2014 Construction Meeting #13
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Michael Kuo
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A), Kimberly Michaels TWM
Dan Walker, James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis,
Bob Bellavigna ACP
Lou Zupan, Bill Planert, Brian Planert (A)
James Edwards (A), Dave Comer (A)
Doug Stafford (A), Jack Barker (A), Dawn Stillwell (A), John Mattiace (A)
Jeff Bubb (A), Flint Brann, Andy Gana (A), Bill Gana (A)
Jack Czapranski, Dennis Kuhn (A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Gateway Structure Shops #TBD
1.1.2.Granite Shop #87
1.1.3.WF Vault #73R1
Notes
Page 1 of 3
Due
Design Team
2.3. NYSEG E Load Letters: Load letters sent
to D. Kuhn
2.4. 158 E State Vault: Labella to issue
drawings and details for sidewalk demo
and replacement ceiling
2.5. 224 E State Vault: Extent of vault appears
to extend to edge of basement stairs to
the east; may encroach on gateway
footer
3. CRITICAL PATH ITEMS
3.1. P&CG: Installation of Bank Alley Electric
DB, HHs, Light Pole Bases, Services
Bedded in Sand
3.2. Vacri/AC+P: Bernie Milton Pavilion
Footings (2 of 3)
3.3. NYSEG Electric: NYSEG to adjust casting
for finish grade date TBD
3.4. NYSEG Gas: Conflicts with Verizon at
Aurora Street and Cayuga find new path
or relocate terracotta; Need date for
pressure test and Tioga St tie-in
3.5. Gateway Footings: @Cayuga St Helical
pile install 7/1; NYSEG G and Verizon
conflict; @Aurora St pending Simeons
shoring plan
3.6. New Water Services (118 & 124 E State):
Vacri to schedule work
3.7. Wood Fence: City to advise where to
deliver fence sections after dismantling
3.8. 202 E State Waterproofing: Notify
property owner of schedule for demo
paving above vault
3.9. Wage Rate Interviews: C#3A and C#3B
4. M&PTP: MAINTENANCE & PROTECTION
OF TRAFFIC & PEDESTRIANS
4.1. Vacri to submit work sequence to City for
review of pedestrian access, etc. prior to
start of Bank Alley work (sidewalk demo,
grading/compaction testing, set valve
boxes, MH covers, slab pour, pavers, etc.)
Page 2 of 3
ADDITIONAL NOTES
Contractors concerned about vibration due to jack hammering and compaction near Simeons
City will coordinate with LaBella for vibration monitoring