Beruflich Dokumente
Kultur Dokumente
To cite this article: Vinod Tare , Sandeep Gupta & Purnendu Bose (2003) Case Studies on Biological Treatment
of Tannery Effluents in India, Journal of the Air & Waste Management Association, 53:8, 976-982, DOI:
10.1080/10473289.2003.10466250
To link to this article: http://dx.doi.org/10.1080/10473289.2003.10466250
TECHNICAL PAPER
ABSTRACT
This paper presents a comparative assessment of the cost
and quality of treatment of tannery wastewater in India by
two common effluent treatment plants (CETPs) constructed
for two tannery clusters, at Jajmau (Kanpur) and at Unnao in
the state of Uttar Pradesh, India. The Jajmau plant is upflow
anaerobic sludge blanket (UASB) process-based, while the
Unnao plant is activated sludge process (ASP)-based. Investigations indicated that the ASP-based plant was superior in
all respects. Total annualized costs, including capital and
operation and maintenance costs, for the UASB and ASP
plants were Rs. 4.24 million/million liters per day (MLD)
and Rs. 3.36 million/MLD, respectively. Land requirements
for the two CETPs were 1.4 hectares/MLD and 0.95 hectares/
MLD, respectively. Moreover, the treated UASB effluent had
higher biochemical and chemical oxygen demand (BOD/
COD) and considerable amounts of other undesirable constituents, like chromium (Cr) and sulfide, as compared with
the ASP effluent, which had lower BOD/COD and negligible
concentration of sulfide and Cr. Sludge production from the
UASB-based plant was also higher at 1.4 t/day/MLD, in comparison to the sludge production of 0.8 t/day/MLD for the
ASP-based plant. Also, the entire sludge produced in the
UASB-based plant was Cr-contaminated and, hence, hazardous, while only a small fraction of the sludge produced in
the ASP-based plant was similarly contaminated. The results
of this study are at variance with the conventional wisdom
of the superiority of anaerobic processes for tannery wastewater treatment in tropical developing countries like India.
IMPLICATIONS
In the field of wastewater treatment, it is generally accepted
that anaerobic treatment is less energy-intensive and, hence,
preferable to aerobic treatment in tropical developing countries like India. While this is true in many cases, a blanket
preference for anaerobic treatment without due regard to
wastewater quality may be ill advised. This paper refers to a
comparative assessment of an aerobic and an anaerobic
treatment facility for treatment of tannery wastewater, which
shows that, at variance with the conventional wisdom, the aerobic treatment facility is superior in most respects, including cost.
INTRODUCTION
Tanneries are significant in terms of Indian exports and
employment opportunities for people of economically
weaker populations.1 However, sustenance of tanneries,
particularly of the small units, is becoming increasingly
difficult because of alarming levels of environmental pollution caused by various tanning operations and practices.2,3 Considering the financial and technological limitations of small tanning units, the general approach
adopted in India for treatment of tannery wastewater
from such units has been the commissioning of common
effluent treatment plants (CETPs) for tannery clusters.4,5
One significant stimulant for the emergence of CETPs is
the scheme announced by the central and state governments in India in 1989, providing 50% of the capital cost
of such CETPs as subsidy to the tanning industry.6
These CETPs have been constructed, operated, and
maintained by member tanneries through independent
companies set up for this specific purpose.7 The exceptions to this rule are the CETPs at Jalandhar in Punjab and
Jajmau (Kanpur) in the state of Uttar Pradesh (UP), which
are managed by government-sector enterprises.8 A review
of the tannery effluent characteristics in India9 indicate
that the pollutants of concern are high biological and
chemical oxygen demand (BOD/COD), sulfide, chromium (Cr), total suspended solids (TSS), and salt concentration. Most CETPs for treating tannery effluents specify
preliminary treatment in the tannery itself10 12 for removal of large suspended solids (grit) and Cr before conveyance of the wastewater for centralized treatment.
Though several sulfide-removal technologies exist,13 its
removal is generally not practiced in tanneries. After preliminary treatment, wastewater with high BOD/COD is
conveyed to CETPs, where it is treated by aerobic or anaerobic biological processes for destruction of biodegradable organic pollutants before release into the natural
environment.
The processes used most frequently for biological
treatment of tannery wastewater in CETPs in India are the
activated sludge process (ASP) and the upflow anaerobic
sludge blanket (UASB) process.9,14 16 In general, ASPbased treatment is considered to be energy-intensive and
Volume 53 August 2003
using the UASB process. Preliminary treatment of wastewater for removal of grit and Cr is performed in the tannery
itself. Because sulfate (SO42) concentration in tannery
wastewater being conveyed to the CETP was expected to be
high, this wastewater was mixed with domestic wastewater
in a 1-3 ratio before treatment, so as to increase the CODSO42 ratio, thus promoting methanogenesis of the influent
COD. This arrangement was also designed to minimize the
detrimental effects of the conversion of SO42 to sulfide
during UASB treatment. Hence, a UASB plant of 36 MLD
capacity had to be designed for treating 9 MLD of tannery
wastewater. A flow sheet for the adopted treatment scheme
is shown in Figure 1.
Average daily rawhide processing in Unnao is 47.5 t
from a cluster of 28 tanneries.8 The Unnao CETP, which is
an ASP-based plant, receives 1.9 MLD of tannery wastewater18 against a design flow of 2.15 MLD. As in previous
cases, preliminary treatment of this wastewater for the
removal of grit and Cr is performed in the tannery itself.
A process flow sheet for this CETP is shown in Figure 2.
Table 1 presents a comparative overview of the two CETPs.
RESULTS OF COMPARATIVE ASSESSMENT
The comparative assessment of the two CETPs described
previously has been conducted considering the following
major factors, namely, overall annual cost (including capital and operation and maintenance costs), land area requirement, treated effluent quality, and quantity and
quality of sludge produced.
