Beruflich Dokumente
Kultur Dokumente
The report describes and evaluates the criteria, constraints and operating
requirements for four types of hypothetical marine facilities that could potentially
be located on West Hayden Island. This report is not a development plan. The
report will assist the Port, consultants and external stakeholders in understanding
marine operational opportunities and constraints and in developing long-term
planning concepts for the site. This paper supplements a separate paper
prepared for the Port on the road and rail industry criteria, constraints and
operating requirements.
Marine Terminals
2009
Background Information:
At the West Hayden Island Community Working Group meeting on the morning
of Tuesday, February 16, 2010, we provided some setback information for the
project.
Upon review of the report and addendum that HDR prepared titled West Hayden
Island Marine Terminal Site and Operation Requirements, it has been
determined that the prepared Concept Plans have shown the northern limit of the
necessary land-based development approximately 100 feet from the +4 contour
according to the Columbia River Datum. The +4 CRD contour line denotes the
upper limit boundary for the shallow water habitat zone.
The text for Section 3.1.1 in the report incorrectly listed this offset to be 300 feet.
Conclusion:
The correct nominal dimension listed in Section 3.1.1 of the report should be 100
feet, which conforms to the Concept Plans that have been prepared.
Page 1 of 1
Port of Portland
Tim Van Wormer,
Marine Development Project Manager
121 NW Everett, Portland, Oregon 97209
Prepared by:
List of Tables
Table 1: Primary Navigational Requirements for Berth Design, Existing Conditions ............. 7
Table 2: Primary Navigational Requirements for Berth Design, 30-Year Forecast .................. 7
Table 3: Vessel Characteristics for Auto Import Terminal, Existing Conditions and
30-Year Forecast .................................................................................................................................. 8
Table 4: Vessel Characteristics for Dry Bulk Cargo, Existing Conditions and 30-Year
Forecast ............................................................................................................................................... 10
Table 5: Liquid Bulk Vessel Parameters, Existing Conditions and 30-Year Forecast ............ 11
Table 6: Container Cargo Vessel Parameters, Existing Conditions and 30-Year
Forecast ............................................................................................................................................... 12
Table 7: Crane Design Parameters, Existing Conditions and 30-Year Forecast ..................... 13
List of Figures/Exhibits
Figure 1. Aerial View of West Hayden Island....4
Figure 2. Typical Berth Configuration.......6
Figure 3. Split-Level Fixed Berth.......9
Figure 4. Floating Platform...9
Figure 5. Travelling Loader.10
Figure 6. Offshore Berth and Marginal Berth..12
Figure 7. Load Lines and Open Layouts.15
Concept Plans
BNSF
CRD
FEMA
FHWA
I-5
Interstate 5
IBC
ISO
LOA
Metro
MTMP 2020
NGVD
RMG
RO/RO
RTG
UFC
UPRR
USACE
Auto import, or roll on/roll off terminals are designed for transferring tracked or wheeled
vehicles such as automobiles onto or off of ships without crane assistance. Cargo is stored
in the yard area and transferred to and from ships by driving on or off the dock using a
ramp.
Bulk cargo terminals provide means for the import or export of commodity-type goods such
wheat, corn, gypsum, fertilizer, petroleum or similar products. Products are handled and
stored in large quantities or volumes in tanks, sheds or in open outdoor storage piles.
Container terminals serve as rapid transit facilities at the interface between land and sea
transportation for the door-to-door shipment of goods. Imported containerized cargo is
brought to the terminal via ship, offloaded by rail-mounted ship-to-shore gantry cranes,
handled at the facility using trucks and a variety of specialized equipment such as bomb
carts, top picks, or side picks. Containers are placed into storage stacks using specialized
stacking equipment such as reach stackers, rubber-tire mounted gantry cranes, or railmounted gantry cranes. Cargo is transported from the site by truck, freight rail, or by
transfer to another ship. For outgoing cargo, the process works in the opposite direction.
This paper will be used by the Port and external stakeholders to better understand the
opportunities and constraints of marine development on the Ports property on Hayden
Island, and to develop long-term planning concepts for this and other sites. This paper
supplements separate papers prepared for the Port for the road and rail industry criteria,
constraints, and operating requirements, as well as previous documents generated for the
development of West Hayden Island.
Existing roadway access to the island is via the northernmost Oregon exit on Interstate 5 (I5). The western side of the island is currently undeveloped and located in unincorporated
Multnomah County. It was added to the regions urban growth boundary in 1983 for the
purpose of marine industrial development. The Port of Portland acquired the tract of land
herein referred to as West Hayden Island in 1993. The site was designated in 1995 as both
regionally significant industrial land and as regionally significant natural habitat.
