the Project Manager and the Chief Interface Manager.
The Interface Managers responsibilities are:
1) Identifying, verify and record the interfacing activities of the system and
interfacing sub-system and provide latest information to Chief Interface
Managers for review;
2) Note the changes and inform the impact to other Interface Manager through
the Interface meetings;
3) To communicate with the Interfacing contractors for information that can
impact the coordination Drawings. Keep the Project Manager, Design
Manager, and Construction Manager abreast of the current interface issue.
4) To coordinate for all Interface activities where VIA is the Lead & Match
Contractor;
5) To convene meetings with the Match Contractors wherever VIA is the Lead
Contractor and subsequently prepare the necessary Interface Specification
Sheets and DID for sign off with the respective Match Contractor. Updation of
the signed off documents shall be posted to all concerned;
6) To ensure that this plan, associate program and subsequent procedures are
kept updated;
7) To support the Project Manager in developing interfaces verification &
validation test plans and activities;
8) Develop and maintain Detailed Interface Document;
9) Following-up the Interface Requirement Specifications;
10)
Coordinate with the other Contractor to establish coordinated CSD & SEM
Drawings [case to case];
11)
IM shall ensure compliance to the Works program of VIA and exchange
data in time for other Contractors to meet their Works program;
12)
To identify & resolve the Interfaces with Employers Contractors who may
be subsequently identified during the course of the Project. To keep up to date
the VIA and other contractors interface list.

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 7 of 28

2.1.4 Execution Manager

Execution of works implementing interface actions agreed in the


interface meetings and in interaction with Interface Manager.
Taking up evolving Interface issues to Interface Manager for
resolutions

2.1.5 Design Manager

2.2

Preparation of GFC drawings incorporating resolved interface issues


in line with section 4
Preparations of as built drawing after the works are executed
incorporating the Interfaces, as part of validation of interfaces.
Update Interface Manager VIA of all such information and
incorporation.

Resource Requirement

The resource requirements of manpower is the allocation/mobilisation of staff for


VIA. This description of the manpower shall be explicitly for the VIA team, the
other contractors shall be limited to the interface manager.
The resource requirement for implementation of IMP is broadly classified to
manpower, tools and logistics.
The manpower allocation is described in section 2.1 and the roles identified in
referred section is mentioned in Appendix A
The tools which are used for effective interfacing are
Interface management plan (IMP)
Detailed Interface Document(DID)
Interface Action Log register
Interface Demarcation Document
Request for information and.
Information change request form
Logistics of VIA contractor will be adhered to/by the other interfacing contractors
and the project schedule. All interface logistics issues will be based on Section
8.1 Key activities and Section 8.2 Key dates.

Interface Requirements

The interface requirements management system is to be implemented between


the Lead Contractor and Match Contractor. It is considered that the above
management provides effective control of information flow related to systems
requirements and in particular the preservation of information for the project life
of the system with respect to the changes in the system and its environment.
The approach proposed in this plan is considered sufficient to meet the package
requirements in order to successfully deliver the Hyderabad Metro Project.

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 8 of 28

The interface requirements shall be identified prior to the Design & Execution
stages by all interfacing parties and entities so that re-design, re-work and
associated costs and schedule impacts are minimized. This shall be
communicated to all affected entities.
The main sources of interface requirements to be imported and traced originate
from:
General Specification;
Technical specification
Interface specification [Appendix A1 to A8];
The Interface Requirements shall be tabulated in Task Allocation Table (TAT) for
all the interfaces listed in the VIA IRS and additional, if any.

3.1

Allocation of Interface requirements

The interface requirements are generally classified in to Design & Execution


Interfaces and the communication shall be established with each of the Other
Contractor. The information shall be regularly updated and periodically reported
to Employer as per the template in Section 3.2 below.

3.2

Interface description between contractors

In continuation to the allocation of interface requirementError: Reference source


not found the following Task Allocation table (TAT) sections identify the
description between the contractors.
Interface ID

Interface
Category

Interface
Description

Responsibi
lity
Of VIA

Responsibility
of Other
Contractor

Remarks

This table (TAT) indicates the responsibility and status in remarks column of all
the interfaces identified and evolved in the design and execution process.
Supporting documents for this table shall be the Interface Specification Forms
(refer Appendix B) and DIDs.