Construction Costs
The construction cost data were taken from the implementing agencies as mentioned in their project completion
Purpose
Capacity
Date commissioned
Capital cost
Implementation
Financial
Operating agency
Power cost
Wages and salaries
Chemicals
Maintenance
Electrical and mechanical
Civil structure at CETP
Oil and lubricants
Sludge disposal
Miscellaneous
Total
4.08
1.2
0.66
0.72
0.36
0.3
0.9
0.6
8.82
Table 2b. Operation and maintenance costs for ASP-based CETP at Unnao.
Rs. (million)/yr
Power cost
Electricity
Generator
Wages and salaries
Chemicals
Maintenance
Electrical and mechanical
Civil structure at CETP
Generator
Oil and lubricants
Sludge disposal
Miscellaneous
Total
2.52
0.54
0.84
0.036
0.18
0.12
0.06
0.12
0.06
0.3
4.776
Land Requirements
The UASB-based plant at Jajmau is constructed on an area of
12.5 hectares. Hence, 1.4 hectares of land is required per
MLD of tannery effluent treated in this plant. The land
requirement for the ASP-based plant at Unnao is 0.95 hectares per MLD of tannery effluent treated.
Treated Effluent Quality
The designed and actual levels of treatment for the two
CETPs are presented in Table 3. While the former values
are based on the original design calculations for CETPs,
the latter values were obtained from performance evaluation studies of the two plants.19 23 Data presented indicate that while the performance of the ASP-based CETP
was close to the predicted performance, the performance
of the UASB-based CETP was much poorer than the designed performance values. This poor performance can be
attributed partially to the presence of high levels of SO42
in tannery wastewater.
UASB performance data presented in Table 3 indicate
that, despite dilution with domestic wastewater, a large
Volume 53 August 2003
COD
BOD5
TSS
SO42
Sulfide
Total Cr
Influent
Effluent
Influent
Effluent
Influent
Effluent
Influent
Effluent
Influent
Effluent
Influent
Effluent
ASP-Based
Designed
(mg/L)a
Actual
(mg/L)b
Designed
(mg/L)a
Actual
(mg/L)c
1875
775
30
1625
50
738
NCe
NC
NC
NC
NC
4000
250
1800
30
2000
200
2000
1000
NC
NC
100
0.5
3600
200
1500
40
750
110
1500
NAd
NA
NA
56
0.8
From ref 19; bFrom refs 2123. Mean standard deviation. Number of data points in
parentheses. On daily composite samples collected for 5 consecutive days, 1997
1999; cFrom ref 19 and the logbook maintained at the Unnao facility, 19971999.
Only mean values reported, effluent characteristics being more or less unchanged over
the years; dNC not considered; eNA not available. Data not monitored during
performance evaluation of the treatment plants.
a
Wastewater quantity
Domestic wastewater required for dilution
Construction costa
Annual operation and maintenance costa
If power generation takes place, then
income/yrb
Annualized capital costa,c
Total annualized costa
Total hide production/yr from tanneries
discharging to CETPd
Cost of wastewater treatment per hide
produced
Sludge generation
UASB-Based
ASP-Based
9 MLD
27 MLD
Rs. 21.3 million/MLD
Rs. 0.98 million/MLD
2.15 MLD
0
Rs. 8.96 million/MLD
Rs. 2.25 million/MLD
0.85 millon
Rs. 9.42
1.4 t/day/MLD
Rs. 8.50
0.8 t/day/MLD
Per MLD of tannery effluent; bIn actual practice, power generation does not takes
place but there is the potential; cAnnualized capital cost construction cost
{r(1 r) n/(1 r)n 1}, where r rate of interest (14%) and n design period of
CETP (15 yr); dAssuming a 20-kg hide.
Volume 53 August 2003
COD
BOD5
TSS
SO42
Sulfide
Cr
Raw Domestic
Sewage (mg/L)
Note: From refs 2123. Mean standard deviation. Number of data points in parentheses. On daily composite samples collected for 5 consecutive days, 19971999.
circumstances, it is debatable that any meaningful treatment of domestic wastewater has occurred in the UASB
plant.
Further, it may be suggested that sludge generation in
the UASB-based CETP is greater only because of the addition of domestic sewage, and this point is not given due
importance while making the comparative assessment. To
answer this criticism, it may be pointed out that unlike
sludge generated from treatment of purely domestic sewage, which is relatively nonhazardous and can be disposed of or used safely, the sludge from the 36 MLD
UASB-based CETP is contaminated with Cr and, hence, is
hazardous. Disposal of such sludge is problematic. Therefore, it is correct to classify entire sludge generated by the
UASB-based CETP as a byproduct of the tannery wastewater treatment process.
Regarding the overall environmental impact of the
two treatment plants, the following points are made.
Treatment of tannery effluents in CETPs involves collection, conveyance, and treatment, followed by final disposal of treated effluents and sludge to natural bodies of
water or on land. It is expected that construction and
operation of CETPs will result in beneficial impacts on the
environment and overall improvement in parameters determining environmental quality, as compared with the
situation before the construction of CETPs. Installation of
both CETPs described in this paper has resulted in reduction in organic loading to surrounding bodies of water.
However, such CETPs also tend to convert distributed
streams of pollutant loading into one large stream and
produce toxic sludge. In the case of the two CETPs studied, the Cr-contaminated sludge produced from both
CETPs is being disposed of without proper care with the
assumption that trivalent Cr is relatively nontoxic. However, there are reports indicating the possibility of trivalent Cr being oxidized to hexavalent Cr.30 Hexavalent Cr
is reported to be highly toxic and, hence, environmental
impacts of sludge disposal should be properly assessed. In
Volume 53 August 2003