In order to accommodate the contemplated development, it is expected that an additional
vehicular bridge will be constructed to the south of the property limits in the future and that
the road traffic accessing the future development will be accommodated by this proposed
bridge and roadway. Rail access is currently anticipated by integrated and expanded service
on the islands existing BNSF north-south mainline.
Marine terminals at West Hayden Island will utilize three primary modes of transportation:
ships and barge access via the Columbia River navigational channel, freight trains via the
interconnecting railroads, and cars and trucks via roads and highways.
Marine terminals are typically multi-berthed to provide flexibility to customers; however,
terminal planning and development studies are often formed on the basis of multiple single
berth facilities to assess overall suitability and flexibility of the site.
Additional information and requirements are shown in the various terminal development
sections and by a variety of documents including the MTMP 2020 and the Development
Standards for Containers provided by the Port of Portland, as well as previous documents
related to the planned development of West Hayden Island.
The following aspects will affect the development characteristics of a marine terminal on
West Hayden Island:
Stability under heavy loads (e.g., cranes) and capability to perform special operations
Vessel squat tendency for increased water velocities flowing under and around a
moving ship to lower the draft of the ship
Channel configuration width, bends, bank clearance, maneuvering lanes, ship clearance
lanes, etc.
Use of tugs (or lack thereof) in the navigation and berthing of a ship
Table 1 and Table 2 shows the suggested minimum basin requirements for the current array
of vessels considered for the study both the MTMP 2020 and 30-year forecasts. Figure
shows a depiction of general basin configurations as recommended by the American Society
of Civil Engineers, Ship Channel Design & Operation, Manuals and Reports on Engineering No. 107.
Existing conditions on the site do not provide the required depth or maneuvering areas for
vessels to berth at the dock; therefore future terminal developments will require coordinated
design of a turning basin in order to accommodate the forecast vessels or coordinated
handling by tugs for use of the existing turning basin downstream of the potential terminal
site on WHI.
Figure 2 Source: ASCE Ship Channel Design & Operation, Manuals and Reports on Engineering No. 107, p.108
6
In normal operations, turning basins or circles are used by pilots in conjunction with two or
more tugs to bring a ship about and maneuver to and from the berths. A variety of
operational and environmental factors affect this layout including vessel configuration, wind,
currents, adjacent shoals, rocks, banks, and structures. Pilot strategy is often dependent
upon all of these factors. In locations with prevailing currents of greater than approximately
1.5 knots, the shape of the turning circle is enlarged or the basin is elongated (i.e. ovalshaped rather than circular) by a length determined by the strength of the current and its
effect on turning vessels. Computer-generated interactive berthing simulations are
performed during the preliminary and final design phase to assess the suitability of the basin
configuration, attempting to reproduce the behavior of a ship based on mathematical
considerations of external influences.
The concept layouts described further in Section 3.0 (refer to Concept Plans 1 to 8 provided
in the form of 11x17 plans and sections) show the turning circles adjacent to the existing
channel; in many ports it is common practice to allow the turning circle to extend across the
main channel. Additional coordination and verification is expected to occur between the
Ports of Portland and Vancouver in conjunction with the Columbia River Pilots, the US
Coast Guard, and/or other entities that work on behalf of the safe operation of the
navigational channel.
Table 1: Primary Navigational Requirements for Berth Design, Existing Conditions
Existing Conditions
Auto
Container
Dry Bulk
Liquid Bulk
Overall Ship Length
LOA
640
965
738
804
Berth Length
1.25 * LOA
800
1,250
950
1,050
Turning Basin
1.75 * LOA
1,150
1,700
1,300
1,450
Berth Length
1.50 * LOA
1,000
1,450
1,150
1,250
Turning Basin
4.0 * LOA
2,600
3,900
3,000
3,250
Stopping Distance
5.0 * LOA
3,200
4,850
3,700
4,050
Tug-assisted
LOA
760
1,200
805
935
Berth Length
1.25 * LOA
950
1,500
1,050
1,200
Turning Basin
1.75 * LOA
1,350
2,100
1,450
1,650
Berth Length
1.50 * LOA
1,150
1,800
1,250
1,450
Turning Basin
4.0 * LOA
3,050
4,800
3,250
3,750
Stopping Distance
5.0 * LOA
3,800
6,000
4,050
4,700
Tug-assisted
Information in Table 1, Table 2, and existing bathymetry drawings for the site show that
dredging will be required for the development of marine terminals at the site; therefore the
7
RO/RO vessels are predominantly employed for the transport of automobiles and other
wheeled or tracked cargo. Typically 600 to 700 feet long, 105 feet wide (Panamax), they carry
up to approximately 6,200 vehicles per trip, although they typically unload a smaller number
of vehicles with multiple port calls.