VIA Contractor has responsibility for the design, installation, coordination, testing
and commissioning of the Viaduct systems. Deal with problems occurring during
the implementation of interfaces and ensure the integrity of the interfaces
between the VIA and interfacing partners.
The interfacing partners with Viaduct are listed below:
1) Interface with Communications (COM)
2) Interface with Depot Civil Works (DCIV)
3) Interface with Overhead Electric Traction System (OETS)

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

4)
5)
6)
7)
8)

Interface
Interface
Interface
Interface
Interface

with
with
with
with
with

Checked by : CS
Nagaraja

Page 9 of 28

Signaling & Train Control (S&TC)


Station Building Services (SBS)
Station Civil Works (Station Civil (SCIV)
Track work (TRW)
Power Supply (PSS)

The interfaces listed in the IRS of the VIA provide the baseline for the interfaces
identified.
Further based on the allocation of roles of via as lead or match contractor with
other interfacing partners is listed below.
Interfacing
Partners
with VIA
OETS
TRW
SBS
SCIV
DCIV
COM
S&TC
PSS

Lead

Match

Contractor

Contractor

OETS
VIA
SBS
SCIV
VIA
COM
S&TC
PSS

VIA
TRW
VIA
VIA
DCIV
VIA
VIA
VIA

The details on the above interfaces shall be as per the respective Detailed
Interface Document to be established with each of the above Contractors.

Both the Lead and Match have similar obligations towards interface management
process. The Roles and Responsibilities of Lead and Match Contractor are
tabulated in the table below:

Responsibility Matrix of the Lead and Match


contractors
Role & Responsibility
1. Initiating the arrangements for interface meetings
2. Arranging the recording and issuing minutes,
(Action Log ) of Interface Management Meetings
3. Preparation of jointly prepared documents and
their
subsequent
revisions
viz.
Interface
Management Plans ( IMP ); Detailed Interface

Lead

Match

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

3.3

Checked by : CS
Nagaraja

Role & Responsibility


Documents ( DID), method statements, interface
test specifications and reports
Initiation for preparation of the jointly prepared
document.
Preparation of document with respect to Lead
Contractors scope of work and responsibility
Preparation of document with respect to Match
Contractors scope of work and responsibility
Signing of the jointly prepared document and
submission
individually
to
the
Employers
Representative
for
information
comments/
approval

Lead

Page 10 of 28

Match

Areas of concern

Any two Contractors of an interface will have an equal degree of responsibility for
achieving interface settlement according to the time schedule, under the
coordination and supervision of the Interface Manager with support from the
Project Manager.
The concerned Contractor shall ensure that all resolutions will be documented
through technical specifications, drawings and detailed schedules agreed by the
affected Contractors. The Project Manager will approve the final resolution.
Ensure that the resolved or unresolved Interface is brought to the notice of
Employer or Employers Representative

Process Management

Various elements in association with the IMP that encompass the entire process
in identified in the
section

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Project: Hyderabad Metro Rail

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 11 of 28

Figure 1: Illustrated Flow chart for VIA Interface


Management

4.1

Change of interfacing requirement

The change shall be initiated formally through an Interface Change Request Form
(ICRF). This should be circulated to all the stakeholders for their reviews and
comments. When an ICRF is initiated to propose a change in interface

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 12 of 28

requirements it shall be captured in the interface action log. If one of the


interfacing contractors requests for a change, this will be managed through an
ICRF, please refer Annexure C for the template. The form shall be used only if
an interfacing contractor requests a change to some aspect which has been
previously agreed in the Interface meeting. The originator has to declare the
close-out of the ICRF in the subsequent Interface meeting, and accordingly
reflect in the action log.
However, during the process if any conflict/ clarification arise, the decision by the
Employers representative shall be final and binding on partners. The same will
be dealt under respective contract conditions and obligations.

4.2 Verification
Requirements

and

Validation

of

Interfacing

Testing activities shall be based on the requirements capture and referred in


Detailed Interface Document. This shall ensure compatibility between systems
and that every component functions and performs in tandem. Task Allocation
Table shall be made to ensure that the identified interface requirements are
verified and validated. This will be developed systematically and shall thoroughly
evaluate all individual system components and their integrated performance.
The V&V needs shall be captured in the T&C Plan, if applicable, which will cover
subsystem qualification testing, factory inspection and testing, installation tests,
on-site inspection, on-site integrated test and finally system acceptance test and
inspection.
As part of verification the preliminary drawings/documents shall then be
updated, revised and issued to relevant Interfacing Parties for review and
confirmation, to resolve any outstanding interface coordination issues. The entire
process of review, comment, feedbacks and meetings shall be repeated until the
final set of coordinated and refined DWGs are completed and submitted to the
LTMRHL/CE for second stage verification before they are progressively issued for
site construction use.

