Beruflich Dokumente
Kultur Dokumente
Summary
Project Planned Start date: 1-april-2013
Project Planned Finish date: 16-april-2015
Project Planned Duration: 2 years
Maximum crew level: 90 people for different resources.
Project cost estimate: 2.713 billion
Project Cash inflow requirement: 1 month
2
1.1
Introduction to project
General
Project
Name of work
Location
DHA, Karachi.
Owner
Consultant
Contractor
NHA
1.2
Scope
1.3
Objectives
1.4
Methodology
The steps for the construction of this project adopted are hiring of consultants, then design, bid and
then construction.The whole infrastructure work would divide into different work packages. These work
packages would comprise of number of streets. Skilled and non-skilled labors are hired to do the job.
The main concerned is quality and completion of given task as per specified amount of time and cost
estimated. The Contractor is accountable to hire all the sub-contractors and material providers needed
for the project.
1.5
Beneficiaries:
The major beneficiaries of this project are DHA and the general public. DHA would get revenue by selling
their land and plots, while the common public will get a secure, safe and healthy environment for living
near beach.
Project Description
2.1
Project data
For sewerage system, steel reinforcement bars have minimum yield stress of 60,000psi.
Painting with colorized plastic emulsion paint of approved shade two coats.
Traffic signs are provided including triangular, circular plate, rectangular post, and
rectangular plate.
2.2
Quantity Estimation
Qty.
Unit
Rate
Amount
660393
Sq m
25
16509825
NGC
660393
Sq m
35
23113755
Earth Excavation
395
Cum.
335
132325
Embankment
1427335
Cum.
111
158434185
Sub Grade
2308
Sq m.
180
415440
Sub Base
33043.1
Cum.
1900
62781890
ABC
33043.1
Cum.
2250
74346975
Prime Coat
220291
Sq m.
145
31942195
18588
Sq m.
2255
41915940
Tack Coat
37177
Sq m.
68
2528036
186354
Sq m.
987
183931398
Pipe Sleeves
653
Rm.
2620
1710860
Utility Chamber
819
Nos.
45500
37264500
42158
Rm.
566
23861428
Kerb Block
62570
Rm.
700
43799000
Pavement Marking
21899
Sq m.
813
17803887
Sign Board
30
Nos.
7137
214110
Payment studs
22008
Nos.
400
8803200
Precast Pillars
63
Nos.
269
16946
Project Appraisal
3.1
Planning and Design stage is the major prospect for successful project. The site must be zero accident
and Safe for all the persons involve in the project. More ease, efficiency and litigation are main
objectives of healthy construction project. Client mainly looks for better construction which includes
quality of work and efficient design. Some of planning considerations are as follows:
Construction must not affect adjacent sea. Debris and waste material raised during construction
must not disturb natural environment
3.2
Diesel for running grader, compactor and roller must be present in stock. Otherwise
unavailability of diesel may cause time over run.
Proper route network is present to the site, so equipment and material are easily transfer to the
site
Project must be planned in such a way that asphalt on different sections of the road is done on
same day.
Traffic regulatory signs must present, it helps in guiding the traffic on the site and avoid
accidents to a considerable extent.
It is necessary to provide camp accommodation for all type of staff involved in the project as the
project is nearly out of city.
It is necessary to have water and toilet facilities in convenient locations to accommodate the
work force.
Fire extinguishers and first aid services must present, as burning asphalt may cause huge
damage to life