Table 3: Vessel Characteristics for Auto Import Terminal, Existing Conditions and 30-Year Forecast
Outlook
Existing
Conditions
30-year Forecast
Length (feet)
Beam (feet)
Number of Cars
640
105
32.2
5,600
689
105
34.1
6,000
656
105
39.0
6,200
760
106
37.1
8,000
Most ro/ro vessels employ quarter ramps that require no special berthing facility, except the
required landing space for the ramp. Fixed ramps are normally considered feasible for water
level variations of less than about 5 feet, and the expected tidal and seasonal variation at
West Hayden Island is on the magnitude of 20 feet or more. However, a split-level fixed
dock can be constructed that provides a working deck surface designed to accommodate
service through the range of changing water levels. This configuration provides added
operational advantages but requires an additional length of dock be constructed for the
second working level.
Berths are typically sized to accommodate the largest ships, with ramps employed
simultaneously at each quarter point. Additional mooring and/or breasting dolphins are
situated as necessary to provide docking capabilities for the expected range and distribution
of the service fleet. A berth length of 400 feet is used for the conceptual layout for the
present-day fleet (based on local availability of barges for conversion to floating dock
platforms); however, future vessel characteristics require a berth of up to 480 to 500 feet in
overall length. The minimum approach trestle or bridge width to the landside terminal is 33
feet.
Floating platform docks, such as those currently used by the Port at Terminal 6, can be
configured to provide the required flexibility in relationship with berth allocation and tidal
and seasonal water level fluctuations; however, their ability to be extended for longer vessel
lengths is relatively difficult. In addition, their ability to withstand larger loads from wheeled
container traffic, construction, farming equipment, etc., and their maintenance and upkeep
requirements limit but do not exclude floating platforms as a design option.
Ships with straight stern or bow ramps usually require careful consideration for the berthing
layout. In 1983, the International Standard Organization (ISO) adopted and issued ISO
6812:1983, Roll on/Roll off ship-to-shore connection Interface Between Terminals and Ships with
Straight Stern/Bow Ramps, with the intent of providing standard details and information for
the development of these special conditions.
9
2.2.2
A bulk carrier, freighter, or bulker is a ship designed to transport unpackaged bulk cargo
such as grains, ore, or other materials such as steel coils or plates. Todays bulkers are
specifically designed to maximize capacity, efficiency and safety while withstanding the rigors
of use. They range in size from small single-hold mini-tankers or barges (DWT less than
10,000) to very large ships of more than 350,000 DWT. Table 4 shows appropriate vessel
parameters for current terminal planning at West Hayden Island.
Table 4: Vessel Characteristics for Dry Bulk Cargo, Existing Conditions and 30-Year Forecast
Length
(feet)
Beam
(feet)
Loaded Draft
(feet)
Dead-Weight
Tonnage
738
105
42.0
60,000 to 75,000
30-year Forecast
805
115
44.9
80,000 to 100,000
A berth length of 650 feet is used for the conceptual layout. This considers a travelling
loader configuration and the initial and 30-year forecast design vessels shown in Table 4. The
minimum berth length is equal to about 80 percent of the longest ships anticipated, allowing
the longest ships to be directly unloaded with minimal ship maneuvering or relocation
during the process, with considerations of either forward or rear house configurations and
corresponding cargo hold positions. Additional mooring and/or breasting structures are
situated as necessary to provide docking capabilities for the expected design vessel(s)
distribution.
Dry bulk terminals require ship loading and unloading to occur at a specific number of
hatches along the length of the ship. The most basic form is for a linear dock structure with
one or more travelling shiploaders capable of loading or unloading the entire length of the
design vessel. Other loading arrangements are used depending on the dry bulk commodity in
question, as well as other structural and operational factors. These primary configurations
include linear shiploaders, quadrant shiploaders, and twin orbiting-slewing shiploaders. The
10
concept plan focuses on the traveling shiploader configuration because of its relative
simplicity and adaptability.
Alternate berth and operational configurations provide for a varying degree of structural and
operational requirements, at the benefit of increased performance for a specific dry bulk
loading or unloading process and at the expense of reduced versatility and adaptability of the
terminal for alternate uses such as general bulk cargo. This versatility is desired when
forecast models predict an expected lower average utilization of the dock, compared to a
higher average utilization of the rail or truck loading yards. The dock is then able to service
alternate ship cargos without disrupting either the call cycle of the dry bulk cargo vessels or
the efficiency of the dry bulk cargo loading yards. Alternatively, highly utilized docks with
large throughput and long tenant-owner relationships may be better suited toward a
specialized facility aimed at maximizing throughput, although at potentially higher initial cost
and lower overall terminal versatility.
