2014 Construction Meeting #15
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Jessica Buckley
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A), Kimberly Michaels TWM
Dan Walker (A), James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis,
Bob Bellavigna ACP
Lou Zupan, Bill Planert, Brian Planert (A)
James Edwards (A), Dave Comer (A)
Doug Stafford (A), Jack Barker (A), Dawn Stillwell, John Mattiace (A)
Jeff Bubb (A), Flint Brann, Andy Gana (A), Bill Gana (A)
Jack Czapranski (A), Dennis Kuhn (A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Gateway Structure Shops #TBD
1.1.2.Granite Shop #87
Notes
Bulletin #12; Knocking out back of box will
void warranty; Contractors asked Sasaki
review installation of EX6 lights on corners
of granite blocks
MK to contact Selux; Location of
receptacles on light poles to be installed
higher
Due