Sie sind auf Seite 1von 4

GENIVAR

CONSTRUCTION SITE MEETING #6


MEETING SUMMARY

Construction Site Meeting #6


Anaeroblc Treatment of Septage/Corn Stover and Biosolids to Produce Biogas,

Electrical Power and Treated Biosolids


Township of Georgian Blutfs and Township of Chatsworth

Date:
Time:
Atrendees:

Thursday, September 16,2010

Prolecr:

os-03-012-11-os

10:00 a.m.

Locatlon:

Project Ste

Ml:

l3,ll;y:f,rr':ffi"'..3'iiiLimited

Mr. Benjamin Strahler, CHFour Biogas lnc.


Mr. Eugene Sztuka, CHFour Biogas lnc.
Mr. Justin Tudor, CHFour Biogas lnc.
Mr. Marvin Weppler, Roads Superintendent, Township of Chatsworth
Mr. Rick Winters, Director of Public Works, Township of Georgian Bluffs
Mr. Dean Patch, Bahler
Mr. Ross Slaughter, P. Eng., GENIVAR Consultants Lp
Mr. Chris Wilson, P. Eng., GENIVAR Consultants Lp
Ms. Corrie DeGroot, GENIVAR Consuttants Lp
Mr. Bob Paranuik, Hydro One
Mr. Jim Figueroa, Hydro One
Mr. Andy MacDonald, Hydro One

Dlstribution:
Prepared

By:

ThosePresent
Ghris Wilson, P.Eng.

The following items were discussed at the Construction Site Meeting #6 for the contract for the anaerobic
treatment of septage/corn stover and biosolids to produce biogas, lectrical power and treated biosolids
for the Township of Georgian Bluffs and the Township of Chatsworth:

Action Bv:
The Minutes from Construction Site Meeting #S were reviewed and the
following comments were provided in reference to the items in the
Minutes.

The CofA amendment concerning receiving other waste products,


has been issued generalizing what additional waste products will be
allowed to be received. A copy of the revised CofA is to be provided

GENIVAR

to CHFour.

The revised application package for the Air & Noise Approval was
submitted to the Ministry of Environment on July 21 , ZO1O. To date,
no Air & Noise C of A has been receved.

.
r

GENIVAR

Payment Certificate #5 has been received by Maple.

Leakage Test Acceptance Reports for each of the digester, FOG


Tank and hydrolizer are to be provided to CHFour and Maple.

OWEN SOUND 945 Third Avenue East, Suite 212, Owen Sound, Ontario N4K

2Kg

GENIVAR

Tet.: (519) 326-2612 Fax (S19) 976-8008

Construction Site Meeting #6


Anaerobic Treatent of Septag/Biosolids/Com Stall(s to Produce Biogas, Electrical Power and
Treated Biosolids - Township of Georgian Bluffs and Township of Chatsworth

Paqe 2

Waste from "Planet Earth" will be provded up to January, 2011,


however a final agreement has not be signed to date.
a

The cooling bed installation has been completed

formal letter has been submitted by Maple to GENIVAR


a request for extension to September 16, 2010 for

concerning

Substantial Completion of the project. A second formal letter is to be


be submitted by Maple to GENIVAR concerning an extenson to
September 30, 2010.

The Project Team was informed that the opening ceremony for the
biogas project would be sometime in October, 2010. The otficial
date would be provided at a later date.
a

Backfilling of the digestate storage tank is complete.

It was noted by CHFour that the hydrolizer would be able to receive


sludge on September 17,2010 at the earliest to be directed into the
digester.

There was discussion that the blower building power requirements


could be met with the use of a smallgenerator operaling the blowers
during the daytime and olf at night, with lhe spray inigation system.
A request to Hydro One would be made for a disconnect from the

Maple

bower building.
Revised MCC component layout drawings were provided by CHFour

to

GENIVAR showing how the equipment locations would be

modified within the MCC Room and where equipment can be located
outside of the Control Building. GENVAR is to review and provde
comment to CHFour.
a
a

GENIVAR

ESA is still reviewing CHFou/s submittal.

Mr. Rick Winters stated that the municipal operator would be Mr.
Troy Unruh.

A change order for the series to parallel metering change is to be

GENIVAR

provided by GENIVAR.

A letter from Bahler concerning the concrete strength issue is going


to be submitted to Miller Group. GENIVAR has requested that a
copy of this letter be sent to them as well.

l. There was discussion concerning progress of

construction on-site.
Maple was confident that the remainng construction was proceeding to
be complete be the end of September,2010.

There was discussion concerning the Ontario Sales Tax after July 2,
2010. Money has been held back in the interim (starting at Payment
Certificate #6) until the finalized value for recovery of the embedded
retailsales tax is calculated and submitted by Maple.
Request for Payment Cerlificate #6 was submitted to the Municipality of
Georgian Bluffs on September 10, 2010.
4.

It was noted by CHFour that the computer specifications provided in the


contract documents were obsolete. An up-to-date computer will be
provided.

Bahler

Construction Site Metng #6


Anaerobic Treatlent of Septage/BiosolidlCom Stalks to Produce Biogas, Electrical Power and
Treated Biosolids - Township of
Blufls and
of Chats$,orth

5. Hydro One noted that motors > 10 HP must not be started


simullaneously.

6. Hydro one noted that the Protection Phitosophy proposal to mitigate the
requirement for transfer trip has not been provided. GENIVAR
commented that s in the process of being completed.

7. Hydro One noted that the site ESA approvatis

to be submitted to Mr.
Paranuik, Hydro One and Ms. Jackie Bradley, Hydro One (FBC) once
completed. Mr. Paranuik noted that S working days would be required
once the ESA approval is received to schedule the transformer install
and load connection.

8.

The COVER document submission was discussed. The COVER


document is not complete to date.

9.

lt was noted that Account setup and connection Authorization s subject


to allother Hydro One requirements being met.

10. lt was noted by Hydro One that a Draft DCA document would be ready
by September 17,2O10.

11. The meeting adjourned at 1 1:30 a,m.

lf there are any errors or omissions in the above minutes, please contact the

undersigned.
Prepared by:

GENIVAR Consultants LP

Chris S. Wilson, P. Eng.


Environmental Engineer
CSW/em

Construction Site Meeting ,6


Anaerobic Treatment of Septage/BiosolidVCom Stalks to Produce Biogas, Electrical Power and
Treated Biosolids - Township ot Georgan Bluffs and Township of Chatsworth

Paqe 4

Das könnte Ihnen auch gefallen