2.2.3
A tank ship, or tanker, is a ship designed to transport liquids in bulk. Major classes include
chemical or oil tankers. Vessels range in size from small vessels with capacity of several
hundred tons, up to several hundred thousand tons for long range cargo transfer. Tankers
are typically specialized for the type of liquid being transferred. There are specialized oceangoing vessels as well as inland waterway tankers which operate on rivers and canals.
Typical products carried by tankers include hydrocarbons, chemicals (ammonia, chlorine,
styrene monomer, etc), fresh water and agricultural products.
Vessel sizes of up to 1,000 ft LOA might be expected in support of raw, unprocessed liquid
bulk commodity at or adjacent to the terminal. On the other hand, maximum vessel sizes of
about 750 feet LOA could be expected if supporting the intermodal handling or transfer of
previously processed products; this length is likely even shorter if supporting refined
agricultural products. Table 5 shows appropriate vessel parameters for current terminal
planning at West Hayden Island.
Table 5: Liquid Bulk Vessel Parameters, Existing Conditions and 30-Year Forecast
Length
(feet)
Beam
(feet)
Loaded Draft
(feet)
Dead-Weight
Tonnage
Existing Conditions
804
105
42.98
60,000
30-Year Forecast
935
135
47.90
100,000
Cargo handling for a liquid bulk terminal usually occurs through a single manifold located at
mid-ship. A loading platform is typically provided at midship to provide space for the
required loading arms and hose-handling equipment. Separate berthing and mooring
platforms are provided as necessary for safe mooring of the design vessels. The various
structures are interconnected by catwalks, gangways, or other light structures.
11
2.2.4
Container Terminals
The primary factor affecting the requirements for the berth is the anticipated vessel sizes.
Most container ships today are of the Panamax Class, based on historical length (965 feet),
width or beam (106 feet), and draft (39.5 feet) limitations imposed by passage through the
Panama Canal. Upon completion of the Panama Canal widening project, the new limitations
will be a length of 1200 feet, a beam of 160 feet, and a draft of 50 feet. The berth is greatly
affected by the berthing loads associated with the design vessels, as well as operational and
machinery loads necessary to load and unload the vessel therefore a detailed list of loading
parameters is included in this report.
Table 6: Container Cargo Vessel Parameters, Existing Conditions and 30-Year Forecast
Length
(feet)
Beam
(feet)
Loaded Draft
(feet)
Dead-Weight
Tonnage
TEU
106
39.5
65,000
5,000
50.0
150,000
12,000
160
985
132
42.65
80,270
6,500
1,100 to 1,200
151 to 160
45.93 up to 50.0
105,000 to
150,000
10,000 to
12,000
38.5
42,429
3,000
12.5
6,300
791
106
250
72
The design berths are configured to provide a suitable distance from the face of the wharf to
the centerline of the waterside crane rail and also from the face of uncompressed fender to
12
the centerline of the waterside crane rail. Berthing structures are very long and configured to
support the variety of potential vessels that are within the terminal forecast.
The Port of Portlands current operations usually place vessel hatch covers between the legs
of the crane. Other operators prefer to place the covers in the backreach area, behind the
clear area of the crane. For planning purposes it is prudent to provide a backreach area that
is 55 feet wide. The crane rail gauge will be 100 feet to meet international standards for
container ship loading and unloading. This interface affects the required width of dock
structure for an offshore container terminal configuration.
Table 7: Crane Design Parameters, Existing Conditions and 30-Year Forecast
Total Outreach
Total Outreach (from CL of waterside crane rail)
13 to 20 containers
118 to 172 ft 11 inches
9 feet
Crane Gauge
100 feet
69 feet
Wharf structures, fenders, and bollards will be designed to accommodate the current design
vessels at any location along the structure, with the ability to convert or upgrade the berth to
accept future design vessels. Additionally, the berth must be adequate to support the
imposed operating and stowed crane wheel loads and all other appropriate design loads that
will occur, including standard accepted environmental loads such as wind or seismic. The
entire berth must support the operating loads; it is common to identify specific locations for
crane stowage pins and/or tie-down locations.
Gate Complex
For cargo not serviced by rail, it will enter or leave the terminal via the gate complex. This
provides a control point for all traffic entering or exiting the terminal. This is typically the
control point where a change of custody occurs for cargo shipments.
Employees and visitors will also utilize the gate complex for access to the terminal. A
carefully planned gate complex can provide operational efficiencies to the terminal by
quickly moving cargo into or out of the terminal. Gate location and accessibility are also
important as they factor into the overall calculation of cargo movement distances and time.
