A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve

only a small portion of them. Which technique would be less helpful in this situation?
A) Consult with the Development Team
B) Prioritize the list and work on them in order
C) Alert management to the impediments and their impact
D) Arrange a triage meeting with all other project managers

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to
resolve only a small portion of the impediments. Which three techniques would be most helpful in
this situation?
a) Prioritize the list and work on them in order.
b) Alert management to the impediments and their impact.
c) Arrange a triage meeting with all other project managers.
d) Discuss the absence of management support with the Development Team.
e) Tell the Product Owner that Scrum isn't working.
f) Consult with the Development Team.