4.3

Testing and Commissioning on Interfaces

The approach to be adopted by the Contractor for the management of interface


in the Testing and Commissioning stage shall be addressed in the respective VIA
Testing & Commissioning Plan
HM-LE-PRWIDE-M0101-DOC-MA-PMC-00-xxx

4.4

Quality Procedures

All activities and works described in the present document would be performed
in line with the approved Quality Management System confirming to
requirements of ISO 9001:2008.

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Project: Hyderabad Metro Rail

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Document Management

5.1

Reference Documents
Title of Document

Checked by : CS
Nagaraja

Page 13 of 28

Reference

Detailed Interface Document of VIA with


OETS
Detailed Interface Document of VIA with
TRW

HM - LE - PRWIDE M0101 - DOC - MA


-PMC - 00 -XXX
HM - LE - PRWIDE M0101 - DOC - MA
-PMC - 00 - XXX

Detailed Interface Document of VIA with


SBS

HM - LE - PRWIDE M0101 - DOC - MA


-PMC- 00 - XXX

Detailed Interface Document of VIA with


SCIV

HM - LE - PRWIDE M0101 - DOC - MA


-PMC- 00 - XXX

Detailed
DCIV
Detailed
COM
Detailed
S&TC
Detailed
PSS
General

Interface Document of VIA with

HM - LE - PRWIDE M0101 - DOC - MA


-PMC- 00 - XXX

Interface Document of VIA

with

Interface Document of VIA

with

Interface Document of VIA

with

HM - LE - PRWIDE M0101 - DOC - MA


PMC - 00 - XXX
HM - LE - PRWIDE M0101 - DOC - MA
-PMC- 00 - XXX
HM - LE - PRWIDE M0101 - DOC - MA
-PMC- 00 - XXX

Specification

Architectural

works

for

and

Civil
MEP

Works

works

January 2012
Interface Requirement Specifications (IRS)

HM-AC-PRWIDE-M0101-DOC-CD-VIA01-001

Manual of Standards and Specifications


(MSS)
Contract Agreement and Conditions of
Contract (COC) Vole II Jan 2012
Co-ordinated Construction Plan
Combined Services Drawings (CSD)
Structural

Electrical

Mechanical

(SEM)

drawings
Interface Demarcation Diagrams (IDD)
Detailed Interface Documents (DID )
Project Management Plan
Work

Plan

(incorporating

HM-LE-PRWIDE- M0101-DOC-MA-PMC00-001
Works

Programme and Submittals Schedule)


Quality Plan

HM-LE-PRWIDE- M0101-DOC-MA-PMC00-003

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Quality Assurance Management Plan

Checked by : CS
Nagaraja

Page 14 of 28

HM-LI-PRWIDE- M0101-DOC-MA-QMS00-001

System Assurance (RAMS) Management


Plan
Design Management Plan
Environmental Plan

HM-LE-PRWIDE- M0101-DOC-MA-PMC00-006

Installation Plan
Testing and Commissioning Management
Plan
Defects Liability Management Plan

HM-LE-PRWIDE- M0101-DOC-MA-PMC00-008

Maintenance Plan

5.2

Structure of Reference Documents

Apart from the plans, the reference Interface documents, namely the following -DID for each contractor
-

No.

DID for each Contractor


o The template and structure of the document shall be as per the
detailed document developed and mutually agreed upon with each
of the other Contractors and Employer
Weekly Interface Action Log shall have the following tabular structure
System

5.3

Dated

Interface Issue From


Raised

To

Remarks

Status

Interface Change Request Form shall be as detailed in Appendix C


Interface Specification Form detailed in Appendix B shall form a part of the
DID, made for each of the Interface activity.

Version Control of Interface Documents

Respective Quality management system for VIA informs on the version control of
all documents for the project, this includes the interface documentation.
Configuration management addressed as part of Quality Management System for
the project is equally applicable to the Interface Management. The same
guidelines are applicable and followed through the Interface Documentation
included in this plan.