Typical gates provide for both inbound and outbound queues and processing areas. Traffic
volumes and equipment sophistication will be important factors in the final arrangement for
13
the gate areas. The area must be sized to accommodate truck queues of sufficient length and
number, especially for trucks entering the facility, and sometimes include special gates for
excepted vehicles.
Additional roadway will be required to integrate the terminal with surrounding
transportation infrastructure. Requirements for these access corridors are as indicated based
on the type of cargo terminal considered. Separate studies have been generated indicating the
possible traffic volumes associated with the development.
2.3.2
Current planning parameters indicate that a total area of approximately 75 to 110 acres is
needed for an auto import facility with an annual throughput ranging from 100,000 to
200,000 vehicles per year. Multiple customers can be accommodated with a single-berth
facility if the ship schedules are synchronized. Terminals handling two or more accounts will
need additional berths to provide flexibility, and a single-berth facility has limitations for
marketing and operations.
Possible designated areas for an auto import terminal include the following sub-areas:
General storage area
Marshalling yards
Truck and rail loading areas
Processing center
2.3.2.1
Currently there are three auto import terminals at the Port of Portland, which comprise
approximately 260 acres. Recent historical statistics generated by the Port of Portland show
an average of 1,500 vehicles per acre per year for the overall terminal footprint, with a peak
of 1,800 vehicles per acre per year in 2006. For the purpose of determining the size of the
general storage area, the estimated throughput per acre will be about 2,000 vehicles per acre
per year. The required storage area relates to the annual throughput and expected average
dwell time.
For estimated maximum terminal throughputs of 100,000 to 200,000 vehicles per year, the
anticipated general storage area will be between 50 and 100 acres, with an overall terminal
footprint of approximately 75 to 125 acres.
Approximately 200 vehicles can be stored per acre at any given time for a load line
arrangement storage yard, while for an open-parking arrangement the storage density is more
likely to be about 140 vehicles per acre. Load lines provide limited selectivity and require
very accurate logistical planning and inventory management to realize the full operating
efficiency. Open layouts provide total selectivity but increase the overall footprint and
associated development, operating, and maintenance impact of the facility.
14
2.3.2.2
Marshalling Yards
The truck loading areas for moving autos off-site will be fed by approximately 12 load lines
of 180 feet in length, and with approximately 10 to 30 spots occupied by trucks, totaling
approximately 5 acres.
A rail loading area is generally designed for transferring tracked or wheeled vehicles onto or
off of flat railcars (flatcars). In the case of smaller wheeled vehicles such as automobiles, auto
racks (trilevel cars) are used. A typical loading area will contain:
End ramps or multilevel ramps for transferring the vehicles to and from the railcars
15
For direct loading, the optimum loading configuration will be of 10 to 20 rail cars per string;
the lower number to minimize switching requirements while the upper limit of 20
correspond to efficient loading capacity. Each loading track has a tangent length extending
10 to 20 railcars from the loading ramp. Loading tracks are aligned parallel to each other,
with sufficient space provided in between for one-way vehicle traffic.
The staging area is located as close to the loading area as possible to facilitate command and
control, and provide adequate storage capacity to stage one full cycle of vehicular cargo.
An access ramp is included in the staging area and will be straight and in line with the ramp
for at least the full length of the longest vehicle to be loaded. For practical purposes, it is
ideal to provide an in-line approach that is twice the length of the longest vehicle to ensure
all vehicles can be properly positioned and secured. The approach should be positioned
with maximum possible operator visibility.
Multi-level ramps are recommended for the loading of doublestacked or triplestacked
railcars. These ramps are typically portable pieces of equipment that can be purchased and
maintained by the commercial railroad. Geotechnical and structural aspects of ramp
placement must be considered; concrete pads are recommended to ensure adequate ramp
stability.
2.3.2.4
Processing Center
A processing center for autos is necessary for each general terminal. Typical components of
a processing center are the marine office, employee parking, drive-through car wash, vehicle
repair garage, and a truck gate area. In general, the support buildings can be modular,
portable, or lightweight metal fabrications that can be easily installed, relocated, or removed.
2.3.3
Estimated throughput requirements for dry bulk terminals are as described in the MTMP
2020 document maintained by the Port of Portland, and assumed to be 5 to 8 million metric
tons per year. The terminal footprint that will be needed to support the required railroad
capacities for loading, unloading, and storage will have the following dimensions:
Assuming a terminal length of 2,500 to 3,000 feet parallel to the shore and an overall track
length from a minimum of approximately 7,000 feet to perhaps 10,000 feet, an expected
terminal property depth perpendicular to shore is approximately 2,000 feet to more than
3,000 feet. Terminal acreage requirements are likely to range from a minimum of 110 acres
upwards to approximately 175 acres. The terminal rail loop can be multi-tracked in order to
provide the adequate track length while also conforming to the available footprint for the
site.
