Purpose
2014 Construction Meeting #10
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric

C#2 Utilities, C#3A Surface, C#3B Electric


Next Date
06/10/2014

Next Time
10:00 AM

Prepared By
Jessica Buckley

Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton
Dan Walker, James Matzat
Ralph Avery, Andy Breznay, Matt Thomas, Roberto DeVincentis, Bob
Belavigna - ACP
Lou Zupan, Bill Planert, Brian Planert
James Edwards, Dave Comer
Doug Stafford, Jack Barker, Dawn Stillwell
Jeff Bubb, Flint Brann, Andy Gana
Jack Czapranski, Dennis Kuhn

Item / Description
1. SITE MANAGEMENT
1.1. Vacri / ACP, PCG are to submit typical
pedestrian traffic M&P plan; include list
of signage available on site; DDSs plan
received
1.2. NYSEG Gas: Provide as-build info to the
project office on a weekly basis to
minimize future conflicts
2. CRITICAL PATH ITEMS
2.1. NYSEG Electric: HH at Aurora St installed;
Coordinate with PCG for electric panel
installation; Signal project work to be
coordinated; Relocation of electric in 156
N areaway
2.2. TTC Telecom: F.O. switch over scheduled
prior to 06/15
2.3. TTC Alley Storm: LaBella to issue FD;
Areaway at #156 to be abandoned
2.4. 119 E State Vault Infill: Scheduled to be
backfilled (06/19?)
2.5. Pavilion / Gateway Footings: Review

Notes

Page 1 of 2

Due

06/10

open items for footings; Establish start


date for installation
2.6. Catenary Lighting: Update on rebar shop
drawings; Confirmation layout accuracy
2.7. Long-Lead Items:
2.7.1. Granite Submittal (#3A)
2.7.2. Glass Submittal (#3A)
2.7.3. Steel Submittals (Vacri #44R2, 51ab, 72a-g, 76R1)
2.7.4. Street Lighting (PCG Submittal #13)
3. SCHEDULE
3.1. NYSEG Gas: Schedule to test & charge
main (06/16?); Schedule work at Aurora
St intersection; Service locations to be
coordinated with Tammy Baker
3.2. Vacri / AC&P:
06/04: Install storm lat to SD 1.J
June: Bank Alley site prep/demo/grading;
foundations / footers
July: Prep & pour slab N Tioga; Paving
program
Aug: State St. Concrete & Paving, Bank
Alley granite?
Sept: Structural Steel
Oct: Furniture and Amenities
3.3. P&CG:
06/05 06/16: Installation of Bank Alley
Electric DB
July: Light Pole Bases, Distribution Panels
September: Street lighting install, power
bollards
3.4. Water Feature: Verizon to continue
relocate DB north of Trolley Circle;
Submittal #73 to be revised and
resubmitted per Architects comments;
Vault cannot be installed until NYSEG G
main is retired
4. M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
4.1. Vacri to submit sidewalk demo and
concrete pour sequence to City for review
prior to start of Bank Alley work
5. New Business: Open RFIs, submittals,
concerns, etc.

ADDITIONAL NOTES

06/03: Gallery Night starts at 5:30 PM

Page 2 of 2

06/17

Das könnte Ihnen auch gefallen