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Communication

Checked by : CS
Nagaraja

Page 15 of 28

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

6.1

Checked by : CS
Nagaraja

Page 16 of 28

Terms of Reference of Interface Meetings

The terms of reference of interface meetings is drawn out as per below example.
The document reference is provided in the Reference document

6.2

Exchange of Information between Contractors

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 17 of 28

The process for the exchange of information between the contractors has been
identified in the Interface Management flow chart, please refer section 4.1 on a
more specific note that exchange of information shall be captured in interface
register and shall be available for engineering traceability
The registers of the interface information and Interface Logs shown below are the
core tools that shall be used for communication on interface issue.
a) RFI Form - Request for Information(Refer Appendix F) ;
b) Interface Action Log;
c) RFI Status Register;
d) Interface Change Request Form (ICRF);

6.3

Submission to Employers Representative

The approach to be adopted by the contractors on the submission of the


Interface Management Plan to Employers Representative shall be through
Electronic Document Management System (EDMS).

6.4 Request for Employer/ Employers Representative


Attention
The main criteria in requesting for Employer / Employers Representative
attention is to request intervention if an issue is not resolved between two
interfacing contractors
Any major re-work or delay arising due to fulfilment of interface requirements
due to improper/inadequate/absence of information, same shall also be brought
to the attention of Employer / Employers Representative.
The clarifications and conflicts shall be dealt under respective contract conditions
and obligations.
The Project identified Electronic Document Management System (EDMS) as
formal method of transmission of information, shall be used to bring Employer /
Employers Representative attention

Interface Hazard Management

7.1

Strategy and Approach

The foreseen interface hazards shall be brainstormed as part of Interface


meeting and the outcome captured in the interface hazard log. This shall be
managed by the Interface Manager and periodically reviewed with the Project
Manager.
Please refer table the following foreseen Interface Hazard table that shall be
followed as part of the Interface management. The interface hazard log as per
below shall be updated continuously during the project life cycle.
ID
VIA_HA
Z-001

Syste
m
OETS

Hazard

Cause

Consequence

Mitigation
plan
Falling of OHE Inadequate
System failure 1)
Ensure
mast.
threaded length of followed
with sufficient
the U bolt for fixing other losses.
threaded length
the OHE mast.
in
design/drawing.
2) Inspect bolts

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

ID

Syste
m

Hazard

Cause

Checked by : CS
Nagaraja

Consequence

Page 18 of 28

Mitigation
plan
during deliver.
3)
Inspect
available length
during casting.
4) Rejection of
parapet
segment
with
improper
threaded length.

Definition of the terms used in Interface Hazard log as follows:


ID: Unique identifier to distinguish every Interface Hazard;
System: The system from which this hazard is originating from;
Hazard: A physical situation resulting in system failure;
Cause: reasons how and why a particular hazard may come into existence;
Consequence: an unintended event or series of events that results in death,
injury, loss of a system or service, or environmental damage.

Programme

The interface activities as detailed in the IRS of VIA TS and any other as required
for the project shall be ensured in a timely manner to meet the Key dates of the
respective VIA Works program and also ensure that the other Contractors
achieve their respective milestone dates.

8.1

Key Activities

The following table shows the Key activities envisaged for the establishment of
the Interface and sign off on the DID with each Contractor. However, the detailed
interface requirements along with additional interfaces as required with each
Contractor shall be established and mutually agreed with other Contractors.
Sl
no
1
2

3
4

VIA Activity

Interface Contractor/s

Area of interface

Casting of Piers, Segments


OETS/PSS
Respect the SOD
and Parapets
/TRW/SBS/SCIV/DCIV/COM/S&TC clearances
Provision of OHE
Casting of Parapet walls
Masts
OETS
including design
Provisions for SME
Coordination for exact
Provide necessary openings
requirement
of
in Viaduct structures for
OETS/SBS/SCIV
openings for location
cable crossing /openings
and size
Piers,
segments
and
OETS/SBS
Detailed drawing and
ParapetsProviding
of
installations of the
earthling
connections,
earthling arrangement
earthling connection for
, connections and

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Hand Rail

OETS/PSS

Design and construction of


Sub Structure

TRW

7
8
9

10

11

12

13

Coordinate
Design of the station
viaducts including providing
dowel bars in pier and pier
cap and diaphragm for
further
construction
by
others
Construction and installation
of precast Box girder for the
main Viaduct within the
station location.
Construction of all the piers
including those supporting
the station Viaduct
Shall
coordinate
and
provide additional width (if
required) to accommodate
the egress steps as per the
requirements of statutory
clearances

seamless
cable
duct
13 containment from viaduct to
station
14 Design and construct the
depot access ramp.