Fixed belt conveyor systems usually transfer the material to and from the loading or
discharge device and storage area. Storage areas are usually open storage yards, sheds, silos,
or slurry ponds, depending on the type of commodity, required throughput, storage area
16
available, and other economic and environmental factors. Storage areas are typically located
close to the ship location, but can be further away at only a modest operational penalty. With
careful coordination and management, ships can be loaded directly from railcars, although
this usually results in reduced efficiencies for large shipments.
Successful dry bulk terminals normally depend on rail for the inland movement of goods;
most dry bulk terminals situated on the Columbia River are export terminals, with most of
the cargo arriving by rail. The terminal area requirements are dependent on the length of the
train or trains required for the efficient loading and unloading operations. Facilities can be
configured to focus on single or multiple commodities, with appropriate storage and
operational conditions to include cleaning between uses.
2.3.4
Berth and land use allocations are typically based upon the supported business. The terminal
layout will be defined by a combination of the receiving, holding, blending, and shipping of
client-owned products. All terminals will require large tank storage areas behind the docks; it
is expected that the tanks will be located within the terminal boundaries established by the
rail storage loading loop (see discussion for dry bulk terminals) but it is conceivable that
storage and/or loading could occur at satellite terminal locations. Most terminaling
companies will have rail and/or truck loading facilities on site for the local distribution or rail
shipment of products.
Refining/feed stock type terminals usually includes larger storage and take-away pipelines
and smaller send-out pipelines at the marine terminal. Refining/product export
configurations typically require smaller on-site storage facilities and receiving pipelines but
with larger send-out pipelines. A terminal providing both processes might require the largest
and most complex terminal arrangement.
2.3.5
Container Terminals
Existing planning parameters indicate the provision for a minimum of two berths and
corresponding throughput of approximately 750,000 to 1,000,000 TEU resulting in a
terminal size ranging from 95 to upwards of 125 acres or more from this minimum service
requirement. Throughputs listed are not verified by this report but based on typical design
and planning parameters for other terminals of similar configurations currently in use or
planned for future use.
It is estimated that the minimum terminal length will be approximately 2,500 feet parallel to
the shore. Suitable working property depths for initial condition and the 30-year forecast
typically range from approximately 2,500 feet perpendicular to shore (for regular shaped
facilities such as Bayport Container Terminal Port of Houston Authority) to approximately
3,500 feet (for unusually constrained facilities such as Alabama State Port
Authority/Mobile). A variety of terminal layouts can be described and developed with
consideration of several factors, some of which are described below.
The overall land area requirement is calculated by using an iterative process based on
matching the required area for storage and handling operations to the throughput for the
wharf. Many of these aspects lend themselves very well to mathematical analysis and
17
simulation models to verify the analysis based on the large number of variables that effect
the overall layout requirements.
Large land areas are required for container terminal storage areas to efficiently manage the
variety of inbound and outbound containers. The amount of time that any individual
container spends is minimized.
Customs processing of the sealed containers occurs on the premises or at inland freight
stations situated nearby.
2.3.5.1
Lift Area
The lift area includes the rail loading tracks and adjacent space where the physical modal
transfer occurs. Transfers are typically provided by rubber tire or rail-mounted gantry cranes
or by side loaders. Lift machines operate at the practical rate of 20 lifts per hour.
2.3.5.2
Provides the ability to manually or automatically wash interiors of refrigerated containers and
include a steam-cleaning pad. Wastewater must be treated prior to offsite discharge, and
recycling of this type of water is typically encouraged.
2.3.5.3
Eastbound containers typically have a dwell time of 24 hours or less. Westbound containers
have average dwell time of several days. Empty containers dwell at the yard for several days
to several weeks on average. The terminal footprint will be primarily sized to accommodate
the proportionate storage of outbound containers, inbound containers, wheeled container
storage, grounded empty container storage, and wheeled reefer storage. The relation between
the various laydown areas as well as the wharf structure, gate vicinity, and related dwell times
and throughputs ultimately dictates the size and arrangement of the container storage yard.
A typical distribution may dictate that 50% of the terminal space be used for wheel activity,
including the gate, and 20% each for storage of grounded containers and another 20% for
empties.
Many of these internal terminal functions are predictable and repeatable over time, while
other functions such as vessel call schedule and the arrival or departure of containers by
truck or train are random yet still based on statistical distribution. For this reason, a
container terminal is well suited for mathematical modeling and simulation during the
detailed developmental phase.
18
2.4.1
Sufficient area for parking or lifting equipment, yard tractors, and other terminal vehicles will
be included. This area comprises approximately 2% to 3% of the proposed terminal area.
Some terminal handling equipment, such as RMGs or RTGs, can be stored in conjunction
with the general storage areas and are not included in the requirements for this storage area.
2.4.2
Administrative Areas
Offices utilized by managers working in some aspect of the terminals daily operation such as
maintenance, security, safety, administrative, or commercial activity. Whenever possible,
consolidate the administrative buildings and locate them in transitional areas or along subdivisions of the terminal. Approximately 3% of the terminal is usually used for these
facilities.
2.4.3
Typically, space is provided for the maintenance and repair of terminal equipment, trailers,
containers, and chassis. A special facility is sometimes required for the maintenance and
repair of spreaders and storage of quay crane parts. The facility includes full-service office
capabilities and might occupy about 2% of the terminal area.
2.4.4
Roadability Area
These areas consist of special parking spaces located near the gate for the purpose of
performing minor repairs on chassis so that they meet legal vehicle and safety requirements
for transport on surface streets and roadways. Federal Highway Administration (FHWA) and
other mandatory inspections are performed in these areas.
2.4.5
Provided so that employees, visitors, and outside service vendors will park at these locations
and walk to and from the various on-site locations; and typically requires a guard hut with
constant supervision.
2.4.6
Perimeter Area
Drainage, security fencing, landscaping, and lighting are typically accommodated around the
perimeter of the terminal. Potential future terminal expansion is considered when
establishing a layout for the terminal perimeter.
2.4.7
Transload Areas
These areas provide the transloading of cargo in damaged containers or rail cars to suitable
units. Similar inspection areas are necessary for governmental and customs officials to
perform required cargo inspections.
19
2.4.8
Typically provide one weeks worth of diesel and gasoline fuel to container/trailer handling,
transport equipment, shuttle buses, utility trucks, and other equipment. Special protection is
required to protect the tanks from equipment that is taking on or delivering fuel.
2.4.9
Required to collect and capture hazardous material without entry into storm drain systems.
utility infrastructure, such as the electrical substation located adjacent to the southern
mainline junction.
The Harbor Line is located parallel to the existing Columbia River Channel.
The northern limit of the necessary land-based development is a nominal horizontal offset
of 300 feet from the +4 CRD contour, which forms the upper limit of the shallow water
habitat zone. The shallow water habitat zone extends from +4 to -20 CRD and has been
indicated as an environmentally-sensitive location; any impact to these regions must be
indicated as such. Vertical Datum will be based on benchmarks located on the Natural
Geodetic Vertical Datum (NGVD) or similarly referenced Columbia River Datum (CRD).
The ideal southern limit of the necessary land-based development (access road, storage yard,
intermodal yard, etc.) is the northern limits of the existing power line corridor easement.
Operating requirements take precedence over this limit and the corridor will be evaluated for
relocation on a case-by-case basis.
21
The eastern limit of the necessary land-based development is defined by the limits of the
existing 36-inch-diameter concrete outfall pipe. It is necessary for accessibility components
of land-based development to occur beyond this assumed limit.
The western limit of the necessary yard development is defined by the existing BPA power
line corridor, which crosses the Columbia River and forms a parallel dissect of this area of
West Hayden Island. It is necessary for accessibility components of land-based development
to occur beyond this assumed limit. Rail will possibly extend beyond the existing power line
corridor, depending on the final development configuration, but will maintain 200 feet clear
distance to the +4 CRD contour of the existing pond.
3.1.2
Terminal intermodal services are to be integrated with the existing rail bridge located on the
eastern limits of the terminal boundaries.
Vehicular access to the terminal is to be achieved by connecting to a proposed bridge and
roadway located to the south of the terminal boundaries across the Oregon Slough to North
Marine Drive. Vehicle access is likely to be provided on the eastern limits of the property.
3.1.3
The existing ground elevations for West Hayden Island west of the Burlington Northern
Santa Fe (BNSF) Railroad tracks and east of the existing power line crossings of the
Columbia River range from +4 to approximately +38 feet NGVD, with most of the
proposed development site between +10 and +25 feet. The previously established terminal
elevation of +30.5 feet was used for the concept layouts. Climate change effects could
impact the final design elevations.