Page 19 of 28

continuity

Leaving openings in Viaduct


Structure and later on
sealing

Design and provide the


transition slabs at the
junction of ballast less and
ballasted track on the ramp
and further shall prepare the
ground ( including sub
grade ) with grading and
drainage
in
remaining
portion of the ramp
Design and construction of
Drainage system for Viaduct
Clear and hand over the
Track construction envelope

Checked by : CS
Nagaraja

TRW

TRW
TRW
TRW

Providing Cable and


dropping from Viaduct
to ground for 25 KV ,
LT and control cables
etc
Construction of Track
plinth / slab/ turn out/
cross over locations/
Provision of transition
slabs between ballast
less and ballasted
track
and
further
laying of track on the
ramp
Details
of
Track
Design
Clearance of track
construction envelope
viaduct lighting and
Emergency
socket
outlets.

SCIV

Supply of dowel bars


and construction of
concourse
and
platform level cross
girders

SCIV

Construction
and
installation of precast
Box girder

SCIV

Construction of all the


piers

SCIV

Egress Steps

SCIV/PSS
DCIV

Seamless cable duct


containment
from
viaduct to station and
vice versa.
Civil interfaces and
Alignment

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 20 of 28

coordination

15

16

17

18

19

20

21

Design, coordinate, supply


and
install
the
cable
containment/ cable trough
etc. and provide openings in
the cable trough as per
COM
contractors
requirements
Design and coordinate the
cable containment, cable
trough along with any
openings required for cable
crossings towards the track
for signalling cables along
Track side
Shall also keep provision
of space for line side
equipments
Coordination and Provision
of adequate space for SAB (
Signaling Apparatus Box )
along Viaduct
Coordination and Provision
of adequate space for signal
mast along Viaduct
Allow the side wall of
viaduct for fixing cable
containment
by
PSS
Contractor.
Provide necessary openings
in Viaduct structures for
cable crossing from viaduct
to station and vice-versa,
inside the station from one
side to other on both ends,
viaduct to viaduct and
trackside
to
top
of
flange/cable trough/parapet
wall/any part of the Viaduct.
Develop SEM drawings
based on requirement

COM

COM
cable
containment system
along trackside and
station platform

S&TC

Installation
of
Trackside equipment
and
cabling
infrastructure
for
signalling along the
viaduct
for
all
corridors

S&TC

Mounting of SAB /
trackside box and
other
line
side
equipments

S&TC

Mounting
post

of

signal

PSS

Arrangement
for
laying power and
control cables on the
Viaduct

PSS

Providing openings in
Viaduct structures

PSS

SEM Provisions

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA -PMC -

Project: Hyderabad Metro Rail

Date: 29-11-2012

00 - 002
Revision. 3
Title: Interface Management Plan

Checked by : CS
Nagaraja

Prepared by: D Srinath

Page 21 of 28

KEY DATES SCHEDULE FOR VIADUCT


SL.N
O

KEY DATE
DISCRIPTION

ACCESS TO SITE

RESPONSIBILITY

EMPLOYER

STAGE 1

STAGE 2

STAGE 3

STAGE 4

STAGE 5

STAGE 6

START

COMPLETE

START

COMPLET
E

START

COMPLETE

START

COMPLETE

START

COMPLETE

START

COMPLETE

4/13/12

7/13/12

4/13/12

11/13/12

4/13/12

12/13/12

4/13/12

9/13/13

4/13/12

3/13/13

4/13/12

6/13/14

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 22 of 28

PERMANENT
WORKS FOR
VIADUCT WORKS

CONTRACTOR

7/14/12

4/13/2014

11/14/12

10/13/14

12/14/12

2/13/15

9/14/13

8/13/15

3/14/13

4/13/15

6/14/14

12/13/2015

PARAPET AND
OTHER FINISHES

CONTRACTOR

3/14/13

6/13/2014

7/14/13

12/13/14

6/14/13

4/13/15

3/14/14

10/13/15

10/14/13

6/13/15

3/14/15

2/13/2016

8.2

Key Dates

Based on the contract schedule, Employers requirement and interface meetings/agreements, the following table will be used for
monitoring the duration of the agreed up on key dates for the interfacing actives / Issues
Key Dates Schedule for Viaduct

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA -PMC -

Date: 29-11-2012

00 - 002
Revision. 3
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 23 of 28

1. Access to Site Availability of 8m ROW (within Barricading) free from


Encumbrances and Utilities to commence construction.

8.3

Critical Items / Critical Path

The critical Items/Critical Path shall be as per the Overall master Works Program
to which the VIA Works Plan meets the requirements.
Accordingly Interface activities shall be relevantly lined up with the Works Plan,
as required

Records
All records shall be maintained as per the table below:
Document Number

APPENDIX A

Description

Retention Period Minimum

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan

Checked by : CS
Nagaraja

Prepared by: D Srinath

Page 24 of 28

List of Role Players for Interface Requirements


Role

Contact
number
Sesha +91
9959022309

Name

Project Manager

Mr K
reddy

Email
k_sr@lntecc.com

VIA
Manager
1,3,5/2

Execution Mr AH Khan
Stage

+91
9502009990,

ahkhan@lntecc.com

VIA
Manager
2,4,5/1

Execution Mr K Mohan
Stage

+91
9000012265,

kmohan@lntecc.com

VIA
Execution Mr
D +91
Manager -ROBs
Sukumaran
9912199910

dsukumaran@lntecc.co
m

+ 0404023687173

raghavendrapandey@lnt
ecc.com

Chief
Manager

Interface Mr
Sanjeev +91
Sharma
9949922377

sanjeev.sharma@lntec
c.com

Interface
VIA

Manager Mr
C.
Nagaraja

csn@lntecc.com

Interface
SCIV,SBS

Manager Mr
Duvvuri +919849471
Gangadhara
934
Sastry
Manager

dgsastry@lntecc.com

Interface
OETS

Manager Mr
Srihari

rsrihari@lntecc.com

Interface
PSS

Manager Mr PVS Pawan +91


Kumar
8886856717

Interface
TRW

Manager Mr Rajan
Kumar

VIA Design Manager

Interface
DCIV, DBS

Interface Manager RS

Mr R Pandey

Mr
Alston

S. +91
9000222047

Ravi +91
9878166363

D +919989993
685

pvspk@lntecc.com

rajand.kumar@lnties.c
om

John +91
7893223964

Interface
S&TC

Manager Boyd
Mckillican

Interface
COM

Manager Diogo Cortez

boyd.mckillican@thale
sgroup.com
+351
320663

915 Diogo.cortez@thalesgr

Rem
arks

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

oup.com
Interface
AFC

Manager TBD

TBD

TBD

Page 25 of 28

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 26 of 28

Appendix B: Interface Specification Form

INTERFACE
SPECIFICATION

Ref: VIA -00001-A-01

Contractors
Sequence
Number

Contract
Designation

Date of Issue

d/m/y

Initiating
Contractor

Interface Manager

Responding
Contractor

Interface Manager

Interface
Specification
Required for;

Response
Required by;

Signature

Signature

Reviewed by;
Design
Sections

Track
work/OETS

Civil Work

Station Arch. /
Building
Services

Systems

Description of the Interface

Specific Details of the Interface

Location

Drawings / Specifications Attached


Title

Document
Prepared by:

Drawing / Specification Ref.

Name

Date

Drg. Issue

Document References (if any)

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

Page 27 of 28

Appendix C: Interface Change Request Form


(ICRF)
Discipline/Contract Package:
Name:

Unique ICR No:

Ref.

Attachments

Subject

Attribute:

Date:

Title:
Description:
Detailed Recommendation:
Reasons for Change/Justification: (Problem/Error/Non Conformance/ Improvement/
Enhancement/ Change due to other factors)
Implications:
Cost:

Importance
to
Originator:
(Critical/ High/ Medium/
Low)

Time:
Implications Remarks:

Areas of Impact:

Documents and Deliverables requiring updates:

Risk involved (if any):

Recommende
d
for
Approval

Recommen
ded
for
Approval

Proposal
Finalizatio
n

Interface
Manager
Discipline
Head/

Project
charge

Interface
Partners

&

Approved by
LTMRHL and
CE
(Technical)

In

Approved
by
LTMRHL
(Project
Control)

Distribution:
Client Advice

Date:

Project: Hyderabad Metro Rail

Doc. No. HM - LE - PRWIDE M0101 - DOC - MA

Date: 27-12-2012

-PMC - 00 - 002
Revision. 4
Title: Interface Management Plan
Prepared by: D Srinath

Checked by : CS
Nagaraja

issued

Appendix D: Request for Information (RFI)

Page 28 of 28