Further development is coordinated with appropriate stakeholders to best evaluate the final
storage yard elevations. Different zones are indicated for development as agreed to by
project stakeholders; e.g., establish all storage facilities above the 100-year flood elevation as
determined by FEMA, as well as critical operational aspects such as the storage track and
loading platforms. Undeveloped regions and storage for empty containers or chassis do not
necessarily require the same final fill elevation, as their sensitivity to high water levels is of
reduced consequence.
22
23
a satellite terminal location (on West Hayden Island and/or other locations as appropriate)
and connected to the marine terminal via a pipeline corridor.
Ultimately a terminal is gauged by its annual throughput and to a lesser degree its overall
efficiency. It is typically desirable to balance a facility so that it operates on a consistent basis
over a unit period of time, with consideration given to expected maximum or peak
conditions. The annual throughput capacity can be associated with a variety of factors, each
of which factors into the overall planning and development of a container terminal. The
optimum terminal design incorporates a productive balance of pertinent factors. Some of
these variables are:
Property configuration
Ship schedule
External market factors shipping, rail, trucks, consumer demand, global supply
demand, etc.
24
The final design evaluates the relative probabilistic chances of occurrence during the
expected lifespan of the terminal, and provides for acceptable levels of damage and repair in
accordance with forward-looking seismic design codes.
A two-level design approach, as currently contemplated in forward-looking structural codes,
is recommended:
Several methods and devices exist for stabilizing slopes and earth, including mechanical
reinforcement or densification of the ground. Additional coordination is required between
the geotechnical and structural engineer to evaluate the potential occurrence and reasonable
mitigation approaches best suited for site development.
Site accessibility constrains rail service and capacity. If alternatives leave the final rail
elevation at less than the 100-year flood elevation, track grades will be inadequate to
maintain the desired speeds and grades for the optimum level of service, thus downgrading
the yard for rail performance characteristics as shown in the rail study.
Final design conditions should be coordinated with anticipated arrival and departure
intervals and with other requirements of the site and stakeholders.
Refer to Comparative Analysis of a Multi-Use Rail Served Port Facility and Applications to
West Hayden Island Working Tracks for descriptive information relating the overall rail
requirements at the site.
26
5.0 References
Agerschou, Hans et al.
2004
Planning and Design of Ports and Marine Terminals, 2nd edition, 2004,
Thomas Telford Publishing,
American Society of Civil Engineers
2005
Ship Channel Design & Operation, Manuals and Reports on Engineering No.
107, American Society of Civil Engineers, 2005
HDR Engineering Inc.
2008
Comparative Analysis of a Multi-Use Rail Served Port Facility and Applications
to West Hayden Island, Port of Portland/ Nov 2008
International Standard Organization (ISO)
1983
ISO 6812:1983, Roll on/Roll off ship-to-shore connection Interface Between
Terminals and Ships with Straight Stern/Bow Ramps
National Center for Engineering Education Research (NCEER)
1997
Bulletin, July 1997, Vol 11, No 3)
Port of Portland
[ ]
Development Standards for Containers, Port of Portland, date unknown
Port of Portland/Parsons Brinckerhoff
2003
Port of Portland Marine Terminal Master Plan 2020, Volume 3 Planning and
Inputs, January 2003
Tsinker, Gregory P.
2004
Port engineering: planning, construction, maintenance, and security, 2004, John
Wiley & Sons, Inc.
United Facilities Criteria (UFC)
2005
4-159-03 Design Moorings, October 3, 2005
http://www.wbdg.org/ccb/dod/ufc/ufc_4_159_03.pdf
West Hayden Island Development Program
1994
Development Parameters Working Paper, Port of Portland/centurywest
Engineering Corporation
27
Basin
The region where a vessel will expect to travel safely between the
main channel and a berth
Berth
The maximum depth to which a berth will be dredged for the 30year forecast vessel
Bow
Breakbulk cargo
Bulk cargo
Bulk carrier
Cargo
Cargo tonnage
Channel
Chassis
Container terminal
Dock
Doublestack train
Draft
Dredging
Dredge maintenance
and disposal program
Eastbound
containers
Export
FEU
Gauge
Harbor line
Hatch
Import
Inbound
Intermodal
Knot
Liquid bulk
Load line
Longshoreman
Manifold
Marshalling yard
Metric ton
Moorage
Mooring
Multimodal
See intermodal
Nautical mile
29
Nearshore
New Panamax
Offshore
Open layout
Outbound
Panamax
Pilot
Port
Post Panamax
Quay
See harborline
Ramp
Reefer
Roll-on roll-off
ro/ro
30
Shoaling
Short ton
Spreader
Stack train
Stakeholders
Starboard
Stern
Straddle carrier
Terminal
TEU
Transloading
Tug-assistance
Turnaround
Turning circle or
basin
Unit train
Westbound
containers
Yard
31